Engineering Overview

advertisement
Engineering Overview
CD-2 Lehman Review
Nadine Kurita - LUSI Chief Engineer
August 19, 2008
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 1 p. 1
Nadine Kurita
kurita@slac.stanford.edu
Outline
Safety
Organization
Engineering Processes
Standards
Reviews
Specifications/Requirements/ICDs
Configuration Management
Value Management
Engineering Status
Requirement Document Status
Basis of Estimate
Cost Methodology
Major Milestones
Summary
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 2 p. 2
Nadine Kurita
kurita@slac.stanford.edu
Safety
Lead Engineer & Engineering Staff
Responsible for integrating safety into their designs
Access to ES&H staff, peer reviews and SLAC Safety Committees
Line Management
Responsible for safety
Responsible for authorizing work to proceed
Utilize verification processes:
LUSI safety review checklist
Design review process includes safety at each stage of design
Safety reviews are included in the P3 schedule
Work Authorization Form – LCLS Procedure
Instrument designs are consistent with SLAC ES&H Policy –
Safety Overview Committee Review
SLAC authorization to energize machine includes sign-off by
SLAC Safety Committees and SLAC Safety Officers
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 3 p. 3
Nadine Kurita
kurita@slac.stanford.edu
Engineering Organization
Nadine Kurita
LUSI Chief Engineer
J. Langton – XPP Lead Engineer
P. Montanez – CXI Lead Engineer
E. Bong – XCS Lead Engineer
E. Ortiz – DCO Lead Engineer
---------------------------------------------D. Arnett – Design Supervisor/Designer
B. Bigornia – Designer
A. Busse – Mechanical Engineer
M. Campell – Mechanical Engineer
J. Castagna – Mechanical Engineer
M. Carracos* – Design Engineer
J. Defever – Design Engineer
J. Delor – Design Engineer
M. Holmes* – Mechanical Engineer
R. Jackson – Design Engineer
M. Kosovsky* – Mechanical Engineer
T. Osier – Designer
*currently supporting AMO
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 4 p. 4
Nadine Kurita
kurita@slac.stanford.edu
Engineering Organization (2)
Staffing Progress
Added 12 engineers/designers since the CD1 Review
All Lead Engineer/CAM positions filled
Manpower Requirements per Current Schedule
Q4FY2008
12.1 FTE Mechanical Engineers
6.6 FTE Mechanical Designers
1.9 FTE Controls Engineers
Currently searching for 3-4 additional engineers
AMO engineers available in September
Maximum load for mechanical engineering is in Q3FY2009
11 FTE Mechanical Engineers
9.3 FTE Mechanical Designers
Maximum load for controls engineering Q2FY2010
5.1 FTE Controls Engineers
1.7 FTE Controls Programmers
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 5 p. 5
Nadine Kurita
kurita@slac.stanford.edu
LUSI Engineering Resource Loading
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 6 p. 6
Nadine Kurita
kurita@slac.stanford.edu
Engineering Organization (4)
Lead Engineer
Reports to Chief Engineer
Responsible for all technical aspects of the project
Responsible for reporting cost and schedule
Control Account Manager (CAM)
Responsible for supervising daily activities of subordinate
engineers, design engineers and designers
Responsible for keeping management informed on critical
issues, delays, etc.
Works with upper management to make critical decisions
Design Supervisor
Responsible for design standards
Checking, approving and releasing drawings
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 7 p. 7
Nadine Kurita
kurita@slac.stanford.edu
Engineering Processes – Standards
Formalize Design Standards
 Incorporated SLAC Mechanical Design Department
standards through SP-391-000-36, LUSI Design Standard
Supplement
 Developed standard engineering notes
 Developed Solid Edge Tool (3D parametric software)
Formalize Manufacturing Practices
LUSI Procedures and Travellers
Produced for critical equipment
Configuration controlled
History archived via LCLS/LUSI sharepoint
Non-Compliance Reports (NCRs), Inspection Reports
History archived via LCLS/LUSI sharepoint
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 8 p. 8
Nadine Kurita
kurita@slac.stanford.edu
Engineering Processes - Reviews
Design review goals and criteria are documented
Design reviews are milestones in our schedule
Essential to ensure the designs meet their
prescribed functionality
Demonstrate value engineering
Engineering review template completed
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 9 p. 9
Nadine Kurita
kurita@slac.stanford.edu
Engineering Processes - Reviews (2)
Preliminary Instrument Design Review (PIDR)
Instrument System Specific (CXI, XPP, XCS)
Goal
Approve the objectives and physics requirements of the instrument
Approval of the conceptual design approach
Presents the following
Science including breadth of applications possible with the instrument
Objectives and the requirements of the system
Instrument System Physics Requirements Document complete and ready for sign off
Performance requirements of the components
“Proof of Concept” Models
Proposed approach to meet the requirements
System design
Mechanical
Electrical
Major system interfaces, organizational and technical
Major design alternatives considered (Value Management)
Safety considerations
Assessment of risk areas
Planned test program if appropriate
After closure of action items this approves the baseline design, continuation of
engineering specifications and preliminary component designs
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 10 p. 10
Nadine Kurita
kurita@slac.stanford.edu
Engineering Processes – Reviews (4)
Preliminary Design Reviews
Component specific
Final design details are not required
Goal
Approval of the component specifications & preliminary design
Approval to complete final design
Approval to fabricate test articles and place long duration
procurements
Presents the following:
Science/technical objectives, requirements, general specification
Engineering Specification Document complete and ready for sign off
Preliminary design & engineering analyses
Design interfaces
Control/software requirements
Quality control, reliability
Safety considerations – “define hazards”
Cost & schedule
After closure of action items preliminary design approved and
long duration items will be purchased. Move to final design.
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 11 p. 11
Nadine Kurita
kurita@slac.stanford.edu
Engineering Processes - Reviews (3)
Final Instrument Design Review (FIDR)
Instrument System Specific (CXI, XPP, XCS)
Prerequisite
All major Component Preliminary Design Reviews must be completed.
Goal
Approve final instrument design / configuration & verify that they meet requirements
Presents the following
System requirements for the instrument
Instrument PRD, ESD and procurement specifications are complete and ready for sign-off
Layout Update - Identify changes from PIDR layout
Component design status and description
Design and analyses to meet the requirements
Major design alternatives considered (value management)
Major system interfaces, organizational and technical
Identify operational modes
Maintenance requirements
Planned test program if appropriate
Installation & alignment plans
Cost & schedule
Safety – status and description of hazard and mitigation
After closure of action items this approves the final design and configuration of
the instrument.
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 12 p. 12
Nadine Kurita
kurita@slac.stanford.edu
Engineering Processes – Reviews (5)
Final Design Reviews
Component specific
Goal
Approval of the final design, cost and schedule
Approval to complete detail drawings
Approval to start procurement & fabrication
Presents the following:
Science/technical objectives, requirements & specifications
Review closure of actions from the Preliminary Design Review
Final design and analyses
Test results and design margins
“Analyze and develop controls” for all safety hazards
Approved safety reviews as required
Identified problem areas/open issues
Cost & schedule
After closure of action items this approves the final design and
detail drawings are completed. Approval to purchase items and
begin fabrication.
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 13 p. 13
Nadine Kurita
kurita@slac.stanford.edu
Engineering Processes – Reviews (6)
Manufacturing Readiness Review
Component specific
Schedule milestone
Goal
Provides status on drawings, procurement, manufacturing and safety
documents.
Presents the following:
Status of assembly and detail drawings
Approval process per Mechanical Department standards
Procedures, travellers, inspection and testing plans
Status of procurement and manufacturing
Installation plans & documents
Work Authorization, Statement of Work
Operational requirements/procedures
checkout, testing, maintenance
“Develop and implement” hazard controls
Safety documents
Review closure of action items from the FDR
Cost and schedule update
After closure of action items this approves the start of assembly,
testing and installation.
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 14 p. 14
Nadine Kurita
kurita@slac.stanford.edu
Engineering Processes – Reviews (7)
Safety Reviews
Safety Overview Committee Review (SOC), K. Moffeit
Completed December 2006 and identified the following
required committee reviews:
Earthquake Reviews
Radiation Safety Reviews
Laser Safety Reviews
Electrical Safety Reviews
Hoisting and Rigging Safety Committee
Fire Marshall
Hazardous Experimental Equipment Committee
SOC approval ensures that the hazard analysis is adequate,
controls planned to mitigate or eliminate hazards are
adequate, and that the activity will conform to SLAC ES&H
policy
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 15 p. 15
Nadine Kurita
kurita@slac.stanford.edu
Engineering Process – Requirements
Physics Requirements Documents (PRD)
Defines functionality of the component
Provides detailed physics/science requirements
Basis for engineering design
Required for the Preliminary Instrument Design Review
Approved by Science Team Leaders and/or LUSI Project Manager
Engineering Specification Document (ESD)
General & engineering specifications to meet the PRD
Covers additional requirements not in the PRD
Space constraints, environment, etc.
Required for the Preliminary Design Review
Approved by Chief Engineer, Scientist, Project Manager
ESD template created
Interface Control Documents (ICD)
Describes the boundaries of one system with respect to another
Physical interface between the two
Responsibilities
Required for the Preliminary Design Review
Approved by all involved system managers
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 16 p. 16
Nadine Kurita
kurita@slac.stanford.edu
INSTRUMENT
PHYSICS REQUIREMENT
DOCUMENT (PRD)
System Engineering
Flow Diagram
PRELIMINARY
INSTRUMENT DESIGN
REVIEW (PIDR)
SAFETY
PRELIMINARY
DESIGN
COMPONENT PRD
COMPONENT
ENGINEERING
SPECIFICATION DOC
(ESD)
INTERFACE CONTROL
DOCUMENTS (ICD)
COMPONENT
PRELIMINARY DESIGN
SAFETY
SIMULATIONS
LONG DURATION
PROCUREMENTS
COMPONENT
PRELIMINARY DESIGN
REVIEW (PDR)
FINAL INSTRUMENT
DESIGN REVIEW (FIDR)
COMPONENT FINAL
DESIGN
SAFETY
APPROVALS
COMPONENT
FINAL DESIGN REVIEW
(FDR)
PROCUREMENTS
LUSI DOE Review, Aug. 19, 2008
Engineering, Cost & Schedule, p. 17
DETAIL
DRAWINGS
COMPONENT
STATUS REVIEW
ASSEMBLY &
TESTING
MANUFACTURING
DOCUMENTS
Travelers
Procedures
Inspection Forms
Nadine Kurita
kurita@slac.stanford.edu
Engineering Process – Requirements (3)
Statement of Work/Technical Purchase
Specifications
Mandates the technical, quality and procurement
specifications for a purchased item
Engineering Notes
Documents engineering analysis and other information
critical to the design of the component
These documents are all configuration controlled via
LCLS/LUSI Sharepoint or SODA (SLAC Online
Database Access)
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 18 p. 18
Nadine Kurita
kurita@slac.stanford.edu
Engineering Processes – Drawing Tree/Structure
Roadmap for building components and installing in the hutch
Assemblies & installations thought through – streamlines modeling
and drawing preparations
Organizes the assemblies & models
Integration between design teams
NEH
GP-391-010-00
Mr. Beam
mr39175000
NEH Building
mr39175010
NEH
Utilities
(non-hutch)
H1
GP-391-100-00
LASER BAY
INSTALL
LO-391-010-01
NEH H3
GP-391-300-00
H2
GP-391-200-00
See Sheet
“H2”
Mr. Beam
mr39175000
NEH Building
mr39175010
Upbeam
Vacuum Systems
ID-391-300-03
Pump Laser
Equipment
ID-391-300-12
H3 XPP
Local Beam
mr39175013
Optics &
Diagnostics Raft
ID-391-300-01
XPP IDs
Diffractometer
ID-391-300-10
HOMS Beam
Vacuum Systems
(Through-Pipe)
ID-391-300-05
Diagnostics Raft
ID-391-300-02
Detector Mover
ID-391-300-11
Downbeam
Vac Systems
ID-391-300-04
H3 Utilities
H3 XPP
Local Beam
mr39175013
H3 XPP
Local Beam
mr39175013
H3 XPP
Stay Clears
mo39175014
KEY:
Pump
H3 XPP
Stay Clears
mo39175014
Kappa
SC-391-32006
Alignment
Fixture
Common
Circles
SC-391-32003
Accessories
SC-391-32008
H3 XPP
Local Beam
mr39175013
Support
Structure
H3 XPP
Local Beam
mr39175013
H3 XPP
Stay Clears
mo39175014
Diagnostics Support
ID-391-350-01
SEISMIC
RESTRAINT
ID-391-350-09
Robot
H3 XPP
Local Beam
mr39175013
Tee
Optics
Tables
Bellows
Girder
SA-391320-09
Feet
Floor
Anchors,
Hiltis
Huber
5102.50 X-Y
Translation
R.A. Valve
Laser
Optics
Tilt
SC-391-32005
Pump
Stand
REF__
Kappa
Huber
115.103
Beamline
Translation
SC-391-32004
Huber
Custom
650mm
Translation
Huber
5103.C40
Lift Stage
Huber 430
Circle
Huber
430-5203.80
Adaptor
Huber
5203.80
Tip/Tilt
H3 XPP
Local Beam
mr39175013
Devices
SA-391300-08
Strong
back
SA-391-35018
Cross
H3 XPP
Stay Clears
mo39175014
Installation
ID
Assembly
AD or SA
Diffractometer
Base Install
ID-391-320-07
H3 XPP
Local Beam
mr39175013
H3 XPP
Stay Clears
mo39175014
H3 XPP
Stay Clears
mo39175014
H3 XPP
Stay Clears
mo39175014
Pedestal
SA-391350-06
Huber
5103.D40
Lift Stage
PF-
Shim
PF-391-35023
Parts or
Purchased
ASM
STOP
ASM X-Y
SA-391350-26
Sunnex
Leveling Jack
Spherical
Washer
STOP
ASM X
SA-391350-37
X ADAPTER
PLATE
PF-391-35025
STOP
PLATE
PF-391-35027
STOP,
THREADED
PF-391-35035
SURFACE
PLATE ASM
SA-391-35002
LEG
PF-391802-19
MAIN BEAM
SIDE
PLATES PF391-802-22
OUTER
UPRIGHT
CROSS
PLATES PF391-802-21
INNER
UPRIGHT
Combined
Diagnostics
Complete
AD-
Window
Bellows
Gate Valve
Drift
Tube
Support
Rails THK
SHS30C
Granite Block
PF-391-35007
IntensityPosition
Monitor
Pop-In
Profile
Monitor
Support
Assy
Spool
SA-391825-11
X-Y
ADAPTER
PLATE
PF-391-35024
Pump
Cross
NUT, 3/8-24
Reference
Models
Pump
Stand
Spool
Rails THK
SHS30C
FLOOR
ANCHORS
HDWE
HDWE
Tee
MISC HDWE
MISC HDWE
Spool
SWIVEL PAD
Gauge
PIVOT PIN
SWING
BOLT
PF-391-35028
STUD 3/8-16
R.A. Valve
PADDLE,
RELEASE
PF-391-35036
Spool
BALL
PLUNGER
CARRLANE
CL40SBP1
Drift
Tube
Support
KNOB
Bellows
Gate valve
H3 XPP
Local Beam
mr39175013
H3 XPP
Stay Clears
mo39175014
UPBEAM
Optics & Diagnostics
ID-391-300-XX
Optics & Diagnostics
Support
ID-391-350-00
Pedestal
SA-391350-06
STOP
ASM X-Y
SA-391350-26
Sunnex
Leveling Jack
Shim
PF-391-35023
Spherical
Washer
STOP
ASM X
SA-391350-37
X ADAPTER
PLATE
PF-391-35025
STOP
PLATE
PF-391-35027
STOP,
THREADED
PF-391-35035
SEISMIC
RESTRAINT
ID-391-350-03
SURFACE
PLATE ASM
SA-391-35004
Rails THK
SHS30C
Granite Block
PF-391-35005
FLOOR
ANCHORS
SIDE
PLATES PF391-802-20
CROSS
PLATES PF391-802-21
HDWE
ACTUATOR
THK KR46
CROSS
BEAM 1
MAIN BEAM
Strong
back
SA-391-35016
H3 Local
Beam
mr39175013
IntensityPosition
Monitor
Complete
AD-
Slits
Complete
AD-
OUTER
UPRIGHT
Support
Assy
Gate valve
INNER
UPRIGHT
XFLS
Complete
AD-
Attenuator
Complete
AD-
H3 Local
Beam
mr39175013
MAIN BEAM
Pulse
Picker
Complete
AD-
Pop-In
Intensity
Monitor
Complete
ADBellows
Support
Assy
CROSS
BEAM 2
NUT, 3/8-24
X-Y
ADAPTER
PLATE
PF-391-35024
LEGS PF391-80219
MOVER ASM
SA-391-350-10
DOWNBEAM
Optics & Diagnostics
ID-391-300-XX
Strong
back
SA-391-35016
Int-Pos
Mon
Device
Slit Device
Support
Assy
XFLS
Device
Support
Assy
Attenuator
Device
OUTER
UPRIGHT
INNER
UPRIGHT
Support
Assy
Pop-In Int
Mon
Device
HRM
Complete
AD-
Bellows
Slits
Complete
AD-
Combined
Diagnostics
Complete
AD-
Gate Valve
Laser Port
Bellows
Pop-In
Profile
Monitor
Chamber
IntensityPosition
Monitor
Pump
Support
Assy
R.A. Valve
Gauge
Rails THK
SHS30C
MISC HDWE
SPRINGS
SWIVEL PAD
Long
Bellows
MISC HDWE
MISC HDWE
HDWE
CUPS
PIVOT PIN
STUD 3/8-16
SWING
BOLT
PF-391-35028
HDWE
PADDLE,
RELEASE
PF-391-35036
LUSI DOE Review, Aug. 19, 2008
Engineering, Cost & Schedule, p. 19
KNOB
BALL
PLUNGER
CARRLANE
CL40SBP1
MISC
Nadine Kurita
kurita@slac.stanford.edu
Document Control
Utilize existing SLAC MD Document Control System and Sharepoint
database
3D-models will use SLAC MD Project Database Management (PDM)
for configuration control and archiving
Drawings and specifications
Check, approval and release process as defined in DS-391-000-36,
“LUSI Design Standards Supplement”
Project documents are released and subject to revision control
Management
PEP, Acquisition Strategy, Hazard Analysis, QIP, Value Management, …
Technical
PRDs, ESDs, ICDs, ...
Fabrication & Installation
Procedures, travellers, ...
Design reviews will be archived
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 20 p. 20
Nadine Kurita
kurita@slac.stanford.edu
Document Control (2)
Engineering Change Orders (ECO)
Working with MD on a sitewide ECO process
ECO procedure is under review
Keeps detailed revision history
Increase efficiency of implementing and documenting
design and manufacturing changes
Allows for quick approval for implementing changes
Helps to maintain these changes in the supporting
design/fabrication documents
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 21 p. 21
Nadine Kurita
kurita@slac.stanford.edu
Value Management
Consistent with DOE Value Management,
DOE order 413.3A and OMB Circular A-131
LUSI Value Management Plan completed, PM-391000-02 R0
Executed LUSI Value Management Plan
Conducted with internal and external reviewers
4 alternative solutions identified
Savings of $355K executed
LUSI Value Management principles are applied to all
LUSI engineering tasks
Design alternatives
Part of the engineering review process
Applying common designs
Value Management principles assisted in finalizing
the LUSI scope
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 22 p. 22
Nadine Kurita
kurita@slac.stanford.edu
Engineering Status - XPP
X-ray Pump Probe
Extensive engineering and design progress for CD-2
Engineering Staff
J Langton - Lead Engineer
Jim Defever – Mechanical Engineer
Jim Delor – Mechanical Engineer
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 23 p. 23
Nadine Kurita
kurita@slac.stanford.edu
XPP Instrument Location
Near Experimental Hall
X-ray Transport Tunnel
AMO
(LCLS)
XPP
Endstation
XCS
CXI
Far Experimental Hall
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 24 p. 24
Nadine Kurita
kurita@slac.stanford.edu
Engineering Status – XPP (3)
CD-2 Activities
Completed – Preliminary Instrument Design
Review
Approved by team leaders in 2007 - System PRD
Completed – System ESD released
Completed - Drawing Tree/File Structure
Completed - High level models & their drafts
Completed - Hutch definitive layout
Completed - Laser table layout & pump laser to FEL
interface
Completed - Detector mover ESD released
Completed - Detector mover “proof of concept”
Testing just completed in August
Completed - Diffractometer ESD released
Documented the interfaces and deliverables with
vendor
Completed - Diffractometer definitive layout
Completed – About 85% complete on design
effort of all the supports and laser tables
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 25 p. 25
Nadine Kurita
kurita@slac.stanford.edu
Engineering Status – CXI
Coherent X-ray Imaging
Significant engineering and design progress since CD-1
Engineering Staff
Paul Montanez - Lead Engineer
Jean-Charles Castagna – Mechanical Engineer
Armin Busse – Mechanical Engineer
Rick Jackson – Design Engineer
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 26 p. 26
Nadine Kurita
kurita@slac.stanford.edu
CXI Instrument Location
Near Experimental Hall
X-ray Transport Tunnel
AMO
(LCLS)
XPP
XCS
CXI
Endstation
Source to Sample distance : ~ 440 m
Far Experimental Hall
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 27 p. 27
Nadine Kurita
kurita@slac.stanford.edu
Engineering Status – CXI (3)
CD-2 Activities
Completed – Preliminary Instrument Design
Review
Approved by team leaders in 2007 - System PRD
Completed – Draft System ESD
Completed –Drawing Tree/File Structure
Completed – XRT/FEH5 beamline layout
Complete drafts for the following ESDs
Sample Chamber
& Injector
Completed – Sample Chamber
Completed – Detector Stage –in review
Completed – Precision Instrument Stand –in review
Completed – Reference laser –in review
Completed – 1 m KB mirror system
Completed – Hutch 5, Common Room & Control
Cabin ESD
Completed – ICD LUSI to LCLS
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 28 p. 28
Fixed Target
Configuration
Nadine Kurita
kurita@slac.stanford.edu
Engineering Status – CXI (4)
Hutch Layout Drawings
Completed – Stay Clears
Completed – Utilities
Completed – Hutch Layout
Preliminary component designs
~75% complete – Sample Chamber
for the 1 m KB system
~75% complete– Detector stage
Preliminary design nearly developed
Detector packaging details needed
Completed – Precision instrument
stand conceptual design
~90% complete - Reference Laser
preliminary design
1 m KB system
Budgetary Inquiry
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 29 p. 29
Nadine Kurita
kurita@slac.stanford.edu
Engineering Status - XCS
X-ray Correlation Spectroscopy (XCS)
Major engineering and design progress since CD-1
Engineering Staff
Eric Bong – Lead Engineer
Jim Delor – Mechanical Engineer
Jean-Charles Castagna – Mechanical Engineer
Armin Busse – Mechanical Engineer
Ted Osier – Designer
Don Arnett – Designer
Ben Bigornia – Designer
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 30 p. 30
Nadine Kurita
kurita@slac.stanford.edu
XCS Instrument Location
Near Experimental Hall
AMO
(LCLS)
X-ray Transport Tunnel
(200m long)
XPP
XCS Hutch
Source to Sample distance : ~ 420 m
CXI
Hutch
Far Experimental Hall
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 31 p. 31
Nadine Kurita
kurita@slac.stanford.edu
Engineering Status – XCS (3)
CD-2 Activities
Completed – Preliminary Instrument Design Review
Approved by team leaders in 2008 - System PRD
Completed – Drawing tree/file structure
Completed – Higher level models/draft
Completed – Definitive hutch and XRT layout
Completed – Detector mover layout
Completed – Diffractometer definitive layout
Completed – Detector mover proof of concept
Completed – Draft detector mover ESD/SOW
Completed – Draft diffractometer ESD
Completed – Conceptual design for tables and supports
Completed – Hutch Design
Completed – Hutch 4 & Control Cabin ESD
Completed– Interface Control Document (ICD) LUSI to LCLS
Hutch Layout Drawings
Completed – Stay Clears
Completed – Utilities
Completed – Hutch Layout
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 32 p. 32
Nadine Kurita
kurita@slac.stanford.edu
Engineering Status - DCO
Profile-Intensity
Monitor
Attenuator
X-ray Focusing Lens
Diagnostics & Common Optics
Engineering Staff
Eliazar Ortiz – Lead Engineer
Marc Campell – Mechanical Engineer
Nadine Kurita – Mechanical Engineer
Rick Jackson – Design Engineer
Don Arnett – Designer
Ben Bigornia – Designer
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 33 p. 33
Dual Blade Slits
Nadine Kurita
kurita@slac.stanford.edu
Engineering Status – DCO (2)
CD2 Activities
Complete Draft ESDs
Completed – Pop-In Profile Monitor
Completed – Pop-In Intensity Monitor
Completed – Intensity-Position Monitor
Completed – Wavefront Monitor
Completed – Slits
Completed – Pulse Picker
Completed – Attenuators
Completed – Be Lens System
Completed – Harmonic Rejection Mirror
Monochromator
Working – Complete draft ICD to instruments.
Pulse
Greater than 50% complete on preliminary designs for
thePicker
CD4a deliverables
Completed – Pop-In Profile Monitor , 75% complete
Completed – Pop-In Intensity Monitor , 75% complete
Completed – Intensity-Position Monitor , 50% complete
Completed – Pulse Picker, 50% complete
Completed – Slits, 50% complete
Conceptual designs for all remaining devices.
Completed – Wavefront Monitor
Completed – Attenuators
Completed – Be Lens System
Completed – Harmonic Rejection Mirror
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 34 p. 34
Nadine Kurita
kurita@slac.stanford.edu
Project PRD & ESD Status
35 PRDs, 91% complete
55 ESDs, 49% complete
SUMMARY
PRD
Total
ESD
XPP Summary
35
55
10% in work
3
4
60% draft review (draft complete out for review)
0
10
80% in work-finalize (revising & preparing final edit)
0
4
90% approvals (out for final review and signatures)
6
100% released
not started
cancelled or obsolete
XCS Summary
PRD
CXI Summary
ESD
Total
5
3
Total
in work
0
0
draft review
0
in work-finalize
10
26
ESD
12
14
in work
2
0
0
draft review
0
9
0
0
in work-finalize
0
0
approvals
2
0
approvals
0
0
8
released
3
3
released
10
3
2
3
not started
0
0
not started
0
2
12
12
cancelled or obsolete
5
0
cancelled or obsolete
6
4
91%
49%
96%
100%
85%
60%
PRD
ESD
Controls & DAQ
PRD
Dia & Common Optics
ESD
Total
5
6
Total
2
8
Total
in work
0
1
in work
0
1
draft review
0
1
draft review
0
in work-finalize
0
0
in work-finalize
approvals
4
0
released
1
not started
cancelled or obsolete
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 35 p. 35
PRD
PRD
ESD
11
9
in work
1
2
0
draft review
0
0
0
0
in work-finalize
0
4
Approvals
0
2
approvals
0
3
2
Released
2
5
released
10
0
0
1
not started
0
0
not started
0
0
0
0
cancelled or obsolete
0
0
cancelled or obsolete
1
7
92%
45%
100%
86%
92%
68%
Nadine Kurita
kurita@slac.stanford.edu
Basis of Estimate
Contains the following
Detailed description of the component
Based on latest PRD
3D model if applicable and available
Detailed cost estimate
Part number, drawing number, vendor, notes, weight,
qty, cost, etc.
Supporting quotations, drawings, catalogs, etc.
Configuration controlled with the CD-2 baseline
Cross referenced to P3 activity ID’s
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 36 p. 36
Nadine Kurita
kurita@slac.stanford.edu
Cost Methodology
Cost Methodology
Engineering labor estimates based on prior experience
of similar designs
Materials & Labor estimates were driven by the latest
design and Physics Requirements
Recently obtained vendor budgetary quotes
Vendor Catalogs
Engineering bottoms up estimate
Engineering judgment
Installation cost and schedule activities were discussed with
LCLS installation manager(s)
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 37 p. 37
Nadine Kurita
kurita@slac.stanford.edu
Major Milestones/Reviews
Completed Reviews
Dec ’06 - Safety Oversight Review
Dec ’07 - XPP Preliminary Instrument Review
Dec ’07 - CXI Preliminary Instrument Review
May ’08 - Design Review – Pop-In Profile Monitor
Jul ’08 - XCS Preliminary Instrument Review
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 38 p. 38
Nadine Kurita
kurita@slac.stanford.edu
Major Milestones/Reviews (2)
Upcoming Reviews (6 month look ahead)
XPP
Q4FY08 - PDRs & FDRs Support Tables & Optical Table
Q4FY08 - PDRs & FDRs Optical Tables
Q1FY09 - PDR Diffractometer & Detector Mover
Q2FY09 - FDR Diffractometer & Detector Mover
CXI
Q42008 – PDR Detector Stage
Q1FY09 - PDR & FDR Reference Laser
Q1FY09 - PDR 1.0 m Sample Chamber
DCO
Q4FY08 - PDR Pop-In Profile & Intensity Monitor
Q4FY08 - PDR Pulse Picker
Q1FY09 - PDR Intensity-Position Monitor
Q1FY09 - PDR & FDR Slit System
Q1FY09 - FDR Pulse Picker
Controls
Q1FY09 - PDR XPP Controls
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 39 p. 39
Nadine Kurita
kurita@slac.stanford.edu
Summary
Instrument teams have made significant design
progress
LUSI has established designs with a consistent cost
estimate. The majority of materials estimates came from
vendor quotations, catalogs, or previous orders
XPP ~80%
CXI ~ 90%
XCS ~ 75%
DCO ~ 65%
Controls & DAQ ~ 95%
The technical scope of LUSI has converged
Resource loaded schedules and Basis of Estimates
are complete
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 40 p. 40
Nadine Kurita
kurita@slac.stanford.edu
Summary (2)
Engineering Staff
Staff consists of experienced SLAC mechanical engineers
and design engineers
Additional staff will be available when AMO work ramps
down – September 2008
Staff is informed in quality and trained in ES&H issues in
their area of expertise
Actively looking for additional engineering resources
Working organization with well understood
processes
Excellent communication and interfacing with
partner labs, LCLS and sub-systems
Engineering staff ready for CD-2 approval!
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 41 p. 41
Nadine Kurita
kurita@slac.stanford.edu
End of Presentation
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 42 p. 42
Nadine Kurita
kurita@slac.stanford.edu
Design Review Standards
Insert pic here
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 43 p. 43
Nadine Kurita
kurita@slac.stanford.edu
Review Template
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 44 p. 44
Nadine Kurita
kurita@slac.stanford.edu
ESD
LUSI DOE Review, Aug. 19, 2008
Engineering, Cost & Schedule, p. 45
Nadine Kurita
kurita@slac.stanford.edu
Value Management Forms
Director’s
LUSI DOE
Review
Review,
March
Aug.4 19,
& 5,2008
2008
Engineering,
EngineeringCost
Overview,
& Schedule
p. 46 p. 46
Nadine Kurita
kurita@slac.stanford.edu
Download