File

advertisement
BU R&D Form No. 3
Republic of the Philippines
BICOL UNIVERSITY
Legazpi City
QUARTERLY R&D MONITORING & EVALUATION FORM
For the quarter July-September, 2011
Program/ Project/ Study/ Title: Design and Establishment of the Electrical Distribution System/Load Center with
Direct Connection to National Grid Corporation of the Philippines in Bicol
University Main Campus.
College/ Unit: BU Research and Development Center/College of Engineering
OBJECTIVES
OUTPUT
INDICATOR
TARGETS
Work Activity
Time Frame
ACCOMPLISHMENTS
Work Activity
Time Frame
Study 1:
1.) Determine
the existing
electrical
equipment
and devices
(ex. Size of
wires, type of
connection,
and type of
electrical
devices) of
the Bicol
University
Main Campus.
* Status of
existing
electrical
equipments
and
devices.
2.) To find out if
each building in
the Main
Campus
complies with
standards
based on
Philippine
Electrical Code
Latest Edition
(2009).
DOCUMENT NO.: BU-F-RDC-03
REVISION NO.: 0
*Inventory of
electrical
equipment and
devices.
Status of
Compliance of
the electrical
system in each
building at BU
Main Campus.
REVISION DATE:
EFFECTIVITY DATE: February 2009
REMARKS
Study 2:
1.) Determine
the existing
KVA installed
capacity of
transformers at
the BU Main
Campus and to
determine the
buildings
supplied by
each
transformer.
*Analysis of
installed
transformer
at the BU
Main
Campus.
2.) Determine
the peak load
for each
building at the
Main Campus.
*List of KVA
installed
capacity of the
existing
transformers
and the
buildings
connected to it.
*Tabulation of
the peak load
for each
building in the
Main Campus.
July to
September
2011
*Sent and
followed up
letters to
concerned offices
requesting for
survey on the
building/s.
*July to
September,
2011
*Conducted
energy Audit on
BU-Admin Bldg.
Measured
ampere rating on
the Service
entrance.
DOCUMENT NO.: BU-F-RDC-03
REVISION NO.: 0
REVISION DATE:
EFFECTIVITY DATE: February 2009
*Conducted
energy audit on
BUCAL.
Measured
ampere rating on
the service
entrance.
3.) Determine if
BU Main
Campus can
comply with all
the
requirements of
NGCP for
direct
connection.
*List of
requirements
for direct
connection to
NGCP
*Conducted
ocular inspection
on BU Admin.
Bldg. and
BURDC.
Photographed the
electrical setting
and installations
of the service
entrance.
July to
September,
2011
*Conducted
ocular inspection
on BUCAL and
BUCS.
Photographed the
electrical setting
and installation of
the service
entrance and
main distribution
panel.
Prepared by:
Noted:
Engr. Fernan D. Dematera
Project Leader
Engr. Arturo C. Gesmundo
Program Leader
DOCUMENT NO.: BU-F-RDC-03
REVISION NO.: 0
Engr. Melvin B. Ballares
College/ Unit Research
Coordinator
Arnulfo M. Mascariňas, Ph.D.
Dean/ Director
REVISION DATE:
EFFECTIVITY DATE: February 2009
Download