The LHC Nominal proton Beam in the PSB and PS Machines

advertisement

THE LHC NOMINAL PROTON BEAM

IN THE PSB AND PS MACHINES

M. Benedikt & E. Metral

PS-OP shut-down lectures, MCR glassbox, 20/02/2001

Requirements of the LHC on its injectors

What are the nominal & already achieved beams at PS exit?

How is it obtained in the PS complex?

 General aspects

Linac2

PSB

PS

Future work

SPS and LHC filling

E.M, PS-OP shut-down lectures, 20/02/2001 1

Requirements of the LHC on its injectors (1/3)

 2 main challenges involved in the design of the LHC

 Very high magnetic field to reach the collision energies in the TeV range

 Very high luminosity necessary to provide significant event rates at this energy

L

 norm ,

,

N

1 x y b

 

N b k b e f rev

It is limited by :

- Space-charge effects in the injectors...

- Head-on beam-beam interaction at collision

E.M, PS-OP shut-down lectures, 20/02/2001

Beam current

Brightness = transverse bunch density

It is limited by :

- Collective instabilities

- Cryogenic load (synchrotron radiation and wall current)

- S.C. magnet quench

2

Requirements of the LHC on its injectors (2/3)

Choice of the nominal LHC parameters

Energy

E [TeV]

Dipole field

B [T]

Luminosity

L [cm -2 s -1 ]

Harmonic number h

Number of bunches k b

Protons / bunch

N b

Bunch spacing

 b.s

[ns] x & y emittances

 x norm,

, y

1

[ 

Long. emittance

 l

2

[eVs]

7

35640

2808

1.1

8.3

10

25

0.5

34

10

3.75

11

1

E.M, PS-OP shut-down lectures, 20/02/2001 3

Requirements of the LHC on its injectors (3/3)

 LHC project leader  L. Evans

 Major upgrade needed all along the injector chain

 Project leader to prepare the PS complex to be a pre-injector (started in 1995)  K. Schindl (Deputy  M. Benedikt )

E.M, PS-OP shut-down lectures, 20/02/2001 4

What are the nominal & already achieved beams at PS exit?

Energy

E [GeV]

Harmonic number h

Number of bunches k b

Protons / bunch

N b

Bunch spacing x & y emittances

 norm, x , y

 b.s

[ns]

1

[ 

Achieved

25

84

72

1.1

10

11

25

2.5

Nominal

25

84

72

1.1

10

11

25

3

Long. emittance

 l

2

[eVs]

0.35

0.35

Total bunch length

 b

[ns]

Momentum spread

2  p

/ p

4

2.2

10

-3

4

2.2

10

-3

 The specifications are met in the PS complex

E.M, PS-OP shut-down lectures, 20/02/2001 5

How is it obtained in the PS complex?

General aspects

 2 main challenges had to be faced

 High brightness production (2  as before) and conservation

 Production of the train of very short bunches with the LHC spacing

 Solutions

 Double-batch filling of the PS (2  1.2 s)

 Lowers the space charge effects at PSB injection ( 50 MeV )

Increase of the PSB ejection kinetic energy (PS injection) : 1  1.4 GeV

 Lowers the space charge effects at PS injection

 1 triple + 2 double splittings to produce the desired number of bunches, longitudinal emittance and bunch spacing

 Bunch rotation to produce the desired bunch length

E.M, PS-OP shut-down lectures, 20/02/2001 6

Linac2

 The initial transverse emittance is given by the duoplasmatron source

Normalised, at 1 

 0 .

4

 m

Depends on extraction aperture, electrode shape and space charge

 The beam is then adiabatically bunched and accelerated in a Radio

Frequency Quadrupole ( RFQ2 ) under high space charge conditions

 0 .

6

 m

 Fine-tuning of the 50 MeV Drift Tube Linac ( DTL ) and of the transfer line to the PSB

 1 .

2

 m

7 E.M, PS-OP shut-down lectures, 20/02/2001

PSB (1/5)

 General aspects

 PSB delivers 2 batches to PS (2 consecutive 1.2 s cycles )

 3 PSB rings per batch ( 3 , 4 and 2 )

 1 bunch per ring ( H1 ) C275, Bdot = 5 Gauss/ms

 Injection at 50 MeV

This is what sets the brightness

 Horizontal plane

 Multi-turn injection : 3 turns exactly  more stability and reproducibility (most homogeneous longitudinal distribution of the unbunched beam)

Adjustment of the horizontal injection steering and injection bump timing to minimise the horizontal emittance  BIX.SKSW2,3,4

Special tune because of large tune shift  Q h

= 4.28

Tiny shaving ~ 30 ms after injection

E.M, PS-OP shut-down lectures, 20/02/2001 8

PSB (2/5)

 Vertical plane

Injection on orbit

Minimisation of vertical oscillations at injection ( 1/2 turn pick-up ) to minimise vertical emittance  BI.DVT 50 and 70

Special tune because of large tune shift  Q v

= 5.44

Shaving vertical  to have a well-defined emittance

 Acceleration from 50 MeV to 1.4 GeV

C275  C765

 Double harmonics operation to increase the bunching factor (bunch flattening) and thus decrease the space charge tune shift at injection

 C02 ( H1 , 1/ring) and C04 ( H2 , 1/ring). C04 voltage slowly reduced to zero at synchronisation/ejection

 Available controlled blow-up  C16 ( H9 , 1/ring)

 No coupling between the transverse planes

 Standard settings of multipoles for resonance compensations

E.M, PS-OP shut-down lectures, 20/02/2001 9

PSB (3/5)

 Synchronisation

Non-standard bunch spacing at ejection to fit the PS H7 RF system

 t

PS h

7

8

7

  t

PS h

8

8

286 ns

327 ns

7

 adjustment with the phase offsets : BA3,4,2.PSYNCOFFSET

( ring 3 is always used as the reference)

 Ejection at 1.4 GeV

C805

 fast extraction towards the PS through the BT/BTP transfer line

E.M, PS-OP shut-down lectures, 20/02/2001 10

Intensity/ ring (

10

10

)

PSB (4/5)

X & Y shavers

E.M, PS-OP shut-down lectures, 20/02/2001

Time [ms]

11

Without blow-up

PSB (5/5)

Beam parameters at PSB extraction

Protons / bunch

Achieved

1 .

4

10

12

Nominal

1 .

32

10

12

Hor. emittance

 x norm, 1

[

Ver. Emittance

 norm, y

1

[

Long. emittance

 l

2

[eVs]

 b

[ns]

Momentum spread

2

 p

/ p

(

10

-3

)

2 .

2

1 .

8

0 .

9

150

2

2 .

5

2 .

5

1 .

5

195

2 .

45

E.M, PS-OP shut-down lectures, 20/02/2001 12

PS (1/10)

 General aspects

 Double-batch injection : 1 batch of 3 bunches + 1 batch of 3 bunches 1.2 s later  6 bunches out of 7 buckets

 Longitudinal beam slicing  complicated RF gymnastics

PSB exit

PS exit

~ 300 ns

 High brightness conservation  careful control of collective effects, injection oscillations, working point, chromaticities, non-linearities at extraction …

E.M, PS-OP shut-down lectures, 20/02/2001 13

PS (2/10)

 At low energy ( 1.4 GeV kinetic energy)

 1 st injection => 3 bunches ( H7 ) Inj 42 at C170

 Transverse matching between PSB and PS, orbit correction...

Careful control of the working point to avoid blow-up during the long flat-bottom  Q h

~ 6.21 and Q v

~ 6.23

A single-bunch head-tail instability (due to the resistive wallimpedance) develops during the long flat-bottom => it is cured by x-y coupling (skew quadrupoles)

 2 nd injection => 3 bunches ( H7 ) => 3 + 3 = 6 bunches ( H7 )

Inj 42 at C1370

C1380

Momentum adaptation PSB-PS => PSB synchro. made with PS beam

Triple splitting => 6 × 3 = 18 bunches ( H21 )

Acceleration from on H21

1.4

to

C1560

25 GeV

C1450

22 Gauss/ms

3 groups of C10 cavities on H7,14,21

 At transition :  -jump + change of the chromaticities sign

E.M, PS-OP shut-down lectures, 20/02/2001 14

PS (3/10)

Head-Tail resistive-wall instability

Intensity (

10

10

)

Beam-Position Monitor

(20 revolutions superimposed)

R signal

I skew

0 .

33 A

Time [ms]

Time (20 ns/div)

m

6

E.M, PS-OP shut-down lectures, 20/02/2001

I skew

 

0 .

4 A

15

C2120

PS (4/10)

Longitudinal coupled-bunch instabilities between 6 and 20 GeV/c cured by controlled longitudinal blow-up Cavities C200 (H420)

 Horizontal orbit correction => PR.GSDHZ15,60-OC

 At high energy ( 26 GeV/c momentum)

It will change this year

=> new high-energy timings

 Synchronisation H1 => the worst

1 st double splitting => 18 × 2 = 36 bunches ( H42 )

2 nd double splitting => 36 × 2 = 72 bunches ( H84 )

1 cavity C20

1 cavity C40

 Bunch compression by a step voltage

=> longitudinal mismatch

1 cavity C40 (H84)

2 cavities C80 (H168)

=> bunch rotation and ejection after 1/4 of synchrotron period

 b

16 ns 

 b

4 ns with

 l

0 .

35 eVs

 Ejection at 26 GeV/c

Ej 16 at C2395

 fast extraction towards the SPS through the TT2/TT10 transfer line

E.M, PS-OP shut-down lectures, 20/02/2001 16

PS (5/10)

Magnetic field and double-batch injection

1000

900

800

700

600

500

400

300

200

100

0

-100

100

I [e10]

B [Gauss] inj1 +10ms

C180

600

E.M, PS-OP shut-down lectures, 20/02/2001 inj2 -10ms

C1360

1100 inj2 +5ms

C1375 ej -6ms

C2389

6000

1600

4000

No 3.5 GeV/c plateau

2000

0

2100

14000

12000

10000

8000

17

PS (6/10)

Longitudinal beam structure in the last turn of the PS

E.M, PS-OP shut-down lectures, 20/02/2001

300 ns/div

30 ns/div

1 ns/div

18

3.5

3

2.5

2

1.5

1

0.5

0

0

PS (7/10)

Normalised transverse emittances at 1 

5 00

BAD

GOOD

20 00

H 54

H 64

V75

V85

25 00 10 00

Ti me [m s ]

15 00

1st batch injection

PSB output

(SEM grids in meas.

line)

2nd batch injection

1.4-25GeV acceleration

PS output

(SEM grids in

TT2 line)

!

without bunch rotation

E.M, PS-OP shut-down lectures, 20/02/2001 19

PS (8/10)

Only 1 measurement is still missing  the transverse emittances in

TT2 in the presence of bunch rotation

Emittance measurements using the Semfils in TT2 without bunch rotation

H - plane

E.M, PS-OP shut-down lectures, 20/02/2001

V - plane

20

PS (9/10)

Emittance measurements using the Semfils in TT2 with bunch rotation

=> Electrons are created ...

H - plane

E.M, PS-OP shut-down lectures, 20/02/2001 21

PS (10/10)

Baseline drift on electrostatic pick-ups in TT2

Also observed in the PS

Without solenoid

With solenoid

~ 50-100 G

Apparently the beam is not affected  this is only a measurement problem for the PS (contrary to the SPS and LHC)

E.M, PS-OP shut-down lectures, 20/02/2001 22

Future work

The nominal beam is within reach, but one item is missing  the quantitative analysis of the non-linear effects due to the stray-field at

PS extraction . It could create an optical mismatch  blow-up

 4 other subjects need to be investigated in the near future

 Consolidation of the nominal beam  improvements in pulse-to-pulse injection mis-steerings, kicker ripples, PSB-PS transverse and energy matching, bunch to bunch intensity fluctuations, instrumentation …

 Multi-gap/multi-spacing beams preparation for SPS MDs (e.g.

50 and

100 ns bunch spacing). In particular, cures for longitudinal instabilities have to be investigated (feedback systems, HOM damping)

 The so-called initial beam should be prepared

1/6 of the intensity, 1/4 of the transverse emittance

 good for collective effects

 bad for injection mis-steerings => damper at injection certainly useful

The so-called ultimate beam

E.M, PS-OP shut-down lectures, 20/02/2001 should also be looked at 1.6  the intensity

23

SPS and LHC filling (1/4)

 The cycle will consist of either 3 or 4 PS injections at 3.6 s intervals

 3 -batch  2.38  10 13 protons in 26% of the SPS circumference

 4 -batch  3.17  10 13 protons in 35% of the SPS circumference

 The injection plateau will therefore lasts up to 10.8 s

 The acceleration phase is about 8.3 s and brings the beam from 26 GeV/c to 450 GeV/c

 A 1 s flat-top is presently assumed. This will be used to prepare the extraction equipment (bumpers, etc...) and perform any RF re-phasing necessary to put the beam on the correct location in the LHC

 SPS issues

Collective instabilities in both longitudinal and transverse planes

 programme for impedance reduction + electron-cloud studies

 Fast extraction towards the LHC through TI2 (via the West extraction channel) or TI8 (via the new East extraction channel)

E.M, PS-OP shut-down lectures, 20/02/2001 24

SPS and LHC filling (2/4)

LHC Proton Injection Cycle (21.6 s)

This cycle is repeated 12 times for each LHC ring . 3 or 4-batch cycles will be interleaved in the form 334 334 334 333 to fill each ring with a total of 2808 bunches. The LHC filling time will be 12  21.6 s = 4.3 minutes per ring

E.M, PS-OP shut-down lectures, 20/02/2001 25

SPS and LHC filling (3/4)

Bunch disposition in the LHC, SPS and PS

E.M, PS-OP shut-down lectures, 20/02/2001 26

SPS and LHC filling (4/4)

 The same M ain T iming G enerator will be used to pilot the PS complex,

SPS and LHC

 Several levels of super-cycles will be introduced

16

2

2

64

16 SPS levels

2 PS levels for each SPS level

Normal + spare

E.M, PS-OP shut-down lectures, 20/02/2001 27

Download