HU131 Project Management Dr. Salah El-Din Sheet 4 Compression 1- Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(s) was crashed the adjusted total cost. 1. Carry out complete compression of the following network. Activity 0-1 1-2 1-3 1-6 2-4 3-5 3-6 4-5 5-6 5-7 6-8 7-8 Normal time Days 10 20 40 28 8 0 10 30 20 24 10 12 Normal Cost “LE” Crash time Days Crash Cost “LE” 200 200 1800 500 150 0 100 3000 2800 1000 200 400 5 10 30 20 8 0 26 10 8 14 6 8 300 300 2700 580 150 0 260 6600 3400 1650 520 520 1 The data for the duration and costs of each activity in a certain project are given in the following table. Activity 1-2 1-3 2-3 2-4 3-4 Normal time Days 6 8 4 5 5 Normal Cost “LE” Crash time Days Crash Cost “LE” 7000 4000 6000 8000 5000 3 5 1 3 3 14500 8500 9000 15000 11000 The indirect cost of the project is 3000LE per week. Determine the optimum duration of the project and the corresponding minimum cost. 2. Make compression for the following project and then find the optimum schedule in case of the indirect cost is LE 175 per unit of time under consideration. Activity A B C D E F G Immediate Normal predecessor time Days 8 A 8 A 6 A 6 B,C 4 B,C,D 12 E,F 10 Normal Cost “LE” 800 400 600 720 320 1200 500 Crash time Days 4 6 3 6 2 6 6 Crash Cost “LE” 1600 1000 1200 720 600 3000 900 3. Given the data and information that follow, compute the total direct cost for each project duration. If the indirect costs for each project duration are $90 (15 time units), $70 (14), $50 (13), $40 (12), and $30 (11), compute the total projectcost for each duration. What is the optimum cost-time schedule for the project? What is this cost? 2 3