Conditioned Space - Midwest Residential Energy Conference

advertisement

2009 IECC –

RESIDENTIAL ENERGY CODE

TRAINING

6/23/08

6/23/08

Summary of Changes

• Windows U-0.35

• Basement Walls R-10 to Frost Line

• Slab Insulation – R-10

• Recessed Lights – Air Tight and IC rated

• Ducts in Unconditioned Space

– Supply Ducts in Attics R-8

– All Other Ducts R-6

• Attic insulation at extends to outside edge of top plate R-30

3

Summary of Changes

• Duct systems that extend into unconditioned space must be visually inspected (mastic) or tested for leakage.

• Air tightness of the building must be visually inspected or tested.

• Access hatches and doors to unconditioned spaces must be insulated and weatherstripped.

4

Summary of Changes

• Fireplaces must have gasketed doors and outside combustion air.

• Using the Performance Option the efficiency of the HVAC system is not considered. The building envelope annual energy use must be equal to a building meeting the prescriptive requirements .

5

Definitions

Conditioned Space:

An area or room within a building being heated or cooled, containing uninsulated ducts, or with a fixed opening directly into an adjacent conditioned space.

6

Definitions

Building Thermal Envelope:

The basement walls, exterior walls, floor, roof, and any other building element that enclose the conditioned space. This boundary also includes the boundary between conditioned space and any exempt or unconditioned space.

attic

Building Thermal Envelope

Conditioned space

7

Building Thermal Envelope

• Components:

• Fenestration

• Windows, doors, skylights

• Ceilings

• Walls

• Above grade

• Below grade

• Mass walls

• Floors

• Slab

• Crawl space

8

The Building Envelope Can Be Deceiving

9

STAIRCASE WALLS

Carefully consider how to define the thermal envelope with an unconditioned basement or attic in the area surrounding the stairs

Notes:

Door to unconditioned space: insulated, weather stripped

Wall to unconditioned space: insulated and sealed on all 6 sides

Area above the stairs: insulated same as floor

Not required with conditioned basement.

10

Builder

11

1. Will there be an HVAC system in the attic and will there be insulation on the ceiling?

2. Performance vs Prescriptive

3. Where and how the thermal barrier will be established (insulation location)

4. Where or how the air barrier will be established (insulation type)

5. Details of meeting Prescriptive requirements, such as ceilings without attic spaces

12

6. What sub-contractor will be responsible for what job function

7. Insure all mandatory provisions are met

8. Provide blueprints with all insulation levels, window and door U-factors specified

– If blueprint includes insulated area square footage it will simplify calculations

–Areas should be provided for every unique external condition, such as walls next to an unconditioned attic.

8. Estimated air leakage rate

13

Foundation Contractor

14

Slab-on-grade floors

R-10 (typically 2 inches) insulation in Zone 4

• Downward from top of slab a minimum of 24”

• Insulation can be vertical or extend horizontally under the slab or out from the building (must be under 10 inches of soil),

• Can be angled at edge of slab

15

Foundation: Typical Slab Installation

How to insulate the top edge internally?

16

Foundation: Typical Slab Installation

Local option allowed

Add taper to top of slab

17

Framer

18

Needs to know

1. Will there be an HVAC system in the attic and will there be insulation on the ceiling?

a) must build platform and insulation dam

2. Where blocking is needed for air barrier a) Kneewall b) Cantilevered floors c) Bonus room over garage

3. Foam strip needed under wall plate

19

HVAC Platform

Extension added to ceiling joists to allow the depth of insulation need to provide an R-38 or R-30, total height of 10 to 12 inches.

20

Attic Insulation Dam

21

Corner Framing to Allow Insulation

22

Ladder Framing to Allow Insulation

No insulation possible

Insulation without bridging

Insulation with some bridging

Insulation without bridging

23

Insulated Header

½” Rigid

Insulation

2x Member

24

Framer - Air Leakage Control

Rim Board

Glue or Foam Strip

Glue or Foam Strip

Glue

Glue

Foam Strip

25

Preparing for Insulation

26

Kneewall Blocking

27

Kneewall Blocking

Unconditioned

Space

Conditioned

Space

Unconditioned

Space

Conditioned

Space

Unconditioned Space Conditioned Space

28

Kneewall Blocking

29

Walls

All walls must have 6 solid side, top, bottom, front, back

No top plate

2x4 Flat – How to insulate???

30

Cantilevered Floor Blocking

Who does what, when?

Ductwork in cavity must maintain R value

31

Dropped Soffit – Framer

Interior Wall

Exterior Wall v

Must be insulated before soffit installation

32

Dropped Soffit – Air Sealer

Interior Wall

Exterior Wall

Must be insulated before air barrier installation

33

Skylight Air Barrier

34

Fireplace Wall Air Barrier

Must be insulated before air barrier installation

35

GARAGE BAND JOIST AIR BARRIER

Incorrect Correct

Filler blocking much simpler shape with dimensional lumber

Filler blocking much harder shape with

Engineered lumber

Two types of joist-gaps created between garage and conditioned space.

36

Air Blocking and Insulation

Behind Tub or Shower

Must be insulated before air barrier installation

37

Air Blocking Needed for Fire Code

38

Plumber

39

• Needs to insure

– Exterior walls are insulated and an air barrier installed prior to installing tubs or showers on exterior walls

• Needs to do normally

– R-2 insulation on a circulation hot water system with automatic or manual switch to turn off system when not in use (cost factor in bid)

40

Air Blocking and Insulation

Behind Tub or Shower

Must be insulated before air barrier installation

41

Electrician

42

• Needs to do normally

– Provide IC airtight rated recessed lights installed to manufacture’s specifications

– Prescriptive - 50% or more of permanently installed lighting be high-efficacy

• Compact fluorescent lamps, T-8 or smaller diameter linear fluorescent lamps

43

Recessed Lighting Fixtures

Type IC rated, and labeled with

no penetrations between the inside of the recessed fixture and ceiling cavity (sealed and caulked)

Sealed with a gasket or caulk between housing and wall or ceiling covering

• Type IC rated, in accordance with ASTM E 283 to be an “Air-

Tight” enclosure

44

Prescriptive Requirements

Lighting Equipment

• Applies to lamps in permanently installed lighting fixtures

• Requires 50% to be high-efficacy

 Compact Fluorescent

 T-8 Linear Fluorescent

 Lamps with a minimum efficacy of o 60 lumens per watt (for lamps

> 40 watts) o 50 lumens per watt (for lamps

< 15 watts) o 40 lumens per watt (for lamps fr0m 15 to 40 watts)

45

HVAC Contractor

46

• Needs to know

– Location of the thermal envelop

– Is the house meeting energy by Performance certification

– Insulation levels including windows and doors on blueprint for load calculations

– The estimated air leakage rate

47

• Needs to provide

– Estimated duct leakage rate

– Heating and cooling load calculation using

Manual J or approved software

– R-8 supply ducts in unconditioned attic unless house is Performance Certified then R-6

– R-6 for all other ducts in unconditioned spaces

– Sealed duct work that can pass duct test and meet estimate used for load calculations

48

• Needs to provide (continued)

– One programmable thermostat

– Heat pump control to prevent backup heat operation in mild weather

– R-3 insulation on all piping carrying fluids over

105 °F or under 55°F

49

Mandatory Requirements

Controls

Programmable Thermostat

• At least 1 thermostat for each separate heating and cooling system.

• Programmable thermostat required when forcedair furnace is primary heating system

Heat Pump Supplementary Heat

• Controls for heat pumps with supplementary heat

50

Mandatory Requirements

Ducts

• All ducts, air handlers, filter boxes… used as ducts must be sealed

• Locate All Ductwork in

Conditioned Space

OR IF ANY DUCTWORK IS IN

UNCONDITIONED

SPACE…

• Duct testing must be performed on the system or

51

Duct Systems Air Sealing

52

Non-Compliant

No return boot through floor.

Consumer duct tape used on duct system

Square insert does not seal I-joist

53

Mandatory Requirements

Ducts

• Seal all ducts, air handlers, filter boxes, and building

cavities used as ducts.

• Seal and securely fasten all joints, transverse seams and connections with:

– welds

– gaskets

– mastics

– mastic-plus-embedded fabric systems

– tapes

Unlisted duct tape is not permitted as a sealant on any metal ducts – must be UL-181 A/B listed

54

Mandatory Requirements

Mechanical Ventilation and

Equipment Sizing

• Ventilation

– Outdoor air intakes and exhausts shall have automatic or gravity dampers that close when the ventilation system is not operating

• Equipment Sizing

– Load calculations determine the proper capacity (size) of equipment

– Calculations shall be performed in accordance with ACCA Manual S and Loads from ACCA

Manual J or other approved methods

55

Duct Insulation

If ducts are NOT located within building thermal envelope:

– Supply ducts in attics: R-8

•R-6 allowed with

Performance option

– All other ducts: R-6

Building framing cavities shall not be used as supply ducts

(return ducts still OK- but not recommended)

56

Two Options for Checking Duct Sealing

Duct Leakage Test

Duct Joint Inspection

57

Duct Tester

58

• Needs to provide

– Certification that ducts meet Postconstruction minimum standard or

• To outside - 8 cfm per 100 ft2 of conditioned floor area serviced by that system OR

• Total - 12 cfm per 100 ft2 of conditioned floor area serviced by that system

– Certification that ducts meet Rough-in minimum standard

• Total - 6 cfm per 100 ft2 of conditioned floor area serviced by that system with air handler OR

• Total - 4 cfm per 100 ft2 of conditioned floor area serviced by that system without air handler

59

Duct Leakage Testing Options

• Duct Blaster

– Seal supply and return registers

– Pressurize to 25 Pascals

– Measures Total Leakage (12 cfm per 100 ft2 requirement)

– Combined with Blower Door to measure Leakage to Outside (8 cfm per 100 ft2 requirement)

• Subtraction (Can not measure Total Leakage)

– Seal supply and return registers

– Pressurize to 25 Pacals

– Difference between reading with and without sealed registers is duct Leakage to Outside (Must meet 8 cfm option)

• Delta Q

– No commercial software available

60

Duct Sealing Inspector

61

Inspection for duct sealing of the following:

• All joints sealed with mastic

– All joints must remain visable

– ??? Building Cavities used as return ducts

62

Insulation/Air Sealing Contractor

63

• Needs to do normally

– Sealing of all penetrations through thermal envelop

– Air blocking for all insulation if not provided by framer

– Sealing around windows (air barrier must be provided)

– Batt insulation cut to fit around an items in cavity being insulated, wiring, pipes, etc

64

Air Sealing

Air permeable insulation can not be used for air sealing

65

Mandatory Requirements

Air Leakage

402.4.1 Building Thermal Envelope

Requires the envelope to be sealed to limit air infiltration.

Sealing methods between dissimilar materials should all for differential expansion and contraction.

All sources of infiltration should be caulked, gasketed, weatherstripped, or otherwise sealed with an air barrier material, suitable film, or solid material.

66

Air Leakage Materials Selection

Care must be taken on the selection and use of air sealing materials, such as caulk to insure they are appropriate for the application and applied in the appropriate manner.

67

Areas for Air Leakage (Infiltration)

Need to be addressed

• Site-built windows, doors and skylights

• Openings between window/ door assemblies and their jambs/framing

• Utility penetrations

• Dropped ceilings /chases adjacent to the thermal envelope

• Knee walls

68

Areas for Air Leakage (Infiltration)

Also…

• Walls/ceilings separating a garage from conditioned space

• Behind tubs and showers on exterior walls

• Common walls between dwelling units

• Attic access openings

• Rim joist junction

69

Air Barrier System

Some is created by the required fire and smoke blocking.

70

Batt Insulation is not an Air Barrier

71

Air Leakage Control

Plumbing Pipes and Vents

72

Air Leakage Control

Chimney Chases

73

Plumbing Services…

74

Air Leakage Control

Electrical penetrations

Foam sealant must be tested to ASTM

184 for use in fire-rated assemblies 75

Chimney Chase Air Sealing

Flashing, caulk

(possibly fire rated) at each side

See IRC 1001.11

Rock wool with heavy duty aluminum foil rolled around it -- Caulk to chimney and framing

76

Duct Penetrations…

77

Air Leakage Control

Caulking Rim Board

78

Foundations

Seal foundation penetrations!

79

Insulation

80

Identification

Sec. 303.1.1 Building thermal envelope insulation –

Insulation installers shall provide a certificate listing type, manufacturer and R-value

81

Identification

Sec. 303.1.1.1 Blown or sprayed roof/ceiling

insulation – Blown in attic floor insulation must have a depth marker for every 300 sq ft. throughout the attic space

Note: Depth of blown insulation is not a good measure of proper insulation R-value because blown insulation can be fluffed. Blown insulation bags give the manufactures coverage for a desired R-value.

82

Identification

Sec. 303.1.2 Insulation

mark insulation

Insulating materials shall be installed such that the manufacturer’s Rvalue mark is readily observable upon inspection.

83

Insulation Installation

“Cut-To-Fit!”

Right Wrong

For Wiring

Electrical Boxes

Right Wrong

84

Insulation Installation

85

Insulation Installation

86

Insulation Installation

87

Insulation Installation

NO GAPS!

88

Insulation Installation – Good

Examples

Assumes an air barrier on the back side.

89

Knee Wall Insulation

90

Insulation Options for Eaves

Wood-Framed Roof

R-38

R-30

Access Hatches and Doors

Attic Hatches

– Air sealed & weatherstripped

– Same insulation level as floors around them

Vertical “Hatches”

(in Kneewalls)

– Also air sealed and insulation equal to wall insulation level.

92

Insulation Note: Above Grade Walls

Insulate walls including those next to unconditioned spaces

Don’t forget to insulate rim/band joists

93

Floors

• Space can be an unheated basement, a crawlspace or outdoor air

• Zone 4: R19

• Insulation must maintain permanent contact with underside of subfloor

• Example of poor insulation job

94

Basement Walls

Zone 4: R10 (continuous) or

R13 (cavity)

- down to frost line

95

Basement Walls – Good Examples

Interior Studding

Exterior Foam

96

Insulating Rim Board

97

Insulating Rim Board

98

Insulated Crawl Space Walls

Crawl Wall Insulation: This practice eliminates the need for insulation in the raised floor above the crawl.

 Crawl space may not have ventilation openings to the outside

 Must be mechanically ventilated or supplied with conditioned air (1 cfm/50 sq. ft)

 Crawl floor must be covered with an approved vapor retarder material

99

Crawlspace Wall Insulation

If insulating crawlspace walls

• R-10/13 (same as basement wall requirement)

Nice Job!

100

Crawl Space Wall Insulation

101

Vented Crawlspace

102

Insulation Installation Inspector

103

Inspection for proper insulation installation of the following:

• Continuous thermal barrier around conditioned space

• No gaps

• Not compressed – fills space

• Cut to fit around items in the cavity such as wiring, pipes, etc

• Insulation under a floor is supported to maintain contact with the floor

104

Inspection for proper insulation installation of the following:

• Blocking between conditioned and unconditioned spaces

– Cantilevered floor cavity

– Floor cavity of bonus room over garage

– Top plates exist

• Behind tubs and showers on exterior walls

• Common walls between dwelling units

105

Inspection for proper insulation installation of the following:

• Attic access cover

– Includes both access scuttle doors and pull down stairs

– Approximately 8 inches for rigid foam insulation for R-38

• Platform provided to any equipment in unconditioned attic space

106

Drywall Contractor

107

• Needs to know

– Construction details expected to reduce air leakage, such as:

• Top plate to drywall joint detail

• Needs to do Normally

– Carefully cut openings where needed

– Mud gaps where larger than necessary openings have been cut

• Especially true on any openings on the ceiling

108

Air Leakage Tester

109

• Needs to provide

– Certification that the house air leakage meet the minimum standard

• 7 ACH50 maximum

– Measured air leakage with estimate of natural air leakage for minimum ventilation rate considerations

110

Blower Door Test

(Testing Option)

111

Air Leakage Inspector

112

Inspection for air sealing of the following:

• All joints, seams and penetrations

• Site-built windows, doors and skylights

• Openings between window and door assemblies and their respective jambs and framing

• Utility penetrations

• Dropped ceilings or chases adjacent to the thermal envelope

113

Inspection for air sealing of the following:

• Knee walls

• Walls and ceilings separating a garage from conditioned spaces

• Behind tubs and showers on exterior walls

• Common walls between dwelling units

• Attic access openings

• Rim joint junction

• Other sources of infiltration

114

Overview of Mandatory

Compliance

Requirements

Mandatory

Requirements

(sec. 301, 303, 401-403)

Prescriptive

Requirements

(sec. 402-404)

REScheck

Software

(sec. 402.1.4 - UA

Alternative)

Performance

(sec. 405)

Mandatory Requirements Handout

115

Prescriptive

Compliance

Requirements

Prescriptive

Requirements

(sec. 402-404)

Mandatory

Requirements

(sec. 301, 303, 401-403)

REScheck

Software

(sec. 402.1.4 - UA

Alternative)

Performance

(sec. 405)

116

Compliance using REScheck

Software

Prescriptive

Requirements

(sec. 402-404)

Mandatory

Requirements

(sec. 301, 303, 401-403)

REScheck

Software

(sec. 402.1.4 - UA

Alternative)

Performance

(sec. 405)

117

U-Factor and Total UA Compliance

Path

(Enables RES check Approach)

• Total UA Alternative

– Same as U-factor alternative but allows tradeoffs across all envelope components

•Approach used in REScheck software

118

Simulated Performance

Alternative

Compliance

Prescriptive

Requirements

(sec. 402-404)

Mandatory

Requirements

(sec. 301, 303, 401-403)

REScheck

Software

(sec. 402.1.4 - UA

Alternative)

Performance

(sec. 405)

119

Simulated Performance

• Requires computer software with specified capabilities

(local official may approve other tools)

• Compliance path allows greatest flexibility - credits such features as:

– Tight building envelope

– Tight ducts (must be leak tested) or hydronic systems

– Exterior shading, favorable orientation, thermal mass,

SHGC, etc.

120

Simulated Performance Alternative

• Analysis includes

– Proposed R-values/U-factors

– Solar Gain

– Various duct and distribution efficiencies

– Service Water Heating

– Infiltration

– Duct tightness

– Orientation

• Mandatory requirements still necessary

– Sections 401, 402.4, 402.5 and 403

121

Simulated Performance Alternative

• Analysis limits on standard reference house

– Limits Widows area to a maximum 15% of condition floor area

– Uses standard efficiency HVAC equipment for both the houses

– Does not credit tight houses without mechanical ventilation

122

Calculation Procedure and Compliance Software

Tools

Proposed

Design

Energy Use of Proposed

Design less than

Standard

Design

Energy

Estimation

Tool

Energy Use of Standard

Design

(“Proposed Building meeting the energy code requirements ”)

In KY – Most Likely

Software Used will be

REMRate

123

Unique Residence

• 1488 ft2, slab on grade, one story

• Walls = Block with R-3 on exterior

• Ceiling = R-38

• Windows = U-0.35, SHGC-0.40

• Slab = R-10

• Air Leakage = 0.25 ACHn

• HVAC system in attic

– Duct leakage = 119 cfm (8 cfm per 100 ft2)

Will it meet 2009 IECC?

124

Unique Residence

Prescriptive – Fails

Wall R below requirement

UA Compliance - Passes

• 2009 Code = 320.7

• As Designed = 311.6

Energy Cost Compliance - Fails

• 2009 Code = $1,728

• As Designed = $1,766

125

HERS Rating Benefits

• Provides necessary inspections, insulation, and testing, blower door and duct leakage, to prove compliance with

2009 IECC

• Supported by many utilites

• Sales tool to demonstrate house’s energy efficiency

• Energy Smart Builder designation

126

Download