The CLIC project • Brief overview of the CLIC machine and collaboration organisation • Status: Feasibility studies and Conceptual Design Report (CDR) • Physics Guidance, stages and energy ranges – the best possible machine • Plans for 2012-16 and towards implementation Steinar Stapnes on behalf of the CLIC collaboration The CLIC Layout D. Schulte ICHEP Paris, July 24, 2010 2 CLIC Power Source Concept Delay Loop 2 gap creation, pulse compression & frequency multiplication Drive Beam Accelerator efficient acceleration in fully loaded linac RF Transverse Deflectors Combiner Ring 3 pulse compression & frequency multiplication Combiner Ring 4 pulse compression & frequency multiplication CLIC RF POWER SOURCE LAYOUT Drive Beam Decelerator Section (2 24 in total) Power Extraction Drive beam time structure - initial 240 ns 140 ms train length - 24 24 sub-pulses 4.2 A - 2.4 GeV – 60 cm between bunches D. Schulte Drive beam time structure - final 240 ns 5.8 ms 24 pulses – 101 A – 2.5 cm between bunches ICHEP Paris, July 24, 2010 3 The CLIC collaboration CLIC multi-lateral collaboration 41 Institutes from 21 countries ACAS (Australia) Aarhus University (Denmark) Ankara University (Turkey) Argonne National Laboratory (USA) Athens University (Greece) BINP (Russia) CERN CIEMAT (Spain) Cockcroft Institute (UK) ETHZurich (Switzerland) FNAL (USA) Gazi Universities (Turkey) Helsinki Institute of Physics (Finland) IAP (Russia) IAP NASU (Ukraine) IHEP (China) INFN / LNF (Italy) Instituto de Fisica Corpuscular (Spain) IRFU / Saclay (France) Jefferson Lab (USA) John Adams Institute/Oxford (UK) John Adams Institute/RHUL (UK) JINR (Russia) Karlsruhe University (Germany) KEK (Japan) LAL / Orsay (France) LAPP / ESIA (France) NIKHEF/Amsterdam (Netherland) NCP (Pakistan) North-West. Univ. Illinois (USA) Patras University (Greece) Polytech. University of Catalonia (Spain) PSI (Switzerland) RAL (UK) RRCAT / Indore (India) SLAC (USA) Thrace University (Greece) Tsinghua University (China) University of Oslo (Norway) Uppsala University (Sweden) UCSC SCIPP (USA) Structure of the project CB: Every 6 months, links to WP update and status to provide active feedback/discussion basis to collaborators Might interact with overall global LC consortium at some stage (CB and CSC) CLIC/CTF3 Collab. Board CLIC Steering Committee Repr. from accelerator and detector/physics management structures CLJC accelerator activities and management Detector/Physics activities and management CLIC Detector Issues • • • Detector requirements are close to those for ILC detectors • First studies indicate that ILC performances are sufficient in many cases • Adapt ILD and SID concepts for CLIC • Close collaboration with validated ILC designs and work Differences to ILC • Larger beam energy loss • Time structure (0.5 ns vs. 738 ns) • Higher background due to: • Higher energy • Smaller bunch spacing • Other parameters are slightly modified • Crossing angle of 20 mradian (ILC: 14 mradian) • Larger beam pipe radius in CLIC (30mm) • Denser and deeper calorimetry Linear Collider Detector study has been established at CERN beginning of 2009 (see http://www.cern.ch/lcd) 6 CLIC main parameters Centre-of-mass energy Total (Peak 1%) luminosity Total site length (km) Loaded accel. gradient (MV/m) 500 GeV 3 TeV 2.3(1.4)·1034 5.9(2.0)·1034 13.0 48.3 80 100 Main linac RF frequency (GHz) 12 Beam power/beam (MW) 4.9 14 Bunch charge (109 e+/-) 6.8 3.72 Bunch separation (ns) Beam pulse duration (ns) 0.5 177 Repetition rate (Hz) Hor./vert. norm. emitt (10-6/10-9) 156 50 4.8/25 0.66/20 202 / 2.3 40 / 1 Hadronic events/crossing at IP 0.19 2.7 Coherent pairs at IP 100 3.8 108 4.1% 5.0% 240 560 Hor./vert. IP beam size (nm) Wall plug to beam transfer eff Total power consumption (MW) Feasibility studies and the CDR Feasibility issues (some examples in the following slides): • Drive beam generation • Beam driven RF power generation • Accelerating Structures • Two Beam Acceleration • Ultra low emittances and beam sizes • Alignment • Vertical stabilization • Operation and Machine Protection System CDRs: • Vol 1: The CLIC accelerator and site facilities (H.Schmickler) • CLIC concept with exploration over multi-TeV energy range up to 3 TeV • Feasibility study of CLIC parameters optimized at 3 TeV (most demanding) • Consider also 500 GeV, and intermediate energy ranges • Vol 2: The CLIC physics and detectors (L.Linssen) • Vol 3: CLIC study summary (S.Stapnes) • Summary and input to the European Strategy process, including possible implementation stages for a CLIC machine as well as costing and cost-drives • Proposing objectives and work plan of post CDR phase (2012-16) • Timescales: • By end 2011: Vol 1 and 2 completed • Spring/mid 2012: Vol 3 ready for the European Strategy Open Meeting Key CTF3 feasibility milestones: drive beam generation Fully loaded acceleration RF to beam transfer: 95.3 % measured. No issues found with transverse wakes in structures. Operation is routinely with full loading 1.2 us drive beam pulse Drive beam current stability at the end of the fully loaded linac : better than CLIC specification: 0.75 10-3 Full commissioning of x 4 combiner ring Unloaded gradient at CLIC 4*10-7 BDR and 180 ns pulse length T18 – strong tapering 1400 T18 – strong tapering 3900 T18 – strong tapering (now with recirculation) 280 T18 – strong tapering (CERN built) 550 conditioning time [hr] TD18 – waveguide damping 60 1300 TD18 – waveguide damping 3200 T24 – high efficiency 600 T24 – high efficiency 1570 70 80 90 MV/m 100 110 120 Interrupted by earthquake in Japan 130 Generations of structures Gradient, BDR and pulse length 2010: Two-beam acceleration with a gradient of 106 MV/m December 14, 2010: Probe beam accelerated by 23 MV in a TD24 accelerating structure, corresponding to 106 MV/m, in a reproducible way. Meas. PETS power input to structure ~ 80 MW (~200 MW in the resonant loop) Drive beam: 12.5 A, 113 MV, 12 GHz in CLEX (1.5 GHz beam combined factor 8), 140 ns pulse length Probe beam: 0.08 A, 173 MV, 1.5 GHz, 8 ns pulse length Two Beam Test Stand (TBST) results 2011 Well established two beam acceleration experiments Calibration converging, structure correctly tuned Interesting breakdown studies started Very preliminary, RF parts in early conditioning phase Blue: all components, Orange: limited to structures 2011 : CTF3 TBTS running for full after winter shut-down. Gradients of 110 – 130 MV/m are routinely reached (20% above CLIC target). Experimental results on vertical nano stabilization Design, hardware and methods are being developed. Methods: Stabilization (mechanical filters), beambased feedback and vibration sensor based feed-forward used No dynamic imperfections (but budget for static ones used fully) L = 120% (20% overhead for dynamic effects) CMS-based ground motion model (hall floor) L = 53% Plus transfer function of tested system L = 108% Plus transfer function of system that will be developed L = 118% DR: comparison to other projects • CLIC requirements close to new generation synchrotron light sources (Operation- Projects) • CLIC 500 GeV similar as ILC and demonstrated in ATF/KEK (normalized emittance) • CLIC 3 TeV similar as PEPX/SLAC project. • Close collaboration with ATF/KEK (small emittances) and CESRTA/Cornell (electron clouds) Emittance conservation a challenges: • For example, CLIC main linac design fulfills emittance requirements. Tight, but feasible component specification Tunnel implementations (laser straight) Central Injector complex Central MDI & Interaction 18 Region Linear Collider Detector project @ CERN LCD: addressing physics and detectors at CLIC and ILC Current focus: Preparation of conceptual design report for CLIC detectors => developed into a truly international effort in 2010 Experimental issues for a CLIC experiment now well understood, and detector geometries for the CLIC benchmark studies were fixed Affiliation of CLIC CDR editors Beam test with a tungsten-based HCAL for linear collider, CALICE collaboration CLIC energy scans (for a single stage) Requirement from physics : vary the c.m. energy for a given CLIC machine. Main options : • Early extraction lines : significant hardware modifications needed • Reduce gradient : disadvantage: need to scale down bunch charge linearly with gradient for stability, leading to a significant luminosity loss (green) • CLIC drive beam scheme: gradient can be reduced while increasing pulse length. A large fraction of the luminosity loss is recovered (black). Modifications to drive beam generation are minimal. Lower gradient can be achieved by switching of phase of incoming drive beam bunches : Drive beam energy after extraction There are limits to the CLIC performance (luminosity) during an energy scan What is the physics ? - some production cross-sections - One of many possible models for new physics SM physics, for example top studies should not be forgotten (not included in this plot) Or whatever your favorite model is … CLIC energy staging CLIC two-beam scheme compatible with energy staging to provide the optimal machine for a large energy range Linac 1 0.5 TeV Stage Lower energy machine can run most of the time during the construction of the next stage. Physics results will determine the energies of the stages. Optimization need to take into many account many others parameters: performance and luminosities at various energies, costs, construction and commissioning times, manufacturing/re-use/move of components, etc Linac 1 I.P. Linac 2 Injector Complex 4 km 4 km ~14 km Linac 1 1 TeV Stage I.P. Linac 2 The drive beam setups can deal with various stages of the machine Injector Complex 7.0 km 7.0 km ~20 km I.P. 3 TeV Stage Linac 2 Injector Complex 20.8 km 3 km 3 km 48.2 km 20.8 km CLIC implementation questions • Many questions: • • • • Waiting for physics guidance: Current trend are increasing limits on squark/gluino masses (but loop holes exist) – and currently no information about other SUSY particles (can be much lighter in some models) or Higgs (Standard Model or several) – Any wiser after summer conferences ? – Benefits of running close to thresholds versus at highest energy, and distribution of luminosities as function of energy – We assume that we have to be sensitive from a light Higgs threshold (~200 GeV) to multi-TeV, in several stages What are the integrated luminosities needed and what it is the flexibility needed within a stage – Interested in looking in more detail for at least one model in order to make sure the machine implementation plan can cope with whatever will be needed – Complementarity with LHC a key What are reasonable commissioning and luminosity ramp up times ? – LHC will need 3 years to get to 50 fb-1 and collects ~50 fb-1/year at 1034 (roughly) How would we in practice do the tunneling and productions/installation of parts in a multistage approach – Cheapest (overall) to do in one go but we don’t know final energy needed, and it is likely that we can make significant technical process before we get to stage 3 (or even 2?) – Timescales for getting into operation, and getting from one stage to another • Answers are possible but must be found based on all available information at the time the project is launched CLIC next phases European Strategy for Particle Physics @ CERN Council Final CLIC CDR and feasibility established 2010 2011 2012 2013 2014 2015 2016 2017 …. Feasibility issues (Accelerator&Detector) Conceptual design & preliminary cost estimation Engineering, industrialisation & cost optimisation Project Preparation Project Implementation ? ? After 2016 – Project Implementation phase: 2011-2016 – Goal: Develop a project implementation plan for a Linear(CLIC Collider • Including an initial project to lay the grounds for full construction 0 – a: significant part of • Addressing the key physics goals as emerging from the LHC data the drive beam facility) •• With a well-defined scope (i.e. technical and operation Finalization of the CLIC technical design, implementation taking into accoun the results ofmodel, technical studies done energy and luminosity), cost and schedule in the previous phase, and final energy staging scenario based on the LHC Physics results, which • With a solid technical basis should be fully available by for thethe timekey elements of the machine and detector •• Including the necessary preparation for production siting the machine CERN Further industrialization and pre-series of large at series components with validation • Within a project governance structure as defined with international partners facilities The next steps – focusing points In order to achieve the overall goal for 2016 the follow four primary objectives for 2011—16 can defined: These are to be addressed by activities (studies, working groups, task forces) or work-packages (technical developments, prototyping and tests of single components or larger systems at various places) Define the scope, strategy and cost of the project implementation. Main input: • The evolution of the physics findings at LHC and other relevant data • Findings from the CDR and further studies, in particular concerning minimization of the technical risks, cost, power as well as the site implementation. • A Governance Model as developed with partners. Define and keep an up-to-date optimized overall baseline design that can achieve the scope within a reasonable schedule, budget and risk. • Beyond beam line design, the energy and luminosity of the machine, key studies will address stability and alignment, timing and phasing, stray fields and dynamic vacuum including collective effects. • Other studies will address failure modes and operation issues. Indentify and carry out system tests and programs to address the key performance and operation goals and mitigate risks associated to the project implementation. • The priorities are the measurements in: CTF3+, ATF and related to the CLIC Zero Injector addressing the issues of drivebeam stability, RF power generation and two beam acceleration, as we as the beam delivery system. (other system tests to be specified) (technical work-packages and studies addressing system performance parameters) Develop the20technical design basis. i.e. move toward a technical design for crucial items of the machine and detectors, the MD interface, and the site.15 • Priorities 10 are the modulators/klystrons, module/structure development including testing facilities, and site studies. (technical work-packages providing input and interacting with all points above) 5 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 TE General Name CLIC-001 Project Implementation Scope. Cost. Power Beam Physics Beam physics and machine parameters Beam & System Tests CTF3+ and CLIC zero, other system-tests Technical Systems Technical design and prototypes of critical components RF RF components and testfacilities Total Material [MCHF] Personnel [FTE years] CLIC General Civil Engineering & Services 6 33 0.8 12 4.3 232 Project Implementation Studies BPH-BASE BPH-LUMI BPH-BCKG BPH-POL BPH-MP BPH-SRC E BPH-SRC P BPH-DR BPH-RTML BPH-ML BPH-BDS BPH-DRV Integrated Baseline Design Integrated Dynamic Studies Background Polarization Machine Protection & Operational Scenarios Main beam source, eMain beam source, e+ Damping Rings Ring-To-Main-Linac Main Linac - Two-Beam Acceleration Deam Delivery System Drive Beam Complex CTF3-001 CTF3-002 CTF3-003 CTF3-004 CLIC0-001 BTS-001 CTF3 Consolidation & Upgrades Drive Beam phase feed-forward and feedbacks TBL+, X-band high power RF production & structure testing Two-Beam module string, test with beam CLIC 0 drive-beam front end facility (includin Photoinjector option) Accelerator Beam System Tests (ATF, Damping Rings, FACET,…) BTS-002 Sources Beam System Tests CTC-001 CTC-002 CTC-003 CTC-004 CTC-005 CTC-006 CTC-007 CTC-008 CTC-011 CTC-012 CTC-013 CTC-014 CTC-015 CTC-016 DR SC Wiggler Survey & Alignment Quad Stability Two-Beam module development Warm Magnet Prototypes Beam Instrumentation Machine-Detector Interface (MDI) activities Beam Disposal (post-collision line & dumps) Controls RF Systems (1 GHz klystrons & DB cavities, DR RF) Powering (Modulators, magnet converters) Vacuum Systems Magnetic stray Fields Measurements DR Exctraction System RF-DESIGN RF-XPROD RF-XTESTING RF-XTESTFAC RF-R&D XTBA-FAC X-band Rf structure Design X-band Rf structure Production X-band Rf structure High Power Testing Creation and Operation of x-band High power Testing Facilities Basic High Gradient R&D & Outreach Creation of an “In-House” TBA Production Facility RF-MISC Miscellaneous RF R. Corsini, CLIC Project Meeting 1st June2011 Summary table • Full info (as of end May): https://indico.cern.ch/getFile.py/access?contr ibId=10&resId=0&materialId=slides&confId=1 34291 Present Status: • • • • • 45.5 269 40.0 211 139.1 1071 Work-program organized in WPs covering from hardware (very straightforward WPs) to working-groups (attempt to also describe as WPs) Description of work-packages in some detail done (see following example) • Mainly top-down, but input from CERN groups and collaborators in several areas 42.6 314 expressed interest to continue All past collaborators have • New collaborators have been contacted and are getting involved (in Germany, US, Russia, Belarus, UK, Spain ...) Material and personnel profiles over 2012-2016 are reasonable agreement with expected resources • Some cuts in material budget already implemented • Still need a 20-30% reduction Expect to converge by end of 2011 – plan collaboration workshop in November as an important event towards final plan R. Corsini, CLIC Project Meeting 1st June2011 RF structures & High-power tests • Basic feasibility ~ OK (for both accelerating structures & PETS) Goals for the next phase (2011-2016): • Implement full features (damping material, wake-field monitors, vacuum, cooling, PETS on-off …) • Increase statistics, long-term running PETS @ASTA - SLAC, klystron powered Typical RF pulse shape in ASTA during the last 125h of operation • Start industrialization/large-series production C L IC target pulse • Optimization of fabrication techniques for cost/performance BDR <1.2 x 10-7/pulse/PETS • Explore potential for further improvements PETS @ CTF3 – TBTS, beam powered Example of activity: X-band Rf structure production WP: RF-xprod Purpose/Objectives/Goals Deliverables Schedule Task 1: Construction of baseline accelerating structures Test structures for statistical and long term high-power testing with all damping features and high power couplers (for SATS and Test modules in CLEX) we have to make sure that we count all the structures. including those for the CLEX modules 3 generations of test structures, total quantity 48, total cost ~6 MCHF. 12 in 2013 24 in 2015 12 in 2016 Task 2: Supply of small series development prototypes and/or medium power test structures Test structures for full features (4), wakefield monitor equipped (4), optimized high-power design (8), different machine energy optima (4), optimized process (8), develop DDS (2) and choke (2), compressor (2) Typically 12 variants in series of 4 structures each, total quantity 40, total cost ~6 MCHF. 8 structures per year Task 3: Supply baseline PETS (note: most PETS fabrication accounted elsewhere, e.g. TBL) PETS for statistical and long term high-power testing 4 PETS, total cost 0.2 MCHF. 3 in 2013 1 in 2015 Task 4: PETS for ON/OFF testing PETS for on/ off test 2 generations 0.1 MCHF Task 5: Alternative fabrication method Explore alternative fabrication methods Structure fabricated with alternative procedure Task 5: Baseline to pre-series development Take the fully tested x band rf systems and evolve their production techniques to an industrialized process Resources: 2011 2012-2016 2015 onwards 2012 2013 2014 2015 2016 Total Material breakdown - - - - - - Personnel (CERN or elsewhere) - - - - - - http://indico.cern.ch/categoryDisplay.py?categId=3589 Summary • CDR underway and good progress on feasibility issues • Increased focus on ensuring the machine can be adapted to running a several energies and be implemented in stages to provide physics as quickly and efficiently as possible • Plans 2011-2016 formulated towards implementation plan – resources situation reasonable thanks to collaborative efforts • CLIC organization adapted to new phase, being implemented now Combined ILC/CLIC working groups + General issues groups for accelerator, chairs M. Harrison (ILC)/P. Lebrun (CLIC) Activity Description Deliverables (2016) Proj. Implementation, scope, cost studies, site, physics reach Update and improve CLIC cost model & civil engineering studies • Technical Design (TD) and Project Implementation Plan (PIP) of CLIC Zero • Improved cost model, feedback to CLIC baseline review, site studies Beam physics studies Beam physics and overall design • Review of the CLIC baseline design • Beam dynamics studies for each area and overall – stability/alignment, timing and phasing, stray fields … • Studies towards CLIC Zero CTF3 + CTF3 consolidation and upgrade • • • • CLIC Zero Injector for the CLIC drive beam generation complex • Build and commission 30 MeV Drive Beam injector with nominal CLIC parameters • Build and commission a few Drive Beam accelerator nominal modules • Participation to Technical Design of full CLIC Zero facility RF Structures Design and fabrication of 12 GHz accelerating structures & PETS and associated R&D • Build and test close to 100 accelerating structures • Build and test about 10 PETS prototype • Establish manufacturing experience, quality control, brazing and assembly procedures for structure fabrication at CERN RF test infrastructure Building, commissioning and operation of highpower RF test stands • Six 12 GHz klystron-based RF high-power test stations, for about 12 slots, running before 2016 • Continue high-power testing at 11.4 GHz (KEK and SLAC) • Contribution to high-power testing in CTF3+ (TBL) Prototypes of critical components Technical R&D – design, build and test prototypes of CLIC critical components • • • • • • • • • • Material Preliminary budget Alignment Quadrupole stabilization system Several nominal CLIC two-beam modules, mechanically tested, beam tested R&D and prototyping of critical beam instrumentation Design and studies of machine protection system DR technologies , e.g. superconducting wiggler prototypes, test with beam, extraction kickers prototypes Warm magnet prototypes MDI and Post collision lines and beam dumps Controls DB RF system and powering See next slides Consolidation and upgrade (higher energy, stability, reliability) Drive beam phase feed-forward experiments Upgrade and operate TBL as 12 GHz power production facility Operation with beam for several CLIC two-beam modules