PROVISIONS CONCERNING CONNECTIVITY I. Electricity Act, 2003 Direct mention of connectivity: i. Section 7. (Generating company and requirement for setting up of generating station): Any generating company may establish, operate and maintain a generating station without obtaining a licence under this Act if it complies with the technical standards relating to connectivity with the grid referred to in clause (b) of section 73. ii. Section 73(b) (Functions and duties of CEA) to specify the technical standards for construction of electrical plants, electric lines and connectivity to the grid. iii. Section 177 2(e) : (Powers of Authority to make Regulations) on the technical standards for construction of electrical plants and electric lines and connectivity to the grid under clause (b) of section 73 Inference on power to grant connectivity Section 38 (Central Transmission Utility and functions) (2) The functions of the Central Transmission Utility shall be (a) to undertake transmission of electricity through inter-State transmission system; …… (c) to ensure development of an efficient, co-ordinated and economical system of inter-State transmission lines for smooth flow of electricity from generating stations to the load centres; …… II. CEA (Technical Standards for Connectivity to the Grid) Regulations, 2007 and First Amendment, 2013 (attached with mail) III. CEA (Technical Standards for Connectivity of the Distributed Generation Sources) Regulations, 2013 (attached with mail) IV. CERC (Indian Electricity Grid Code) Regulations, 2010 i. Regulation 2.5.3: In case of Inter-state Transmission System, Central Transmission Utility shall be the nodal agency for the connectivity, long-term access and medium –term open access . The procedure formulated by CTU and approved by CERC and modalities in regard to connectivity, long term access and medium-term open access shall be in accordance with the Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Mediumterm Open Access in inter-State Transmission and related matters) Regulations, 2009, as amended from time to time. ii. Regulation 3.5(e): CTU shall carry out planning studies for Reactive Power compensation of ISTS including reactive power compensation requirement at the generator’s /bulk consumer’s switchyard and for connectivity of new generator/ bulk consumer to the ISTS in accordance with Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Mediumterm Open Access in inter-state Transmission and related matters) Regulations, 2009. iii. Part IV: Connection Code Regulation 4.1: CTU, STU and Users connected to, or seeking connection to ISTS shall comply with Central Electricity Authority (Technical Standards for connectivity to the Grid) Regulations, 2007 which specifies the minimum technical and design criteria and Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium term Open Access in inter-state Transmission and related matters) Regulations, 2009. Regulation 4.2 The objective of the code is as given below: a) To ensure the safe operation, integrity and reliability of the grid. b) That the basic rules for connectivity are complied with in order to treat all users in a non-discriminatory manner. c) Any new or modified connections, when established, shall neither suffer unacceptable effects due to its connectivity to the ISTS nor impose unacceptable effects on the system of any other connected User or STU. d) Any person seeking a new connection to the grid is required to be aware, in advance, of the procedure for connectivity to the ISTS and also the standards and conditions his system has to meet for being integrated into the grid. Regulation 4.3 Scope The Connection code applies to CTU, STU and all Users connected to or seeking connection to the ISTS, The Connection code does not apply to Generating Units, transmission/distribution systems embedded in the intra-State systems, and not connected to the ISTS. However, such entities shall abide by the CEA (Technical Standards for connectivity to the Grid) Regulations, 2007, in order to ensure that the integrated grid is not adversely affected. Regulation 4.4 Procedure for connection A User seeking to establish new or modified arrangement of connection to or for use of ISTS, shall submit an application on standard format to CTU in accordance with Central Electricity Regulatory Commission (Grant of Connectivity, Longterm Access and Medium-term Open 30 Access in inter-state Transmission and related matters) Regulations, 2009. The CTU shall process the application for grant of connectivity in accordance with these regulations Regulation 4.5 Connection Agreement A Connection agreement shall be signed by the applicant in accordance with the Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-state Transmission and related matters) Regulations, 2009. Regulation 4.6 Important Technical Requirements for Connectivity to the Grid 4.6.1 Reactive Power Compensation a) Reactive Power compensation and/or other facilities shall be provided by STUs, and Users connected to ISTS as far as possible in the low voltage systems close to the load points thereby avoiding the need for exchange of Reactive Power to/from ISTS and to maintain ISTS voltage within the specified range. b) The person already connected to the grid shall also provide additional reactive compensation as per the quantum and time frame decided by respective RPC in consultation with RLDC. The Users and STUs shall provide information to RPC and RLDC regarding the installation and healthiness of the reactive compensation equipment on regular basis. RPC shall regularly monitor the status in this regard. 4.6.2 Data and Communication Facilities Reliable and efficient speech and data communication systems shall be provided to facilitate necessary communication and data exchange, and supervision/control of the grid by the RLDC, under normal and abnormal conditions. All Users, STUs and CTU shall provide Systems to telemeter power system parameter such as flow, voltage and status of switches/ transformer taps etc. in line with interface requirements and other guideline made available by RLDC. The associated communication system to facilitate data flow up to appropriate data collection point on CTU’s system shall also be established by the concerned User or STU as specified by CTU in the Connection Agreement. All Users/STUs in coordination with CTU shall provide the required facilities at their respective ends as specified in the Connection Agreement. 4.6.3 System Recording Instruments Recording instruments such as Data Acquisition System/Disturbance Recorder/Event Logging Facilities/Fault Locator (including time synchronization equipment) shall be provided and shall always be kept 31 in working condition in the ISTS for recording of dynamic performance of the system. All Users, STUs and CTU shall provide all the requisite recording instruments and shall always keep them in working condition. 4.6.4 Responsibilities for safety CTU/STU and the concerned Users shall be responsible for safety in accordance with Central Electricity Authority (Technical Standards for connectivity to the Grid) Regulations, 2007 , Central Electricity Regulatory Commission (Grant of Connectivity, Long-term Access and Medium-term Open Access in inter-state Transmission and related matters) Regulations, 2009 and CEA (Safety Requirements for construction, operation and maintenance of electrical and electric lines) Regulations, 2008. 4.6.5 Cyber Security All utilities shall have in place, a cyber-security framework to identify the critical cyber assets and protect them so as to support reliable operation of the grid. Regulation 4.7 International Connections to ISTS The procedure for international Connection to ISTS and the execution of agreement for the same shall be determined by CTU in consultation with CEA and Ministry of Power (MOP). Regulation 4.8 Schedule of assets of Regional Grid CTU and other transmission licensees granted license by CERC shall submit annually to CERC by 30th September each year a schedule of transmission assets, which constitute the Regional Grid as on 31st March of that year indicating ownership on which RLDC has operational control and responsibility. V. CERC (Grant of Connectivity, Long-term Access and Medium-term Open Access in interState Transmission and related matters) Regulations, 2009 Regulation 8: Grant of Connectivity (1) The application for connectivity shall contain details such as, proposed geographical location of the applicant, quantum of power to be interchanged, that is the quantum of power to be injected in the case of a generating station including a captive generating plant and quantum of power to be drawn in the case of a bulk consumer, with the inter-State transmission system and such other details as may be laid down by the Central Transmission Utility in the detailed procedure; Provided that where after filing of an application, there has been any material change in the location of the applicant or change in the quantum of power to be interchanged with the inter-State transmission system, by more than 100 MW in the case of applicant defined under Regulation 2(1) (b)(i) (a) and 40% of the Installed capacity in the case of applicant defined under Regulation 2(1) (b) (i) (b) and 40% of the aggregate Installed capacity in the case of applicant defined under Regulation 2(1) (b)(i) (c), such an applicant shall make a fresh application, which shall be considered in accordance with these regulations.1 Provided further that the application by the applicant defined under Regulation 2(1) (b)(i) (c) shall be considered by CTU only if all the generators, whose aggregate capacity is connected at the single connection point, formalize a written agreement among themselves that the lead generator shall act on behalf of all the generators to undertake all operational and commercial responsibilities for all the collective generators connected at that point in following the provisions of the Indian Electricity Grid Code and all other Regulations of the Commission, such as grid security, scheduling and dispatch, collection and payment/ adjustment of Transmission charges, UI charges, congestion and other charges, etc., and submit a copy of the agreement to the CTU, with the application of connectivity, along with a copy to the respective RLDC in whose control area it is located.2 Provided further that the CTU shall suitably incorporate the requirement of formal agreement amongst such generators in the detailed procedure and Connection Agreement signed with such lead generator.3 Provided further that the application by the applicant defined under Regulation 2(1) (b)(i) (e) shall be considered by CTU only if the existing generating station agrees to act as the "Principal Generator" on behalf of the renewable energy generating station(s) seeking connectivity through the electrical system of the generating station and formalizes a written agreement/arrangement among them to undertake all operational and commercial responsibilities for the renewable energy generating station(s) in following the provisions of the Indian Electricity Grid Code and all other regulations of the Commission, such as grid security, scheduling and dispatch, collection and payment/adjustment of Transmission charges, UI charges, congestion and other charges etc., and submit a copy of the agreement to the CTU, alongwith the application for connectivity, with copy to the respective RLDC in whose control area it is located.4 (2) On receipt of the application, the nodal agency shall, in consultation and through coordination with other agencies involved in inter-State transmission system to be 1 First Amendment, 2010 First Amendment, 2010 3 First Amendment, 2010 4 Third Amendment, 2013 2 used, including State Transmission Utility, if the State network is likely to be used, process the application and carry out the necessary interconnection study as specified in the Central Electricity Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007. (3) While granting connectivity, the nodal agency shall specify the name of the substation or pooling station or switchyard where connectivity is to be granted. In case connectivity is to be granted by looping-in and looping-out of an existing or proposed line, the nodal agency shall specify the point of connection and name of the line at which connectivity is to be granted. The nodal agency shall indicate the broad design features of the dedicated transmission line and the timeframe for completion of the dedicated transmission line. (4) The applicant and all Inter-State Transmission Licensees including the Central Transmission Utility shall comply with the provisions of Central Electricity Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007. (5) The applicant or inter-State transmission licensee, as the case may be, shall sign a connection agreement with the Central Transmission Utility or inter-State transmission licensee owning the sub-station or pooling station or switchyard or the transmission line as identified by the nodal agency where connectivity is being granted: Provided that in case connectivity of a generating station, including captive generating plant or bulk consumer is granted to the inter-State transmission system of an inter-State transmission licensee other than the Central Transmission Utility, a tripartite agreement as provided in the Central Electricity Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007 shall be signed between the applicant, the Central Transmission Utility and such inter-State transmission licensee. (6) The grant of connectivity shall not entitle an applicant to interchange any power with the grid unless it obtains long-term access, medium-term open access or shortterm open access. (7) Notwithstanding anything contained in Clause (6) of this Regulation and any provision with regard to sale of infirm power in the Power Purchase Agreement, a unit of a generating station including a captive generating plant which has been granted connectivity to the inter-State Transmission System in accordance with these regulations shall be allowed to inter-change infirm power with the grid during the commissioning period, including testing and full load testing before the COD, after obtaining prior permission of the concerned Regional Load Despatch Centre for the periods mentioned as under:(a) Drawal of Start-up power shall not exceed 15 months prior to the expected date of first synchronization and 6 months after the date of first synchronization. (b) Injection of infirm power shall not exceed six months from the date of first synchronization. Provided that drawal of Start-up power shall be subject to payment of transmission charges and the generator shall have to open a Revolving and Irrevocable Letter of Credit issued by a Scheduled Bank equivalent to 2 months transmission charges prior to drawal of Start-up power. Provided further that the Start-up power shall not be used by the generating station for the construction activities; Provided further that RLDC shall stop the drawl of the Start-up Power in the following events: (a) In case, it is established that the Start-up power has been used by the Generating Station for construction activity. (b) In case of default by the Generating Station in payment of monthly transmission charges to the transmission licensee for the drawal of Start-up power, on the request of the transmission licensee. Provided that the Commission may in exceptional circumstances, allow extension of the period for inter-change of power beyond the period as prescribed in this clause, on an application made by the generating station at least two months in advance of completion of the prescribed period: Provided further that the concerned Regional Load Despatch Centre while granting such permission shall keep the grid security in view: Provided also that the onus of proving that the interchange of infirm power from the unit(s) of the generating station is for the purpose of commissioning activities, testing and commissioning, shall lie with the generating company and the respective RLDC shall seek such information on each occasion of interchange of power before COD. For this, the generating station shall provide RLDC sufficient details of the specific commissioning activity, testing and full load testing, its duration and intended period of interchange, etc: Provided also that the infirm power so interchanged by the unit(s) of the generating plant shall be treated as deviation and the generator shall be 3 paid/charged for such injection/drawal of infirm power in accordance with the provisions of the Central Electricity Regulatory Commission (Deviation Settlement Mechanism and related matters) Regulations, 2014, as amended from time to time or subsequent reenactment thereof.5 (8) An applicant may be required by the Central Transmission Utility to construct a dedicated line to the point of connection to enable connectivity to the grid: Provided that a thermal generating station of 500 MW and above and a hydro generating station or a generating station using renewable sources of energy of capacity of 250 MW and above, other than a captive generating plant, shall not be required to construct a dedicated transmission line to the point of connection and such station shall be taken into account for coordinated transmission planning by the Central Transmission utility and Central Electricity Authority.6 Provided further that the construction of such dedicated transmission line may be taken up by the CTU or the transmission licensee in phases corresponding to the capacity which is likely to be commissioned in a given time frame after ensuring that the generating company has already made the advance payment for the main plant 5 6 Fourth Amendment, 2014 First Amendment, 2010 packages i.e. Turbine island and steam generator island or the EPC contract in case of thermal generating station and major civil work packages or the EPC contract in case of hydro generating stations for the corresponding capacity of the phase or the phases to be commissioned, subject to a minimum of 10% of the sum of such contract values:7 Provided also that the transmission charges for such dedicated transmission line shall be payable by the generator even if the generation project gets delayed or is abandoned.8 7 8 Second Amendment, 2012 Second Amendment, 2012