IEC-61508 Implementing a Compliance Program

advertisement
• Motivation
• Education
• Implementation
Pharmaceuticals
IEC-61508 Implementing a
Compliance Program
Pharmaceuticals
Overview
Pharmaceuticals
Overview
Pharmaceuticals
Overview
• Do you or your company believe in the
infallibility of Engineered systems?
Pharmaceuticals
Motivation
• Roche Ireland does not have this delusion
• 25 + years operational experience
• Including some close calls
• Reality has motivated out safety culture.
Pharmaceuticals
Motivation
Much of the rest of this presentation has been
generated from training presentations given
in Roche Ireland to
• Management
• Process Engineering
• Instrument / Electrical Engineering
Pharmaceuticals
Education
Need to educate yourself :
• Guidelines for Safe Automation of
Chemical Processes {CCPS/AIChE}
• ISA S84
• Functional Safety, {Smith & Simpson}
• IBC conferences
• Various WWW resources (exida/ sis-tech
etc)
Pharmaceuticals
Education
• Functional safety of electrical / electronic &
programmable electronic safety-related
systems.
• Critical Protective equipment - Safety
Instrumented Systems
Pharmaceuticals
IEC-61508, SOP 973

Safety requires protection from hazards of different
causes (movement, heat, radiation, el. shock, etc.)

“Functional Safety” means protection from hazards
due to incorrect functioning.
... hazards due to
incorrect function
... heat
Protection
against ...
...electrical
shock
... radiation
Pharmaceuticals
IEC-61508, SOP 973
•
•
•
•
•
Process Engineers:
Instrument/Electrical Designers:
Mechanical Engineering
Commissioning:- Extra Effort
Documentation :- Extra Effort
Pharmaceuticals
IEC-61508 Will Effect:
•
•
•
•
Not legislation
Meets ‘Reasonably practicable’ duty
Health, safety & welfare at Work act, 1989
Have to put in place a compliance program.
Pharmaceuticals
IEC-61508 is legally vague
Intolerable
region
1 x 10-4
ALARP
1 x 10-6
Negligible
risk
Figure 65-1
Pharmaceuticals
Risk
(deaths/year)
•
•
•
•
•
As low as reasonably practicable.
IEC 61508 based on ALARP concept.
ALARP concerns region of risk.
Risk is an emotive and irrational thing.
Commonly accepted values are:
upper limit 1 x 10-4 deaths per year
lower limit 1 x 10-6 deaths per year
Pharmaceuticals
RISK Reduction - ALARP
• ISA S84 life cycle depicted in Fig 65-3.
• ISA S84 focuses on Box 9 of IEC 61508.
Pharmaceuticals
Safety life cycle - milestone
approach
Pharmaceuticals
Passive systems layer
Active systems layer
ESD
Alarm handling
Diagnostics
F&G
Alarms, trips & interlocks
Figure 64-1
Intrinsic safety
Control
systems layer
Figure 65-3
1 Conceptual process design
2 Perform process HAZAN & risk assessment
3 Apply Category 0 protection systems to prevent hazards & reduce risk
No
4 Are any Category 1 protection systems required?
5 Define target safety integrity levels (SIL)
6 Develop safety requirements specification (SRS)
7 Conceptual design of active protection systems & verify against SRS
8 Detailed design of protection system
9 & 10 Installation, commissioning
and pre-start-up acceptance testing
11 Establish operating &
maintenance procedures
12 Pre-start-up safety review
13 Protection system start-up, maintenance & periodic testing
yes
14 Modify protection system?
15 Decommission system
End
Pharmaceuticals
Start
• First Stage of realisation of high-integrity
safety instrumented systems
• Modified PHA
• Feeds into SRS
• Based on good process data & good process
judgement.
Pharmaceuticals
Process Engineering
•
•
•
•
•
Carius Tube test for decomposition
Pressure Dewar Calorimetry
Understanding of Exotherms
Knowledge of onset temperatures
{Chilworth}
Pharmaceuticals
Process Chemistry
• Good process judgement.
• Hazop
• Margins of safety
Pharmaceuticals
Process Engineering
• Reactant being transferred in from Reactor
1 without agitation could accumulate &
react in a sudden, violent manner.
• Reactor 2 Inlet valve 205 should OPEN
only if agitator ON
Pharmaceuticals
Hazard identification,
Interlock Identification
• Simplified Technique.
• MIL Std 882
Pharmaceuticals
Hazard identification,
Interlock Identification
• Consequence of this is overpressure, loss of
batch, over-temperature, possible
destruction of vessel.
• 1 week downtime to recover.
• Fatality or Serious injury unlikely.
• Critical
• (C2)
Pharmaceuticals
Consequences
• Building is continually occupied
• (F2)
Pharmaceuticals
Occupancy factor
• There is quite a good chance of an operator
observing that something is going wrong &
intervening successfully.
• (P1)
Pharmaceuticals
Manual Avoidance factor
•
•
•
•
•
Likely to occur once every 5 years.
Occasional
The process is DCS automated.
DCS is not a SIS – no SIL rating.
DCS control reduces frequency of
Unmitigated Demand.
• (W2)
Pharmaceuticals
Unmitigated demand rate.
C1
F1
C2
F2
Start
C3
F1
F2
C4
Most risk
EN 954 Approach
P1
P2
P1
P2
W3 W2 W1
x0?
1 x0?
1 1 x0?
2 1 1
3 2 1
3 3 2
4 3 3
x2? 4 3
Pharmaceuticals
Least risk
Pharmaceuticals
ROCHE IRELAND LIMITED
POLICIES AND PROCEDURES
INDEX:
SOP 973
ATTACHMENT:
3.001
PAGE:
1of1
ISSUED:
17/07/2002
SUPERSEDES:
None
WRITTEN BY:
SECTION:
Engineering
APPROVED BY:
________________________________________________________________________
SUBJECT:
Safety Instrumented System – Safety Integrity Determination
Number of
Independent
Protections
Rating of the SIL required for a SIS, as per IEC 61508 Section 5, Table E.1 & as per Roche K9
ely
x
x
x
x
x
x
x
x
x
x
x
x
Occasional
Rare
Moderate
x
x
?1
Frequent
Negligible
Catastrophic
Critical
Marginal
Negligible
People
Environment
Business
People
Environment
Business
People
Environment
Business
People
Environment
Business
x
x
x
Unlikely
x
x
x
Rare
x
?1
1
x
x
?1
Occasional
Moderate
?1
1
2
Frequent
x
x
x
Unlikely
x
x
?1
Rare
x
?1
1
Occasional
Critical
Marginal
Fatalities >1
Significant loss to offsite environment. Indictable breach of License
Loss > €8 million : Interruption > 1 Month
Serious injuries (permanent damage). Multiple lost time accidents.
Only site area affected. Serious breach of licence.
Loss €200 thousand to €8 million : Site interruption > 1 week
Lost time accident
Only site area affected. Minor breach of licence
Loss €5 thousand to €200 thousand. Interruption 1 day to 1 week
Minor Injuries
Negligible effect on environment
Loss < €5 thousand. Interruption < 1 day
Frequent
Once per month
Rare
Once per 20 years
Moderate
Once per year
Unlikely
Once per 100 years
Occasional
One per 5 years
V Unlikely
Once per 1000 years
?1
1
1
Moderate
1
1
2
Frequent
x
?1
1
x
1
2
Unlikely
Rare
?1
1
2
Occasional
1
1
2
Moderate
Catastrophic
1
2
3
Frequent
3
2
1
Event
Frequency
Event
consequence
Rating of Consequences
class
I
II
III
IV
rating
consequences
catastrophic
people
fatalities, evacuation outside the site area
environment
irreversible, long-term damage outside the site area
business
loss:
interruption:
image:
people
serious injuries, irritations outside the site area
environment
reversible, short-term damage outside the site area
business
loss:
interruption:
image:
people
minor injuries, molestation outside the site area
environment
only site area affected
business
loss:
interruption:
image:
people
no effects
environment
no effects
business
loss:
interruption:
image:
critical
marginal
negligible
> 10 mio. US $
> 6 month
severely damaged, > 1 week, national
< 10 mio. US $
> 2 weeks
damaged, > 1 week, regional
< 1 mio. US $
2 days to 2 weeks
< 1 week, local
< 100'000 US $
< 2 days
no effects
Pharmaceuticals
Roche Consequences
Rating of Probability
class
rating
probability
A
frequent
once a year or more
B
moderate
once in 5 years
C
occasional
once in 10 years
D
rare
once in 25 years (e.g. once in life cycle of the system)
E
unlikely
once in 100 years (e.g. once in life cycle of a site)
F
very unlikely
once in 1'000 years or less (e.g. once in life cycle of Roche or less)
Pharmaceuticals
Roche ‘unmitigated’ demand
rate.
• Second Stage of realisation of high-integrity
safety instrumented systems
• Modified Instrument design
• Modified Instrument Commissioning
• Feeds into SRS
Pharmaceuticals
Instrument / Electrical Design
Hazard
reduction
factor
HRF
PFD
(fractional)
Availability A
(fractional)
1
>101
10-1 to 10-2
0.9 to 0.99
10-5 to 10-6
2
>102
10-2 to 10-3
0.99 to 0.999
10-6 to 10-7
3
>103
10-3 to 10-4
0.999 to 0.9999
10-7 to 10-8
4
>104
10-4 to 10-5
0.9999 to 0.99999
10-8 to 10-9
Demand mode of operation
Table 65-1
Continuous mode
Failure rate 
(failures per hr)
Pharmaceuticals
Safety
integrity
level
SIL
• SIL value is measure of quality of protection
system, end to end.
• System has to be designed, specified, built and
maintained to that standard.
• Proof testing at regular intervals
• Conformance assessment for safety systems
Pharmaceuticals
Equipment implications
•
•
•
•
Simplified Equation
ISA-TR84.00.02-2002 Part 2
Equation B.34 – Rare event approximation
“Adequate” for SIL 1 or 2, where the plant is well
controlled, well maintained, understood process,
conservative engineering with good mechanical
integrity
Pharmaceuticals
PFD Calculation
• MTBF = Mean (Average) time between failures
• Information provided by vendor.
• MTBF = 86 Years
Pharmaceuticals
PFD Calc. Motion Sensor
Failures can be
• fail to danger (Falsely shows agitator moving)or
• fail to safe (Falsely shows agitator stopped)
• Aim of good design is to maximise fail to safe,
minimise fail to danger. The failure mode split is
the percentage in the fail to danger category.
• Failure mode split = .1 (SA estimate)
Pharmaceuticals
PFD Calc. Motion Sensor
• Proof test interval = 1 year (8760 hours)
• Time between re-tests of the interlock.
• Need to be genuine tests
Pharmaceuticals
PFD Calc. Motion Sensor
• 86 years * 8760 hours/year = 753,000 (MTBF in
hours)
•  = 1/ MTBF = 1.30 E-6 failures per hour
• FMS =.1
• Proof test = 1 year (8760 hours)
• PFD(SS) = 1.30 E-6 * .1 * 1 * (8760/2)
• PFD(SS)=.0006
Pharmaceuticals
PFD Calc. Motion Sensor
• MTBF = 4 Years
• Failure mode split = .4
• Proof test interval = 1 year (8760 hours)
 = 1/ MTBF = 2.87 E-5 failures per hour
PFD(B6) = 2.87 E-5 * .4 * 1 * (8760/2)
• PFD(B6)=.0500
Pharmaceuticals
PFD Calc. Barrier 6
• MTBF = 100 Years
• Failure mode split = .01
• Proof test interval = 1 year (8760 hours)
 = 1/ MTBF = 1.14 E-6 failures per hour
PFD(R5) = 1.14 E-6 * .01 * 1 * (8760/2)
• PFD(R5)=.00005
Pharmaceuticals
PFD Calc. Relay 5
• MTBF = 10 Years
• Failure mode split = .9
• Proof test interval = 1 day (24 hours)
 = 1/ MTBF = 1.14 E-5 failures per hour
PFD(MB) = 1.14 E-5 * .9 * 1 * (24/2)
• PFD(MB)=.001242
Pharmaceuticals
PFD Calc. Main Barrier
• MTBF = 10 Years
• Failure mode split = .4
• Proof test interval = 1 day (24 hours)
 = 1/ MTBF = 1.14 E-5 failures per hour
PFD(SOL) = 1.14 E-5 * .4 * 1 * (24/2)
• PFD(SOL)=.00006
Pharmaceuticals
PFD Calc. Solenoid
• MTBF = 10 Years
• Failure mode split = .2
• Proof test interval = 1 day (24 hours)
 = 1/ MTBF = 1.14 E-5 failures per hour
PFD(VA) = 1.14 E-5 * .2 * 1 * (24/2)
• PFD(VA)=.00003
Pharmaceuticals
PFD Calc. Valve & Actuator
•
•
•
•
•
•
•
PFD(VA)=.00003
PFD(SOL)=.00006
PFD(MB)=.00124
PFD(R5)=.00005
PFD(B6)=.0500
PFD(SS)=.0006
PFD = .052 => SIL 1
Pharmaceuticals
PFD Calc. Overall
Pharmaceuticals
∑ PFD = 10%
SIL 1 Limit
PFD Mapping
Valve
Barrier
Overall
∑ PFD = 1%
SIL 2 Limit
Relay
Logic
Barrier
Instrument
• Elements in series: USYS  Ui
62-16
Elements in parallel: USYS  Ui
-17
• Common cause failure:
SYS = IND + . MAX
-18
• Voting systems:
UKOON n.Uk
-19
• For more complex systems – Fault Tree Analysis
using ISA-TR84.00.02-2002 Part 3.
• “Probabilistic Risk Assesment” – Henley, E J
Pharmaceuticals
PFD Calc. Issues
• Roche have decided that valve & actuator
may be shared for SIL 1 only.
• SIS & BPCS share barrier, solenoid,
actuator & Valve. This is not recommended
• Solenoid has local SMO, which might be
OK for normal operation, but not for SIS.
Pharmaceuticals
Design issues
Pharmaceuticals
Design issues
• ##### ####-# type barrier not
recommended (TTL Logic switching –
independent energy source)
• No clear indication on loop sheet or in field
of safety critical nature of instruments
Pharmaceuticals
Design issues
• Design of periodic re-test method is the
instrument designers responsibility.
• This would help facilitate periodic testing
• Loop sheet to indicate safety critical nature
of instruments
Pharmaceuticals
Design issues
• SIS to actuate solenoid in panel, which
controls air supply to Shutoff Valve &
Control Valve
• High energy panel mount solenoid, not IS
pilot operated solenoid => more ‘suitable’
for SIS
• Control Valve should have positioner
suitable for SIS
Pharmaceuticals
Improvement suggestions
Pharmaceuticals
Loop sheet modifications
• IQ / OQ + Proof testing of the safety
function
• Validation of the retest method
• Loop sheet to indicate safety critical nature
of instruments
• Field marking
Pharmaceuticals
Commissioning Aspects
• Supplier might have correctly designed
safety Engineering.
• That does not mean it reaches standard.
• Modified Instrument/Electrical design
• Modified Instrument/Electrical
Commissioning
• Feeds into SRS
Pharmaceuticals
Machine / Package Design
•
•
•
•
E Ex d motor – Surface temperature limits
Variable Speed Drive.
Never below 10 Hz
Always with Thermistor Protection
Pharmaceuticals
Machine / Package Design
Pharmaceuticals
Machine / Package Design
Thermistor
Relay
Pharmaceuticals
Machine / Package Design
Pharmaceuticals
Maintenance
• Vital part of ensuring safety function remains
intact.
• Will have to retest interlocks on a periodic
basis.
• Will need to follow methods set out during
Instrument/Electrical design stage.
• Care required in effecting changes to the loop
when in use.
• Document which brings together the design
thread.
• Started by the Process Engineering group
• Continued by the Instrument / Electrical
engineering group
• Reviewed by Safety Engineering group.
• Live document until pre-start safety review.
Pharmaceuticals
Safety Requirements Spec
• Different way of thinking
Defence in Depth
Layers of Protection
• Risk Analysis
• Basic Statistics
• Fault Tree Analysis
Pharmaceuticals
New skills
Pharmaceuticals
6 June 1967
Pharmaceuticals
Pharmaceuticals
Pharmaceuticals
Download