THIRD QUARTER PERFORMANCE EVALUATION REPORT OF EMALAHLENI BULK WATER SUPPLY MPUMALANGA CHIEF DIRECTORATE: BULK INFRASTRUCTURE PROGRAMME PERIOD: 01 OCTOBER 2014 TO 31 DECEMBER 2014 2 REGIONAL BULK INFRASTRUCTURE GRANT 31 December 2014 TABLE OF CONTENTS 1 2 3 4 5 6 7 INTRODUCTION ............................................................................................................................................. 3 BACKGROUND TO THE PROJECT ............................................................................................................ 3 ATTENDEES OF THE EVALUATION MEETING ....................................................................................... 3 PROJECT DESCRIPTION ............................................................................................................................. 4 PROJECT SCOPE .......................................................................................................................................... 4 AREA OF SUPPLY.......................................................................................................................................... 5 PROJECT CONTRACT AND COST ............................................................................................................ 5 7.1 Contract Details........................................................................................................................................ 5 7.2 8 Funding Allocated to the Project............................................................................................................ 5 PROGRESS ON PROJECT........................................................................................................................... 5 8.1 Refurbishment of Point D Floating Cover Reservoir .......................................................................... 5 8.2 Construction of the 900mm Rising Main .............................................................................................. 6 8.3 Construction of a New Pump Station at Point D ................................................................................. 6 8.4 Upgrade of the 600ø Pumping Mains from Point D to Point A and from Point D to Point B ........ 6 8.5 Upgrade of Water Quarry at Point B ..................................................................................................... 6 8.6 Construction of a 10Mℓ Reservoir at Point E ....................................................................................... 7 8.7 Development of O&M Manual of All Bulk Supply Assets................................................................... 7 8.8 Replacement of a 400mm pipe with a 500mm diameter pipe........................................................... 7 8.9 Cleaning of Reservoirs ............................................................................................................................ 7 8.10 Installation of Telemetry at Four (4) Pump Stations ........................................................................... 8 9 10 11 12 RISKS AND MANAGEMENT THEREOF ..................................................................................................... 8 PROJECT BENEFICIARIES .......................................................................................................................... 8 OBSERVATIONS AND RECOMMENDATIONS......................................................................................... 9 PROJECT IMPLEMENTATION PHOTOS ................................................................................................... 9 ANNEXURE A: ANNEXURE B: ANNEXURE C: Project Implementation Photos Details of contracts awarded Details of job opportunities 3 REGIONAL BULK INFRASTRUCTURE GRANT 1 31 December 2014 INTRODUCTION In terms of Section 10(7) (b) of the Division of Revenue Act No 10 of 2014 (DORA) as promulgated in Government Gazette No 37595 dated 26 April 2014, the transferring national officer must submit a quarterly performance report for all Programmes funded by a Schedule 6 allocation within 45 days after the end of each quarter, in accordance of the relevant framework to the National Treasury. The Regional Bulk Infrastructure Grant (RBIG) is a Schedule 6 indirect conditional grant for the benefit in kind of municipalities. The objective of this Report is to provide a quarterly performance evaluation report of RBIG funded projects, in compliance with the DORA. The objective of this evaluation was to determine whether the progress on the project is commensurate with the expenditure to date as well as to determine whether the project is still on course in terms of the original planning. This performance evaluation report, covering quarter 3 of the 2014/15 financial year is for the Emalahleni Bulk Water Supply Project in Nkangala District Municipality under the Emalahleni Local Municipality (LM). 2 BACKGROUND TO THE PROJECT The Emalahleni Local Municipality (ELM) conducted an audit and assessment on the bulk water infrastructure at the beginning of 2011. The investigation was initiated as a result of pressing challenges in respect of water services in the town. The water treatment and delivery infrastructure as well as the operational management systems had degraded to the extent that water services were compromised in respect of both water quality and quantity. The audit recommended a phased implementation approach in order to mitigate the risks faced by ELM. The initial phase identified actions that would immediately improve the quality and assurance of supply of the bulk water infrastructure. Phase I was completed in the 2011/2012 financial year with recommendations that Phase II should be continued. Phase II was implemented in the 2012/13 financial year and was completed in April 2013. Phase III is focused on the upgrading of the key bulk infrastructure to meet the growing demand. Isiphethu Water Services was appointed by Rand Water to undertake the “Turnkey Project for the Upgrading of Key Bulk Water Infrastructure at Emalahleni Local Municipality” 3 ATTENDEES OF THE EVALUATION MEETING Below are the names of the people who attended the evaluation session on 13 January 2015: Name D. Van Der Boon C. Malefane M. Senyolo Organisation DWS Head Office DWS Mpumalanga DWS Mpumalanga 4 REGIONAL BULK INFRASTRUCTURE GRANT Name BJ.Matshiane L. Modiba B. Botes P.Madonsela M.Sello T. Nkonyane V.Ndaba P.Mguni 4 31 December 2014 Organisation DWS Mpumalanga Rand Water Emalahleni LM Emalahleni LM Rand Water Isiphethu Water Services Isiphethu Water Services Isiphethu Water Services PROJECT DESCRIPTION The proposed phases for the refurbishment work are summarised below. Phase I: Phase II: Phase III: Emergency Interventions to prevent System Collapse Short-Term Interventions to improve System Performance Medium-Term Interventions aimed at upgrading the infrastructure to meet the growing demand The project forms parts of operation and maintenance projects. The project is implemented in a Phased approach aimed at addressing two key problem areas: Dealing with losses Quality infrastructure From the planning of the project it was evident that there are huge water losses in the system and the municipality wanted to circumvent having to increase the supply and Water treatment, just to have the existing infrastructure over capacitated. The project is implemented as a turn-key contract. The Conditions of Contract are for EPC/TURNKEY, First Edition 1999 (The Silver Book), available separately from the International Federation of Consulting Project Managers (FIDIC). Copies of these conditions of contract can be obtained from the South African Association of Consulting Project Managers. Tel: (011) 463 2022. 5 PROJECT SCOPE The project scope for Phase III is made up of the following activities as outlined in the tender document: Installation of Non-Return Valves at Old Point D Pump Station Installation of Stand-By Generator for the Witbank WTW Inlet Facility. Refurbishment of Point D Square Reservoir Construction of the Missing Section of the 900mm Rising Main from Witbank Dam to Point B Pump Station Construction of a New Point D Pump Station Upgrade of Pumping Main from Point D to Point A Upgrade of Pumping Main from Point D to Point B 5 REGIONAL BULK INFRASTRUCTURE GRANT 6 31 December 2014 Upgrade of Water Quarry at Point B Refurbishment of Valves on Point A to Point E Pipeline Construction of Additional Storage Reservoir at Point E Pump Station Development of O&M Manual of All Bulk Supply Assets Replacement of an existing 400mm diameter pipe with a 500mm diameter pipe Training of ELM Personnel Cleaning of All Reservoirs Repair of leaks on bulk network Installation of Telemetry at Four (4) Pump Stations AREA OF SUPPLY The area of supply is within the jurisdiction of the Emalahleni Local Municipality. 7 PROJECT CONTRACT AND COST 7.1 Contract Details The details on the contract for the Phase III of the project are mentioned below: Name of Consultant/Contractor Contract Amount Period of the Contract Period Start Date Completion Date 7.2 : : : : : Isiphethu Water Services R 65 982 300 incl Vat 28 months 11 November 2013 30 June 2016 Funding Allocated to the Project Table 1: Project Budget Phases 1 to 3 Approved budget amount and spent 8 2011/12 R20 000 000 2012/13 R25 999 271 2013/14 R14 778 778 2014/15 R51 739 360 Total R134 517 409 PROGRESS ON PROJECT The overall physical progress for Phase III is at 30 % and it’s detailed below: 8.1 Refurbishment of Point D Floating Cover Reservoir The floating cover was successfully installed and practical hand over and the floating cover was commissioned on 2 October 2014. However the completion certificate was signed on 27 January 2015 as the contractor had to submit all the as-built drawings as well as the guarantees. A copy of the completion certificate is appended to this report. Isiphethu water services, Emalahleni Local Municipality and Rand Water Officials Quality assurance consultants were satisfied with 6 REGIONAL BULK INFRASTRUCTURE GRANT 31 December 2014 the works. Warranty and guarantee documents were handed over and accepted by ELM and Rand Water 8.2 Construction of the 900 mm Rising Main Construction of this activity has not yet commenced and is behind schedule due to the following: 8.3 Approval of TRAC (SANRAL) way leave – Pending arrangement of a guarantee of R250 000 required by TRAC. This Rand Water is in the process of arranging the Guarantee and the expected completion date 20 February 2015. The Wayleave will be approved once the guarantee is submitted to TRAC. Supply and Delivery of 900 mm pipes from Hall-Longmore, delivery expected 11 February 2015. The pipes were ordered on in September 2014 and the expected delivery date was 15 December 2015, but due to challenges with the supplier the revised expected delivery date applies. The original delivery schedule is attached to this report. Construction of a New Pump Station at Point D The designs were submitted to Rand Water and comments were received on the designs and drawings. Revised drawings and design report will be submitted on 9 February, for approval. Construction of the pump station will commence as soon as communication of approval is received from Rand Water 8.4 Upgrade of the 600ø Pumping Mains from Point D to Point A and from Point D to Point B The designs for the pipeline were submitted to Rand Water on 18 December 2014 the designs are being assessed by Rand Water for Approval. The 600 mm dia ductile iron pipes were delivered on site on 28 November 2014.The contractor is busy exposing existing services on the pipe route and setting out of the pipeline and construction is expected to commence on 6 February 2015 pending the approval of the designs. 8.5 Upgrade of Water Quarry at Point B The requirements for refurbishment and upgrade, or modifications to existing systems to improve the operations and efficiency of the pump station, has been identified as follows: Installation of four complete new 700 ℓ/s, 250 KW submersible pumps. (3 x Duty and 1 x Standby) Alterations to delivery pipework. Extension of the existing control station to cater for the new MCC’s Construction of concrete palisade fence around control station Refurbishing of existing bypass and interconnecting pipework and valves. Installation of an additional 500 KVA transformer and the bulk electrical supply upgraded. Construction of a new rectangular dry well abstraction chamber which will consist of a concrete structure with size of 8.5 x 6.1 x 15 m deep equipped with a safety ladder. The 7 REGIONAL BULK INFRASTRUCTURE GRANT 31 December 2014 cover of the walkway will be checkered plate panels of size 2 m by 2 m. The chamber will be open however cover will be supplied by enclosing the steel structure on top of the well. The detailed designs were submitted to Rand Water on 22 September 2014 and a go ahead was given by Rand Water on 21 October 2014 to proceed with work without the formally signed designs. Subsequently a meeting with ELM and Rand Water was conducted on 28 October 2014 for the final presentation of drawings indicating the activities to be carried out. Isiphethu Water Services is awaiting the variation order for temporary electrical works from Rand Water; however activities such as ordering of the pumps and other works can proceed. 8.6 Construction of a 10 Mℓ Reservoir at Point E The designs for the reservoir have been completed but it will form part of the scope of works for the later phases as the current need for the Emalahleni Local Municipality is increased abstraction capacity and not storage. 8.7 Development of O&M Manual of All Bulk Supply Assets This activity is ongoing with the anticipated finalisation in mid February 2015 8.8 Replacement of a 400 mm pipe with a 500 mm diameter pipe The overall progress of this activity is 70%. Table 3 below outlines the milestones for this activity. Table 2 INSTALLATION OF 500 MM DIA PIPELINE: PROGRAMME Activity Start Finish Progress Delivery of material 12 May 2014 16 May 2014 100% Exposing of Existing Services 23 June 2014 10 July 2014 100% Trench Excavation 8 July 2014 10 July 2014 75% Pipe Installation 4 August 2014 23 January 2015 70% Final Inspection and Handover 26 January 2015 30 January 2015 CHALLENGES: There was a three weeks delay during the month of August due to labour unrest which occurred on a project parallel to this. The site activity was affected as the site was closed off by local residents. The situation was well handled by the local councillor. A revised program for the replacement of the GRP line was submitted in October 2014. 8.9 Cleaning of Reservoirs A total number of 19 reservoirs have been successfully cleaned to date. There is only reservoir namely an 11.5 Mℓ Res at Point B. An isolating valve at the inlet of this reservoir is broken thus it needs to be replaced when the reservoir is cleaned. A variation order for the fixing if this valve has been submitted to Rand Water and it will be attended to once the variation order is approved. 8 REGIONAL BULK INFRASTRUCTURE GRANT 8.10 31 December 2014 Installation of Telemetry at four (4) Pump Stations Rand Water indicated that this item will be treated as a separate project since the installation of the new system is not only a variation but a deviation from the original scope of work. The original scope of work entailed the repair of the existing system however the Emalahleni Local Municipality indicated that a new system should be installed instead of repairing the old one. Isiphethu Water Services is still awaiting a directive with regards to the way forward in implementing this item. 9 RISKS AND MANAGEMENT THEREOF There were a number of challenges experienced on site of which can be summarized as follows: a) Delays in the construction of the 500 mm pipeline b) Upgrading of the Point B Quarry Pump Station 10 There was a three weeks delay during the month of August due to labour unrest which occurred on a project parallel to ours. The site activity was affected as the site was closed off by local residents. The situation was well handled by the local councillor. A revised program for the replacement of the GRP line was submitted in October 2014. The conceptual design presented in the tender document entailed the construction of a dry well with submersible pumps. During interaction with ELM a concern was raised with regards to the maintenance of submersible pumps, therefore the request was made to consider other alternatives. Numerous meetings were held with the municipality where the original concept of constructing a dry well was approved. PROJECT BENEFICIARIES There are a number of water supply systems supplying potable water to the residence of the Emalahleni Local municipality. These include the following: (i). (ii). (iii). Emalahleni water supply system – This supplies the town of Emalahleni, the industries and the surrounding communities which include Clewer to the immediate west; Ogies and Phola which are approximately 25 km from the town of Emalahleni Kriel water supply system – This is a separate scheme which supplies the town of Kriel and the township of Thubelihle. The scheme used to be managed by Eskom before the scheme was transferred to Emalahleni LM by Eskom Wilge water supply system –This is a separate scheme which supplies the town of Wilge west of Emalahleni. The scheme is dependent on groundwater. The project will benefit the Emalahleni community by assuring the supply and improving the water quality. The number of people who benefited during quarter 3 in the 2014/15 financial year from job opportunities during Phase III of the project is 13. This includes 6 adult men and 7 young men. 9 REGIONAL BULK INFRASTRUCTURE GRANT 11 31 December 2014 OBSERVATIONS AND RECOMMENDATIONS The progress on the project has been slow due to the completion the first phase of the project, professional services (design, drawings, and contextual obligations), but construction has commenced on various parts of the project and measurable progress should be noted in the next few months. 12 PROJECT IMPLEMENTATION PHOTOS The pictures below on the progress of work carried out on this project. 10 REGIONAL BULK INFRASTRUCTURE GRANT ANNEXURE A: 31 December 2014 Project Implementation Photos Figure 1: Replacement of 400 mm dia. Old GRP Line with 500 mm dia. DI Pipe Figure 2: Blanket and Backfilling of replaced 400 mm dia. Line along Schonland Drive 11 REGIONAL BULK INFRASTRUCTURE GRANT 31 December 2014 Figure 3: Installation of 500 mm dia. Gate Valve for the Pipe line in Figure 2 Figure 4: Installation of 500 mm dia. Bend and Backfilling for the Pipe line in Figure 1 12 REGIONAL BULK INFRASTRUCTURE GRANT 31 December 2014 Figure 5: Final Backfill for the replaced Old GRP Line in Figure 1 Figure 5: Welding of electrical cable for the Rain Water Pump on the Floating Reservoir 1 REGIONAL BULK INFRASTRUCTURE GRANT 31 December 2014 ANNEXURE B: DETAILS OF CONTRACTS AWARDED CONTRACTOR CONTRACT VALUE (incl. VAT) CONTRACT AWARD / START DATE PLANNED COMPLETION DATE ACTUAL COMPLETION DATE EXPENDITURE AS AT 31 Dec 14 (incl. VAT) % COMPLETIO N Emalahleni Bulk Infrastructure Programme Phase 1 Bosch Munitech R 45 000 000 Sept 2011 March 2012 March 2012 R 45 000 000 100% Emalahleni Bulk Infrastructure Programme Phase 2 Tlou – Siza Tech JV R 26 000 000 Nov 2012 Apr 2013 Apr 2013 R 26 000 000 100% R 31 016 134.02 30% CONTRACT NO. AND NAME Emalahleni Upgrade of Bulk Isiphethu Water R66 000 000 Nov 2013 April 2016 Water Services Infrastructure NOTE: Retention monies withheld have been included as expenditure. All figures include 14% VAT. In Progress 2 REGIONAL BULK INFRASTRUCTURE GRANT ANNEXURE C: 31 December 2014 Details of job opportunities Last name I.D. Number Youth Men Adult Men Adult Woman Youth Woman First name Gender . OCTOBER 2014 Start date Number of labour days Daily wage rate . NOVEMBER 2014 . DECEMBER 2014 Number of labour days Daily wage rate Number of labour days Daily wage rate Female 0 R 180.00 0 R 180.00 0 R 180.00 Female 0 R 180.00 0 R 180.00 0 R 180.00 Liwis Nohunga AC166625 Male 2014/08/25 21 R 180.00 21 R 180.00 10 R 180.00 Victor Mlangeni 7607275385081 Male 2014/08/29 21 R205.74 21 R 205.74 10 R205.74 Boetie Nkosi 7909285685082 Male 2014/08/29 21 R205.74 21 R205.74 10 R205.74 Ndumiso Mdewuka 7803135922086 Male 2014/09/01 21 R 205.74 12 R 205.74 10 R 205.74 Sipho Ncongwane 7309185540083 Male 2014/09/01 21 R 205.74 15 R 205.74 10 R 205.74 Xolani Sibanyoni 8712235197086 Male 2014/09/01 21 R 205.74 17 R 205.74 10 R 205.74 Emilio Sefo Carlos Bheki Sizonqoba Sbusiso Doee Timbe Sigaugue Mavuso Mahlangu Mabena 8026 12AC71422 AC159958 8406245329082 8611025822087 9205065374080 Male Male Male Male Male Male 2014/08/25 2014/08/25 2014/08/25 2014/08/25 2014/08/29 2014/09/01 21 21 21 21 21 21 R 180.00 R 180.00 R 180.00 R 180.00 R205.74 R 205.74 21 21 21 21 21 15 R 180.00 R 180.00 R 180.00 R 180.00 R 205.74 R 205.74 10 10 10 10 10 10 R 180.00 R 180.00 R 180.00 R 180.00 R 205.74 R 205.74 Vusi Ndaba 8204105281083 Male 2014/08/18 21 R205.74 21 R 205.74 15 R225.00 TOTALS (DO NOT ENTER DATA IN THIS LINE) 273 248 135