Week 3: Strategic Decision Management Discussion Project Cost (graded) Whether you are a project manager or a program manager, you will be concerned with project cost. Below is a list of terms that you would see and use when working with project cost. Choose only one, explain it, and give some examples of how it works. Cost Performance Index (CPI) Schedule Performance Index Point of Total Assumption (PTA) Planned Value (PV) Actual Cost (AC) Earned Value (EV) Budget at Completion (BAC) Cost Variance (CV) Schedule Variance (SV) (SPI) Estimate at Completion (EAC) Estimate to Complete (ETC) Variance At Completion (VAC) Probability (P) Impact (I) Expected Monetary Value (EMV) Expected Activity Duration (EAD) Standard Deviation (SD) Late Start, Early Start, Late Finish, Early Finish (LS, ES, LF, EF) To Complete Performance Index [TCPI] To Complete Performance Index [TCPI] Responses Response Different ways of defining cost Author Instructor Ohayia Date/Time 7/22/2012 5:53:38 AM Class - there are many ways to look at cost, in general, I see cost as a resource sacrificed or fore-gone to achieve a specific objective or something given up in exchange. I look forward to reading your posts this week...enjoy the discussion! RE: Different Corinne Lisefski ways of 7/22/2012 3:12:00 PM defining cost I discussed Late Start, Early Start, Late Finish, Early Finish (LS, ES, LF, EF) in my last class, Project Management. The way it was explained in that class, is that Late start is the latest date a project can start without going over schedule or costing more money to finish on schedule. Early Start is the earliest a project can start. Late finish is the latest a project finish and early finish is the earliest a project can finish. If a project gets behind schedule, its going to cost more money to get it back on schedule and finish in the allotted amount of time. Likewise it will cost more money than originally budgeted if the project doesn't finish by the end date. It also costs more money to get started earlier and getting started late means that you will have to make up time somewhere or the project could go both over budget and over schedule. "The early start, early finish, late start, and late finish dates of a project schedule are the primary dates that are calculated in any project schedule. The early start dates of the project schedule are the earliest that any activity in the schedule can be scheduled to start given the logic and constraints of the schedule. The early finish of an activity in the schedule is the earliest that the activity can be scheduled to be completed given the logic and constraints of the schedule. The late start of an activity is the latest that a project activity can be scheduled to be started without having to reschedule the calculated early finish of the project. The late finish of an activity is the latest that a project activity can be finished without having to reschedule the late finish of the project. The late finish of the project is the late finish of the last activity to be completed in the project. The schedule that is made up of the early start and early finish of each activity in the schedule is called the early schedule. The schedule that is made up of the late start and late finish of each activity in the schedule is called the late schedule." http://www.adeak.com/2010/01/what-are-the-early-start-early-finishlate-start-and-late-finish-dates-of-a-project-schedule/ RE: Different ways of Instructor Ohayia defining cost 7/24/2012 11:36:12 AM Modified:7/26/2012 1:42 PM Thanks Corrine! Class - an interesting thing about ES, LS, EF, and LF is that they play a major role help to identify the critical path of a project. This is a good indicator of cost management as well, delay of any activity on the critical path will inevitably impact the project cost! RE: Different ways of Timothy Mark Thurman defining 7/25/2012 8:54:56 PM cost to tie ES LS EF LF into this and your first post, I think time is more frail and constant expenditure of a project. On a project, or program for that matter, the work can be stopped and sponsors can pull money but the clock is still running. The critical path can be crashed (assuming there is time planned for it) at a higher cost to the project but making the project conclude sooner than originally planned. This is important with project's like research and development, if a company needs to get a new product to market to beat the competition then the clock is likely to be a stronger motivating factor than cost. I'm sure there are other examples too. RE: Different ways of Troy Brown defining cost 7/28/2012 6:38:21 AM Modified:7/28/2012 6:38 AM Timothy nice example with bring up crashing a project. With crashing the critical it will add more cost to the project because you are reducing the time to do something, which would require adding more resources to reduce the time. The other very important thing you have to keep in mind is that when you crash your project it will start to affect other paths on your project. You might start with one critical path, crash that path and end up with 5 additional critical paths. RE: Different ways of Timothy Mark Thurman defining cost 7/28/2012 11:55:33 AM You bring up an interesting point, all pieces are connected in one way or another. This is what makes managing a project or program as difficult as it is. It's important to think several steps ahead so that when surprises do arise the solution doesn't create more problems than it solves. I'm sure we've all seen examples in our own lives of allowing haste to be detrimental. That is all the more reason to be thorough in the planning stage. RE: Different ways of Tyrone Labad defining cost 7/25/2012 7:02:51 AM Hello ES, LS, EF, and LF, this is what i make of them . They are my friends" said a project manager. The newly proposed " revisiting PM" strategies methodology is not showing up encouraging results. What is interesting here is to observe that , cutting costs is not always being clinical about the system. Costs can be optimized by processes s which focus on trimming the layers in the organization. This in all is directed towards identifying and then researched on for defining the critical path of the project RE: Different ways of Steven Frank defining cost 7/25/2012 7:21:05 PM Just when I was getting over my nightmares about AON charts from an earlier class, you bring this back up. HA! Early and late schedules are very handy for adjustments due to slack in the critical path. I can honestly say that manually creating AON charts made me really appreciate the amount of calculations done by software like MSProject. I never want to have to do that again, though it is nice to know more of the work the software does for us. To relate this back to cost, I would say that cost is a resource I would gladly sacrifice to have PM software do some of the heavy lifting for me. I tend to see cost as one member of a troika or triad. Cost, Time, and Quality are three parts of a balanced equation. If you reduce the amount of cost, either the time gets larger or the quality gets smaller. Any time you change one, the other two react accordingly within the static scope of work. Normally a scope change is what changes the balance. RE: Different ways of Corinne Lisefski defining cost 7/26/2012 3:37:34 PM I was thinking the same thing Steven. But I actually enjoyed doing the AON, well the ones we did by hand were easy, few steps in the project. I didn't really get to use MSProject, just the very basics. I would like to learn more though. I agree with you about the triad. You do have to find a balance between all three of those, to ensure a good product is produced and your customer is happy. In our construction we do have alot of change orders, and its usually for change in the scope of work or an unforeseen condition. Sometimes it changes the time sometimes not. It usually increases the cost. RE: Different ways of Steven Frank defining cost 7/26/2012 5:39:44 PM MS Project training is probably the one thing I think my education plan lacks. Looking at the rest of my curriculum, I see I'll need to find an outside source for MS Project training. Any suggestions from the class? RE: Different ways of Robert Allen defining cost 7/27/2012 7:52:33 PM My observation has been that many companies seem more willing to throw money at cost overruns, than at project planning. My theory as to why this is, is this: large companies are built on many fiefdoms of VPs and Directors. These people are selected for their jobs by their aggressiveness, at least in US companies. This level of aggressiveness and desire to move up the corporate ladder seems to mean that they are less prone to help each other out for the common (company) good. I can somewhat understand this, as if you're in a division that is clearly supporting current but getting older product, you may be in more of a dead end than those working on the next level of product to replace it. Still it's disturbing that everyone seems to have to be engaged in protecting their domain. This causes so much waste. Robert RE: Different ways of Courtney Little defining cost 7/29/2012 6:25:09 PM Robert, I agree in many ways. Companies do seem to spend exorbitant amounts of money on projects that end up going well over the original estimates in order to "save face" or to "look good" to their superiors. I know when I used to work in the retail channel for the wireless company I work for, there was a regional VP of sales that wanted to have a kiosk at a local mall. There was a standalone store at the bottom of the mall, but he wanted both. They paid a ridiculous amount of rent for the space, salaries to employees (of which most got fired for not meeting quotas due to low traffice-everyone went to the standalone store), and many times borrowed headcount from the standalone store during holiday hours due to higher mall traffic but still no increase in sales. For years the kiosk struggled and the VP tried many different tactics to try to improve sales to no avail. I would be curious to know how much he put the company in the red due to his not wanting to admit his idea had failed. Planned Value (PV) Nazar Eljack 7/23/2012 3:40:55 PM Planned Value (PV) is the approved value of work to be completed in a given time period; i.e. it is the money that you should have spent as per the schedule. As per the PMBOK Guide “Planned Value (PV) is the authorized budget assigned to work to be accomplished for an activity or WBS component. Total planned value for the project is also known as Budget At Completion (BAC).” PV = (Planned % Complete) X (BAC) Planned Value is also known as Budgeted Cost of Work Scheduled (BCWS). Example: You have a project to be completed in 12 months and total cost of project is $100,000. Six months have been passed (and schedule says that 50% of work should be completed). What is the Planned Value? Let us see that what we have been given in this questionProject duration – 12 months Project Cost (BAC) – $100,000 Time elapsed – 6 months Percent complete – 50% (as per the schedule) Definition of Planned Value says that Planned value is the value of work that should have been completed so far (as per the schedule). Therefore, in this case we should have been completed 50% of total work. Hence, Planned Value = 50% of value of total work = 50% of BAC = 50% of $100,000 = (50/100)X $100,000 = $50,000 Therefore, Planned Value (PV) is $50,000 http://pmstudycircle.com/2012/05/planned-value-pv-earned-value-ev-actual-cost-acanalysis-in-project-cost-management-2/ Project Cost Darren Coleman 7/23/2012 5:52:36 PM Standard Deviation The standard deviation is a statistic that tells you how tightly all the various examples are clustered around the mean in a set of data. When the examples are pretty tightly bunched together and the bellshaped curve is steep, the standard deviation is small. When the examples are spread apart and the bell curve is relatively flat, that tells you you have a relatively large standard deviation. One standard deviation away from the mean in either direction on the horizontal axis accounts for somewhere around 68 percent of the people in a group. Two standard deviations away from the mean account for roughly 95 percent of the people. Three standard deviations account for about 99 percent of the people. x = one value in your set of data avg (x) = the mean (average) of all values x in your set of data n = the number of values x in your set of data RE: Project Corinne Lisefski Cost 7/24/2012 11:35:54 AM To add to your comment Darren, I found this site, that give the formulas for PM. It does give the formula for Standard Deviation, but your explanation is easier to understand. http://69.13.149.40/Students/Formulas.htm RE: Project Instructor Ohayia Cost 7/26/2012 1:49:53 PM Thanks Darren/Corrine! Standard deviation is a great tool for assessing variations (or deviation) from you estimates. Typically PERT analysis is also used to address variations in estimates. Any experience with PERT analysis? RE: Project Tyrone Labad Cost 7/27/2012 4:42:50 AM The constant need of reviewing progress lead to the need of the PERT formula and and how it is used to make estimates when you have a high level of uncertainty.Regardless of the technique , the tendency in project estimation is to provide one number for each estimate. In other words, if you have 100 activities on your schedule, each activity would have one estimate associated with it. This is generally viewed as the “most likely” estimate.In many cases you can be more accurate by applying a simple PERT (Program Evaluation and Review Technique) model. PERT is an estimating technique that uses a weighted average of three numbers to come up with a final estimate and provides an accurate status report. RE: Project Emilia Crespo Cost 7/27/2012 3:50:57 PM Pert is a formula similar to the risk management process, it will examine the possible results of the project: Best case, worse case, and expected case. In project management always preparing for the unexpected is important in reducing possible errors further in the project. Pert formula does just this provides a variety of results to increase the possible solutions to any potential programs. RE: Project Corinne Lisefski Cost 7/28/2012 12:11:07 PM I haven't had any experience with PERT analysis. We do a price/cost analysis before we award the project and with any change orders that increase the total cost of the project. We do track the amount of money spent on contracts, but that is mostly done with task order contracts. Schedule Variance (SV) Steven Frank 7/23/2012 7:26:07 PM Schedule variance is the difference between the planned schedule and the actual schedule. This variance can come from delays or from tasks being performed in less time. While early is always better, too much is a sign of schedule padding. You want enough padding in the schedule to take the pressure off, but not enough to be inaccurate. One of my projects that recently had delays was a data center power outage. Facilities was doing UPS maintenance, so they took UPS A down one weekend, then UPS B the next weekend. The UPSes are redundant of each other, so there was little planned impact. On the second weekend, when facilities was bringing UPS B up, UPS A failed momentarily. It was just long enough to create a power spike when the UPS came back up, burning 40 line cards in the server farm and dropping 1,920 server connections. My 14 hour simple project became a week-long rush to find enough parts to repair the site. Most of my projects run smoother than that one. The refresh sites I'm doing, we schedule the entire night from an hour after the last client business finishes in the building to an hour before the first comes in in the morning. When we do a small site like a banking center, we have 7pm to 6 am, but there is only one switch and one router to swap out, so we finish early. we've even had equipment show up DOA and had a tech drive 3 hours to pick up a replacement and finished the site. His drive time gave me time to process the return paperwork for Cisco so I could replace the one I borrowed. Earned Value (EV) Venkat Yetrintala 7/23/2012 9:15:43 PM I have learned most of these concepts in my previous class Project Management. Here I would like to talk about Earned Value (EV): Earned value is a way to measure project's progress and forecast it's completion date and final cost, and provide schedule and budget variances along the way. By Integrating three (cost, schedule and work) measurements, it provides consistent, numerical indicators with which you can evaluate and compare projects. For example, if the Planned Value (PV) is $5,000 and the project is 50% complete, the EV would be calculated as, EV = PV x % = 5,000 x 50/100 = $2500 RE: Earned Elvis Niangoran Value (EV) 7/23/2012 10:45:04 PM Thank you for you comment Venkat and to add to your comment Earned Value is also known as Performance Measurement, Management by Objectives, Budgeted Cost of Work Performed and Cost Schedule Control Systems. RE: Earned Nazar Eljack Value (EV) 7/24/2012 11:25:22 AM Found another example here: You have a project to be completed in 12 months and total cost of project is $100,000. Six months have been passed and $60,000 is spent but on closer look you find that only 40% of work is completed so far. What is the Earned Value (EV)? From the above question you can clearly see that only 40% of work is actually completed. Definition of Earned Value says that it is the value of project that has been earned. In this case only 40% of work has been completed. Hence, Earned Value is = 40% of value of total work = 40 % of BAC = 40% of $100,000 = 0.4X$100,000 = $40,000 Therefore, Earned Value (EV) is $40,000 http://pmstudycircle.com/2012/05/planned-value-pv-earned-value-ev-actualcost-ac-analysis-in-project-cost-management-2/ RE: Earned Value Instructor Ohayia (EV) 7/24/2012 12:17:24 PM Thanks Nazar - EV is a powerful tool to assess the value of your project in relation to the schedule and cost. In your example, besides the fact that you have received 40% value, what does that say about the overall status of the project? RE: Earned Value Tiffany Bullard (EV) 7/28/2012 4:39:55 PM I don't think .40 is a bad earned value. As far as I know as long as it's a positive number it's good. Its only when the figure comes back negative that the project manager should worry. Essentially, a positive number is good, ahead of schedule, while a negative number is bad, behind schedule. RE: Earned Value Nazar Eljack (EV) 7/24/2012 12:49:54 PM Unfortunately that mean something is wrong, where we running behind. Can’t say that the project will fail but there a possibility to go over budget or we could miss the time target. RE: Earned Value Venkat Yetrintala (EV) 7/24/2012 4:35:42 PM Based on earned value of above example project is in risk, here are some advantages of using earned value analysis to program / project managers: - provides a set of specific guidelines and set methods, it allows even the novice user to produce more accurate plan than before - eleminates subjectivity, it provides a reliable method for understanding project status - by maintaining record of both planned and actual performance, it allows project managers to understand planning errors and improve ability to plan future projects. - by recording actual data, it provides a basis for making more accurate estimates next time RE: Earned Value Troy Brown (EV) 7/24/2012 7:24:55 PM I think one more thing you can here Venkat is the EV helps PM give better understanding and realistic value or measure of the performance of the project. From an traditional standpoint, most people other than Project Management professionals look at only the cost or schedule of the project to measure the if the project is on track or at risk. Where EV shows a realistic view of the overall performance of the projects. This realistic measures does help PM's look at risk or performance of the team. Like our Professor stated EV is a Powerful tool, the only problem most people outside the PM circle doesn't use it or understand it. For example, at my company we do not use this tool and most of the PM's don't even know what earn value means. And from an accounting standpoint their major measure in the success of a project is the cost. RE: Earned Value Elvis Niangoran (EV) 7/25/2012 12:43:59 PM This means the overall project is coming under budget. If the ratio were one, it would be exactly on budget. If it is over one, the project is over budget. RE: Earned Tiffany Bullard Value (EV) 7/25/2012 5:17:57 PM Venkat, I agree with your reasoning and I believe Earned Value is the easiest and most useful measure of cost that a project manager can use. You can easily use this calculation to compare various project which would prove useful to a program and portfolio manager as well. RE: Earned Value Kim Easter (EV) 7/25/2012 10:59:38 PM I enjoyed learning earned value (EV). Other measurements an be determined once the EV is calculated such as the CPI. The cost performance index refers specifically to a method, chart, or other instrument that is implemented for the purposes of measuring the actual cost, AC, and efficiency of a project. The CPI is determined by measuring the ratio of EV to AC. The equation to determine the CPI can be derived by the following equation: CPI=EV divided by AC. If the resulting value is greater than one indicates that the conditions of cost efficiency for the project are considered to be favorable. A resulting value that is less than one indicates that the conditions of cost efficiency for the project are considered to be less than favorable. The CPI can change over the life of a project depending on the ways in which the EV and AC change. http://project-management-knowledge.com/definitions/c/costperformance-index/ Project Oral Bestman 7/24/2012 12:11:06 PM cost Actual Cost- is the total amount of material, labor cost and any directly associate with overhead costs that can be charge to a specific project. The goal is to breakdown specific cost of a project. For example, a pair of shoe cost $20.00 in material, $10.00 in labor, and $25.00 for overhead cost which include equipment, and operation cost. The actual cost for the pair of shoe is $55.00. RE: Project Tiffany Bullard cost 7/26/2012 4:51:19 PM I believe Actual cost is an important measure in project management because it doesn't allow costs to 'hide' . With your shoe example it shows you exactly how much it will cost to manufacture the shoe and that helps the company figure an acceptable cost in order to break even. RE: Project Instructor Ohayia cost 7/27/2012 10:03:00 PM Thanks Tiffany/Oral - Actual cost is good once your begin the project, however, at the beginning of the project all you to work with is an estimate. RE: Project Jenna Pingitore cost 7/29/2012 6:46:22 PM Actual cost and estimate cost are both used at different times in a project, but are both important in their own way. Before the project is officially up and running and you are comparing what one company may have to offer versus another, you need to know what you are comfortable spending and need to make sure that what you are paying for will give you what you are looking for. When you look at the estimate cost, you need to keep in mind that it is just that, an estimate. When you get in to the thick of a project and are actually spending money on the project, that is when it becomes actual cost and when you have done just that, actually spent the money. RE: Emilia Crespo 7/29/2012 9:39:19 PM Project cost The esitmate should also be higher then the actual cost. If the estimate is just taking into consideration the labor and materials it may lead to problems when during the project. Once the actual project begins there is also a high possibility that additional funding will need to be use, whether that is for labor or materials. Therefore, having a higher estimate is most beneficial in reducing the possibility of not having enough funding if the project needed it. RE: Project Corinne Lisefski cost 7/28/2012 12:43:53 PM We start with an estimate (Independent Cost Estimate - ICE) for the cost of project. When in bids come in, we compare the bids to the estimate. There is an acceptable range that the bids must be within. If they are below the range, we ask the bidder to explain the scope of work to ensure they understand the scope of the work and can do the work for the price they bid. If the bid is above the ICE, we reevaluated the ICE or ask the bidder for a Best and Final Offer. Prices are evaluated by out in-house architects and engineers(A/E), as well as our consulting A/E RE: Project Shavonda Marks cost 7/28/2012 11:55:37 PM I believe in certain instances that starting with an estimate is always better. There was one project in my department where they were trying to implement a new gateway that will pass along information to the FDA faster. Other pharma companies were researched on how they use their gateway. The software was reviewed by quality, speed, and cost. From these estimates, the project team could determine if it more cost effective to purchase the software or built own. RE: Paul Lindeke 7/28/2012 12:52:27 PM Project cost With working on a huge project, there are a lot of variables and it is difficult to determine the actual cost of the project so you don't know the actual cost until the end of the project. Of course the estimate that you come up with is usually pretty close to the actual cost, unless something huge happens and the project has to go through a huge change which would cost more money. Planning the project first is the most important step since you will be able to figure out how much materials and labor you are going to need to get the project done within budget, plus it will give you a very accurate estimate. RE: Project Ricardo Antezana cost 7/28/2012 7:05:06 AM Yes professor is an estimate that could have been done by a top-down estimating where there is actually not very many details know about the project, it's just based on previous projects of similar nature, often used on early stages of a project. Or a bottom-up estimating where most of the details are know about the project, basically the people who are doing the work, look closely to each activity and estimate the cost of that activity, this is often used on later stages of a project. Project Cost Darren Coleman 7/24/2012 1:20:25 PM Schedule Performance IndexConsiders all tasks, not just those on the critical path, so that non-critical tasks are not ignored. Does not take into account if a project's critical path is on schedule. Ignores tasks that have $0 budget such as submittals that require approval or ordering materials. Is used in conjunction with critical path analysis A project with a SPI greater than 1.0 indicates that the project is ahead of schedule this is a great thing. If the project SPI is less than 1.0 the project is behind schedule absolutely unacceptable. An SPI equal to 1.0 indicates that a project is precisely on schedule. The SPI for individual projects and a company's projects as a whole will vary. Some parts of a project may be ahead of schedule and some will lag behind. RE: Project Costs Andrea Johnson 7/24/2012 1:49:56 PM It has been a few classes back since I used these formulas so I had to do some research. I looked into CPI, the Cost Performance Index. The CPI is “a measure of how well the project is doing in terms of spending the project budget.” The CPI is calculated by dividing the budgeted cost of work performed by the actual cost of work performed. It is a comparison of the actual money spent to complete work up to date versus the actual amount of work that has been completed to date. This article stood out to me because it explains how calculating the CPI is beneficial for projects of all sizes. It also rationalizes that if the project is running as planned the actual amount of money spent to complete work up to a certain point in the project will equal the actual amount of work completed at that same point in the project, and this would generate a computing result of 1. Therefore any variation from 1 should provide an indication to reevaluate project costs whether they are slightly good (results greater than 1) or slightly bad (results less than 1). http://www.adeak.com/2010/03/what-is-the-cost-performance-index/ EAC. Robert Allen 7/24/2012 3:46:38 PM Being a computer programmer I'm somewhat anal-retentive. Thus I find it particularly annoying that the shell is asking us about these things when the book doesn't discuss them at all, and the lecture notes say what the formula is but nothing more. I've seen these discussed in a previous PM class but couldn't find EAC. Who knows, maybe the search mechanism in VitalSource bookshelf is just broken. I was going to expand and explain the forumula a step at a time, but it gets cumbersome so I'll just fall back to this web definition: "EAC is equal to the actual cost of work performed (ACWP) plus the estimate to complete (ETC) for all of the remaining work.", http://www2.cit.cornell.edu/computer/robohelp/cpmm/Glossary_Words/Estimate_at_Com pletion.htm . To explain this, you would use EAC at a time/times during a project when the project is not yet complete, and you'd like to know if you're going to complete on budget. Thus it looks at what you've already spent. Actual Cost of Work Performed, plus the amount Estimated To Complete the project/portfolio. Note that you can't simply say for example, if you're 2/3 of the way through the budget halfway through the project that you're in trouble, because ETC could be 1/3 or less than the budget. Budget and time are not in the same timeline. Robert RE: Point of Total Assumption Steven Frank 7/24/2012 7:40:00 PM Modified:7/24/2012 7:43 PM The point of total assumption is the fixed price of a fixed price contract. This is the balance point where the seller starts to absorb costs. The PTA is usually set at a point where the seller doesn't absorb costs with reasonably expected issues. An earthquake at a construction site would quickly push most sellers past the PTA, as an example. I found a pretty good graphic for this one: http://er-sspawar.blogspot.in/ RE: Point of Total Troy Brown Assumption 7/26/2012 8:48:47 PM To add to Steven post I found an detailed article explaining PTA and how to arrive at using or formulating the PTA formula: http://pmpsnacks.wordpress.com/2011/07/23/point-of-total-assumption-ptawhats-the-point/ With using PTA it gives an opportunity for the seller/buyer to negotiate an fixed contract or an target cost of a project with attached unknown cost. Instead of of the seller eating the cost of a very risk project that goes over the target price because of the variables that can't be defined as a cost, both parties share some of the burden. When the project hits the target cost It is usually than both parties will split the cost to a certain % of the project cost. Usually there is a 80/20 between the seller and buyer. I wish the company that I work at now would start using a tool like this for some of our riskier projects and rebuild that have a lot of unknowns... These projects usually turn to a big issue because the unknowns inflate the cost of the project as does the expediting costs as more unknown come up later in the project. Cost Performance Index (CPI) Troy Brown 7/24/2012 7:44:33 PM CPI is a measure of the cost efficiency with which the project is being performed. (Gido 253) CPI = CEV(cumulative earned value)/CAC(cumulative actual cost) To determine the performance of a task or of the project using the CPI it is measured in a ratio that is equaled 1. So for every dollar that is consumed in the project, the CPI measures the earned value of each dollar. So, if you earned $9 of work but actual spent $10 your CPI would be .9 or $.90 of of every dollar used on the project so far. Shown in formula: CPI = $9/$10 = .9 The thing you have to look at here is how much below or how high your are above 1. The standard for a successful project or to be on track with your project is staying as close to the ratio of 1 as you can. If you get too low or too high, as a PM you then need to look into the issue and find a way to get back on track or develop an action plan to fix the risk or problem. A rule of thumb that I learned from another PM class is the threshold is +/- 10% of 1 before you start to looking into the problem or risk. Gido, Clements. Successful Project Management, 5th ed., 5th Edition. South Western Educational Publishing, 02/2011. <vbk:9781133614487#outline(7.7.2)>. Cost Performance Index Damion Alexander 7/24/2012 10:05:32 PM The cost performance index refers to a method, chart, or other instrument that is implemented for the purposes of determining/measuring the actual cost efficiency of a project. The cost performance index is determined by measuring the ratio of earned value (also known by the abbreviation of EV) to actual costs (also known by the abbreviation of AC). The formula for cost performance index is CPI=EV divided by AC. If the resulting value is greater than one indicates that the conditions of cost efficiency for the project are considered to be favorable. A resulting value that is less than one indicates that the conditions of cost efficiency for the project are considered to be less than favorable. Source: http://project-management-knowledge.com/definitions/c/cost-performanceindex/ Good or bad... Instructor Ohayia 7/25/2012 12:35:19 PM Class - What constitutes a good or bad CV, SV, CPI, or SPI? Explain your answer. RE: Good Damion Alexander or 7/26/2012 9:22:35 PM bad... Schedule variance provides metrics on individual performance that can be loaded into a tool like critical path analysis and can be used for prediction of future tasks. But if the task is not staffed per the dates needed, then Schedule Variance provides an answer that is accurate, but not particularly useful. Schedule Variance is not useful for parallel development efforts, so if there is any parallelism at all in the project, then the summation of schedule variances has no meaning. RE: Good Oral Bestman or bad... 7/25/2012 1:56:49 PM A good CV is when the cost is under or met budget, and bad CV is when project is go over budget which create variance that affect the CV total. On the other hand SV is good when project are ahead of schedule or meet schedule, if the project is delay or run schedule as plan, it increase the CV cost. RE: Good Jenna Pingitore or bad... 7/25/2012 2:56:11 PM I would absolutely agree with you, Oral. A good CV is definitely when the cost is under budget or has met budget and this is often easier said, than done. Everyone wants to end up under or on budget when a project has been completed, but there are often things that can get in the way. I watch a lot of HGTV (sorry if this is not a great example) and there is a show called Love It or List It and when the woman is doing the renovations, there is always something that comes up and causes an additional cost to the home owners, which brings down the amount that they can use on renovations. Along this line, when these costs come up, they are going against the CV and can bring it down in a bad way. RE: Good Timothy Mark Thurman or bad... 7/27/2012 2:19:16 PM exactly, and this is where the CPI comes in. The cost performance index is how to measure the health of the project. Criteria should be determined for the CPI so the project doesn't fly off course in regards to how much it costs and the PM can know when something is going awry when it comes to cost. This criteria should be determined in the planning stage and monitored regularly. RE: Good Jenna Pingitore or bad... 7/28/2012 7:12:26 PM It absolutely does need to be monitored from the beginning (planning) stages so that unexpected things do not throw the budget off course. If you think of the saying "prepare for the unexpected" you will often find yourself in a better situation by following that. If you have a budget of $100,000 to complete renovations (example) and you know that there are certain things that you want to be able to accomplish, it may be a good idea to keep $10,000 (give or take) as a contingency budget so that as the project gets rolling, if you come across any issues, you have a budget already set aside to work with and aren't trying to scrounge for additional funding. If you get to the end of the project and have that $10,000 remaining, you can do one of two things: 1) you can use this to show that the project is below budget or 2) you can use this $10,000 for additional improvements that you may not have budgeted for initially. RE: Good Instructor Ohayia or bad... 7/29/2012 6:49:53 AM Excellent input folks - CPI is and SPI are great measure of how efficiently are resources being applied to as assigned task! For example, if the outcome of your SPI is 90%, this means that the resource is operating at a 90% efficiency. The question becomes, why, because a a 90% efficiency the project would end up behind schedule! RE: Good Melinda Larsh or bad... 7/29/2012 6:43:04 PM I think a reason a project can get behind when the resources are running at 90% is things that are out of resources control such as weather delays if the work is outdoors. Another reason could be external delays such as government red tape or parts not being delivered on time. The resources of the project are just one component of it and there are many influences on a project. RE: Good Kyle Simmons or bad... 7/29/2012 10:18:55 PM Well I agree this could be a resource issue but it could also be out of the control of the PM to get the project done in time. Natural disasters could hit and you have no control. You could lose an entire data center for a day and then your project could be off target. I think that it is good to look at an index of how you are doing but in the end it is the question of Why that must be addressed in the AAR (After Action Review) RE: Good Venkat Yetrintala or bad... 7/25/2012 7:44:39 PM Cost Variation helps answer following questions: Why did one project cost more or less than planned? Were objectives met? Is a positive variance a cost saving or a failure to implement? RE: Good Ricardo Antezana or bad... 7/25/2012 8:34:42 PM Well, since the CV is equal to the BCWP (budget cost of work performed) ACWP (actual cost of work performed), a negative result would mean that the project is over budget. And SV is equal to the BCWP- BCWS (budget cost of work schedule), a negative result would mean that the project is behind schedule. Going to the CPI that is the equal to the BCWP/ACWP, a low ratio would mean that the project is not cost efficient, close to 1 efficient, close to 0 very inefficient. Now going to SPI that is equal to BCWP/BCWS, a low ratio would mean that the project is not time efficient, a ratio of 1 the project is on track, greater that 1 the project is very efficient. RE: Good Kyle Simmons or bad... 7/25/2012 11:40:20 PM SPI (Schedule Performance Index) is the measurement of the amount of work complete based on the goal of completion. SPI will take into account Planned Value and End Value and multiplying them together to get a number that will allow you to determine if the project is on or over schedule, on or over budget. A good SPI is going to be ~1 or >1 because this will indicate that the project is on or ahead of schedule. When you get a lower value then you are running over budget and are behind schedule. RE: Good Damion Alexander or bad... 7/27/2012 1:55:50 PM I agree with you Kyle because when the SPI is a negative number or less than 1, the project would be in bad shape and behind schedule. But when it is a positive number or greater than 1, then the project would be in good shape and ahead of schedule. So this is a way to determine whether you have a good or bad SPI. RE: Tyrone Labad 7/26/2012 6:19:35 AM Good or bad... Although you can easily calculate most all earned value metrics (i.e. PV, EV, AC, SV, CV, SPI, CPI, EAC, ETC, etc) you don’t necessarily need to track all these values , what is critical for most projects is to track the Schedule Variance (SV), Cost Variance (CV), Schedule Performance Index (SPI) and Cost Performance Index (CPI). These four values provide a reliable measurement of the project’s performance.For example if the project is on Schedule and is greater than zero, the clear understanding is the project is is earning more value than planned thus it’s ahead of schedule. If SV is less than zero, the project is earning less value than planned thus it’s behind schedule. RE: Good Robert Allen or bad... 7/28/2012 11:47:22 AM Tyrone, thanks for pointing that out. I agree that we don't have to track all things all the time. The way I see it is these formulae are a box of tools. Most of the time we use the same few tools to do our jobs (hammer, screwdriver :)). But sometime we reach in and pull out that special tool to solve a particular problem. The key is to ensure that we have all the metrics we need along the way so that if we do need to use the different tools, we can. Robert RE: Good Nazar Eljack or bad... 7/26/2012 10:56:52 AM Schedule Performance Index tells us about the efficiency of time utilized on the project. It is a measure of progress achieved compared to planned progress. Schedule Performance Index = (Earned Value)/(Planned Value) Schedule Performance Index informs us that how efficiently we are progressing with compared to planned progress. If SPI is greater than one, means more work has been completed than planned work. If SPI is less than one, means less work is completed than planned work. If SPI is equal to one, means work completed is equal to planned work. http://pmstudycircle.com/2012/05/schedule-performance-index-spi-and-costperformance-index-cpi/#axzz21kQ0yTwc RE: Good Instructor Ohayia or bad... 7/26/2012 2:05:41 PM Thanks Nazar! Class - is positive SV or SPI always a good thing? RE: Good Charlese Adams or bad... 7/27/2012 10:42:05 PM Professor, Having a positive SV and SPI can be considered a good thing because you are ahead of schedule and under budget. I can't really think of a negative aspect of having a positive SV or SPI. Could it be that the company may have overbid the project and although it would not affect them right now because the project has already started but could affect future projects if another company manages to bid under them. Chalese Adams RE: Good Kyle Simmons or bad... 7/28/2012 7:11:39 PM I think that a positive number as in 1.1 through 1.2 would be good but after that your sponsors may start to think that we have over allocated resources or that the project is not define correctly. Too much of a good thing can always be bad. RE: Good Ricardo Antezana or bad... 7/27/2012 7:06:59 PM Professor a positive SV would mean that the project is ahead schedule, and if it is too favorable that could mean that the project is not being performed with high quality or the efforts have been overestimated. Same with SPI, if the ratio is equal to 1 the project is on track and if it greater than 1 the project is very efficient and if it is too greater than 1 something could be going on that needs the project manger's attention. RE: Good Darren Coleman or bad... 7/27/2012 7:18:22 PM If your SV >0 and your SPI > 1.0, you are ahead of schedule and under budget. To me is a good place to be in. If your SV < 0 and your SPI < 1.0 you are behind in budget and schedule. This means you have to fix this now and get back on budget and see where you can make some time up. RE: Good Paul Lindeke or bad... 7/26/2012 6:03:28 PM I would have to say that a positive value could be good or bad since it could mean that unnecessary work is being done that is not planned which can cause money to be wasted. Of course it could also mean that work that needs to be done is getting done ahead of time without being planned and that could result in the project being done faster than expected. It all depends on the work that is being done and whether or not it is beneficial to the project. RE: Good Courtney Little or bad... 7/28/2012 10:18:52 AM Paul, I would tend to agree. Being under budget and ahead of schedule can definitely be a bad thing. I think the inital reaction is that it's great, but if you're doing this much faster and cheaper than you initially estimated, either you gave a bad estimate or you are missing something in the overall picture. You could be skipping steps or not covering all your bases. To have a successful project, it entails a lot of anticipation and contingency plans because in the real world, things don't always go as planned. Honestly, assuming that your initial estimates in your bid or whatever were well thought out and you were able to anticipate future roadblocks, etc. you should be pretty close to all values you initially stated. RE: Good Andrea Johnson or bad... 7/29/2012 10:30:45 PM I believe that a positive SV or SPI is good, for obtaining the very bottom line of completing on time and within budget. These indicators do not measure quality however. A high SV or SPI could also indicate that work may have been rushed or not up to standard. It may also mean that resources were overestimated and with that comes money being spent for those resources. RE: Good Kim Easter or bad... 7/26/2012 8:10:13 PM Variances will always exist, unless there is perfect execution of the Project Plan. Variances are not always a bad omen, or cause of concern, or an indicator of poor management. Significant variances are those variances that break predetermined thresholds, require management attention, and corrective action. Significant variance may mean the original plan was inappropriate, or the EVT was not appropriate, or the actuals (ACWP) were incorrect. Significant variances inform management that something needs to be examined, analyzed and proper corrective action instituted. http://guidebook.dcma.mil/79/evhelp/var.htm RE: Good Instructor Ohayia or bad... 7/29/2012 6:53:57 AM "Variances will always exist, unless there is perfect execution of the Project Plan." Great observation Kim! There no perfect plans - remember, our plans is as good as our estimates. The only way to get to perfection execution to to have exact data, but unfortunately we do not have the exact data until the end of the project. Schedule Variane Melinda Larsh 7/25/2012 12:42:58 PM Schedule variance is any deviation in what was originally noted for completion date vs. the actual completion date. For example, if you are building a house for your project and the framing is supposed to take you only four days for the framing, but maybe due to weather delays it takes eight. Well your schedule variance would be +4 days. Once you have a variance (especially if it is a delay vs. finishing early) you need to make adjustments in your schedule so you ensure you meet the time frame set by the stakeholder. RE: Schedule Shavonda Marks Variane 7/29/2012 6:36:27 PM I just wanted to add to your post. The formula for calculating schedule variance is EV (earned value) - PV (planned value) = SV (scheduled variance). Also, a positive variance means the project is ahead of schedule and negative variance means it is behind schedule. It is very important for the project management to manage the variance throughout the project. Actual Cost (AC) 7/25/2012 5:41:11 PM Paul Lindeke "The actual cost of a project represents the true total and final costs accrued during the process of completing all work during the pre-determined period of time allocated for all schedule activities as well as for all work breakdown structured components. Actual costs are primarily made up of a number of specific items including, but not limited to, cost in direct labor hours, direct costs alone, and also all costs including indirect costs." http://project-management-knowledge.com/definitions/a/actual-cost/ At the beginning of the project only an estimate of how much the project will cost is given because it is hard to determine the actual cost of the project. Only till the end of the project with the actual cost be known and then adjustments can be made later to the estimate so it will match the actual cost. CPI Courtney Little 7/25/2012 6:30:59 PM A CPI of 1 means the project is exactly on budget. Anything below 1 means the project is over budget and anything over 1 means the project is under budget. In this case, the closer to 1 you can be the better. You wouldn't want to be too much under or over because that means you mis-estimated to begin with. Obviously, too far below 1 and the stakeholders would not be very happy. RE: CPI Troy Brown 7/25/2012 9:01:36 PM To add to Courtney's thoughts I think a good CPI or SPI is anything that is within your contigency plan for the project. If your organization has a threshold of 10% +/- of 1 and you stay within that variance than I would consider that a good SPI or CPI. Because projects have so many changes that go on during the life cycle of the project that you need to have some variance below or below 1 to allow you as the PM to be effeicent and effective Project facilitator. If you don't have this contingency in place for the project, every time the project falls off track or misses the budget you will be creating an action plan to fix the issue that might plays it's self as the project moves on. RE: CPI Instructor Ohayia 7/26/2012 2:03:07 PM Thanks Courtney/Troy/Class! Troy says "If you don't have this contingency in place for the project, every time the project falls off track or misses the budget you will be creating an action plan to fix the issue that might plays it's self as the project moves on." In reality, contingency are used for manage unexpected deviation from a "planned task", it should not be used for any changes or new items. RE: CPI Kyle Simmons 7/28/2012 7:24:57 PM Just to be clear you are saying we would use congregant for unexpected issues arising, for example your project is to drill 500 feet into a mountain and when you hit 300 you hit some unforeseen rock density so it requires around the clock drilling. As opposed to once you hit 300 feet the sponsor tells you that you need to drill 650 on the same timeline? RE: CPI Elvis Niangoran 7/27/2012 10:40:44 PM I would agree with you professor, contingency will offset the project uncertainties, such as unexpected events that can make initial budgets inaccurate and meaningless. Standard Deviation Shavonda Marks 7/25/2012 9:54:31 PM The standard deviation is a measure of the degree of dispersion of the data from the mean value. A large standard deviation indicates that the data points are far from the mean and a small standard deviation indicates that they are clustered closely around the mean. For example, the sets {0, 5, 9, 14} and {5, 6, 8, 9} each have a mean of 7, but the second set has a much smaller standard deviation. Sometimes, the standard deviation is defined as the average distance between any score in a distribution and the mean of the distribution. http://www.wordiq.com/definition/Standard_deviation RE: Standard Melinda Larsh Deviation 7/28/2012 6:56:05 PM Great example! I often get confused by the standard deviation. I wonder when see it if the SD is good or not good and what it tells me about the data itself. I think that the standard deviation is a wide know term, but I don't think a lot of people understand the meaning. EV Emilia Crespo 7/25/2012 10:03:40 PM EV= PV+AC Earned value is sort of like x'tra money but not really. The actual cost is the actual cost and the planned value is an estimate of the cost based on a number of factors. Once both are determine there is going to be a gap which is the earned value, which is what may be left after the actual cost has been subtracted from the planned value. Example House for sale Plan on spending $200,000 Actual cost of house $120,000 Earned value which is what we saved $70,000 However the earned value should not be spent or perceived as earned money because it may come in handly for another project that the actual cost exceeds the planned value -Emilia Crespo RE: EV Kim Easter 7/28/2012 3:55:52 PM Modified:7/28/2012 3:57 PM The earned value that is remaining, $70,000, can be deposited in the project reserve or contingency reserve for potential unidentified risks that could materialize later in the project or saved for other projet endeavors. RE: EV Oral Bestman 7/29/2012 12:53:58 PM Setting aside reserver can definitely become useful, when unexpected challenges develop later on the project. Point of Total Charlese Adams Assumption 7/29/2012 11:34:15 PM The point of total assumption is the point in a contract where the subcontractor assumes responsibility for all additional costs. The formula is calculated as: PTA = (Ceiling Price - Target Price) / BSR (Buyer's Share Ratio) + Target Cost On the fixed price plus incentive fee contract (FPIF), the target cost, target price, ceiling price, and one or more share ratios are specified.