VANDERBILT COMMUNITY ASSOCIATION, INC. VANDERBILT COUNTRY CLUB BOARD OF DIRECTORS MEETING I. Call to Order: A meeting of the Vanderbilt Community Association, Inc. Board of Directors convened in the Multi-Purpose Room at 8250 Danbury Boulevard, Naples, FL, on Thursday, June 19, 2014 began at 5:00pm. Notice of this meeting was posted on the Vanderbilt Country Club website and in the Calendar of Events. II. Establish Quorum: Directors: Bob Teschke, President; Kent Friedman, Executive Vice President; Bev Gromek, Treasurer; Ron Khachadoorian, Secretary (via conference call) and Jerry Petrarca, Vice President; John Laliberte, General Manager; Jonathan Beers, Director of Finance; and Niki Dutton, Membership Director were in attendance. Approximately 12 resident members were present, as well as Jessica DiCarlo, Food & Beverage Service Manager. Noting that a quorum was present, Mr. Teschke called the meeting to order at 5:04pm. III. Review/Acceptance of Minutes: The May 15, 2014 Board Meeting were distributed prior to the meeting to all Board members for their review. Mr. Friedman motioned to accept the minutes as submitted. Dr. Petrarca seconded; all were in favor and the motion carried. IV. Treasurer’s May Financial Summary – Bev Gromek May was the month that we had planned to have the Clubhouse open and while the Terrace Café did take in $43k in food and beverage sales during the month, we had budgeted for $64k in sales with the Clubhouse open. We also had a loss of $26k in golf and cart fees as a result of suspending reciprocal play. Thus total income was $48k less than budgeted for the month, however total income YTD is $135k greater than budgeted. The cost of food was high as it usually is in May when the chef reduces inventory for the summer months. All of these transactions leave us with a time adjusted loss of $13k for the month and still maintaining a profit of $109k YTD. In reviewing the expenses, we find that cleaning, electricity, and payroll were significantly under budget due to the clubhouse not being open in May. Most of the other expense lines were near budget, and we had some adjustments to golf course expenses being made in anticipation of the course renovation in 2015. A review of our Balance Sheet on 5/31 shows that we had $3.2M in cash at the end of the month including $2M in asset replacement reserves, $173k in the FMP accounts, and $530k in resale and original capital combined. We will continue to draw on our loan for the major expenses of construction and furnishing through the end of the FMP project. Preliminary #2 1 7/8/2014 Food, pro shop and tennis inventories were being reduced as we head into the slow season. We continue to have 4 units which are in arrears on their fees, all have been properly liened and negotiations continue with owners and institutions. During May, 3 closings took place, and bringing the total number of sales to 33 in 2014. While we are all eagerly looking forward to the opening of the Clubhouse, it is comforting to have our year to date profit be in excess of $100k as we head into some unpredictable months. We hope that you will all continue to support the Terrace Café as we go through the transition to the new Clubhouse. V. General Manager’s Report – John Laliberte a) Old Business ~ Reports 1. 2014 “New” Capital & “Asset Replacement” Capital Projects – Updates: The 2014 Capital Project updates as highlighted in the following four (4) reports: (1) “2014 New Capital Improvements”; (2) “2014 Asset Replacement/Reserve Capital Expenditures”; (3) “2014 Emergency Reserve Capital Expenditures”; and, (4) “2014 Additional New Capital Improvements” (funded by Resale Capital Contribution Funds). There are no significant changes to the 2014 Capital Projects completion statuses from last month’s update, as the majority of this year’s Capital projects are summer-related. For the 2014 “New” Capital Projects, one project has been eliminated as a result of the golf course renovation approval for 2015 ~ (1) Drainage on Fairways @ $10,423.10 budgeted/zero spent. For the remaining three (3) board-approved New Capital projects, all have been completed Y-T-D, including: (1) Six (6) Greens Walk Mowers w/Trailers @ $27,507.00 budgeted/$27,507.00 actual ~ John Deere 220E gas powered, electric reel walk mowers; purchased through ShowTurf; as Stuart is utilizing the walk mowers Monday thru Friday on all 20 greens, and the triplex mowers on the weekends with less GCM crew scheduled; (2) Ultimix Chemical Pre-mix Station @ $3,826.56 budgeted/$3,610.00 actual ~ the Chemical Pre-mix Station is utilized for mixing chemicals, fertilizers and/or wetting agents into one batch, thereby promoting safer & shorter mixing time, as well as more efficient mixing of turf care chemicals, that can be done and re-loaded into the applicator’s spray tank (once it becomes empty and must return to the GCM chemical building) in a few minutes versus the normal 30-45 minutes required for chemical products that do not go into solution easily ~ thereby taking extra time; Preliminary #2 2 7/8/2014 this powerful, 100 gallon agitation tank, driven by a 110v electric motor, allows this efficient process to occur, and keeps the GCM crew ahead of the field of play in the morning; (3) Jonas Gift Card Module @ $3,392.00 budgeted/$3,100.00 actual ~ the software for the new Jonas Gift Card Program has been purchased and installed; Niki Dutton finalized the VCC Gift Card design (aka: “Cash Cards”) with Technology Training Associates, Inc. (a Jonas preferred system supplier) including: front/back layout with logo, wording, font, color, magnetic strip set up, and disclaimer verbiage. A total of 500 gift cards are included. A card swipe unit is attached to Niki’s PC, as this is how the cash cards will be issued. Both Niki and Corky have participated in the Jonas training on the proper use of the software. Promotion of the VCC Gift Card Program is on-going through Niki to our VCC membership. For the 2014 “Asset Replacement” Capital Projects, five projects have been eliminated as a result of the golf course renovation approval for 2015: (1) Green #15 Renovation @ $29,398.00 budgeted/zero spent; (2) Inboard/Outboard Greens Irrigation @ $178,000.00 budgeted/zero spent; (3) Widen Hole #13 Tee Box with Rip Rap @ $10,976.56 budgeted/zero spent; (4) Driving Range Island Renovation @ $42,526.00 budgeted/zero spent; and, (5) Raise Hole #2 Green Collar with Rip Rap @$6,699.20 budgeted/zero spent. Three (3) of the remaining board-approved ten (10) Asset Replacement Capital projects are currently in progress or completed, including: (1) Common Landscape Improvement (Phase 4) ~ Perimeter (Phase 2) @ $37,434.00 budgeted/$3,800.00 spent-to-date ~ as Grow, Inc. has performed Live Oak Tree trimming on the Gleneagle Way perimeter, as part of this project; the majority of this Phase 4 Project will focus on the Parkstone & Danbury perimeters, prior to and during the summer months; (2) Main Pool Speakers @ $3,562.68 budgeted/$3,262.68 actual ~ project completed, including the replacement of all wiring & the installation of eight (8) speakers & one (1) volume control around the main pool complex; (3) Main Entrance (Exit Side) Landscape @ $5,000.00 budgeted/$4,910.00 actual ~ project completed, with focus on the removal of all Fountain Grasses, which were replaced with Arbocola, Crotons & Black Magic. a) New Business ~ Board Action Required 1. New Handicap Parking Signs for the VCC Clubhouse Complex Parking Lot: John requested Board approval for the purchase and installation of eight (8) custom Handicap Signs for the Clubhouse complex parking lot, from Lykins Signtek ~ in the amount of $5,469.60. Although not part of the LRPC’s original presentation to the Board, it is felt that Preliminary #2 3 7/8/2014 these Handicap Signs are a necessary component of the project scope. This signage would match the Clubhouse complex “building & directional” signage that was approved by the VCA Board ~ in the amount of $27,504.33 ~ at last month’s May board meeting, specifically: (1) Lykins Signtek ~ one (1) Monument Sign – Vanderbilt Country Club (at the entrance to the Clubhouse parking lot) and ten (10) Stop Signs (for the Clubhouse parking lot); and, (2) John Deere Golf ~ one (1) Main Clubhouse Directional Sign with Six (6) Arrows and four (4) Building/Directional Signs ~ all within the Clubhouse complex. Again, it is important to point out that this LRPC request is only for the immediate Clubhouse complex area, not the entire VCC community (i.e. street signs, stop signs, speed signs, etc.). Staff recommendation this evening is to request VCA Board approval for the eight (8) custom Handicap Signs (minus the “$250 FINE” portion of the sign, which is optional and not desired by the LRPC) in the amount of $5,469.60 ~ to be considered as a “2014 Additional New Capital Improvement”, to be funded by Resale Capital Contribution Fund. Mr. Friedman made a motion to approve John’s recommendation. Dr. Petrarca seconded the motion. All were in favor and the motion passed unanimously. 2. Tennis Utility Cart ~ Emergency Replacement: John requested the VCA Board to formalize its approval of the emergency replacement of the Tennis Utility Cart as of June 17, 2014. The Club has purchased a “2010 – Reconditioned Club Car Precedent 48VoltIQ” from A-1 Golf Cart Express for a total of $4,459.55 ~ including: six new Trojan batteries T875 (8 volt batteries), folding windshield, aluminum dump box, and trailer hitch. This is an electric utility cart. Jay Valero, our GCM Equipment Manager, has inspected this cart on two occasions. The cart was delivered to VCC on Friday 6/20/2014. This is to be considered as a “2014 Emergency Asset Replacement Capital Expenditure” ~ to be funded by the Asset Replacement Reserve Fund. Mr. Friedman made a motion to approve the recommendation as presented. Mrs. Gromek seconded the motion and the Board unanimously passed the motion. b) New Business ~ Other 1. Vanderbilt Staff Recognitions: Letters of commendation to three of our Vanderbilt management staff: a. Jonathan Beers ~ for achieving the designation of “Certified Hospitality Accountant Executive” (CHAE) in May, 2014 ~ Preliminary #2 4 7/8/2014 through the Hospitality Financial and Technology Professionals (HFTP). Congratulations! b. Niki Dutton ~ for successfully completing the “Future Leaders Education Program – Core Competency #7 – Golf, Sports & Recreation Management” in May, 2014 ~ through the Club Managers Association of America (CMAA). Congratulations! c. Jessica DiCarlo ~ for successfully completing the “Future Leaders Education Program – Core Competency #7 – Golf, Sports & Recreation Management” in May, 2014 ~ through the Club Managers Association of America (CMAA). Congratulations! John personally congratulated Jonathan, Niki and Jessica for their individual professional achievements and commitment to furthering their education in the club industry. Well done! 2. Vanderbilt CC Receives Recognition from the Governor: A letter received this month, dated June 18, 2014, from Governor Rick Scott, recognizing Vanderbilt Country Club for being one of only 23 food service establishments in the entire State of Florida for having no safety or sanitation violations within the past year. Quite an accomplishment! My gratitude and “congratulations” to Chef Mitchell and his kitchen staff, along with our frontof-the –house Service Staff, headed by Joe Newell and Jessica DiCarlo. This is a team effort and commitment to excellence! c) Informational Reports Golf Revenue Report – May, 2014 Rounds of Golf Report – May, 2014 Golf Revenue Report – June 1-18, 2014 Rounds of Golf Report – June 1-18, 2014 Rover Vehicle – Monthly Mileage Report – May, 2014 VI. Old Business a) FMP Update, John Laliberte General Contractor Update: Construction progress is more evident around and inside of the Clubhouse, now that the roof is dried in and roof tiles near fully installed. Exterior work on the Clubhouse continues, as stucco work and painting nears final stages. Interior wise, subcontractors are working diligently while focusing on the unfinished areas of the Clubhouse, including: electrical, HVAC, insulation & drywall, painting, and extensive millwork. Craig Miles, BCBE Senior Estimator/Project Manager, reports that BCBE is completing its final punch list items for the following areas in Phase 2: Pro Shop, Cart Barn & Activities Center, and provides the following update for the Vanderbilt project: Clubhouse: Preliminary #2 5 7/8/2014 We urge to be aware of potential hazards around the Pro Shop entrances/exits until the Clubhouse is completed. We apologize for any inconveniences that this may cause, but this was quickest way for the members to enjoy the newly remodeled Pro Shop. The Clubhouse exterior needs the final grading by BCBE and then VCC can start with its irrigation, landscaping and sod. The brick pavers are being installed for outdoor tables. The retaining wall is complete, along with the large propane tank installation. The outdoor covered dining area ceiling work is wrapping up, and the new outdoor tile will be installed in a few weeks. Also, the outdoor fireplace and its stone surround are ready to be installed. The roll-down weather screens will soon be installed, as rough-in is complete. The administrative and foyer area of the Clubhouse is substantially complete aside from punch out type items. Also, the Waterford & Wedgewood rooms will be complete within the next two weeks. Our field management is finishing up the kitchen along with VCC staff ~ this includes startup & trouble shooting of all the equipment, electric and gas appliances. The millwork and painting in the Bar and Grille Room is ongoing. The new bar area floor tile will be installed beginning this week. The new acoustical ceilings will be installed shortly, and the new bar cabinets and countertops will be installed toward the end of the month. In the Vista Room, the drywall is concluding, as painting and the extensive millwork is on-going. We are installing the acoustical ceiling in the next few weeks. The HVAC and final electrical connections, along with the fixture installations, are in process, as we are looking to start up the A/C systems shortly and begin installing the new wood flooring in the Vista Room. We ask that you please take extreme caution in the parking lots, cart paths and sidewalks around these areas. We have a very active site and want to ensure everyone’s safety, both inside the project limits and outside. Please remember per company policy, we require all individuals, excluding BCBE employees, vendors and subcontractors, to sign it with VCC management before entering the project. Please help us keep this an accident free area by keeping out of the construction zone (designated by the construction fence). BCBE reports the following weekly progress for this current week ending June 21, 2014: Weekly Progress 6.21.14 This week Finish installing ceiling tile in main kitchen Framing and electric inspection for Vista Room Preliminary #2 6 7/8/2014 Subgrade and lime rock for brick pavers at outdoor patios & walkways Re-install LP gas tank and propane lines to building Install all MEP trim, HVAC trim, and Sprinkler trim Install stain grade trim at bar Finish installing all drywall in Vista Room Hook up all kitchen equipment ~ with Fishman, along with plumbers, electricians, gas installer Install granite counter tops in lobby restrooms Complete all exterior stucco on building Finish installing all “Hanson Paradise” roof tiles on Clubhouse building Look ahead Install trim and beams in private dining ~ The Vanderbilt Room Complete bar area trim & ceiling details Install ceiling beams and insulation in outdoor covered dining area Re-install LP gas tank and lines to building Install stone and trim detail around outdoor fireplace Install bar area tile flooring Punch out the main kitchen and appliances Install carpet in the Waterford & Wedgewood Rooms Continue A/C ductwork & electrical installation in Clubhouse toward completion Finish installing brick pavers for outdoor patios & walkways Finish installing grout in all foyer and hallway floor tile Complete cabinetry install in Admin reception desk area Complete final landscape plan for submission to civil engineer and county Preliminary #2 7 7/8/2014 Refurbish & resurface all Hufcor dividing wall doors in WA/WE Rooms and Vista Room Finish Bar, Grille Room & Vista Room millwork ~ and install bar walls, countertop, and back bar cabinetry/finish wood Conduct Admin Office wing punch out with OAC reps Architect’s Update: Dave Humphrey, our architect with Humphrey-Rosal Architects, summarizes the activities occurring during the last month for the Vanderbilt FMP Project, including punch list statuses for “Phase 1 & 2” and construction updates for the Clubhouse ~ “Phase 2”: Fitness Center: The punch list has been worked on throughout the month with only a couple of items remaining to close out. Activities Building: Punch list has been compiled by the OAC reps and BCBE is proceeding to complete the items. Pro Shop Building: Punch list has been compiled by the OAC reps and BCBE is proceeding to complete the items. Clubhouse Building: The cabinets in the administration area have been delivered and installation has begun. All other items in this area have been completed. The wood trim is being installed in the Private Dining area. The restrooms have the cabinetry and countertops installed ~ awaiting final plumbing connections. The entry doors have been finished and are awaiting hardware. The trim in the main entry lobby area has been completed and is in the process of being painted. The Wedgewood and Waterford Rooms have the ceiling grids, electrical fixtures, and HVAC grilles installed. Carpet is installed this week in the Wedgewood and Waterford Rooms. The existing Grille Room beams have been re-plastered and primed, ready for paint. The Bar ceiling trim has been completed and electrical, HVAC, sound, etc. have been installed. The perimeter blocking for the acoustical ceiling treatment has been installed in the Bar area. Preliminary #2 8 7/8/2014 All mechanical and electrical ceiling systems have been roughed in for final trim in the Vista Rooms. The existing Vista Room and expansion has the rough framing for the ceiling trim installed. The perimeter blocking for the acoustical ceiling treatment in the Vista Room has been installed. The fiberglass panels in the kitchen have been put in place. Kitchen equipment was delivered and installed over the past month. The Kitchen is being cleaned and will be ready to "turn over" to the Club for testing equipment. The roll down screens has been roughed in at the covered dining terrace. The ceiling at the Covered Dining Terrace is being lathed ~ for stucco to be installed in the ceiling between the beams. The lath is being screwed into the framing above, not stapled. The stacked block retaining wall is complete (less one area left unfinished to access sun deck) and has been backfilled. The patio sun deck and other terrace & walkways have been laid out, and lime rock installed, awaiting final paver installation. The underground for lighting at the rear patio terraces is installed. Shop drawings are being sent to the architect and reviewed as an ongoing process. Interior Design Team Update: The 29th Interior Design Team meeting was held this past month on May 22nd, as the I.D. Committee continues to review and finalize the remaining artwork and accessory selections for the Clubhouse. Members of the I.D. Team met on-site at the Clubhouse on June 12th to conduct a Clubhouse space walk-thru of these art selections for each room and interior area. The following update is provided by our interior designer, Lisa Miles-Briggs, with Club Design Group: Interior Design Update: 6.13.14 FITNESS CENTER New cyclist canvas art is being framed. Expected to be complete for pick up next week. The existing toilet roll holders in the FC ~ temporarily installed from the former Clubhouse ~ need to be changed out for new as they are stained and missing parts. PRO SHOP Existing bulletin board fabric to be refinished with black fabric paint. CLUBHOUSE & TERRACE Custom restroom mirrors ordered. Art reviewed & all pieces selected. Stone signage package designed and submitted to VCC for approval. Bar ceiling fabric reselected, approved & ordered by BCBE. Preliminary #2 9 7/8/2014 Window treatments will be measured & ordered when finish trim is complete. Reception “Vanderbilt” signage to be refinished by BCBE. CDG will make color selections. Door hardware selected and approved. Custom Lobby Furniture ordered. Hostess stand ordered. Outdoor Service stations ordered. Two “tile to carpet” Shluter transitions are missing from Gallery 120; BCBE notified. All flooring must be protected. Paper on the tile is tearing and the carpet is not covered. BCBE is correcting and closing off these areas to subcontractors. Reviewed paints on site with Tony (BCBE) & Todd (HRA). Area 141 outside the Vista Room & Bar to be painted the same as the Bar & Grille. Barrel ceiling ribs including their side profiles to be painted Brainstorm Bronze. Kitchen Design Team Update: With the installation of the ceiling tile and other miscellaneous work, the construction of the main kitchen is nearly complete, with a late June turnover expected by the General Contractor to (and acceptance by) VCC. This will occur once all FPL power, water, and propane are fully connected and activated. The carbonation system for the beer and soda lines was installed on May 22. The beer cooler pump location was framed and the pump installed. The roof penetration for the kitchen cooler/freezer cooling system was completed, thereby allowing final refrigeration installation. The minor kitchen equipment installation damage identified by Chef Mitchell and Fishman and Associates will be repaired by Fishman at their expense. An additional Dormont gas hose was ordered to service the existing salamander oven, since the previous connection arrangement would not work. The existing dish machine disposal required a new disposal control panel, which was ordered and installed to replace the prior panel which was corroded. A Combi Oven water shut-off valve was installed per code. The main line “Chef's table” POS (point of sale) and chit order printer line networking wiring required special attention and is now operable. On June 12, Balgas filled the 1,000 gallon underground propane tank ~ that will service the main kitchen and the outdoor covered dining fireplace. The next steps are a state inspection to update food service and beverage licenses and a Collier County health inspection ~ both of which will be conducted in the coming weeks. The bar equipment installation by Fishman is scheduled once the bar wall, countertop, and back bar/millwork construction is 100% complete by BCBE. All bar equipment is delivered and being stored on-site. FMP Project Financial Update: As of June 12th, the FMP Fund has received $3,908,269 of member assessments, $640,885 of capital funds, $25,799 of bank interest and $1,832,647 of loan funding, for a total cash in-flow of $6,407,600. Preliminary #2 10 7/8/2014 There has been $6,558,928 of recorded expense including borrowing costs of $19,232 and BCBE retainage of $274,271 ~ which will be held back until project completion. An FMP recap shows that 10% of these expenses are considered soft costs; including architect, civil engineering, kitchen design and permit fees; 25% Furniture, Fixtures and Equipment (FF&E); and 65% Construction costs. The current available fund balance is $122,943 before retainage. At this time essentially all of the buildings have been completed, with the exception of the Clubhouse -which will be the focus of activity over the next several months. The Terrace Café, Fitness Center, Activity / Cart Barn and Pro Shop had cumulative budgets of $2.6m and were completed at a cost of $2.74m, an overage of $135k or 5.2% primarily due to county mandated items. The Clubhouse is the final building to be completed. Dollar-wise, at this time the process is approximately 81% complete. Demolition has been completed, the building’s footprint has now been expanded and closed in, the offices and kitchen are close to completion and the interior architecture and finishes are materializing. The allocated budgets for the Clubhouse of $4.57m, campus re-roofing (including Pro Shop, Activities/Cart barn, Cabana and Clubhouse) of $169k and general costs of $122k, totaling $4.86m are currently forecasted to be completed for $4.65m, a savings of $208k or 4.3%. The original Project cost of $7.465m included a five percent contingency of $357,529 for all of the unexpected items that arise during a project of this complexity. This contingency ~ as of June 12, 2014 ~ has a current forecasted balance at completion of $100k after the inclusion of bank interest earnings; however, there are a number of expenses currently in negotiation or the “pending decision” stage that may affect this value. Once the values of those items are better solidified, they will be factored into the project forecast, which will reduce this stated forecasted ending value. Bottom line, the project is moving smoothly and on target schedule, and it is expected to be completed on or below budget! d) Golf Course Renovation Update – Irrigation Consultant, Jerry Petrarca: We are on schedule of the planning for the renovation. The Architect has been on the job for almost three months. The renovation committee has given all of the member input to the Architect. At a meeting held earlier today, the Architect shared rough version of hole changes. The renderings (which will be shared with the membership on the website) will be available in August. We have already hired the Architect, Project Manager and still must hire the General Contractor (October) and an Irrigation Contractor (October). The Architect will make a presentation to the membership, including all renderings in November. The Irrigation Consultant is responsible for designing the irrigation system for the golf course. He will in addition inspect the work of irrigation after the contractor installs it. He will also construct and program a GPS data system for the central Preliminary #2 11 7/8/2014 control system. We will be adding 250 or more sprinkler heads to the golf course. After interviewing 4 Irrigation Consultants, the greens committee has recommend hiring Mike Pignato of the Pignato Group as the Irrigation Consultant. He has designed irrigation on over 200 courses, including 16 in SWFL. He is currently working on Spring Run. Dr. Petrarca made a motion to approve Mike Pignato as the Irrigation Consultant. Mrs. Gromek seconded the motion. The Board was unanimously in favor and the motion passed. VII. Committee Reports a) Sponsorship Packages Recommendation, Grand Re-Opening Sub-Committee, Helen Roth & Lois Fawcett: The Grand Re-Opening Sub Committee which consists of some members of the Activities Committee and the Communications/PR Committee were charged with planning the Grand Re-Opening events for the Clubhouse. The festivities were planned for the last week in October, as this is when a majority of our members return to Vanderbilt. The Committee presented the Board and John Laliberte packets of information containing the following: Grand Re-Opening Celebration Events Outline Grand Re-Opening Celebration Sponsorship Packages & Benefits Grand Re-Opening Sub-Committee’s recommendations The Sub-Committee agreed the Grand Re-Opening events should be spectacular and, in order to achieve that goal, we would definitely need money. Since we aren’t aware of a budget nor do we want to charge the members for the expense, we came up with the idea of getting Sponsors! The Sub-Committee developed four Sponsorship Celebration packages along with a list of Benefits. The packages clearly define those costs and the benefits they would gain from contributing. Grand Re-Opening Committee: Helen Roth, Lois Fawcett, Camille Pandolfelli, Tim McCann (Chair), Nancy Fowler, Fred Marcell, Cathi Hughes and Niki Dutton (Staff Liaisons) The Grand Re-Opening Sub Committee recommended that the VCA Board of Directors approve seeking sponsorships and The Sponsorship Packages as proposed and also recommends that The Board and the Project Manager procure those sponsors for the Committee because they have first-hand experience, the negotiation expertise, and the salesmanship to deal with those vendors/contractors associated with VCC. The Board Preliminary #2 12 7/8/2014 and John unanimously approved the recommendations and thanked the Grand ReOpening Committee for “an incredible effort”. Mr. Teschke stated the Board is “fully in agreement” to proceed with the sponsorships as we strive to defray as much of the cost as possible, while recognizing there will be some costs that the members will bear. VIII. Upcoming Meetings & Important Dates: Board Meeting, Tuesday, July 17, 2014 at 5:00pm (Multi-Purpose Room). IX. Adjournment Mr. Friedman made a motion to adjourn the meeting at 6:10pm. Mrs. Gromek seconded the motion. All were in favor and the meeting was adjourned. Respectfully submitted, _________________________________ Niki Dutton Membership Director, Vanderbilt Country Club Preliminary #2 13 ______________________________ Ron Khachadoorian Secretary, VCA Board of Directors 7/8/2014