New Mexico Department of Public Safety Computer Aided Dispatch (CAD) / Records Management System (RMS) PROJECT MANAGEMENT PLAN (PMP) EXECUTIVE SPONSOR – SECRETARY GREGORY J. FOURATT BUSINESS OWNERS - PETE N KASSETAS, CHIEF DPS, KIMBERLEY CLARK, COMMUNICATIONS DIRECTOR PROJECT MANAGER – CESARIO ALVILLAR ORIGINAL PLAN DATE: FEBRUARY 1, 2012 REVISION DATE: APRIL 16, 2015 REVISION: 2.0 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM REVISION HISTORY................................................................................................................................................ IV 1.0 PROJECT OVERVIEW ......................................................................................................................................... 1 1.1 EXECUTIVE SUMMARY- RATIONALE FOR THE PROJECT ..................................................................................................1 1.2 FUNDING AND SOURCES .............................................................................................................................................1 1.3 CONSTRAINTS ..........................................................................................................................................................2 1.4 DEPENDENCIES.........................................................................................................................................................2 1.5 ASSUMPTIONS.....................................................................................................................................................2 1.6 INITIAL PROJECT RISKS IDENTIFIED..............................................................................................................................3 2.0 PROJECT AUTHORITY AND ORGANIZATIONAL STRUCTURE .............................................................................. 4 2.1 STAKEHOLDERS ........................................................................................................................................................4 2.2 PROJECT GOVERNANCE STRUCTURE .............................................................................................................................7 2.2.1 Describe the organizational structure – Org Chart .....................................................................................7 2.2.2 Describe the role and members of the project steering committee ............................................................7 2.2.3 Organizational Boundaries, interfaces and responsibilities ........................................................................9 2.3 EXECUTIVE REPORTING..............................................................................................................................................9 3.0 SCOPE ............................................................................................................................................................ 10 3.1 PROJECT OBJECTIVES ..............................................................................................................................................10 3.1.1 Business Objectives ...................................................................................................................................10 3.1.2 Technical Objectives ..................................................................................................................................10 3.2 PROJECT EXCLUSIONS .............................................................................................................................................10 3.3 CRITICAL SUCCESS FACTORS .....................................................................................................................................10 4.0 PROJECT DELIVERABLES AND METHODOLOGY ............................................................................................... 12 4.1 PROJECT MANAGEMENT LIFE CYCLE ..........................................................................................................................12 4.1.1 Project Management Deliverables ............................................................................................................12 4.1.2 Deliverable Approval Authority Designations ...........................................................................................13 4.1.3 Deliverable Acceptance Procedure ............................................................................................................14 4.2 PRODUCT LIFE CYCLE .........................................................................................................................................14 4.2.1 Technical Strategy .....................................................................................................................................14 4.2.2 Product and Product Development Deliverables .......................................................................................15 4.2.3 Deliverable Approval Authority Designations ...........................................................................................30 4.2.4 Deliverable Acceptance Procedure ............................................................................................................30 5.0 PROJECT WORK .............................................................................................................................................. 30 5.1 WORK BREAKDOWN STRUCTURE (WBS) ....................................................................................................................30 5.2 SCHEDULE ALLOCATION -PROJECT TIMELINE ................................................................................................................32 5.3 PROJECT BUDGET ...................................................................................................................................................34 5.4 PROJECT TEAM ......................................................................................................................................................35 5.4.1 Project Team Organizational Structure .....................................................................................................35 5.4.2 Project Team Roles and Responsibilities ...................................................................................................36 5.6 PROJECT LOGISTICS ...........................................................................................................................................40 5.6.1 Project Team Training ...............................................................................................................................40 6.0 PROJECT MANAGEMENT AND CONTROLS ...................................................................................................... 41 6.1 RISK AND ISSUE MANAGEMENT.................................................................................................................................41 6.1.1 Risk Management Strategy .......................................................................................................................41 6.1.2 Project Risk Identification ..........................................................................................................................41 6.1.3 Project Risk Mitigation Approach ..............................................................................................................41 REVISION: 1.0 DOIT-PMO-TEM-020 ii OF vi PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 6.1.4 Risk Reporting and Escalation Strategy.....................................................................................................41 6.1.5 Project Risk Tracking Approach .................................................................................................................42 6.1.6 ISSUE MANAGEMENT ................................................................................................................................44 6.2 INDEPENDENT VERIFICATION AND VALIDATION - IV&V .............................................................................................44 6.3 SCOPE MANAGEMENT PLAN ....................................................................................................................................44 6.4 PROJECT BUDGET MANAGEMENT..............................................................................................................................47 6.4.1 Budget Tracking ........................................................................................................................................47 6.5 COMMUNICATION PLAN ..........................................................................................................................................47 6.5.1 Communication Matrix .............................................................................................................................47 6.5.2 Status Meetings ........................................................................................................................................47 6.5.3 Project Status Reports ...............................................................................................................................47 6.6 PERFORMANCE MEASUREMENT (PROJECT METRICS) ......................................................................................48 6.6.1 Baselines....................................................................................................................................................48 6.7 QUALITY OBJECTIVES AND CONTROL ................................................................................................................49 6.7.1 quality Standards ......................................................................................................................................49 6.7.2 Project and Product Review AND ASSESSMENTS ......................................................................................50 6.7.3 Agency/Customer Satisfaction ..................................................................................................................50 6.7.4 PRODUCT DELIVERABLE ACCEPTANCE PROCESS .....................................................................................51 6.8 CONFIGURATION MANAGEMENT .....................................................................................................................51 6.8.1 Version Control ..........................................................................................................................................51 6.8.2 Project Repository (Project Library) ...........................................................................................................51 6.9 PROCUREMENT MANAGEMENT PLAN ..............................................................................................................51 7. 0 PROJECT CLOSE ............................................................................................................................................. 52 7.1 Administrative Close .....................................................................................................................................52 7.2 Contract Close ..............................................................................................................................................52 ATTACHMENTS .................................................................................................................................................... 52 REVISION: 1.0 DOIT-PMO-TEM-020 iii OF vi PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM REVISION HISTORY REVISION NUMBER DATE COMMENT 1.0 February 1, 2012 draft 2.0 April 15, 2015 Updated for Change Request, continued Planning release of funds REVISION: 1.0 DOIT-PMO-TEM-020 iv OF vi PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 1.0 PROJECT OVERVIEW 1.1 EXECUTIVE SUMMARY- RATIONALE FOR THE PROJECT The New Mexico Department of Public Safety proposes the replacement of the existing Computer Aided Dispatch (CAD) system. CAD is one of the core systems DPS provides to the State Police and other Law Enforcement Agencies (LEAs). CAD is the system used to dispatch 911 calls out to the officers, map the call location in the dispatch center, provide Automatic Vehicle Location (AVL) for officers in the field, and provide National Crime Information Center (NCIC) access within the application. CAD is essential in providing rapid response from LEAs to crime/incident scenes. The current CAD has been in place for over 10 years, and is at end of life (vendor support soon to be discontinued), and DPS is unable to take advantages of newer technology, such as the latest map generation methods. One of the primary missions of DPS is to support LEAs throughout the State of New Mexico in protecting their citizens. DPS fulfills this mission through a variety of means, one of which is to provide data, systems and networks that allow criminal justice agencies to access information in a timely fashion that is useful for decision making. The DPS CAD system is currently used by law enforcement agencies in Sierra, Valencia and Luna Counties. The cost to move these agencies to the new DPS CAD system will be included in our planning. DPS currently operates without an integrated RMS. Separate, non-enterprise record systems are utilized for different disciplines within DPS to create and store records. These disparate systems require an officer to utilize several applications to retrieve the necessary data to support their activities. DPS is decades behind most other law enforcement agencies in the country in the deployment of a comprehensive records management technology. Implementation of an integrated, effective RMS will assist DPS maintenance of data records through the entire life-cycle. This includes classifying, storing, securing, and destruction (or in some cases, archival preservation) of records which are key to DPS’s mission. This is necessary to improve the efficiency of processing information and people. An integrated RMS will provide Law Enforcement personnel onestop access to the agency’s data records. DPS currently operates without an integrated RMS. Implementation of an integrated RMS system will be a separate project. 1.2 FUNDING AND SOURCES SOURCE LAWS 2012, 2ND SESSION, CH 19, SEC 7, ITEM 019 Laws 2012, Chapter 227, Sec 7, Item 019 – Reauthorized Laws 2015, Chapter 101, Sect 7, Item 023 for CAD and RMS through FY2017. PAGE | 1 AMOUNT $300,000 $2,850,000 ASSOCIATED RESTRICTIONS EXPENDED PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM SOURCE AMOUNT Laws 2013, Chapter 227, Sec 7, Item 020 – Repurposed in Laws 2015 Chapter 101, sec7, Item 25 for CAD and RMS $450,000 Laws 2014, Chapter 63, Sec 7, Item 020 – Repurposed in Laws 2015 Chapter 101, sec7, Item 25 for CAD and RMS $550,000 ASSOCIATED RESTRICTIONS 1.3 CONSTRAINTS Constraints are factors that restrict the project by scope, resource, or schedule. NUMBER DESCRIPTION C-01 None at this time 1.4 DEPENDENCIES Mandatory dependencies are dependencies that are inherent to the work being done. D- Discretionary dependencies are dependencies defined by the project management team. This may also encompass particular approaches because a specific sequence of activities is preferred, but not mandatory in the project life cycle. E-External dependencies are dependencies that involve a relationship between project activities and non-project activities such as purchasing/procurement NUMBER DESCRIPTION TYPE M,D,E D-01 MAPS AND MAP DATA M D-02 DOT GIS DATA M D-03 NMROADS DATA M 1.5 ASSUMPTIONS NUMBER PAGE | 2 DESCRIPTION PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM NUMBER DESCRIPTION A-01 Funding will be available for Implementation A-02 Map data will be in final form prior to go live A-03 The system will utilize a GIS database as the basis for routing A-04 Map data refresh process in place for implementation 1.6 INITIAL PROJECT RISKS IDENTIFIED Stakeholders Description – Project will be at risk if all stakeholders are not fully engaged Probability Low Impact HIGH Mitigation Strategy Emphasize communication to all stakeholders and be sure they understand the benefits of a successful project. Hold regular project meetings to keep all parties informed of current status and accountable for their deliverables. Contingency Plan Escalate to sponsors DPS Resources Description – Availability of DPS resources when the project timeline requires. Probability Low Impact HIGH Mitigation Strategy DPS will plan for resources availability based on project schedule Contingency Plan Hire contractors Requirements Description – Requirements not being fully met. PAGE | 3 Probability - Low Impact - HIGH Mitigation Strategy - Create, maintain, and enforce Requirements Traceability Matrix (RTM). Have vendor create a test plan. Monitor vendor testing. Contingency Plan – Advise vendor of contract non-compliance. PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 2.0 PROJECT AUTHORITY AND ORGANIZATIONAL STRUCTURE 2.1 STAKEHOLDERS Name Stake in Project Organization Subscriber Agencies Title Phone email Subscriber Agencies Glen Condon SME DFA / LGD 911 GIS Specialist 505-827-4977 Glenn.Condon@state.nm. us Gar Clarke Central State GIS DOIT NM Geospatial and Broadband Program Manager 505-827-1663 Gar.Clarke@state.doit.us Diana Dejarnette Administrative DPS ASD Deputy Director 505-827-9035 Diana.Dejarnette@state. dps.us Elizabeth (Karana) Haring Contracts DPS Purchasing AgentAdvanced 505-827-9626 mailto:Elizabeth.Haring@ state.nm.us Elizabeth Trickey General Counsel DPS Deputy General Counsel Fran Dunaway Procurement DPS Chief Procurement Officer 808-827-9018 FrancesA.Dunaway@stat e.nm.us Gregory J. Fouratt Executive sponsor DPS Cabinet Secretary 505-827-3370 Greg.Fouratt@state.nm.us Regina Chacon DPS DPS Bureau Chief – LERB 505-827-9297 regina.chacon@state.nm .us Kimberly Clark Business Owner DPS Communication s Bureau DPS Emergency Communications Director 505-841-9256 Kimberly.Clark@state.nm .us Kristian Reveles SME DPS Communication s Bureau Communications Supervisor 575-622-7200 KristianV.Reveles@state. nm.us Perry McPhee SME DPS Communication s Bureau Communications Specialist 505-841-9256 PerriM.McPhee@state.n m.us Cesario Alvillar Project Manager DPS IT Project Manager 505-827-9538 Cesario.alvillar@state.nm .us Darrell Graham DPS Resources, Technical Lead DPS IT ITD/TSB Bureau Chief 505-827-3460 Darrell.Graham@state.dp s.us PAGE | 4 Elizabeth.Trickey+E3:J39 @state.nm.us PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Marco Silva CAD Administrator DPS IT IT Systems Manager 3 575-382-2565 mailto:Marco.Silva@state .nm.us Ron Burton Sponsor - DPS Resources DPS IT CIO 505-827-3353 Ronald.Burton@state.dps .us Tim Struck DPS DPS IT IT Technical Support Supervisor 505-827-9292 Tim.Struck@state.nm.us David Abeita SME DPS MTPD Lieutenant 505-660-6276 Mario Montaño SME DPS MTPD Officer 505-425-6771 Sector Captain MTPD DPS MTPD Sector Captain Adrian Armijo DPS SP DPS NMSP Deputy Chief District Captain NMSP DPS NMSP District Captain District Captain NMSP Training DPS NMSP District Captain Sean Healy SME DPS NMSP Miguel Aguilar SME Pete N Kassetas david.abeita@state.nm.u s Mario.Montano@state.n m.us 505-827-3321 adrian.armijo@state.nm. us Officer 505-841-9241 sean.healy@state.nm.us DPS SP Major 505-827-9068 Sponsor DPS SP Chief 505-476-2467 Michael Inglis EDAC UNM Earth Data Analysis Center Associate Director 505-2773622x235 minglis@edac.unm.edu Zone Commanders IB IB Zone Commanders Jack Yates NMDOT Data Management (ARNOLD) NMDOT Staff Manager 505-216-8059 Jack.Yates@state.nm.us Jeff Vigil NMDOT NMDOT Civil Engineer - A 505-827-5457 Jeff.Vigil@state.nm.us John Di Ruggiero nmroads.com NMDOT ATIS/IT Project Manager 505-490-2561 John.DiRuggiero@state.n m.us Joseph Valdez Bridge NMDOT Data Analyst 505-827-5540 joseph.valdez@state.nm. us Mel Herrera NMDOT NMDOT IT/Planning GIS Section 505-827-5453 Mel.Herrera@state.nm.u s Tamara Haas NMDOT NMDOT Executive Manager 505-795-2126 TamaraP.Haas@state.nm. us PAGE | 5 miguel.aguilar@state.nm. us pete.kassetas@state.nm. us PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Director Shirley V. Baros PAGE | 6 SID SID EDAC UNM UNM GIS Clearing House Earth Data Analysis Center runs the Resource Geographic Information System (RGIS), New Mexico’s Geodata Clearinghouse. Mgr,Geographic Info Svcs: Earth Data Analysis Center 505-277-3622 o RGIS: http://rgis.unm. edu/ sbaros@edac.unm.edu PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 2.2 PROJECT GOVERNANCE STRUCTURE 2.2.1 DESCRIBE THE ORGANIZATIONAL STRUCTURE – ORG CHART CAD Project Governance Mr. Gregory J. Fouratt Cabinet Secretary Department of Public Safety Executive Sponsors Pete Kassetas Chief Department of Public Safety State Police Scott Weaver Deputy Secretary Department of Public Safety Business Owners Ron Burton CIO Department of Public Safety IT Adrian Armijo Deputy Chief Department of Public Safety State Police Project Management Cesario Alvillar ITD Project Management Bureau Chief Project Manager Department of Public Safety IT Darrell Graham ITD-TSB Bureau Chief Technical Lead Department of Public Safety IT Kimberly Clark Department of Public Safety Communications Director Operational Support 4/14/2015 2.2.2 DESCRIBE THE ROLE AND MEMBERS OF THE PROJECT STEERING COMMITTEE NAME GROUP ROLE Executive Sponsor Gregory J. Fouratt Scott Weaver PAGE | 7 DPS DPS Steering Committee Member Deputy Secretary RESPONSIBILITY Review presented documentation Balance larger picture versus details of project Review project funding and expenditures Champion the project Communicate with the Legislature Review presented documentation Balance larger picture versus details of project Review project funding and expenditures PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Pete Kassetas DPS Chief Ron Burton DPS IT Steering Committee Member Business Owner Kimberley Clark MTPD Steering Committee Member SME DC Adrian Armijo DPS SP Steering Committee Member Project Manager Cesario Alvillar PAGE | 8 DPS Steering Committee Member Champion the project Communicate with the Legislature Review presented documentation Balance larger picture versus details of project Review project funding and expenditures Champion the project Communicate with the Legislature Attend and participate in meetings Review and accept deliverables Review presented documentation Balance larger picture versus details of project Review project funding and expenditures Champion the project Attend and participate in meetings Review and accept deliverables Review presented documentation Balance larger picture versus details of project Review project funding and expenditures Champion the project Attend and participate in meetings, review all documents in the capacity of a technical representative for his/her respective agency Participate in the planning process Provide business process guidance Review and accept deliverables Review presented documentation Balance larger picture versus details of project Accomplish and provide deliverables Assist or delegate system testing activities as required Attend executive requirements reviews and resolve requirements problems. Represent specific area(s) (e.g., technical, clinical, process, etc.) for the overall project as assigned Report progress, issues, etc. Recommend go/no based on testing results Champion the project Contribute to lessons learned Appoint Committee and Team members Facilitate meetings Conduct planning sessions Attend requirements reviews and resolve requirements problems Provide management review for changes to project plan, contract or deliverables Vendor and contract management Conduct risk assessment Maintain risk/issues/action log PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Develop plans with project team for risk, change and quality Develop management plan and project plan Review project funding and expenditures Report on project status Assign tasks Track schedules Recommend go/no go based on testing results Manage expectations Facilitate lessons learned Contribute to lessons learned Close-out action items Provide leadership for a coordinated project effort Champion the project Provide Information Technology guidance Attend and participate in meetings Review and accept deliverables Review presented documentation Balance larger picture versus details of project Champion the project Contribute to lessons learned Technical Lead Darrell Graham DPS Steering Committee Member 2.2.3 ORGANIZATIONAL BOUNDARIES, INTERFACES AND RESPONSIBILITIES A Contract will be entered into between DPS and the Vendor defining the project agreements made and the services being provided. There are two Project Managers (PM) – one for DPS IT and one from the Vendor. The PM from DPS IT works with the PM from the Vendor for overall coordination. Each will meet internally to define needs, plan and coordination of project execution. On a predefined schedule, PMs and project teams from both DPS and the vendor will meet to communicate and resolve needs regarding requirements, design, implementation, testing, expectations, timing, budget and issues as they arise. 2.3 EXECUTIVE REPORTING Current status of this project will be reported to DPS executive management on a monthly basis or as requested. Weekly status report to project team and a project status report on a monthly basis to DoIT. A project web site will be created with project status and information accessible to governance and project teams. Signatures from the Executive Sponsors are required for some project documents. PAGE | 9 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 3.0 SCOPE 3.1 PROJECT OBJECTIVES 3.1.1 BUSINESS OBJECTIVES NUMBER DESCRIPTION BO-01 Efficiently receive and document call response information to expedite the dispatch of calls to officers. BO-02 BO-03 BO-04 BO-05 Map call location in the dispatch center, facilitating effective routing of units to calls for service, providing rapid response from LEAs to crime/incident scenes. Providing routing direction to responding officers. Improving officer safety by tracking unit location using Automatic Vehicle Location (AVL) for officers in the field and providing a secondary means of communication and access to National Crime Information Center (NCIC) access within the application. Gathering call response and officer initiated event information for data collection and intelligence gathering purposes. Improved reporting of crime data and performance statistics for state and federal grant purposes, operational assessment and unit deployment. 3.1.2 TECHNICAL OBJECTIVES NUMBER TO-01 TO-02 TO-03 TO-04 TO-05 TO-06 DESCRIPTION Replace outdated Computer Aided Dispatch System nearing obsolescence. This system is fundamental to DPS Operations. Improve mapping capabilities and enhance ability to capture incident data based on GIS information. Implement new technologies not available in current system. Leverage existing secondary technologies incompatible with current system. Enhanced system stability. Improved interface capabilities. 3.2 PROJECT EXCLUSIONS N/A 3.3 CRITICAL SUCCESS FACTORS PAGE | 10 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM NUMBER DESCRIPTION QM-01 Formal testing will determine whether the implementation of targeted requirements have been successful or not. QM-02 Requirements - Team and Stakeholder review and signed Accepted QM-03 QM-04 QM-05 QM-06 QM-07 PAGE | 11 Design - Technical Lead review Requirements Traceability to design and signed Accepted Test Plan - Formal testing will determine whether the implementation of targeted requirements have been successful or not.- Business owner, and Stakeholders review Requirements Traceability to test results and signed Accepted Production version - Technical Lead review of configuration and signed Accepted Schedule - Milestone dates, status reports Accepted Budget - Budget reports, status Accepted PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 4.0 PROJECT DELIVERABLES AND METHODOLOGY 4.1 PROJECT MANAGEMENT LIFE CYCLE 4.1.1 PROJECT MANAGEMENT DELIVERABLES Phase Summary of Phase Key Deliverables Initiation This phase defines overall parameters of the project and established the appropriate project management and quality environment required to complete the project. Project Charter, Initial Risk Assessment, High level schedule, Approval for next phase Planning This phase defines the exact parameters of the project and ensures all the pre-requisites for execution and control are in place. RFP, signed vendor contract, Project Management Plan, Team members identified, Stakeholder list, Functional Requirements, High level WBS, High level Schedule, Budget and Communication Plans, Roles and Responsibilities, Status reports, approval for next phase Implementation The phase configures and deploys the system. Certification Form, updated Project Management Plan, Project Schedule, Configuration Documentation, Testing Documentation, Training Documentation, Updated Budget, Risk/Issue Management Log, Status Report, Acceptance Closeout The phase accesses the project and derives any lessons learned and best practices. Post Implementation Review and Report, Administrative Close-Out 4.1.1.1 Project Charter Description – The initial project deliverable plan will contain the Project Charter. This deliverable may be revised during planning PAGE | 12 Deliverable Acceptance Criteria – Sign-off by Project Sponsor or Project Director Standards for Content and Format – Use of DoIT Project Charter template PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM phase. Quality Review – Project team members review 4.1.1.2 Project Management Plan Description – The Project Management Plan will be the guide used throughout the Project. This plan will contain the following plans: Scope Management, Schedule Management, Budget, Risk Management, Communications, Change Management, Lessons Learned and Roles/Responsibilities of team members. This plan is an evolving document as new information will be added and existing information will be revised during initiation and planning phase. Deliverable Acceptance Criteria – Approval by Project Team and Steering Committee Sign-off by Project Sponsor. DoIT Standards for Content and Format – Use of DoIT Project Management Plan template Quality Review – Project team members review for consensus Final review by Steering Committee and Sponsor 4.1.2 DELIVERABLE APPROVAL AUTHORITY DESIGNATIONS DELIVERABLE NUMBER DELIVERABLE APPROVERS (WHO CAN APPROVE) PRJ-DEL-001 Project Charter Governance Team, DoIT PRJ-DEL-002 Project Management Plan (PMP) Governance Team, DoIT PRJ-DEL-003 Kickoff Meeting Notes Project Manager, Business Owner PRJ-DEL-004 Vendor Project Plan Project Manager, Project Team PRJ-DEL-005 Vendor Requirements Analysis Document Project Manager, Project Team PRJ-DEL-006 Phase Launch Project Manager, Project Team PRJ-DEL-007 Phase Completion Project Manager, Project Team PRJ-DEL-008 System Completion Project Manager, PAGE | 13 DATE APPROVED PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM DELIVERABLE NUMBER DELIVERABLE APPROVERS (WHO CAN APPROVE) DATE APPROVED Governance Team 4.1.3 DELIVERABLE ACCEPTANCE PROCEDURE The Project Manager, Project Team and the Project Sponsors will review and accept the project documents. 4.2 PRODUCT LIFE CYCLE Phase Summary of Phase Key Deliverables I Milestones 1-N Requirements Analysis Document , installed system, user documentation, training, phased launch, bug fixes, acceptance testing II Milestones 1-N System modifications, Testing, Training, Phased Launch, Bug fixes and modifications III Maintenance Vendor system maintenance and support 4.2.1 TECHNICAL STRATEGY TBD PAGE | 14 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 4.2.2 PRODUCT AND PRODUCT DEVELOPMENT DELIVERABLES To be determined through vendor contract negotiations. The following is a sample. Deliverable One: Kickoff Meeting Deliverable Name Due Date Compensation Kickoff Meeting XX Calendar Days After Contract Execution Not to exceed $$$$ Task Item Kickoff meeting Acceptance criteria PAGE | 15 Sub Tasks Description Sub 1 The Contractor and the Procuring Agency will hold a kickoff meeting. The subject of the meeting will be to discuss an overview of the project, voice any concerns, seek input from all parties, discuss the Project Plans and identify Procuring Agency data elements and data sources. The Contractor will work with the Procuring Agency project manager to produce an agenda for the meeting and the Contractor will take notes of the meeting and deliver a summary of the meeting. Sub 2 The Contractor will take notes at the kickoff meeting and share the notes with the Procuring Agency project manager. Sub 3 The Procuring Agency will review and approve the kickoff meeting notes. If the Agency notes any corrections or additions to the notes, the Contractor will add said note or corrections Deliverable 1 will be considered complete when the Procuring Agency accepts the kickoff meeting notes. PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Deliverable 2: Project Plan Deliverable Name Due Date Compensation Project Plan XX Days After Contract Execution Not to exceed $$ including Gross Receipts Tax with 100% Retainage per Article 3, Paragraph D. Task Item Sub Tasks Description Project Plan Sub 1 The Contractor will Sub 2 The Procuring Agency will Sub 3 The Contractor will prepare the Project Plan. The Project Plan is the single comprehensive plan for the project and is managed by the Contractor’s documentation manager. Changes to any portions, including the Contractor’s schedule, must be approved via the change control process. The Project Plan also includes all components identified in the acceptance criteria below and the project management content referenced in the contract. Sub 4 The Procuring Agency will review the Project Plan. The Contractor will update the Project Plan with all changes and additions provide by the Procuring Agency and resubmit the Project Plan. Sub 5 The Contractor will provide weekly status reports including but not limited to status of activities, issues, risks, dependencies and proposed resolutions Sub 6 Deliverables will be reviewed and Accepted by the Procuring Agency Acceptance criteria PAGE | 16 Deliverable 2 will be considered complete when the Procuring Agency accepts the Project Plan. PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Deliverable 3: Requirements Analysis Document Deliverable Name Requirements Analysis Document Task Item Sub Tasks Requirements Sub 1 Analysis Document Due Date Compensation Not to exceed $$ including Gross XX Days After Contract Receipts Tax with 100% Retainage Execution per Article 3, Paragraph D. Description The Contractor will create the Requirements Analysis Document. This document will have the following components: Flow diagram for the system– provides a schematic and narrative work flow description for each major system business process including a description of business rules and user actions impacting the work flow. Each work flow description provides reference to the applicable specific requirements in the RFP that are satisfied by the work flow processes. Functional design specification provides a detailed description of how the system will function and will provide detail of the user interface. This document will describe how the user interacts with each screen and will provide guidance on the layout of the screens. The emphasis is on functionality of the screens. Final details of the screens including color and branding will be developed during prototyping and implementation. The Prototype will be used to aid the development of this document. PAGE | 17 Sub 2 The Procuring Agency will review the Requirements Analysis Document. The Procuring Agency will note and changes or additions which the Contractor will add to the document. Sub 3 The Contractor will revise the Requirements Analysis Document based on input from the Procuring Agency and resubmit the document. Sub 4 The Procuring Agency will review and approve the Requirements Analysis Document. Sub 5 The Contractor will provide weekly status reports including but not limited to status of activities, issues, risks, dependencies and proposed resolutions Sub 6 Deliverables will be reviewed and Accepted by the Procuring Agency PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Acceptance criteria PAGE | 18 Deliverable 4 will be considered complete when the Procuring Agency accepts the Requirements Analysis Document. PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Deliverable 4: Phase X Launch Deliverable Name Phase X Launch Task Item Sub Tasks Phase Launch Sub 1 Acceptance criteria PAGE | 19 Due Date Compensation Not to exceed $$ including Gross XX Days After Contract Receipts Tax with 100% Retainage Execution per Article 3, Paragraph D. Description The Contractor will implement all Phase I functionality as defined in the RFP, selected by the Procuring Agency, and refined in the Requirements Analysis Document. Sub 2 The Contractor will create test scripts for all Phase I functionality and perform testing on all Phase I functionality using these test scripts. The Contractor will correct errors when identified and retest. Sub 3 The Contractor will re-import updated company and permit data. This is the data that will be used for the Phase I launch and will reflect all new accounts and permits since the initial import. This import will have any corrections identified in the testing of the initial data. Sub 4 The Contractor will Sub 5 The Contractor will create user documentation for all Phase I functionality. The Contractor will implement online help for all Phase I functionality. Sub 6 The Contractor will perform Phase I training for all Procuring Agency personnel. Training will be performed XX Sub 7 The Contractor and the Procuring Agency will launch the Phase I functionality on the production environment. Sub 8 The Contractor will provide weekly status reports including but not limited to status of activities, issues, risks, dependencies and proposed resolutions Sub 9 Deliverables will be reviewed and Accepted by the Procuring Agency Deliverable 5 will be considered complete when the Contractor successfully launches Phase I functionality. PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Deliverable 5: Phase I Completion Deliverable Name Phase Completion Task Item Phase Completion PAGE | 20 Sub Tasks Due Date Compensation All Retainage for Deliverable #1 through Deliverable #X shall be paid XX Days After Contract upon Acceptance of this Deliverable, Execution not to exceed $$ including Gross Receipts Tax Description Sub 1 The Procuring Agency will perform a phased rollout of Phase I functionality at locations and with users of its choosing. Sub 2 The Contractor will correct errors and implement user-specified modifications in the system. All fixes and modifications will be developed on the development environment, tested on the test environment, and if Accepted by the Procuring Agency, implemented in the production environment using a schedule of the Procurement Agency’s choosing. Sub 3 The Contractor will create a complete suite of Phase I acceptance test scripts that fully test Phase I functionality. Each item in the test scripts will refer to a project requirement and will have a description of how to perform the test, expected correct results, and possible failure methods to look for. The Procuring Agency will be free to add or change tests in its acceptance scripts. The Contractor will insure that the system passes all tests on all Phase I acceptance test scripts before declaring the system ready for the Procuring Agency’s acceptance testing. Sub 4 The Procuring Agency will perform acceptance testing. Sub 5 The Procuring Agency and the Contractor will perform all Phase I close out tasks and complete all Phase I closeout documentation. Sub 6 The Contractor will provide weekly status reports including but not limited to status of activities, issues, risks, dependencies and proposed resolutions Sub 7 Deliverables will be reviewed and Accepted by the Procuring Agency PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Acceptance criteria PAGE | 21 Deliverable 6 will be considered complete with the Phase I closeout. PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Deliverable 6: Phase X Launch Deliverable Name Phase X Launch Task Item Phase X Launch Acceptance criteria PAGE | 22 Sub Tasks Due Date Compensation Not to exceed $$ including Gross XX Days After Contract Receipts Tax with 100% Retainage Execution per Article 3, Paragraph D. Description Sub 1 The Contractor will implement all Phase II functionality as defined in the RFP, selected by the Procuring Agency, and refined in the Requirements Analysis Document. Sub 2 The Contractor will create test scripts for all Phase II functionality and perform testing on all Phase II functionality using these test scripts. The Contractor will correct errors when identified and retest. Sub 3 The Contractor will create user documentation for all Phase II functionality. The Contractor will implement online help for all Phase II functionality. Sub 4 The Contractor will perform Phase II training for all Procuring Agency personnel. Training will be performed in accordance with the training plan in the Project Plan. Sub 5 The Contractor and the Procuring Agency will launch the Phase II functionality on the production environment. Sub 6 The Contractor will provide weekly status reports including but not limited to status of activities, issues, risks, dependencies and proposed resolutions Sub 7 Deliverables will be reviewed and Accepted by the Procuring Agency Deliverable 7 will be considered complete when the Contractor successfully launches Phase II functionality. PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Deliverable 7: Phase X Completion Deliverable Name Phase X Completion Task Item Phase X Completion Sub Tasks Due Date Compensation All Retainage for Deliverable #X XX Days After Contract shall be paid upon Acceptance of this Execution Deliverable, not to exceed $$ including Gross Receipts Tax. Description Sub 1 The Procuring Agency will perform a phased rollout of Phase II functionality at locations and with users of its choosing. Sub 2 The Contractor will correct errors and implement user-specified modifications in the system. All fixes and modifications will be developed on the development environment, tested on the test environment, and if Accepted by the Procuring Agency, implemented in the production environment using a schedule of the Procuring Agency’s choosing. Sub 3 The Contractor will create a complete suite of Phase II acceptance test scripts that fully test Phase II functionality. Each item in the test scripts will refer to a project requirement and will have a description of how to perform the test, expected correct results, and possible failure methods to look for. The Procuring Agency will be free to add or change tests in its acceptance scripts. The Contractor will insure that the system passes all tests on all Phase II acceptance test scripts before declaring the system ready for the Procuring Agency’s acceptance testing. Sub 4 The Contractor will complete all system documentation and deliver to the Procuring Agency. Sub 5 The Procuring Agency will perform, but not limited to, performance and user acceptance testing. PAGE | 23 Sub 6 The Procuring Agency and the Contractor will perform all Phase II close out tasks and complete all Phase II closeout documentation. Sub 7 The Contractor will provide weekly status reports including but not limited to status of activities, issues, risks, dependencies and proposed resolutions PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Sub 8 Acceptance criteria PAGE | 24 Deliverables will be reviewed and Accepted by the Procuring Agency Deliverable 8 will be considered complete with the Phase II closeout. PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Deliverable 8: Support Maintenance Deliverable Name Due Date Support, Maintenance Year 1 Support and Maintenance Begins upon Acceptance of Deliverable #X and Ends 12 Months Later. Task Item Problem Support Sub Tasks Compensation Not to exceed $$ including Gross Receipts Tax. Description Sub 1 The Contractor shall make technical support personnel available by phone and email on the following schedule: Monday through Friday, 8:00A.M. To 5:00P.M., excluding state holidays. Sub 2 The Contractor will log requests and provide to the Procuring Agency technical support services for the Software based on the priority levels and problem resolution processes described in the Performance Measures, above. Sub 3 The Contractor will update documentation (Systems Administration Guide, User Guide, and Product Manual) to reflect changes made to the system as a result of problem resolution. Sub 4 The Contractor will respond to technical and functional questions about the CAD system. Such requests will be assigned a default Priority of Priority 3 unless the Procuring Agency requests a higher priority be assigned to the request. Monthly Report Sub 1 The Contractor shall provide or make available online a monthly report on the activity and status of all logged requests received from the Procuring Agency. Activities Tracking Sub 1 Contractor shall maintain a log of requests in a Procuring Agency approved tracking system with a unique number assigned to each Procuring Agency request. The unique number shall be provided by the contractor to Procuring Agency for reference and communication. Sub 2 The Procuring Agency will assign one of four levels of priority to each request: Priority 1 is the most severe program error and represents a situation where mission critical features and functions of the CAD System are unavailable and no practical alternate mode of operation is available. PAGE | 25 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM PAGE | 26 Priority 1 problems will be corrected or a solution will be provided by Contractor for corrective action within two (2) hours. Priority 2 indicates a problem in which certain features and functionality are not available and no practical alternate mode of operation is available. Priority 2 problems will be corrected or a plan will be provided by the Contractor for corrective action within one (1) Business Day. Priority 3 is the normal “next-in-line” problem priority assignment. At this level, requests are worked on in the order in which they are received. Priority 3 problems will be corrected or a plan will be provided by Contractor for corrective action within ten (10) Business Days. Priority 4 is the Release assignment. At this level, requests are worked on as deemed appropriate by Procuring Agency. Priority 4 issues will be incorporated into specific releases, documented in an Application Deployment Package, which will be scheduled for delivery at the discretion of the Procuring Agency after time and cost estimates are provided by the Contractor and approved by the Agency, if applicable. As such, priority 4 issues will be due at the time the specific Release is delivered. PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Deliverable 9: No Cost Warranty Period Deliverable Name Due Date No Cost Warranty Period Begins upon Acceptance of Deliverable #X and Ends 12 Months Later. Task Item Problem Support Sub Tasks Compensation No Compensation. Description Sub 1 The Contractor shall make technical support personnel available by phone and email on the following schedule: Monday through Friday, 8:00A.M. To 5:00P.M., excluding state holidays. Sub 2 The Contractor will log requests and provide to the Procuring Agency technical support services for the Software based on the priority levels and problem resolution processes described in the Performance Measures, above. Sub 3 The Contractor will update documentation (Systems Administration Guide, User Guide, and Product Manual) to reflect changes made to the system as a result of problem resolution. Sub 4 The Contractor will respond to technical and functional questions about the CAD System. Such requests will be assigned a default Priority of Priority 3 unless the Procuring Agency requests a higher priority be assigned to the request. Monthly Report Sub 1 The Contractor shall provide or make available online a monthly report on the activity and status of all logged requests received from the Procuring Agency. Activities Tracking Sub 1 Contractor shall maintain a log of requests in a Procuring Agency approved tracking system with a unique number assigned to each Procuring Agency request. The unique number shall be provided by the contractor to Procuring Agency for reference and communication. Sub 2 The Procuring Agency will assign one of four levels of priority to each request: Priority 1 is the most severe program error and represents a situation where mission critical features and functions of the CAD System are unavailable and no practical alternate mode of operation is available. Priority 1 problems will be corrected or a solution will be provided by Contractor for corrective action within two (2) hours. PAGE | 27 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM PAGE | 28 Priority 2 indicates a problem in which certain features and functionality are not available and no practical alternate mode of operation is available. Priority 2 problems will be corrected or a plan will be provided by the Contractor for corrective action within one (1) Business Day. Priority 3 is the normal “next-in-line” problem priority assignment. At this level, requests are worked on in the order in which they are received. Priority 3 problems will be corrected or a plan will be provided by Contractor for corrective action within ten (10) Business Days. Priority 4 is the Release assignment. At this level, requests are worked on as deemed appropriate by Procuring Agency. Priority 4 issues will be incorporated into specific releases, documented in an Application Deployment Package, which will be scheduled for delivery at the discretion of the Procuring Agency after time and cost estimates are provided by the Contractor and approved by the Agency, if applicable. As such, priority 4 issues will be due at the time the specific Release is delivered. PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Deliverable 10: Year 3 Support and Maintenance Deliverable Name Year 3 Support and Maintenance Task Item Problem Support Sub Tasks Due Date Begins 36 Months after Acceptance of Deliverable #X Months and Ends 48 Months after Acceptance of Deliverable #X. Compensation Not to exceed $$ including Gross Receipts Tax. Description Sub 1 The Contractor shall make technical support personnel available by phone and email on the following schedule: Monday through Friday, 8:00A.M. To 5:00P.M., excluding state holidays. Sub 2 The Contractor will log requests and provide to the Procuring Agency technical support services for the Software based on the priority levels and problem resolution processes described in the Performance Measures, above. Sub 3 The Contractor will update documentation (Systems Administration Guide, User Guide, and Product Manual) to reflect changes made to the system as a result of problem resolution. Sub 4 The Contractor will respond to technical and functional questions about the CAD System. Such requests will be assigned a default Priority of Priority 3 unless the Procuring Agency requests a higher priority be assigned to the request. Monthly Report Sub 1 The Contractor shall provide or make available online a monthly report on the activity and status of all logged requests received from the Procuring Agency. Activities Tracking Sub 1 Contractor shall maintain a log of requests in a Procuring Agency approved tracking system with a unique number assigned to each Procuring Agency request. The unique number shall be provided by the contractor to Procuring Agency for reference and communication. Sub 2 The Procuring Agency will assign one of four levels of priority to each request: Priority 1 is the most severe program error and represents a situation where mission critical features and functions of the CAD System are PAGE | 29 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM unavailable and no practical alternate mode of operation is available. Priority 1 problems will be corrected or a solution will be provided by Contractor for corrective action within two (2) hours. Priority 2 indicates a problem in which certain features and functionality are not available and no practical alternate mode of operation is available. Priority 2 problems will be corrected or a plan will be provided by the Contractor for corrective action within one (1) Business Day. Priority 3 is the normal “next-in-line” problem priority assignment. At this level, requests are worked on in the order in which they are received. Priority 3 problems will be corrected or a plan will be provided by Contractor for corrective action within ten (10) Business Days. Priority 4 is the Release assignment. At this level, requests are worked on as deemed appropriate by Procuring Agency. Priority 4 issues will be incorporated into specific releases, documented in an Application Deployment Package, which will be scheduled for delivery at the discretion of the Procuring Agency after time and cost estimates are provided by the Contractor and approved by the Agency, if applicable. As such, priority 4 issues will be due at the time the specific Release is delivered. 4.2.3 DELIVERABLE APPROVAL AUTHORITY DESIGNATIONS Complete the following table to identify the deliverables this project is to produce, and to name the person or persons who have authority to approve each deliverable. See 4.1.2 4.2.4 DELIVERABLE ACCEPTANCE PROCEDURE Signed document stating formal acceptance. 5.0 PROJECT WORK 5.1 WORK BREAKDOWN STRUCTURE (WBS) PAGE | 30 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM A WBS is a deliverable-oriented grouping of project elements that organizes and defines the total work scope of the project. Describe the work activities that comprise the work breakdown structure (WBS) or the work packages within the WBS. Identify the WBS element or other work package identifier and provide a general description of the tasks or activities, the definition or objectives, and the milestones and deliverables of each work package. Use the chart below for highest level presentation, and provide a more detailed WBS as an attachment to this project plan. Identifier Work Package Description Detailed tasks will be defined with the vendor. PAGE | 31 Definition/Objective Milestone/Deliverable PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 5.2 SCHEDULE ALLOCATION -PROJECT TIMELINE ESTIMATE Computer Aided Dispatch Schedule Estimated No. Task Name Duration Start Days after NTP End Days after NTP Pred Resource 1 Project start date 1 day 1 1 2 Kickoff meeting 2 days 2 3 1 STATE,VENDOR 3 Kickoff meeting notes 5 days 4 10 2 VENDOR 4 State reviews/approves kickoff meeting notes 5 days 11 17 3 STATE 5 Milestone 1 17 17 4 8 VENDOR prepares Project Plan 5 days 11 17 3 VENDOR 9 State reviews/approves Project Plan 5 days 18 24 8 STATE 10 Milestone 2 24 24 9 11 Project Requirements meetings 25 30 10 17 Milestone 3 59 59 15,16 18 VENDOR creates Requirements Analysis Document 10 days 31 44 11 VENDOR 19 State reviews Requirements Analysis Document pass 1 10 days 45 58 18 STATE 20 VENDOR revises Requirements Analysis Document 5 days 59 65 19 VENDOR PAGE | 32 5 days STATE, VENDOR PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Computer Aided Dispatch Schedule Estimated No. Task Name Duration Start Days after NTP End Days after NTP Pred Resource 21 State reviews/approves Requirements Analysis Document 5 days 66 72 20 STATE 22 Milestone 4 72 72 21 24 Phase testing 15 days 66 86 23 VENDOR 26 VENDOR stands up Production Environment 10 days 73 86 24FF VENDOR 27 VENDOR creates Phase user documentation and help 30 days 45 86 24FF 28 Phase Training 10 days 87 100 24 STATE, VENDOR 29 Phase phased launch 1 day 101 101 28 STATE,PSDC 30 Milestone 5 101 101 29 32 Phase bug fixes and modifications 15 days 193 213 31 VENDOR 33 Phase acceptance testing 5 days 214 220 32 STATE 34 Phase closeout 16 days 221 242 33 STATE, VENDOR 35 Milestone 6 242 242 34 PAGE | 33 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 5.3 PROJECT BUDGET TBD Identifier PB-01 PB-02 PB-03 PB-04 PB-05 PAGE | 34 PSDC Permitting and Routing System Cost All Phase Functionality TBD Year 1 Support and Maint. No Cost/Warranty TBD Year 2 Host, Support, Maint. TBD Year 3 Host, Support, Maint. TBD Total fees for development and four years of maintenance and hosting TBD PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 5.4 PROJECT TEAM 5.4.1 PROJECT TEAM ORGANIZATIONAL STRUCTURE CAD Project Team Mr. Gregory J. Fouratt Cabinet Secretary Department of Public Safety Executive Sponsors Scott Weaver Deputy Secretary Department of Public Safety Business Owners Ron Burton CIO Department of Public Safety IT Adrian Armijo Deputy Chief Department of Public Safety State Police Project Management Cesario Alvillar ITD Project Management Bureau Chief Project Manager Department of Public Safety IT Darrell Graham ITD-TSB Bureau Chief Technical Lead Department of Public Safety IT Pete Kassetas Chief Department of Public Safety State Police Kimberly Clark Department of Public Safety Communications Director Operational Support Marco Silva CAD / GIS Systems Administrator Subject Matter Expert Department of Public Safety IT 4/14/2015 PAGE | 35 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 5.4.2 PROJECT TEAM ROLES AND RESPONSIBILITIES Project Artifacts (with Roles and Responsibilities) Sponsor QA Lead Architecture † Procurement Lead C C C I I I I A, R C C C C I C I Planning Certification Request Project Management Plan A,R C C C I I C A,R C C C I C C Risk & Issues Log A, R C C C C I C I Stakeholder list Business Requirements Business Requirements Review Communications Plan A R C C I C I I C A R C C C I C I C A R I C C I C I C A, R C C C C C C I Process Models A R I C C I C I I C * Request for X (Info, Proposal, Quote) A R C C C I C C I * Requirements Fit/Gap Analysis A R I C C I C I C Artifact Business Analyst A,R Tech Leads Business Lead Project Phase Project Manager Vendor Initiation Initiation Certification Request Initiation Project Charter Planning * * PAGE | 36 C PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM * * * IV&V Contract A R I C C C C C C Project Schedule Budget (Spend Plan) A,R C C C C C C C C A,R C C C C I C C Project Test Plan A C C C R C C I Training Strategy Implementation Certification Request Architectural Solution Package Architecture Technical Review Presentation Architecture Technical Architecture Review Request Form Architecture Business Continuity Architecture Operations and Support Plan Architecture System Design Document Architecture Hosting Exception Request Form A C C R I I C I A,R C I I I C C C A C I C I C R C A R C C C C C C A R I I I I I A R I C I C C C A R I C I C C C A C I C I C R C A C C C I C R C A C I C C R C Architecture NM DoIT Security Questionnaire PAGE | 37 C C PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Implementation & Closeout * * * Change Management Request A C C C C C R C C Contracts A R C C I C C R C Status Reports Invoice Processing & Accruals A R I C C I C I C A C I C I I I R I Lessons Learned A, R C C C C C C C Project Acceptance Project Change Control A, R R C C C C C C A, R C C C C C C C C Project Closure Purchase Requisitions and/or Orders QA User Acceptance Test Sign-off Sponsor Status Reports Team Meetings & Reports Test Coverage Matrix A, R C I I C C C C C A, R C I I I I I R C A,R I C C R I C C C A, R C I C C A, R C C C C C C I C A C C C R C C C A C I C R C A, R C I R C C C Test Results and Defect Reports * Training Plan R = Responsible A = Accountable C = Consulted I = Informed * If applicable to the project scope PAGE | 38 I C C C † Includes Integration, Application, Infrastructure, and Info Security Leads PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM ROLE RESPONSIBILITY NAME FUNCTIONAL AREA Project Manager/Business Analyst See RACI Above Cesario Alvillar DPS IT Sponsor See RACI Above Gregory J. Fouratt DPS Business Lead/QA Lead See RACI Above Kimberly Clark DPS Communications Architecture See RACI Above DoIT DoIT Technical Lead See RACI Above Darrell Graham DPS IT Procurement lead See RACI Above Elizabeth (Karana) Haring DPS Vendor See RACI Above Tim Pilcher Vendor PAGE | 39 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 5.6 PROJECT LOGISTICS Logistics describes how the project manager, project team, the business owner/customer and any vendor resources will physically work together. Include anything to do with moving or starting resources. Training specifically related to project team members should be included here. 5.6.1 PROJECT TEAM TRAINING Describe training if any needed by project team members. This is not to include training for end users, system administrators or business owners; those should be handled within a training document or part of the transition to operations planning. N/A Resource Marco Silva PAGE | 40 Cost Estimate Estimated Hours Availability Skill Set Work Product/Deliverable SQL Server Reporting SQL Server Reporting PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 6.0 PROJECT MANAGEMENT AND CONTROLS 6.1 RISK AND ISSUE MANAGEMENT 6.1.1 RISK MANAGEMENT STRATEGY Maintain a Project Risk Log. 6.1.2 PROJECT RISK IDENTIFICATION At the beginning of each project team meeting, the risk log will be reviewed/updated and any new risks identified. 6.1.3 PROJECT RISK MITIGATION APPROACH Each identified risk will be assigned to someone to mitigate and a due date assigned. See matrix below. 6.1.4 RISK REPORTING AND ESCALATION STRATEGY Steering Member Project Sponsor Project Manager PAGE | 41 Review and accept the initial risk assessment, management plan, project plan and budget Review and accept the initial risk assessment, management plan, project plan and budget Conduct initial risk assessment Develop plans with project team for risk Keep an issue and risk tracking log and will work with the Project Team for corrective action Hold reviews of the issue and risk log with the Project Director as required Provide an issue and risk log review at meetings PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 6.1.5 PROJECT RISK TRACKING APPROACH Category Sequence Risk/Issue/Action Planning P-A15 Provide network spec/Description pg. 31 Planning Planning Planning Planning P-A22 P-A23 P-A24 P-A25 P-I01 PAGE | 42 Impact Meet with Karana, does word "shall" eliminate a vendor? Ask Karana if column Priority (H,M,L)can be deleted for RFP to vendor and keep for internal scoring? Coralate to 1,2,3? Delete if Priority column deleted? Can funds be used for an RFP for the RMF system? What is contract approval process? There are questions about the funding of the project and the rules/law governing use and expenditures. Spending deadlines missed, project jeopardized due to lack of funds Owner Mitigation Start Date Due Date Darrel 2/14/2014 2/20/2014 Cesario 2/20/2014 2/21/2014 Kim 2/20/2014 2/272014 Kim 2/21/2014 3/3/2014 Kim, Cesario Ask Karana 2/24/2014 3/3/2014 Kim Cesario and Kim will meet with Steve Riggs for process review 2/26/2014 2/26/14 Date Completed PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Planning P-R07 Planning P-R11 Planning P-A29 P - Planning A - Action R - Risk I- Issue IM Implementation Risks are mitigated mitigated by reducing its probability of happening to zero Risk - an uncertain event that may or may not happen, that will impact your project adversely (positive or negative) affecting the outcome of the project PAGE | 43 Maps Moving the contract through the approval process could take longer than wanted. Data Requirements assessment - meet and provide DPS with a template and help with a survey Issues are resolved - taking action Issue - an issue is a matter in question or dispute that is disruptive to the smooth execution of a project as planned. There is no probability attached, it is a certitude. An Issue will happen, is happening now, or has already happened. No maps for dispatchers, a must for CAD Project delays, loss of funds Darrel/Marco Work with Gar on his consolidated mapping project 2/4/2014 2/27/2014 Kim, Cesario Kim and Karana will move the contracts through the process 2/25/2014 2/25/2014 EDAC,Marco, Perri Meet and provide DPS with a template and help with a survey 3/6/2014 3/24/2014 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 6.1.6 ISSUE MANAGEMENT 6.1.6.1 Internal Issue Escalation and Resolution Process Issues will be entered into the Issue Tracking Log. The Project Team will be responsible for tracking issues through to resolution. The project team will review the issues list at each project meeting. Issues that require resolution by executive sponsors will be brought to their attention. 6.1.6.2 External Issue Escalation and Resolution Process External issues will be entered into the Issue Tracking Log and tracked the same as internal issues. The Project Manager will escalate to executive sponsors as required. 6.2 INDEPENDENT VERIFICATION AND VALIDATION - IV&V Independent Verification and Validation will be contracted to MTG to perform for the duration of the project. Weekly status meetings will be held with the contractor to review contracted deliverables. 6.3 SCOPE MANAGEMENT PLAN 6.3.1 CHANGE CONTROL 6.3.1.1 Change Control Process Changes to the project will use the following process: PAGE | 44 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Project Manager Technical Lead Permitting & Routing Change Control Process Change Order Update Design, Specs, Requirements Baseline New versions Log and Review Change Requests Change Request impacts scope, time, Budget? No Create Change Order Update Change Request Log Update Charter, Scope,Requirements Schedule, Budget Create Change Order Yes Steering Committee Business Owner No Yes Raise to Steering Committee? No Approve? Yes 3/25/2014 PAGE | 45 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 6.3.1.2 Change Control Board (CCB) The Steering Committee will act as the CCB. See change control process above. CAD Project Governance Mr. Gregory J. Fouratt Cabinet Secretary Department of Public Safety Executive Sponsors Scott Weaver Deputy Secretary Department of Public Safety Business Owners Ron Burton CIO Department of Public Safety IT Adrian Armijo Deputy Chief Department of Public Safety State Police Project Management Cesario Alvillar ITD Project Management Bureau Chief Project Manager Department of Public Safety IT Darrell Graham ITD-TSB Bureau Chief Technical Lead Department of Public Safety IT Pete Kassetas Chief Department of Public Safety State Police Kimberly Clark Department of Public Safety Communications Director Operational Support 4/15/2015 PAGE | 46 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 6.4 PROJECT BUDGET MANAGEMENT 6.4.1 BUDGET TRACKING The Project Manager will work with Contracts, Business Owner and the Executive Sponsor to verify cost estimates with the actual billed amounts and ensure that Project reporting is accurate. 6.5 COMMUNICATION PLAN 6.5.1 COMMUNICATION MATRIX Audience Steering Committee Method SharePoint project website progress update and/or email Status Meeting delivering status report documents Timing Participants Weekly* Project Manager, Vendor** Weekly VENDOR, Project Manager, Project Team, Optional Stakeholders Weekly Project Manager, Project Team, Optional Stakeholders Project Team meetings Project Team SharePoint project website progress update and/or email Key Topic discussions Vendor Email progress update; Meeting * or as requested ** others as requested Status report documents include Project schedule update, Deliverables update, Issues update 6.5.2 STATUS MEETINGS Project team meetings will be weekly, with other meetings as required. 6.5.3 PROJECT STATUS REPORTS In addition to the status listed above, the monthly DoIT Status Report will be completed by the Project Manager and submitted to DoIT. PAGE | 47 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 6.6 PERFORMANCE MEASUREMENT (PROJECT METRICS) 6.6.1 BASELINES Project Area Category Measure Requirements Quality Team and Stakeholder review and signed Functional Baseline Design Quality Allocated Baseline Test Plan Quality Testing Production version Quality Production Baseline Technical Lead review Requirements Traceability to design and signed Business owner, and Stakeholders review Requirements Traceability to test results and signed Technical Lead review of configuration and signed Schedule Project Time Milestones Milestone dates, status reports Budget Project Budget Milestones Budget reports, status PAGE | 48 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 6.7 QUALITY OBJECTIVES AND CONTROL 6.7.1 QUALITY STANDARDS No. Quality Standard Tracking Tool or Measure Certification to proceed to next phase by DoIT • Approval from DoIT Project Certification Committee and release of funds 2 Project issues/risks documented, tracked, and worked to resolution • Issues/risks Log 3 Project budget • Weekly budget review 4 Project Schedule • Weekly Schedule update and review 5 Verification and Validation • Scheduled reviews • Issue tracking and resolution • Reports 6 Project completed within budget, schedule, and scope • Project Management Plan • Project Change Control Process • Scope Management • Steering Committee Meeting Decisions 1 PAGE | 49 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 6.7.2 PROJECT AND PRODUCT REVIEW AND ASSESSMENTS Review Type Quality Standard Tools Reviewer Reports Requirements Approved and signed Requirements document Meetings, MS Word, MS Excel, Visio, other tools as needed Project Team, Project Stakeholders, Steering Committee Status Plans Input from team, Stakeholders, SMEs, vendors Meetings, MS Project, Visio, other tools as needed Project Team, Sponsor(s) Status Milestones Scheduled dates MS Project Project Team, Project Sponsor Status Testing Test results in alignment with Requirements Test scripts, user input, SMEs, Project Team, test tracking Project Manager Test plan, User acceptance Training All training delivered to at planned time and users Vendor dependent Training Plan Business owner, SMEs 6.7.3 AGENCY/CUSTOMER SATISFACTION Areas of feedback When How Often DPS Anytime Anytime Project quality of communications Meetings Project Team meetings Manages project tasks Meetings Monthly Productive Meetings Anytime Anytime PAGE | 50 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 6.7.4 PRODUCT DELIVERABLE ACCEPTANCE PROCESS Deliverable Final Approval Process Customer Acceptance Criteria Kickoff meeting notes Project Manager and Business Owner review Notes are complete Project Plan Project Manager and Team review Plan includes all in contract Preliminary permitting and routing system – prototype Team review As stated in contract Requirements Analysis Document Project Manager, Business Owner and Technical Lead review Review of requirements document Test Environment Technical Lead will approve Review of system specs Production Environment Technical Lead will approve Review of system specs User Documentation Business Owner will approve Business Owner review Training Business Owner, SMEs SMEs review and feedback Phase X Acceptance Test Business Owner, Technical Lead Project Team review of test results Phase XX Acceptance Test Phase X Acceptance Test Project Team review of test results 6.8 CONFIGURATION MANAGEMENT 6.8.1 VERSION CONTROL All documents will receive a version number and stored in the project folder(s). 6.8.2 PROJECT REPOSITORY (PROJECT LIBRARY) All project documents will be stored in the following folder: Z:\Communications Director\CAD RFP 6.9 PROCUREMENT MANAGEMENT PLAN All procurements will be tracked by the Project Manager and Business Owner. PAGE | 51 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM 7. 0 PROJECT CLOSE 7.1 ADMINISTRATIVE CLOSE The closeout activities for the CAD Project will be by milestones defined in the project. The final closeout will include the completion of CAD Project documentation, the DoIT closeout report and a presentation to the DoIT Project Certification Committee for approval to formally close the project. 7.2 CONTRACT CLOSE Review of contract deliverables for completeness by the Project Manager and the Business Owner. ATTACHMENTS Attachments are included for additional information, but are not formally considered part of the Project Plan for approvals and change management purposes. Examples Acronyms, abbreviations and definitions o CAD, Computer Aided Dispatch o DPS, Department of Public Safety o DOT, Department of Transportation o EDAC, Earth Data Analysis Center o PAGE | 52 PROJECT MANAGEMENT PLAN FOR COMPUTER AIDED DISPATCHING SYSTEM Project timeline CAD Timeline Jun 2015 - Jan 2017 Development / Testing / Training / Cutover Today Feb 2013 - Jun 2015 Planning Phase Sep 2012 Initiation Cert Apr 2015 Planning Cert Release of Funds Feb 2013 Apr 2013 - Jun 2013 Planning Cert Processes Written Sep 2012 - Feb 2013 Initiation Phase 1/1/2013 Jun 2015 - Jan 2017 Implementation Phase Apr 2013 - Dec 2013 Recommendations Jun 2015 Implementation Cert Jan 2014 - Feb 2015 RFP 1/1/2014 1/1/2015 1/1/2016 9/1/2012 Assessment Sep 2012 - Dec 2012 Page 1 PAGE | 53 Mar 2017 Close Out Cert Project Mgr starts Nov 2013 1/1/2017 3/31/2017 Finish April 14, 2015