WECC Capital Cost Recommendations June 4, 2012 Arne Olson, Partner Nick Schlag, Consultant Gabe Kwok, Associate History In 2009, E3 provided WECC with recommendations for capital costs of new electric generation technologies to use in its 10-year study cycles • Prior to this effort, the relative costs of WECC’s study cases could only be compared on a variable-cost basis (using PROMOD results) • This effort provided WECC with a framework to quantify relative scenario costs on a basis reflecting their actual prospective costs to ratepayers by combining variable & fixed costs Total Cost = Variable Costs (PROMOD) + Fixed Costs (E3 Capital Cost Tool) In 2011, WECC asked E3 to review the capital costs to ensure continued accuracy • Due to the continued evolution of solar PV technologies, E3 lowered its estimates of photovoltaic capital costs 2 Background In the midst of its 10- and 20-year study plans, WECC has asked E3 to provide guidance on resource cost and performance to use in those studies These capital costs will serve as inputs to the 10- and 20-year studies: • Including capital costs in the 10-year study cycles enables comparisons of total costs between scenarios • Capital costs will serve as an input to the 20-year study’s LTPT, allowing for the development of robust scenarios through cost minimization 3 Updates E3 presented its initial recommendations to stakeholders on May 15, 2012 Based on stakeholder feedback and comments, E3 has reviewed its recommendations for wind and solar costs Minor revisions were made to several of the present day solar PV costs to better capture expected cost differentials between system types and sizes E3 has revised some of the data inputs used to forecast of cost declines for solar PV and solar thermal technologies: • Forecasts of installed capacity for solar PV and solar thermal have been revised to account for near-term projections of global market dynamics • Learning rate for solar thermal has been adjusted to reflect greater potential for technological improvements than originally anticipated Modeling Framework 2032 Study 2022 Study Resource Portfolio Resource Performance (NREL) PROMOD Total Scenario Costs Capital Costs (E3 Capital Cost Tool) Resource Performance (WREZ) LTPT/NXT Resource Portfolio Total Scenario Cost Capital Costs (E3 Capital Cost Tool) 5 Scope of Updates E3’s Capital Cost Tool considers a broad range of potential new generation technologies The scope for E3’s update is divided into two phases: • • Near term (integrated in this year’s study cycle): update costs for wind and solar technologies Long term (integrated into subsequent study cycles): review costs for all technologies This division prioritizes updating those costs that are most likely to have changed given the limited time before the start of this study cycle Technologies in E3’s Capital Cost Tool Technology Subtypes Biomass Biogas Landfill, Other Gas CT Gas CCGT CHP Small, Large Coal Steam, IGCC Nuclear Hydro Small, Large, Upgrade Solar PV Fixed Tilt, Tracking Solar Thermal No Storage, 6hrs Storage Wind Onshore 6 Technologies Covered E3’s current update encompasses the following technologies—an expanded set compared to the original Capital Cost Tool New to This Year’s Study Cycle Modeled in Prior WECC Studies Solar PV Large Utility (20 MW +) • Fixed Tilt • Tracking Solar Thermal No Storage 6hrs Storage Wind Onshore Small Utility (1-20 MW) • Fixed Tilt • Tracking Rooftop • Commercial • Residential New technology characterizations are needed to represent increasing specificity of photovoltaic resources modeled by WECC, especially in the High DG/DSM Case 7 Approach 1. Determine the cost to install a power plant today (2012) • Given limited time, focus is on wind and solar technologies • Prior recommendations for other technologies are carried forward 2. Use learning curves to forecast declines in technology capital costs over the next two decades 3. Determine the appropriate applicability of federal tax incentives for renewable technologies over the 10- and 20-year study cycles 4. Develop and apply updated regional multipliers to capture geographic variations in resource costs around the WECC 8 Notes on Resource Performance With the limited time available before the commencement of the present study cycles, E3’s present scope of work focuses on updating resource costs WECC staff is developing assumptions on resource performance for use in the current study cycle Over a longer timeframe, E3 will work with WECC to ensure that cost and performance assumptions are consistent with one another and represent our best expectations of future development patterns 9 Present Day Wind and Solar Costs Present-Day Costs To derive estimates of present-day wind and solar costs, E3 has reviewed a wide range of recent studies and publications For developing technologies, precise capital costs are a moving target that are difficult to pin down • A review of literature provides both… • …outdated forecasts of what costs would be today; and • …retrospective analysis of actual costs from several years ago E3 has used this information to develop its best estimates of costs to install wind and solar plants in 2012 All costs are expressed in 2010 dollars 11 Historical Trends in Solar PV Costs Installed solar PV costs continue to decrease: • Average U.S. behind-the-meter PV data from 1998-2010 (Left) • California Solar Initiative (CSI) data from 2009-2011 (right) • CSI is focused on rooftop PV Less data available for utility-scale PV and solar thermal Tracking the Sun IV: An Historical Summary of the Installed Cost of Photovoltaics in the United States from 1998 to 2010 California Solar Statistics 12 Current Trends in Solar PV Prices Market data and experience have shown substantial movement in PV prices over the past two years, suggesting we are on a relatively steep portion of the “learning curve.” This makes identifying current prices a challenging exercise. Source: Technical Potential for Local Distributed Photovoltaics in California 13 Historical Trends in Wind Costs Average 2010 installed cost was similar to 2009 14 2010 Wind Technologies Market Report (June 2011) Data Sources Author Report Name Publication Date Installation Year Historical or Forward CPUC 33% RPS Calculator Update May 2012 2012 Forward E3/CPUC Technical Potential for Local Distributed Photovoltaics in California Mar. 2012 2009 – 2020 Both B&V/NREL Cost and Performance Data for Power Generation Technologies Feb. 2012 2010 - 2050 Both NREL Residential, Commercial, and Utility-Scale Photovoltaic (PV) System Prices in the United States: Current Drivers and CostReduction Opportunities Feb. 2012 2010 Historical DOE SunShot Vision Study Feb. 2012 2010 – 2020 Both CSI California Solar Statistics Jan. 2012 2009 - 2011 Historical LBNL Tracking the Sun IV: An Historical Summary of the Installed Cost of Photovoltaics in the United States from 1998 to 2010 Sept. 2011 2010 Historical LBNL 2010 Wind Technologies Report June 2011 2010 Historical Lazard Levelized Cost of Energy Analysis – Version 5.0 June 2011 2012 Forward Sandia Power Tower Technology Roadmap and Cost Reduction Plan April 2011 2013 Forward EIA Updated Capital Cost Estimates for Electricity Generation Plants (for AEO2011) Nov. 2010 2011 Forward NWPCC Sixth Northwest Conservation and Electric Power Plan Feb. 2010 2010 Forward CEC Comparative Costs of California Central Station Electricity Generation Jan. 2010 2010 Forward 15 Solar PV – Fixed Utility (20 MW+) TEPPC 2011 Author Cost ($/kWDC) Generic LCOE ($/MWh) Installation Vintage Size (MW) 20 RETI 2B $3,230 2010 LTPP $3,400 2010 EIA $3,963 2011 180 $3,400 2012 100 Installation Vintage Size (MW) TEPPC 2011 Notes Thin Film Current Update Author Cost ($/kWDC) Generic LCOE ($/MWh) B&V/NREL $2,396 2015 100 NREL $3,800 2010 187.5 CPUC $2,380 2012 150 2012 100 Recommended $2,550 $117 Notes California Capital costs for solar PV technologies shown here are expressed relative to the DC nameplate rating. To convert to an AC capital cost, these costs should be multiplied by 1.18 (assuming DC-AC conversion of 85%). 16 Solar PV – Tracking Utility (20 MW+) TEPPC 2011 Author Cost ($/kWDC) Generic LCOE ($/MWh) Installation Vintage Size (MW) Notes NWPCC $7,294 2008 25 Crystalline RETI 2B $3,825 2010 20 Crystalline LTPP $3,995 2010 CEC $4,626 2010 25 $3,995 2012 100 Installation Vintage Size (MW) TEPPC 2011 Current Update Author Cost ($/kWDC) Generic LCOE ($/MWh) B&V/NREL $2,664 2015 100 NREL $4,400 2010 187.5 CPUC $2,800 2012 150 2012 100 Recommended $2,800 $123 Notes California Capital costs shown relative to DC nameplate rating 17 Solar PV – Fixed Utility (1-20 MW) Technology has not been represented in past WECC modeling efforts Generic LCOE ($/MWh) Installation Vintage Size (MW) $5,042 2011 8.4 B&V/NREL $2,877 - $3,538 2010 1 - 10 B&V/NREL $2,593 - $3,233 2015 1 - 10 CPUC $2,590 - $2,730 2012 5 - 20 California $2,750 2012 10 Crystalline 2012 1 - 20 Author EIA Lazard Recommende d Cost ($/kWDC) $2,975 $135 Notes Capital costs shown relative to DC nameplate rating 18 Solar PV – Tracking Utility (1-20 MW) Technology has not been represented in past WECC modeling efforts Author Cost ($/kWDC) Generic LCOE ($/MWh) Installation Vintage Size (MW) B&V/NREL $3,142 - $3,844 2010 1 - 10 B&V/NREL $2,827 - $3,477 2015 1 - 10 CPUC $3,325 2012 1-5 Lazard $3,500 2012 10 2012 1 - 20 Recommende d $3,225 $138 Notes Crystalline Capital costs shown relative to DC nameplate rating 19 Solar PV - Commercial Technology has not been represented in past WECC modeling efforts Author Cost ($/kWDC) Generic LCOE ($/MWh) Installation Vintage Size (kW) LBNL $5,800 2010 100 – 500 NREL $4,590 2010 217 CSI $5,622 2011 56 B&V/NREL $4,870 2010 100 B&V/NREL $3,904 2015 100 Recommended $5,000 $256 Notes California 2012 Capital costs shown relative to DC nameplate rating 20 Solar PV - Residential Technology has not been represented in past WECC modeling efforts Author Cost ($/kWDC) Generic LCOE ($/MWh) Installation Vintage Size (kW) LBNL $6,600 2010 5 – 10 NREL $5,710 2010 4.9 CSI $6,472 2011 5.5 B&V/NREL $6,050 2010 4 B&V/NREL $4,413 2015 4 2012 <10 Recommended $6,000 $301 Notes California Capital costs shown relative to DC nameplate rating 21 Solar Thermal – Without Storage TEPPC 2011 Author Cost ($/kW) Generic LCOE ($/MWh) Installation Vintage Size (MW) Notes NWPCC $4,761 2008 100 Trough CEC COG $3,687 2010 250 Trough; California RETI 2B $5,350 - $5,550 Trough; California LTPP $5,300 Trough; California EIA $4,714 2011 100 Trough; Wet-cooled EIA $4,692 2011 100 Tower; Wet-cooled TEPPC 2011 $5,350 2012 Current Update Author Cost ($/kW) Generic LCOE ($/MWh) Installation Vintage Size (MW) Notes B&V/NREL $4,992 2010 200 Trough B&V/NREL $4,799 2015 200 Trough DOE SunShot $4,500 2010 100 Trough; Wet-cooled $5,000 - $5,400 2012 250 Trough Lazard Recommended $4,900 $187 2012 22 Solar Thermal – With Storage TEPPC 2011 Generic LCOE ($/MWh) Installation Vintage Author Cost ($/kW) RETI 2B $7,650 - $7,850 California $7,500 California LTPP TEPPC 2011 Size (MW) Notes $7,500 Current Update Author Cost ($/kW) Generic LCOE ($/MWh) Installation Vintage Size (MW) Notes B&V/NREL $7,178 2010 200 Trough, 6hrs B&V/NREL $6,914 2015 200 Trough, 6hrs DOE SunShot $7,870 2015 250 Trough, 6hrs $6,300 - $6,500 2012 250 Trough, 3hrs B&V/NREL $7,158 2010 200 Tower, 6hrs Sandia $7,427 2013 100 Tower, 9 hrs DOE SunShot $5,940 2015 100 Tower, 6 hrs Lazard Recommended $7,100 $199 2012 Generic, 6 hrs 23 Wind TEPPC 2011 Author NWPCC RETI 2B Cost ($/kW) Generic LCOE ($/MWh) $2,127 Installation Vintage Size (MW) 2008 100 Notes NW $2,150 - $2,600 CA LTPP $2,350 CA EIA $2,438 TEPPC 2011 2011 100 Installation Vintage Size (MW) 50 $2,350 Current Update Author Cost ($/kW) Generic LCOE ($/MWh) CEC COG $2,023 2010 LBNL $2,148 2009-2010 B&V/NREL $2,013 2010 $1,300 - $1,900 2012 Lazard Recommended $2,000 $63 Notes CA US 100 2012 24 Recommended Resource Costs Cost Summary (2010 $) Technolog y Solar PV DC Capital Cost ($/kWDC) AC Capital Cost ($/kW) Generic AC Capacity Factor (%) Generic LCOE ($/MWh) Fixed (>20 MW) $2,550 $3,000 27% $117 Tracking (>20 MW) $2,800 $3,300 29% $123 Fixed (1-20 MW) $2,975 $3,500 27% $135 Tracking (1-20MW) $3,225 $3,800 29% $138 Comm Roof $5,000 $5,900 23% $256 Res Roof $6,000 $7,100 23% $301 Subtype Solar Thermal No Storage n/a $4,900 28% $187 6hr storage n/a $7,100 36% $199 Wind Onshore n/a $2,000 37% $63 Capital costs for solar PV are converted from DC to AC by multiplying by 1.18 (assuming DC-AC conversion of 85%). 25 Comparison of Updated Costs to Prior Recommendations Cost Summary (2010 $) Technology WECC 2011 2012 Update Generic AC Capacity Factor (%) AC Capital Cost ($/kW) Generic LCOE ($/MWh) AC Capital Cost ($/kW) Generic LCOE ($/MWh) Fixed (>20 MW) 27% $4,000 $150 $3,000 $117 Tracking (>20 MW) 29% $4,700 $164 $3,300 $122 Fixed (1-20 MW) 27% n/a n/a $3,500 $135 Tracking (1-20MW) 29% n/a n/a $3,800 $138 Comm Roof 23% n/a n/a $5,900 $256 Res Roof 23% n/a n/a $7,100 $301 No Storage 28% $5,350 $200 $4,900 $187 6hr storage 36% $7,500 $208 $7,100 $199 Onshore 37% $2,350 $75 $2,000 $63 Subtype Solar PV Solar Thermal Wind 26 Forecasting Future Costs for Wind and Solar Considerations in Forecasting Technology Cost Technology cost changes • As nascent technologies become increasingly mature, they may experience cost declines as a result of learning by doing and increased scale of manufacturing • Technology costs are sensitive to other factors as well: • Trends in the costs of raw materials • Relationship of supply and demand Tax credit expiration • ITC for solar technologies is set to expire in 2017 • PTC for wind expires in 2013; for other technologies in 2012 Learning Curve Theory Learning curves describe an observed empirical relationship between the cumulative experience in the production of a good and the cost to produce it • Increased experience leads to lower costs due to efficiency gains in the production process • The functional form for the learning curve is empirically derived and does not have a direct theoretical foundation Example: 20% Learning Rate The learning rate (LR) is used to describe the expected decrease in costs with a doubling of experience Price The theory of learning curves in economics was formalized by Kenneth Arrow in 1962 in “The Economic Implications of Learning by Doing”. This empirical relationship has since been affirmed in a number of works that span many sectors of the economy. 2x -20% 2x -20% Cumulative Experience 29 Learning Curves and Solar PV Declines in solar PV module price have tracked the functional form of the learning curve with a learning rate of approximately 20% since 1976 Past performance does not indicate future potential Recent cost reductions have not followed the longer-term trends of historical learning Source: Global Overview on Grid-Parity Event Dynamics (Breyer and Gerlach) 30 Learning Curves and Solar PV Module costs represent only a fraction of solar PV system costs; total system costs have historically declined at a slightly lower learning rate (~17%) Source: Navigant Consulting 31 Uncertainty in Future Costs Past trends do not guarantee future declines, and other factors influence technology costs Optimistic Path Pessimistic Path Solar PV continues to reap benefits of a high learning rate Today’s low prices caused by excess supply followed by a rebound as markets re-equilibrate Global installed capacity grows rapidly Cost of raw materials rise Installed PV Cost Int’l markets saturate and US growth slows as the ITC expires 2010 Historical Trend Pessimistic Path Optimistic Path 2012 2014 2016 2018 2020 32 Uncertainty in Global Installed Capacity Future growth of solar PV can vary widely, as shown by the IEA’s 2010 Energy Technology Perspectives scenarios Global Installed Capacity (GW) Solar PV 3,500 3,000 3,000 2,500 2,000 1,700 1,500 1,000 500 40 300 0 Existing, 2010 Baseline BLUE MAP BLUE High Renewables IEA Projections, 2050 • IEA BLUE, High Renewables: renewables serve 75% of load in 2050 • IEA BLUE Map: global CO2 emissions reduced to half of 2005 levels • IEA Baseline: business-as-usual; no new policies affect energy sector 33 Sensitivity of Learning Curves to Global Installations Forecast The impact of an additional MW of capacity declines as the cumulative installed capacity increases Global Installed Solar PV Capacity (GW) 1,800 1,600 1,400 1,200 1,000 800 600 400 200 0 2012 Solar PV Capital Cost (% of 2012) The choice of a forecast of future installations has a significant impact on anticipated future cost declines 2,000 2017 2022 2027 2032 2037 140% 120% 90% 100% 80% 71% 60% 65% 40% 20% 0% 2012 2017 IEA BLUE, High Renewables 2022 2027 IEA BLUE Map 2032 2037 IEA Baseline Forecast declines based on a 10% learning rate 34 Near-Term Outlook for Solar PV E3 has reviewed additional predictions of trends in global installed capacity for solar PV The European Photovoltaic Industry Association’s Global Market Outlook predicts between 208 and 343 GW of solar PV by 2016 Solar PV Global Installed Capacity (GW) 400 350 300 250 EPIA Moderate 200 EPIA Policy Driven 150 Historical 100 50 0 2004 2006 2008 Moderate Scenario: pessimistic market behavior, reduced policy support for PV development 2010 2012 2014 2016 Policy Driven Scenario: continuation of support mechanisms (FiTs) and strong political favor for solar PV 35 Forecasting Solar PV Global Installations Through 2032 Short-term market outlook is generally consistent with IEA’s long-term vision The average trajectory of the EPIA’s forecasts results in approximately 1,000 GW of solar globally by 2030 • E3 uses the average of the EPIA-derived long-term forecasts to forecast cost reductions for solar PV Solar PV Global Installed Capacity (GW) 1,400 1,200 EPIA Moderate 1,000 EPIA Policy Driven 800 Historical 600 EPIA Moderate (Extrap) EPIA Policy Driven (Extrap) 400 IEA 2050 BLUE Map (Linear) 200 Avg of EPIA-Derived Forecasts 0 2010 2014 2018 2022 2026 2030 36 Solar PV Learning Rate Recommendation E3 recommends a learning rate of 10% for solar PV, which is applied to the entire capital cost (not just modules) No guarantee that historical rates (17%) will continue • Learning rates for mature technologies (coal & gas) have decreased with technology maturation • As balance-of-systems components begin to represent larger shares of system costs, learning rates are likely to decrease 120% Solar Thermal Capital Cost s (% of 2012) Coupled with the EPIA-derived longterm PV forecast, this learning rate yields the following estimates of longterm cost reductions 100% -16% 80% -23% -27% -29% 2027 2032 60% 40% 20% 0% 2012 2017 2022 37 Comparison of Recommended PV Costs to Other Sources Res Roof PV Comm Roof PV $8,000 $8,000 E3 LDPV (20% LR) E3 LDPV (20% LR) E3 LDPV (0% LR) E3 LDPV (0% LR) $6,000 B&V/NREL CSI Data NREL Benchmark $4,000 $/kW-DC $/kW-DC $6,000 B&V/NREL CSI Data NREL Benchmark $4,000 NREL Evolutionary NREL Evolutionary DOE Sunshot $2,000 DOE Sunshot $2,000 LBNL LBNL E3/WECC 2012 2016 $6,000 2020 2024 2028 2032 2036 2012 2016 $6,000 Small Ground PV - Fixed Tilt $5,000 E3 LDPV (0% LR) B&V/NREL NREL Benchmark $3,000 NREL Evolutionary $2,000 DOE Sunshot 2020 2024 2028 2032 2036 Large Ground PV - Fixed Tilt $5,000 E3 LDPV (20% LR) $4,000 $/kW-DC E3/WECC $0 2008 B&V/NREL $4,000 $/kW-DC $0 2008 NREL Benchmark NREL Evolutionary $3,000 DOE Sunshot $2,000 CPUC RPS Calc CPUC RPS Calc $1,000 $0 2008 E3/WECC 2012 2016 2020 2024 2028 2032 2036 E3/WECC $1,000 $0 2008 2012 2016 2020 2024 2028 2032 2036 38 Forecasting Solar Thermal Global Installed Capacity by 2032 IEA’s BLUE Map Scenario includes 600 GW of solar thermal capacity by 2050 • To reach this goal, solar thermal global installed capacity would have to reach approximately 200 GW by 2030 • European Solar Thermal Electricity Association’s Solar Thermal Electricity 2025 anticipates a cumulative total between 60 and 100 GW by 2025—substantially less E3 has developed a forecast based on the ESTELA forecast that reflects lower anticipated near-term installations of solar thermal facilities Total global capacity installed by 2032 is forecast to be 51 GW Solar Thermal Global Installed Capacity (GW) • 250 Aspirational 200 150 100 51 50 Pessimistic 0 2010 2014 2018 2022 2026 2030 ESTELA 2025 Potential Greenpeace - Reference Greenpeace - Moderate IEA ETP Reference IEA ETP BLUE Map Interp/Extrap 39 Solar Thermal Learning Recommendation Based on stakeholder feedback, a learning rate of 10% was selected for solar thermal Combined with the forecast of global installed capacity from the prior slide, this learning rate yields the following projection of solar thermal cost reductions: Solar Thermal Capital Cost s (% of 2012) 120% 100% -20% 80% -29% -36% -39% 2027 2032 60% 40% 20% 0% 2012 2017 2022 40 Wind Learning Recommendation Wind is a much more mature technology than either solar PV or solar thermal, with a global installed capacity of close to 200 GW Estimates of learning rates for wind range from 0% - 15%; E3 has adopted a rate of 5% 120% Wind Capital Cost s (% of 2012) • In combination with IEA’s BLUE Map scenario (2,000 GW of wind by 2050), this assumption results in a 12% reduction in wind capital costs by 2032 100% -5% -8% -10% -12% 2017 2022 2027 2032 80% 60% 40% 20% 0% 2012 41 Federal Tax Credit Landscape Current federal tax policy provides large incentives to wind and solar developers: • Accelerated depreciation (5-yr MACRS for wind and solar) • Investment tax credit (30% of capital costs for solar) • Production tax credit ($22/MWh for wind) $350 $301 LCOE ($/MWh) $300 $250 $200 $186 $186 $150 $100 Impact of Five Year MACRS $114 Impact of Federal Tax Credit $114 $50 $63 $0 Large Solar PV Solar Thermal Wind 42 Expiration of Federal Tax Credits Federal tax credits are scheduled to retire in the near future • Investment tax credit reverts from 30% to 10% in 2017 • Production tax credit ($22/MWh for wind) expires in 2013 • PTC for other technologies expires in 2014 The 5-year MACRS, as part of the general tax code, is assumed to remain in place 43 Combined Impact of Tax Credit Expiration and Technology Learning Increased resource costs resulting from the expiration of tax credits are largely offset by technological progress over the next two decades 250 LCOE (2010 $/MWh) 200 Solar Thermal (no storage) 150 Large Solar PV (Fixed Tilt) 100 Wind 50 0 2012 2017 2022 2027 2032 44 Recommended Resource Costs AC Capital Costs by Installation Year (2010 $/kW) Technology 2012 2022 2032 Fixed (>20 MW) $3,000 $2,322 $2,121 Tracking (>20 MW) $3,300 $2,554 $2,333 Fixed (1-20 MW) $3,500 $2,709 $2,475 Tracking (1-20MW) $3,800 $2,941 $2,687 Comm Roof $5,900 $4,567 $4,171 Res Roof $7,100 $5,496 $5,020 Solar Thermal No storage $4,900 $3,455 $2,992 6hr storage $7,100 $5,007 $4,336 Wind Onshore $2,000 $1,834 $1,711 Solar PV Subtype Recommendations that have been modified since May 15 are highlighted in orange 45 Resulting LCOEs Levelized Cost of Energy by Installation Year (2010 $/MWh) AC Capacity Factor (%) 2012 2022 2032 Fixed (>20 MW) 27% $117 $117 $109 Tracking (>20 MW) 29% $123 $122 $114 Fixed (1-20 MW) 27% $135 $134 $124 Tracking (1-20MW) 29% $138 $137 $127 Comm Roof 23% $256 $254 $235 Res Roof 23% $301 $299 $276 Solar Thermal No storage 28% $187 $172 $153 6hr storage 36% $199 $182 $161 Wind Onshore 37% $63 $82 $80 Technology Solar PV Subtype 46 Average vs. Marginal Average vs. Marginal The cost to install one additional MW of solar in 2022 will not equal to the average cost of the solar resources installed between present day and 2022 A large fraction of the solar resources installed by 2022 will have been installed gradually over the next decade 250 200 LCOE (2010 $/MWh) • Solar Thermal (no storage) 150 Large Solar PV (Fixed Tilt) 100 Wind 50 0 2012 2017 2022 2027 2032 48 Recommendations for Installed Cost Vintages To account for the many mitigating factors that will affect resource development over the, E3 recommends using the 2015 installed cost for resources installed in the first decade and the 2027 installed cost for resources installed in the second decade To simplify this analysis, E3 also recommends assuming that the PTC is extended through the same time horizon as the ITC, expiring in 2017 First Decade Most new resources (especially solar) will come online relatively soon to claim tax credits The choice of 2015 for “average” resource costing reflects this expectation Second Decade No resources can claim tax credits Year-by-year development of renewables is highly uncertain, so the midpoint of the range (2022-2032) is used as a basis for installed costs 49 Regional Multipliers Regional Multiplier Methodology The original Capital Cost Tool included statespecific estimates of technology costs derived from “regional multipliers” • Regional multiplier methodology captures geographical differences in costs of labor and materials As part of this update, E3 has explored several questions related to this subject: 1. With the release of an update to the Civil Works Construction Cost Index System, should the regional cost multipliers be updated? 2. What other factors besides construction cost contribute to geographic difference in resource cost and can easily be incorporated into E3’s capital cost tool? 51 Regional Multiplier Methodology E3 derives technology-specific regional multipliers based on: • The relative proportions of equipment, material, and labor that constitute a plant’s costs • The Civil Works Construction Cost Index System’s (CWCCIS) state adjustment factors The CWCCIS is a construction-based cost indexing system developed by the US Army Corps of Engineers • State adjustment factors capture approximate geographic cost differences in generic construction projects • Since equipment costs represent a larger share of costs in power plant construction than in other construction applications, E3 applies state adjustment factors only to the shares of a plant’s cost associated with materials and labor 52 Sample Comparison of Regional Multiplier Calculations Example regional multiplier calculations, Gas CCGTs in California and Wyoming A California Wyoming B C D E F CWCCIS State Adjustment Factor Category Percent of Total Costs Percent Variable by Location Total Weight {=D x [B x E + (1-E)]} Equipment 70% 0% 0.700 Materials 10% 50% 0.111 Labor 20% 100% 0.242 Total 100% 1.21 1.053 Equipment 70% 0% 0.70 Materials 10% 50% 0.095 Labor 20% 100% 0.180 Total 100% 0.90 0.975 53 CWCCIS Update The Army Corps of Engineers released an update to the CWCCIS in March 2011 • E3’s prior work was based on CWCCIS from March 2008 1.40 ACOE (March 2008) ACOE (March 2011) 1.20 1.00 0.80 0.60 0.40 0.20 0.00 Changes to state adjustment factors are minimal but are easy to incorporate into TEPPC pro-forma 54 Benchmarking Regional Adjustment Factors E3’s adjustment factors capture the same general regional trends as those used by EIA (created by RW Beck) Gas CCGT Regional Multiplier 1.2 1.4 Correlation: 88% 1 0.8 E3 0.6 RW Beck 0.4 0.2 Correlation: 94% 1 0.8 E3 0.6 RW Beck 0.4 0.2 0 0 CA CO ID MT 1.4 NV NM OR UT Wind 1.2 WA WY AZ CA CO ID 1.4 Correlation: 77% 1 0.8 E3 0.6 RW Beck 0.4 0.2 MT NV NM OR UT Solar Thermal 1.2 Regional Multiplier AZ Regional Multiplier Small PV 1.2 Regional Multiplier 1.4 WA WY Correlation: 92% 1 0.8 E3 0.6 RW Beck 0.4 0.2 0 0 AZ CA CO ID MT NV NM OR UT WA WY AZ CA CO ID MT NV NM OR UT WA WY 55 Other Factors Affecting Relative Geographic Costs State and local tax codes vary widely by location and that have important implications for plant costs The table below shows different tax policies for wind projects in WECC states and their resulting impact on project LCOEs, which range from $88 to $101/MWh AZ CA CO ID MT State Income Tax (%) 7.0% 8.8% 4.6% 7.6% 6.8% Sales Tax (%) 2.4% 0.8% 4.3% 6.0% Property Tax (%) 0.3% 1.0% 0.4% Gross Receipts Tax (%) Tax Credit ($/MWh) NV NM OR UT 7.6% 7.9% 5.0% 3.0% 1.2% 0.5% 3.0% 1.0% WA WY 0.7% 3.9% 5.4% 0.6% 1.0% 0.7% 6.5% $10 0.5% $10 $3.50 Excise Tax ($/MWh) Generic Wind Cost ($/MWh) $1 $88 $96 $94 $96 $94 $96 $91 $92 $92 $101 $99 Source of information: Tax policies based on E3’s Wyoming Wind Energy Costing Model Generic wind cost calculated assuming capital cost of $2,000 and a capacity factor of 30% 56 Incorporating State Income Tax One significant variant in state-by-state tax codes that affects the cost of development is the state income tax • Ranges from 0% (NV, WA and WY) to 9% (CA) • Can be easily integrated into E3’s updated pro-forma In addition to an update of regional multipliers, E3 proposes to incorporate state-by-state income tax rates into the pro-forma to enhance the geographic differentiation of project costs 57