MBA 570 Summer 2011 Facility planning answers: How much long-range capacity is needed When more capacity is needed Where facilities should be located (location) How facilities should be arranged (layout) Maximum output of a system in a given period (general definition) ◦ May be units, hours, dollars, sq. ft. etc. ◦ Example: Tons of steel per month Effective capacity: Maximum output given standards, product mix, etc. Rated capacity: Maximum usable output given utilization & efficiency ◦ RC = (Capacity)(Utilization)(Efficiency) How would you define capacity for the following firms (e.g., steel mill, tons of steel per day): ◦ ◦ ◦ ◦ ◦ Beer brewery Auto plant Restaurant Warehouse Grocery store Beer brewery: Barrels of beer per year (output) Auto plant: Cars per week (output) Restaurant: Customers per hour (output) or number of seats (input) Warehouse: Square feet of space (input) Grocery store: Square inches of shelf space (input) Forecast Demand Develop Alternative Plans Quantitative Factors (e.g., Cost) Compute Rated Capacity Evaluate Capacity Plans Qualitative Factors (e.g., Skills) Compute Needed Capacity Select Best Capacity Plan Implement Best Plan Long Range Planning Intermediate Range Planning Add Facilities Add long lead time equipment Sub-Contract Add Equipment Add Shifts *Limited options exist Add Personnel Build or Use Inventory * Short Range Planning Modify Capacity * Schedule Jobs Schedule Personnel Allocate Machinery Use Capacity Capacity: The “throughput,” or number of units a facility can hold, receive, store, or produce in a period of time. Effective capacity: Capacity a firm can expect to receive given its product mix, methods of scheduling, maintenance, and standards of quality. Utilization: Actual output as a percent of design capacity. Efficiency: Actual output as a percent of effective capacity. Actual (or Expected) Output = (Effective Capacity)(Efficiency) Measure of planned or actual capacity usage of a facility, work center, or machine Measure of planned or actual capacity usage of a facility, work center, or machine Expected capacity Utilization Capacity Planned hours to be used Total hours available Measure of how well a facility or machine is performing when used Measure of how well a facility or machine is performing when used Actual output Efficiency Effective capacity Actual output in units Standard output in units Average actual time Standard time Forecast demand accurately Understanding the technology and capacity increments Finding the optimal operating level (volume) Build for change 1. 2. 3. 4. Making staffing changes (increasing or decreasing the number of employees) Adjusting equipment and processes – which might include purchasing additional machinery or selling or leasing out existing equipment Improving methods to increase throughput; and/or Redesigning the product to facilitate more throughput Expected Demand Expected Demand New Capacity Demand Demand New Capacity Time in Years Capacity leads demand with an incremental expansion Time in Years Capacity leads demand with a one-step expansion Expected Demand New Capacity New Capacity Time in Years Capacity lags demand with an incremental expansion Demand Demand Expected Demand Time in Years Attempts to have an average capacity, with an incremental expansion Expected Demand Demand New Capacity Time in Years Capacity leads demand with an incremental expansion Expected Demand Demand New Capacity Time in Years Capacity leads demand with a one-step expansion Expected Demand Demand New Capacity Time in Years Capacity lags demand with an incremental expansion Demand New Capacity Expected Demand Time in Years Attempts to have an average capacity, with an incremental expansion Demand Management Vary prices Vary promotion Change lead times (e.g., backorders) Offer complementary products Sales (Units) 5,000 4,000 3,000 Snowmobiles 2,000 1,000 0 J M M J S N J M M J S N J Time (Months) Sales (Units) 5,000 4,000 3,000 Snowmobiles 2,000 1,000 Jet Skis 0 J M M J S N J M M J S N J Time (Months) Sales (Units) 5,000 4,000 3,000 Total Snowmobiles 2,000 1,000 Jet Skis 0 J M M J S N J M M J S N J Time (Months) Sales (Units) Variation is reduced by Total Snowmobiles Time (Months) J O J A J O J Jet Skis A J 5,000 4,000 3,000 2,000 1,000 0 combining demands Demand Management Vary prices Vary promotion Change lead times (e.g., backorders) Offer complementary products Capacity Management Vary staffing Change equipment & processes Change methods Redesign the product for faster processing