LSST Telescope and Site Status William J. Gressler Telescope and Site Manager J. Andrew, J. Barr, F. Delgado, J. DeVries, E. Hileman, M. Liang, P. Lotz, D. Mills, D. Neill, W. Schoening, G. Schumacher, J. Sebag, O. Wiecha SPIE 2014 Astronomical Telescopes & Instrumentation SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 1 Presentation summary • • • • • Brief status of LSST Project Description of Telescope and Site (T&S) scope Status of early major subsystem awards Review of remaining procurements Plans moving forward SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 2 LSST is prepared to enter into construction in 2014 • LSST NSF FDR successfully passed in December 2013 • LSST Project in approved federal budget • LSST at National Science Board in Feb/May 2014 SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 3 Telescope and Site group part of an integrated project team PMO WBS 1 Data Management EPO WBS 2 WBS 5 Commissioning WBS 6 LSST Camera WBS 3 Telescope & Site WBS 4 SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 4 T&S scope defined by major subsystems within detailed WBS • Current design team grows to support design/build contracts • Software team to develop OCS/TCS with make/buy decisions • Concludes with integration/test activities on summit Design Build Contracts 04C 04C.00 04C.01 04C.02 04C.03 04C.04 04C.05 04C.06 04C.07 04C.08 04C.09 04C.10 04C.11 04C.12 04C.13 04C.14 WBS Name Telescope and Site Construction T&S Level 2 Milestones Telescope System Management Telescope System Engineering Summit Facilities and Infrastructure Dome Telescope Mount Mirror Systems Wavefront and Alignment Systems Calibration System Reflective Coating System Observatory Control System Telescope Control System Utilities and Support Equipment Base Facility and Infrastructure Telescope Integration and Test SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 Scope Defined by WBS Elements 5 The T&S team observatory system baseline designs meet the LSST mission requirements 30-m Dome Summit Facility 350-ton Telescope Controls Survey Captures Light Calibrates Conditions 1.2-m Atmospheric Telescope 1,380m2 Service and Maintenance Facility Camera Clean Room Control Room Coating Chamber Base Facility Operations Support Data Access Center SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 6 Important pre-construction work complete and many early procurements in place • Work complete: – Site selection and early preparation – Mirror substrates acquired (M1M3, M2) – Calibration telescope obtained • Contract awards (Phase A/Phase B): – – – – – M1M3 polishing M2 Cell Assembly (polishing and integrated testing) Hexapod/Rotator system award Telescope Mount Assembly award Summit Facility award pending • Future awards: – – – – – Dome system M1M3 mirror cell Coating chamber system Calibration spectrograph Base facility SPIE 2014 • Montreal, Quebec, Canada • June 22 nd - June 27th, 2014 7 LSST to be built on Cerro Pachón in Chile (chosen in 2006 & all use permits secured) Central Chile Location Map La Serena port Coquimbo La Serena airport LSST Base Facility Puclaro dam & tunnel Vicuña AURA property (Totoral) CTIO Gemini & SOAR N 0 10 20 km SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 LSST Summit Facility 8 Summit facility drawing package complete to support general contractor selection • ARCADIS A&E supported Chilean procurement – Bids received April 2014; vendor recommended – Planning for site mobilization in late 2014 SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 9 Facility layout driven by functional requirements & thermal considerations • Key features: – 16-m reinforced concrete pier – Tapered design with interior platforms – Vertical lift to support 65-ton M1M3 cart assembly – Cladding shaped to channel wind SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 10 Y X Z SST Ver 3.3 Baseline Design /2/2011 Compact 3-mirror optical system enables stiff design to achieve rapid cadence • LSST booth (#217) M2 Mirror Camera 3D Layout LSST Ver 3.3_Baseline_Design.zm Configuration 3 of M1M3 Primary Mirror Cross section through telescope and camera SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 11 Telescope Mount Assembly (TMA) in final stages of contract execution with vendor • Key elements: – – – – Hydrostatic bearing system, linear drive motor system (az/el) Coolant/utility lines, Camera cable wrap Capacitor bank system Surrogates (camera, M1M3, M1M3 cell, M2) SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 12 TMA design provides camera access and subsystem removal as assemblies SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 13 M1M3 optical polishing and final acceptance testing to be completed this year SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 14 M1M3 shipping container complete and local storage location identified Vacuum Pumps Lifter Frame Vacuum Cups Mirror Lifter Installed on LBT mirror LBT Mirror Container Loading SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 15 T&S group will procure M1M3 cell and fabricate support system hardware • Trial fit at TMA vendor; back to AZ for M1M3 testing Exploded View SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 16 T&S group will fabricate the M1M3 support system hardware for integrated testing Hardpoint Actuator Assembly Typical Dual Axis Actuator Assembly Fan On–Board Blower Assemblies (turquoise squares) B C Coolant Supply and Return Manifolds (copper) A F E D SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 Heat Exchanger Blower Assembly (telescope horizon pointing) 17 Integrated optical testing at SOML planned before shipment of M1M3 to summit • SOML provides integration support and facilities • Full active optics support demonstration and tuning of thermal control system M1M3 mirror with fully integrated mirror support system within the cell SOML Test Tower Configuration SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 Previous SOML Integration Efforts 18 M2 Cell Assembly to be fabricated/tested before shipment to summit • M2 substrate in near net shape (in turnover box) • Exelis to provide polishing and integrated optical testing in mirror cell (CX down orientation) SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 19 M2 Hexapod and Camera Hexapod/Rotator to be fabricated by Moog/CSA SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 20 Early efforts to determine final strut design and rotator bearing components SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 21 Dome system procurement planned for release in Fall 2014 • Key features: – – – – Oversized bi-parting aperture shutter Integrated light/wind screen, louvered vent system Rear access doors, overhead crane system Az drive system (crawl), capacitor bank system Aperture Shutters (ApS) Light/Wind Screen (LWS) Louvered Light Baffling Vents (LLBV) Rear Access Doors (RAD) SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 22 Coating chamber on summit provides enhanced aluminum via rotating magnetrons • Subsystem procurement in 2015 • M1M3 cell functions as lower vacuum vessel • M2 removed from cell for coating SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 23 Includes mirror strip/clean station and additional lower vessel to coat M2 SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 24 Base facility and data center designs driven by Operations plan and DM needs SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 25 T&S team responsible for calibration screen system within dome • Diffuse screen illuminated by tunable laser source – Two arrays of projectors overfill pupil – Measured output via NIST-calibrated photodiodes • Additional broadband collimated source SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 26 Kitt Peak Calypso 1.2-m telescope relocated to Tucson facility to enable refurbishment • Utilities and pier provided by summit facility vendor • Nasmyth ports used for spectrograph and SHWFS for alignment • PWV measurement (GPS/microwave radiometer ) and cloud monitoring via visible/IR all-sky (ASIVA) SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 27 Custom inner loop controller (ILC) electronics developed to provide common interface • ILCs intended for use with any actuator within TMA – – – – – – – M1M3 electromechanical hardpoints M1M3 pneumatic actuators M1M3 thermal control units M2 electromechanical axial actuators M2 electromechanical tangent links M2 tangent link strain gauges General protocol converter for non-standard serial digital devices SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 28 Software team to develop OCS/TCS software deliverables • Control architecture based on data distribution system using communications middleware • Scheduler prototyping via OpSim effort • Cadence workshop in August to engage community SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 29 Significant progress on curvature WFS code, guiding, and alignment strategies • Edge of FOV detectors provide wavefront/guider data • Major optical axes capture via laser tracker SMRs SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 30 Telescope system integration activities defined for initial 3-mirror testing • Repeat M3 optical test on TMA under full active control as zenith pointing (with PhaseCam) • Install integrating structure with SHWFS • Perform on-axis 3-mirror telescope alignment (diffraction limited on-axis by design) M3 Interferometer Shack-Hartmann WFS SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 31 The Telescope and Site plan is aligned with the overall Integrated Project Schedule Dome Complete Mount Complete Summit Complete 3-Mirror Testing Install Camera Science Verification Early Completion Start Early Commissioning with ComCam SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 32 Moving into construction will require help • LSST hiring campaign kick-off • T&S Tucson team almost doubles in size – Additional space within NOAO (offices/labs) – Office in La Serena established • Transition to Chile as major subsystems arrive and are integrated • T&S resources transition into Commissioning and eventually Operations The LSST Project is Ready for Construction SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 33 Thank you SPIE 2014 • Montreal, Quebec, Canada • June 22nd - June 27th, 2014 34