MGT 3110: Exam 3 Study Guide DO NOT RELY ONLY ON THIS STUDY GUIDE ALONETO PREAPRE FOR THE EXAM Discussion questions 1. Define independent and dependent demand items. 2. What is Master Production Schedule? 3. What is Bill of Materials? 4. What is Low-Level coding and what how is it used? 5. What are the benefits of MRP? 6. What are the inputs required for MRP? 7. What is “Lot Sizing” in MRP? 8. What are the reasons for using a lot sizing method other than Lot-for-lot? 9. What does the part-period balancing lot-sizing technique attempt to do in deciding the lot sizes? 10. Explain the terms flowtime and lateness. 11. What are the advantages and disadvantages of shortest processing time (SPT) rule? 12. What is the Critical Ratio? To what jobs does Critical Ratio give priority to? 13. What can be said about the jobs if CR < 1, or =1, or > 1? 14. What is input-output control? 15. Define maintenance. 16. Define reliability. 17. What is FR(%)? Define it. 18. Define FR(N). How is computed? 19. Define MTBF. How is related to FR(N)? 20. What is redundancy? 21. What is the impact on system reliability of adding parts or components in parallel? 22. Increasing the number of parts or components in a product tends to reduce its reliability. Why is this true only when adding components in series? 23. Explain carefully how redundancy improves product reliability. 24. What is breakdown maintenance? 25. Is there an optimal amount of preventive maintenance? What caution should be exercised before calculating this optimal amount? Problems 1. Consider the following Solver model for an aggregate planning problem. a. Determine the excel formula for the following cells: B18 B19 B20 B23 E23 F23 B24 B31 C31 F31 G31 H31 B32 B37 B38 B39 B40 B41 B42 B43 b. c. d. e. 2. What is the Solver Target cell? What are the Solver changing cells? What are the Solver constraints? What options of Solver must be checked? A Bill of Materials is desired for a bracket (A) that is made up of a base (B), two springs (C) and four clamps (D). The base is assembled from one clamp (D) and two housings (E). Each clamp has one handle (F) and one casting (G). Each housing has two bearings (H) and one shaft (I). a. Develop a product structure tree. b. The lead time for the parts are given below. Develop a time-phased product structure. c. The available inventory for each part is given in the table below. Determine the net requirement quantities of all parts required to assemble 50 units of bracket A. Item A B C D E F G Lead time 1 2 3 2 1 2 1 Available 5 5 10 20 50 150 50 H I 3. Lead time 1 3 2 4 On-hand 100 30 0 0 Scheduled receipts 50 in week 1 20 in week 1, 30 in week 2 50 in week 1 30 in week 1, 40 in week 3 For the following item the inventory holding cost is $0.80 per week and the setup cost is $300. Determine the lot sizes and total cost for this item under (i) Lot-for-Lot, (ii) EOQ, and (iii) PPB methods Item Week: Gross requirement Scheduled receipts Projected on-hand 100 Net Requirement Planned receipts Planned order releases 5. 5 0 A product (A) consists of a base (B) and a casting (C). The base consists of a plate (P) and three fasteners (F). The lead time, current on-hand inventory and scheduled receipts are given below. All components are lot for lot. The MPS requires start of production of 100 units of product A in week 4 and 150 in week 6. Produce the MRP for the upcoming six weeks. Produce a list of all planned order releases. Part B C P F 4. 1 2 LT = 1 100 1 2 250 3 200 4 150 5 250 6 200 7 200 8 150 Consider the following planned and actual hours of input and output. Week ending Planned input Actual input Planned output Actual output 1 2 3 4 5 6 7 8 500 700 650 600 800 700 650 700 700 700 650 800 600 800 650 700 600 600 650 650 800 500 700 500 700 500 700 600 800 800 700 800 Prepare the Input/Output Control chart for this workstation. Assume an initial actual backlog of 120 hours. 6. A company wishes to assign a set of jobs to a set of machines. The following table provides data on the profit margin of each job when performed on a specific machine. Setup an Excel Solver model to determine the set of assignments that maximizes production value. a. Fill out the Excel formulas for the following cells: G13 G14 G15 G16 C17 D17 E17 F17 G19 b. c. d. e. What is the Solver Target cell? What are the Solver changing cells? What are the Solver constraints? What options of Solver must be checked? 7. The following jobs are waiting to be processed on day 250 Job A B C D E F Date Job received 215 220 225 240 245 250 Production days needed 30 20 40 50 20 35 Date job due 290 415 375 315 420 380 Sequence the jobs in the order of SPT, EDD, and Critical Ratio, and compute (i) Average flow time, (ii) Average lateness, (iii) Average no. of jobs in the system, and (iv) Utilization, for each of the three schedule of jobs. 8. A control rod mechanism is a nuclear reactor has 15 critical components with an average reliability of 99.5% for each component. Determine the overall reliability of the mechanism. 9. Determine the system reliability for the following systems. (a) R = 90% R = 98% R = 92% R = 90% R = 90% R = 98% (b) R = 99% R = 98% R = 95% R = 90% R = 94% R = 95% R = 90% R = 94% R = 95% R = 90% R = 94% R = 95% 10. Fifty components of a safety system were tested for reliability, each for 200 hours of operation. Of the 50, 2 failed after 50 hours of operation, 3 after 75 hours, 1 after 120 hours, and 1 after 150 hours. The rest of the components did not fail. Determine the following failure rate statistics. a. b. c. d. 11. Percentage of failures. Number of failures per unit-hour of operation. Mean time between failures. What is the expected number of failures over 1000 hours of operation? In a mining operation an electoral exhaust system is used to pump out the fumes. The break down data over the past 200 weeks is shown in the table below. Each time the system breaks down the mining operation must be shut down. The estimated cost to repair the system and the lost production amounted to $12,000. Routine maintenance service for the exhaust system may be purchased at a cost of $6,000 per week. With this contract the number of breakdowns is expected to average only 1.2 per week. Then, the cost to bring the system back on line is $5,000 in lost production. Determine whether it is economical to purchase the preventive maintenance contract. No. of breakdowns No. of weeks that many breakdowns occurred (Frequency) 0 75 1 35 2 50 3 20 4 10 5 10 Answers to discussion questions 1. Define independent and dependent demand items. Finished products whose demand is independent of production decisions are called “Independent demand” items. Items for which demand can be directly calculated from production decisions are called “Dependent demand” items. These are raw-materials and parts required for the production of the finished goods. 2. What is Master Production Schedule? Master Production Schedule specifies production quantities of each Independent Demand item for a planning horizon of 12 to 15 weeks. Total of MPS quantities must be in accordance with the aggregate production plan. 3. What is Bill of Materials? Bill of materials is structured list of components, ingredients, and materials needed to make an end product. Items needed to produce a given part are called components or “children”. The part into which the components go us called “Parent”. The BOM also gives the number of units of a child item needed to produce one unit of the parent item. 4. What is Low-Level coding and what how is it used? A level code starting from zero at the top of the BOM tree and incremented by 1 going down each level of the BOM tree is assigned. Then, the lowest level at which an item appears is called Low-Level code. The MRP computations are processed one level at a time, starting from level zero. 5. What are the benefits of MRP? Better response to customer orders Faster response to market changes Improved utilization of facilities and labor Reduced inventory levels 6. What are the inputs required for MRP? Master Production Schedule Bill of Materials Inventory status 7. What is “Lot Sizing” in MRP? The process of combining net requirements into production lots is called lot sizing. 8. What are the reasons for using a lot sizing method other than Lot-for-lot? Lot-for-lot often requires too many lots that may not be economically justifiable Sometime lot-for-lot generates absurdly small lots 9. What does the part-period balancing lot-sizing technique attempt to do in deciding the lot sizes? It balances the setup and holding costs. PPB uses additional information by changing the lot size to reflect requirements of the next lot size in the future. 10. Explain the terms flowtime and lateness. Flow time is the length of time a job is in the system; lateness is completion time minus due date. 11. What are the advantages and disadvantages of shortest processing time (SPT) rule? SPT minimizes the average flow time, average lateness, and average number of jobs in the system. It maximizes the number of jobs completed at any point. The disadvantage is that long jobs are pushed back in the schedule. 12. What is the Critical Ratio? To what jobs does Critical Ratio give priority to? The Critical Ratio (CR) is an index number computed by diving the time until due date by the working time remaining. The CR gives priority to jobs that must be done to keep shipping on schedule. 13. What can be said about the jobs if CR < 1, or =1, or > 1? If CR < 1, then the job has fallen behind, the work remaining exceeds the time until due date. If CR = 1, then the job is on schedule, the work remaining exactly equals the time until due date. If CR > 1, then there is slack, the time until due date exceeds the work remaining. 14. What is input-output control? Input/output control keeps track of planned versus actual inputs and outputs, highlighting deviations and indicating bottlenecks using cumulative backlog. 15. Define maintenance. Maintenance consists of all activities involved in keeping a system's equipment in working order. 16. Define reliability. Reliability is the probability that a machine part or product will function properly for a specified time under stated conditions. 17. What is FR(%)? Define it. FR(%) refers to product failure rate. It measures the percent of failures among the total number of products tested. 18. Define FR(N). How is computed? FR(N) refers to the number of failures during a period of time. It measures the number of failures over the total unit-hours the products operated without failing. it is the ratio of failed units to total operating hours. 19. Define MTBF. How is related to FR(N)? MTBF stands for Mean time between failures. It is the expected time between a repair and the next failure of a component, machine, process, or product. MTBF is the reciprocal of FR(N) 20. What is redundancy? Redundancy is the use of a component in parallel to raise reliabilities. 21. What is the impact on system reliability of adding parts or components in parallel? This will increase the reliability of the system by introducing redundancy. 22. Increasing the number of parts or components in a product tends to reduce its reliability. Why is this true only when adding components in series? Adding parts in series involves an additional multiplication by a value less than one, so that reliability must fall. Adding parts in parallel (the redundancy concept) increases reliability because only one part of the parallel system must function. 23. Explain carefully how redundancy improves product reliability. A redundant part or component is connected in parallel with the primary part or component. "In parallel" means that either the original part or its backup needs to work, not that both must work at the same time. Redundancy increases reliability by providing an additional path (through the redundant part) to provide system reliability. 24. What is breakdown maintenance? Breakdown maintenance is the remedial maintenance that occurs when equipment fails and must be repaired on an emergency or priority basis. 25. Is there an optimal amount of preventive maintenance? What caution should be exercised before calculating this optimal amount? Too little preventive maintenance causes breakdown costs to rise sharply, adding more to cost than is saved by less preventive maintenance; too much preventive maintenance reduces breakdowns, but by an amount insufficient to offset the added cost of preventive maintenance. Operations managers should assure that all costs of breakdowns have been properly included in the calculations. There is a history of not including indirect and subjective breakdown cost elements, which leads to performing too little preventive maintenance. Answers to problems 1. B18 B19 B20 B23 E23 F23 B24 B31 C31 F31 G31 H31 B32 B37 B38 B39 B40 B41 B42 B43 =B14/B13 =B14*B5 =B13*B6 =E13 =B23+C23-D23 =E23*F6*$B$18 =E23 =E14 =F23 =E6 =B31+SUM(C31:E31)-F31 =C31*$B$15 =G31 =SUMPRODUCT(E23:E26,F6:F9)*B19 =D35*B20 =E35*B7 =C27*B9 =D27*B10 =G35*B8 =SUM(B37:B42) b. B43 c. C23:D26, D31:E34 d. D31:D34 <= H31:H34 G31:G34 >= E15 C23:D26 = Integer (if needed) D31:E34 = Integer (if needed) e. Assume linear model Assume non-negative 2. A B C2 F D4 E2 D1 G H2 I F G F D G B H E I C A F D G 1 2 3 4 5 Lead time = 7 weeks Part A B C D E F G H I Gross 50 1 x A = 45 2 x A = 2 x 45 = 90 4 x A + 1 x B = 4 x 45 + 40 = 220 2 x B = 80 1 x D = 200 1 x D = 200 2 x E = 2 x 30 = 60 1 x E = 30 Available 5 5 10 20 50 150 50 5 0 Net 50 – 5 = 45 45 – 5 = 40 90 – 10 = 80 220 – 20 = 200 80 – 50 = 30 200 – 150 = 50 200 – 50 = 150 60 – 5 = 55 30 – 0 = 30 6 7 3. A has releases of 100 in 4, 150 in 7; B has a release of 150 in 6, but on hand inventory accounted for all other needs; C has releases of 150 in 4, 70 in 1; P has a release of 150 in 5 and F has a release of 450 in 5 (the beginning inventory of B leads to no other gross requirements of P or F). 1 2 3 1 0 50 100 0 0 2 0 3 0 150 0 0 150 0 0 MPS start for A Item B Item C Week: Gross requirement Scheduled receipts Projected on-hand 30 Planned receipts Planned order releases Item F Week Gross requirement Scheduled receipts Projected on-hand Planned receipts Planned order releases 5 6 150 4 100 5 0 6 150 150 0 0 50 0 100 50 100 0 Lead time = Week: Gross requirement Scheduled receipts Projected on-hand 100 Planned receipts Planned order releases Item P Week: Gross requirement Scheduled receipts Projected on-hand Planned receipts Planned order releases 4 100 0 0 1 0 20 30 0 20 1 0 50 0 0 0 1 0 30 0 0 230 2 0 30 50 0 0 Lead time = 3 0 4 100 5 0 6 150 80 0 150 80 20 0 0 0 0 0 150 0 4 0 5 100 6 0 50 0 0 50 50 0 0 0 0 4 0 5 300 6 0 70 0 0 70 230 0 0 0 0 Lead time = 3 0 2 0 50 0 0 50 0 50 Lead time = 3 0 40 30 30 0 0 0 0 2 0 1 3 2 4 4. (i) L-4-L Item Week: Gross requirement Scheduled receipts Projected on-hand Net Requirement Planned receipts Planned order releases LT = 1 100 1 2 250 3 200 4 150 5 250 6 200 7 200 8 150 100 0 0 250 0 250 250 200 0 200 200 150 0 150 150 250 0 250 250 200 0 200 200 200 0 200 200 150 0 150 150 0 5 250 0 150 100 375 0 6 200 0 275 0 0 375 7 200 0 75 125 375 0 8 150 0 250 0 0 0 100 No. of setup = Carrying cost = Setup cost = 7 x $300 = Total cost = 7 0 2100 2100 (ii) EOQ: Total demand for 8 weeks = 1500 D (1 year) = (1500/8) x 52 weeks/year = 9750 H (for 52 weeks) = $0.80/week x 52 weeks = $41.60 S = 300 Q=√ 2(9750)300 41.6 = 375 Item Week: Gross requirement Scheduled receipts Projected on-hand Net Requirement Planned receipts Planned order releases 100 LT = 1 100 0 100 0 0 375 1 2 250 0 0 250 375 375 3 200 0 125 75 375 0 4 150 0 300 0 0 375 Annual setup cost = (D/Q) S = (9750/375) x 300 = Annual holding cost = (Q/2)H per year = (375/2) x 41.60 = Annual cost = Annual setup cost + Annual holding cost = 7800 + 7800 = Weekly cost = Annual cost/52 = 15600/52 = Cost for 8 weeks = Cost per week x 8 weeks = 300 x 8 = (iii) PPB EPP = 300/0.80 = 375 7800 7800 15600 300 2400 Item Week: Gross requirement Scheduled receipts Projected on-hand Net Requirement Planned receipts Planned order releases 100 LT = 1 100 0 100 0 0 600 Periods Quantities combined combined Lot #1 Receipt in week #2 1 2 250 0 0 250 600 3 200 0 350 4 150 0 150 5 250 0 0 250 450 6 200 0 200 7 200 0 0 200 8 150 0 450 Periods brought forward – last qty New Partperiods Total combined partperiods 250 250 + 200 = 450 0 1 0 1x 200 = 200 2, 3, 4 450 + 150 = 550 Lot #2 Receipt in week #5 5 250 2 2 x 150 = 300 0 0 + 200 = 200 200 + 300 = 500 (Close to 375) 0 0 5, 6 250 + 200 = 450 5, 6, 7 450 + 200 = 650 Lot #3 Receipt in week #7 7 200 7, 8 200 + 150 = 350 1 2 1 x 200 = 200 2 x 200 = 400 0 0 + 200 = 200 (Close to 375) 200 + 400 = 600 0 1 0 1x 150 = 150 0 0 + 150 = 150 2 2, 3 Summary: Lot # in Week Lot PP Setup cost = 3 setups x $300 = $900 Total Lot PP = 850 500 Total holding cost = 850 x $0.80 = $680 200 Total cost = 900 + 680 = $1,580 150 Lot size Lot #1 Receipt in week #2 550 Lot #2 Receipt in week #5 450 Lot #3 Receipt in week #7 350 Total cost = 700 + 460 + 420 = $1,580 #5. Week ending Planned input Actual input Cumulative deviation Planned output Actual output Cumulative deviation Backlog 120 1 2 3 4 5 6 7 8 500 700 200 650 600 -50 220 800 700 100 650 700 0 220 700 700 100 650 800 150 120 600 800 300 650 700 200 220 600 600 300 650 650 200 170 800 500 0 700 500 0 170 700 500 -200 700 600 -100 70 800 800 -200 700 800 0 70 #6. G13 =SUM(C13:F13) G14 =SUM(C14:F14) G15 =SUM(C15:F15) G16 =SUM(C16:F16) C17 =SUM(C13:C16) D17 =SUM(D13:D16) E17 =SUM(E13:E16) F17 =SUM(F13:F16) G19 =SUMPRODUCT(C5:F8,C13:F16) Solver parameters Set Target Cell Options: G19 MAX Changing cells C13:F16 Constraints G13:G17 <= 1 C17:F17 = 1 □ Assume linear model □ Assume non-negative #7. SPT Job B E A F C D Processing time (Days) 20 20 30 35 40 50 195 Average flow time = Average lateness = Average WIP = Utilization = 95.833 30 2.949 0.339 Days till due date 165 170 40 130 125 65 Completion time (Flowtime) 20 40 70 105 145 195 Lateness 0 0 30 0 20 130 575 180 EDD Job A D C F B E Processing time (Days) 30 50 40 35 20 20 195 Days till due date 40 65 125 130 165 170 Average flow time = Average lateness = Average no. of jobs in the system = Utilization = Completion time (Flowtime) 30 80 120 155 175 195 755 Lateness 0 15 0 25 10 25 75 125.83 12.50 3.87 0.26 CR Job D A C F B E Processing time (Days) 50 30 40 35 20 20 195 Days till due date 65 40 125 130 165 170 Average flow time = Average lateness = Average no. of jobs in the system = Utilization = Completion time (Flowtime) 50 80 120 155 175 195 775 Lateness 0 40 0 25 10 25 100 CR 1.30 1.33 3.13 3.71 8.25 8.50 129.17 16.67 3.97 0.25 #8. 0.99515 = 0.9257569 or 92.7569% #9. (a) RRow 1= 0.98 x 0.92 x {1 – (1-.9) (1-.9) (1-.9)} = 0.900698 RRow 2 = 0.98 x 0.92 x 0.98 x 0.95 = 0.903256 RS = 1 – (1 - RRow 1)( 1 - RRow 2) = 1 – (1 – 0.900698)(1 – 0.903256) = 0.990393, or 99.0393% (b) R1 = 1 – (1 – 0.95) (1 – 0.95) (1 – 0.95) = 0.999875 R2 = 1 – (1 – 0.90) (1 – 0.90) (1 – 0.90) = 0.999 R3 = 1 – (1 – 0.94) (1 – 0.94) (1 – 0.94) = 0.998659 Rs = R1 x R2 x R3 = .998659 = 99.8659% #10. (a) Failed = FR(%) = Total tested unit-hours = Failed 2 3 1 1 (b) (c) (d) 7 14.0% 10000 Operating Non-operating time time/unit 50 150 75 125 120 80 150 50 Total non-operating time = Operating time = 10000 – 805 = Non-operating time 300 375 80 50 805 9195 7/9195 = 0.000761283 1/0.000761283 = 1313.57 1000* 0.000761283 = 0.761283306 #11. No. of breakdowns 0 1 2 3 4 5 No. of weeks that many breakdowns occurred (Frequency) 75 35 50 20 10 10 200 Expected number of failures/week = Average breakdown with routine maintenance = Repair cost/breakdown without routine maintenance = Routine maintenance cost/week = Repair cost/breakdown with routine maintenance = Cost without routine maintenance/week = 1.425 x $12,000 = Cost with routine maintenance/week = 6000 + 5000 x 1.2 = Relative frequency Expected breakdowns 0.375 0.000 0.175 0.175 0.250 0.500 0.100 0.300 0.050 0.200 0.050 1.000 0.250 1.425 1.425 1.2 12000 6000 5000 $17,100 $13,200 Total cost/week with routine maintenance is less expensive compared to without it. Therefore, purchase routine maintenance contract.