Cost Approach
The Cost Approach is most useful when:
Property is unique
Property is reasonably new and the improvements represent the highest and best use of the site
Cost Approach
Value equals value of land plus value of improvements
Improvements value equals reproduction cost new less loss in value because of depreciation caused by age, wear and tear, and functional and external problems
Value must be adjusted for interests other than fee simple
Cost New
Reproduction cost
Best for new or nearly new improvements that represent contemporary construction methods
Replacement cost
Eliminates most forms of functional obsolescence
Reproduction cost and replacement cost may differ for older buildings.
Cost New
Types of costs
Direct
Indirect
Entrepreneurial profit
Methods of Estimating Costs
1.
Comparative unit method
2.
Segregated cost method
3.
Unit in place method
4.
Quantity survey method
Comparative unit method
Cost estimate derived from lump-sum unit cost base on either the square footage or the cubic footage
Construction classification
Type
Quality
Find unit cost for similar structures
Adjust for possible differences in mechanical systems, size, loading docks and so forth.
Multiply modified unit cost by the actual size of the subject structure
Comparative unit cost example
Gross building area
Construction type
Bearing walls quality
Number of stories
Number of elevators
Base building cost/sqft
Plus HVAC adjustment
Plus sprinkler adjustment
Adjusted unit cost
Story height multiplier
Perimeter multiplier
Adjusted unit cost
Building cost ($65.40 x 24,000 sqft)
Elevator
Reproduction cost new
24,000 sqft
Masonry load
Good
2
1
$64
$1.04
$2.06
$67.10 x1.030
x0.947
$65.45
$1,570,800
55,000
$1,625,800
Segregated cost method
Cost of each structural component is estimated separately and summed to derive cost of total building
Often used when
The comparative unit method is difficult to apply because of an unusual design or mix of components
Lack of unit cost data
All components in the building do not represent the same level of quality
Segregated cost example
Item
Site preparation
Foundation
Frame
Floor structure - 1st floor
Floor structure - 2nd floor
Floor cover - carpet
Ceiling
Interior partitions
Sprinkler
Plumbing
HVAC
Electrical/lighting
Exterior wall
Roof structure
Roof cover
Elevator
Total
Size, sqft Unit cost per sqft Cost
12,000
24,000
24,000
$0.67
$2.57
$8,040
$61,680
$5.47 $131,280
12,000
12,000
24,000
24,000
24,000
24,000
24,000
$3.31
$3.70
$39,720
$9.88 $118,560
$88,800
$6.20 $148,800
$15.78 $378,720
$2.06 $49,440
$3.40 $81,600
24,000
24,000
12,480
12,000
12,000
24,000
$4.45 $106,800
$4.51 $108,240
$12.77 $159,370
$6.07 $72,840
$1.85 $22,200
$2.30 $55,200
$1,631,290
Unit in place method
Costs of structural components are summed to derive cost of total building
An allowance for contractor’s profit and overhead are built into the unit costs used
Quantity survey method
Cost of each item is identified and estimated separately, then summed
Adjustments for hours of labor, overhead and profit are added
Most accurate method
Is seldom used for the following reasons:
Time consuming
Some construction materials may not be readily visible
May be used to estimate the value of unusual components if they exist in a structure
Sources of cost information
Professional cost estimating companies
Actual costs of newly completed buildings
Contractor’s estimates
Appraiser’s files
Methods of Estimating
Depreciation
1.
Age life method
2.
Breakdown method
3.
Market extraction method
Age life method
Effective age
Total economic life
Remaining economic life
Modified age-life method
Deferred maintenance
Age-Life method example
Reproduction cost new (30,000 sqft@$19/sqft)
Total economic life
Remaining economic life
Effective age
Depreciation %: 10/40 (25%)
Depreciation value of improvements
Contributing value of site improvements
Land value
Total value
40 years
30 years
10 years
$570,000
($142,500)
$427,500
$15,000
$65,000
$507,500
Breakdown method
Physical curable depreciation
Measured as cost to cure
Physical incurable depreciation
Short-lived
Measured individually as the effective age/economic life x replacement (or reproduction) cost and summed
Long-lived
Measured as replacement cost new minus deferred maintenance and short-lived items multiplied by the effective age/economic life.
Breakdown method: Identify component cost
Excavation and site preparation
Frame
Floor structure
Floor cover, office
Ceiling, office
Partitions, office
Sprinkler
HVAC warehouse
HVAC, office
Plumbing
Electrical
Exterior wall
Roof cover
Roof structure
Total
$9,600
97,500
67,200
3,850
13,500
36,000
40,500
21,950
11,700
47,200
53,000
93,000
25,000
40,000
$560,000
Breakdown method:
Deferred Maintenance
Roof leak
Space heaters
Total
Cost New
$25,000
Replacement cost to cure Remainder
$3,500 $21,500
$21,950 $23,500
$27,000
0
Breakdown method: Physical incurable depreciation – Shortlived items
Roof cover
Floor cover
Ceiling
HVAC, office
Plumbing fixtures
Replacement cost
$21,500
$3,850
$13,500
$11,700
$6,500
Electrical fixtures
Total
$14,300
$71,350
Economic age
10
2
10
10
10
8
Effective life % Depreciation Depreciation
15 67 $14,405
8
20
25
50
$962
$6,750
15
20
15
67
50
53
$7,839
$3,250
$7,579
$40,785
Breakdown method: Physical incurable depreciation – Longlived items
Replacement cost new
Less Deferred maintenance
Less Incurable short-lived items
Total short-lived items
Effective age
Remaining useful life
Deprciation percentage
$27,000
$75,350
$560,000
-102,350
$457,650
8 years
42 years
16% $73,224
Breakdown method
Curable functional obsolescence
Superadequacy
Deficiency
Measured as the difference between the cost to add the item today minus the cost to add the component originally
Must be less than the value added by adding or modifying the existing structure
If the deficiency results in the replacement of an existing item, any remaining value attributed to the item at this point must also be deducted
Breakdown method:
Curable functional obsolescence
Deficiency:
Installation of truck-height loading dock
Original cost of installation
Loss in value
$4,500
-2,500
$2,000
Breakdown method
Incurable functional obsolescence
Deficiency
Superadequacy — measured as
The extra cost of construction minus physical depreciation
The income difference between the level needed to support the superadequacy and current functional income levels capitalized by the overall capitalization rate
Incurable functional obsolescence
Method 1: Excess cost adjustment
Incurable Functional Obsolescence: Superadequacy
Exterior wall (added cost)
Less depreciation taken
Depreciation
$40,000
-6,400
$33,600
Incurable functional obsolescence
Method 2: Rent loss
Incurable Functional Obsolescence: Superadequacy
Rent needed to support masonry construction $2.10 per sqft
Market rent
Rent difference
-1.95 per sqft
$0.15 per sqft
Incurable functional obsolescence
Method 2: Rent loss (continued)…
Note that in the previous example the operating expenses do not change, but the management fee is reduced by 3% of the difference. Net loss per year is [0.15(1-.03)]=$0.1455 per sqft or
$4,365 per year. Assuming a cap rate of 10.5, this results in a loss in value of $41,571.
Value loss
Less depreciation taken
Depreciation
$41,571
-6,400
$35,171
Breakdown method
External obsolescence
Economic
Locational
Measured as the present value of the
NOI lost
External obsolescence:
Locational
Market rent
Current rent
Rent difference
$1.95 per sqft
-1.75 per sqft
$0.20 per sqft
Note: operating expenses are identical but management fee is reduced by
3% of the difference. The net loss is [.20(1-.03)]=$0.194 per sqft or $5,820 per year. Assuming an overall cap rate of 10.5, this results in a loss in value of
$55,429. The value represents total loss in property value. Since the land contributes to 20% of total value, the portion of the loss in value that can be attributed to the improvements is $55,429 x .80 = $44,343.
Depreciation summary
Physical Deterioration
Curable, deferred maintenance
Incurable, short-lived items
Incurable, long-term items
Total
Functional obsolescence
Curable
Incurable
Total
External obsolescence
Total accrued depreciation
$27,000
$42,905
$73,224
$143,129
$2,000
$33,600
$35,600
$44,343
$223,072
Summary of Final Value
Estimate
Reproduction cost new
Less accrued depreciation
Depreciated value of improvements
Plus contributing value of improvements
Plus land value
Fee simple value indication
$560,000
-223,072
$336,928
$15,000
$65,000
$416,928
Market extraction method
Percentage loss is extracted from market sale of similar properties
Comparable sales must be available
Difficult to apply if comparable and subject vary significantly in age, quality and/or condition
Assumes same market forces affect comparable and subject
Market extraction method example
Sales price
Less land value
Less contributing value of site improvements
Depreciated value of the improvements
$1,400,000
-300,000
-50,000
$1,050,000
Depreciated %
1
Depreciation value of improvements
Cost new of improvements