Earned Value Project Management ---A Tutorial--PART II - Implementation with Primavera presented by Don McNatty D. R. McNatty & Associates Agenda Basis of EV and Performance Reporting in P3 and SureTrak Methods for capturing and storing data Methods for calculating and applying CPI and SPI Example Reports and how they are created Basis of EV and Performance Reporting in P3 and SureTrak Stores current period and to-date P3 can calculate BCWP/BCWS on target 1 EV Pct is Input - basis and calculation come from out side P3 except for LOE ETC/EAC can be calculated with Global Change Methods for capturing and storing data Hammocks to store “non-schedule” scope Custom data items to store past period data and report “trends” Target 2 (or 1) to capture “performance baseline” Must use a “performance baseline” when the “Approved Baseline” doesn’t reflect scope. Code Fields to store alpa/numeric data USING HAMMOCKS TO CAPTURE SUMMARY ACTUALS A100 Resource B A100-01 Resource A C D A100-02 Resource A C D A100-03 Resource ETC (B+D) EAC 0 0 340 0 100 0 0 250 0 63 187 187 0 150 0 0 150 150 33 500 340 163 337 677 A B BUDGET ACTUAL 37 0 340 A100-01 100 100 A100-02 25 A100-03 TOTAL Resource A100 Pct C D EARNED A C D Method Import Actuals Status Pct Status Pct, GC ETC Roll-up on Code Value Methods for calculating and applying CPI/SPI Linked spreadsheets to document earned value calculations Set the autocost rules to preserve, not destroy Global Change to calculate and store CPI/SPI Global Change to calculate EAC and ETC based on performance Arithmetic window in custom reports Example reports and how they are created Graphs based on P3 Reports P3 Standard Reports SureTrak Standard Reports P3 Custom Reports P3 Graphics SureTrak Graphics Graphs based on P3 reports Bubble Reports Deliverables Performance Cost Status by Category Design Support Services Perfomance Performance Summary by Discipline Discipline Progress toward milestone PROJECT STATUS REPORT (EARNED VALUE) EARNED VALUE - MAN HOURS PROBLEM OK (at present) CONCERN COMPLETE EARNED VALUE - COST PROJECT TIME REMAINING AT COMPL PERFORMANCE D0301 XXXXXXXXXXXXXXX STATION & TUNNELS PAGE 1 D0321 BIG CITY STATION D0322 PEDESTRIAN UNDERPASS @ STATION COMPLETED LATE AND OVER BUDGET D0326 CITY ROAD/RESTORATION/LANDSCAPE D0352 N. XXXXXXXXXXX SITEWORK D1610 TRACKWORK INSTALLATION V620 AUTOMATIC TRAIN CONTROL (D.F.I.) V710 ESCALATORS/ELEVATORS -------------------------------------------------------------------------------------------------------------------------D. R. McNatty & Associates PRIMAVERA PROJECT PLANNER SAMPLE PROJECT USING EARNED REPORT DATE 10AUG97 RUN NO. 1359 XXXXXXXXXXXX TRANSPORTATION AUTHORITY START DATE 01JUN92 FIN DAT 15:26 RW-G1 BUBBLE CHART - PERF DATA DATE 31MAY97 PAGE NO -------------------------------------------------------------------------------------------------------------------------ACTIVITY DESCRIPTION TOTAL PCT HOURS COST MHOUR COST TIME ID FLOAT COMPL CPI CPI PERF PERF LEFT ---------- ------------------------------------------------ ----- ----- - ------ ------ - -------- - -------- - -------- C0301 D0301 XXXXXXXXXXXXXXXXXX STATION-TUNNELS -12 60 % 1.00 1.06 | GREEN | GREEN | RED | C0321 D0321 BIG CITY STATION 0 61 % 0.96 0.96 | YELLOW | YELLOW | GREEN | C0322 D0322 PEDESTRIAN UNDERPASS @ STA. 100 % 0.45 0.51 | RED | RED | BLUE | C0326 D0326 CITY ROAD/RESTORATION/LANDSCAPE 0 0 % 0.00 0.00 | | | GREEN | C0352 D0352 N. XXXXXXXXX SITEWORK 0 0 % 0.00 0.00 | | | GREEN | C1610 D1610 TRACKWORK INSTALLATION 0 10 % 0.69 0.74 | RED | RED | GREEN | Graphic report based on P3 Custom Report Data Activity description Budgeted Cost Cost to Date Cost to Complete Cost Variance + 11F FACILITIES 8,893,420 6,994,104 1,899,357 -41 4,398,210 2,468,304 2,578,946 -649,040 2,593,503 2,276,535 299,493 17,475 935,329 886,000 339,148 -289,819 3,398,849 3,643,019 0 -244,170 354,740 211,898 314,369 -171,527 6,951,189 5,220,677 1,366,304 364,208 + 12S SYSTEMS GRAPH DATA BASED ON P3 LAYOUT + 15C PROJECT CONTROL + 16A PROJECT ADMINISTRATION + 2SD SECTION DESIGNER + 3SS SPECIALTY SUB CONSULTANT + 4OD OTHER DIRECT COSTS $ 9 ,0 0 0 $ 8 ,0 0 0 Project Start Project Finish 06/01/92 06/30/00 NF75 Data Date 05/31/97 Run Date 08/10/97 © Primavera Systems, Inc. Sheet 1 of 1 Date D. R. McNatty & Associates Reision Checked Approved C:\P3WIN\P3OUT\COST $ 7 ,0 0 0 $ 6 ,0 0 0 $ 5 ,0 0 0 $ 4 ,0 0 0 $ 3 ,0 0 0 $ 2 ,0 0 0 $ 1 ,0 0 0 $0 F a c i l i ti e s PAGE 3 S ys te m s P ro j C o n tr o l P ro j Ad m in Se c D e si g n e r C o st C a te g o r y S p e c i a l i ty O D C 's PAGE 4 14000 12000 10000 Hours by Function 8000 6000 4000 2000 0 Log-ins Shop Dwgs Rfi's Changes As-Builts Budget 1400 6236 13070 6394 3594 To Date 500 0 13126 4547 30 Performance/Utilization by Function 120 100 80 60 40 20 0 Const Time Log-ins Shop Dwgs Rfi's Changes As-Builts Total Budget 100 100 100 100 100 100 100 To Date 34 36 0 101 71 1 59 P3 Custom Report --------------------------------------------------------------------------------------------------------------------Report: RW-C3 XXXXX XXXXXX SEGX - NORTH XXXXXXXXXX EXTENSION REPORT DATE 11AUG97 Project Name: NF75 DATA DATE 31MAY97 DESIGN SERVICES DURING CONSTRUCTION PAGE NO. 1 --------------------------------------------------------------------------------------------------------------------| LOG INS | SHOP DRWGS | RFI Etc. | CHANGE NOTICE | AS BUILTS | TO TAL º CONTRACT | | | | | | º | Budget Actual | Budget Actual | Budget Actual | Budget Actual | Budget Actal | Budget Actual º ------------------- - ------ ------ - ------ ------ - ------ ------ - ------ ------ - ------ ------ - ------ ------ ARCHITECTURAL 0 20 0 0 2280 1421 1215 473 0 0 3495 1914 CIVIL 600 430 0 0 2164 89 1131 363 0 0 3895 882 ELECTRICAL 0 0 0 0 2462 1436 1186 1259 0 0 3648 2695 FACILITIES-GENERAL 800 50 6236 0 0 0 0 0 0 0 7036 50 MECHANICAL 0 0 0 0 2240 1349 1090 649 0 0 3330 1998 SYSTEMWIDE INTERFACE 0 0 0 0 496 1 0 0 3594 30 4090 31 STRUCTURAL 0 0 0 0 2528 8313 1222 1431 0 0 3750 9744 TRACK WORK 0 0 0 0 100 0 50 0 0 0 150 0 UTILITIES 0 0 0 0 800 517 500 337 0 0 1300 854 = ====== ====== = ====== ====== = ====== ====== = ====== ====== = ====== ====== = ====== ====== = 1400 500 6236 0 13070 13126 6394 4547 3594 30 30694 181378 Performance Summary by Contract Unit Based on data from P3 report G3 J900 PAGE 6 J800 H7002 H700 Earned D600 Actual D500 Planned D400 C300 A200 A100 0 20 40 60 80 Percent Complete 100 120 Performance Summary by Contract Unit (Report G3) ----------------------------------------------------------------------------------------------------------------------------------------------------------------------------D. R. McNatty & Associates PRIMAVERA PROJECT PLASAMPLE PROJECT USING EARNED VALUE REPORT DATE 10AUG97 RUN NO. 1360 XXXXXXXXXXXXXXXXXXXXXXXXXXXXX AUTHORITY 01JUN92 FIN DATE 30JUN00 16:44 RW-G3 PERF SUMMARY BY CONTRACT DATA DATE 31MAY97 PAGE NO. 1 ----------------------------------------------------------------------------------------------------------------------------------------------------------------------------DESCRIPTION EARLY EARLY BUDGET SCHEDULED PLANNED EARNED EARNED HOURS PCT HRS HOURS AT HRS AT START FINISH HOURS HOURS HRS PCT HOURS HRS PCT & TO DATE TO DATE & COMPLETION CMP PCT ------------------------------------------------ -------- -------- ---------- ---------- ---------- - ---------- ---------- - ---------- ---------- - ---------- ---------- FACILITIES D0301 D0321 D0326 D0352 D1610 V710 V740 V000 V000 POLLYWOOD/LOWLAND STATION-TUNNELS ORANGE CITY STATION ORANGE CITY ROAD/RESTORATION/LANDSCAPE POLYLWOOD SITEWORK TRACKWORK INSTALLATION ESCALATORS/ELEVATORS VENTILATION EQUIPMENT ENGINEERING SUPPORT FACILITIES DIVISION 01JAN93A 01SEP92A 02JUN97 13JAN95 24JUN96A 19MAY97A 03MAR97A 01JUL92A 01JUL94A -------01JUL92A 19JUL99 20104 14062 69.95 % 17246 85.78 % 18511 92.08 % 24673 122.73 % 31MAY00 49388 40609 82.22 % 42507 86.07 % 49449 100.12 % 60443 122.38 % 04JUN99 967 0 0.00 % 0 0.00 % 0 0.00 % 0 0.00 % 05MAY99 560 0 0.00 % 0 0.00 % 0 0.00 % 560 100.00 % 30JUN00 2432 1094 44.98 % 1120 46.05 % 1614 66.37 % 4922 202.38 % 03JAN00 686 7 1.02 % 0 0.00 % 1 0.15 % 875 127.55 % 30DEC99 130 5 3.85 % 0 0.00 % 35 26.92 % 500 384.62 % 30JUN98 8768 6833 77.93 % 6990 79.72 % 2818 32.14 % 4578 52.21 % 30JUN00 53440 38114 71.32 % 37855 70.84 % 37563 70.29 % 43977 82.29 % -------- ---------- ---------- ---------- - ---------- ---------- - ---------- ---------- - ---------- ---------- 30JUN00 136475 100724 73.80 % 105718 77.46 % 109991 80.59 % 140528 102.97 % 05FEB96A 01JUL92A -------01JUL92A 20JUN00 9901 672 6.79 % 672 6.79 % 627 6.33 % 9848 99.46 % 30JUN00 57701 35581 61.66 % 35581 61.66 % 39624 68.67 % 66986 116.09 % -------- ---------- ---------- ---------- - ---------- ---------- - ---------- ---------- - ---------- ---------- 30JUN00 67602 36253 53.63 % 36253 53.63 % 40251 59.54 % 76834 113.66 % SYSTEMS B620 S000 AUTOMATIC TRAIN CONTROL (D.F.I.) SYSTEMS DIVISION PROJECT CONTROL P000 PROJECT CONTROL 01JUN92A 31DEC98 39818 38372 96.37 % 38367 96.36 % 38163 95.84 % 43138 108.34 % -------- -------- ---------- ---------- ---------- - ---------- ---------- - ---------- ---------- - ---------- ---------- 01JUN92A 31DEC98 39818 38372 96.37 % 38367 96.36 % 38163 95.84 % 43138 108.34 % PROJECT ADMINISTRATION A000 PROJECT ADMINISTRATION 01JUL92A 30JUN00 14437 11614 80.45 % 11614 80.45 % 12799 88.65 % 19091 132.24 % -------- -------- ---------- ---------- ---------- - ---------- ---------- - ---------- ---------- - ---------- ---------- 01JUL92A 30JUN00 14437 11614 80.45 % 11614 80.45 % 12799 88.65 % 19091 132.24 % SECTION DESIGNER D0301 D0321 D0322 D0326 POLLYWOOD/LOWWLAND STATION-TUNNELS ORANGE CITY STATION PEDESTRIAN UNDERPASS @ IRVINE STA. ORANGE CITY ROAD/RESTORATION/LANDSCAPE PAGE 7 01FEB93A 01MAY94A 01SEP92A 02JUN97 -------01SEP92A 14MAR94A 1183 1183 100.00 % 1183 100.00 % 0 0.00 % 0 0.00 % 01DEC95A 5085 5085 100.00 % 5085 100.00 % 0 0.00 % 0 0.00 % 28APR95A 19200 19200 100.00 % 19200 100.00 % 42969 223.80 % 42969 223.80 % 27MAY98 13200 0 0.00 % 0 0.00 % 0 0.00 % 0 0.00 % -------- ---------- ---------- ---------- - ---------- ---------- - ---------- ---------- - ---------- ---------- 27MAY98 38668 25468 65.86 % 25468 65.86 % 42969 111.12 % 42969 111.12 % ======== ======== ========== ========== ========== = ========== ========== = ========== ========== = ========== ========== = 01MAY92A 30JUN00 297000 212431 71.53 % 217420 73.21 % 244173 82.21 % 322560 108.61 % Planned Earned Actual At Compl PAGE 8 Each Discipline provided a target percent complete for their work at the 60% submittal - earned value is measured based on earning rules developed with the baseline D0502 Little China Station & Line Segment 80 60 Percent 40 Complete 20 0 ARCH CIVIL ELEC MECH ROW STRUC UTILS SYS Earned Value 71 60 45 45 45 60 55 55 Baseline Schedule 72 68 52 67 65 70 55 70 Discipline Progress Toward In-Progress Design Submittal The purpose of this report is to demonstrate to the client that all disciplines are ready for the submittal P3 & SureTrak Standard Reports Earned Value Report - Resources Earned Value Report - Costs Earned Value Report - SureTrak P3 Resource Earned Value Report ----------------------------------------------------------------------------------------------------------------------------------D. R. McNatty & Associates PRIMAVERA PROJECT PLANNER SAMPLE PROJECT USING EARNED VALUE REPORT DATE 10AUG97 RUN NO.13621 EARNED VALUE REPORT - QUANTITY START DATE 1JUN92 FIN DATE 30JUN00 20:24 RE-01 Resource Earned Value Report DATA DATE 31MAY97 PAGE NO. 1 ----------------------------------------------------------------------------------------------------------------------------------COST PCT ..........CUMULATIVE TO DATE.......... ........VARIANCE......... ......AT COMPLETION...... ACCOUNT RESOURCE ACTIVITY ID CMP ACWP BCWP BCWS COST SCHEDULE BUDGET ESTIMATE ------------ -------- ----------- ----- ------------ ------------ ------------ ------------ ------------ ------------ -----------A1F* - FACILITIES A1FFA KQ-ACTUALS .0 31000 0 0 -31000 0 0 31000 A1FRI KQ-ACTUALS .0 0 0 0 0 0 0 0 A1FSF KQ-ACTUALS .0 3000 0 0 -3000 0 0 3000 A1FUT KQ-ACTUALS .0 1000 0 0 -1000 0 0 1000 L A1FAR JH-7FBB055 100.0 341 550 358 209 192 550 579 L A1FAR JH-7FBC131 100.0 777 1000 658 223 342 1000 977 L A1FAR JH-7FBE055 100.0 428 550 550 122 0 550 428 L A1FAR JH-7FZZ601 56.0 70 45 45 -25 0 80 110 L A1FAR JH-7HAB304 100.0 151 151 151 0 0 151 151 L A1FAR JP-6ADP990 100.0 6704 8063 8063 1359 0 8063 6704 L A1FAR JP-6AZZ135 100.0 358 410 410 52 0 410 358 PAGE 9 L L L L L L L L L L L L L L L L A1FEL A1FEL A1FEL A1FEL A1FEL A1FEL A1FST A1FST A1FST A1FST A1FST A1FST A1FST A1FST A1FST A1FTR JP-6ADP990 JP-6AZZ135 JP-7FBB086 JP-7FBC134 JP-7FBE105 JP-7FBE106 JH-7FBB055 JH-7FBC131 JH-7FBE055 JH-7FZZ190 JH-7FZZ601 JH-7HAB304 JP-6ADP990 JP-7FBC134 JP-7FBE105 KA-6TDP496 100.0 6840 5044 5044 -1796 0 5044 6840 100.0 84 80 80 -4 0 80 84 75.2 355 451 276 96 175 600 955 70.0 317 840 513 523 327 1200 861 100.0 309 309 309 0 0 309 309 41.9 230 122 122 -108 0 291 338 100.0 743 550 358 -193 192 550 1180 100.0 4354 1200 790 -3154 410 1200 6329 100.0 807 550 550 -257 0 550 807 20.0 0 18 19 18 -1 90 90 56.0 94 112 112 18 0 200 174 100.0 119 119 119 0 0 119 119 100.0 11915 11237 11237 -678 0 11237 11915 70.0 3959 840 513 -3119 327 1200 6909 100.0 295 295 295 0 0 295 295 100.0 1207 888 888 -319 0 888 1207 ----- ------------ ------------ ------------ ------------ ------------ ------------ -----------A1F* TOTAL 77.2 105466 100096 95673 -5370 4423 129641 134456 =================================================================================================================================== P3 Cost Earned Value Report ----------------------------------------------------------------------------------------------------------------------------------D. R. McNatty & Associates PRIMAVERA PROJECT PLANNER SAMPLE PROJECT USING EARNED VALUE REPORT DATE 10AUG97 RUN NO.13622 21:00 CE-01 Cost Earned Value Report EARNED VALUE REPORT - COST START DATE 1JUN92 DATA DATE 31MAY97 FIN DATE 30JUN00 PAGE NO. 1 ----------------------------------------------------------------------------------------------------------------------------------COST PCT ..........CUMULATIVE TO DATE.......... ........VARIANCE......... ......AT COMPLETION...... ACCOUNT RESOURCE ACTIVITY ID CMP ACWP BCWP BCWS COST SCHEDULE BUDGET ESTIMATE ------------ -------- ----------- ----- ------------ ------------ ------------ ------------ ------------ ------------ ------------ PAGE 10 A1F* - FACILITIES L L L L L L L L L L L L L L A1FAR A1FAR A1FAR A1FAR A1FAR A1FAR A1FAR A1FAR A1FAR A1FAR A1FFA A1FFA A1FFA A1FRI JH-7FBB055 JH-7FBC131 JH-7FBE055 JP-6ADP990 JP-6AZZ135 JP-6AZZ191 JP-6AZZ251 JP-7FBB086 JP-7FBC134 JP-7FBE105 KQ-C3AA095 KQ-C3AA096 KQ-C3AA097 KQ-6JAJ095 L L L L L L L L L L L L L L A1FRI A1FRI A1FST A1FST A1FST A1FST A1FST A1FST A1FST A1FUT A1FUT A1FUT A1FUT A1FUT KQ-6JAJ096 KQ-6JAJ097 JH-6CZZ103 JH-7FBB055 JH-7FBC131 JP-6ADP990 JP-7FBB086 JP-7FBC134 JP-7FBE105 JH-7FBE055 JP-7UAA112 JU-7UAA115 KA-7A7A627 KQ-CWACE15 100.0 100.0 100.0 100.0 100.0 100.0 100.0 75.2 70.0 100.0 100.0 100.0 91.7 100.0 18265 37780 24399 344661 17585 10000 4000 9086 40624 15370 200000 200000 150000 75000 35809 65107 35809 522351 24495 11790 4640 29376 54690 15422 208276 200203 146990 75003 23297 42857 35809 522351 24495 11790 4640 39064 33390 15422 208276 200203 146989 75003 17544 27327 11410 177690 6910 1790 640 20290 14066 52 8276 203 -3010 3 12512 22250 0 0 0 0 0 -9688 21300 0 0 0 1 0 35809 65107 35809 522351 24495 11790 4640 39064 78128 15422 208276 200203 160294 75003 33259 50380 24399 344661 17585 10000 4000 9086 53476 15370 200000 200000 150000 75000 100.0 75000 88480 88480 13480 0 88480 75000 91.7 80000 89197 89196 9197 0 97270 80000 100.0 43165 29725 29725 -13440 0 29725 43165 100.0 47933 35809 23297 -12124 12512 35809 77212 100.0 285829 78128 51428 -207701 26700 78128 418154 100.0 727808 731866 731866 4058 0 731866 727808 75.2 55864 29376 17990 -26488 11386 39064 114355 70.0 300159 54690 33390 -245469 21300 78128 497809 100.0 20458 20458 20458 0 0 20458 20458 100.0 28808 22787 22787 -6021 0 22787 28808 32.3 984 14721 18164 13737 -3443 45575 33189 25.6 3390 11667 25089 8277 -13421 45575 34854 15.0 0 975 637 975 338 6500 5700 100.0 8174 8174 8174 0 0 8174 8174 ----- ------------ ------------ ------------ ------------ ------------ ------------ -----------A1F* TOTAL 77.1 6475722 6481369 6196457 5647 284912 8410343 8274726 =================================================================================================================================== PAGE 11 P3 Custom Reports Resource Performance by Workpackage Cost/Schedule Performance Baseline and Change Orders Resource Performance Summary CPI Trend Report PAGE 12 ----------------------------------------------------------------------------------------------------------------------------- ----------------------------------------D. R. McNatty & Associates PRIMAVERA PROJECT PLANNER SAMPLE PROJECT USING EARNED VALUE REPORT DATE 10AUG97 XXXXXXXXXXXXXX TRANSPORTATION AUTHORITY PLANNED EARNED ACTUALS RW-G4 PERF SUMMARY BY Category PAGE NO. 1 ----------------------------------------------------------------------------------------------------------------------------- ----------------------------------------DESCRIPTION EARLY EARLY BUDGET SCHEDULED PLANNED EARNED EARNED HOURS PCT HRS HOURS AT HRS AT START FINISH HOURS HOURS HRS PCT HOURS HRS PCT TO DATE TO DATE COMPLETION CMP PCT ----------------------------------------- -------- -------- ---------- ---------- ---------- - ---------- ---------- - ---------- ---------- - ---------- ---------- FACILITIES 01JUL92A 30JUN00 136475 100724 73.80 % 105718 77.46 % 10 9991 80.59 % 140528 102.97 % SYSTEMS 01JUL92A 30JUN00 67602 36253 53.63 % 36253 53.63 % 4 0251 59.54 % 76834 113.66 % PROJECT CONTROL 01JUN92A 31DEC98 39818 38372 96.37 % 38367 96.36 % 3 8163 95.84 % 43138 108.34 % PROJECT ADMINISTRATION 01JUL92A 30JUN00 14437 11614 80.45 % 11614 80.45 % 1 2799 88.65 % 19091 132.24 % SECTION DESIGNER 01SEP92A 27MAY98 38668 25468 65.86 % 25468 65.86 % 4 2969 111.12 % 42969 111.12 % ======== ======== ========== ========== ========== = ========== ========== = ========= = ========== = ========== ========== = 01MAY92A 30JUN00 297000 212431 71.53 % 217420 73.21 % 24417 3 82.21 % 322560 108.61 % PAGE 14 CPI/SPI TREND GRAPH 12 0 10 0 80 60 40 20 SPI 0 May J u n J u l Au g Sep Oct Nov Dec J an Feb Mar Apr May J u n J u l Au g Sep SP I 1 0 0 7 0 85 91 95 97 98 95 93 91 91 92 91 92 92 93 94 CP I 1 0 0 1 2 4 9 3 87 85 82 80 78 75 71 72 72 75 74 72 70 68 SPI CPI PAGE 15 P3 & SureTrak Graphics Performance Layout - P3 Performance Layout - SureTrak Performance Curves - P3 Performance Layout - P3 1992 + FACILITIES + 11F 1993 1994 1995 1996 1997 1998 1999 2000 + SYSTEMS + 12S + PROJECT + 15C CONTROL ++ PROJECT 16A ADMINISTRATION + SECTION + 2SD DESIGNER ++ SPECIALTY 3SS SUB CONSULTANT ++ OTHER 4OD DIRECT COSTS x 100000 x 1000000 32 60 28 50 24 40 PAGE 16 20 16 30 12 20 8 10 4 1992 1993 1994 1995 1996 1997 1998 1999 2000 Resource/Cost Profile Legend Current Estimate Earned Value Planned Project Start Project Finish Data Date Run Date © Primavera Systems, Inc. 06/01/92 06/30/00 05/31/97 09/04/97 Early Bar Progress Bar Critical Activity Detail scale (left): X 100000 Cumulative scale (right): X 1000000 NF75 Sheet 1 of 1 ENGINEERING CONSULTANT Date Revision D:\DATA\EVPRES\PRIMA Checked Approved Performance Layout - SureTrak PAGE 17 Performance Curves - P3 EST TO COMPLETE 100 90 PLANNED 80 ACTUAL EXPENDED EARNED TO DATE 70 CREATE TARGET 2 FROM CURRENT PERCENT 60 50 40 30 20 10 RUN GLOBAL CHANGE TO SET ACTUALS = TO EARNED 0 JUN NOV APR SEP 1992 1993 Pr oject Start Pr oject Finish Data Date Plot Date 1JUN92 30JUN00 31MAY97 11AUG97 FEB JUL 1994 Schedule dates Target 1 dates as of: 30MAR97 Target 2 Dates as of: 31MAY97 DEC MAY OCT 1995 MAR AUG JAN JUN 1996 1997 FEB JUL 1999 DEC MAY 2000 Sheet 1 of 1 Date RC-Q1 PERFORMANCE CURVE # 1 (c) Pr imaver a Systems, Inc. NOV APR SEP 1998 Revision Checked Approved Summary Understand what Earned Value is and how you can apply it to your project Performance Measurement must be based on an accurate budget Use performance indices to provide perspective to your forecasts Define Earned Value at lowest budget level Measure and report performance at a level where responsibility can be recognized Communicate performance creatively