(Date) 2014
From: Senior Safety Manager
To:
Executivel Manager
Subject: # 36 -2014, ACTIVITY HAZARD RISK ASSESSMENT FOR INSTALLING FLOOR TILING AND VINYL FLOOR COVERINGS
Ref: (a) Ministry of Manpower Regulations Regarding General Safety and Health 354A
1. Per reference (a), this risk assessment was completed to identify hazards that pose risk to workers, evaluate those hazards for
severity and likelihood of occurrence, and recommend corrective actions that will eliminate or minimize hazards associated with
.
2. This AHA will be reviewed periodically and updated as needed to reflect changes in working conditions, processes or addition of
new materials or equipment.
Inventory of Work Activities………………………………………………………………………………….Page
Activity Risk Assessment Matrix……………………………………………………………………………Page
Activity Based Risk Assessment Form……………………………………………………………………Page
Listing of Competent Persons……………………………………………………………………………….Page
2
3
4-5
6
3. Please address any questions or concerns to me at 8205 8249 or lee_wilson@pnhgrp.com.
1
Respectfully,
T. L. Wilson
2
Risk Assessment Form
# 36-2014, ACTIVITY HAZARD RISK ASSESSMENT FOR INSTALLING FLOOR TILING AND VINYL FLOOR COVERINGS
Inventory of Work Activities ( Method of Statement )
Company: PNH Resources PTE LTD
May 2014
No.
Process Description
Work Activities
1
Site Preparation
2
Floor tiling
3
Vinyl flooring
4
Housekeeping, cleaning.
Erect protective barricades, safety barriers and or safety tape and post safety signage as needed
to alert all that this is a construction area and access is only for authorized personnel. Preparation
of floor tile or vinyl tile and storing them at work areas.
Laying of floor tiles.
- Application of tile adhesive.
- Cutting of floor tiles for corner, edges or awkward corners.
- Light hammering of placed tiles to get leveling of the finishing floor level
To prepare floor level for vinyl tiles
- Prepare floor level by application of self leveling cement. This will take one day for
cement to cure and dry.
- Sweeping and vacuum of floor to remove cement dust, dirt or debris as much as possible.
- Apply floor adhesive. Most probably solvent base rubber glue onto vinyl tile and floor
surface thinly.
- Putting vinyl tiles onto adhesive applied surfaces.
- Cutting of vinyl tiles for corner , edges or awkward corners
- Rolling finished surface with heavy weight roller to drive out any air bubbles.
Clean work finished area by sweeping , wiping down . Remove unused materials tools and waste
from work area.
3
#2014-36-2014, ACTIVITY HAZARD RISK ASSESSMENT – FIVE POINT MATRIX EMPLOYED
TO QUANTIFY RISK – JUNE 2014
Risk Criteria
Severity (1-5, Lowest – Highest)
Likelihood ( 1-5, Lowest - Highest)
1-Negligible Injuries: slight injury or health effect,
2-Minor Injuries: Injury or ill health requiring first aid treatment only
3-Moderate Injury: Injury requiring medical treatment or ill health leading to disability
4-Major Injury Disability: serious injury or life threatening occupational disease
5-Castrophic: serious injury resulting in fatality or irreversible health damage with death
1-Rare: very unlikely to happen,
2-Remote: not likely to happen most of the time,
3-Occasional: likely to happen sometime,
4-Major Injury Disability: likely to happen several times regularly,
5-Almost Certain: Likely to happen
Risk Level (Severity x Likelihood)
Trivial Risk
:
Tolerable Risk :
Moderate Risk :
Substantial Risk :
Intolerable Risk :
1 to 2 (L)
3 to 9 (L)
10 to 19 (M)
20 to 24 (H)
25 (H)
- First aid treatment injury, minor cuts or bruises, clean-up effort for environmental impact
- First aid treatment Injury, minor cuts or bruises, clean-up effort for environmental impact
- Temporary disability, lost time injury, outpatient treatment, minor or short term environmental impact
- Serious Injury, permanent disability, major disruption and damage to equipment or structure, significant environmental
- Fatality or fatalities, serious injury, permanent disability, major structural or equipment damage, detriment environmental
The table above provides numerical methodology to better prioritize hazards. These values are the
criteria for the Activity-Based Risk Assessments beginning on the following page. No catastrophic
risk of any certainty was identified.
Risk is calculated mathematically by multiplying severity of the operation by the likelihood an
accident will occur. Generally risk levels calculated at 9 and below are considered acceptable,
manageable risk. This does not preclude the need to try and mitigate all risk to the lowest
possible level. However, those above nine should receive additional scrutiny to determine what
steps are available to reduce overall risk including, administrative controls, substitution of a
higher hazardous material for a less hazardous material, use of engineering controls or use of
personal protective equipment (PPE).
4
Activity-Based Risk Assessment Form
Company:
PNH RESOURCES PTE LTD
Process/Location:
Floor tiling and vinyl tiles
Conducted by: (Names,
designations) (Date)
Approved by:
Project Manager
(Name, designation)
(Date) 2014
(Date)
1. Hazard Identification
Lee Wilson
Senior Safety Manager
May 2014
19th May 2014
Last Review
Date:
2. Risk Evaluation
Next Review
Date:
17th May 2015
3. Risk Control
1a
1b
1c
1d
2a
2b
2c
2d
3a
3b
No
Work Activity
Hazard
Possible
Accident/
Ill Health &
Persons at Risk
Poor storage or
stacking of
materials.
Person working in
the area
Existing Risk Control
(if any)
SevErity
Likelyhood
Risk
Level
Additional Risk Control
Action Officer
Designation
1
Supervisor to ensure area house
keeping and PPEs to be put on in this
area.
Project
Manager and
Senior Safety
Manager
Project
Supervisor
6
Break time interval for this type of
task.
Supervisors to monitor work
activities on site.
Project
Supervisor
Project
manager
1
Site preparation
Preparation of
tools and
material on site.
Trip / Fall
Musculoskeletal
strain from
handling heavy
materials or
equipment and
work position
– injuries or pain
in the body's
joints,
ligaments,
muscles, nerves,
tendons, and
structures that
support limbs,
neck and back
due to working
with in awkward
position or by
MSD.
Persons
performing the
task.
Steel toed shoes and
hard hats to be worn.
Maintain good house
keeping. Planning for
designated area for
storing of material and
tools.
1
Training with regard to
avoidance of these
types of injuries.
Provide trolleys for
shifting of materials to
work area. This training
is conducted several
times over the year and
is also reiterated prior
to starting a new project
if applicable.
2
5
1
3
No
2
3
Work Activity
Floor tiling
works
Vinyl floor
works
manual handling
of materials
Hazard
Inhalation of
crystalline
silica dust.
Possible
Accident/
Ill Health &
Persons at Risk
Person laying tiles
work. Preparation
of tile adhesive.
Mixing of cement
adhesive
Existing Risk Control
(if any)
Severity
Likelyhood
Risk
Level
Wearing Respiratory
protection N95 mask
3
2
6
Additional Risk Control
Project
Manager and
Senior Safety
Manager
Project
Supervisor
Sight hazard
Eye injury while
cutting tiles.
Flying debris
getting into eyes
Safety goggles to be
worn.
3
2
6
PNH workers receive Sight
Conservation Training as part of the
routine safety training several times
annually.
Skin contact
with cement
adhesive. Hands
are most
common
affected.
Dermatitis.
Prolong skin
contact with
cement adhesive
which are highly
alkaline .Person
laying floor tiles.
Inhalation of
fumes from
rubber glue.
Person applying
the glue
Putting on rubber hand
gloves.
2
2
4
Check for any puncture to rubber
hands gloves as and when necessary.
If skin exposure ,wash off cement
immediately.
Putting on organic face
mask.
Force ventilation to
work area where glue is
being applied.
2
3
6
Open all windows and keep area as
much ventilated as possible.
Limit exposure time for this task.
Respiratory
(Tailor this section to the individual Project)
6
Action Officer
Designation
Project
Manager and
Senior Safety
Manager
Project
Supervisor
Risk Assessment Form
QUALIFICATIONS AND POINTS OF CONTACT FOR THIS PROJECT FROM PNH RESOURCES PTE
LTD AND GOODMNAN ENVIRONMENTAL PTE LTD (APPLICABLE MONTH) 2014
Competent/Qualified Personnel: (These should be tailored to fit the project)
Lee Wilson - 8205 8249
QP/ First Aid CPR/ Heat Stress Program/ Respiratory Protection Program/ Hearing/Sight Conservation Program/Training Coordinator
Ms. Thazin Nwe (Jennifer) 8522 6014
HAZMAT Coordinator
Lim Joseph – 9683 7072
CP/ Scaffolds/ Fall Protection
Eng Yong Chye – 9626 9262
PNH Project Manage/CP/ Electrical/ First Aid CPR/Lock Out/Tag Out
Equipment Used:
Ladders/Scaffolds
Hand and Power Tools
First Aid Kit
Eyewash Station
LOTO Kit
Fire Extinguishers
Inspection Requirements:
Training Requirements
Inspect PPE daily and before use.
Inspect first aid kit at least weekly.
Inspect electrical extension cords before use
Visual inspection of Fire extinguisher daily
Daily Housekeeping of work areas
Daily site safety inspections by Safety Manager
and project Quality Control
7
Ladders/Scaffolds
Proper Lifting Techniques
First Aid/CPR
Emergency Telephone Numbers
Daily/Weekly Safety Tool Box Meetings