Project_info_pack

advertisement

C O O K I S L A N D S G O V E R N M E N T

I N F O R M A T I O N

D O C U M E N T

I s s u e d o n

2 4 N O V E M B E R 2 0 1 4

F o r

TE MATO VAI STAGE 2 – CONSTRUCTION AND OPERATION

Contact Entity:

TE MATO VAI PROJECT MANAGEMENT

UNIT, MINISTRY OF FINANCE and

ECONOMIC MANAGEMENT

Table of contents

1.

General Information ....................................................................................................................... 1

1.1

Introduction .......................................................................................................................... 1

1.2

Purpose ................................................................................................................................ 1

1.3

Reliance on this Document and/or any information Contained in this Document ............... 1

2.

Scope of Work ................................................................................................................................ 2

2.1

Locations and Project Drawings .......................................................................................... 2

1.1

Design and Build Works – Headworks ................................................................................ 2

1.2

Build Only Works – Operations, Roads and Pipelines ........................................................ 3

3.

Design and Build Requirements .................................................................................................... 6

1.3

Concept Design ................................................................................................................... 6

3.1

Treatment Facility Performance ........................................................................................... 7

4.

Other Information ........................................................................................................................... 9

4.1

Site Visit and Presentation ................................................................................................... 9

4.2

Tender timeline .................................................................................................................... 9

4.3

Local Contractor Involvement .............................................................................................. 9

Appendices

Appendix A - Drawings

Appendix B – Watercare Water Quality Report

Appendix C – Local Contractors

Te Mato Vai | Information Pack for Cook Islands Government - Te Mato Vai Stage 2 - Construction and Operation,

51/32561/00 | i

1.

General Information

1.1

Introduction

This document covers the general requirements for the construction and refurbishment of water intakes, treatment, storage and water supply (to the ring main) for the Government of the Cook

Islands, through the Ministry of Finance, Economic Management (MFEM), Te Mato Vai PMU.

The Te Mato Vai project is generally made up of the following components:

1) The design and construction of the inner and outer ring mains (construction currently being undertaken).

2) The design and construction of new water treatment facilities (currently part of this potential tender).

3) The design and construction of replacement trunk mains as required (currently part of this potential tender).

4) Upgrade of roading assets to improve all weather access to the water treatment facilities

(currently part of this potential tender).

5) The installation of domestic and commercial meters for the purposes of monitoring water consumption (as part of a future tender).

6) The design and installation of a SCADA system (as part of a future tender).

1.2

Purpose

The purpose of this document is to provide some project specific design information to the industry prior to the release of the tender document in order to assist the contracting industry to prepare for the tender and understand the scope of work.

1.3

Reliance on this Document and/or Any Information

Contained in this Document

Information contained in this document is subject to change and no reliance can be placed on the scope of the tender being the same as the information contained in this document.

Also, the issue of this document does not constitute a tender, or infer that any tender will actually be released for this work at any point in the future.

Any costs incurred by any prospective contractor will be at that contractor’s risk, irrespective of whether any tender, in any form, is actually released at any point in the future.

Report for Cook Islands Government - Te Mato Vai Stage 2 - Construction and Operation, 51/32561/00 | 1

2.

Scope of Work

2.1

Locations and Project Drawings

The contract works are located across eleven (11) sites in Rarotonga, Cook Islands:

The 11 sites are:

Site

Avana

Avatiu

Matavera

Akaoa

Ngatoe

Papua

Drawing Site Location Number

01

02

03

04

05

06

Taipara

Takuvaine

Tupapa

Turangi

08

09

10

11

Totokoitu 12

Preliminary site layout drawings and P&ID’s have been provided for information purposes

2.2

Design and Build Works – Headworks

For the purposes of this project, Headworks are defined as stream intakes, pre-treatment facilities, treatment facilities and, where specified, any storage identified for each of the locations. The headworks, and hence the scope of the design build, does not include the trunk main pipeline works.

2.2.1

Design Works

It is intended that the headworks will be a design and build component, with the design works incorporating the design, design report, drawings, documentation and Principal ’s approval (on a site by site basis) of all works required to be constructed for the headworks.

The activities to be completed under the design will be, but not necessarily limited to:

Production of all Design Documentation

Production of Process Documentation

Production of the Contractor Quality Plan

Approval of the design and relevant documentation by the Engineer

Other project requirements as necessary to satisfactorily complete the design of the headworks

2.2.2

Headworks Construction

It is intended that the Headworks Construction i s a ‘design and build’ component and shall incorporate all works required to complete the construction of detailed design as approved by the Engineer. It includes the following sites:

2 | Report for Cook Islands Government - Te Mato Vai Stage 2 - Construction and Operation, 51/32561/00

Site

Intake* Water Treatment Plant

Max Flow

(m 3 /day)

N/A

Min Flow

(m 3 /day)

N/A

Storage

(m 3 )

Akaoa

N/A 1400

Avatiu

New 2000 450 4800

Avana

Upgrade 3400 1200 1400

Matavera

Upgrade 1200 325 600

Ngatoe

Upgrade 2000 250 2800

Papua

Upgrade 2000 1200 1400

Taipara

New 1200 250 N/A

Takuvaine

Upgrade 3000 675 600

Totokoitu

New 2000 400 N/A

Tupapa

Upgrade 1200 275 1400

Turangi

New 3000 1200 2800

*Note these are based on the concept design layouts and hydraulics, this can be altered depending on the design and build recommendations.

The activities to be completed under the headworks construction will be, but not necessarily limited to:

Production of the Contractors Construction Management Plan and Programme

Review and update of the Contractor Construction Management Plan and Programme

Completion of construction works to the satisfaction of the Engineer

Initial commissioning of the Headworks to the satisfaction of the Engineer

Production of As built documentation

Production of Operation and Maintenance manuals

Approval of Operation and Maintenance manuals by the Engineer

2.3

Build Only Works – Operations, Roads and Pipelines

2.3.1

Headworks Operational Period

Headworks Operation Period is a ‘build only’ component and shall require the contractor to complete all works required to prove the performance of the plant installed in the headworks locations. It is likely that the contract will be required to operate the headworks components for

12 months.

The activities to be completed under this separable portion are, but not necessarily limited to:

Post commissioning of the plant to refine the production process

Supply and shipment of any coagulant required to operate the plant

Provision of water quality testing equipment for ICI(new SOE) operations staff

Water quality testing to prove the performance of the treatment process

Report for Cook Islands Government - Te Mato Vai Stage 2 - Construction and Operation, 51/32561/00 | 3

Training of TMV staff on the operation of the plant (both formal office based training and on-site training)

Direction of TMV operation staff in the day to day operation of the water treatment plants

2.3.2

Pipelines Construction

Pipelines Construction is a ‘build only‘ component and shall incorporate supply and construction of the following pipelines . The work starts at the extent of the ‘design and build’ component works and ends at (and including) the connection to the ring main.

Site

Pipe Material Pipeline Length (m)

Akaoa

Avana

Avatiu

Matavera

Ngatoe

Papua

Taipara

Takuvaine

Totokoitu

Tupapa

Turangi

225 OD PE100 PN10

315 OD PE100 PN10

355 OD PE100 PN10

200 uPVC

200 uPVC

225 OD PE100 PN10

200 uPVC

200 uPVC

315 OD PE100 PN10

200 uPVC

315 OD PE100 PN10

180

4174

2624

Repairs Only

Repairs Only

1503

Repairs Only

Repairs Only

1695

Repairs Only

1864

The activities to be completed the pipeline construction will be, but not necessarily limited to:

Review and update of the Contractor Construction Management Plan and Programme

Supply and installation of pipeline materials

Weld testing

Pipeline Pressure testing

Flushing and cleaning of pipeline

Supply and installation of pipeline fittings

Reinstatement of disturbed surfaces

Removal and disposal of existing pipeline materials where disturbed by the works

Production of as built documentation

Production of Operation and Maintenance manuals

Approval of Operation and Maintenance manuals by the Engineer

4 | Report for Cook Islands Government - Te Mato Vai Stage 2 - Construction and Operation, 51/32561/00

2.3.3

Access Road Construction

Access Roads Construction is a ‘build only‘ component and shall incorporate supply and construction of improvements to the access roads. Generally, road require improvements to the surface drainage, pavement replenishment and construction of stream crossings. The work to be undertaken is based on the following:

Site

Existing Road Distance (m) River Ford Crossings (No.)

Avana

Akaoa

Ngatoe

Taipara

Matavera

Tupapa

Turangi

4060

180

1590

1200

1660

2020

2220

19

N/A

1

0

3

2

0

The activities to be completed under this separable portion are, but not necessarily limited to:

Review and update of the Contractor Construction Management Plan and Programme

Clearing of vegetation

Creation of road water table drains

Supply and construction of additional pavement

Construction of concrete river ford crossings

Report for Cook Islands Government - Te Mato Vai Stage 2 - Construction and Operation, 51/32561/00 | 5

3.

Design and Build Requirements

3.1

General Design Requirements

The design of the treatment facilities will be robust in terms of performance under varying weather conditions and as such shall:

Use robust mechanical and hydraulic flow controls.

Eliminate, or minimise, the use of electricity (it is not available at most of the sites). All

Site must be reliably controlled.

Incorporate simple, low maintenance hydraulic chemical dosing systems (where required).

Be of simple construction using long design life materials (i.e. concrete) where possible for civil structures and when this is not possible metal structures shall be adequately protected for coastal and tropical environments.

Have standardised treatment systems and equipment across all sites.

Allowance for access for ongoing operation and maintenance of equipment being installed.

The footprint of the headworks to be kept to a minimum.

Equipment shall be located to minimise the extent and associated cost of new infrastructure.

Headworks location to minimise the need for erosion protection due to the proximity to the stream and the requirement for stream protection works.

Minimise lengths of watermain pipes and stream crossings.

Levels shown on Process Flow Diagram drawings are indicative only and may be modified to meet the design requirements.

Where storage is proposed at a site, floor levels of the storage tanks proposed by the contractor shall not be below the design floor level of the tank as shown in the concept design. Deviations from these levels will need to be check during tender to prove no detrimental impact to the operation of the supply system.

Where no storage is proposed at a site, the outlet from the filtration device proposed by the contractor shall not be below the outlet level of the AVG shown in the concept design. Deviations from these levels will need to be check during tender to prove no detrimental impact to the operation of the supply system.

3.2

Concept Design

A concept design for an appropriate treatment process has been developed for proof of concept purposes, based on the result of water quality investigations carried out at all intakes, site constraints identified during the site investigations and a review of available technology.

The concept design is as follows:

Intakes upgraded to improve water capture and reduce occurrences of blockages caused by debris in stream flows.

Settling tank with flow control arrangement at inlet to settlement tank, coagulant dosing and settlement (possibly including further aeration).

6 | Report for Cook Islands Government - Te Mato Vai Stage 2 - Construction and Operation, 51/32561/00

No

1

5

6

2

3

4

Parameter

Sites

Detention time

Loading rate

Water Treatment

Plant Max Flow:

2900-3700 m 3 /day

Avana, Turangi,

Takuvaine

3.5 hrs

25 m 3 / m 2 / hr

4:1

Water Treatment

Plant Max Flow:

1600- 2200 m 3 /day

Avatiu, Ngatoe,

Papua, Totokoitu

3.5 hrs

25 m 3 / m 2 / hr

4:1

Water Treatment

Plant Max Flow:

1200-1400 m 3 /day

Matavera, Taipara,

Tupapa

3.5 hrs

25 m 3 / m 2 / hr

4:1 Minimum

Length:width

No of tanks

Surface area of one tank

Length

Width

58 m

2

2 – 72 m 2 64 m

1

2 – 100 m 2

1

40 m 2 - 56 m 2

7

8

15 - 19

4 - 4

16 - 18

4 - 4

12 - 14

4 - 4

9 Depth (minimum depth at outlet end)

2.9 2.9 2.9

An Automatic Valveless Gravity (AVG) filter(s) directly fed by gravity from the outlet of the settling tank.

No Description

1 Filtration rate

2 Backwash rate

Rate

Not to exceed 9 m 3 / hr / m 2 (2.5 l / s / m 2

Declining rate within range 7 mm / s

)

– 18 mm / s

3 Backwash initiation Automatic based on pressure loss with provision for manual over-ride

Hydraulic control module 4 Control

Sediment collection, drainage, drying and collection for backwash and settling tank scour.

Provision for connection of disinfection facilities if later required.

Storage tanks.

The concept design has been provided in good faith and the Contractor will be deemed to have carried out further research and investigations as needed before either offering an optimised design based on the concept design, or an alternative design.

3.3

Treatment Facility Performance

The objectives of the treatment facilities are those consistent with the Hydraulic Levels of

Service as set out in the ICI Technical Standards for Water Supply, May 2014, Section 3.0

Design Levels of Service which states the treatment system design will not include any disinfection.

In terms of the Te Mato Vai Project the specific water quality objectives for treatment are to generally meet WHO Guidelines for aesthetic determinands at all times with allowance for unusual weather events as summarised in the table below.

Report for Cook Islands Government - Te Mato Vai Stage 2 - Construction and Operation, 51/32561/00 | 7

2

3

4

No Determinand

1 Turbidity (NTU)

Apparent colour (TCU)

Total iron (mg/l)

Manganese (mg/l)

Treated Water Requirements

1 or < 1 NTU

5 or < 5 NTU

< 0.1 mg/l

< 0.1 mg/l

A water quality assessment and report has been completed and is included in Appendix B. This information will be required to be expanded on by the contractor after award of contract.

8 | Report for Cook Islands Government - Te Mato Vai Stage 2 - Construction and Operation, 51/32561/00

4.

Other Information

4.1

Site Visit and Presentation

As part of the pretender information pack it is proposed to hold a Presentation and site visit day.

The details are as follows:

Date: 12 th December 2014

Start time:

Meeting Venue:

9am (CKT)

CCECC Conference Room, Te Mato Vai Compound

Sites to be visited: Matavera, Avana, Akaoa, Totokoitu

Prospective Tenderers shall notify their interest in attending the site visit to Latu Kupa

( latu@kew.com.ws

) by 12noon 05 th December 2014 (CKT).

Information to be supplied when notifying interest in attending the site visit is as follows:

- Names of all people attending the presentation site visit

- Names of delegated representative to attend the site visit

- Name of company

There will be a maximum of 30 places available on the site visit component, as such and unless attendance allows otherwise, it is only intended that representatives of companies intending to tender for the entire project works will be selected to attend the site visit. Companies that are looking to subcontract as part of the greater project are not intended to be catered for during the site visit, however, they will be welcome to attend the presentation.

If necessary, and as available spaces dictate, it may be required to limit attendance at the site visit to 1 or 2 people per prospective tenderer.

4.2

Tender Timeline

It is proposed that the tender timeline would be as follows:

Release of Tender document: 16/12/2014

Close of Tender:

Tender Award:

06/02/2015

27/02/2015

Start of construction: 20/03/2015

These are general timeline and should not necessarily be replied on. The Te Mato Vai project reserve the right to change, alter or cease the tender process at any time.

4.3

Existing Site Investigation Information

Other information that has been collected during the design stage, and will be issued during the tender phase is as follows:

1) Basic factual geotechnical report

2) Environmental Impact Assessment (EIA)

4.4

Local Contractor Involvement

A key component of selecting the preferred tender for this construction works will be the level of involvement of local contractors (loosely defined as a company, or operation, that would be

Report for Cook Islands Government - Te Mato Vai Stage 2 - Construction and Operation, 51/32561/00 | 9

registered, or domiciled, in the Cook Islands, has a majority ownership by nationals of the Cook

Islands and generally, or wholly, employs people that permanently reside in the Cook Islands), and can show a successful term track record of operating in the Cook Islands.

During the design process, local contractors were requested to submit their interest in providing services to the project. Their names, contacts and general skill areas are contained in the table below, and their actual registration forms are attached in Appendix C.

There is no representation that any information supplied in this document in relation to the skills, or suitability, of these registered local contractors to complete any works associated with this project can be relied upon. The list is not extensive and is not meant to provide a full list of available local contractors. The list is also not exclusive, and any other local contractor not registered on this list would be considered in the same context as the ones that are contained on this list.

No screening has been undertaken on this list, and it is replied upon that the prospective tenderers would satisfy themselves that any contractor listed here is in fact a local contractor.

4.5

Further Information

Further information on this project can be requested through contacting Latu Kupa

( latu@kew.com.ws

). No individual correspondence will be entered into with any one prospective tenderer, however, if deemed to be suitable at this point in the project process, further information may be released to all prospective tenderers by way of the Cook Islands tender website where this document has been sourced from. www.tematovai.com

; www.procurement.gov.ck

; www.pwwa.ws

; www.gets.govt.nz

10 | Report for Cook Islands Government - Te Mato Vai Stage 2 - Construction and Operation, 51/32561/00

Company Contact Person Contact

Number

Email Postal

Address

Staff Comments

AC Drainage

Limited

Riki Cowan

Baker Tree Services

Limited

Nooroa Baker

Chris Holford Chris Holford

G & S Contractors Robert Wichman

Landholdings

Limited

Maoate

Contractors Limited

Master Builder

Mike Rennie

Builders Limited

Pati's Landscaping

& Construction

Limited

PTS The Plumbing

Shop

W.G. Doherty

Paul Maoate

Vira Williams

Mike Rennie

Samuel Patiora

Heather

Ian Ibbetson

+682 23582

+682 58723

+682 22164

+682 55964

+682 28499

+682 71733

+692 26980

+682 26980

+682 23415

+682 55103

+682 31773

+682 54335

+682 78365

+682 20375

+682 55256

+682 21967

+682 54038

+682 22199

'+682 55199 acdrainage@hotmail.co.nz

trim4u@oyster.net.ck

PO BOX

041

Muri

PO BOX

3277

Avarua chrisholford214@gmail.com

N/A

Yes

Yes Yes

Yes Yes Yes

Yes Yes gns.diggas@gmail.com

PO BOX

2033

Arorangi landholdings@oyster.net.ck

PO BOX 94 Yes

Yes Yes Yes

Yes Yes Yes

Yes

Yes

3

5

1

7

Arborist

52 mcontrac@aitutaki.net.ck

teuvira@hotmail.com

rennie@oyster.net.ck

patland@oyster.net.ck

ptsplumber@gmail.com

PO BOX

132

Aitutaki

PO BOX

3290

PO BOX 32

Avarua

PO BOX

3080

Avatiu

Rarotonga

PO BOX

154

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Yes Yes

11

-

30

8

8

Report for Cook Islands Government - Te Mato Vai Stage 2 - Construction and Operation, 51/32561/00 | 11

Rarotonga Mining

Limited

Charlie Strickland

Rarotonga

Plumbings &

Drainage Limited

Rio Heather

Moana Bates

Rio Heather

RVK Contractors

Limited

S & T Contractors

Limited

T & M Heather

Limited

Keta Williams

Henry Ariihe'e

Joseph Heather

+682 55770

+682 25218

+682 55218

+682 72849

+682 57027

+682 55359

+682 26699

+682 55929

+682 24249

+682 55688 tinairo@oyster.net.ck

mbates@raroplumbing.co.c

k

PO BOX

203

Avarua

PO BOX

845 vantay7@hotmail.com

keta-ttn@oyster.net.ck

ariihee@oyster.net.ck

jojocontractorheather@gma il.com

PO BOX

2197

Arorangi

PO BOX

328

PO BOX

362

PO BOX

303

Avarua

Rarotonga

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Yes

Yes Yes Yes Yes

5

9

1

Aggregate supplier

26

12

17

12 | Report for Cook Islands Government - Te Mato Vai Stage 2 - Construction and Operation, 51/32561/00

Appendices

Appendix A

Drawings

Drawings Content:

51-32561-01-G001 – Water Supply - Cover Page

51-32561-01-W002 – Avana – WTP Layout Plan

51-32561-01-W003 – Avana – Process Flow Diagram

51-32561-02-W002 – Avatiu – WTP Layout Plan

51-32561-02-W003 – Avatiu – Process Flow Diagram

51-32561-03-W002 – Matavera – WTP Layout Plan

51-32561-03-W003 – Matavera – Process Flow Diagram

51-32561-04-W002 – Akaoa – WTP Layout Plan

51-32561-04-W003 – Akaoa – Process Flow Diagram

51-32561-05-W002 – Ngatoe – WTP Layout Plan

51-32561-05-W003 – Ngatoe – Process Flow Diagram

51-32561-06-W002 – Papua – WTP Layout Plan

51-32561-06-W003 – Papua – Process Flow Diagram

51-32561-08-W002 – Taipara – WTP Layout Plan

51-32561-08-W003 – Taipara – Process Flow Diagram

51-32561-09-W002 – Takavaine – WTP Layout Plan

51-32561-09-W003 – Takuvaine – Process Flow Diagram

51-32561-10-W002 – Totokoitu – WTP Layout Plan

51-32561-10-W003 – Totokoitu – Process Flow Diagram

51-32561-11-W002 – Tupapa – WTP Layout Plan

51-32561-11-W003 – Tupapa – Process Flow Diagram

51-32561-12-W002 – Turangi – WTP Layout Plan

51-32561-12-W003 – Turangi – Process Flow Diagram

Appendix B

– Watercare Water Quality Report

Water Quality Report

Appendix C

– Local Contractors

Contractor Registration Sheets:

AC Drainage Ltd

Baker Tree Services Limited

Chris Holford

G&S Contractors

Land holdings Limited

Maoate Contractors Limited

Master Builder

Mike Rennie Builders Limited

Pati’s Landscape & Construction Limited

PTS The Plumbing Shop

Rarotonga Mining Limited

Rarotonga Plumbing & Drainage Limited

Rio Heather

RVK Contractors Limited

S&T Contractors Limited

T&M Heather Limited

Download