Best Practice Guide for CPs on Modem Conformance

advertisement
Best Practice Guide for
CPs on Modem
Conformance Testing
Issue 1.1
August 2015
Legal Statement
Disclaimer
Openreach makes every effort to ensure the information in this presentation
is accurate at the time of compilation, however, Openreach does not
represent that it is complete and Communications Providers should check
with Openreach for the latest available information. Any developments
carried out by a CP based on the contents of this slide-pack are entirely at the
CP’s own risk.
© British Telecommunications plc 2015
Contents
 Purpose of this Guide
 Case Study : CP achieving MCT Full pass in First Attempt
 Best Practices :







Working with Vendors and General Readiness
Form wise form submission
Device Submission
Standby List
Gatekeeper tests
OAM/CFM Loopback test
Full Cycle MCT
 Frequently Asked Questions
 References
 Glossary of Terms
Introduction : Purpose of this Guide
This best practice guide is designed to help CPs through the MCT process in order to help
minimise rejections from the registration form submission and improve your chances of success in
MCT testing.
Openreach has observed a number of common issues both with completion of the registration
form which results in resubmission and delay, and where devices are not prepared correctly to
meet the standards defined in the technical specifications which result in them failing the MCT
process. Many of these mistakes can be prevented with careful preparation in conjunction with
the Vendors you have chosen to provide your device.
This guide reflects best practice at each of the following stages MCT:
• Working with vendors & general readiness
• Formwize form submission
• Device submission
• Standby list
• Gatekeeper tests
• OAM/CFM Loopback test
• Full cycle MCT
Case Study : How a CP Achieved MCT Full Pass at the First Attempt
Obtaining MCT full pass at the first attempt is quite achievable. CPs have achieved this milestone by proper
planning and taking appropriate steps. Here are the steps taken by one such CP:
Prepare well
The CP ensured
that their
vendors
understood
exactly what was
required to pass
MCT.
They focused on
SIN 498 and MCT
process.
Engaging
Stakeholders
They entered
discussions with
Vendors, and
Openreach to
obtain
clarification and
answer specific
concerns with
SIN 498 and the
MCT Process . So
they were clear
on the process
and MCT
requirements.
Focus on Key
Areas
Some test results
will make a
device fail
straight away
while others will
result in a
conditional pass.
The CP focused
firstly on the
Tests first that
would result in a
straight fail, then
also working on
preparing for all
other test
parameters.
Avoiding Basic
Mistakes
The CP was very
careful with the
common settings
and device
standard
operations. They
provided specific
information
which could help
during testing.
This reduced the
need to clarify
elements with
the CP saving
time and test
failures.
Proactive and
positive
approach
The CP accepted
and reviewed
each set of Test
Feedback
proactively. They
put real effort to
ensure device
would be ready.
This helped them
to minimise the
potential
failures.
Best Practice : Working with Vendors and General Readiness
You should:
 familiarise yourself with the MCT process and associated documentation. This includes the
Process Guide [https://www.openreach.co.uk/orpg/home/products/super-fastfibreaccess/cpeenablement/cpeenablement.do]
 ensure that all of your vendors are aware of the standards set out in BT SIN 498. This
document also provides a detailed breakdown of the modem conformance test (MCT)
requirements to enable a piece of vendor CPE to be validated against the CPE Requirements.
 ask your vendors to confirm that the elements of your device that they are responsible for will
pass all of the relevant tests described in SIN 498 before it is presented for testing.
 if you need help, contact the Openreach MCT Front Door team and they will set up a
conference call with our technical experts to provide additional support and guidance.
 focus on key tests which can straightaway mark the device as a failed device.
 avoid committing basic mistakes like not configuring the device properly for DHCP or PPP
authentication prior to submitting it. These common mistakes delays testing and sometime
results into failure.
Best Practice : Form wise form submission
 There are a number of mandatory conditions which require YES to be recorded against these
questions. If these are not correct your form may get rejected while screening.
– 21) Is CPE fully configured and implemented for Vectoring (i.e. vector ready) on this
device and firmware version?
– Device must have vectoring implemented as we cannot accept a device which has not
been implemented with Vectoring.
– 22) Is CPE configured for AELEM (mode ELE-M1) on this device and firmware
version?
 Device must be preconfigured with AELEM as this is mandatory for Openreach Network.
– 23) Is CPE configured for downstream PHY Layer retransmission on this device and
firmware version?
 We cannot accept a device which is not configured for downstream PHY Layer
retransmission.
–
26) Is the CPE configured for VLAN ID 101 on this device and firmware version?
 We cannot accept a device for MCT which is not configured for VLAN ID 101.
Best Practice : Device Submission
 Please note the following specific items before presenting a device to Openreach for MCT.
 Please discuss with your chipset vendor around the presence of v43 tones on the device. The
presence of V43 tone on your device will make it a fail.
 Please ensure that development of the device has not turned off Seamless Rate Adaption.
 Please check for IGMP implementation. The device must be presented with it enabled as default.
Multicast channels should be viewed and traffic should flow.
 For Vendor ID Reporting, the device must show the Serial Number and not the MAC address.
 Please ensure the device should have below features enabled for OAM loopback tests as default.
 Support of Loop Back Messages
 Support of Ethernet 802.3ah Loopback
 Device should not break the ANFP mask defined for different profiles into SIN. It should be
compliant with the requirements of Part C of the BT Access Network Frequency Plan.
Best Practice : Standby List
 Once you have received the slot confirmation email, please note the following:
– If you want the device to be included in the Standby list, then please confirm in reply to the
slot confirmation email and send your devices immediately to Openreach.
– Once a device is submitted for the standby list, Openreach will perform the Gatekeeper1
test in next available slot.
– Please provide all the settings and required details for the gatekeeper1 test.
– Once the device has passed Gatekeeper1 test, it will be added into standby list. In the event
of a slot becoming available at short notice the next device on the Standby List will enter
MCT. Once MCT has started the original slot booked for the device will be released.
– Please note once added into standby list, no firmware changes are allowed.
– Please note that no device can be added into standby list without passing gatekeeper tests.
– Please note if you fail a Gatekeeper 1 test for the Standby List and cannot fix the issue for
Gatekeeper two test, then you will keep your original slot, however you will only have 1
Gatekeeper test remaining to get into the MCT cycle.
Best Practice : Gatekeeper Tests
 Please note the following important steps while going through the Gatekeeper tests.
– Please provide us all information requested in the additional questions document sent with
the slot confirmation email.
– Gatekeeper tests are carried out in order to check the device is ready for full Cycle MCT. It
must not be considered as a development trial cycle. Please ensure your device is ready to
pass the Gatekeeper test.
– Only the following list of tests will be performed as part of Gatekeeper Testing:




Compliance to ANFP Part C
Use of Tone-sets A43 and/or A43c
PPP or DHCP Session Establishment
OAM 2 Compliance (TBC)
– Please ensure all the settings related to these tests are enabled.
– Please submit 2 device units on or before the required date.
– Where Gatekeeper 1 test fails, please analyse and fix all issues identified and provide the
fixed firmware loaded devices within the timescales advised. Gatekeeper2 test is the last
chance for passing the Gatekeeper test.
– Each device will only get 2 Gatekeeper tests to enter a full MCT cycle.
Best Practice : OAM/CFM Loopback test
 OAM loopback is a mandatory test and failing this means the device will be either failed or
would be given only a conditional pass depending on the observation.
 On observation of the devices that under went MCT,the percentage of failure of the device is
high around the OAM.
 So we have come up with the below test case that can be performed in your environment
itself.
 CFM/OAM test has two levels:
 MD Level 1 for Openreach testing from L2S to Modem.
 MD Level 2 for the CP.
 CP can send traffic through the L2S as part of their data service and test themselves
 Below are few wireshark captures which contains the frame format of the service layer OAM
(802.1ag/Y.1731) and EFMOAM (802.3ah) as sent from the Openreach L2S and DSLAM
respectively:
 CFM LBM Single: single LBM frame as transmitted by the Openreach L2S to the modem/CPE at MD Level 1
 CFM LBMs with modem LBRs: capture of a test showing the loopback replies from an Openreach modem at MD
level1
 EFM OAM loopback: shows the EFM initialisation, the command from the DSLAM for the modem to apply a loopback
(frame 49) and subsequently to remove the loopback (frame 77).
Best Practice : OAM/CFM Loopback test
 You can generate the loopback messages in the following ways.
– A Third party freeware program like Colasoft can be used to transmit these frames into a
network from a PC.
– You can use a proper test equipment also to transmit these frames into the network.
– Another test possibility is for a sponsor CP to send service layer OAM at MD level 2 from
their network down to the CPE over a live access.
 You can perform these tests before submission of our device to the Gatekeeper tests.
 This will help to identify any issues earlier and will avoid the device failure or conditional pass.
Best Practice : Full Cycle MCT
 Please provide an additional 3 devices by the agreed date. Any delay in providing the devices
may result loss of the slot to the next device on the Standby list.
 Please provide any additional settings and steps that our test team may require to follow while
Testing. This helps our test team while executing the tests and may prevent failures due to
confusion.
 Openreach will advise any configuration issues immediately. Please respond as soon as
possible, especially where your advice on settings or steps can correct the result. The later this
additional information is provided in the test slot diminishes the possibility that testing can be
repeated, so please react as quickly as possible.
 Openreach will provide you with a weekly Test results Matrix and details of any test failures
found. Please review these issues when you see them, however Openreach will not be
accepting fixes during the test cycle.
 When the MCT cycle has finished, a full test report will be sent detailing all the issues and the
final result. If the device has not passed the CP can resubmit the device for MCT when all the
failures are fixed and can apply to go onto the standby list.
Frequently asked questions





I am unable to submit the Formwise and receive errors while submitting. Whom should I contact?
Where I can approach for any enquiry for MCT?
– Please write to MCT.FRONT.DOOR@OPENREACH.CO.UK for any MCT related enquiries or
issues.
Can my engineers visit Test Facility prior to submitting the device?
– CPs cannot access the MCT facility but a CP can access the Openreach Performance Test
Facility (PTF) which provides access to the Openreach Network and the CPs own network
allowing testing against the current and next Network release. It does not provide any test or
diagnostic equipment.
How do you book access to the Performance Test Facility?
– Please write to MCT.FRONT.DOOR@OPENREACH.CO.UK with your device MCT and launch
plan, We will allot and confirm the schedule. Additionally please use the link below for further
information on the PTF.
– https://www.openreach.co.uk/orpg/customerzone/helpandsupport/cts/documentation/ctsdocume
ntation/downloads/AdastralParkTestFacilityGuide10.pdf
Can we provide new firmware in the middle of MCT testing?
– No Openreach cannot accept an new version of Firmware once the device has passed the
Gatekeeper Test or in the MCT slot.
Can I send the units and firmware separately and Openreach can load the firmware?
– No, Openreach need all devices to be pre loaded with the firmware and all setting enabled as
default.
References
Please refer to product description and the contracts documents for the latest updates,

GEA-FTTC Product Description – https://www.openreach.co.uk/orpg/customerzone/products/superfastfibreaccess/fibretothecabinet/description/productdescription.do

GEA Contract –
https://www.openreach.co.uk/orpg/home/products/super-fastfibreaccess/contracts/sffacontracts.do

CPE Enablement –
https://www.openreach.co.uk/orpg/home/products/superfastfibreaccess/cpeenablement/cpeenablement.do

Performance Test Facility –
https://www.openreach.co.uk/orpg/customerzone/helpandsupport/cts/documentation/ctsdocumentati
on/downloads/AdastralParkTestFacilityGuide10.pdf

SIN – http://www.sinet.bt.com/

New Customers – http://www.openreach.co.uk/orpg/home/ourcustomers/becomeacustomer.do
Glossary of Terms
Acronym
CP
CPE
EMP
EU
FTTC
GEA
MCT
NGA
PTF
SIN
STC2
VDSL
OAM
IGMP
Meaning
Communications Provider
Customer Premise Equipment
Equivalence Management Platform
End User
Fibre to the Cabinet
Generic Ethernet Access
Modem Conformance Test (i.e. SIN-498 Device verification testing)
Next Generation Access
Performance Test Facility
Supplier Information Note
Safe To Connect2
Very-high-bit-rate digital subscriber line
Operations, Administration, Maintenance
Internet Group Management Protocol
Download