Capacity Forecast Report Mark Ruane Director, Market Credit CWG / MCWG March 10, 2015 ERCOT Public 1 Capacity Forecast Model ERCOT began posting of the capacity forecast model results commencing February 24th for Operating Day February 23rd. The report shows: • Hourly forecast MW excess reserves for OD+1 through OD+6, with partial day forecast for OD+7. • For OD-1 through OD-7, • Hourly MW forecast for the Operating Day generated on the OD-1 relative to that day (eg the most recent capacity forecast for that day) • Actual MW excess reserves for that hour • HUBBUSAVG price for the hour Forecast values are P50. ERCOT may consider possible Px forecast values. ERCOT Public 2 Capacity Forecast Model For the ODs for which results are available, the OD+1 forecast more often than not underestimated reserves on the OD (consistent with initial concept modelling). OD+1 Forecast MW o/(u) Actual Monday, March 02, 2015 Saturday, February 28, 2015 Thursday, February 26, 2015 Tuesday, February 24, 2015 Sunday, February 22, 2015 Friday, February 20, 2015 Wednesday, February 18, 2015 Monday, February 16, 2015 1 3 Hour 5 7 9 11 13 15 17 19 21 23 -10,000--5,000 False positive ERCOT Public -5,000-0 0-5,000 5,000-10,000 False negative 3 Capacity Forecast Model Percentage error OD+1 Forecast % o/(u) Actual Monday, March 02, 2015 Saturday, February 28, 2015 Thursday, February 26, 2015 Tuesday, February 24, 2015 Sunday, February 22, 2015 Friday, February 20, 2015 Wednesday, February 18, 2015 Monday, February 16, 2015 1 3 Hour 5 7 9 11 13 15 17 19 21 23 -40%--20% False positive ERCOT Public -20%-0% 0%-20% 20%-40% 40%-60% False negative 4 Capacity Forecast Model There are five ODs for which there are both OD+4 and actuals. For each of the days the OD+4 forecast was higher than actual. OD+4 Forecast MW o/(u) Actual Tuesday, March 03, 2015 Monday, March 02, 2015 Sunday, March 01, 2015 Saturday, February 28, 2015 Friday, February 27, 2015 1 3 5 7 9 11 13 15 17 19 21 23 Hour 0-5,000 Lesser error ERCOT Public 5,000-10,000 10,000-15,000 Greater error 5 Capacity Forecast Model For the five days with both OD+1 and OD+4 forecasts there was generally a material reduction in forecast error. OD+1 Forecast Error o/(u) OD+4 Error Tuesday, March 03, 2015 Monday, March 02, 2015 Sunday, March 01, 2015 Saturday, February 28, 2015 Friday, February 27, 2015 1 3 Hour 5 7 9 11 13 15 17 19 21 23 -15,000--10,000 Reduced error ERCOT Public -10,000--5,000 -5,000-0 0-5,000 Increased error 6 Capacity Forecast Model Questions ERCOT Public 7