Agenda • • • • • • • • • Background – LRP 2008-2016 Long Range Facilities Plan 2013-2017 Planning Survey and Process Enrollment Projections Academic Program Needs ASF to FTE Projections Summary Long Range Facilities Plan Questions, Considerations and Comments Campus Detail • Classroom Utilization • Swing Space Needed • CPCC and County Timeline LRP Planning Process used in 2007 CCBenefits Data Program Outlook Survey NCCCS Planning Process Enrollment Projections Listening Forums CPCC 10-Year Enrollment Projections in 2006 FTE Projections (56.7% Cumulative Growth Rate) 23000 22,063 22000 21,325 21000 20,243 19,497 20000 18,745 19000 17,716 18000 17000 16,019 16000 15000 14000 14,652 14,073 16,489 16,967 Future High Growth Programs Identified • AA, AS and AFA Degree Programs (General Education Courses) • Developmental/Remediation Courses • Basic Skills Programs • Health Care and Sciences Programs • Information Technology Programs • Geospatial Program • Manufacturing & Engineering Technologies • Construction and Trades • Green Industry • Education and Teacher Training • New and Expanded Continuing Education Programs • Library Resources Summary of 10-Year Plan in 2008 PROJECT NEW GSF REHAB GSF 2008 Basic Skills Literacy Center 60,000 $18.9 mil $18.9 mil 2009 Levine Campus Phase 3 Advanced Tech Center Rehab Ballantyne Center (included in PLCMC) Cato Campus Phase 3 120,000 $43.2 mil $16.2 mil $76.9 mil 50,000 $17.5 mil 2011 Kratt Replacement Hagemeyer LRC Rehab 100,000 $35.1 mil $26.4 mil $61.5 mil 2013 North Campus Phase 4 Central Campus @ Charlottetowne 60,000 100,000 $28.5 mil $38.0 mil $66.5 mil 2015 Central Campus @ Central High Future Northwest Campus 100,000 100,000 $41.1 mil $41.1 mil $82.2 mil 2017 Central Campus @ Quad 100,000 $37.0 mil $37.0 mil 10-Year Total 790,000 63,690 110,493 174,183 AMOUNT TOTAL $343 mil Note: Based on current construction cost estimates shown in current dollars with estimated inflation of 7% in 2008; 8% in 2009-11; 4% thereafter. Completed Construction Projects PROJECT COMPLETION DATE 3D Visual Arts, CAT November 2009 Culinary Arts Building November 2009 Student Deck I January 2010 Health Careers April 2010 Faculty Deck June 2010 Student Deck 3 August 2010 Cato Foodservice, Bookstore January 2012 Construction Projects -WIP PROJECT COMPLETION DATE Harper Addition & Renovation May, June, July 2012 CAT Scene Shop July 2012 Taylor Hall Expansion July 2012 Central High Renovation ESS December 2012 Education Center December 2012 Central Energy Plant Spring 2013 New Classroom Building November 2013 Citizens Renovation, Data Center December 2013 Academic Program Planning Survey Results in 2012 January 2012: Online Survey was developed by the Office of Planning and Research The 55 requests were prioritized by the Academic Deans and the VP, Learning Unit Top Academic Programs Indicating Maximum Growth Potential The Academic Programs survey section resulted in 55 requests for new or renovated space 33 high priority requests were voted on by members of Facilities Partners • • • • • • • • • • • • Sciences General Education Basic Skills Nursing Education Paralegal Technology Library Resources EMS and EMT Culinary Arts Re-Careering Center Career and College Promise Arts and Communication Dental Assisting Updated 5-Year Enrollment Projections CPCC FTE (FY13 County Operating Budget) 22,000 21,000 20,000 19,000 18,000 17,000 16,000 15,000 14,000 18,538 18,863 18,910 19,099 20,667 20,066 19,481 16,980 15,997 14,073 14,652 35 percent FTE growth 12 percent FTE growth 21,288 Updated List of Projects 2012 PRIORITY PROJECT 1 Renovation of Giles Science Labs (a) 2 Central Campus @ Charlottowne 3 Cato Campus Land Acquisition 3 Cato Campus Phase 3 3 Cato Structured Parking Spaces 4 Central Campus Land Acquisition 5 Terrell Renovation & Expansion (b) 6 Basic Skills Literacy Center 7 Levine Campus Land (transfer from county) 7 Levine Campus Phase 3 7 Levine Structured Parking Spaces 8 Hendrick Automotive Expansion 9 Merancus Campus Land Acquisition 9 Merancus Campus Phase 4 (c) 10 Adv Tech Center Renovation & Addition (d) 10 Harper Campus Phase 4 11 Harris Campus Land Acquisition 12 Hagemeyer LRC Renovation 13 Central Campus @ Central High + Deck (e) 14 Kratt Replacement Classroom SPACES NEW GSF REHAB GSF TOTAL GSF 21,000 100,000 50,000 500 81,500 200,000 40,320 120,000 800 13,000 100,000 75,000 150,000 63,690 110,493 1000 150,000 150,000 2,300 1,189,500 235,503 AMOUNT 21,000 $ 121,000 $ $ 171,000 $ $ $ 292,820 $ 492,820 $ $ 612,820 $ $ 625,820 $ $ 725,820 $ 864,510 $ 1,014,510 $ $ 1,125,003 $ 1,275,003 $ 1,425,003 $ 5,250,000 25,500,000 3,000,000 12,750,000 10,250,000 9,000,000 30,476,500 56,100,000 31,100,000 16,750,000 3,315,000 1,000,000 26,500,000 33,363,000 41,250,000 3,000,000 24,308,460 59,250,000 38,250,000 1,425,003 $ 430,412,960 TOTAL AMOUNT $ $ $ $ $ $ $ $ 5,250,000 30,750,000 33,750,000 46,500,000 56,750,000 65,750,000 96,226,500 152,326,500 $ $ $ $ $ $ $ $ $ $ $ 183,426,500 200,176,500 203,491,500 204,491,500 230,991,500 264,354,500 305,604,500 308,604,500 332,912,960 392,162,960 430,412,960 Questions, Considerations, Comments • All prices are based on FY 2012 costs. • Additional land is a critical needs. The acquisition of land at existing campuses is addressed. Building of a new campus is not addressed. • Utilization of space at each campus should be a factor in project prioritization. • Should the expansion or moving of major programs (i.e. health, trades, etc.) be considered? • Planning for swing space during facility renovation or demolishing must be included. Actual ASF vs. County Goal of 90% ASF 2,500,000 CPCC With County Funding County Goal of 90% ASF CPCC Without Additional County Funding Beyond 2014 2,000,000 90% 90% 90% 90% 90% 90% 76% 90% 1,500,000 90% 92%90% 90% 69% 66% 68% 70% 64% 62% 60% 63% 63% 58% 67% 1,000,000 500,000 0 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 Swing Space Needed • Renovation of Giles • Cato Parking • Hendrick Automotive Expansion • Adv. Technology Center Renovation & Expansion • Terrell Renovation and Expansion • Kratt Replacement • Hagemeyer LRC Renovation • Basic Skills Literacy Center CPCC and County Timeline June 11, 2012 – Cabinet review of plan June 11, 2012 – Draft of plan to Mecklenburg County staff June 13, 2012 – F&F Committee reviews the plan July 11, 2012 – Full Board reviews plan June 30, 2012 – CCBAC orientation process July – August 2012 – agencies present plans and needs to CCBAC September – December 2012 – CCBAC reviews, applies criteria, ranks and prioritizes plans. January 2013 – CCBAC recommendation to County Manager. CPCC Campus Locations Cato Campus 8120 Grier Road Charlotte, NC 28215 704.330.4801 Central Campus 1201 Elizabeth Avenue Charlotte, NC 28235 704.330.2722 Harper Campus 315 West Hebron Street, Charlotte, NC 28273 704.330.4400 Harris Campus 3210 CPCC Harris Campus Drive Charlotte, NC 28215 704.330.4601 Levine Campus 2800 Campus Ridge Road Matthews, NC 28105 704.330.4200 Merancas Campus (formerly North) 11930 Verhoeff Drive Huntersville, NC 28078 704.330.4101