HVLS Fans - College of Engineering | SIU

advertisement
PROPOSAL
HVLS FANS
Alex Kee
Bill Ennis
to AISIN MFG. ILLINOIS
by SALUKI ENGINEERING COMPANY, TEAM 48
Joel Chaplin
Micah Buchanan
Kyle Florian
Ryan Riffel
HVLS Fans: Aisin Mfg. Illinois
Page 1 of 47
November 18, 2010
Saluki Engineering Company
Senior Engineering Design Center
College of Engineering – Mailcode 6603
Carbondale IL 62901-6603
618-453-7031
Jim McReynolds
Facilities Engineer
11000 Redco Drive
Aisin Manufacturing Illinois
Marion, IL 62959
Mr. McReynolds,
This letter is in response to your request for proposals concerning the overall comfort of the
employees at your facility. Our company has assembled an impressive and competitive proposal
for your project, which you will find attached to this letter. Furthermore, I would like to
personally thank you for giving us the opportunity to submit a design proposal for this project.
The proposal is based on the need for an effective and economical system to provide a
comfortable working environment. Design goals include improvements in thermal comfort and
heating/cooling costs.
Once again, thank you for your consideration.
Respectfully,
Alex Kee
Project Manager, TEAM 48
Saluki Engineering Company
HVLS Fans: Aisin Mfg. Illinois
Page 2 of 47
Executive Summary
The Saluki Engineering Company (SEC) proposes to study three design options for the current
Heating, Ventilation, and Air Conditioning (HVAC) systems at AISIN Manufacturing Illinois
(AMI) to reduce temperature and energy costs, and to make a recommendation as to which
design should be implemented into AMI’s facility. The criteria for the design are cost,
effectiveness, and economical benefit. The primary reason for modifying the current HVAC
system is to create a system to maintain a comfortable environment through the hot summer
months. During research for this proposal, certain standards from the American Society of
Heating, Refrigeration, and Air Conditioning Engineers (ASHRAE) were found regarding
thermal comfort, and the design recommendations will be based on these standards.
Design 1 will consist of adding a new chiller to the current HVAC system. The size of the new
chiller needed will be calculated based on the difference between the current load capabilities
and the load requirements during the hot summer months. This addition will create a greater
chiller efficiency and lower temperatures for a better work environment in the facility. Design 2
will consist of adding High Volume Low Speed (HVLS) fans to the facility to supplement the
current HVAC system to improve the humidity level and air flow, which will increase comfort
even if the temperature stays the same. If Designs 1 or 2 will not provide the desired conditions
cost-effectively, then the two options will be combined to make up Design 3. An energy audit
and economic analysis will also be included in the study.
The projected date of completion for the proposed engineering study and design recommendation
is April 26th, 2011. It is estimated that there will be no cost to the Client for the study and design
recommendation, since this project will be carried out from a consulting standpoint, and all
resources and instruments needed are on hand.
HVLS Fans: Aisin Mfg. Illinois
Page 3 of 47
RESTRICTION ON DISCLOSURE OF INFORMATION
The information provided in or for this proposal is the confidential, proprietary property of the
Saluki Engineering Company of Carbondale, Illinois, USA. Such information may be used
solely by the party to whom this proposal has been submitted by Saluki Engineering Company
and solely for the purpose of evaluating this proposal. The submittal of this proposal confers no
right in, or license to use, or right to disclose to others for any purpose, the subject matter, or
such information and data, nor confers the right to reproduce, or offer such information for sale.
All drawings, specifications, and other writings supplied with this proposal are to be returned to
Saluki Engineering Company promptly upon request. The use of this information, other than for
the purpose of evaluating this proposal, is subject to the terms of an agreement under which
services are to be performed pursuant to this proposal.
HVLS Fans: Aisin Mfg. Illinois
Page 4 of 47
Table of Contents
Transmittal Letter (AK) ............................................................................................................... 2
Non-Disclosure Statement ............................................................................................................ 4
List of Figures ................................................................................................................................ 7
List of Tables ................................................................................................................................. 7
Introduction (AK) ......................................................................................................................... 8
Literature Review (MB) ............................................................................................................... 8
HVLS FANS (JC/RR) ............................................................................................................................. 8
Table 1: Comparison of HVLS Fans [1-3] (RR)................................................................................... 9
Concepts (JC) ........................................................................................................................................ 9
Figure 1: Typical Air Foil Design for Fan Blade [4] (JC) .................................................................. 10
Figure 2: HVLS Fan Air Circulation [4] (JC) ..................................................................................... 10
Benefits (JC) ....................................................................................................................................... 11
HVAC SYSTEMS (AK/BE) ................................................................................................................. 11
Chillers - Background (BE) ................................................................................................................ 12
Chiller Controls (BE) ..................................................................................................................................... 12
Advantages of Chillers (BE)........................................................................................................................... 13
Current Setup (AK) ............................................................................................................................. 13
Figure 3: Aisin HVAC Layout ( ) ...................................................................................................... 14
III. THERMAL COMFORT (MB) ..................................................................................................... 15
Figure 4: Thermal Interaction of the Human Body with the Environment [12] (MB) ....................... 16
Figure 5: ASHRAE Summer and Winter Comfort Zones [12] (MB) ................................................ 16
Figure 6: Air Speed to Offset Temp above Warm-Temp Boundaries of Figure 2 [12] (MB) ............ 17
Figure 7: Air Velocities and Operative Temperatures at 50% RH Necessary for Comfort of Persons
in Summer Clothing at Various Levels of Activity [12] (MB) ........................................................... 17
Figure 8: Draft Conditions Dissatisfying 15% of Population [12] (MB)............................................ 19
Figure 9: Percentage of People Dissatisfied as Function of Mean Air Velocity [12] (B) ................... 19
IV. SUMMARY (MB) ........................................................................................................................... 20
Basis of Design (RR) ................................................................................................................... 21
Table 2: Design Basis (RR) ................................................................................................................ 21
Project Description (AK/MB) .................................................................................................... 21
Figure 10: Block Diagram (MB) ......................................................................................................... 22
Engineering Specification (MB)................................................................................................. 22
Scope of Work (BE) .................................................................................................................... 22
Subsystems (MB/JC) ................................................................................................................... 23
HVLS Fans: Aisin Mfg. Illinois
Page 5 of 47
Current Load Capabilities (MB) ......................................................................................................... 23
Deliverables (MB) .......................................................................................................................................... 23
Energy Audit (MB) ............................................................................................................................... 23
Figure 11: Example for Energy used in Cooling (MB)....................................................................... 24
Deliverables (MB) .......................................................................................................................................... 24
Required Load Calculations (MB) ...................................................................................................... 24
Application for Cooling Load (MB) ................................................................................................... 24
Description of Heat Gain (MB) ...................................................................................................................... 24
Description of Cooling Load (MB) ................................................................................................................ 25
Figure 12: Schematic Relation of Heat Gain to Cooling Load [13] (MB) .......................................... 25
Design Conditions (MB) ................................................................................................................................ 25
Infiltration (MB) ................................................................................................................................. 26
Air Change Method (MB) .............................................................................................................................. 26
Auxiliary Heat Sources (MB) ............................................................................................................. 28
Occupancy (MB) ............................................................................................................................................ 28
Lights (MB) .................................................................................................................................................... 28
Equipment (MB) ............................................................................................................................................. 28
Conduction (Thermal Transmittance) (MB) ....................................................................................... 29
RTSM for Cooling Load Calculations (MB) ...................................................................................... 31
Design Activities (MB) .................................................................................................................................. 31
Load Calculation Based on History of Energy Consumption and Ambient Temps. (MB)................. 31
Deliverables (MB) .......................................................................................................................................... 32
Design 1: Additional Chiller (AK) ....................................................................................................... 32
Design 2: HVLS Fans (JC) ................................................................................................................... 32
Deliverables (JC) ............................................................................................................................................ 33
List of Activities (JC) ..................................................................................................................................... 33
Design 3: Combined System (MB)....................................................................................................... 34
Control System (AK) ............................................................................................................................ 34
Economic Analysis (MB) ...................................................................................................................... 34
References (MB - compile/edit).................................................................................................. 35
Commercial (MB) ....................................................................................................................... 36
Resources Needed (MB) ....................................................................................................................... 36
Organizational Chart (MB) ....................................................................................................... 36
Draft Schedule (MB) ............................................................................................................................. 38
Draft Schedule - Detailed (JC/MB) ..................................................................................................... 39
AIL (MB) ............................................................................................................................................... 40
Appendix - Resumes
HVLS Fans: Aisin Mfg. Illinois
41
Page 6 of 47
List of Figures
Figure 1: Typical Air Foil Design for Fan Blade [4] ............................................................. 10
Figure 2: HVLS Fan Air Circulation [4] ............................................................................... 10
Figure 3: Aisin HVAC Layout .............................................................................................. 14
Figure 4: Thermal Interaction of the Human Body with the Environment [12].................... 16
Figure 5: ASHRAE Summer and Winter Comfort Zones [12] ............................................ 16
Figure 6: Air Speed to Offset Temp above Warm-Temp Boundaries of Figure 2 [12] ........ 17
Figure 7: Air Velocities and Operative Temperatures at 50% RH Necessary for Comfort of
Figure 8: Draft Conditions Dissatisfying 15% of Population [12] ........................................ 19
Figure 9: Percentage of People Dissatisfied as Function of Mean Air Velocity [12] ........... 19
igure 10: Block Diagram ....................................................................................................... 22
Figure 11: Example for Energy used in Cooling ................................................................... 24
Figure 12: Schematic Relation of Heat Gain to Cooling Load [13] ...................................... 25
List of Tables
Table 1: Comparison of HVLS Fans [1-3] .............................................................................. 9
Table 2: Design Basis ............................................................................................................ 21
HVLS Fans: Aisin Mfg. Illinois
Page 7 of 47
Introduction
In the summer months, when temperatures reach well above 90°F, buildings turn into ovens. To
counteract the outside conditions, most buildings are fitted with an air conditioning/ventilation
system. In some industrial settings with large machines creating a large amount of heat, these
systems are not sufficient to maintain a comfortable environment which creates a problem for
industrial production. Production requires employees to do the work needed to maintain a steady
process, but when employees are uncomfortable productivity can decrease. American Society of
Heating, Refrigeration, and Air-Conditioning Engineers (ASHRAE) provides optimum
environmental conditions for worker comfort. The goal of this project is to find a way to provide
such an environment to not only help to increase production through supplying thermal comfort,
but also cut down on energy costs.
Literature Review
HVLS FANS
High Volume Low Speed (HVLS) fans are a relatively new technology that is starting to gain
momentum in the HVAC world. Since the technology is so new, there are only a few major
producers of these fans which include Macro Air, BigAssFans, and Rite-Hite. Table 1 shows
some specifications of fans comparable in maximum displacement and horsepower from these
companies.
HVLS Fans: Aisin Mfg. Illinois
Page 8 of 47
Company
MacroAir
Model Name
MaxAir24
Diameter (ft.)
# of Blades
Power of Motor (HP)
Max Displacement (CFM)
Max Speed (RPM)
Max Effective Area (ft2)
Fan Weight
24
6
2.0
376,804
65
20,000
236
Big Ass
Fans
Powerfoil
X
24
10
2.0
345,941
42
20,000
439
Big Ass
Fans
Powerfoil
X Plus
24
10
2.0
368,516
39
30,000
446
Rite-Hite
Rite-Hite
Rite-Hite
Revolution
Revolution
Revolution
24
4
2.0
428,000
48
22,000
300
20
4
2.0
400,000
58
20,000
292
16
4
2.0
365,000
72
20,000
284
Table 1: Comparison of HVLS Fans [1-3]
Because Aisin has decided to test out a fan from Marco Air, this is where the project will start.
Macro Air has a wide range of fans from which to choose. They have a fan for any situation
and available in every electrical voltage, so they can be implemented into the existing electrical
system with minimal work. Currently, Aisin is using the MaxAir24 (see Table 1) as a
demonstration model on the floor.
Concepts
HVLS fans were designed by looking at the physics of air movement and at how to improve
overall efficiency. The first thing that was addressed was how to make a fan that needed a less
powerful motor. Since the laws of physics dictate that the power needed to drive a fan is
proportional to the speed of the fan cubed, the logical answer would be to create a low speed fan.
Using this logic engineers began looking at ways to design low speed fans. To do this they
turned their attention to the field of aviation. This is from where the idea came to use an airfoil
shape for the blades of the fan.
HVLS Fans: Aisin Mfg. Illinois
Page 9 of 47
Figure 1: Typical Air Foil Design for Fan Blade [4]
These airfoil blades let the fans move large quantities of air at very low speeds. The fan blades
use an air foil design with greater pitch on the blade to get air flow upwards of 300,000 cfm and
produce around 100 lbf of thrust. The chord length also affects the performance of the blade (in
general, the longer the chord length the more lift the blade will have). The design is especially
impressive as this air movement is all done at a low velocity, allowing workers to remain
undisturbed by windy conditions. Instead the fans produce low speed columns of air that hit the
ground and spread out along the floor, reaching well beyond the footprint of the fan. This effect
is called the floor jet and has a height that is directly proportional to the diameter of the fan.
Under ideal conditions a 24ft fan would produce a floor jet of 108 inches. The figure below
illustrates the air movement of the fan in a large room.
Figure 2: HVLS Fan Air Circulation [4]
Another carry over from aviation is the concern for weight. Since weight is the enemy when one
is trying to make something fly, the wings and rotors are made of lightweight strong materials
such as aluminum and advanced alloys. Using this technology in the fans helped reduce the
HVLS Fans: Aisin Mfg. Illinois
Page 10 of 47
rotating mass and hanging weight of the fan, and since the technology is already there, costs are
kept reasonable. The efficient design along with a small rotating mass allows these fans to be
powered by 1-2hp electric motors. This translates to more economical operating costs since
fewer fans would be required to keep conditions comfortable.
Benefits
HVLS fans result in decreased energy costs in relation to heating and cooling in every facility
that has been looked into. From research, the actual energy savings have varied based on the
size of the building, layouts, and individual comfort levels, but seem to range from 10 to 30%.
Besides energy savings, there are also many other benefits of HVLS fans. When installed in
buildings, people report that the humidity levels have decreased significantly, the air quality has
improved due to better mixing of the air, and worker productivity has also improved. In the
summer months, these fans are best used at a high speed setting, pushing a lot of air down from
the ceiling. In the winter, most people want to reverse the fans to get the best effect. However,
this is actually counterproductive. The most effective way to use these fans during cold months
is to keep them blowing down but at a very slow speed. This gradually moves the hot air down
to the workers without creating any draft effect or wind chill, as discussed later. [4-8]
HVAC SYSTEMS
In order to study the effects of adding HVLS fans to the environment, it is important to have a
solid understanding of HVAC (heating, ventilating, and air-conditioning) systems – both of how
they work and what the current setup at Aisin is. If the addition of fans is insufficient to reach
requirements, it is possible that additional cooling will be required via a new chiller or some
other method of HVAC.
HVLS Fans: Aisin Mfg. Illinois
Page 11 of 47
Chillers - Background
HVAC chillers are refrigeration systems that provide cooling for industrial and commercial
applications. Chillers consist of a compressor, condenser, thermal expansion valve, evaporator,
reservoir, and stabilization assembly. Chilled water systems operate like a normal air
conditioning unit except they use water instead of refrigerant in the condenser unit. A watercooled air chiller works by pumping refrigerant through coils that cool the water, filling the
condenser coils with the circulating cool water. Refrigerant is compressed, creating a high
pressure gas. The condenser uses cool water to condense the compressed gas turning it into a
warm liquid. The warm liquid goes through the thermal expansion valve releasing refrigerant
into the evaporator while converting the warm liquid into a cool, dry gas. A hot gas bypass is
generally used to warm up the evaporator to stabilize the temperature of the chilled water. The
water is then pumped from the reservoir to the compressor to restart the cycle. The temperature
of the water pumped through the coils is determined by the set point of the chiller. The
temperature change through the chiller is typically around 10oF. The normal temperature of the
water leaving the chiller is generally around 45oF, so the water returning to the chiller is
generally around 55oF. [9]
Chiller Controls
There are three different sizes for the power sources of the chiller controls. These power sources
are given by three numbers separated by forward slashes, which refer to the voltage, frequency
and phase. The power sources for the controls come in the following sizes: 208-230/60/3,
380/50/3, and 460/60/3. HVAC chillers can have a local or a remote control panel with
temperature and pressure indicators. Some control units also have microprocessor controls,
emergency alarms, and an integral pump. HVAC chillers can also be used to cool plastics,
HVLS Fans: Aisin Mfg. Illinois
Page 12 of 47
printing equipment, laser cutting machines, and magnetic resonance imaging equipment. The
microcomputer control panel includes all controls necessary for safe and reliable operation of the
chiller. There are many types of controls available for chillers. Fastforward adaptive control is a
predictive control strategy used to compensate for load changes. Soft loading is a control used to
accommodate load changes or temperature set point by gradually applying these changes,
preventing unnecessary cycling by the chiller. Multi-objective limit arbitration keeps the chiller
focused on its main priority (evaporator exit temperature) until it can no longer obtain its ideal
temperature, then it switches to the chiller’s second priority. The adaptive frequency drive
control mathematically figures the best position for the inlet guide which allows the system to
run longer with higher efficiency. The variable primary flow control reduces the energy
consumed by pumps. Variable flow compensation improves the chiller’s ability to accommodate
variable flow. With this information, it will be possible to look into coupling the systems (HVLS
fans and chillers) to find the best method for controlling the systems. [9-11]
Advantages of Chillers
Air chillers are convenient as they permit components of the system to be sold separately,
allowing the engineer to strategically place different parts of the system to accommodate space
specifications. Chilled water refrigeration systems are preferred because of their contained use
of refrigerant. The refrigerant in these units is centralized minimizing the risk for leaks or
making them easier to contain if one does arise.
Current Setup
HVAC systems are used to make for a more comfortable indoor environment and are employed
by many different sizes of indoor environments ranging from an automobile to a 290,000 square
foot automobile component manufacturing plant such as Aisin Mfg. There are also different
HVLS Fans: Aisin Mfg. Illinois
Page 13 of 47
types of HVAC systems. Trane offers a Direct-Expansion Unitary System, where an evaporator
is in direct contact with the air stream, and a Chilled Water Applied System, which is the system
currently in use at Aisin. A chilled-water applied system uses “chilled water to transport heat
energy between the airside, chillers and the outdoors” (Trane). Trane is not the only HVAC
manufacturer on the market; during a period of expansion, Aisin doubled the size of its
manufacturing facility and added an Aaon HVAC system to the addition which is similar to the
existing Trane setup. The chillers at Aisin have a capacity of 400 tons, and are set to cool the
water to 42 oF. They are connected to seventeen roof top units that pump the cooled air. Twelve
of the roof top units are responsible for providing conditioned air to the main manufacturing
section of the building that is being studied (See Figure 3 – not to scale).
Figure 3: Aisin Manufacturing HVAC Layout
With temperatures topping around 83 to 85oF inside the manufacturing section, these chillers run
at maximum capacity 24 hours a day. During the summer months, the temperature level in the
plant often reaches unacceptable levels, and since the chillers are running at full capacity, there is
no way for the current system to keep the environment at a comfortable temperature.
HVLS Fans: Aisin Mfg. Illinois
Page 14 of 47
In such situations, many companies have made the decision to simply add another chiller to the
equation. However, chillers that are the size of those at Aisin are quite expensive, and there are
other ways to deal with these uncomfortable temperatures. In looking for a solution to the
problem at Aisin, the effect of airflow through the plant to make for a more comfortable working
environment will be studied. One way to improve the airflow is the addition of the HVLS fans
in order to circulate the cool air from the AC units to all employees on the plant floor.
THERMAL COMFORT
Thermal comfort, as stated by ASHRAE Standard 55, is “that condition of mind that expresses
satisfaction with the thermal environment”. In itself, thermal comfort is not quantifiable but is
based on one’s physical, psychological, physiological, as well as other processes. However, it is
possible from an engineering standpoint to procure quantitative stipulations for an environment
that will provide for thermal comfort for an estimated percentage of satisfied population. These
standards are based on combined calculations of a heat transfer energy balance of the human
body in varying conditions as well as results of surveys taken of people in these environments.
The environmental factors affecting a person’s thermal balance and therefore his or her thermal
comfort include the surrounding air dry bulb temperature, humidity, relative velocity, and
radiation [13]. Besides these, personal variables including the amount of activity and clothing of
a person also affect thermal comfort.
While some aspects of thermal comfort from the biological standpoint are beyond the scope of
this review, providing a comfortable work environment is essential for employee satisfaction.
Estimating thermal comfort can be simplified by doing an energy balance on the body (see
Figure 3), taking into consideration the majority of methods of heat transfer to and from the
body. [12]
HVLS Fans: Aisin Mfg. Illinois
Page 15 of 47
Figure 4: Thermal Interaction of the Human Body with the Environment [12]
The most applicable portion of thermal comfort for this project deals with the effect of wind
speed and humidity on thermal comfort (in relation to temperatures), both of which could
potentially be affected by the installation of HVLS fans and/or an additional HVAC unit.
Although based on a nearly sedentary level of activity, Figure 4 gives an estimate of acceptable
levels of operative temperature and humidity for environments of little to no air movement for
people wearing clothing appropriate for the season (1.0/0.5 clo winter/summer).
Figure 5: ASHRAE Summer and Winter Comfort Zones [12]
HVLS Fans: Aisin Mfg. Illinois
Page 16 of 47
With the addition of the HVLS fans, the hope is that the HVAC units will run at a lower load and
that a higher temperature will be acceptable with the increased air movement. This would allow
for potential energy saving. Figure 5 displays the air speed required to offset temperatures above
ideal operative temperature [12]. Similarly, Figure 6 shows necessary air velocities for operative
temperatures at 50% relative humidity to maintain comfort for different levels of activity
measured in mets.
Figure 6: Air Speed to Offset Temp above Warm-Temp Boundaries of Figure 2 [12]
Figure 7: Air Velocities and Operative Temperatures at 50% RH Necessary for Comfort of
Persons in Summer Clothing at Various Levels of Activity [12]
HVLS Fans: Aisin Mfg. Illinois
Page 17 of 47
It should also be mentioned that fans potentially could reduce dissatisfaction due to radiant
temperature asymmetry and vertical air temperature difference, as a significant amount of mixing
and more even conditions would occur throughout the plant, as discussed earlier.
With an increase in air speed, it is possible to cause discomfort due to drafts, especially during
winter months. Active persons are much less sensitive to these discomforts, [13] and it can be
assumed that the majority of workers on the floor that would be affected by HVLS fans will be
somewhat active. However, in the winter months for workers doing near sedimentary work, draft
could potentially become an issue. For this reason, it is important to examine effects of air
movement. As stated earlier, in the winter HVLS fan manufacturers recommend running the fans
at lower speeds. This will cause warm air near the ceiling to be slowly pushed downward. Figure
7 shows the effects of wind speeds and turbulences causing 15% of the population to be
dissatisfied. It would be wise to keep this concept in mind in determining operating conditions of
HVLS fans or the HVAC system as a whole. Along these same lines, Figure 8 shows the
percentage of people dissatisfied for different temperatures as air velocities increase [12].
HVLS Fans: Aisin Mfg. Illinois
Page 18 of 47
Figure 8: Draft Conditions Dissatisfying 15% of Population [12]
Figure 9: Percentage of People Dissatisfied as Function of Mean Air Velocity [12]
HVLS Fans: Aisin Mfg. Illinois
Page 19 of 47
Using this gathered information and applying it while making calculations and modeling
installation of the HVLS fans and/or a new HVAC system/chiller, it will be possible to create an
environment that will be comfortable for team members working on the floor at Aisin. Knowing
these requirements will allow modeling to be done in such a manner as to provide a comfortable
work environment while potentially reducing heating and cooling costs.
While this information is for standard acceptable conditions, it should be noted that Aisin has
their own requirements. The plant area where the study will be done is required to be in the range
of 68 to 82oF. While a specific humidity range is not required, a comfortable working
environment is necessary for team members working on the floor.
SUMMARY
From what this information gathered, the thought is to create three possible solutions using a
combination of systems researched. Using the current chiller setup and knowing current
conditions, it will be possible to find the load of which Aisin is currently capable. Also, it will be
possible to perform calculations to find the load required of the HVAC system in a worst case
scenario (using data from the hottest days of the year). Knowing the difference between these
two loads, the load required to fulfill the need at Aisin will be known. From this point, it will be
possible to choose an appropriate system or combination of systems to make up this difference.
Three design systems will be investigated and set forth as options to Aisin: an additional chiller
to supplement the current chiller, a setup of HVLS fans, and a combination of these. For
choosing the additional chiller size, the information gathered in the load calculations can be used
directly. For the HVLS fans option, conditions for thermal comfort based on wind speeds,
humidity, temperature gradient, etc. will be used to determine the number and placement of fans.
HVLS Fans: Aisin Mfg. Illinois
Page 20 of 47
For the combined system, the possibility of using both of the systems on a smaller level will be
investigated. Cost analyses can then be applied to each setup to help determine the best design.
Basis of Design
The documents listed in Table 2 provide the basis for the designs of SEC Team 48. In the event
of a conflict between the Request for Proposal (RFP) and the Client’s design requests stated in
the project definition, the Client’s design requests control. As new data becomes available, Client
may supply additional data and criteria that will be incorporated into the designs. All designs will
comply with the 2011 National Electric Code.
Request for Proposal (RFP)
16-Sept-10
SEC RFP Project Definition – Attachment 1
SEC RFP Design Report Deliverables Checklist – Attachment 2
16-Sept-10
16-Sept-10
2011 National Electric Code (NEC)
16-Sept-10
Proposal for Project # F10-48-AISINFAN
18-Nov-10
Table 2: Design Basis
Project Description
The purpose for modifying the current HVAC system is to create a more comfortable work
environment when the current system cannot keep up with the ambient conditions. This
modification must keep the environment at a comfortable temperature while reducing energy
usage to cool the facility. Three designs to fix Aisin’s cooling problem will be submitted to
Aisin for consideration, as described below, along with a brief economic analysis of each. Prior
to these designs, a look at current load capabilities at Aisin will be investigated, as will a load
size required to maintain acceptable conditions during peak cooling. Also, an energy audit of the
current system will be done as a basis for the economic analysis. The layout of these subsystems
is shown below in a block diagram.
HVLS Fans: Aisin Mfg. Illinois
Page 21 of 47
The block diagram is composed of three levels, the design activities of each to be done
simultaneously.
Figure 10: Block Diagram
Engineering Specification
The output of this project will be three proposed designs to solve Aisin’s problem of cooling to
comfortable temperatures during peak cooling times. Designs will be done so as to produce yearround comfort, keeping temperatures between 68 and 82oF as required by Aisin, or at equivalent
conditions according to ASHRAE’s definitions of thermal comfort based on incorporated wind
speeds and other conditions.
Scope of Work
The following subsystems give in some detail what will be designed and presented to Aisin. For
anything beyond what is stated, Team 48 is not responsible though additional work may be done
HVLS Fans: Aisin Mfg. Illinois
Page 22 of 47
as time allows. Team 48 will be working only as a consulting group and will not make a final
decision as to which direction Aisin should go. Team 48 will be merely submitting suggested
designs needed.
Subsystems
Current Load Capabilities
In order to determine what will be needed to maintain thermal comfort throughout the year, it
will first be important to examine the current system and find what it is capable of cooling (and
heating – to be used to later examine energy savings). To do this, the ratings of the current
chillers will be taken to find cooling ability.
Also, temperatures at which the chiller becomes unable to keep up will be examined, and
conditions at which this occurs will be noted.
Deliverables
Deliverables will include a report of the calculated total load capabilities.
Energy Audit
Using past energy bills, an energy audit will find current costs of heating and cooling. This will
be done by plotting average monthly gas and electrical usages from 2005 to 2010. For heating,
the approximated base load will be taken to be the amount of gas used during summer months,
and for cooling, the base load can be approximated by finding the electrical usage during the
winter months. This will allow for calculating the approximate energy used in both heating and
cooling by finding the amount under the curve but above the baseline (see example Figure 10.)
HVLS Fans: Aisin Mfg. Illinois
Page 23 of 47
950000
Electricity Used Monthly
BTU
900000
850000
COOLING
LOAD
800000
750000
BASE LOAD
700000
Figure 11: Example for Energy used in Cooling
Deliverables
From the calculations done, all spreadsheets will be submitted to Aisin showing results of the
energy audit.
Required Load Calculations
To determine the unit size needed to offset the current chiller system for year-round thermal
comfort at Aisin, an approximation of the actual load required to cool to desired temperatures
will be calculated. This load calculation will be based on a time when Aisin is running at full
production and when ambient temperature is at a design temperature of 100°F (99% of the time,
the ambient temperature in Southern Illinois is below this temperature). [13]
Application for Cooling Load
Description of Heat Gain
Heat gain is the rate at which energy is generated or transferred within a space. This energy can
be sensible or latent heat and must be computed separately. This heat gain can be in the form of
HVLS Fans: Aisin Mfg. Illinois
Page 24 of 47
heat conduction through boundaries, sensible heat convection and radiation from surfaces within
the space, latent heat generation within the space, solar radiation into the space, and ventilation
and infiltration air.
Description of Cooling Load
Cooling load is the rate at which energy must be removed from a conditioned space in order to
maintain the conditions with the space. It is different from the heat gain because radiation from
inside wall surfaces and objects inside do not directly heat the air inside the space. The
contribution to the cooling load from this radiant energy is delayed because the energy is first
absorbed by floors and interior walls and later released to the space by convection. This is
displayed in the following schematic.
Figure 12: Schematic Relation of Heat Gain to Cooling Load [13]
Design Conditions
Design conditions are given by ASHRAE, and will be used in load calculations. These
conditions include dry bulb and mean coincident wet bulb temperatures that equaled or exceeded
0.4, 1, and 2% of the hours during a year. Also, daily range of dry bulb temperatures is given for
the difference between the average maximum and minimum for the warmest month, which has
an effect on the energy stored by the building structure. Also given are mean wind speed and
HVLS Fans: Aisin Mfg. Illinois
Page 25 of 47
wind direction for the 0.4% design condition. However, for summer conditions the local wind
velocity is generally assumed to be about 7.5 mph or 3.4 m/s [13].
Depending on the time of day, the hourly outdoor temperature is assumed to vary between the
outdoor design temperature and a minimum value of temperature. Thus is given by the following
equation:
π‘‡π‘œ = 𝑇𝑑 − 𝑋(𝐷𝑅)
(1)
where 𝑇𝑑 is the design dry bulb temperature, 𝑋 is the percentage of daily range, and 𝐷𝑅 is the
daily range. [12, 13]
Infiltration
Outside air leaks into a building no matter how well constructed it may be and an equal amount
of conditioned air leaks out of the building. This leakage of air through cracks and openings
around doors and windows is called infiltration air, which results in heat loss or gain. Because
Aisin has many bay doors which may be opened at different times, an estimate will be found
based on the average number of pickups/deliveries with associated time doors are spent open for
infiltration calculations. Although not part of the project per se, it would be suggested that Aisin
that air curtains be looked into for any bay doors that are often in use. This may help to reduce
heat gain/loss from these points. Also, it may be possible to tie in rooftop units or proposed
HVLS fans to the doors to allow them to be automatically turned off in the vicinity of the door
when opened.
Air Change Method
For cooling load calculations, infiltration and required ventilation will be combined and
estimated as close as is possible from further investigation. The air-change method will be used
to calculate what effect this has on heat gain/loss. For this method, the flow rate of outdoor air
HVLS Fans: Aisin Mfg. Illinois
Page 26 of 47
that crosses the boundary of the building and requires conditioning is expressed in terms of air
changes per hour (ACH). This relationship is shown in the following equation:
𝑄̇ =
𝐴𝐢𝐻 × π‘‰
𝐢𝑇
(2)
where 𝑄̇ is infiltration in cfm or m3/s, 𝑉 is building volume in ft3 or m3 and 𝐢𝑇 is 60 for English
units and 3600 for SI units. ACH depends on construction, building type and use. Newer
buildings, such as Aisin, generally are in a range of 0.3 to 0.7 ACH. However, losses from the
bay doors may need to be added into this, as will any values from ventilation. Also, this number
can vary based on local chemical use.
Infiltration is usually based on volume flow rate at outdoor conditions. Therefore, the equation
for calculating latent heat transfer due to infiltration is
π‘žΜ‡ π‘Žπ‘–π‘Ÿ,π‘™π‘Žπ‘‘π‘’π‘›π‘‘ =
𝑄̇
(βˆ†π‘Š)β„Žπ‘“π‘”
π‘£π‘œ
(3)
where βˆ†π‘Š = (π‘Šπ‘– − π‘Šπ‘œ ) or βˆ†π‘Š = (π‘Šπ‘œ − π‘Šπ‘– ) depending whether the HVAC system is heating
or cooling, π‘£π‘œ is the specific volume of the outdoor air, hfg is latent heat of vaporization at
outdoor conditions and π›₯π‘Š is the difference in design humidity ratio.
Similarly, sensible heat transfer due to infiltration is
π‘žΜ‡ π‘Žπ‘–π‘Ÿ,𝑠𝑒𝑛𝑠 =
𝑄̇ 𝑐𝑝
(βˆ†π‘‡)
π‘£π‘œ
(4)
where βˆ†π‘‡ = (𝑇𝑖 − π‘‡π‘œ ) or βˆ†π‘‡ = (π‘‡π‘œ − 𝑇𝑖 ) depending whether the HVAC system is heating or
cooling, 𝑐𝑝 is the specific heat of the air, and βˆ†π‘‡ is the difference in design temperature.
HVLS Fans: Aisin Mfg. Illinois
Page 27 of 47
Auxiliary Heat Sources
Another large source responsible for heat gain is auxiliary heat sources from within the plant.
Being a manufacturing plant with several plastic injection lines and steam ovens, Aisin has
several large sources of heat from equipment as well as from its team members and lighting.
Occupancy
Having over 700 employees, split up over 3 shifts, Aisin will definitely have a heat gain due to
occupancy. This heat gain is made up of sensible and latent heat, the proportions of which
depend on the level of physical activity. Typical values of these ratios are given by ASHRAE
and will be used in these calculations. Also, for occupancy, it is generally assumed that sensible
heat gain is 70% radiative (which will be slightly delayed) and 30% is convective (instant
cooling load). [13]
Lights
Lighting is divided into radiative and convective loads. Lights are often turned off at times to
conserve energy. When lights are turned off, the cooling load will decrease, but it does not
immediately go to zero due to the radiative component.
The instantaneous rate of heat gain is given by the following equations:
π‘žΜ‡ = 3.41(π‘Š 𝐹𝑒 𝐹𝑠 )
Btu
[ hr ]
(5)
π‘žΜ‡ = (π‘Š 𝐹𝑒 𝐹𝑠 ) [𝑆𝐼]
(6)
where π‘Š is the total light wattage, 𝐹𝑒 is the use factor, and 𝐹𝑠 is the ballast factor. Heat gain to a
conditioned space from fluorescent lighting is assumed to be 59% radiative and 41% convective.
Equipment
For cooling load calculations, heat gain from miscellaneous equipment is generally assumed to
be 70% radiative and 30% convective. [13]
HVLS Fans: Aisin Mfg. Illinois
Page 28 of 47
Likely the largest source of heat gain at Aisin is due to equipment. To find this portion of gain,
the different types of equipment will be researched to find estimated amounts of heat given off.
If this cannot be found, heat gain will be estimated based on energy used in the process,
assuming that a given percentage is eventually turned to heat (i.e., for a plastic injection
machine) nearly all electricity used to run the machine ends up as heat either emitted from the
machine and barrel or by the process. Some energy is used to open and close the mold, and this
would be estimated.
There are two basic forms of calculating heat gain from equipment. Evaluation-Based-onOperating-Schedule will be used if possible, which examines each piece of equipment
individually [13]. Equations can be used for electrical motors and other types of equipment.
When not enough information is given, the maximum hourly heat gain can be estimated using
50% of the catalog input rating.
Otherwise, a simpler method is the Wattage-Per-Square-Foot Basis which is generally employed
when not enough data is available for the use of the first method. This method uses estimate
factors established by experience for a given type of building and multiplies this by the square
footage. [13]
Conduction (Thermal Transmittance)
This portion of the load calculation incorporates the effects of solar radiation, thermal radiation,
and convection. To calculate this heat gain, the hourly outdoor air dry bulb temperature To and
the effective temperature of outdoor air (sol-air temperature) are first calculated as shown:
𝑇𝑒 = π‘‡π‘œ +
HVLS Fans: Aisin Mfg. Illinois
𝛼𝐺𝑑
− π‘‡π‘π‘œπ‘Ÿπ‘Ÿ
β„Žπ‘œ
(7)
Page 29 of 47
where π‘‡π‘œ is the hourly outdoor air dry bulb temperature, 𝛼 is solar absorptivity, 𝐺𝑑 is total solar
irradiation incident on the surface, ho is the exterior surface heat transfer coefficient/conductance,
and π‘‡π‘π‘œπ‘Ÿπ‘Ÿ is thermal radiation correction term (7°F for horizontal surfaces and 0°F for vertical
surfaces). [13]
Because there are basically no windows on the floor at Aisin, conduction heat gains due to
windows will be negligible. For the walls and roof, after hourly π‘‡π‘œ and 𝑇𝑒 for a surface have been
determined for all the 24 hours of the design day, the heat conduction at the inside surface of the
walls and roof is obtained from the equation
𝑛=23
π‘žΜ‡ = 𝐴 ∑ π‘Œπ‘ƒπ‘› (𝑇𝑒,𝑛𝛿 − π‘‡π‘Ÿπ‘œπ‘œπ‘š )
(8)
𝑛=0
where 𝐴 is surface area, π‘Œπ‘ƒπ‘› is the nth periodic response factor, 𝑇𝑒,𝑛𝛿 is the value of 𝑇𝑒 , n hours
ago and π‘‡π‘Ÿπ‘œπ‘œπ‘š is the room temperature. Periodic response factors for multilayer walls will be
found using a computer program (HvacLoadExplorer) which is associated with [13].
Alternatively, a simpler method of finding thermal transmittance may be used, which is not
applicable to the Radiant Time Series Method (RTSM) for cooling but will allow for an easy
method of finding heat gain due. This is the following.
π‘ž = π‘ˆπ΄βˆ†π‘‡
(9)
where π‘ˆ is the U-factor equal to the inverse of the resistance and βˆ†π‘‡ is the temperature
difference of the conditioned space and the ambient.
HVLS Fans: Aisin Mfg. Illinois
Page 30 of 47
RTSM for Cooling Load Calculations
This method applies a radiant time series to the radiative portion of the heat gain. For this reason,
all gains must be divided into radiative and convective parts. The hourly cooling load due to the
radiative portion of each heat gain is obtained using the following equation.
π‘žπΆπΏ,𝑑 = π‘Ÿπ‘› π‘žΜ‡ 𝑑−𝑛𝛿 = π‘Ÿ0 π‘žΜ‡ 𝑑 + π‘Ÿ1 π‘žΜ‡ 𝑑−𝛿 + π‘Ÿ2 π‘žΜ‡ 𝑑−2𝛿 + π‘Ÿ3 π‘žΜ‡ 𝑑−3𝛿 + β‹― + π‘Ÿ23 π‘žΜ‡ 𝑑−23𝛿
(10)
where rn is the nth radiant time factor, π‘žπΆπΏ,𝑑 is the cooling load at the current hour, and π‘žΜ‡ 𝑑−𝑛𝛿 is
the heat gain, n hours ago. [13]
Design Activities
List of activities for the RTSM calculation for load requirement include:
ο‚·
Determination of exterior boundary conditions-incident solar radiation and sol-air
temperatures
ο‚·
Calculation of heat gains
ο‚·
Splitting heat gains into radiative and convective portions
ο‚·
Determining cooling loads due to the radiative portion of heat gains
ο‚·
Summation of loads due to convective and radiative portions of heat gains
Load Calculation Based on History of Energy Consumption and Ambient Temps.
This method will be used as a check of the previous approach to load sizing calculations. This
method uses the history of energy usage as well as corresponding average ambient temperatures
along with the seasonal energy efficiency ratio rating of the system to calculate expected loads
given an ambient temperature. Using a design temperature, it will then be possible to find the
required load.
This method will give the expected cooling load at a given temperature. To find the maximum
load, an error analysis will be done, and the maximum load will be estimated based on a chosen
HVLS Fans: Aisin Mfg. Illinois
Page 31 of 47
prediction interval; e.g. at 90% confidence, the predicted cooling load at 95/78oF (typical design
conditions) is 225 Btu/ft2 +/-50Btu/ ft2.
Deliverables
Deliverables for the Load Calculation subsystem will include spreadsheets produced using the
RTSM procedure, listing the load requirement found as well spreadsheets produced for load
calculation requirements based on the history of energy consumption. This information will be
incorporated into the final design report submitted to Aisin.
Design 1: Additional Chiller
In order for the HVAC system to keep up with the troubling conditions, the feasibility of an
additional chiller added to the current chiller system will be investigated. The size required will
be determined from the difference in current and required load calculations, described in
subsystems 1 and 3. The current chiller systems’ manufacturers will be kept in mind in looking
at possible units to install. A report will be submitted to Aisin containing the recommendations
for this chiller.
Design 2: HVLS Fans
This subsystem will be used to supplement the HVAC system to provide more efficient heating,
cooling and ventilation year round. This will lead to increased thermal comfort, better air
circulation, lower humidity, and lower energy costs.
The fans will be integrated into the current HVAC system. When running, they will circulate the
cold air from the A/C system down to the workers on the floor. As the name implies, they will
do this at very low air speeds. An average air speed for a 24ft fan is 600 ft/min where a 30in fan
would produce air speeds near 4800 ft/min. This slower airspeed gives workers the cooling
HVLS Fans: Aisin Mfg. Illinois
Page 32 of 47
effect of a light breeze without overly windy conditions. This added cooling effect will make the
workers feel cooler without changing the ambient temperature of the plant. We will consult
ASHRAE standards to determine the optimum air speed and the relative cooling effect it will
have.
Factors to be considered with HVLS fans:
ο‚·
Design of fan
o Airfoil blade design and chord length
o Construction of fan
o Estimated life span
ο‚·
Placement of fans
ο‚·
Obstructions on floor
ο‚·
CFM ratings and how they were obtained
ο‚·
RFI and EMI compliancy
Deliverables
ο‚·
Fan specifications
ο‚·
Expected energy usage
ο‚·
Fan placement in factory
ο‚·
Suggested operation during heating, cooling and ventilation
ο‚·
Projected energy savings and return on investment
List of Activities
ο‚·
Collect data from temporary fan in building
ο‚·
Estimate effective area with current conditions on floor
ο‚·
Build model to estimate fan interaction
ο‚·
Design fan layout in factory
ο‚·
Estimate effect on heating and cooling
ο‚·
Calculate operation cost on annual basis
HVLS Fans: Aisin Mfg. Illinois
Page 33 of 47
Design 3: Combined System
Combining attributes of designs 1 and 2, design 3 will be a proposal for a system composed of
HVLS fans and smaller chiller to supplement the current HVAC system. A balance will be found
that will create the environment needed for thermal comfort. A cost summary will be compiled to
be used in the economic analysis, and all design information will be submitted in the final design
report to Aisin as an option to correct the current problem.
Control System
In the event of the HVLS fans being able to provide for a comfortable environment, a control
system for the fans will need to be put in place. Research will be done to provide a choice of
three different control systems for the HVLS fans. A report of the findings will be submitted to
Aisin in the final design report.
Economic Analysis
When designs 1, 2, and 3 have been completed, a cost analysis will be done on each. This may
include simple payback period calculations, life cycle cost/savings analysis, and/or benefit to
cost ratio. Calculations will be done to find net present values and/or net future values of cash
flows created for each design. These will be compared to find the most economical choice. All
results will be incorporated into the final design report submitted to Aisin.
HVLS Fans: Aisin Mfg. Illinois
Page 34 of 47
References
HVLS FANS
[1] "Installation and Warranty." MacroAir Technologies, Inc., 2010. Web. 4 Oct. 2010.
<http://www.macro-air.com/products/installation-and-warranty>.
[2] "Literature - Rite Hite - Revolution HV/LS Fans." Rite Hite - Revolution HVLS Fans. Rite
Hite HVLS Fans, 2010. Web. 4 Oct. 2010. <http://www.ritehitefans.com/pages/literature>.
[3] "Technical Downloads." Big Ass Fan Co. Delta T Corp., 2010. Web. 4 Oct. 2010.
<http://www.bigassfans.com/page/technical_downloads>.
[4] Macro air. (2010). Retrieved from www.macro-air.com, 1 Nov. 2010.
[5] DeGaspari. "A fan for all seasons." Mechanical Engineering 121.12 (1999): 58. MasterFILE
Premier. EBSCO. Web. 11 Oct. 2010.
[6] "HVAC manufacturer finds a cool solution with HVLS fans." Plant Engineering 63.9 (2009):
37-39. Academic Search Premier. EBSCO. Web. 30 Sept. 2010.
[7] "HVLS Fan." Material Handling Management 65.7 (2010): 34. Business Source Complete.
EBSCO. Web. 30 Sept. 2010.
[8] Oleson, Rick. "The top 10 myths about HVLS fans." Plant Engineering 62.7 (2008): 40.
Academic Search Premier. EBSCO. Web. 30 Sept. 2010.
HVAC SYSTEMS
[9] “Chilled Water Applied Systems - HVAC Systems”. Trane, 2010. Web. 4 Oct. 2010.
<http://www.trane.com/COMMERCIAL/HvacSystems/1_1_ChilledWater.aspx?i=863>
[10] “Water Chiller System”. Web. 5 Oct. 2010.
<http://www.air-conditioning-and-refrigeration-guide.com/water-chiller-system.html>
[11] “HVAC Chillers”. Global Spec, 2010. Web. 5 Oct. 2010.
<http://www.globalspec.com/LearnMore/Building_Construction/HVAC/Cooling/HVAC_Chillers>
THERMAL COMFORT
[12] 2009 ASHRAE Handbook - Fundamentals (SI Edition). American Society of Heating,
Refrigerating and Air-Conditioning Engineers, Inc, 2009.
[13] McQuiston, Faye C, Jerald D Parker and Jeffrey D Spitler. Heating, Ventilating, and Air
Conditioning Analysis and Design. 6th Edition. Hoboken: John Wiley & Sons, 2005.
HVLS Fans: Aisin Mfg. Illinois
Page 35 of 47
Commercial
Saluki Engineering Company hereby offers to do the work defined in this proposal for the costplus-award-fee determined by Aisin Mfg. Illinois, equal to zero dollars or greater ($0.00 +). This
project will be conducted as a consulting service offered to Aisin free of charge, with the
understanding that all expenses arising that Aisin deems acceptable for equipment, travel, etc.
will be covered by Aisin.
This proposal is valid for a period of 30 days from the date of the proposal. After this time,
Saluki Engineering Company reserves the right to review it and determine if any modification is
needed.
Resources Needed
The following is a table of items to be used in this project. All of the items are either on hand or
will be borrowed.
ITEM
1
2
3
4
5
DESCRIPTION
Anemometer
Psychrometer
Pyrometer
Infrared Camera
HvacLoadCalc Software
QUANTITY
1
1
1
1
1
$ EACH
Borrowed
Borrowed
Borrowed
Borrowed
On Hand
$
0.00
0.00
0.00
0.00
0.00
Organizational Chart
Below is an organizational chart for Team 48, which includes team members’ names, discipline,
and principle responsibility, as well as the name of the faculty technical advisor.
HVLS Fans: Aisin Mfg. Illinois
Page 36 of 47
TEAM 48 - Organizational Chart
NAME
Alex Kee
Bill Ennis
Joel Chaplin
Kyle Florian
DICIPLINE
ME
EE
ME
EE
Micah Buchanan
ME
Ryan Riffel
ME
PRINCIPLE RESPONSIBILITY
Current Load Capabilities
Control System
Design 2, Economic Analysis, Design 3
Control System
Current Load Capabilities, Energy Audit,
Load Requirements, Design 3
Design 2, Design 3
Faculty Technical Advisor - Dr. James Mathias
The following pages contain two schedules, the first being an overall chronological schedule of
events for the Spring 2011 semester. Following this is a more detailed schedule of these events
with targeted and actual due dates given. Finally, after the schedules is an Action Item List for
the Spring 2011 semester.
.
HVLS Fans: Aisin Mfg. Illinois
Page 37 of 47
Draft Schedule
DRAFT SCHEDULE - TEAM 48
1-Jan
31-Jan
2-Mar
1-Apr
1-May
Data Collection - AK, MB, KF
Energy Audit - MB
Estimate Current System Capacity - MB
Unit Sizing/Load Required - MB
Design 1 - MB
Create Controller System - BE, KF
Explore HVLS Fans - JC, RR
Design 2 - JC, RR
Design Reviews - ALL
Progress Reports Posted - ALL
Design 3 - JC, MB
Economic Analysis - JC
Demonstrations - ALL
Design Report - MB
Build Integrated Fan Model - AK, KF
Design Poster Presentation - ALL
Design Oral Presentation - ALL
Completed
HVLS Fans: Aisin Mfg. Illinois
Remaining
TEAM MEMBERS: Alex Kee (AK), Bill Ennis (BE), Joel
Page 38 of 47
Draft Schedule - Detailed
Aisin Fan Project Schedule - Team 48
X
Class Deadline
Group Deadline
Estimated W orking Time
As W orked
Deliverable
Team Members
Alex Kee (AK) Bill Ennis (BE)
Joel Chaplin (JC)Kyle Florian (KF)
Ryan Riffel (RR) Micah Buchanan (MB)
Project Deliverables
Design Report
2-May
25-Apr
18-Apr
11-Apr
4-Apr
28-Mar
21-Mar
14-Mar
7-Mar
Design Poster Presentation - ALL
3-May
X
Design Oral Presentation - ALL
3-May
X
Demonstrations - ALL
28-Apr
X
Design Reports - ALL
26-Apr
X
Progress Reports posted to W eb Space - ALL
24-Feb
Design Reviews - ALL
X
3-Mar
X
Design 1 - MB
X
Design 2 - JC, RR
X
Design 3 - JC, MB
X
Energy Audit - MB
17-Jan
Estimate Current System Capacty - MB
Unit Sizing - Load Required - MB
Design Tasks
28-Feb
21-Feb
14-Feb
7-Feb
31-Jan
24-Jan
17-Jan
DUE
DATE
10-Jan
PROJECT TASKS
3-Jan
W eek of - Starting with Monday
Data Collection - AK, MB, KF
1-Jan
Create Controller System - BE, KF
Explore HVLS Fans - JC, RR
Economic Analysis - JC
Build Integrated Fan Model - AK, KF
HVLS Fans: Aisin Mfg. Illinois
Page 39 of 47
AIL
ACTION ITEM LIST
PROJECT: HVLS FANS - AISIN MFG. ILLINOIS
For Beginning of Spring 2011
TEAM MEMBERS
Alex Kee, ME
Micah Buchanan, ME
Joel Chaplin, ME
Ryan Riffel, ME
Bill Ennis, EE
Kyle Florian, EE
DATES
ITEM #
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
ACTIVITY
TM
Current HVAC Load Calculations
MB
Energy Audit
MB
Load Calculation Based on Energy Usage History
MB
Thermal Transmittance Calculations
MB
Infiltration/Ventilation Calculations
MB
Auxiliary Heat Sources Heat Gain
MB
Total Required Load Calculations - From 2,3,4
MB
Additional Load Required Calculations
MB
Design 1
MB
Create Controller System
Design 2
Design 3
Economic Analysis
HVLS Fans: Aisin Mfg. Illinois
BE/KF
JC/RR
MB/JC
JC
ASSIGN
ED
7-Nov
7-Nov
7-Nov
7-Nov
7-Nov
7-Nov
7-Nov
7-Nov
7-Nov
DUE
NEW
DUE
STATUS
COMMENTS
Find current load capabilities.
15-Dec
20-Dec
25-Dec
30-Dec
5-Jan
10-Jan
15-Jan
25-Jan
Find current energy usage for heating and cooling based off of energy bills.
Investigate procedure. Based on energy usage coorelated with ambient condition
Conduction heat gain through walls, roof, etc.
Use Air-Change method - approximation.
Due to people, lights, equipment. Based on operating schedule.
Use RTSM for cooling load calculations.
Find current and required load differences.
Find appropriate chiller unit to offset load difference.
25-Jan
7-Feb
21-Feb
21-Feb
Page 40 of 47
William Arthur Ennis
E-mail: ennis747@siu.edu
Permanent:
933 Glenda Lane
Taylorville, IL 62568
Telephone: (217)824-5494
Objective:
Local:
1205 S. Wall St.
Carbondale, IL 62901
Telephone: (217)825-5801
An entry level electrical engineering position with a focus on power systems.
Education:
Lincoln Land Community College- Springfield, Illinois
Associates Degree in Business Administration, 2004
Southern Illinois University- Carbondale, Illinois
Bachelor Degree in Electrical Engineering, expected December 2011
Skills:
ο‚·
ο‚·
ο‚·
ο‚·
ο‚·
Excellent written and verbal communication skills
Experienced with Excel and spreadsheets
Very hard working and excellent with team work
Some experience with computer programming
Quick learner and dedicated employee
Experience:
May 2006-May 2008
ο‚·
ο‚·
ο‚·
ο‚·
May 2005-May2006
Culligan Water Service- Decatur, Illinois
Route Salesman and Service Technician
Built and repaired electrical components for water softener control units
Serviced and installed water softeners and drinking water systems on both a commercial
and residential level
Organized and managed routes for new and existing customers
Delivered water and water softener salt while maintaining a good relationship with
customers
ο‚·
ο‚·
GSI group- Assumption, Illinois
Machine Operator
Used computer programs to cut metal components for distribution and production
Organized and shipped steel components to other plants for production
ο‚·
ο‚·
ο‚·
ο‚·
MBM- Taylorville, Illinois
Puller/Loader
Pulled packages from pallets to fill orders for restaurants
Organized and stacked pallets to be pulled or to be shipped
Checked pallets ready for shipment for damage and accuracy
Strategically loaded pallets of product and loose product into semi trailers to be shipped
June 2004-May 2005
Relevant Coursework:
ο‚·
ο‚·
ο‚·
ο‚·
ο‚·
Computer Systems and Business Applications
Introduction to Business Organizations
Problem Solving with Computers
Discrete Logic and Digital Systems
Introduction to Management
Kyle Matthew Florian
E-mail: kylef10@siu.edu
Permanent:
Local:
1602 W. Maplewood
12417 N. Hwy 51
Marion, IL 62959
Murphysboro, IL 62966
Telephone: 618-925-3722
Telephone: 618-925-3722
______________________________________________________________________________
Objective:
To obtain an entry-level electrical engineering position to focus on power and
energy systems.
Education
Associate Degree in Science, May 2007
John A. Logan College, Carterville, IL 62918
Bachelor of Science in Electrical Engineering, December 2011
Southern Illinois University, Carbondale, IL 62901
Relevant Coursework
ο‚· FTP Clients
ο‚· Controls and Systems
ο‚· Java Platform
Experience
Food Service Worker, Marion VA Medical Center
September 2005 - present
ο‚· Provide excellent service and support to customers and veterans
ο‚· Am now a Supervisor of Food Service Operations(from September of 2009)
ο‚· Run diet reports on all veterans in the Marion VA Medical Center
ο‚· Once awarded “Best Canteen in the Nation”
ο‚· Gained many friends from different departments at the Marion VA
Skills
ο‚· PSpice and MATLAB
ο‚· Microsoft Visio and Microsoft Vista
ο‚· Xilinx and AutoCAD
ο‚· Problem Solving with Computers
ο‚· Electronics
ο‚· Digital Circuit and Design Work
Activities
ο‚· Adult League Softball with the Marion VA team
ο‚· Adult League Soccer
ο‚·
Recreational Tennis and Golf
Micah Buchanan
920 Kathryn Lane, Carterville, IL 62918
P: (618) 943-0123 E: micahbuchanan@gmail.com
SUMMARY OF QUALIFICATIONS
Proficient team player with a positive and task-oriented attitude, as well as an excellent team leader,
proven through design projects and past work experiences. Highly adaptable and able to learn and
apply engineering concepts quickly and completely. Excellent communication skills (oral and written)
demonstrated through group work, experimental lab work, and course work. Ability to multi-task and
work with diverse people and organizations.
EDUCATION
Southern Illinois University Carbondale (SIUC), Carbondale, IL
Bachelor of Science in Mechanical Engineering, Minor in Mathematics
G.P.A.: 3.81/4.0
EMPLOYMENT HISTORY
Aisin Mfg. Illinois, Marion, IL
Manufacturing Engineer Intern
ο‚·
ο‚·
ο‚·
ο‚·
Farmhand
ο‚·
ο‚·
Jan 2003 – Jan 2010
May – Aug 2008, 2009
Gained experience in feeding/care of hogs (managed a set of hog barns - 5,000 head),
feeding/care and milking of cattle, planting/harvesting of corn, soybeans, and wheat
Learned to resolve unexpected conflicts in order to maintain a steady process of production
Gained knowledge of how to accomplished large tasks through organized team work
Branching Out, Inc., Lawrenceville, IL
Foreman
ο‚·
ο‚·
ο‚·
April 2010-Present
Learning in depth the processes associated with plastic injection molding for automotive
components
Setting up new robot systems, running mold trials, and preparing line setups for the 2012 Camry
Constructing new regrind systems to recycle scrap and mix with virgin material to reduce waste
Using teamwork to collaborate and solve problems in a manufacturing atmosphere
Buchanan Dairy Farm, St. Francisville, IL
Lazy B Farms, Lawrenceville, IL
ο‚·
May 2011
May 2003 – July 2005
Managed the planting, care, harvesting, and sale of trees and shrubs
Increased profits by 10% through selective hiring and marketing strategies
Hired and oversaw a team of eight during planting and harvesting seasons
VOLUNTEER WORK
Mission Trip to Ecuador
Summer 2007 & 2008
ο‚· Involved in preparations and management of multiple events at a children’s Bible camp
ο‚· Visited several underprivileged communities to hand out evangelistic literature
Landscaper
April 2003 – July 2008
ο‚· Volunteered landscaping services for both a nearby church and an elderly neighbor
ο‚· Consisted of mowing, trimming, landscaping, and painting
AWARDS
ο‚· Dean’s List Fall 2007-Spring 2010
ο‚· Awarded University of Evansville Trustee Scholarship ($18,000)
ACTIVITIES
ο‚· American Society of Heating, Refrigeration, & A/C Engineers (ASHRAE), Vice-President 2010-2011
ο‚· Tau Beta Pi, in the process of being inducted December 2010
ο‚· American Society of Mechanical Engineers (ASME) member since 2007
SKILLS
SolidWorks, Matlab, Simulink, SolidEdge, Maple, Microsoft Office Platform (Word, Excel, PowerPoint)
Joel M Chaplin
416 s Washington St.
Carbondale, IL. 62901
(573)579-4390
jchaplin@siu.edu
Objective
To pursue a career in Mechanical Engineering that is challenging with opportunity for
professional advancement.
Education
ο‚·
Southern Illinois University Carbondale (fall 2007-spring 2011)
ο‚·
Bachelor of Science
ο‚·
Major: Mechanical Engineering
ο‚·
Elective studies:
ο‚·
Internal Combustion Engines
ο‚·
Hydraulic systems
ο‚·
Penn State University (fall 2006-spring2007)
ο‚·
Major: Mechanical Engineering
Experience
ο‚·
Beck Bus transportation, Carbondale IL. (January 2010-present)
ο‚·
Successfully troubleshoot complex electrical and mechanical problems
ο‚·
Gained valuable knowledge of heavy duty equipment reliability issues
ο‚·
Maintained fleet of city and school buses
ο‚·
Outdoor turf professionals, Carterville IL. (March 2009-June 2010)
ο‚·
Maintained and operated turf equipment
ο‚·
Marathon Petroleum LLC, Robinson, IL. (summer 2008)
ο‚·
Updated equipment files and documentation
ο‚·
Made excellent progress on an internal reliability program
ο‚·
Created a training program on this issues that addressed installation, safety and reliability
issues
ο‚·
Assisted engineers in troubleshooting problems
ο‚·
J&N Auto salvage and recovery, Coatesville, PA. (May 2003-June 2007)
ο‚·
Troubleshoot mechanical and electrical failures in automobiles, commercial trucks and
heavy equipment.
ο‚·
Inventoried used parts to ensure efficient and up to date information for customers
ο‚·
Fabricated recovery equipment to ensure safer operation of tow truck
ο‚·
H&H Nursery, Thorndale, PA. (spring-summer 2007)
ο‚·
Maintained and operated agricultural equipment to ensure efficient operation
Demonstrated Abilities:
ο‚·
Analyze research and apply corrective action to mechanical problems.
ο‚·
Highly skilled in the use of AutoCAD 2D&3D Modeling, over 6 years experience with various
versions dating back to AutoCAD 2000
ο‚·
Confident in basic functions in Solid Works and MatLab programs
ο‚·
Skilled in the use of Visio.
ο‚·
Highly Experience with the use of Microsoft office, including Word, Access, PowerPoint, and
advanced knowledge of Excel.
ο‚·
Work well in a team environment
ο‚·
Learn extremely fast and anticipate where help is needed before being asked.
ο‚·
Advanced hands on skill set and knowledge base with vast array of mechanical equipment
Ryan M. Riffel
ryan.riffel11@gmail.com
Permanent Address:
School Address:
485 Shadow Valley Ln.
Buncombe, IL 62912
618.833.4125
606 E. Park St, Apt. N
Carbondale, IL 62901
618.697.4749
_____________________________________________________________________________________
OBJECTIVE
An entry level position in mechanical engineering
EDUCATION
Southern Illinois University Carbondale
Carbondale, IL
Bachelor of Science in Mechanical Engineering, May 2011
Minor: Mathematics
GPA: 3.73/4.00
Southeast Missouri State University
Cape Girardeau, MO
Major: Engineering Physics
August 2006-May 2008
GPA: 3.7/4.0
AWARDS/
ACTIVITIES
SKILLS
ο‚·
ο‚·
ο‚·
ο‚·
AISIN Mfg. Illinois, LLC (AMI) Scholarship, SIUC, 2010-2011
College of Engineering Dean’s Scholarship, SIUC, 2009-2010
Dean’s List Status, SIUC, 2008-2010
American Society of Mechanical Engineers, Student Member, 2010
ο‚·
ο‚·
ο‚·
Proficient in Microsoft Excel, Word, and PowerPoint
Experience with AutoCAD and MATLAB
Experience with C++ and Python programming
ο‚·
ο‚·
ο‚·
Sales Clerk, Larry’s House of Cakes (July 2010-Present)
Carbondale, IL
Responsible for growth in volume, rate, and quality of sales
Improve customer satisfaction with excellent customer service
Increase bakery production rate and quality of goods with team of bakers
ο‚·
ο‚·
ο‚·
Clerical Work & Laborer, Earthwork (May 2005-June 2010)
Carbondale, IL
Gained a strong work ethic by managing and maintaining customer properties
Worked with a team on major landscaping projects
Responsible for bookkeeping and invoicing
WORK
EXPERIENCE
Alex Kee
1408 Newton Ave.
Johnston City, IL 62951
618-889-1762
akee_11@msn.com
OBJECTIVE
Seeking full time employment as a Mechanical Engineer
Qualifications
Strong people, problem-solving, and group skills
Attention to detail, accuracy, and deadlines
Education
Southern Illinois University Carbondale, Carbondale, IL
Bachelor of Science, Mechanical Engineering, expected graduation May 2011
Blackburn College, Carlinville, IL, Aug 2006-May 2008
Transferred to SIUC
Experience
Blackburn College, New Construction Crew
Aug 2006-May 2007
ο‚· Building maintenance including: drywall, brickwork, and wood-work
ο‚· Working with hand-tools and power-tools
ο‚· Wiring and reading/working with building plans
Blackburn College, Utilities Crew
Aug 2007-May 2008
ο‚· Building maintenance including: electricity and plumbing
ο‚· Working with hand-tools and power-tools while rebuilding many plumbing and electrical
appliances
ο‚· Wiring and reading/working with building/piping plans
Aisin Manufacturing, Manufacturing Engineering Intern
Feb 2010-present
ο‚· Injection molding and specialized maintenance on injection machines
ο‚· Designing machine and mold modifications
ο‚· Hands on modifications to machines and molds using many different tools
ο‚· Some machining work
ο‚· Documentation i.e. capacity studies for new product launches
Employment
The Mattress Store, Delivery/Stock
November 2004-May 2006
Marion, IL
Franklin County Country Club, Maintenance
West Frankfort, IL
Summer 2006-Summer 2007
ο‚· General maintenance around the course, clubhouse, and swimming pool
ο‚· Supervise 3-5 employees, making sure they perform daily duties along with special projects
around the course.
Kroger Co. Courtesy Clerk/Produce Clerk
Feb 2009-Feb 2010
Awards/Activities
ο‚·
ο‚·
Blackburn College Honor Scholarship
Blackburn College Baseball
Carbondale, IL
Download