Risk Modelling of a Notional Mega Project Cost Estimate 11 Nov 2011 Overview Mega Projects by their very nature consist of smaller individual projects that integrate together to form a whole. In a similar fashion the estimate for such a project also comes from a multitude of diverse disciplines with differing sources and work practices. This paper will use a case study to show how a risk model for the Cost Estimate was built in Palisade @Risk to identify appropriate levels of Contingency and Management Reserve. Inputs to the model were taken from a variety of sources including • • • • • Control Estimate Systemic risk models Quantitative schedule risk models Risk ranging workshops Various risk registers 2 Contingency & Management Reserve Contingency Contingency is the amount of money used in the estimate to deal with the uncertainties inherent in the estimating process. Contingency is required because estimating is not an exact science. • The amount of infill and concrete to cover an underground pipe, the number of manhours to complete the task, and the actual all in labour rate, are all best estimates until the work is complete Management Reserve An amount added to the estimate to allow for specific risks that may or may not occur that are within the project’s control or influence. Risk is defined as an undesirable potential outcome and its probability of occurrence • Does not include force majeure, currency risk, political risk etc Scope Both amounts are based on a defined scope. Should scope change , the estimate must be revised to reflect such changes in scope. Neither Contingency nor Management Reserve are a source of funds to cover scope changes 3 Mega Project vs Project Portfolio Key Differences So why is a Mega Project so different to a Portfolio of Projects being executed by a Company. Key differences are: • Same key personnel • Mega project is a number of inter related projects with numerous key interfaces. Any delay or changes to one can have a significant effect on one or the others • Site Wide Services common to all sub projects • Same geographical location Effect Must not underplay the significance of these differences. Sub projects must not be modeled in isolation • Liberal use of correlation between sub projects to avoid nodal bias • Schedule must be modeled at the mega project level ensuring all interfaces are included. 4 Identifying the Risks The Risk Register Prior to estimating contingency or otherwise quantifying risk impacts, the risks must first be identified and then logged in the Risk register. Husky uses a standard 5 x 5 risk Matrix as a Probability Impact Diagram for Project Risk. Impacts are defined specific to project Consequence Very High High Medium Low Very Low Very Low Low 5A 4A 3A 2A 1A 5B 4B 3B 2B 1B Likelihood of Occurrence Medium High 5C 4C 3C 2C 1C 5D 4D 3D 2D 1D Very High 5E 4E 3E 2E 1E Priority Action Setting Critical Immediate Action must be taken to Prevent or Mitigate the Risk Serious Mitigation Action Required Moderate Mitigation Strategies to be investigated Acceptable Be aware of Potential Mitigation Strategies 5 Typical Risk Register 6 Typical Boston Square 7 The Cost Model Main input to the Cost Model was the Control Estimate. However elements of the estimate were modelled using a variety of techniques and then brought into an overall Cost Risk model • • • • Risk ranging workshops using range estimating techniques Systemic risk modelling Quantitative schedule risk models Specific risk modelling 8 Traditional Probability Distribution Functions @Risk contains a wealth of distribution functions. Most are useful to the in depth simulation requiring sophisticated tools. Only a few are suitable for general cost modelling 9 Typical Probability Distribution Functions Risk Uniform Used when we have no idea what the value is between two limits Risk Triangle Most Popular distribution to show Most Likely value tapering to a Min and Max Risk Trigen Modification of Triangle Allows for a finite probability of achieving Min & Max Values Fundamental Flaw of Triangle and Trigen is when the distribution is skewed 10 Most Likely =5, Min =4, Max =15 Most Likely = 5 Mean = 8 P50= 7.58 Most Likely = 5 Mean = 6.5 P50= 6.16 11 AACE International Recommended Practice No. 41R-08 RISK ANALYSIS AND CONTINGENCY DETERMINATION USING RANGE ESTIMATING • Monte Carlo software for risk analysis requires identification of a probability density function (PDF) for each critical item. In rare instances the behavior of a critical item is known to conform to a specific type of PDF such as a lognormal or beta distribution, which reflects items that may skew heavily to one side of a distribution. However in most instances it is unlikely that the actual type of PDF that truly represents the item is known. Thus a reasonable approximation is to use either - Triangular Distribution - Double Triangular Distribution In most cases, the double triangular distribution is a better approximation since it can be made to conform to the implicit skew of the project team’s probability assessment. The double triangle allows the risk analyst to use the probabilities which the project team believes are reasonable rather than letting the triangular distribution dictate a probability which, more often than not, is invalid. 12 Probability Density Double Triangle Method Area = Underrun Probability Area = Overrun Probability a c Random Variable x b Most Likely = 5 Mean = 6.5 P50= 5.0 13 Double Triangle Method Probability Density F1 F2 Urun Min Min -10% Max 20% 1-Urun ML Urun 30% Max F1 F2 6 7 RF 1.00 F1= 2*Urun/Min F2= 2*(1-Urun)/Max RF=1+RiskGeneral(Min,Max,{0,0},F1:F2,RiskStatic(0)) 14 Schedule Risk Quantitative Schedule Risk Analysis Husky uses Primavera P6 to schedule all projects greater than $5MM. Oracle Primavera Risk, formerly known as Pertmaster, is used for quantitative schedule risk analysis (QSRA) To bring in the cost element of schedule delay, the results of the QSRA were brought into the cost model as a set of percentiles “days delay” from P0 to P100. Use of the @Risk Fit Manager was used to fit the best curve to this profile, with options set to update the curve each simulation. This simplified the update process each time the schedule model changed. The schedule @Risk function was then multiplied by another @Risk function that represented the uncertainty in “cost per day” to give an effective cost for schedule slippage 15 Schedule Cost Risk 27/06/2013 0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50% 55% 60% 65% 70% 75% 80% 85% 90% 95% 100% 25-Feb-13 07-May-13 23-May-13 04-Jun-13 13-Jun-13 21-Jun-13 28-Jun-13 05-Jul-13 11-Jul-13 17-Jul-13 22-Jul-13 28-Jul-13 02-Aug-13 09-Aug-13 16-Aug-13 23-Aug-13 01-Sep-13 11-Sep-13 24-Sep-13 12-Oct-13 24-Dec-13 -122 -51 -35 -23 -14 -6 1 8 14 20 25 31 36 43 50 57 66 76 89 107 180 =RiskLoglogistic(-1063,1088.2,38.361, RiskFit("Schedule","RMSErr"), RiskName("Schedule"), RiskStatic(0)) 16 Use of a Systemic Risk tool Systemic Risk Systemic risk drivers such as the level of project scope definition affect individual, disaggregated estimate line items in a way that is hard to see and predict. • Best practice is to address systemic risk drivers using empirical knowledge (from historical data) to produce stochastic models that link known risk drivers (e.g. scope definition) to bottom line project cost growth. • It was decided that this approach would be best suited for the Process Plant, which formed the major part of the cost estimate. • Conquest Consulting Group , who have wide experience in the use of such tools, were engaged to construct a parametric model which used a series of questionnaires to the project team based on : - Contractor Organisation - Contractor Experience - Project Planning - Execution Strategy - Scope Definition • Fit Manager was again used to integrate the results from the parametric model into the overall model 17 Systemic Risk Questionnaire Case Description: Date: 2 SNAM 9/30/2010 & 10/22/2010 Enter Contractor Bid Value Enter Execution Schedule Bid Duration 1,079,000 39.8 ($ thousands) (months) Currency Canadian$ BID MATURITY WORKSHEET 3 Ratings: 0=N/A, 1=Greatly Exceeds, 2 = Exceeds, 3 = Meets, 4 = Does Not Meet, 5 = Fails (EXPECTATIONS) Rating Contractor Organization Evaluation Overall Contractor Capabilities 3 Meets expectations with regard to overall capabilities (including financial strength, reputation, experience, resources, etc.). added note: Contractor Organizational Structure 3 Meets expectations with regard to the proposed organization structure to support the project. added note: Alignment of JV Partners 3 Meets expectations with regard to clear and documented alignment of JV Partners. added note: Key Project Personnel Proposed 4 Does not meet expectations with regard to the key personnel proposed for the project (years of experience, applicable experience, guarantee of staying with the project, etc.) added note: Contractor Ramp-up Strategy and Capability 3 Meets expectations with regard to the proposed ramp-up strategy and capability to adequately resource the project in a timely fashion. added note: Contractor Resource Capability and Availability 4 Does not meet expectations with regard to resource capabilities and availability (such as number of in-house resources and capability to contract resources). added note: Alignment with Subcontractors and Suppliers 3 Meets expectations with regard to alignment of the contractor with sub-contractors and suppliers. added note: Contractor Organization Evaluation 3.3 18 Specific Risk Input Probability and Impact Specific Risks consist of both a probability of occurrence, and an impact should they occur • Risk Probability modeled as simple binomial to simulate Yes/No • Risk Impact modeled as a PDF to give uncertainty of the impact • Risk outcome modeled as a product of Probability (0 or 1) and Impact Problems Prior to release of @Risk 5.0 there were inherent problems using this method in that Tornado Diagram showed both Probability and Impact as two separate risk inputs RiskMakeInput @Risk5.0 onwards allowed for use of RiskMakeInput to combine the two together. Use extract from Risk Register to directly map risks into the model RiskID Description FFH-013 Construction in advance of sufficient engineering Score A3 Prob 5% Min $ 2,000,000 Max $ Risk amount $ 0 3,500,000 Risk Amount = RiskMakeInput( (RiskBinomial(1, Prob,RiskStatic(0))* RiskUniform( Min,Max)),RiskName(Description)) 19 Risk Results Summary Results Individual Risk models were established on separate MSExcel sheets and outputs summarised on tabular results sheet Extensive use made of the @Risk function RiskPercentile to provide tabular output that could be copied and pasted direct into reports $MM Process Plant SubSurface Development Drilling & Completions Infrastructure Midstream Business & System Management Ow ners Costs Additional Specific Risk TOTAL PROGRAM Management Reserve Overall Total Estimate Risked Value 50% $918.3 $918.3 $1,038.2 $1.6 $1.6 $1.8 $193.8 $193.8 $208.4 $124.4 $124.4 $133.4 $30.2 $30.2 $33.2 $11.3 $11.3 $12.8 $156.6 $156.6 $171.7 $.0 $.0 $22.3 $1,436.2 $1,436.2 $1,623.6 $.0 $.0 $17.9 $1,436.2 $1,436.2 $1,648.2 70% 90% $1,107.7 $1,209.4 $2.0 $2.3 $217.0 $229.3 $137.4 $143.3 $34.6 $36.6 $13.2 $13.9 $176.4 $183.2 $28.2 $38.1 $1,693.4 $1,798.6 $30.7 $59.6 $1,717.8 $1,825.1 P50 13.1% 16.4% 7.6% 7.2% 9.9% 13.2% 9.6% P70 20.6% 27.2% 12.0% 10.4% 14.6% 16.8% 12.6% P90 31.7% 42.9% 18.3% 15.2% 21.2% 22.7% 17.0% 13.0% 17.9% 25.2% 14.8% 19.6% 27.1% Note the values in the above table are for a fictitious project 20 Summary The cost risk model built in @Risk used a variety of techniques to both represent uncertainty from ranging workshops and from other studies. Highlights include: • Use of the RiskGeneral function to mimic the Double Triangular Distribution recommended by AACE for range estimating • Use of the Fit Manager to replicate output from other models as input to the overall risk model, in particular: - Results from a quantitative schedule risk analysis - Results from systemic parametric risk analysis - Automatic recalculation of the curve fit on change of input data • Use of RiskPercentile and other output functions to provide templated report formats that can be copied and pasted direct into presentational materials 21 Any Questions 22