Earned Value Variance Reporting Dos and Don’ts Presenter: Gary Heth, PMP Agenda Earned Value Basics •Earned Value in a Nutshell •Performance without Earned Value Earned Value Framework •Planning •Executing •Controlling Earned Value Benefits Earned Value Lessons Learned Earned Value Limitations Earned Value Do’s and Don’ts 2 Earned Value Basics 3 Earned Value Basics Earned Value In a Nutshell What is more important? •Knowing where you are on schedule? •Knowing where you are on budget? •Knowing where you are on work accomplished? It compares the PLANNED amount of work with what has actually been COMPLETED, to determine if COST , SCHEDULE, and WORK ACCOMPLISHED are progressing as planned. Work is “Earned” or credited as it is completed. Did we get what we planned, for the amount of money we planned to spend, and did we get it when we needed it? 4 Earned Value Basics Project Analysis Without Earned Value? Gantt Charts Most used PM tool for representing phases and activities of a WBS A clear way of showing schedule status to your sponsor and team Great for small projects but can be hard to read for larger projects with many dependencies Only show part of Triple Constraint (focus on schedule management) Married to waterfall development Does not adequately represent project size or size of the work element Magnitude of “behind schedule” condition can be misleading •If two projects are the same # of days behind schedule •Which of the two has the larger impact on resource utilization? •Gantt does not represent the difference •Gantt does not show resource management •Does not indicate if the task is “front” or “back” loaded % complete may be miss-represented 5 Earned Value Basics Project Analysis Without Earned Value? Gantt Charts ID Task Name 1 1.0 Requirements Definition 2nd Quarter Duration Predecessors Apr May 10 days 2 2.0 Architectural Design 10 days 1 3 3.0 Detailed Design 20 days 2 4 4.0 Coding and Unit Testing 45 days 3 5 4.1 Coding 25 days 6 4.2 Unit Testing 20 days 5 7 5.0 Integration Testing 15 days 6 8 6.0 System Testing 10 days 7 INFO 638 Jun 3rd Quarter Jul Aug Sep 4th Quarter Oct Nov Dec 1st Quarte Jan 6 Earned Value Basics Project Analysis Without Earned Value? Budget Spend Plan Medium to Large Projects – “S” Curve Project Spend Tracking •Provides a budget baseline for tracking actual costs against periodic budget targets. •Start by creating a time-phased budget by plotting your weekly, monthly, quarterly budgeted costs or hours (time and dollars) •Use MS Project baseline estimated project costs and plot graphically over time, they usually result in an “S” curve •Add MS Project actuals to plot dotted lines at each chosen interval to track variances. •Provides a simple Top-Level view of project financial performance useful for status reports and dashboards. •If you don’t have labor rates you will need to use budgeted vs actual hours. Challenges •Works fine if your project is on schedule – Spend plan still needs additional status information (for example Gantt) •If behind schedule – PM may not be able to understand project status from this graph •Actual budget could be in worse or better shape than shown •If your budget spend shows overspending and your schedule shows milestone slippage you know you are in trouble. You may not be able to tell how bad the trouble is. 7 Earned Value Basics Project Analysis Without Earned Value? Budget Spend Plan Budget Ceiling Spend Plan Actuals 8 Earned Value Basics Minimal Requirements EVM Requires 3 values •Planned Value (PV) - Baseline •Actual Costs (AC) – Based on Time Entry or Cost Entry •Earned Value (EV) – What you “earned” Work is “Earned” or credited as it is completed. Did we get what we planned, for the amount of money we planned to spend, and did we get it when we needed it? Answer: •Where have we been? •Where are we now? •Where are we going? 9 Earned Value Basics Minimal Requirements Term Interpretation (PV) Planned Value How much work you planned to have accomplished by now? Replaces BCWS (AC) Actual Cost Replaces ACWP (EV) Earned Value Replaces BCWP The budgeted costs of the work scheduled • The project’s time-phased budget • Can only change when baseline is changed What is the actual cost incurred ($ / Hours) The actual costs of the work completed during the month or reporting period • Actual costs by work code • Requires accurate charging of staff time to appropriate “control account” What is the estimated value of the work actually accomplished? The project’s physical progress • Progress reported in baseline or planned dollars • Represents sum of % completion for each task or deliverable Planned value and Actual Cost will be compared to Earned value in terms of differences / ratios Will result in variances and performances indexes 10 Earned Value Framework 11 Earned Value Framework Steps to Success Condensed ANSI/EIA748 32 Step Standard Planning •Step 1: Define the Scope (Planning) •Step 2: Determine Who Will Perform the Work •Step 3: Plan and Schedule Work •Step 4: Establish Resources and Budgets •Step 5: Determine Performance Metrics and Thresholds •Step 6: Create Performance Measurement baseline and Mgmt Control Executing •Step 7: Record Direct Costs Controlling •Step 8: Monitor EV Performance Against Baseline (Control Step) •Step 9: Forecast Final Required Costs (Variance Reporting Step) •Step 10: Manage Scope Through Change Control 12 Earned Value Framework Steps to Success Planning Steps Planning •Step 1: Define the Scope (Planning) •Step 2: Determine Who Will Perform the Work •Step 3: Plan and Schedule Work •Step 4: Estimate Work and Procurement •Step 5: Determine Performance Metrics and Thresholds •Step 6: Create Performance Measurement baseline and Mgmt Control Executing •Step 7: Record Direct Costs Controlling •Step 8: Monitor EV Performance Against Baseline (Control Step) •Step 9: Forecast Final Required Costs (Variance Reporting Step) •Step 10: Manage Scope Through Change Control 13 Earned Value Framework Steps to Success: Planning Step 1: Define the Scope Scope Definition • Single most important factor to a sound EVM process and implementation Work Breakdown Structure •Roadmap for analyzing the project progress and performance •Each element of the WBS is broken down into pieces – each piece defines responsibility to a person for that element •100% of scope – What is not in the WBS is not in scope •Work is broken down into measurable work packages •Focus on “authorized” work •Must be firm –Critical for Earned Value Projects Break the Work Packages into activities of the project. These should be included within your WBS and will produce the project schedule activities. Organization Breakdown Structure (matrix organizations) •Relates WBS elements at the work package level to the organizational unit responsible for completing the work 14 Earned Value Framework Steps to Success: Planning Step 2: Determine Who Will Perform the Work Who will perform the work? • Determine Skill Level Experience is faster but more costly Task identification takes place during this step Make or Buy Decision (Internal or Sub Contracting) •Will all or some of your project be outsourced? •Internal projects (Make Decision) has some cost flexibility •Scope definition critical for external (Buy Decision) Contracts are unforgiving – Cost to change can be excessive Critical to get scope right because cost to change can be excessive Responsibility Assignment Matrix (RAM) •Tied to the WBS with the OBS •Responsibly Chart for activities 15 Earned Value Framework Steps to Success: Planning Step 3: Plan and Schedule Work Scheduling is vital to Earned Value •Formal scheduling system (i.e. MS Project) is required •EV is nothing more than: Scheduling system, authorized scope, timeframes, and budgets •Reflects PM’s baseline “Planned value (PV)” for everyone to follow Critical Path (Task Sequencing) •Which tasks are sequential? Parallel •Network Diagramming tools •Must be aggressively managed when negative earned value schedule variances are discovered. •Will help determine which task variances receive the most attention High risk tasks must also be identified for same reason Begin Scheduling 16 Earned Value Framework Steps to Success: Planning Step 4: Establish Resources and Budgets Establish resource requirements (budgets) for all defined tasks Start-up sequence may be different for your organization •Scope, Schedule, and Budget vs. Scope, Budget, Schedule •Best practices – should be iterative but SCOPE DEFINITION MUST COME FIRST Enter resources for each task Determine the costs for the activities •Labor rates per task hour •Fixed cost per activity or work package (need to be spread across each lower level activity) Risk Analysis and Risk Management Plan Resource Leveling Exercise Management will then approve the budget Contingency – Never include contingency in an individual task… why? Will most likely cause a variance Contingencies and other reserves should be isolated and owned by the PM Must plan/schedule all defined tasks along with the authorized budget necessary to complete each task. This is required to have a viable project baseline. 17 Earned Value Framework Steps to Success: Planning Step 5: Determine Performance Metrics and Thresholds How is planned value completion measured? EV Systems rely on the effective collection of the Performance and the Costs. There are basically 2 types of methods of collecting the Performance: Discrete – something tangible to measure against •0/100 – no EV credit until 100% of work is completed. •50/50 and 25/75 – some EV credit at 25% or 50%, remaining EV at close of Work Package •Weighted Milestone – Each completed milestong completion “earns” a percentage of EV. Must be individually valued. May also consider monthly milestones •Physical % Complete – ie. 5% start, 50% unit test, 75% code review, 100% signoff •% Complete based on hours necessary to complete the task (common) least desirable • Units completed – For physical counts of product or outputs • Incremental milestones - % complete based on individual milestone completion Non-discrete – where the measuring of performance is not associated with anything tangible Level of effort should only be used when schedule performance is of no importance. A level of effort package can never give an indication of the work that has actually been performed (PV) will always equal the schedule work (PV) 18 Earned Value Framework Steps to Success: Planning Step 6: Create Performance Measurement baseline and Mgmt Control Earned Value requires a baseline project schedule (time-Phased budget baseline) Indirect costs “could” be included in some commercial type contracts Schedule Management focuses on the schedule performance of the project. • It looks at the relationships between the Earned Value (EV) and the Planned Value (PV). This will be your Planned Value (PV) for the life of the project Remember, MS Project can handle multiple baselines but you should always measure against the last baseline required by the stakeholders. This information will be plotted into a traditional “S” Curve diagram. Results should be added to the Performance Management Plan See Next Slide for an example 19 Earned Value Framework Steps to Success: Planning Traditional Cost Analysis – Budget Spend Plan Is this Good or Bad? Management Reserve Budget Ceiling Dollars Spend (PV) (Planned Costs) Cost to Date “Actuals” Time 20 Analysis Traditional Cost Analysis – Budget Spend Plan Is this Good or Bad? Actual costs are below planned costs (good news?) Management Reserve Budget Ceiling Unless you look at the planned costs of the completed work, you don’t know if this is good or bad That is exactly what is missing and what Earned Value will tell you Spend Plan (Planned Costs) Dollars Cost to Date “Actuals” Time 21 Earned Value Framework Steps to Success Executing Steps Planning •Step 1: Define the Scope (Planning) •Step 2: Determine Who Will Perform the Work •Step 3: Plan and Schedule Work •Step 4: Estimate Work and Procurement •Step 5: Determine Performance Metrics and Thresholds •Step 6: Create Performance Measurement baseline and Mgmt Control Executing •Step 7: Record Direct Costs Controlling •Step 8: Monitor EV Performance Against Baseline (Control Step) •Step 9: Forecast Final Required Costs (Variance Reporting Step) •Step 10: Manage Scope Through Change Control 22 Earned Value Framework Steps to Success: Executing Step 7: Record Direct Costs Purpose is to show how much money they have spent on a project Update the schedule with the period progress PM’s are required to enter actual hours on a consistent basis Costs from invoices are also entered After actuals are entered cost and schedule variances can be calculated This is where discrete measures come into play Earned value must then be relatable to the actual costs in order to determine the cost efficiency factor, called the Cost Performance Index (CPI). The CPI is likely the single most important metric for any project employing earned value. •To-Complete Performance Index (TCPI) 23 Earned Value Framework Steps to Success Controlling Steps Planning •Step 1: Define the Scope (Planning) •Step 2: Determine Who Will Perform the Work •Step 3: Plan and Schedule Work •Step 4: Estimate Work and Procurement •Step 5: Determine Performance Metrics and Thresholds •Step 6: Create Performance Measurement baseline and Mgmt Control Executing •Step 7: Record Direct Costs Controlling •Step 8: Monitor EV Performance Against Baseline (Control Step) •Step 9: Forecast Final Required Costs (Variance Reporting Step) •Step 10: Manage Scope Through Change Control 24 Earned Value Framework Steps to Success: Controlling Step 8: Monitor EV Performance Against Baseline (Control Step) Next Calculate all Earned Value components Determine cost and variances from baseline Determine three Required Values (PV budget, AC (Actuals) EV for the work accomplished to date •Tip: EV is based on a % of your budget – “We have actually completed “$” worth of work Calculate Variances, indices and factors from baseline • Variances (SV, CV, SPI) • Performance Indexes (CPI, SPI) -- ratio expressions of the Schedule and Cost Variances PMs should focus on exceptions using thresholds determined during planning •Management by Exception (Lessons Learned) •Cannot simply review parent tasks or phases What if there is a negative task and a positive tasks. Both will need attention •How critical is the task? Is it on the critical path or is it a high risk task? Start at the higher levels of the plan and work your way down Cost overruns are typically non-recoverable. 25 Earned Value Terminology Steps to Success: Controlling Basic EV - Summary Term Interpretation (PV) Planned Value This is your baselined budget as approved by your stakeholders (AC) Actual Cost These are your actual hours and costs as entered by the project team. PM must (at a minimum) audit these to verify Discrete Entries: Verify if work completed is “DONE” (EV) Earned Value What is the estimated value of the work actually accomplished? (BAC) Budget at Completion The project’s physical progress • Progress reported in baseline or planned dollars • Represents sum of % completion for each task or deliverable The sum of all of the budgets allocated to a program. How much did we Budget for the Total Job. Planned value and Actual Cost will be compared to Earned value in terms of differences / ratios Will result in variances and performances indexes 26 Earned Value Terminology Steps to Success: Controlling Variance Calculations Term Interpretation (SV) Schedule Variance Represents the difference between the amount of work actually completed and the amount of work scheduled to complete. This variance tells us if the schedule is ahead or behind what was planned for during this period of time. (CV) Cost Variance This is the Difference between the estimated and the actual cost to complete the same work. The cost variance tells us if the costs are higher than budgeted or lower than budgeted. (VAC) Variance at Completion Represents how much over/under budget will we expect to be at the end of the project It calculates the difference between the budget at completion and the estimate at completion. 27 Earned Value Terminology Steps to Success: Controlling Variance Calculations =1 (SV) Schedule Variance On schedule (EV – PV) (CV) Cost Variance (EV - AC) (VAC) Variance at Completion On budget <1 >1 Poor Performance If SV is less than 1.0 than your project is behind schedule. Less work completed than planned Good Performance If SV is greater than 1.0 than your project is ahead of schedule More work has been accomplished than scheduled Poor Performance If CV is less than 1.0 than your project is over budget. You have cost overruns Typically not recoverable Will continue to deteriorate unless corrective action is taken to mitigate Good Performance If CV is greater than 1.0 than your project is under budget You have cost under runs A negative number means we are doing poorer with costs than we anticipated A positive number means we are doing better with costs than we anticipated (BAC – EAC) REQUIRES PM ATTENTION Why would attention be needed for a positive number? •What if the schedule was over estimated? •Are we using our resources efficiently? 28 Earned Value Terminology Steps to Success: Controlling Performance Indices Term Interpretation (SPI) Schedule Performance Index •Calculates a ratio of the value of what was accomplished (EV) versus what was budgeted to accomplish it (PV), up to the status date. •We are (only) progressing at __% of the rate originally planned (CPI) Cost Performance Index •Calculates a ratio of the value of what was accomplished (EV) versus what was actually spent to accomplish it (AC), up to the status date. •Indicates if the cumulative actual costs during the assessed period are higher or lower than budgeted for the work completed. •Single most important EV calculation •We are getting ___$ out of every $1 spent 29 Earned Value Terminology Steps to Success: Controlling Performance Indices (SPI) Schedule Performance Index =1 <1 >1 On schedule Poor Performance If SPI is less than 1.0 than less work was completed on your schedule than what was planned Good Performance If SPI is greater than 1.0 than your work accomplished was more than planned Work done out of sequence can lead a team to believe the project is ahead of schedule when it is not Poor Performance If CPI is less than 1.0 than you are over budget. •Spending is more than planned for the work accomplished Good Performance If CPI is greater than 1.0 than you are under budget. • Spending is Less than planned for the work accomplished (EV / PV) (CPI) Cost Performance Index On budget (EV / AC) If your project is more than 20% complete, the CPI stabilizes. In other words, if you are overrunning at 20%, you will be overrunning at completion. Furthermore, the % overrun at completion will be greater than the % overrun to date! Source: research on 700 DOD contracts REQUIRES PM ATTENTION Why would attention be needed for a positive number? •What if the schedule was over estimated? •Are we using our resources efficiently? 30 Calculation Example You have a project to build a new fence. Fence is four sided (all sides are equal) Each side is to take one day to build Each side is budgeted for US $1,000 The sides are planned to be completed sequentially (one after the other) Today is end of day three Using the project status chart below, calculate EV, etc. When completed, check your answers on the answer sheet on the following page. Task Day 1 Side 1 S---F Side 2 Side 3 Side 4 Day 2 DAY 3 Day 4 Status Complete, Spent $1,000 S---PF ---F Complete, Spent $1,200 PS—S-PF Half Done, spent $600 PS----PF Not Started 31 Calculation Example Description Calculation Answer Interpretation PV Planned Value 1,000 + 1,000, + 1,000 3,000 We should have done $3K worth of work EV Earned Value Complete, Complete, half done or 1,000 + 1,000 + 500 2,500 We have actually completed $2,500 worth of work AC Actual Cost 1,000 + 1,200 + 600 2,800 We have actually spent $2,800 BAC Budget at Completion 1,000 + 1,000 +1,000 + 1,000 4,000 Our project budget is $4,000 CV Cost Variance EV – AC 2,500 – 3,000 -300 We are over budget by $300 CPI Cost Performance Index EV / PV 2,500 / 2,800 .893 We are only getting 89 cents out of every dollar we put into the project SV Schedule Variance EV – PV 2,500 – 3,000 -500 We are behind Schedule SPI Sched. Performance Index EV / PV 2,500 / 3,00 .833 We are only progressing at 83% of the rate planned EAC Est. at Completion BAC / CPI 4,000 / 2,800 4,479 We currently estimate that the total project will cost $4,479 ETC Estimate to Complete EAC - AC 4.479 – 2,800 1,679 We need to spend $1,679 to finish the project VAC Variance at Completion BAC - EAC 4,000 – 4,479 -479 We currently expect to be $479 over budget when the project is complete 32 Compare Actual Performance with the Baseline Plan $60K Earned Value on Bottom: Wk 2: Management Attention Corrective Action $50K $40K Legend: Planned Value Earned Value Actual Costs $30K $20K $10K Wk 1: Negative Cost Variance (EV-AC) Wk 1: Negative Schedule Variance (EV-PV) 1w 2w 3w 4w 5w 6w 7w 8w 9w 10w 33 Compare Actual Performance with the Baseline Plan $60K $50K $40K Earned Value now on top: Wk 5: Positive Cost Variance (EV-AC) Wk 5: Positive Schedule Variance (EV-PV) Legend: Planned Value Earned Value Actual Costs $30K $20K $10K EARLY MANAGEMENT ATTENTION…… 1w 2w 3w 4w 5w 6w 7w 8w 9w 10w 34 EVM – Early Attention to Issues Avoids this Problem $60K $50K BIG VARIANCE AT COMPLETION $40K $30K Legend: Planned Value Earned Value Actual Costs $20K $10K 1w 2w 3w 4w 5w 6w 7w 8w 9w 10w 35 Tracking the CPI & SPI Cost and Schedule Performance Trends Early Management Attention can result in improvement Periodic Index Value 1.2 1.0 Performance As Planned 0.8 CPI 0.6 SPI 0.4 0.2 0.0 10/06 11/06 12/06 02/07 03/07 Jan-07 Feb-07 Mar-07 01/07 Apr-07 May-07 Jun-07 Period Ending 36 Earned Value Framework Steps to Success: Controlling Step 8: Monitor EV Performance Against Baseline (Control Step) Variance analysis should address: •Separate discussion of CV, SV (current and cum) and VAC •Clear description of reason for variance •Quantity variances (e.g., price vs. usage) •Be specific, not general •Corrective action •Technical, schedule, and cost impacts •Impact to estimate at completion What is a significant variance? •% variance (e.g., >10%) •$ variance (e.g., >$50,000) •Critical path element •Risk/complexity •impact to other elements Performance Metric Green Yellow Red CPI/SPI 0.95 – 1.25 CV/SV <10% .85 - .89 Or 1.15 – 1.25 <10% and Corrective action in motion <0.85 Or > 1.25 > 10% or Correction action in not in place •Top 10, Top 20, etc. •Owner 37 Earned Value Framework Steps to Success: Controlling Step 8: Monitor EV Performance Against Baseline (Control Step) Potential Causes of Unfavorable (-) Cost Performance Potential Causes of Unfavorable (-) Schedule Performance Work more complex than estimated Manpower shortage Design review comments extensive Revised Execution Plan Rework Supporting organization behind schedule Unclear Requirements Late Vendor deliver Scope Creep (Gold Plating) Delayed customer feedback / decision Increased Market costs for labor or material Rework Overhead Rate Increases Design Review comments extensive Work more complete than anticipated Unclear Requirements Potential Causes of Favorable (+) Cost Performance Scope Creep The opposite of unfavorable cost performance 38 Earned Value Framework Steps to Success: Controlling Step 8: Monitor EV Performance Against Baseline (Control Step) Corrective Action- How to bring the task back in line •Crashing Goal: Gain the greatest amount of schedule compression with the least amount of cost Looks at cost and schedule tradeoffs Add Resources to the tasks in the critical path (internal or external) Reduce project scope Review changing the sequence of tasks Often causes costs to increase Which is the most important of the triple constraints to your stakeholders? (Cost, Schedule, Quality) •Fast Tracking Starting two tasks at the same time that were previously scheduled to start sequentially Can increase risk and might cause the project team to rework tasks Develop a process to “Reuse” code – This actually can reduce defect risk •Example: We are six months into a million dollar project. CPI = 1.2 (we are getting 1.2 dollars for every dollar spent SPI = .89 (we are progressing only at 89% of what was planned) What can be done? • Replace a more expensive member from the project team? (This would improve cost not schedule and add risk) • Bring in an additional programmer to work on the next two tasks. (Most effective choice) 39 Earned Value Framework Steps to Success: Controlling Step 9: Forecast Final Required Costs This step is in place to forecast the final required costs based on actual performance Keep management apprised so corrective action can take place Actual performance results are sunk costs. These are unrecoverable Any improvements in performance must come from future work. EAC indicates where the cost is heading Earned value provides the capability to quickly and independently forecast total funds required to complete the project (ETC) ETC is a forecast for completing the total project. Considers the performance to date plus future estimates Variance Reporting 40 Earned Value Framework Steps to Success: Controlling Step 9: Forecast Final Required Costs (EAC) Estimate at Completion A. BAC / CPI B.AC + ETC C.AC + BAC - EV D.AC + (BAC – EV) / CPI Gives us an idea of final costs of a project. It takes into account the original budget (BAC). The earned value and the cost performance index of the already complete work. As of now, how much do we expect the total project to cost? $____. Formulas: A. Used if no variances from the BAC have occurred or you will continue at the same rate of spending B. Used when the original estimate assumptions were fundamentally flawed or no longer relevant due to a change in conditions • Requires PM to perform bottom up evaluation of Estimate to Complete • Example: Complete change in in environmental regulations creates a need for a different design than was scoped. Need rebaseline. C. Used when current variances are seen as atypical and the expectation is that similar variances will not occur in the future. Actual to date plus remaining budget modified by performance. D. Used when current variances are seen as typical of future variances Most respected, since cumulative variances are indicative of future variances (ETC) Estimate to Complete From this point on, how much MORE do we expect it to cost to finish the project? EAC - AC An estimated cost to complete the remaining work on the project . 41 Project Earned Value Analysis Sample Dashboard 1.50 140 1.50 Behind Schedule and Under spent 140 130 130 1.20 1.20 1.10 CPI Ahead of Schedule and Under spent 0.90 SPI = 0.71 CPI =Target 0.86 SPI = 0.48 CPI = 0.81 1.10 Target 0.90 0.80 0.80 07/15/05 08/25/05 0.70 0.60 0.50 06/28/05 0.50 0.70 0.60 Ahead of Schedule and Over spent Behind Schedule and Over spent 0.30 0.70 SPI = 0.61 CPI = 0.74 0.90 1.10 1.30 1.40 0.50 1.60 SPI 42 Project Earned Value Analysis MS Project 2003 Variance Report Example 43 Let software tools do the number crunching 44 Earned Value Framework Steps to Success: Controlling Step 9: Forecast Final Required Costs MS Project (2003) Earned Value tools (downloads) • Help>Performing Earned Value Analysis • You will be taken to MS Project Download Template Page Manage costs during the project life cycle (Article) • Use these strategies to ensure that your project stays within your budget. Goal: Monitor costs (Article) • Examine your current, actual, remaining, and baseline cost totals in Project 2003. Goal: Adjust costs to keep the project on budget (Article) • After you identify a budget problem, learn to take corrective action with Project 2003. Project earned value analysis (Template) • Track time-phase expenses for projects by using this template. Cost analysis with Pareto chart (Template) • Use this statistical method to identify the most critical cost problem areas to improve. Project resource plan (Template) • Use this template to communicate project resource planning information to all key project stakeholders. 45 Project Earned Value Analysis MS Project 2003 Project earned value analysis (Template) Track time-phase expenses for projects by using this template. Metric Budget at Completion Actual Cost Earned Value Planned Value Cost Variance Cost Performance Index Schedule Variance Schedule Performance Index Estimate to Completion Estimate at Completion Variance at Completion Status Thresholds Abbre v. XYZ Project Jan Description Formula/Value BAC Baseline cost for 100% of project. N/A AC Total costs actually incurred so far. N/A Amount of budget earned so far based on physical work accomplished, without EV reference to actual costs. N/A The budget for the physical work scheduled to be completed by the end of the time PV period. N/A Measure of cost overrun. The difference between the budget for the work actually Earned Value–Actual Cost CV done so far and the actual costs so far. EV–AC Cost efficiency ratio. A CPI of 1.00 means Earned Value/ that the costs so far are exactly the same Actual Cost CPI as the budget for work actually done so far. EV/AC Measure of schedule slippage. The difference between the budget for the work Earned Value–Planned actually done so far and the budgeted cost Value SV of work scheduled. EV–PV The schedule efficiency ratio. An SPI of 1.0 Earned Value/Planned means that the project is exactly on Value SPI schedule. EV/PV Estimate at Completion– Actual Cost ETC The expected additional cost to complete. EAC–AC Budget at Completion/Cost Expected total cost based on the current Performance Index EAC cost efficiency ratio. BAC/CPI Budget at Completion– Estimated cost overrun at the end of Estimate at Completion VAC project. BAC–EAC (Cost Performance Index+Schedule Performance Index)/2 Average of CPI & SPI. (CPI+SPI)/2 GREEN = On track >1.0 YELLOW = Slightly behind schedule or budget >0.85 RED = Needs immediate attention >0.65 BLACK = Killed or Restore <0.65 Budget at Completion (BAC) Feb Mar Apr May Jun Jul Aug Sep Oct $1,230 $1,230 $1,230 $1,230 $1,400 $1,400 $1,400 $1,400 $1,400 $1,400 Earned Value (EV) $100 $200 $300 $450 $750 $800 $1,125 $1,200 $1,400 $1,400 Actual Cost (AC) $100 $205 $315 $600 $800 $1,000 $1,200 $1,350 $1,475 $1,525 Planned Value (PV) $100 $220 $325 $550 $725 $925 $1,175 $1,275 $1,450 $1,500 Cost Variance (CV) $0 ($5) ($15) ($150) ($50) ($200) ($75) ($150) ($75) ($125) Schedule Variance (SV) $0 ($20) ($25) ($100) $25 ($125) ($50) ($75) ($50) ($100) Cost Performance Index (CPI) 1.00 0.98 0.95 0.75 0.94 0.80 0.94 0.89 0.95 0.92 Schedule Performance Index (SPI) 1.00 0.91 0.92 0.82 1.03 0.86 0.96 0.94 0.97 0.93 Estimate to Completion (ETC) $1,130 $1,056 $977 $1,040 $693 $750 $293 $225 $0 $0 Estimate at Completion (EAC) $1,230 $1,261 $1,292 $1,640 $1,493 $1,750 $1,493 $1,575 $1,475 $1,525 Variance at Completion (VAC) $0 ($31) ($62) ($410) ($93) ($350) ($93) ($175) ($75) ($125) YELLOW YELLOW YELLOW YELLOW YELLOW YELLOW Status based on Average Performance Index GREEN RED YELLOW RED Comments New baseline set 46 Project Earned Value Analysis MS Project 2003 Trend Analysis Earned Value Analysis $1,800 Performance Index 1.10 $1,600 1.00 $1,400 $1,200 0.80 $600 Efficiency $800 $ (000) $1,000 0.90 0.70 $400 $200 0.60 $0 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Period 0.50 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Period Budget at Completion (BAC) Actual Cost (AC) Earned Value (EV) Planned Value (PV) Cost Performance Index (CPI) Schedule Performance Index (SPI) 47 Project Earned Value Analysis MS Project 2003 Trend Analysis Variance Analysis Estimate at Completion $1,800 $50 $1,600 ($100) $1,500 ($150) ($200) $ (000) ($50) $1,400 $(000) $1,700 $0 $1,300 ($250) ($300) $1,200 ($350) $1,100 ($400) $1,000 Jan ($450) Jan Feb Mar Apr May Jun Jul Aug Sep Feb Mar Apr May Jun Jul Aug Sep Oct Oct Period Period Cost Variance (CV) Schedule Variance (SV) Budget at Completion (BAC) Estimate at Completion (EAC) 48 Earned Value Framework Steps to Success: Controlling Step 10: Manage Scope Through Change Control Integrated Change Control Without a CC process performance baselines become invalid Changes and new work due to issue management should be added to the schedule. All change requests must be addressed quickly •Accept or reject by Change Control Board, Steering Committee or Sponsor PMs should have authority to say no to changes All changes should be documented No Gold Plating! • Single most important factor to a sound EVM process and implementation 49 Earned Value Benefits 50 Earned Value Benefits Provides managers with information at a practical level of summarization Alerts PMs to potential schedule and cost risks early Provides a documented project performance trail Communicates project status Tracks and monitors discrete project metrics Relates time-phased budgets to specific contract tasks Provides comparisons between planned and actual work Provides accurate and reliable readings of cost and schedule performance Actual performance at the 15% complete point can be used to predict final performance. The schedule performance index (SPI) is useful in assessing how much work has been accomplished. The CPI index provides a statistical basis for a “best case” final estimate. The CPI and SPI indices may be combined to statistically forecast the “most likely” final estimate. 51 Earned Value Key Lessons Learned 52 Earned Value Key Lessons Learned Lesson Attributed To 1 Schedule Compression incurs Corrective Action •Work cannot be scheduled and resourced in an optimal fashion •Schedule compression almost always results in inefficiencies due to resource loading and reword additional project cost 2 Education and buy-in are Lack of Senior Level Commitment • Executives • Project Managers • Staff 3 WBS Quality / Reliability WBS Quality not maintained • All parties buy in to the WBS • WBS is simple - composed of measurable, deliverable pieces • Risk-adjusted SPI/CPI 4 Sustenance Perceived Complexity Keep Process Simple and Tool Supported – See #2 5 No variance reports / No policy in place or no standard •Weekly high level metrics, Monthly Dashboard reporting with full EV •Graphs and text – Period/period compare 6 Manage by Exception – Too Micro Management Manage by exception. Focus on significant variances to the plan. Apply timely corrective actions. 7 Tracking conducted PM Discipline Track – Track – Track No Pain NO Gain 8 Time for data measurement, Growing Pains Plan ahead – Provide amble PM time to create and research results crucial Through time not just to start Plan the work carefully and accurately dashboards much management will scare your PMs inconsistently. input, and manipulation can be considerable. 53 Earned Value Limitations 54 Earned Value Limitations Traditional EV is not intended for non-discrete (continuous) effort. •When a plan contains a significant portion of LOE intermixed with discrete effort, EVM results will be contaminated The use of EVM presumes that stakeholders care about measuring progress objectively. Quantifying/measuring work progress can be difficult. Time required for data measurement, input, and manipulation can be considerable. EVM requires thorough and accurate planning of cost and schedule to be effective. Future performance is being forecast based on past performance (so if your data is bad, so is your forecast) Earned Value does not measure quality EVM is designed to ensure that the future predicted by EVM does not materialize – as it encourages corrective action 55 Earned Value Do’s and Don'ts 56 Earned Value Do’s and Don'ts Do’s Take the necessary building steps seriously •Integrate the scope of work, schedules, and costs using a WBS. Train your stakeholders. It is critical they can understand the variance reports Document all performance metrics and thresholds in the Project Plan (Performance Plan) Determine how you will measure your tasks (discrete options) Assess variances early – No later than 15 % in ..Highest Potential for Cost / Schedule Recovery.. Make sure the bad news is heard Take corrective action •Staff changes? •Mid-term evaluation of work •Crashing •Fast Tracking 57 Earned Value Do’s and Don'ts Do’s Request and monitor that staff enters actual hours each week Provide PMs with a reliable labor and overhead rates for each resource. •Without the rate CPI does not mean much Have policies in place for rebaselining •Keep your original baseline in tact and always measure against it •If for no other reason, it keeps historical estimates in place Re-plan as necessary •Budget increase? •Scope change? •Schedule change? Create a weekly or Monthly Variance Report Use standard templates for reporting •Helps with the learning curve •Helps to compare or aggregate data across projects Institute Standard Reporting Cycles 58 Earned Value Do’s and Don'ts Do’s Perform scheduling and WBS creating at the same time. •There is a documented order defined in the PMBOK •Most Common Error Don’t set up your project with “level of effort” planning. •Creating one task (i.e. design) and allocating a certain number of people to it over a fixed amount of time. •Earned value will not be possible. The only measurement possible will be cash flow Leave planning until your financials and WBS are integrated through Cost Control •Cost account structures and the level of detail to be tracked must support the earned value management system. •Each cost account should have a unique identifier to enable an accurate calculation of the actual cost of work performed (ACWP). Manage at only the contract / engagement level •Rarely are projects managed at the WBS Deliverable Level – EV Loses Control 59 Earned Value Do’s and Don'ts Don'ts Focus solely on schedules. This is the typical PM Mindset by Business Culture. PMs: • Are focused on Schedules --NOT Costs • Manage at the contract level vs the WBS Deliverable Level Leave real Billing Rates out of the WBS •Competition Sensitive Data •Artificial Blended Rates •Fixed Price, So Why Bother •The $1.00 per hour fix Let your tasks or milestones get too large in duration, cost and scope •Could impact PM’s ability to identify variances at a level that can be corrected Include multiple individuals on the same task whenever possible •Helps identify root cause of variances easier Forget Success factors •A full WBS is required (all scope) •Beware of GIGO: Garbage-in, garbage-out No Gold Plating! If you know there is a significant variance don’t wait until you create the monthly report to begin corrective action planning Assume adding a resource or adding paid overtime will “fix” the schedule variance – most likely will create a CPI issue. Cover this with stakeholders early. 60 Why do we need early warning Course corrections are easier when you have time to make small adjustments It’s too late when you’re this close to the iceberg! 61