WATER PENETRATION TEST APPARATUS ME 493 Final Report – Year 2010 Portland State University Industry Advisor/Sponsor Group Members Academic Advisor Bryan Hayes Morrison Hershfield Andy Park Luke Defrees Andrew Williams Brian Pinkstaff Dr. David Turcic Portland State University 1 EXECUTIVE SUMMARY A small division of Morrison Hershfield, an engineering consulting organization, performs tests on exterior windows, curtain walls, skylights, and doors for water penetration. It does so through the use of a spray rack, which is designed to evenly spray water at specified flow rates (standard ASTM E1105-00) onto each test specimen. Because this standard does not outline any required design elements other than symmetry, there are potentially unlimited design possibilities to meet these flow rate requirements. The spray rack that Morrison Hershfield currently utilizes has a number of design flaws and performance deficiencies that limit productivity, and produce questionable results. This capstone project involves addressing these deficiencies, by designing, prototyping, and testing an original, fully-operational spray rack that meets these standards, and satisfies the constraints set forth by Morrison Hershfield. At the start of this project, these constraints were defined in a PDS document, along with a timeline outlining the goals for completing different stages of the project. This report evaluates the overall success of the project by examining whether each of the constraints specified in the PDS were met. 2 TABLE OF CONTENTS Executive Summary…………....………………………………………………………………………... 2 Introduction and Background.……..………………………………………………………..……... 4 Mission Statement.............................................................................................. 5 Main Design Requirements……………………………………………………………………………. 5-8 Final Design….…………….…………………………………………………………………………..…….. 8-11 Evaluation of Design.……….…………………………………………………………………….….….. 12-15 Conclusion…….…………………………………………………………………………………….…….….. 15 Appendices......................................................................................................... 16 A. Assembly Components............................................................................................... B. Justification of Final Design........................................................................................ C. Operation Manuals……………………………………………………………………………………………….. D. Product Data Specification Table............................................................................... E. House of Quality………................................................................................................. F. Part Drawings………………............................................................................................. G. Bill of Materials.………….............................................................................................. H. ASTM E 1105-00 Standard.......................................................................................... 17-21 22-34 35-36 37-38 39 40-48 49-52 53-57 3 INTRODUCTION AND BACKGROUND the catch box in front of the nozzles and simulating a spray test for a long enough Morrison Hershfield’s building science period of time to gather a measurable consultants test the resistance of installed amount of water. The flow acquired from products such as windows and doors to each corner must be within the range stated water penetration. The tests are performed in the ASTM standard. using a spray rack, which is a labyrinth of piping containing strategically placed nozzles that project water uniformly against a test specimen. An example of a spray rack can be seen in Figure 1. The amount of water applied to a test specimen must meet the flow requirements outlined in the ASTM E1105 standard, which details the constraints for successful water penetration tests. Figure 2. Catch box currently used by Morrison hershfield to calibrate their spray rack. Upon completion of a test, the installed test specimen is thoroughly inspected for water leakage. If any leakage is discovered, appropriate action is taken to determine the party at fault. Although the current spray rack apparatus used by Morrison Hershfield is not calibrated properly, it is the only Figure 1. Typical spray rack device used in water penetration tests. system available for their building science consultants. This is one of the primary In order to meet the flow requirements, the spray rack must be calibrated every six months. Calibration is done using a catch box, as seen in Figure 2. Each of the four reasons our group has been asked to improve upon their current device. Other significant design considerations that have been addressed by the customer include: corners of the rack are calibrated by placing 4 modularity, material integrity, and portability of the rack itself. These product conditions and performance criterion have been examined and presented in the team’s Product Design Specification table in Appendix D. • Improve portability and usability of previous design • Ensure safety and structural integrity of design • Nice aesthetics and professional appearance • Is completed within Morrison Hershfield’s MISSION STATEMENT budget The Water Penetration Test Apparatus Team will design and prototype a spray rack system ASTM E 1105-00 Calibration Standards to exceed the performance and usability of Meeting the calibration requirements Morrison Hershfield’s current testing device. verifies that the water penetration testing In addition, an easy to use catch box will be device performs properly. The key elements designed and fabricated in order to meet all of functionality include a uniform spray of the calibration and testing standards pattern and meeting a target spray rate. As outlined in the ASTM E 1105-00 document. stated in the standard, the water spray Finally, this project will be completed on system shall deliver water uniformly against time, meeting appropriate deadlines, and the exterior surface of the test specimen at within the budget requirements outlined by a minimum rate of 5.0 US gal/ft2-hr. The Morrison Hershfield. acceptable tolerance for the device ranges from 4-10 US gal/ft2-hr. MAIN DESIGN REQUIREMENTS Improved Portability and Usability In order for this project to be considered The ease of use of the water penetration successful, it must meet the following testing device relies upon required requirements: manpower, setup time, and transportation. The device should be assembled, • Meet flow rate requirements of ASTM standard E 1105-00 transported, and operated by one person unless it is being used in suspension which would require two people. The assembly or 5 disassembly of the spray device should take a consistent in appearance throughout the maximum of 5 minutes. Most of the parts rack. need to be stock and easily replaceable in case they break or malfunction. Finally, it is important that the device is able to be transported via a compact passenger car, eliminating the need for a truck/utility Top-Level Alternative Conceptual Solutions After brainstorming possible design ideas, the team evaluated three final design solutions. A circular rack, flexible tubing rack, and a square modular rack were vehicle. compared to the current Morrison Hershfield Structural Integrity model in the scoring matrix in Table 1 below. The structural integrity of the water The square modular rack accumulated the penetration testing device maintains that it highest score. will withstand the stresses acting on it during Table 1: Decision matrix for 3 possible design solutions. Morrison Hershfield Square Modular Rack Flexible Tubing Rack Circular Rack operation. The spray device must be Portability 3 4 5 5 operation. The device also needs to Ease of Use 3 4 3 4 withstand the rough handling and abuse of a Maintenance 2 4 2 4 Durability 2 4 2 2 Calibration 1 5 3 3 Adjustable Spray Range 3 4 3 3 Safety Features 3 4 4 4 ASTM E1105 3 5 3 4 Manufacturing 4 5 2 2 Cost 4 4 4 2 Total 28 43 31 33 43 86 % of Possible Score 1 = low, 5 = high 62 66 structurally sound when standing on the ground or in suspension. This ensures the safety of the users and other individuals within the proximity of the device during construction environment while maintaining functionality. Because the device will be regularly exposed to water, all the device parts need to be corrosion resistant. Aesthetics The water penetration testing device should PDS Criteria have a neat and professional appearance. Other key details include hardware that is 6 Circular Test Apparatus The circular test apparatus, shown in Figure 3 below, has the following advantages: • Easily disassembled: the piping can be unthreaded from the center hub to be broken down into an easily carried bundle. • For a 5 x 5 ft specimen, this design will meet the uniformity specification. • Extra piping can be threaded to the ends of each pipe to test larger specimens. • Because this device can be completely disassembled, parts may get misplaced. • The lack of structure on the outer pipes could result in severe damage if dropped or impacted. Flexible Tubing Apparatus The flexible tubing design, show in Figure 4 below, has the following advantages: • Assembly affords flexibility in transport. • Cost of materials is very low. • Overall weight is very low. Figure 3: Circular Apparatus Assembly Figure 4: Flexible Tubing Assembly The design has the following disadvantages: The following limitations of this design • Manufacturing is expensive. include: • Onsite assembly would be difficult. • If testing large specimens (up to 10 x 10 ft) • Calibration setup would be inconsistent. the extra piping will not meet the uniform spray grid requirement. There will be Square Rack excessively large gaps between the pipe The square rack, shown in Figure 5 below, ends. includes the following advantages: • This device would be harder to fabricate than a rectangular spray rack. • Easily adjustable to accommodate a variety of different sized test specimens. 7 • Easy to manufacture. telescoping stand were selected to be • Horizontal water supply pipe fit with valves manufactured at the PSU machine shop with capable of creating consistent pressure Aluminum T6061-T6. throughout the rack. The primary material is ¾ in. copper tubing • With the aid of quick release copper that is brazed together and painted Morrison couplings, rack can be broken down and Hershfield colors. The overall structure disassembled for portability. meets industrial grade requirements for stress and reliability. This design allows simple monitoring and adjustment of flow rates if the rack were to fall out of calibration. Portability is also maximized with quick release copper couplings, easily disassembled side supports, and medium length horizontal pipes. Figure 5: Square rack assembly The design had the following disadvantages: • Heavier than other designs. • Moderately high cost to fabricate. FINAL DESIGN Overview The overall water penetration test system Final Design constructed for Morrison Hershfield consists Our final design incorporates the advantages of four main assemblies. These items include from each design. The final design is simple, the spray rack system, spray rack stand, cost effective, and calibrated. The horizontal calibration stand, and calibration box. The design eliminates the need for multiple following sections describe each of these valves and pressure gages. The design can be parts in detail. Specific components semi-permanently set, with no additional important to the functionality of the main need for adjusting valves and regulating flow assemblies can be found in Appendix A. after the initial calibration. The hanging mounts, vertical supports, wall spacers, and 8 Spray Rack car. To give the spray rack form and rigidity, The spray rack system shown in Figure 6 was aluminum vertical supports were designed to meet the requirements incorporated into the design. The supports presented in the PDS document. In order to also restrict rotation of the horizontal spray achieve equal flow rates from the top to pipes at the quick release coupling bottom sections of the spray rack, a single connections. vertical supply pipe was designed with two flow regulating valves placed between the three horizontal spray pipes. Appropriate valves were selected such that the user can throttle the system to obtain consistent flow rates at all elevations then remove the valve handle. This minimizes the risk of accidental throttling while the system is on a job site, and hence un-calibrating the system. Figure 6: Front view of the final spray rack system. At the inlet of the vertical supply pipe a pressure gauge is placed following the inlet throttling valve. This characteristic was designed to meet ASTM standards. When water is introduced to the system, the user can adjust the inlet throttling valve to obtain the appropriate calibration pressure. The horizontal spray pipes are connected to the vertical supply pipe by quick release copper couplings. Selection of the couplings was made to allow disassembly of the entire spray rack system. When disassembled, the rack can be bundled together and transported to a job site in a small passenger Small orifice (0.05 in.), 120 deg full cone spray nozzles were selected to meet the necessary flow rates outlined in the ASTM standard. Appendix B shows the necessary calculations used in nozzle selection. Placing the nozzles 2 ft. apart on the horizontal pipes and 2.25 ft. vertically, the spray pattern achieves approximately 30% of overlap between all adjacent nozzles when the spray rack is spaced 12 in. away from a test specimen. Significant spray overlap is necessary to ensure wetting of all parts of a test specimen. 9 Telescoping window spacers were designed two sandwiched plates that secure it in the to allow proper spacing between the spray same plane as the telescoping tubing. Eye rack and a test sample. The telescoping bolts allow for the use of industrial strength tubing allows for spacing between 10 and 18 carabiners to make the connection between inches. By spacing the rack 18 in. away from the spray rack stand and the hanging mounts a sample, the water coverage area can be of the spray rack system. The stand can also increased from 33 - 53 ft2 when compared to be used during calibration to hold the rack 12 in. of spacing. Increasing the distance securely on the ground. Because the stand from the rack to the specimen requires an will be used for these multiple elevations, a increase in system pressure in order to pivoting system was designed at the base to maintain proper water flow rate allow shallow angles of the stand during requirements. Hanging mounts were calibration and large angles when the stand is designed for easy suspension of the spray used to elevate the spray rack. Installed on rack with either ropes or the spray rack the bottom of the base plate is a thick rubber stand. slab to ensure large frictional forces to hold the stand in place on surfaces like cement or Spray Rack Stand concrete. The installed products that Morrison Hershfield test range from ground level to multi-story, high rise buildings. Specimens on the second floor and higher must be tested by suspending the rack from ropes. Products at ground level and on the first floor of a building can be tested using the spray rack stand illustrated in Figure 7. In order to reach heights of up to 9 ft. above the ground, thick walled aluminum telescoping tubing Figure 7. Spray rack stand assembly. Calibration Stand was selected as the main structure of the During calibration of the spray rack system, stand. The horizontal tube is held in place by the calibration box and graduated cylinders 10 must be placed on a stand to reach the required locations detailed in the ASTM standard. The stand designed in Figure 8 accomplishes this task by incorporating a vertical pole held in place by a tripod base. All materials of the stand were chosen to be aluminum for corrosion resistance and weight reduction. The bottom plates of the stand are 0.25 in. thick aluminum that are designed so the vertical tube can protrude through the top plate, and rest on the bottom plate. An acrylic block is situated where the tube rests on the bottom plate and forms a tight fit on the inside of the vertical tube for further restriction of sideways movement. This configuration allows the vertical tube to be removed from the base for compact storage. The total height of the stand is 6 ft, which exceeds the maximum height of the spray rack system, allowing all possible locations of the rack to be calibrated. Figure 8. Calibration stand assembly. Calibration Box The catch box in Figure 9 is used to gather the impinging spray from the rack during calibration, and was designed according to the ASTM standard. It is 2 x 2 ft. and separated into four equal sections. The walls of the calibration box are 4 in. wide to ensure that all of the spray water is captured and accumulates within the box. A hole is drilled in the bottom corner of each of the four box sections. Micro tubing can be installed in the holes through the back of the calibration box to displace the water from the collecting areas to the graduated measuring containers. To hang the rack on the calibration stand, an I-plate configuration was designed. Two small 0.25 in. thick plates are bolted 12 in. apart on the back of the box. When the Iplate is bolted to the two spacing plates, the box can be fastened to the calibration stand 11 by two hose clamps. The full assembly can acceptable flow rates must be between 0.25 be found in Appendix A. – 0.63 liters/min-ft2. Figure 9. Final manufactured calibration box. Figure 10: Locations for testing flow rates of the spray rack. Each square represents 1 square foot, and each grouping of EVALUATION OF DESIGN 4 squares represents how samples were taken. After the final design was approved by After testing the rack at various internal members of Morrison Hershfield, a prototype pressures, the minimum pressure required at of the final design was fabricated, and a 12 inch rack-wall separation for acceptable various aspects of the design were evaluated flow rates across the entire spray surface was according to the product design found to be 25 psi. At 25 psi, the range of specifications. flow rates were 0.25-0.49 liters/min-ft2, meeting ASTM requirements at all four Flow Rates locations. If the internal pressure of the The ASTM E 1105-00 standard requires that system were to fall below 25 psi, parts of the the spray rack be tested for flow rates at four spray surface may not receive acceptable specific locations at the theoretical surface: flow rates. At 20 psi, the flow rates at the both the upper corners, and at locations top corners fell below 0.25 liters/min-ft2, but along the horizontal center, one quarter the the center test areas did not. This is largely length of the total width from each side. due to the fact that there is minimal spray Figure 10 shows the four locations below. With 1 ft2 sample areas, the range of 12 nozzle overlap at the outermost sample areas. At an 18 inch rack-surface separation, the spray rack effectively covered 61% more surface area, but the required internal pressure of the system rose to 30 psi. When the pressure of this system fell below 30 psi, it behaved almost identically to that of the 12 inch rack-wall separation system. Portability The portability of the new spray rack system has fully satisfied the requirements of the Figure 11: The spray rack disassembled and bundled with Velcro straps. PDS. The rack can be assembled/ disassembled on site by one person in The spray rack and stand were tested and approximately 5 minutes, which minimizes easily fit into a compact sedan (Nissan 200SX) the additional time needed to improve by one person. Rubber caps were also portability. attached to the ends of each member, shown Disassembled and bundled with Velcro straps in Figure 12, so that forces of impact from shown in Figure 11, the rack’s dimensions are transportation and industrial handling will be 6 ft. long, with its largest diameter equal to more effectively absorbed. about 9 inches. The spray rack stand, used for mounting at ground level applications, is Maintenance a 6.5 ft long, which intersects perpendicularly Although the spray rack has not required any at one end with a 3 ft section of tube. maintenance after the fabrication was completed, the team does not foresee many instances where potential problems could not be easily maintained and serviced in the field or at the Morrison Hershfield facility. 13 Copper was chosen as the piping material Setup/Operation with soldered joints. If a section of piping, The setup and operation constraints of the valve, or pressure gage were to be PDS were satisfied, maintaining or improving irreparably damaged, the affected area can upon the current spray rack used by be cut out if needed, and replaced with parts Morrison Hershfield. As mentioned commonly found at most hardware stores. If previously, assembling the rack can be leaks occur, the joints can be heated and re- routinely performed in about 5 minutes by soldered. one worker. The ground level stand is a Brass nozzles and bushings, shown in Figure single telescoping tube, which can be 12, were chosen with simple designs to controlled by one person. Once assembled, minimize corrosion, to be easily cleaned of the rack (without water) weighs 24.3 lbs, clogs, and easily replaced. These parts were which is far below the PDS constraint of purchased online at the popular website 50lbs, allowing one person, instead of two McMaster-Carr, where in the event a nozzle for the current spray rack, to setup and or bushing becomes damaged, the part can mount the spray rack at ground level be replaced within a couple of business days applications. at minimum cost. The total setup of the rack or mounting of the rack to the installation at ground level takes no more than 15 minutes, which satisfies the PDS requirement. The team was unable to test the suspension mounting time, due to limited resources. Although it is conceivable that the spray rack be setup and mounted onto roof-suspended Figure 12: Rubber caps and brass nozzles and bushings were used in the final design, which require little maintenance, and are easily replaceable. applications by a single worker, the new design was intended to be operated by two workers; which is also required for Morrison Hershfield’s current spray rack. This is due to the increased degree and quantity of risk 14 inherent to suspending a spray device of this only the internal pressure of the device at size from a large building. Two workers can steady state needs to be monitored. The ensure more stability and accuracy in project was also completed in the timeline suspending this device, and can monitor each specified, meeting acceptable deadlines, and other as well to ensure there are no crucial under budget by $300. oversights that may result in injury or even Brian Hayes of Morrison Hershfield has death of people below. viewed the prototype and was pleased with The simplicity of operating the rack is the final design. He commented that all of maintained, where only the internal pressure the major assemblies were more functional of the system needs to be monitored. The and appeared more user friendly than their coverage area and expandability however are current device. By meeting or exceeding the improved. The current design used by the requirements outlined in the PDS, the project sponsor has a relatively small, fixed customer, and the PSU capstone curriculum, coverage area. With the new design, the the design and prototyping of our water spray rack has a larger coverage area, which penetration testing apparatus was a success. can also be expanded if necessary. CONCLUSION The team has designed, fabricated, and tested a water penetration testing device that meets or exceeds the requirements set forth in the product design specifications. Most importantly, our testing showed that flow rates of the spray rack at an internal pressure of 25 psi satisfy the ASTM requirements. The rack is more easily transported and covers a larger surface area than the customer’s current apparatus. Operation simplicity is maintained, where 15 appendices 16 APPENDIX A: ASSEMBLY COMPONENTS The following components and parts were used in the main assemblies of the entire spray rack and calibration system. Name: Spray Rack System Main Assembly: Spray Rack System Description: The spray rack system is used to uniformly spray water on installed exterior products. Name: Nozzle Spray Pattern Main Assembly: Spray Rack System Description: Spacing the spray rack 12 in. from the test specimen results in the illustrated water spray pattern. Nozzle spacing was selected to achieve approximately 30 percent of spray overlap for proper uniformity of spray onto the specimen. Name: Quick Release Copper Coupling Main Assembly: Spray Rack System Description: The couplings were selected to connect the horizontal spray pipes to the vertical supply pipe. Quick release couplings allow for disassembly of the entire spray rack system for ease of transportation. 17 Name: Disassembled Spray Rack System Main Assembly: Spray Rack System Description: When completely disassembled, the spray rack system can be bound by Velcro straps and transported in a small passenger car. Name: Telescoping Window Spacers Main Assembly: Spray Rack System Description: The spray rack must be spaced 12 in. away from the test specimen to achieve the cover pattern presented above. Telescoping winder spacers allow the user to achieve this distance, and increase the distance to expand the spray coverage area. Name: Hanging Mounts Main Assembly: Spray Rack System Description: In order to suspend the spray rack by ropes or the spray rack stand, the hanging mounts must be used to relieve stress on the copper piping. The two part design allows for adjustment of the mount in horizontal and rotational directions by loosening the bolts and positioning in the correct orientation. 18 Name: Vertical Supports Main Assembly: Spray Rack System Description: To give the spray rack rigidity, the vertical supports can be installed onto the horizontal spray pipes to eliminate rotation of the pipes at the quick release coupling connections. Name: 0.05 in., 120˚ Full Cone Spray Nozzles Main Assembly: Spray Rack System Description: The nozzles selected produce a flow rate of 0.4 GPM at 30 psi. Name: Pivoting Stand Base Main Assembly: Spray Rack Stand Description: To achieve a range of angles necessary for the spray rack stand, the pivoting base was designed to allow the user to easily position the stand and rack where ever it needs to be placed. 19 Name: Calibration Stand Assembly Main Assembly: Calibration Stand Description: Stand used to hold the calibration box and container rack at heights governed by the ASTM standard. Name: Calibration Stand Base Main Assembly: Calibration Stand Description: To reduce sideways motion of the vertical tube, the acrylic block forms a tight fit against the inside of the square tubing. This allows eliminates the need for permanent fixing, and permits easy storage as two separate parts. Name: Container Rack Main Assembly: Calibration Stand Description: The container rack is used to hold the graduated containers by sliding the two horizontal square tubes through the handles of the containers. Name: Calibration Box Main Assembly: Calibration Box Description: 2 ft. x 2 ft. box divided into four equal sections used to collect water during calibration. 20 Name: Calibration Box I-Plate Main Assembly: Calibration Box Description: By spacing the Iplate 0.25 in. from the back of the calibration box, two hose clamps can sufficiently hold the box to the calibration stand. Name: Calibration Box Hose System Main Assembly: Calibration Box Description: To get the water from the calibration box to the graduated containers, the hose system consists of microsprinkler tubing and spigots. 21 APPENDIX B: JUSTIFICATION OF FINAL DESIGN To validate the usability and integrity of our final design, the following tests, calculations, and analyses were completed. Spray Rack Deflection during a Water Penetration Test Given: The water penetration testing device consists of a grid of nozzles. The nozzles are placed in specific locations in order to meet the requirements of flow rate and coverage area stated in the ASTM E 1105 standard. The rack is composed of one vertical ¾ in. copper pipe connected to three horizontal ¾ in. copper pipes that house the nozzles. The copper pipe’s outer radius is 0.4375 in. with a thickness of 0.065 in. In addition to the piping there are two 4.5 ft. aluminum members supporting each side of the rack with cross sectional dimensions of 0.25 x 1.5 inch. The rack is suspended from two mounts symmetrically located on the top horizontal member of the rack, each spaced 1.5 ft. from the vertical centerline. The copper pipes, when filled with water carry a distributed force of 0.11 lb/in, while the aluminum support members carry a distributed force of 0.0375 lb/in. Suspension Location Copper Pipe Nozzle Vertical Support 22 Find: Given the loads impressed upon the spray rack, is the deformation in the spray rack substantial enough to change the nozzle placement and alter the geometry of the rack enough to undo the calibration specs? Solution: A simplified model using ABAQUS software was used in order to solve the problem with finite element methods. Rack was sketched and profiles implemented based on given information about cross sections of the pipe and aluminum members. The boundary conditions can be seen in the image above. There was no translation at the hanging points of the rack. Displacement was allowed at every other location of the model. The copper pipes that channel the water had a downward load of 0.11 lb/in and the aluminum members had applied forces of 0.0375 lb/in. 23 Results: The image above shows the solution to the ABAQUS spray rack model. The displacement of the rack varies from 0.003 to 0.03 inch. The greatest displacement occurs where the suspension is made. The displacement at these points is approximately 0.03 inch which is negligible compared to the overall dimensions of the spray rack. This small amount of deflection will have no affect on the functionality of the rack during a water penetration test. Shear Strength of Copper Tubing Given: During a water penetration test, the rack is suspended by the hanging mounts. The entire weight of the rack is 35 lbs when water is added to the system. The 0.5 inch thick hanging mounts are attached to ¾ inch copper pipe which has shear strength of 42 MPa (6100 psi). Find: Will the copper piping fail in shear due to the weight of the entire rack during a water penetration test? Solution: The hanging mounts are located symmetrically along the top horizontal spray pipe, and split the weight of the rack during a test. When suspended, therefore, the force applied to the pipe at the location of each hanging mount is half of the rack’s weight. Wt = 35 lbs FA = FB = Wt/2 = 17.5 lbs The equation to calculate shear stress is: τ = F/A 24 The necessary information to calculate the area of the applied shear stress is the width of each mount and the diameter of the copper pipe: Hanging mount width = W = 0.5 in. Copper pipe diameter = D = 0.875 in. Area of applied force = W x D = 0.5 x 0.875 = 0.4375 in 2 Shear stress can then be calculated by employing the shear stress equation from above: τ = 17.5 lb / 0.4375 in2 = 40 psi Results: The shear stress developed where the hanging mounts are fastened to the copper piping is 40 psi. The shear strength of the copper is 6100 psi which is much higher than the stress impinging on the pipe at the hanging mounts. Shear stress developed by the hanging mounts during a test, therefore, will not exceed the rack’s material constraints. Stress Analysis of Hanging Mounts Given: A ¾ inch diameter copper pipe spray rack with a weight of 35 lbs (weight includes water, hardware, vertical supports, and valves). The pipe has a thickness of 0.065 inch. Mounts are fastened on the top pipe of the rack, spaced 3 ft. apart uniformly from the vertical line of symmetry. The material of the hanging mounts is T6061-T6 aluminum with a thickness of 0.5 inch. The dimensions for the profile of the mounts are listed below. Find: Determine the Von Mises stress in the hanging mount, and determine the factor of safety. Solution: C3D8I: An 8-node linear brick, incompatible mode elements. Using a finite element software package such as ABAQUS, the analysis can be performed to determine the static stress on the hanging mount. Taking advantage of symmetry, the computation time was reduced and it allows for a more refined mesh for the same number of elements. 25 Loading ConditionsTotal Rack Weight / 2 mounts = weight per mount = 35 lbf/2 = 17.5 lbf Surface area of inside surface of hanging mount where the carabiner will be hooked = 0.07 in2 Pressure load 17.5 lbf / 0.07 in2 = 250 psi Boundary Conditions: Fixed Support (clamped section of mount to copper) no x, y, z translation or rotation. Symmetry about y plane (y-displacement = 0, rotations about x and z = 0) (1/2 thickness = 0.25 inch). Symmetry about the x plane, half width (x-displacement = 0, rotations about y and z = 0). The model was setup with a hex sweep mesh of 2048 3D stress shell elements. The area of maximum stress is just above the fillet on the left and right side of the triangle cutout. The Von Mises stress and displacement magnitude are as follows: 26 Results: For the static loading analysis there is a large factor of safety, because the mounts were designed to withstand an impact load. The ABAQUS stress analysis shows a maximum Von Mises stress magnitude of 0.45 ksi with a factor of safety of 29 and a maximum displacement magnitude of 4.489e-5 inches. These mounts are designed to be able to withstand the stresses applied by the total weight of the rack, water, hardware, and vertical supporting mounts under a static load. Spray Nozzle Selection Given: The spray rack system uses full cone nozzles that spray at 120˚. The nozzle supplier offers many different sizes of orifice for this type of nozzle which operate efficiently at different pressures. The nozzles of the spray rack are positioned along the grid as shown in the illustration below. The spray system impinges onto a surface 12 inches away from the nozzles. 27 The surface needs to be sprayed at a flow rate of at least 5 gal/hr-ft2 (0.0833 gal/min-ft2), as outlined in the ASTM standard. The diameter of the spray coverage at the test specimen is equal to 3.46 feet. The figure is to scale. The box represents 90% of the actual spray area covered by the nozzles. Find: What is the minimum flow rate required out of each nozzle in order to meet the flow requirement impinged on the box shown in the figure. Use this information to choose the most appropriate spray nozzle selection for the rack. Solution: Area of spray coverage = A = length*height = 6.75*6 = 40.5 ft2. Total flow rate for this coverage area = 5 gal/hr-ft2 * A = 202.5 gal/hr (3.375 gal/min) With the total flow rate necessary to meet the constraints in the ASTM standard, the amount of water exiting each nozzle can be calculated by: Total flow Rate / # of nozzles (3.375 gal/min)/12 nozzles = 0.281 gal/min-nozzle Because the area of the box is smaller than area covered by nozzles, the flow rate must be adjusted so that it sprays the entire spray area at the minimum required rate; assume a 90 % adjustment factor. Required flow rate from each nozzle at 25 psi = (Flow rate/nozzle) / 0.90 (0.281 gal/min)/0.90 = 0.313gal/min. 28 Conclusion: An acceptable flow rate for each nozzle is approximately 0.31 gal/min. Based on the supplier’s selection of nozzles, for an inlet pressure of 25 psi and a required flow rate of 0.32 gal/min, the recommended nozzles are 1/8 inch pipe size with an orifice diameter of 0.05 inch. These nozzles can produce 0.3 gal/min at 20 psi and 0.5 gal/min at 40 psi, making them the most appropriate nozzles selection. Horizontal Pressure Differences in the Spray Rack Given: Uniformity of spray rates is required along the horizontal spray pipes of the rack as detailed in the ASTM standard. Junction and friction pressure losses that occur within the piping will affect the spray rates as the flow moves further from the inlet water supply. A test rack was made of a 6 ft. long, ¾ inch PVC pipe with drilled orifices simulating nozzle spray diameters. The inlet water pressure was 40 psi and produced a flow rate of 3.2 GPM. Find: Determine whether or not there is sufficient evidence of a difference in flow rates exiting the orifices along the horizontal spray pipe. Results: To test the differences in flow rates along the horizontal pipe, an experiment was devised to complete the task. Four equally spaced small orifices were drilled into the pipe 9 inches apart on each side of the horizontal center. A graduated container was used to gather water for 1 minute from each orifice. Two different trials of data were collected for each orifice. 29 After sufficient data was gathered for the smallest orifice size, the hole diameters were increased. The three orifice diameters tested were: 0.128 in., 0.161in., and 0.209 in. The results of this data are presented in the ANOVA test below. The following hypothesis and null hypothesis were developed to test the effects of pressure differences in the horizontal pipe: Ho = The flow rates from each hole are equal as the distance from the horizontal center is increased. HA = Flow rates are significantly different as the distance from the center is increased. α = 0.05 ANOVA: flowrateout versus holediameter, hole, trial Factor holediameter hole trial Type fixed fixed fixed Levels 3 4 2 Values 0.128, 0.161, 0.209 A, B, C, D 1, 2 Analysis of Variance for flowrateout Source holediameter hole trial holediameter*hole holediameter*trial hole*trial Error Total S = 0.00395360 DF 2 3 1 6 2 3 6 23 SS 0.00018567 0.00005326 0.00001603 0.00023994 0.00000744 0.00001842 0.00009379 0.00061455 R-Sq = 84.74% MS 0.00009283 0.00001775 0.00001603 0.00003999 0.00000372 0.00000614 0.00001563 F 5.94 1.14 1.03 2.56 0.24 0.39 P 0.038 0.407 0.350 0.139 0.795 0.763 R-Sq(adj) = 41.50% Boxplot of Flow Rate (gpm) Flow Rate (gpm) 0.4 0.3 0.2 0.1 0.0 Hole Location Hole Diameter (in) A B C 0.128 D A B C 0.161 D A B C 0.209 D 30 Conclusion: Multiple factors were tested, the most applicable being the hole vs. flow rate. Our hypothesis test was designed with a level of significance of 95%. The P-value for the tested factor was 0.407 which is much greater than 0.05. This result was similar for the other two orifice diameters tested. With this high P-value, we fail to reject the null hypothesis and it can be concluded that the difference in flow rates is insignificant as the orifice distance increases along the horizontal pipe. Through the results of this test, it was determined that there is no need for flow regulation along the horizontal spray pipes. Vertical Pressure Differences on the Spray Rack Given: A full sized test-spray rack was constructed out of PVC pipes with holes drilled in the same locations as the final design. Each of the orifices were drilled with a 0.209 in. diameter. Water was introduced into the system from a standard garden hose tap with 40 psi of water pressure available. The configuration and dimensions of the testspray rack can be seen in the illustration. When water was spraying from each of the orifices, the spray streams reached the locations detailed in the figure. Find: For the differences in elevation between the top, middle, and bottom horizontal spray pipes, find the internal pressure of the water behind each spray orifice. Solution: Variables used in the following calculations: t = time (s) h = vertical height (m) g = gravitational constant v = velocity (m/sec) d = distance (m) The time required for the water to fall the vertical distance is equal to: t = ((2*h)/g)1/2 t = ((2*0.61 m)/9.81 m/sec2)1/2 = 0.35 sec The velocity at the orifice exit is equal to 31 V2 = d/t V2 = 2.49m/0.35 sec = 7.06 m/sec Using the Bernoulli equation, we can evaluate the pressure at points just before the orifice. 𝑃1 𝑉12 𝑃2 𝑉22 𝑧1 + + = 𝑧2 + + 𝜌𝑔 2𝑔 𝜌𝑔 2𝑔 Assumptions that can be made: z 1 = z 2, V1 = 0, P2 = 0 With these assumptions the Bernoulli equation reduces to: 𝑉22 𝜌 𝑃1 = 2 To calculate the pressure before the orifice at the lowest horizontal spray pipe (elevation = 2 ft.) the following example calculation is made: P1 = ρv22/2 P1 = [(1000 kg/m3)*(7.06 m/sec)2]/2 = 24943.81 pascals By converting pascals to psi we get: 24943.81 pascals*0.00014503774 psi/pascal = 3.62 psi The equation used above to calculate the pressure just before exiting the orifices at an elevation of 2 ft was used to calculate the pressures for elevations of 4 and 6 ft. These results can be found in the table below. h = starting height (ft) 6 4 2 x= t = time to distance velocity hit ground traveled (m/s) (s) (m) 1.83 2.3 0.61 3.77 1.22 2.45 0.50 4.91 0.61 2.49 0.35 7.06 h = starting height (m) pressure in pipe at orifice (pascals) Pressure in pipe at orifice (psi) 7094.12 12074.42 24943.81 1.03 1.75 3.62 Results: The pressure behind the orifices at the three different elevations are as follows: at a height of 6 ft. the pressure was 1.03 psi, at a height of 4 ft. the pressure increased to 1.75 psi, and at 2 ft. above the ground the pressure was 3.62 psi. The pressure in the bottom horizontal spray pipe is approximately 3 times greater than the top spray pipe. This amount of inconsistency requires throttling at the different elevations of the spray rack to achieve uniformity of pressures within the system. To solve this problem, the final design uses two 32 throttling valves along the vertical supply pipe in order to eliminate pressure differences among elevation changes. Calibration Test Data Required: The ASTM E1105-00 standard requires that three specific areas of the spray rack are calibrated to ensure proper water coverage. These areas include both upper corners and the quarter point of the horizontal center line. Calibration entails that the water gathered from the calibration box exceeds 1.26 L/min total for the four areas, and is between 0.25 to 0.63 L/min for any one section of the calibration box. Procedure: To accurately calibrate the spray rack, the calibration box was positioned to the correct location and spaced 12 in. from the rack. Water was applied to the system via a standard garden hose tap. The flow was throttled at the inlet to three different pressures: 20, 25 and 30 psi. When water began filling the graduated containers, a stop watch was started. The spray rack was turned off after 2 minutes of water impinging upon the calibration box. The water collected in each graduated container was recorded and divided by 2 to obtain the appropriate L/min measurement. After testing each of the three inlet pressures at all of the three calibration locations the data was organized and can be found below. Results: For an inlet pressure of 20 psi the lowest flow rate was in the upper right corner of the rack and was 0.15 L/min, which is below the requirements of the standard. This inlet pressure does not meet the minimum flow rate of the total four calibration box areas (1.26 L/min) either. The spray rack does not meet ASTM standards at an inlet pressure of 20 psi, when spaced 12 in. away from a test specimen. Calibration data for an inlet pressure of 20 psi. Captured Water in (L/min) Calibration Box Section Calibration Location Upper Right Upper Left Quarter Point Total I 0.34 0.19 0.28 II 0.44 0.39 0.31 III 0.27 0.39 0.41 IV 0.15 0.31 0.44 1.19 1.28 1.44 33 When the inlet pressure was increased to 25 psi the acquired flow rates improved greatly. Each individual section gathered enough water, and the minimum flow rate for the total of all areas met the ASTM standard. At an internal pressure of 25 psi and 12 in. away, the spray rack system meets the flow rate requirements. Calibration data for an inlet pressure of 25 psi. Captured Water in (L/min) Calibration Box Section Calibration Location Upper Right Upper Left Quarter Point Total I 0.44 0.25 0.31 II 0.49 0.43 0.36 III 0.35 0.43 0.45 IV 0.25 0.37 0.48 1.52 1.48 1.59 At an internal pressure of 30 psi all of the flow rates stayed within the tolerances of the ASTM standard. Each individual area and the total of the areas met all the requirements. It can be concluded that at 30 psi and 12 in. of separation between the nozzles and the test specimen the spray rack meets all of the constraints to conduct a water penetration test set forth by the ASTM E 1105-00 standard. Calibration data for an inlet pressure of 30 psi. Captured Water in (L/min) Calibration Box Section Calibration Location Upper Right Upper Left Quarter Point Total I 0.43 0.26 0.32 II 0.50 0.44 0.38 III 0.39 0.44 0.50 IV 0.27 0.40 0.50 1.58 1.54 1.70 34 APPENDIX C: OPERATION MANUALS Overview In order to complete a successful water penetration test to conform to ASTM standards, the spray rack must be calibrated. At a test site, the rack must be assembled and set up at the same settings used to calibrate the rack. The following instructions describe the necessary procedures to assemble and calibrate the spray rack in order to complete a successful water penetration test. Spray Rack Assembly and Testing Take all of the parts of the spray rack and lay them on the ground. Set the three horizontal spray pipes in the general area that they will be connected to the vertical supply pipe (i.e. set them 2.25 ft. apart vertically). With the nozzles facing the ground, connect the quick release copper couplings of the vertical pipe to the horizontal pipe inlets. Maintain the form of the spray rack by placing it gently with the nozzles on the ground. Fasten the aluminum vertical supports toward the outside of the rack configuration, making sure that the top of the vertical supports (labeled in red) are located at the top of the rack. Install the water supply (garden hose) to the inlet of the rack, making sure that the connection is tight to eliminate pressure losses due to leaks. Remove the rack from the ground and set it upright, resting on the bottom of the vertical supports. Align the window spacers in their respective locations: two on the top horizontal pipe, and one ¾ down the vertical pipe. Set the telescoping tubing at the required distance to achieve 12 inches of space between the nozzles and the test specimen. For specimens that are above the first floor of the building use ropes to suspend the rack to the correct elevation. For specimens on the first floor of the building, acquire the spray rack stand. Determine the necessary height elevation needed, and set the stand at that height. Connect the 35 carabiners of the stand to the hanging mounts and raise the rack to the appropriate height. When the spray rack is located in the correct location, adjust the inlet throttling valve until the pressure gauge on the rack reads the necessary pressure determined during calibration to meet the required flow rates, begin the test. Calibration of the Spray Rack System With the spray rack assembled via the instructions above, use the spray rack stand to hold the rack in place at ground level. Position the calibration box vertically along the calibration stand by loosening the hose clamps and sliding to the appropriate location. Follow this procedure for the graduate container rack so that it is fastened just below the calibration box. Place each of the calibration box hoses into the individual graduated containers by using the Velcro tape. Move the calibration stand and assembly to the calibration locations outline in the ASTM standard. Open the inlet throttling valve and allow water to impinge upon the calibration box. When water begins filling the graduated containers begin timing the process. After adequate water has been gathered in each container stop the timer, and turn off the rack. Let the water drain from the box sections before making measurements. Record the amount of water collected in each container and divide it by the time it took to fill them, this method will result in obtaining a L/min measurement for each section of the calibration box. Validate that the flow rates from each section, and the total of all sections of the calibration box, fall within the required flow rates as outline in the ASTM standard. Record the inlet pressure that the measurements were made, this is the pressure that must be used when a water penetration test is carried out on a job site. 36 APPENDIX D: PRODUCT DATA SPECIFICATIONS TABLE MH = Morrison Hershfield □□ Medium □□□ High Customer Metric Target Target Basis Verification Notes Reliability MH cycles ≥ 1000 cost effective testing 3 tests/week Portability to site MH vehicle size required to transport easier/more cost effective to transport end user feedback □□□ Portability to test subject MH lbs/outer dimensions small pickup truck average person can carry efficiency end user feedback □□□ □□ Ease of Operation MH - - - end user feedback Weight (heaviest component) MH lbs < 50 portability/ fatigue end user feedback □□ Service Life MH years ≥5 MH testing □□ Durability MH shock loading 10G SELF Abaqus Environment easy to operate consistently with minimal training Priority Water MH surface treatment corrosion resistant SELF end user feedback Operation Temperature MH degrees °F 35-105 SELF testing □□ Suspension forces SELF 10G consistent operation end user feedback □□ Safety Performance Requirements □ Low Frame Integrity MH 10G SELF Abaqus □□□ Handling MH - - - □□□ factor of safety factor of safety - □□□ withstand industrial stresses, impact, □□□ handling, transport □ 37 MH = Morrison Hershfield Documentation Maintenance Company Codes and Materials Constraints Standards Installation Requirements □ Low □□ Medium □□□ High Customer Metric Target Target Basis Verification Notes Setup Complexity MH setup time (in hrs) < 5 min MH/SELF end user feedback setup should be intuitive Manpower required (ground floor setup) MH # people 1 MH/SELF end user feedback □□□ Manpower required (above ground setup) MH # people 2 MH/SELF end user feedback □□□ Frame SELF USD < 550 SELF yes/no corrosion resistant □□ Other SELF USD < 450 SELF yes/no corrosion resistant □□ MH/SELF gallons ft2*hour >5 ASTM requirement testing SELF USD < $1500 MH yes/no MH/SELF in2 14400 test area testing Serviceable in field MH yes/no yes SELF end user feedback □□ Replaceable components MH yes/no yes SELF end user feedback □□ MH/SELF difficulty easy SELF end user feedback □□ PDS self deadline 2/8/2010 PSU documentation □□ Progress Report self deadline 3/8/2010 PSU documentation □□ Final Report self deadline 5/31/2010 PSU documentation □□□ Timeline self deadline PSU documentation □□ ASTM E1105-00 Budget Coverage Area Repair complexity Priority □□ □□□ needs to be approved □□ □□□ 38 APPENDIX E: HOUSE OF QUALITY TABLE Criteria Customer Weight Design MH/user user user MH/user MH/user □□□ □□ □ □ □ □ □□□ □ □ □□□□□ □□□□□ □□□□ □□□□□ □□□□□ □□□□□ □ □ □ □□□□□ □ □□□ □□ □□□ □□□ □ Portability (to specimen) 10 6 6 7 9 9 MH/user □ □□□□□ □□□□ □□□□□ □□ Maintenance (unrestricted) 3 MH □□ □ □□□ □ □□□□□ Maintenance (field) 5 user □□ □ □□□ □ □□□□□ Service Life 2 MH □□ □ □□□ □ □□□□□ Customer Requirements Performance Ease of Installation Ease of Operation Portability (to site) Manpower Required 10 = high Cost Importance Outer Dimensions Components Engineering MH = Morrison Hershfield Low/Negligible □ High/Critical □□□□□ 39 APPENDIX F: PART DRAWINGS 40 41 42 43 44 45 46 47 48 APPENDIX G: BILL OF MATERIALS VENDOR PURCHASER 3/4 x 10 pvc $0.98 3 $2.94 HD Andy 3/7/2010 Test app Dauber $1.31 2 $2.62 HD Andy 3/7/2010 Test app primer $4.58 1 $4.58 HD Andy 3/7/2010 Test app cement pvc $3.76 1 $3.76 HD Andy 3/7/2010 Test app 3/4 cap pvc $0.35 6 $2.10 HD Andy 3/7/2010 Test app 3/4 elbow pvc $0.69 1 $0.69 HD Andy 3/7/2010 Test app 3/4 cross pvc $1.70 2 $3.40 HD Andy 3/7/2010 Test app 3/4 tee pvc $0.33 2 $0.66 HD Andy 3/7/2010 Test app 3/4 m adapter $0.33 1 $0.33 HD Andy 3/7/2010 Test app sprink HD $9.89 1 $9.89 HD Andy 3/10/2010 Test app 3/4x10 pvc $0.98 1 $0.98 HD Andy 3/10/2010 Test app 3/4 f adapt pvc $0.44 1 $0.44 HD Andy 3/10/2010 Test app 1/2 elbow pvc $0.90 1 $0.90 HD Andy 3/10/2010 Test app 1/2 elbow (type 2) pvc $0.69 1 $0.69 HD Andy 3/10/2010 Test app 3/4 busing pvc $0.38 2 $0.76 HD Andy 3/10/2010 Test app 3/4 'M' adapter pvc $0.33 1 $0.33 HD Andy 3/10/2010 Test app 1/2x260 teflon tape $0.98 1 $0.98 HD Andy 3/10/2010 Test app 1/2x24 pvc $0.79 1 $0.79 HD Andy 3/10/2010 Test app 1/2 M adapter $0.32 1 $0.32 HD Andy 4/1/2010 Test app 3/4 cap pvc $0.35 3 $1.05 HD Andy 4/1/2010 Test app 3/4 tee sss $0.33 1 $0.33 HD Andy 4/1/2010 Test app 3/4 cross pvc $1.70 1 $1.70 HD Andy 5/8/2010 Rain rack Pipe Bushing 3/4-1/2" $2.37 12 $28.44 HD Andy PART TOTAL PURCHASE TOTAL Test app Application 3/7/2010 DATE # MS = Metal Supermarkets AH = Ace Hardware PRICE HD = Home Depot $30.97 $6.19 $3.08 $28.44 49 5/10/2010 5/10/2010 Rain Rack Rain Rack Copper Tube 3/4" Copper Fem Adpt $15.53 $5.81 3 12 $46.59 $69.72 HD HD Andrew Andrew 5/10/2010 Rain Rack 3/4 Copper Tee $2.39 18 $43.02 HD Andrew 5/10/2010 Rain Rack 3/4 Copper Cap $1.11 6 $6.66 HD Andrew 5/10/2010 Rain Rack 8oz flux $6.43 1 $6.43 HD Andrew 5/10/2010 Rain Rack Copper Female adpt $3.54 1 $3.54 HD Andrew 5/10/2010 Rain Rack Pipe Cutter $10.26 1 $10.26 HD Andrew 5/10/2010 Rain Rack 3/4" valve $9.87 3 $29.61 HD Andrew 5/10/2010 Rain Rack Shark Bit Clip $1.54 2 $3.08 HD Andrew 5/10/2010 Rain Rack Shark Bite joint $6.92 3 $20.76 HD Andrew 5/10/2010 Rain Rack 1/2 lb solder $13.81 1 $13.81 HD Andrew 5/10/2010 Rain Rack Interior brush $1.95 1 $1.95 HD Andrew 5/10/2010 Rain Rack Exterior Brush $3.46 1 $3.46 HD Andrew 5/10/2010 Rain Rack Copper male Adapter $2.11 1 $2.11 HD Andrew 5/10/2010 Rain Rack 3/4 Copper elbow $1.31 3 $3.93 HD Andrew 5/10/2010 5/10/2010 Misc Misc Arch Aluminum Tube (6063) square 1x1x12, 1/16" Arch Aluminum Tube (6063) square (3/4)x(3/4)x12, 1/8" $2.37 $2.56 1 1 $2.37 $2.56 McMaster McMaster Andy Andy 5/10/2010 Misc Arch Aluminum Tube (6063) square (3/4)x(3/4)x36, 1/8" $6.23 1 $6.23 McMaster Andy 5/10/2010 Misc Arch Aluminum Tube (6063) square 1x1x3', 1/16" $5.29 1 $5.29 McMaster Andy 5/10/2010 Misc Release pin W/lanyard, 3/16", 1.3" Usable length $3.92 3 $11.76 McMaster Andy 5/10/2010 Misc Brass Spray Nozzle, 3/8" NPT Male, 2gpm@40psi, 120 deg $10.19 12 $122.28 McMaster Andy 5/12/2010 Rain rack Butane $5.99 1 $5.99 4th Store Andy 5/17/2010 Calibration Box Aluminum Sheet (6061) 3x4' $68.36 1 $68.36 MS Andrew 5/17/2010 Misc. Aluminum Plate (6061) 1x2' $44.86 1 $44.86 MS Andrew 5/17/2010 Calibration Box Aluminum Square Tube (6061) 1.5x1.5x72 $26.36 2 $52.72 MS Andrew 5/17/2010 Misc Aluminum flat (6061) .1875x.75x72 $4.00 4 $15.98 MS Andrew 5/17/2010 Rain Rack Aluminum Tube Round (6061) .75x48, 0.049" $13.78 1 $13.78 MS Andrew 5/17/2010 Rain Rack Aluminum Tube Round (6061) .625x48, 0.058 $19.29 1 $19.29 MS Andrew 5/17/2010 Misc. Aluminum Plate (6061) 1x1', 0.5" $43.50 1 $43.50 MS Andrew 5/18/2010 5/18/2010 Calibration Box Calibration Box 1/4 Barb 3/4 cop cplg $1.48 $0.87 1 2 $1.48 $1.74 HD HD Andrew Andrew $264.93 $28.21 $5.99 $258.49 $20.94 50 5/18/2010 5/18/2010 5/18/2010 5/18/2010 5/18/2010 Calibration Box Rain Rack Rain Rack Calibration Box Calibration Box Microtube 15" velcro 23' velcro swivel cop male adp $4.07 $3.96 $3.46 $4.12 $2.11 1 1 1 1 1 $4.07 $3.96 $3.46 $4.12 $2.11 HD HD HD HD HD Andrew Andrew Andrew Andrew Andrew This box tabulated on previous page 5/19/2010 Calibration Box Graduated Pitcher $8.75 4 $35.00 Scientific Andrew $35.00 5/21/2010 Rain Rack Brass Nozzle, 1/8" NPT Male, 0.5 GPM @40 PSI, 120Deg $7.52 12 $90.24 McMaster Andy 5/21/2010 Rain Rack Brass Hex Reducing Bushing 3/8" Male X 1/8" Fem $1.00 16 $16.00 McMaster Andy 5/21/2010 Rain Rack Brass Nozzle, 1/4" NPT Male, 1 GPM @40PSI, 120Deg $8.02 12 $96.24 McMaster Andy 5/21/2010 Rain Rack Brass Nozzle, 1/8" NPT Male, 0.7 GPM @40 PSI, 120Deg $7.52 12 $90.24 McMaster Andy 5/21/2010 Rain Rack Brass Hex Reducing Bushing 3/8" Male X 1/4" Fem $1.49 16 $23.84 McMaster Andy 5/24/2010 Calibration Box JB Weld $19.47 1 $19.47 AH Luke 5/25/2010 Rack Stand Aluminum Pipe (6061) 1.25x72" $27.17 1 $27.17 MS Andy 5/25/2010 Rack Stand Aluminum Tube (6061) 1.25"x108", .125" thickness $37.16 1 $37.16 MS Andy 5/26/2010 Calibration Box Combo Pack $1.41 1 $1.41 HD Andrew 5/26/2010 Calibration Box Plastic Baggds $0.98 1 $0.98 HD Andrew 5/26/2010 Rain rack 1/4x2" lag screw $0.46 1 $0.46 HD Andrew 5/26/2010 Rain rack 1/4x2x1/2" H bolt $0.76 1 $0.76 HD Andrew 5/27/2010 Calibration Box Rubber washer (4) 1/4" $0.83 2 $1.66 HD Andy 5/27/2010 Misc Shipping parts back $9.70 1 $9.70 USPS Andy 5/27/2010 Rain Rack Leg Tip, black rubber, 1" $0.69 6 $4.14 AH Andy 5/27/2010 Rain Rack Aluminum bulk (used for supports) $6.50 6 $39.00 AH Andy 5/27/2010 Rack Stand Eye Bolt $7.49 2 $14.98 AH Andy 5/27/2010 Rack Stand 16 gauge 11/2 dia squar tubing pl $0.69 3 $2.07 AH Andy 5/27/2010 Calibration Box Hose Clamp $4.79 2 $9.58 AH Andy 5/27/2010 Rack Stand 2 1/2" snapper $4.19 2 $8.38 AH Andy 5/27/2010 Rack Stand Spring Snap link $4.99 2 $9.98 AH Andy 5/27/2010 Rack Stand 1x8 glv nipple $3.79 1 $3.79 AH Andy 5/27/2010 Rack Stand 1" Galv Tee $4.19 1 $4.19 AH Andy 5/27/2010 Rack Stand nuts and washers $1.53 2 $3.06 AH Andy 5/27/2010 Rack Stand nuts and washers $2.19 2 $4.38 AH Andy $106.24 $19.47 $64.33 $3.61 $1.66 $9.70 $117.85 51 5/27/2010 5/30/2010 Rack Stand Calibration Box Large Hex Bolt Stopwatch $7.15 $7.99 2 1 $14.30 $7.99 AH Fred Meyer Andy Andrew 5/30/2010 Calibration Box Auto Epoxy $4.29 1 $4.29 Fred Meyer Andrew 5/30/2010 Calibration Box Caster wheels $4.49 1 $4.49 HD Andy 5/30/2010 Rain rack Water Gage $10.68 1 $10.68 HD Andy 5/30/2010 Calibration Box blk 5/8" leg tips $1.69 1 $1.69 AH Andy 5/30/2010 Calibration Box Tip Leg vynl blk 1/2" $1.49 1 $1.49 AH Andy 5/30/2010 Calibration Box Round pad 1.5" $3.29 1 $3.29 AH Andy 5/30/2010 Rain rack 16 gage 11/4 dia squar tubing $0.99 4 $3.96 AH Andy 5/30/2010 Rain rack Wet/dry 9x11 150 grit sandpaper $0.99 3 $2.97 AH Andy 5/30/2010 Rain rack Standard 9x11 150 grit sandpaper $1.69 2 $3.38 AH Andy 5/30/2010 Rain rack Spray paint gray primer $6.99 2 $13.98 AH Andy 5/30/2010 Rain rack Spray paint olive $4.79 2 $9.58 AH Andy 5/30/2010 Rain rack Spray paint smoke gray $4.49 2 $8.98 AH Andy 6/1/2010 School Capstone Poster $65.25 1 $65.25 Kinko's Andy 6/1/2010 Calibration Box Scrap glass (acrylic) $4.00 1 $4.00 AH Andy 6/1/2010 Rain Rack Metric Fasteners $0.38 6 $2.28 AH Andy 6/1/2010 Calibration Box 11 gage 11/2 dia square tubing plug $0.79 4 $3.16 AH Andy 6/1/2010 Calibration Box Velcro strip 18" black $3.99 1 $3.99 AH Andy 6/1/2010 Rain Rack Lacquer Gloss $6.49 2 $12.98 AH Andy $12.28 15.17 $49.32 $65.25 $26.41 Grand Total $1173.53 Purchaser Andrew $595.25 Andy $558.81 Luke $19.47 Returned for credit, not included in price 52 APPENDIX H: ASTM E1105-00 STANDARDS 53 54 55 56 57