01 35 18 - LEED Requirements

advertisement
Section Cover Page
Section 01 35 18
LEED Requirements
2014-10-01
Include this Section for new building and major renovations unless the work of the Contract:
.1
is excluded by the Department’s policy on LEED, or
.2
the Department has determined that the work of this Contract is not to attain a LEED rating.
Use this Section to specify those LEED (Leadership in Energy and Environmental Design)
requirements and procedures that are required by the Canada Green Building Council (CaGBC) for the
attainment of prerequisites and credits for LEED Canada-NC certification. Silver rating is typical, but
confirm requirements with project manager.
The primary purpose of this Section is to assist in the timely and accurate collection of information
required for the certification level of CaGBC LEED-NC.
Canada Green Building Council's (CaGBC) LEED rating systems allocates points by meeting specific
performance criteria set out in Prerequisites and Credits.
Review CaGBC LEED Rating System: LEED Canada for New Construction and Major Renovations
2009. LEED Canada for Core and Shell Development 2009.
Note that all LEED credits are optional except prerequisites, so requirements for credits not sought
should be deleted.
This Master Specification Section contains:
.1
.2
.3
This Cover Page
Data Sheet – Editing Instructions
Specification Section Text
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
1.10
Related Requirements
Reference Documents
Definitions
LEED Administration Requirements
Project Coordination
Project Meetings
Construction Schedules
Quality Assurance
Submittals
LEED Submittal Forms
2.1
2.2
2.3
2.4
2.5
Salvaged and Refurbished Materials
Recycled Content of Materials
Regional Materials
Certified Wood
Low-Emitting Materials
3.1
3.2
3.3
3.4
Site Disturbance
Refrigerants and Clean-Agent Fire Extinguisher Agents Removal
Construction Waste Management
Construction Indoor Air Quality Management
BMS Basic Master Specification
Infrastructure
Master Specification System
Page 0
Data Sheet – Editing Instructions
2014-10-01
Section 01 35 18
LEED Requirements
Headings are included for convenience only, to provide a standard structure and framework for the
identification of requirements.
Headings should be added if requirements noted in the CaGBC LEED Canada reference guides
identify additional options beneficial to the project.
END OF DATA SHEET
BMS Basic Master Specification
Infrastructure
Master Specification System
Page 01
Section 01 35 18
LEED Requirements
Page 1
Plan No:
Project ID:
SPEC NOTE DESCRIPTION: This Section specifies requirements and procedures defined by
Canada Green Building Council's (CaGBC) LEED prerequisites and credits required for LEED,
Certified, Silver, Gold, or Platinum Project certification.
1.
General
1.1
RELATED REQUIREMENTS
SPEC NOTE: List to only those sections containing specific information that would directly affect
the work of this section.
.1
.2
.3
.4
.5
.6
.7
1.2
Project Coordination
Project Meetings
Construction Schedules
Submittal Procedures
Environmental Procedures
Quality Control
Waste Management and Disposal
Section 01 31 13
Section 01 31 19
Section 01 32 16
Section 01 33 00
Section 01 35 20
Section 01 45 00
Section 01 74 19
REFERENCE DOCUMENTS
.1
American Society of Heating Refrigeration and Air-Conditioning (ASHRAE):
Website: www.ashrae.org:
.1
.2
.5
LEED Canada for New Construction and Major
Renovations. LEED Canada for Core and Shell
Development.
CRI Green Label Indoor Air Quality Test Program - Green Label Testing Program
Green Seal Environmental Standards, Website: www.greenseal.org:
.1
Standard GC-03-97
Anti-Corrosive Paints
.2
Standard GS-11-93
Architectural Paints
Sheet Metal and Air Conditioning Contractors National Association (SMACNA):
Website: www.aqmd.gov
.1
2014-10-01 BMS Version
LEED Canada 2009
Rating System
Carpet and Rug Institute (CRI):
Website: www.carpet-rug.org
.1
.4
Method of Testing General Ventilation Air-Cleaning
Devices for Removal Efficiency by Particle Size (ANSI
approved)
Canada Green Building Council (CaGBC):
Website: www.cagbc.org
.1
.3
ASHRAE 52.2-99
IAQ Guideline for Occupied Buildings Under Construction, Chapter 3, 1995
Section 01 35 18
LEED Requirements
Page 2
Plan No:
Project ID:
.6
.7
SCAQMD South Coast Air Quality Management District, California State (SCAQMD):
Website: www.aqmd.gov
.1
SCAQMD Rule 1113- Architectural Coatings
1996
.2
SCAQMD Rule 1168- Adhesives and Sealants Applications.
05
United States Federal Trade Commission (US Federal Trade Commission):
Website: www.ftc.gov
.1
.8
Trade Commission Guidelines for the Use of
Environmental Marketing Claims
Forest Stewardship Council:
Website: www.ftc.gov
.1
1.3
16 CFR 260.7
Principles and Criteria for Forest Stewardship
DEFINITIONS
.1
Definitions as written below are supplementary to all laws, statutes, and regulations
effective in Alberta. Where definitions conflict, laws, statutes, and regulations take
precedent over the definitions below.
.2
CFC: Chlorofluorocarbon. CFC’s are halogenated substances that have a significant
impact on the Earth’s atmosphere as they are ozone depleting and contribute to global
warming.
.3
Chain-of-Custody Certification - certificates signed by manufacturers certifying that
wood used to make products was obtained from FSC certified forests. Certificates include
evidence that mill is certified for chain-of-custody by FSC-accredited certification body.
.4
Carbon Dioxide Monitoring: A method for determining indoor air quality by using the
concentration of carbon dioxide as an indicator. Although the level of CO2 is a good
general indicator of air quality, it is reliant on the presence of certain conditions and must
be applied accordingly.
.5
Commissioning (Building): The process of ensuring installed systems function as
specified, performed by a third party Commissioning Authority. Elements to be
commissioned are identified, installation is observed, sampling is conducted, test
procedures are devised and executed, staff training is verified, and operations and
maintenance manuals are reviewed.
.6
Construction and Demolition Waste: Waste building materials, dredging materials,
treestumps, and rubble resulting from construction, remodeling, repair, and demolition of
homes, commercial buildings and other structures and pavements. May contain lead,
asbestos, or other hazardous substances.
2014-10-01 BMS Version
Plan No:
Project ID:
Section 01 35 18
LEED Requirements
Page 3
.7
Construction Indoor Air Quality Management Plan: A systematic plan for addressing
construction practices that can impact air quality during construction and continuing on to
occupation.
.8
Construction Site Recycling: See Construction Waste Management
.9
Construction Waste Management: General term for strategies employed during
construction and demolition to reduce the amount of waste and maximize reuse and
recycling. Construction waste management is a sustainable building strategy in that it
reduces the disposal of valuable resources, provides materials for reuse and recycling, and
can promote community industries.
.10
Energy Star: Program administered by the Environmental Protection Agency that
evaluates products based on energy efficiency.
.11
Fluorocarbons (FCs): Any of a number of organic compounds analogous to hydrocarbons
in which one or more hydrogen atoms are replaced by fluorine. Once used in the United
States as a propellant for domestic aerosols, they are now found mainly in coolants and
some industrial processes. FCs containing chlorine are called chlorofluorocarbons
(CFCs). They are believed to be modifying the ozone layer in the stratosphere, thereby
allowing more harmful solar radiation to reach the Earth's surface. 1
.12
Flush-Out: A period after finish work and prior to occupation that allows the building’s
materials to cure and release volatile compounds and other toxins. A building flush-out
procedure is normally followed, with specified time periods, ventilation rate, and other
criteria.
.13
Forest Stewardship Council (FSC): A third-party certification organization, evaluating the
sustainability of forest products. FSC-certified wood products have met specific criteria
in areas such as forest management, labor conditions, and fair trade.
.14
Global Warming: An increase in the near surface temperature of the earth. Global
warming has occurred in the distant past as the result of natural influences, but the term is
most often used to refer to the warming predicted to occur as a result of increased
emissions of greenhouse gases. Scientists generally agree that the earth's surface has
warmed by about 1 degree Fahrenheit in the past 140 years. The Intergovernmental Panel
on Climate Change (IPCC) recently concluded that increased concentrations of
greenhouse gases are causing an increase in the earth's surface temperature and that
increased concentrations of sulfate aerosols have led to relative cooling in some regions,
generally over and downwind of heavily industrialized areas.
.15
Green Label: A certification program by the Carpet and Rug Institute for carpet and
adhesives meeting specified criteria for release of volatile compounds.
.16
Halon: Bromine-containing compounds with long atmospheric lifetimes whose
breakdown in the stratosphere causes depletion of ozone. Halons are used in firefighting.
2014-10-01 BMS Version
Plan No:
Project ID:
Section 01 35 18
LEED Requirements
Page 4
.17
Heat Island Effect: A "dome" of elevated temperatures over an urban area caused by
structural and pavement heat fluxes, and pollutant emissions.
.18
HCFC - Hydrochlorofluorocarbon: HCFCs are generally less environmentally detrimental
to depletion of stratospheric ozone than CFCs (chlorofluorocarbons). HCFCs are
generally used to replace CFC’s where mandates require CFC’s to be eliminated. A total
ban on all CFC’s and HCFCs is scheduled, effective 2030.
.19
HVAC: Heating Ventilation and Air Conditioning to provide thermal comfort and
ventilation to building.
.20
Hydrocarbons (HC): Chemical compounds that consist entirely of carbon and hydrogen.
.21
Indoor Air Quality (IAQ): ASHRAE defines acceptable indoor air quality as air in which
there are no known contaminants at harmful concentrations as determined by cognizant
authorities and with which 80% or more people exposed do not express dissatisfaction.
.22
LEED: Leadership in Energy and Environmental Design. A voluntary, consensus-based,
standard, measurement system designed for rating new and existing buildings based on
accepted energy and environmental principles, striking a balance between knowledge,
established practices, and emerging concepts. A performance-oriented system where
points are earned for satisfying criterion in each of five categories: Sustainable Sites,
Water Efficiency, Energy & Atmosphere, Materials & Resources, and Indoor
Environmental Quality. LEED promotes integrated and sustainable design practices.
LEED® is a trademarked name.
.23
LEED Accredited Professional (LAP): A professional who has successfully passed the
LEED Accreditation exam and is knowledgeable in green building design practices.
.24
Low VOC: Building materials and finishes that exhibit low levels of "off gassing," the
process by which VOCs (Volatile Organic Compounds) are released from the material,
impacting health and comfort indoors and producing smog outdoors. Low (or zero) VOC
is an attribute to look for in an environmentally preferable building material or finish. See
"Volatile Organic Compound (VOC)" for more information.
.25
Organic Compound: Vast array of substances typically characterized as principally carbon
and hydrogen, but that may also contain oxygen, nitrogen and a variety of other elements
as structural building blocks.
.26
Ozone Depletion: Destruction of the earth's ozone layer, which can be caused by the
photolytic breakdown of certain chlorine- and/or bromine-containing compounds (e.g.,
chlorofluorocarbons), which catalytically decompose ozone molecules.
.27
Post-Consumer Recycling: Use of materials generated from residential and consumer
waste, raw material or feedstock, for new product or similar purposes; e.g. converting
wastepaper from offices into corrugated boxes or newsprint.
2014-10-01 BMS Version
Section 01 35 18
LEED Requirements
Page 5
Plan No:
Project ID:
.28
Post-Consumer Recycle Content: A product composition that contains some percentage
of material that has been reclaimed from the same or another end use at the end of its
former, useful life.
.29
Post-Industrial Material: Industrial manufacturing process scrap or waste; also called preconsumer material.
.30
Post-Industrial Recycle Content: A product composition that contains some percentage of
manufacturing waste material that has been reclaimed from a process generating the same
or a similar product. Also called pre-consumer recycle content.
.31
Pre-Consumer Materials/Waste: Materials generated in manufacturing and converting
processes such as manufacturing scrap and trimmings and cuttings. Includes print
overruns, over issue publications, and obsolete inventories.
.32
Rapidly Renewable Materials - materials made from agricultural products that are
typically harvested within a ten-year or shorter cycle. Rapidly renewable materials
include but are not limited to products made from bamboo, cotton, flax, jute, straw,
sunflower seed hulls, vegetable oils, and wool.
.33
Regionally Materials - materials that are extracted, harvested, recovered and processed
within a radius of 800 km from the final manufacturing site when transported by truck,
2400 km by boat or train and the final manufacturing site is within 800 km of the Project
site, 2400 km if shipped by rail or water. Manufacturing refers to the final assembly of
components into the building product that is installed at project site.
SPEC NOTE: The following paragraphs are from the US Federal Trade Commission 16 CFR 260.7
(e), guidelines for the use of Environmental Marketing Claims.
.34
.35
Recycled Content - percentage by weight of constituents that have been recovered or
otherwise diverted from solid waste stream, either pre-consumer or post-consumer.
.1
Wastes and scraps from manufacturing process that are combined with other
materials after minimal amount of reprocessing for use in further production of
same product are not recycled materials.
.2
Discarded materials from one manufacturing process that are used as materials in
another manufacturing process are pre-consumer recycled materials.
Reuse: Using a product or component of municipal solid waste in its original form more
than once. (e.g., refilling a glass bottle that has been returned or using a coffee can to hold
nuts and bolts.)
.1
Reuse is a sustainable building strategy in that it:
.1
2014-10-01 BMS Version
Reduces the strain on both renewable and nonrenewable resources.
Section 01 35 18
LEED Requirements
Page 6
Plan No:
Project ID:
.2
.36
When materials are reused on or near the site of salvage, they reduce
transportation-related environmental impacts.
VOC: (Volatile Organic Compound). Organic substances capable of entering the gas
phase from either a liquid or solid form. VOCs are volatile enough to evaporate from
material surfaces into indoor air at normal room temperatures (referred to as off-gassing).
These substances are generally thought of to be harmful to both humans and the
environment. They are common in and emitted by many building products over time
through out-gassing:
.1
Solvents in paints and other coatings;
.2
Wood preservatives; strippers and household cleaners;
.3
Adhesives in particleboard, fiberboard, and some plywood; and foam insulation.
.4
When released, VOC’s can contribute to the formation of smog and can cause
respiratory tract problems, headaches, eye irritations, nausea, damage to the liver,
kidneys, and central nervous system, and possibly cancer.
.37
Wastewater: The spent or used water from a home, community, farm, or industry that
contains dissolved or suspended matter.
.38
Waste Management Plan: See Construction Waste Management
1.4
LEED ADMINISTRATION REQUIREMENTS
.1
The Consultant will apply for LEED Certification for the building.
.2
The certification process will be conducted through the CaGBC (Canada Green Building
Council) based LEED.
.3
Submission criteria, and support documentation will be provided by the Consultant and
the Contractor and assembled by the Consultant.
.4
Contractor and Subcontractors shall assist the Consultant, to assemble complete and
accurate information, as part of the contract requirements and as their portion of work is
undertaken.
.5
The Province has established, with the design team, the general sustainable goals for
design and for construction of the Project. The Contractor, Subcontractors, suppliers, and
manufacturers shall assist the Consultant by making the required submissions and
performing the required procedures to realize the Province’s sustainable goals.
1.5
PROJECT COORDINATION
.1
2014-10-01 BMS Version
Provide coordination associated with LEED Certification.
Section 01 35 18
LEED Requirements
Page 7
Plan No:
Project ID:
.2
1.6
Refer to section 01 31 13 project coordination.
PROJECT MEETINGS
.1
Provide LEED program meetings, pre-construction and progress meetings, associated
with monitoring the progress of LEED requirements.
.2
Refer to Section 01 31 19 Project Meetings.
1.7
CONSTRUCTION SCHEDULES
.1
Provide schedule of LEED submittals as a sub-schedule in the construction schedule.
.2
Refer to Section 01 32 16 construction schedules.
1.8
QUALITY ASSURANCE
.1
Contractor shall assign one person responsible for sustainable issues compliance and coordination and fulfill the requirements of this Section, a LEED Accredited Professional
(LAP).
.2
LEED Accredited Professional shall not be the Site Superintendent nor the Project
Manager but a knowledgeable employee who will assemble the required documentation
and screen it for adherence to the criteria stated in the Contract Documents prior to
submitting it for review to the Consultant.
1.9
SUBMITTALS
.1
Provide submittals in accordance with Section [01 33 00 - Submittal Procedures]
[
].
.2
Submit shop drawings and product data in accordance with Section [01 33 00 - Submittal
Procedures] [01 33 23 – Shop Drawings, Product Data and Samples].
.1
Shop drawings: stamped and signed by professional engineer, licensed in the
province of Alberta.
.3
Submit required letters, calculations, spreadsheets and templates for submittal to CaGBC.
.4
Submit additional LEED submittal requirements included in other sections in accordance
with Section [01 33 00 - Submittal Procedures] [
].
.1
2014-10-01 BMS Version
Submit in multiple copies when required, as separate submittals for compliance
with LEED requirements.
Section 01 35 18
LEED Requirements
Page 8
Plan No:
Project ID:
.5
Submit Project Materials and Cost Data: provide statement for total cost for building
materials used for Project. Include statement indicating total cost of mechanical and
electrical components.
SPEC NOTE: Paragraphs below require Contractor to make early submittals indicating how certain
LEED requirements will be met.
.6
Submit: LEED Action Plan: provide preliminary submittals within [14] [21] [30] days of
date for Award of contract indicating how the following requirements will be met.
SPEC NOTE: Edit the following paragraphs for LEED Credits to suit project.
.1
Materials and Resources:
.1
[Credit MR-2 Construction Waste Management]
.1
.2
.2
Prepare Construction Waste Management plan in accordance with
Section 01 74 19 - Waste Management and Disposal. [01 74 19BA - Waste Management Plan Construction and Demolition Projects
and 01 74 19B-B - Cost/Revenue Analysis Workplan Construction
and Demolition Projects]
Waste Management and Disposal goals for the project is [50%]
[75%].
[Credit MR-3 Materials Reuse].
.1
.2
.3
.4
Resources Reuse: prepare list of proposed salvaged and refurbished
materials.
Identify materials that will be salvaged or refurbished.
Identify source and cost of materials.
Materials reuse goals for the Project is [5%] [10%].
SPEC NOTE: Delete paragraph below if recycled content of various materials is specified, rather
than giving the Contractor the option to determine how recycled content requirement will be met.
.3
[Credit MR-4 Recycled Content].
.1
.2
.3
2014-10-01 BMS Version
Use materials with recycled content such that the sum of postconsumer recycled content plus 1/2 pre-consumer content
constitutes at least [10%] [20%] based on cost, of the total value of
materials in the project.
Recycled Content. Submit list of proposed materials with recycled
content.
Identify cost, post-consumer content and pre-consumer content for
products having recycled content.
Section 01 35 18
LEED Requirements
Page 9
Plan No:
Project ID:
.4
[Credit MR-5 Regional Materials].
.1
.2
.3
.4
.9
[Credit MR-7 Certified Wood] [
.1
.2
.3
.2
].
Submit list of proposed certified wood products.
Indicate products containing certified wood.
.1
Indicate source, and cost.
Include statement indicating total cost for wood-based materials
used for project, including non-rented temporary construction.
Environment Quality:
.1
.2
.7
Regional Materials: Submit list of proposed regionally
manufactured materials [and regionally extracted, harvested, and
recovered materials] [
].
Identify regionally manufactured materials.
.1
Identify source and cost.
Identify regionally extracted, harvested or recovered material.
.1
Identify source and cost.
Regionally extracted and manufactured products goals for the
Project is [20%] [30%].
Credit EQ-3.1 Construction IAQ Management Plan.
Submit Construction indoor air quality management plan.
LEED Progress Reports: Submit with Applications for Progress Payments, submit
reports comparing actual construction and purchasing activities with LEED action plans
for the following:
SPEC NOTE: Edit the following paragraphs to suit project.
2014-10-01 BMS Version
.1
Materials and Resources Credit MR-2 Construction Waste Management. Submit
Waste reduction progress reports in accordance with Section 01 74 19 Waste
Management and Disposal [01 74 19B-A - Waste Management Plan Construction
and Demolition Projects and 01 74 19B-B - Cost/Revenue Analysis Workplan
Construction and Demolition Projects]
.2
Materials and Resources Credit MR-3 Materials Reuse. Submit list of salvaged
and refurbished materials.
.3
Materials and Resources Credit MR-4 Recycled Content. Submit list of recycled
content of materials.
.4
Materials and Resources Credit MR-5 Regionally Materials. Submit list of
regionally manufactured materials [and regionally extracted, harvested, or
recovered materials] [
].
Section 01 35 18
LEED Requirements
Page 10
Plan No:
Project ID:
.8
LEED Documentation Submittals:
SPEC NOTE: Edit the paragraphs below to be submitted to CaGBC as part of LEED certification
process. See Division 07 Roofing Sections for information about Energy Star compliant roofing.
Energy Star compliant roofing requires a highly reflective roof surface, a light color material, which
is ideal in a climate with more cooling days than heating days.
.1
Submit product data for roofing materials for Sustainable Sites Credit [SS-7.2
Heat Island Effect: Roof] [
]indicating [Energy Star compliance] [green
vegetated roof system] [emissivity rating to ASTM E408] [minimum initial
reflectance and minimum 3-year-aged reflectance].
.2
Submit product data for lighting fixtures for Sustainable Sites Credit [SS-8.0
Light Pollution Reduction] [
]. Submit data for interior and exterior
lighting fixtures that stop direct-beam illumination from leaving the building site.
Submit photos per credit requirements.
.3
Submit product data for plumbing fixture for Water Efficiency Credits [WE
Prereq-1 Water Use Reduction, 20% Reduction] [WE-2 Innovative Wastewater
Technologies] [WE-3 Water Use Reduction]. Submit Data for plumbing fixtures
indicating water consumption.
SPEC NOTE: Retain option in subparagraph below if Contractor is required to establish the phaseout plan.
.4
Submit product data for Energy and Atmosphere Prerequisite [EA-3 Fundamental
Refrigerant Management] [
].
.1
Include product data for new HVAC equipment indicating absence of CFC
refrigerants [and] [Phase-out plan to replace CFC refrigerants in
HVAC&R systems with CFC-free refrigerants within the Construction
Period].
SPEC NOTE: Edit the following paragraphs below for the specific project.
2014-10-01 BMS Version
.5
Submit product data for Energy and Atmosphere Credit [EA-4 Enhanced
Refrigerant Management] [
]. Submit product data for new HVAC
equipment indicating absence of HCFC refrigerants [and for clean-agent fireextinguishing systems indicating absence of HCFC and Halon] [
].
.6
Submit product data for Energy and Atmosphere Credit [EA-5 Measurement and
Verification] [
]. Submit product data and wiring diagrams for sensors
and data collection systems for metering of building energy and water
consumption performance.
.7
Submit Construction Waste Management Plan for Materials and Resources Credit
MR-2. Comply with Section 01 74 19 Waste Management and Disposal
[01 74 19B-A - Waste Management Plan Construction and Demolition Projects
Section 01 35 18
LEED Requirements
Page 11
Plan No:
Project ID:
and 01 74 19B-B - Cost/Revenue Analysis Work plan Construction and
Demolition Projects]. Include the following submittals:
.1
Submit receipts for Materials and Resources Credit [MR-3 Materials
Reuse]. Submit receipts for salvaged and refurbished materials used for
project, indicating sources and costs for salvaged and refurbished
materials.
.2
Submit product data and certification letters for Materials and Resources
Credit [MR-4 Recycled Content]. Submit product data and certification
letter indicating percentages by weight of post-consumer and preconsumer recycled content for products having recycled content. Include
statement indicating costs for products having recycled content.
.3
Submit product data for Materials and Resources Credit [MR-5 Regional
Materials]. Submit product data indicating location of material
manufacturer for regionally manufactured materials. Include the following:
.1
Statement indicating cost and distance from manufacturer to
project for each regionally manufactured material.
SPEC NOTE: The paragraph below applies to Credit MR 5.2.
.2
.4
Statement indicating cost and distance from point of extraction,
harvest, or recovery to project for each raw material used in
regionally manufactured materials.
Submit product data for Materials and Resources Credit [MR-6 Rapidly
Renewable Materials] [
]. Submit product data for rapidly
renewable materials.
.1
Include statement indicating costs for each rapidly renewable
material.
SPEC NOTE: Submittals in subparagraphs below are required to be submitted to CaGBC in order to
obtain indicated credit.
.5
2014-10-01 BMS Version
Submit product data and certificates for Materials and Resources Credit
[MR-7 Certified Wood] [
]. Submit product data and certificates of
chain-of-custody for products containing certified wood.
.1
Include statement indicating costs for products containing certified
wood.
.2
Include statement indicating total cost for wood-based materials
used for project, including non-rented temporary construction.
Section 01 35 18
LEED Requirements
Page 12
Plan No:
Project ID:
.8
Submit product data and shop drawing for Indoor Environmental Quality Credit
[EQ-1 Outdoor Air Delivery Monitoring] [
]. Submit product data and shop
drawings for carbon dioxide monitoring system.
.9
Provide submittals for Indoor Environmental Quality Credit [EQ-3.1 Construction
IAQ Management Plan During Construction] [
]. Include the following:
.1
.2
.3
.4
.10
Provide submittals for Indoor Environmental Quality Credit [EQ-3.2 Construction
IAQ Management Plan Before Occupancy] [
]. Include the following:
.1
.2
.3
.11
.2
.2
2014-10-01 BMS Version
Submit product data for interior adhesives and sealants indicating VOC
content of product used.
Indicate VOC content in g/L calculated in accordance with SCAQMD
Rule 1168.
Submit product data for Indoor Environmental Quality Credit [EQ-4.2 LowEmitting Materials: Paints and Coatings] [
].
.1
.13
Signed statement describing building air flush-out procedures including
start and completion dates of flush out and statement that filtration media
was replaced after flush-out.
Product data for filtration media used during flush-out and during
occupancy.
Report from testing and inspecting agency indicating results of IAQ testing
and documentation showing conformance with IAQ testing procedures and
requirements.
Submit product data for Indoor Environmental Quality Credit [EQ-4.1 LowEmitting Materials: Adhesives and Sealants] [
].
.1
.12
Construction indoor air quality management plan.
Product data for temporary filtration media.
Product data for filtration media used during occupancy.
Construction documentation submit [6] [
] photographs at [3] [
]
different times during construction along with description of utilized IAQ
measures in accordance with SMACNA, documenting protection of ducts
and on-site stored or installed absorptive materials from moisture.
Submit product data for interior paints and coatings indicating chemical
composition and VOC content for products used.
Indicate VOC content in g/L calculated in accordance with [Green Seal's
Standard GS-11] [and] [Green Seal's Standard GC-03] [and] [SCAQMD
Rule 1113].
Submit product data for indoor Environmental Quality Credit [EQ-4.3 LowEmitting Materials: Carpet] [
].
Section 01 35 18
LEED Requirements
Page 13
Plan No:
Project ID:
.1
.2
.14
.15
Submit product data for Indoor Environmental Quality Credit [EQ-4.4 LowEmitting Materials: Composite Wood and Agrifibre Products] [
].
.1
Submit product data for composite wood and agrifiber products indicating
products contain no urea-formaldehyde resins.
.2
Include statement for adhesives use in fabrication of laminated assemblies.
.3
Submit photos of products at project site.
Submit product data and shop drawing for Indoor Environmental Quality Credit
[EQ-6.1 Controllability of Systems: Lighting] [
].
.1
.16
Submit product data and shop drawings for lighting system controls for
minimum 90% of the building occupants.
Submit product data and shop drawing for Indoor Environmental Quality Credit
[EQ-6.2 Controllability of Systems: Thermal Comfort] [
].
.1
1.10
Submit product data for carpet products.
Indicate VOC content in accordance with CRI Green Label Indoor Air
Quality Test Program.
Submit product data and shop drawings for sensors and control systems
used for individual airflow and temperature for minimum 50% of the
building occupants.
LEED SUBMITTAL FORMS
.1
LEED submittal forms are available to LEED members from the Canada Green
Building Council website at http://www.cagbc.org.
2.
Products
2.1
SALVAGED AND RE-FURBISHED MATERIALS
SPEC NOTE: Delete option in title of paragraph below if 5% is selected; retain option if 10% is
selected.
.1
Credit MR 3:
.1
.2
2014-10-01 BMS Version
Provide salvaged, re-manufactured or refurbished materials for [5] [10]% of
building materials, by cost.
The following materials may be salvaged or refurbished materials:
.1
[
].
.2
[
].
Section 01 35 18
LEED Requirements
Page 14
Plan No:
Project ID:
SPEC NOTE: Delete paragraph above or below. Retain above if Contractor is given the option to
determine how requirement for salvaged or refurbished materials will be met. Retain below to specify
materials that are required to be salvaged or refurbished materials.
.2
Credit MR 3: The following materials shall be salvaged or refurbished materials:
SPEC NOTE: Retain list below with either paragraph above. Insert list of applicable materials.
.1
.2
.3
2.2
[
[
[
].
].
].
RECYCLED CONTENT OF MATERIALS
.1
Credits MR 4:
.1
Provide building materials with recycled content such that post consumer recycled
content plus one half of pre consumer recycled content constitutes a minimum of
10% of the cost of materials used for the Project or such that post consumer
recycled content plus one half of pre consumer recycled content constitutes a
minimum of 20% of the cost of materials used for the Project:
SPEC NOTE: Retain four subparagraphs below with either paragraph above.
2.3
.1
The cost of post consumer recycled content of an item shall be determined
by dividing the weight of post consumer recycled content in the item by
the total weight of the item and multiplying by the cost of the item.
.2
The cost of post consumer recycled content plus one half of pre consumer
recycled content of an item shall be determined by dividing the weight of
post consumer recycled content plus one half of pre consumer recycled
content in the item by the total weight of the item and multiplying by the
cost of the item.
.3
Do not include mechanical and electrical components in the calculation.
.4
Recycled content of materials shall be as defined above.
REGIONAL MATERIALS
SPEC NOTE: If retaining either paragraph in this article, be sure to select materials for the Project
that can comply.
.1
2014-10-01 BMS Version
Credit MR 5: Provide [20%] [30%] of building materials, by cost, that are regionally
extracted, harvested, and recovered materials.
Section 01 35 18
LEED Requirements
Page 15
Plan No:
Project ID:
2.4
CERTIFIED WOOD
SPEC NOTE: Delete this article if certified wood is specified for certain items in Divisions 2 through
49, rather than allowing the Contractor to choose how the 50% requirement will be met. Note that
wood materials must constitute two% of the cost of building materials to gain this credit.
.1
Credit MR 7.0: Provide a minimum of 50%, by cost, of wood based materials that are
produced from wood obtained from forests certified by an FSC accredited certification
body to comply with FSC 1.2, Principles and Criteria.
.1
Wood based materials include but are not limited to the following materials when
made from made wood, engineered wood products, or wood based panel products:
SPEC NOTE: Delete items from list below that do not apply.
.1
.2
.3
.4
.5
.6
.6
.8
.9
.10
.11
.12
.13
.14
2.5
Rough carpentry.
Miscellaneous carpentry.
Heavy timber construction.
Wood decking.
Metal plate connected wood trusses.
Structural glued laminated timber.
Finish carpentry.
Architectural woodwork.
Wood paneling.
Wood veneer wall covering.
Wood flooring.
Wood lockers.
Wood cabinets.
Non-rented temporary construction, including bracing, concrete formwork,
pedestrian barriers, and temporary protection.
LOW EMITTING MATERIALS
SPEC NOTE: Adhesives and sealants are required for various products where they may be specified
only by the requirement to install according to manufacturer's written instructions. For this reason, it
is probably best to retain this article.
.1
Credit EQ 4.1: For interior applications use adhesives and sealants that comply with the
following limits for VOC content when calculated according to 40 CFR 59, Subpart D,
EPA Method 24:
SPEC NOTE: Edit list below by deleting applications not used. VOC limits listed are from South
Coast Air Quality Management District Rule #1168 for adhesives and from Bay Area Air Quality
Management District Regulation 8, Rule 51, for sealants and sealant primers.
.1
.2
.3
2014-10-01 BMS Version
Wood Glues: 30 g/L.
Metal to Metal Adhesives: 30 g/L.
Adhesives for Porous Materials (Except Wood): 50 g/L.
Section 01 35 18
LEED Requirements
Page 16
Plan No:
Project ID:
.4
.5
.6
.7
.8
.9
.10
.11
.12
.13
.14
.15
.16
.17
.18
.19
.20
.21
.22
.23
.24
.25
.2
Credit EQ 4.2: For interior applications use paints and coatings that comply with the
following limits for VOC content when calculated according to 40 CFR 59, Subpart D,
EPA Method 24 and the following chemical restrictions:
.1
.2
.3
.4
.5
.6
.7
2014-10-01 BMS Version
Subfloor Adhesives: 50 g/L.
Plastic Foam Adhesives: 50 g/L.
Carpet Adhesives: 50 g/L.
Carpet Pad Adhesives: 50 g/L.
VCT and Asphalt Tile Adhesives: 50 g/L.
Cove Base Adhesives: 50 g/L.
Gypsum Board and Panel Adhesives: 50 g/L.
Rubber Floor Adhesives: 60 g/L.
Ceramic Tile Adhesives: 65 g/L.
Multipurpose Construction Adhesives: 70 g/L.
Fibreglass Adhesives: 80 g/L.
Structural Glazing Adhesives: 100 g/L.
Wood Flooring Adhesive: 100 g/L.
Contact Adhesive: 250 g/L.
Plastic Cement Welding Compounds: 350 g/L.
ABS Welding Compounds: 400 g/L.
CPVC Welding Compounds: 490 g/L.
PVC Welding Compounds: 510 g/L.
Adhesive Primer for Plastic: 650 g/L.
Sealants: 250 g/L.
Sealant Primers for Nonporous Substrates: 250 g/L.
Sealant Primers for Porous Substrates: 775 g/L.
Flat Paints and Coatings: VOC not more than 50 g/L.
Non Flat Paints and Coatings: VOC not more than 150 g/L.
Anti Corrosive Coatings: VOC not more than 250 g/L.
Varnishes and Sanding Sealers: VOC not more than 350 g/L.
Stains: VOC not more than 250 g/L.
Aromatic Compounds: Paints and coatings shall not contain more than 1.0% by
weight total aromatic compounds (hydrocarbon compounds containing one or
more benzene rings).
Restricted Components: Paints and coatings shall not contain any of the
following:
.1
Acrolein.
.2
Acrylonitrile.
.3
Antimony.
.4
Benzene.
.5
Butyl benzyl phthalate.
.6
Cadmium.
.7
Di (2 ethylhexyl) phthalate.
.8
Di n butyl phthalate.
.9
Di n octyl phthalate.
.10
1,2 dichlorobenzene.
Section 01 35 18
LEED Requirements
Page 17
Plan No:
Project ID:
.11
.12
.13
.14
.15
.16
.17
.18
.19
.20
.21
.22
.23
.24
.25
Diethyl phthalate.
Dimethyl phthalate.
Ethylbenzene.
Formaldehyde.
Hexavalent chromium.
Isophorone.
Lead.
Mercury.
Methyl ethyl ketone.
Methyl isobutyl ketone.
Methylene chloride.
Naphthalene.
Toluene (methylbenzene).
1,1,1 trichloroethane.
Vinyl chloride.
SPEC NOTE: If retaining paragraph below, coordinate with Sections where composite wood
products are specified to avoid conflicting requirements in those Sections.
.3
Credit EQ 4.4: Do not use composite wood and agrifiber products that contain
urea formaldehyde resin.
3.
Execution
3.1
SITE DISTURBANCE
SPEC NOTE: Paragraph below is for green field sites. For previously developed sites, Credit SS 5.1
requires that 50% of the open area of the site be restored by planting native or adapted vegetation.
Show site restoration on a landscape plan.
.1
Credit SS 5.1: Comply with requirements of Section 01 11 00: Summary of Work.
SPEC NOTE: Delete option in article title below if clean agent fire extinguishing systems are not
used.
3.2
REFRIGERANT AND CLEAN AGENT FIRE EXTINGUISHING AGENT
REMOVAL
.1
Prerequisite EA 3.0: Remove CFC based refrigerants from existing HVAC and
refrigeration equipment indicated to remain and replace with refrigerants that are not CFC
based. Replace or adjust existing equipment to accommodate new refrigerant as described
in HVAC Sections.
SPEC NOTE: Delete option in paragraph below if clean agent fire extinguishing systems are not
used.
.2
Credit EA 4.0: Remove HCFC based refrigerants from existing HVAC and refrigeration
equipment indicated to remain and replace with refrigerants that are not HCFC based.
2014-10-01 BMS Version
Section 01 35 18
LEED Requirements
Page 18
Plan No:
Project ID:
Replace or adjust equipment to accommodate new refrigerant; [ remove clean agent fire
extinguishing agents that contain HCFCs or halons, and replace with agent that does not
contain HCFCs or halons]:
.1
Refer to HVAC Section [
] for additional requirements.
SPEC NOTE: Delete subparagraph below if clean agent fire extinguishing systems are not used.
.2
3.3
Refer to Section [
] fire extinguishing system for additional requirements.
CONSTRUCTION WASTE MANAGEMENT
.1
3.4
Credit MR 2: In accordance with Section 01 74 19 - Waste Management and Disposal.
CONSTRUCTION INDOOR AIR QUALITY MANAGEMENT
SPEC NOTE: Verify that equipment receiving MERV 13 air filters can support associated static
pressures before retaining paragraph below. MERV 13 air filters may have higher static pressures
than originally designed for air handlers.
.1
Credit EQ 3.1: Comply with SMACNA IAQ Guideline for Occupied Buildings under
Construction, Chapter 3:
SPEC NOTE: Coordinate subparagraph below with CMS Division 1 section Temporary Facilities
and Controls. Identify air handlers and associated return air inlets authorized by Province for use
during construction period.
.1
If the Province authorizes the use of permanent heating, cooling, and ventilating
systems during construction period as specified in Section [
] - Temporary
Controls, install filter media having a MERV 8 according to ASHRAE 52.2 at
each return air inlet for the air handling system used during construction.
SPEC NOTE: Retain first option in subparagraph below if building air flush out is not required.
.2
.2
Replace all air filters immediately prior to [occupancy] [building air flush out].
Replacement air filters shall have a MERV 13 according to ASHRAE 52.2.
Credit EQ 3.2:
SPEC NOTE: Many air handling units are not capable of 100% outdoor air. Only make up air units
and replacement air units and those units specified with economizer cycles have duct connections to
allow for 100% outdoor air. Units with economizer cycles may not have capacity to do building air
flush out during other than moderate outdoor air temperature and humidity conditions. This may
limit the time when building air flush out can be performed and, because of limitations in duct
connections, it may not be possible to perform a building air flush out in some or all of the building.
Temporary provisions must be required to relieve or exhaust outdoor air introduced during building
air flush out. Verify that equipment receiving MERV 13 air filters can support associated static
2014-10-01 BMS Version
Section 01 35 18
LEED Requirements
Page 19
Plan No:
Project ID:
pressures before retaining paragraph below. MERV 13 air filters may have higher static pressures
than originally designed for air handlers.
.1
Conduct a two (2) week building air flush after construction ends with new air
filters and 100% outdoor air. Replace air filters after building air flush.
Replacement air filters shall have a MERV 13 according to ASHRAE 52.2:
SPEC NOTE: Specify details of air flush below. Details will need to designate HVAC equipment and
air filters to be used, minimum air flow rates, etc.
.1
[
]
SPEC NOTE: If seeking this credit, select subparagraph above and insert details or select one of two
subparagraphs below. EPA document referenced in two subparagraphs below is available at
www.epa.gov/rtp/new bldg/environmental/s_01445.htm.
.2
The Province will conduct a baseline indoor air quality testing program according
to EPA Protocol for Environmental Requirements, Baseline IAQ and Materials,
for Research Triangle Park Campus, Section [
]. Payment for these services
will be made [by the Province.] [from the IAQ Testing Allowance, as authorized
by Change Orders.]
.3
Engage an independent testing and inspecting agency to conduct a baseline indoor
air quality testing program according to EPA Protocol for Environmental
Requirements, Baseline IAQ and Materials, for Research Triangle Park Campus,
Section 01 45 00 Quality Control.
END OF SECTION
2014-10-01 BMS Version
Download