Project work, TMR 4225 Marine Operations By: Jon Eivind Skurtveit, Ole Gunnar Helgøy, Morten Haukom, Camilla Stokvik and Ingrid Ødegård TMR 4225 – Marine Operations Project work Preface This report is a group project in the subject “TMR 4225 Marine Operations” the spring 2007. The report is based on the curriculum in the subject. It counts 30% of the final grade. The project focuses on the operational phases load out, towing and installation of a subsea template. For one of the operational phases we have used MATLAB to execute calculations. The information used to develop this report is based on the compendium and teaching material in the course. We have also used a lot of supplement literature found on the internet and from the library. The Lecturers and the assistant have answered questions and helped us trough the process of writing the report. We would like to thank Finn Gunnar Nielsen, Tor Einar Berg and Ken-Robert G. Jakobsen for all help and answers. There have been some difficulties with understanding and sorting out the task information. But with good cooperation within the group we solved the difficulties and moved on. The group has worked well together. Trondheim, april 07 _________________ _________________ Jon Eivind Skurtveit Ole Gunnar Helgøy _________________ _________________ Morten Haukom Ingrid Ødegård _________________ Camilla Stokvik I Project work TMR 4225 – Marine Operations Summary We have considered the case where a subsea template is transported on a barge to the Ormen Lange field. We have focused our work on the operational phases load out, towing to site and installation. The Ormen Lange field is located in the in the Norwegian Sea. The field is situated on deep water and faces challenging sea and wave conditions. These factors require that the operations are carefully planned with regard to weather forecasts and statistical values. The sea bed topography also has to be considered. In the case of Ormen Lange the sea floor can be extremely rough. Mapping and survey operations are important and require great attention when the template is being installed. The template is constructed in Tønsberg and is then being rolled on to the barge. The weight and large dimensions of the template makes the operation complicated. The next phase is the towing of the barge to the installation site. Important aspects to consider in this phase are mean towing force, effect of propeller race, directional stability and the dynamic loads in the towing line. The installation process involves several sub operations. The sub operations we have considered are the lift operation, water entry, immersion, landing and anchoring of the template. The vessels involved in the different operations have to be effective in performing their mission. In addition, all have to be in accordance with rules and regulations and satisfy safety requirements. Based on this the main vessels used have been decided. Autonomous underwater vehicles (AUV) and remotely operated vehicles (ROV) can be used to perform a fine-scaling geological mapping as a preparation to the installation phase. This is important in planning the installation process. It is important that the Det Norske Veritas (DNV) standards are followed in all parts of the operations. In this consideration it is necessary to calculate and evaluate maximum wave height allowed. The coupled movements in the crane operation in the installation phase are considered in greater detail. MATLAB is used as a tool in these calculations. A comparison of the eigenperiods and the dynamic response from the coupled motions between the lifting of the template in water and in air is performed. The eigenperiod in both cases indicates that resonance is not likely to occur. This conclusion is based on a comparison of our results with statistical wave data. II Project work TMR 4225 – Marine Operations Index PREFACE ............................................................................................................................................................... I SUMMARY .......................................................................................................................................................... II INDEX .................................................................................................................................................................. III INDEX OF FIGURES......................................................................................................................................... IV INDEX OF TABLES .......................................................................................................................................... IV 1 INTRODUCTION ....................................................................................................................................... 1 2 SCOPE OF WORK ..................................................................................................................................... 2 2.1 LOCATION ............................................................................................................................................. 2 2.2 WATER DEPTH ...................................................................................................................................... 3 2.3 ENVIRONMENT...................................................................................................................................... 3 2.3.1 Sea floor topography ....................................................................................................................... 3 2.3.2 Water temperature........................................................................................................................... 4 2.3.3 Wind, Weather and waves ............................................................................................................... 4 3 MAIN PHASES ........................................................................................................................................... 5 3.1 LOAD-OUT ............................................................................................................................................ 5 3.2 TOWING TO SITE.................................................................................................................................... 6 3.2.1 Towline ............................................................................................................................................ 6 3.2.2 Mean towing force and effect of propeller race .............................................................................. 6 3.2.3 Critical issues .................................................................................................................................. 7 3.3 INSTALLATION ...................................................................................................................................... 7 3.3.1 Crane operation .............................................................................................................................. 7 3.3.2 Water entry ...................................................................................................................................... 9 3.3.3 Immersion and landing at the bottom .............................................................................................. 9 3.3.4 Critical issues ................................................................................................................................ 11 4 VESSEL INVOLVED ............................................................................................................................... 12 4.1 4.2 4.3 4.4 4.5 5 TOR VIKING II (TUGBOAT) .................................................................................................................. 12 BOA BARGE 21 ................................................................................................................................... 12 SSCV THIALF (CRANE VESSEL) .......................................................................................................... 13 M/S GEOBAY( ROV-VESSEL) ............................................................................................................. 14 TRITON XL37 ROV ............................................................................................................................ 14 ROV AND AUV SUPPORT ..................................................................................................................... 16 5.1 5.2 MAPPING AND PREPARING THE SEAFLOOR .......................................................................................... 16 TEMPLATE INSTALLATION .................................................................................................................. 16 6 GANNT – CHART .................................................................................................................................... 18 7 USE OF THE DNV OFFSHORE STANDARD ...................................................................................... 20 8 DYNAMIC MODEL FOR CRANE VESSEL AND LOAD ................................................................... 22 8.1 CALCULATION OF EIGENPERIODS AND RESPONSES .............................................................................. 24 8.2 DYNAMIC RESPONSE ........................................................................................................................... 26 8.2.1 Template hanging in the air .......................................................................................................... 26 8.2.2 Template submerged ..................................................................................................................... 30 8.3 COMMENTS ......................................................................................................................................... 35 8.3.1 Results ........................................................................................................................................... 35 8.3.2 Improvements ................................................................................................................................ 35 8.3.3 Further work ................................................................................................................................. 35 9 FEASIBILITY OF THE OPERATION .................................................................................................. 36 10 KILDER ..................................................................................................................................................... 37 APPENDIX A: MODEL OF THE TEMPLATE, AND DEFINITIONS OF NOTATIONS ..........................A III Project work TMR 4225 – Marine Operations APPENDIX B: MATLAB ROUTINE “WATERRESPONSE.M” ...................................................................A APPENDIX C: MATLAB ROUTINE “AIRRESPONSE.M” ...........................................................................A APPENDIX D: WAVE STATISTICS ................................................................................................................. B Index of figures FIGURE 1: ILLUSTRATION OF TOWING ROUTE [MAP1] .............................................................................................. 2 FIGURE 2: A PICTURE SHOWING THE LOCATION OF ORMEN LANGE [MAP2] ............................................................ 2 FIGURE 3: ILLUSTRATION OF THE PLACING OF THE TEMPLATE ................................................................................. 3 FIGURE 4: AN ILLUSTRATION OF THE SEA BED TOPOGRAPHY ................................................................................... 4 FIGURE 5: LOAD OUT. THE TEMPLATE IS ROLLED ON THE BARGE............................................................................. 5 FIGURE 6: TOWING .................................................................................................................................................. 6 FIGURE 7: SSCV THIALF ......................................................................................................................................... 8 FIGURE 8: THE TEMPLATE RIGHT BEFORE LIFT-OFF .................................................................................................. 9 FIGURE 9: WATER ENTRY ........................................................................................................................................ 9 FIGURE 10: HYDRO ACOUSTIC TRANSPONDERS ...................................................................................................... 10 FIGURE 11: THE TEMPLATE IN DETAIL FIGURE 12: THE SUCTION ANCHOR ...................................................... 10 FIGURE 13: CRITICAL ISSUES FOR CRANE LIFT ....................................................................................................... 11 FIGURE 14: TOR VIKING II ..................................................................................................................................... 12 FIGURE 15: BOA BARGE 21 .................................................................................................................................... 13 FIGURE 16: SSCV THIALF ..................................................................................................................................... 13 FIGURE 17: M/S GEOBAY ...................................................................................................................................... 14 FIGURE 18: TRINTON XL37 ROV .......................................................................................................................... 14 FIGURE 19: SEA FLOOR TOPOGRAPHY .................................................................................................................... 16 FIGURE 20: GANNT CHART..................................................................................................................................... 18 FIGURE 21: MASS MATRIX ..................................................................................................................................... 22 FIGURE 22: THE MOORING AND HYDROSTATIC STIFFNESS...................................................................................... 23 FIGURE 23: COUPLED VESSEL-TEMPLATE STIFFNESS.............................................................................................. 23 FIGURE 24: DYNAMIC RESPONSE IN DIRECTION 1 ................................................................................................... 26 FIGURE 25: DYNAMIC RESPONSE IN DIRECTION 2 ................................................................................................... 26 FIGURE 26: DYNAMIC RESPONSE IN DIRECTION 3 ................................................................................................... 27 FIGURE 27: DYNAMIC RESPONSE IN DIRECTION 4 ................................................................................................... 27 FIGURE 28: DYNAMIC RESPONSE IN DIRECTION 5 ................................................................................................... 28 FIGURE 29: DYNAMIC RESPONSE IN DIRECTION 6 ................................................................................................... 28 FIGURE 30: DYNAMIC RESPONSE IN DIRECTION 7 ................................................................................................... 29 FIGURE 31: DYNAMIC RESPONSE IN DIRECTION 8 ................................................................................................... 29 FIGURE 32: DYNAMIC RESPONSE IN DIRECTION 9 ................................................................................................... 30 FIGURE 33: DYNAMIC RESPONSE IN DIRECTION 1 ................................................................................................... 30 FIGURE 34: DYNAMIC RESPONSE IN DIRECTION 2 ................................................................................................... 31 FIGURE 35: DYNAMIC RESPONSE IN DIRECTION 3 ................................................................................................... 31 FIGURE 36: DYNAMIC RESPONSE IN DIRECTION 4 ................................................................................................... 32 FIGURE 37: DYNAMIC RESPONSE IN DIRECTION 5 ................................................................................................... 32 FIGURE 38: DYNAMIC RESPONSE IN DIRECTION 6 ................................................................................................... 33 FIGURE 39: DYNAMIC RESPONSE IN DIRECTION 7 ................................................................................................... 33 FIGURE 40: DYNAMIC RESPONSE IN DIRECTION 8 ................................................................................................... 34 FIGURE 41: DYNAMIC RESPONSE IN DIRECTION 9 ................................................................................................... 34 Index of tables TABLE 1: RESPONSE IN AIR .................................................................................................................................... 24 TABLE 2: RESPONSE IN WATER .............................................................................................................................. 25 IV Project work TMR 4225 – Marine Operations 1 Introduction Norway is one of the leading countries on subsea technology. The projects in the Norwegian Sea and the North Sea continually move to larger sea depths and the sea bottom is more hilly and tough. The development of subsea technology in the offshore industry is therefore growing. Larger and more advanced systems are installed at the sea bottom. In this report we will consider the transportation of a subsea template on a barge. We want to make the installation realistic and have therefore chosen to consider a real case. We will install our template at the Ormen Lange field in the Norwegian Sea. The report focuses on three main phases, load-out, towing to site and installation. Sub phases and critical issues for each of them will be described. We also look more detailed into the installation phase where an analysis of the lifting operation will be performed. When the template is lifted off the barge and lowered into the sea, high risks are involved in the operation. The movements of the barge, template and crane vessel all have to be taken into consideration. The vessels we have used to perform different tasks in the operations will be presented with a description of their work field. Remotely operated vehicles (ROV) are very effective in assisting operations. ROVs can be used in several types of operations and perform different tasks. Important work fields will also be described. A schedule including the duration time for different tasks will be presented and the information is represented in form of a Gannt diagram. It is extremely important to be consistent with the rules and regulations established by the classification companies. We will use offshore standard DNV-OS-HI101 in our discussion on this. 1 Project work TMR 4225 – Marine Operations 2 Scope of work In this report we will use the Ormen Lange field as a reference. In the following subchapters we will present relevant information on location and environment at the actual site. 2.1 Location We want to transport our template to the Ormen Lange field, which is a gas field located 120 kilometres northwest of the Mørecoast, Norway [Hydro1]. The template will be produced in Tønsberg, where the load-out operation is performed, and then towed on a barge from Tønsberg to the Ormen Lange field. This is a distance of approximately 570 nautical miles. Figure 1: Illustration of towing route [Map1] Figure 2: A picture showing the location of Ormen Lange [Map2] 2 Project work TMR 4225 – Marine Operations 2.2 Water depth The water depth at the site varies from 850 to 1100 m [Hydro1][Hydro2][Hydro3]. This depth sets requirements to the hydrodynamic pressure the template have to withstand. The template consists of several structural parts that all have to be dimensioned for the pressure and forces it is exposed to. This has to be taken in consideration when the template is designed. The depth also has an effect on the complexity of the subsea operations. Large water depth cause higher pressure, low temperatures and unpredictable currents. Figure 3: Illustration of the placing of the template 2.3 Environment 2.3.1 Sea floor topography The location where the template is placed permanently depends on the sea bed topography. It is preferable that the ground is horizontal and free of large variations. At the Ormen Lange field, the topography of the sea floor is irregular, hilly and challenging, therefore the sea bed needs modification. Modifications can be removing of ground mass or filling of immersions in the sea bed. 3 Project work TMR 4225 – Marine Operations Figure 4: An illustration of the sea bed topography 2.3.2 Water temperature The Ormen Lange field is located in the Norwegian Sea. The Gulf Stream, a heated oceanic current, moves from the Caribbean Sea to the Norwegian Sea [Golf]. The current brings heated water and provides the region with a milder climate. Despite of this, the water temperature near the sea bottom, at 800 to 1100 m depth, is down to zero degrees Celsius. We can also find temperatures below zero [Water1][Water2]. The low temperatures combined with high pressure can induce hydratization in the pipes on the template and in the pipes connected to the template. That makes it necessary to take precautions, and this is often preformed by injecting anti-freeze substances. The cold environment also effects the material which the template is build of, and this has to be taken into consideration in the design phase. 2.3.3 Wind, Weather and waves The execution of the operational phases, transporting and installing, of the template is extremely weather dependent. The weather in the Norwegian Sea is very tough, and the wind can be, and often is, very strong which induces large waves. This will affect the possibility to carry out the operations. During the summer season the wind velocities and wave heights are generally at their lowest, which can be seen from statistics. The weather interference is therefore smallest at this time. Many operations are for this reason carried out in the summer. Delays in the operations are very expensive and must be avoided if possible. It is important to plan the operation with regard to weather forecasts so that stop because of the weather is not likely to occur. In the Offshore Standard DNV-OSH101 section 3 we find requirements for the environmental conditions such as wind, wave and current. We will follow these in the planning and during the operations. 4 Project work TMR 4225 – Marine Operations 3 Main phases As mentioned, the main phases we are going to consider in this report are the load-out, towing to site and installation phase. These phases consist of several smaller operations. The most important aspects of these operations and critical issues for each phase are discussed in the following sub chapters. 3.1 Load-out Load-out is the operation where a structure is moved from land to the sea. There are different ways of performing such an operation. A structure can be lifted from a quay onto a ship/barge, or it can be rolled on to a barge. If the structure is self-floating it can be built in a dry-dock and then towed out after water has been filled. When deciding how to perform the load-out operation there are many important factors. However, crucial factors involve the structure itself. Structures with a small weight and dimensions have relative small forces involved which will simplify the operation. For small structures it is common to use crane lifts in able to move the structure to a ship or a barge. For larger structures the load-out operation is more difficult. The crane capacity is limited. Thus it is often more convenient to execute the load-out operation without a crane involved. This can be done using a custom made vehicle that rolls the structure onto a barge, or if it is floating, directly into the sea. In our case we have a subsea template with length 44m, breadth 33m and height 15m and weight 1150 ton. The template is constructed in Tønsberg at Grenland Group. The weight of the template makes it a heavy lift and the crane capacity on the construction site cannot handle the weight of the structure. Using a crane vessel is expensive, especially if delay occurs. There may also be some difficulties according to the motion of the structure during the lift operation. The template has a large mass and extension. As a result, the motion response has to be limited. This can be difficult to maintain especially since the crane is not on fixed ground. Another possibility is to roll the structure on the barge. This will cause a trim moment on the barge and a huge ballast capacity is needed to handle the weight. Figure 5: Load out. The template is rolled on the barge From a risk viewpoint, the crane lift is much more exposed to accidents and the consequences can be large. Intuitively the possibility of accident is larger for a crane operation than with a roll-on operation, and the consequences are bigger. The economical aspect is also important to consider. The cost of planning and execute a lifting operation is larger than for a roll-on operation. Especially the hiring of a crane vessel is very expensive. 5 Project work TMR 4225 – Marine Operations Since the template has to be transported from the construction site to the quay, it is already on a vehicle and thus the roll-on alternative is definitely easiest. From the discussion above we have concluded that the roll-on alternative is the best load-out method in our case. 3.2 Towing to site When the template has been constructed and placed on a barge it is ready to be towed to the installation site. We estimate that the towing operation from Tønsberg to the Ormen Lange field will take about four days. That means that we will have an average towing velocity of about 6 knots. Normally, different towing configurations are used during inshore and offshore tows. A classical towing configuration for offshore towing of a barge is using a single tug. Towing velocity, bollard pull and loads in the towing line are important factors to consider during offshore tows. For inshore towing, maneuverability is the most important consideration. The towing configuration can consist of more than one tug and shorter towing lines in order to control and maneuver the barge. Figure 6: Towing In the following subchapters we have presented topics that are relevant to evaluate during a towing operation. 3.2.1 Towline The towline has to be chosen based on important parameters like breaking load, stiffness of the line, weight, damping and abrasion and corrosion characteristics. Det Norske Veritas (DNV) has established rules and regulations for minimum breaking strength of the towing line. In addition, there are requirements set by DNV for minimum length. It is important that we follow these rules in our case. It is extremely important to analyze the dynamic loads in the towing lines. Damage to the towing lines can be critical in a towing situation. The line is experiencing large loads and need to be dimensioned accordingly. Critical happenings in this regard can be overloading, fatigue, local chafing and cutting by propeller. 3.2.2 Mean towing force and effect of propeller race Another important factor is to consider is the mean towing force. Wind and waves will increase the towing resistance and the available towing force will be reduced. The result is a decrease in towing velocity. The available towing force will thus depend on the forces that act on the tug. It is important to note that the mean force will depend on the relative importance 6 Project work TMR 4225 – Marine Operations between the forces on the tug and the barge. Wave drift forces also contribute as a resistant force. The forces that act on the barge may not have the same direction. This has to be considered in the towing of the barge. The interaction between the tug and the barge is important to evaluate in towing operations. This is especially relevant to consider when the towing lines are short. The propeller race will have an effect on the towed structure that will produce an additional towing force. Momentum considerations can be used to estimate the additional forces. By calculating the difference in the flux of momentum of two planes located before and after the water hits the structure, we can make an estimation of the axial force that is working on the body. Model tests should be preformed in order to evaluate the effect of the propeller race on the towed structure in a more precise matter. 3.2.3 Critical issues The climate and oceanographic conditions can cause critical situations in the towing phase. The Ormen Lange field faces a lot of challenges with regard to the climate. Challenging sea and wave conditions demand careful planning of the operation. Some parts of the template might be especially vulnerable to these forces and has to be protected in special ways. Land proximity and near-shore water depth also require great consideration in planning the operation in able to avoid critical situations like stranding and collisions. Directional stability is also important to evaluate in the towing phase. Directional stability is the tendency of a moving body to align itself with the direction of motion. Difficult and critical situations may occur if the barge lacks this stability. The barge will then move uncontrolled and make sudden turns. The reason that the barge may experience loss in direction stability is in many cases because of the length of the towline or the point where it is attached. In able to evaluate the tugs ability to tow the barge in the actual case, it is necessary to understand the dynamics of the situation. Simple calculations can be preformed by illustrating the tug and the barge by two masses which are influenced (acted upon) by time varying accelerations, damping and spring coefficients. The towline can in this analysis be modeled by a spring. The system that is described is very complex and in heavy sea the system will be affected by large forces. 3.3 Installation The installation process starts when the structure arrives at the field where it is supposed to be installed. We can divide the whole process into several minor phases, and we will in the following take a look at each of these phases. 3.3.1 Crane operation Crane operations play an important role in many kinds of marine operations. Examples of these operations are crane assisted installation of jacket structures, installation of deck modules, installation of subsea equipment, and maintenance of subsea equipments. Crane operations are normally divided into two subcategories, light lifts and heavy lifts. 7 Project work TMR 4225 – Marine Operations Lifts where the magnitude of the load is about 1-2% of the vessel displacement and less than a few hundred tons can be classified as light lift operations. The motion characteristics of the vessel can be assumed to be unaffected by the load, and heave compensation is possible for these types of operations. Heavy lifts is typically for loads over 1000tons. For such heavy lifts it is necessary to consider the coupled effect between the vessel and the load system as there will be mutual interaction. It is of great importance to avoid collision between the load and the lifting vessel, as this can lead to damages on both parts. Normally, it is not possible to use heave compensation for such huge loads. Figure 7: SSCV Thialf In our case, the Ormen Lange project, the weight of each template is 1150tons. The vessel involved in the crane operations is “SSCV Thialf”. The crane vessel has a maximum capacity of about 14200tons. This means that the weight should not cause any problems. The dimensions of the templates should not cause problems either since the vessel is able to lift such a weight if the lifting radius is less than 80m, though this depends on the weather conditions.[Heerema] The crane vessel is of great dimensions and can use its ballast system to keep the upper deck stable even in strong winds and rough sea.[metoffice] Unfortunately this doesn’t mean that the vessel can operate under almost any weather condition. As mentioned earlier there will be coupled effects between the crane vessel and the load systems. This means that even if the crane vessel is stable, the barge and the load can be highly affected by winds and waves. Therefore it is of great importance to take weather forecasts and statistics in to consideration when planning such a marine operation. The daily rate for a crane vessel is very high, and a delay will cause huge and unnecessarily costs. 8 Project work TMR 4225 – Marine Operations Figure 8: The template right before lift-off 3.3.2 Water entry A critical part of the installation process is when the template enters the water, also called water entry. In this phase the structure will be exposed to forces caused by wind, waves and currents. These forces may lead to uncontrolled motions such as wire snatch. The hydrodynamic forces working on a body entering the water depends on the downward velocity and the instantaneously submerged volume and added mass. Since the Ormen Lange templates are of such great dimensions, 44[m] x 33[m] x 15[m], there is no doubt that great forces will be acting in the water entry phase. When dealing with such great forces it is very important that the preparations have been done carefully. Figure 9: Water entry 3.3.3 Immersion and landing at the bottom When the entire body has entered the water it has to be placed at the right location at the sea bottom. In this phase the water depth and the currents play important roles. Large water depths cause extreme challenges when it comes to landing in the accurate position. This problem can be solved in different ways. One way is to use guidelines; another is to use ultrasonic equipment. 9 Project work TMR 4225 – Marine Operations If guidelines are not being used, acoustic sound transponders placed on the sea floor can be used for positioning of the template. The speed of sound in water is then used to determine the templates position. This information is transferred to the computers on the surface. As showed in the picture below there is communication between the surface vessel, the ROV and the transponders on the sea floor. In our case, transponders are also present on the template. The transponders are deployed by a ROV using information from to the sea floor mapping. Figure 10: Hydro acoustic transponders A critical issue is the speed of sound. This can influence the acoustic sound transponder for positioning. Several aspects affect the speed of sound in water; the water temperature, the concentration of salt and layer formation. As indicated in chapter 2, the Gulf Stream is affecting the water temperature in the Norwegian sea. Because the temperatures in this area are varying, the speed of sound is constantly changing. The communication between the components must be calibrated correct. The template is equipped with suction anchors. When they hit the sea floor the water inside the cylindrical foundations flows out of a valve that is located on the top. To get the right “suction effect” the valves closes and pumps located inside the foundation legs produce low pressures in the cylinder. This form of anchoring will hold the template in exact position. This is controlled by a ROV. The system is shown in the following figures. Figure 11: The template in detail Figure 12: The suction anchor 10 Project work TMR 4225 – Marine Operations 3.3.4 Critical issues The figure below demonstrates different phases of the crane operation. The mass is located in five different positions in the figure. Several critical issues can be discussed for each phase. Figure 13: Critical issues for crane lift Phase number one represents the lift-off operation. This is when the template is lifted off the barge. A critical issue related to this phase is the possibility of snatch loads. The load can also start to slide horizontal which will cause problems in this phase. This problem can be solved using “tugger lines”. The second phase deals with the situation where the load has been lifted off the barge and is in air. Problems in this phase are the pendulum movement and the possibility of collision. The use of tugger lines can also be effective in this phase. In phase number three in the figure we have the water entry. In this phase the template is crossing the splash zone. Possible problems related to this phase can be dynamical forces caused by waves. This can lead to yank and breakage of the winch and damage to the template. When the template is deeply submerged, as shown in phase number four, problems related to vertical resonance can occur. Landing the template at the bottom can cause severe damage to the template. This is a very critical phase of the operation. 11 TMR 4225 – Marine Operations Project work 4 Vessel involved Several vessels are involved in the operations. In this chapter we have presented the vessels we have used in our discussion. The vessels we have included are involved in the three main phases we have considered; load out, towing and installation. The same vessels are in some cases used in all three phases of the operation. It is important to emphasize that we are only considering the operations that has to do with the operations in close connection to handling of the template. 4.1 Tor Viking II (tugboat) This is the tug that we use for towing the barge. Inshore and in narrow fjords it is necessary to use an additional tugboat in the back of the tow. In these cases the importance of manoeuvrability is increasing. In some cases the tug and barge has a large turning radius. The use of another tugboat can in this case be very effective. Figure 14: Tor Viking II Information: Length Over All (LOA): Length between p.p.: Breadth, moulded: Depth, moulded: Dead Weight: Light Ship: Gross: 83.70 metres 75.20 metres 18.00 metres 8.50 metres 2,528 tonnes 4,289 tonnes 3,382 tonnes 4.2 Boa Barge 21 We need a barge that can handle the templates dimensions of 44x33x15 m and its weight of 1150 tons. Even though the barge is only 31.5 m wide there will no problem because the legs of the template is mounted with distance smaller than 31.5 m 12 TMR 4225 – Marine Operations Project work Figure 15: Boa Barge 21 Information: Description: Deck cargo barge Dimensions: 92 x 31.5 x 6.71m Deadweight: 11 000 t Pumping rate: 1 000 t/hr Deck load: 25 t/m2 Built: 2000 4.3 SSCV Thialf (crane vessel) The heavy-lift operation requires an enormous precision (±1m of design location and ±2 degree of design heading). Thialf and Heerema (owner company) has great experience with heavy-lifts. Their co-operation with Sonardyne which is the developer of the acoustic sound positioning system (skal være nevn under rov-bruk ) makes Thialf number one in the heavylift class. The template is lowered with cabels from Thialf and positioned with the help from the sonar-sound-system. Special for Thialf is the enormous capacity of the ballast pumps, and the use of tandem lift technology. Figure 16: SSCV Thialf Length overall: Length of vessel: Breadth: Depth to workdeck: Draught: GRT: NRT: 201.6 m 165.3 m 88.4 m 49.5 m 11.8-31.6 m 136,709 t 41,012 t 13 TMR 4225 – Marine Operations Project work 4.4 M/S Geobay( ROV-vessel) The Geoconsult ASA’s vessel M/S Geobay is used to assist in the placing of the sound transponders on the sea floor. The transponders are placed on the sea floor with use of a ROV. The M/S Geobay can be used with the ROV mention beneath. Figure 17: M/S Geobay Info: LOA: LBP: Beam: Draught: Gross tonnage: Net tonnage: Service Speed: 85.45 m 78.0 m 15.6 m 6.91 m 3502 ton 1051 ton 11 knots 4.5 Triton XL37 ROV We choose to use this flexible work class ROV. It can be operated in water depths up to 2500m, and has a 150 Hp system with 5 horizontal and 3 vertical thrusters. The ROV is used to place the sound transponders on the seafloor, and have great light and cameras for deep water filming. Figure 18: Trinton XL37 ROV Info: Forward speed: 3 knots 14 TMR 4225 – Marine Operations Project work Lateral speed: Height: Width: Length: Weight (approx.): Operating range: 2 knots 2.10 m 1.80 m 3.00 m 3.7 ton 4,000 m 15 Project work TMR 4225 – Marine Operations 5 Rov and Auv Support In the last few years there have been considerable changes in the oil/gas drilling market. A large difference is that oilfields are found on constantly deeper depths. Marine operations in connection to subsea installations at large water depths (i.e. OrmenLange at 850 m) require complex equipment. Operations that used to be preformed by scuba divers, are now to a large extent replaced by remotely operated vehicles (ROV’s) and autonomous underwater vehicle (AUV’s). 5.1 Mapping and preparing the seafloor It is important to map and establish a model of the seafloor in able to plan the installation operation properly. In our case we use AUV’s as a support at an early phase of the operation. Especially seafloor mapping is preformed by an AUV. Programmed AUV’s can be used to scan the area at interest and get a 3-D picture of the sea floor. In these days it is possible to make a full 3-D model of the installation with the correct sea floor dimension and curvatures. The Ormen Lange field is located at a water depth of approximately 850 m. At large sea depths the seafloor can be very hilly with peaks up to 30-50 meters high. As you can see from the picture below it is important to make a detailed plan for both pipeline survey and positioning of the template. Figure 19: Sea floor topography The template that is being installed has large dimensions (44[m] x 33 [m] x 15[m]). The locations where the templates are installed have to be smooth and horizontal. It is therefore necessary to prepare the seafloor for the installation of the templates. Special designed ROV’s are used for these objectives, like Nexans “Spider dredging system (for pipe laying)”. ROV’s are often used for placing equipments for positioning of the template on the sea floor. This has to be done before the actual installation process begins. 5.2 Template installation During the installation of the template at the sea floor, we can use a ROV for observation. The ROV is equipped with hi-resolutions cameras (often more than one, with different wide angel and focus) and special tool packages. The ROV have arms similar to human arms. The arms can be controlled by the operator located on the surface. For installations of smaller constructions, a ROV can be used for positioning of the object by observation and communication to the surface. A ROV can also be used to push the object. 16 Project work TMR 4225 – Marine Operations Other components and pipelines are design to be mounted on to the template by a ROV. In addition all valves are designed to be operated by a ROV. All operation in respect to inspection and maintenance will be executed by ROV. The template and the complex structure of line units are designed in accordance with the ROV’s ability to operate and maintenance it. The previously mentioned acoustic- sound-sonar system is also compatible with the ROV’s. The ROV communicate with both the acoustic transponders and the surface vessel. ROVs are also used in the pre-phase of the installation, when the transponder is calibrated and mounted on the sea floor. ROV in co-operation with the surface vessel is very important for the accuracy of the installation of the template. With a possible deviation of ±2 meter of design location and ±2 degrees of design location, at a depth of 850 m requires an extreme degree of accuracy. 17 TMR 4225 – Marine Operations Project work 6 Gannt – Chart Most of marine operations are high-cost operations. They often use large crane vessels and a number of support and operation vessels. The daily costs are high and the tasks are often sensitive for wind and waves. Based on this thorough and accurate planning are very important. A key factor is estimating the completion time of operations which include waiting on weather. To start with, the total operation can be divided into sub operations. The sub operations are usually dependent on each other. This means that if one sub operation stops because of the weather conditions the total operation is put on hold. Some sub operations may be performed in parts, and some sub operations are none reversible. If you start a non reversible operation you have to finish the task within the weather window. It is also useful to determine if any of the sub operations may be performed parallel to each other. The total duration for each sub operation and weather waiting time have to be defined. Important key parameters in the planning phase are significant wave height, wave peak period, wave direction, wind speed and wind direction. Norsk Hydro and Metrologisk Institutt have designed a simulation program, Marsim 1.1, for presenting these data graphical. This system can be run both in a hindcast and forecast mode. That means that Marsim is using wave and wind data from systemized observations (hindcast mode), and 3-weeks weather/wave forecast (forecast mode). In this project work we have made the Gannt-chart without the forcast/hindcast, but with respect to the vessel and operations weather limits. We have estimated a rough timescale for the total operation and the sub operations. 15 apr 2007 ID Task Name Start Finish 22 apr 2007 Duration 18 1 Load Out 18.04.2007 18.04.2007 8h 2 Towing 18.04.2007 22.04.2007 96h 3 Positioning and preparation 22.04.2007 22.04.2007 6h 4 Crane Heavy Lift 22.04.2007 22.04.2007 3h 5 Installation on the sea floor 22.04.2007 22.04.2007 6h 19 20 21 22 23 Figure 20: Gannt chart The chart gives the duration in hours. We have chosen to divide the operation in five tasks. All of the tasks are linked to each other and there is no overlapping of the tasks. The durations are based on information from the Ormen Lange project and our own logical assumptions. 18 24 25 26 2 Project work TMR 4225 – Marine Operations The load-out process is scheduled for one ordinary work day (8hours). This operation takes place in sheltered waters and we assume the operation can be completed as long as the weather is not extreme. This task is not very weather sensitive. The towing phase is more critical with regard to the weather. Because of the large size of the template, wind and waves can influence the towing. In this phase the barge cannot withstand significant wave heights larger than 5m. [FinnG] Before the lift-operation can take place all the vessels have to be in perfect position and all equipment has to be prepared and ready for use. The duration is assumed to be 6 hours. This phase is not directly weather dependent. The weather limits in this phase is the same as for the crane lift. It is not necessary to start this task if the crane lift cannot be completed. The crane lift is the most critical task and it is non reversible. You have a point of no return when the template is elevated from the barge. The maximum significant wave height for this operation is 2.5 meters [FinnG] and [Heerema]. It is very important to plan this task, because of the restricted weather window. Use of weather forecasts is an important remedy in the planning. The installation of the template at the bottom has two critical issues regarding the weather. They are water entry for the ROV and influences from currents on the ROV and its umbilical. ROV’s can sometimes enter the water from a moonpool located below the ROV-vessel, or being lowered into the water inside a cage. That will make the weather window wider for this task. The currents close to the template can influence the ROV stability and steering. A solution to this problem can be to select a ROV with several thrusters and more power. 19 Project work TMR 4225 – Marine Operations 7 Use of the DNV Offshore Standard To be sure that we have considered all relevant aspects when planning a marine operation we can follow the DNV Offshore Standard DNV-OS-H101. Most aspects off marine operations, precautions and security factors are included in the standard. We can classify the operations into two groups: Restricted operations, Section 4B 501: “Marine Operations with a reference period (TR) less than 72 hours may be defined as weather restricted.” Unrestricted operations, Section 4B 801: “Marine operations with an operation reference period exceeding72 hours need normally to be defined as unrestricted operations. Environmental criteria for these operations shall be based on extreme value statistics.” Categorizing of the operations in our case: Restricted operations: Load-out, crane operation, water entry, immersion and landing at the bottom. Unrestricted operations: Towing The standard covers all of these operations and is important for the whole marine operation. In this report we take a closer look at the points in the standard that is relevant to the case we are analysing. In our analysis we have focused on the crane operation. As mentioned earlier it is important to evaluate the effects of wind and waves during lift and how it interrupts the stability of the barge and crane vessel. We have considered the following paragraphs in our analysis: Section 2A203: “For operations passing a point where the operations can not be reversed, a point of no return shall be defined. The first safe condition after passing a point of no return shall be defined and considered in the planning.” In our operation we consider it to be a point of no return when the template is lifted off the barge and the barge is removed. At this point the operation can not be reversed. A safer condition is when the template is fully submerged and at a depth where the largest surface effects can be neglected. Section 3B: Wind Conditions and Section 3C: Wave Conditions. We have to map the weather in the area where the operation is to be executed. Wind and waves are factors that decide if the operation is to be carried out. The lift operation has to be planned according to this section. Section 4C200 Weather forecast levels: This paragraph divides different operations into forecasts levels. The categorisation for our operation phases will be: Level B: Towing, installation, lifting Level C: Load-out. Section 4B600: Operational limiting criteria. 20 Project work TMR 4225 – Marine Operations We have to follow these paragraphs and decide the design value of the significant wave height. We do not have enough information to calculate this value at this point, but we use the wave statistics from the area and estimate a design value for the significant wave height (Limiting operational criteria). OPLIM= 2,5m Section 4B701: Forecasted- and monitored operational limits: “Uncertainty in both monitoring and forecasting of the environmental conditions shall be considered. It is recommended that this is done by defining a forecasted (and if applicable, monitored at the operation start) operational criteria – CO, defined as CO= α* OPLIM.” We correct the significant wave height with the alpha factor in order to consider uncertainty in the weather forecasts. The alpha factors can be found in the last appendices in the DNV standard. We have in our crane vessel a monitoring system which applies to the DNV standard for the monitoring, in section 4D300. And our crane lifting operation has duration of 3 hours. That gives: α = 1.0 CO = 1.0 * 2,5m= 2,5m. If the weather forecast announces a wave height of 2,5m or larger the operation will not be preformed. Section 5 Stability requirements: This chapter deals with the stability of the vessels involving the operation. Section 5D201: “Other vessels, semi submersibles, crane vessels etc, involved in marine operations shall, for both intact and damaged conditions, comply with national or international (IMO) stability regulations or codes” The stability of the vessels involved in the operation has to be calculated before the operation is started to make sure that the vessels can handle the load. From the statistics we have found that the waves in the weather window we are considering for the operation, the period of the waves lies between 4 and 13 seconds, more details can be found in Appendix D. This means that if the response curve shows large motions in this area, significant motions may occur, and extra precautions must be made. 21 Project work TMR 4225 – Marine Operations 8 Dynamic model for crane vessel and load We have decided to look more detailed into the installation phase, and the lifting operation of the template. The template is lifted from the barge and then lowered to about 800 meters below the surface. We want to compare the coupled motion of the vessel and the template hanging in air versus the template submerged to the sea. This can be modeled as a coupled mass- damping- spring system. The system has 12 degrees of freedom, but neglecting the rotations of the load gives us 9 DOF. By solving the equation Mx Bx Cx F for each DOF, we can find the eigenperiods and eigenvalues for the system. To solve the equation of motion, we need to estimate the mass-, damping- and restoring forces for each DOF. That will require some detailed data about the crane vessel and template. The mass matrix consists of mass and added mass in the translation directions and moments of inertia and added mass in the rotation directions. Since we have few data about the crane vessel, it is difficult to get a good estimate of the components in the matrix. Thus we need to make some assumptions and simplifying the matrix. The coordinate system is placed with the origin in the waterline, above the centre of gravity. We may assume the vessel to be symmetric along the x-axis, which make the components A23 A13 0 . Still there are some couples added mass contributions in the other directions that will affect the motion of the vessel, but we choose to exclude these contributions. The coupled moments of inertia are also excluded. Finally we get the following mass matrix: 0 0 0 mzG A15 0 0 0 0 m A11 m A22 0 mzG 0 0 0 0 0 m A33 0 0 0 0 0 0 I 44 A44 0 0 0 0 0 M I 55 A55 0 0 0 0 I 66 A66 0 0 0 mL A77 0 0 mL A88 0 mL A99 Figure 21: Mass matrix The definitions of the notations used are placed in appendix A. The stiffness matrix of the system is a sum of three different contributions, where stiffness and mooring on the vessel, and stiffness between the load and template are the parts. The hydrostatic stiffness is a result of change in location and size of buoyancy. That gives hydrostatic stiffness contribution inn heave-, roll- and pitch directions, since motion in these directions will change buoyancy. Mooring will also have some contribution, but usually the mooring stiffness is soft and will not influence on the resonance periods. If the vessel uses a DP system, this can be modeled in the same way as a mooring system. It is also natural to neglect mooring effects in vertical directions. With a DP-system this is evidently because the thrusters don’t have a thrust component in the z-direction. Thus DP-system gives contribution in surge, sway and yaw directions. The mooring and hydrostatic stiffness for our system may be gives as: 22 TMR 4225 – Marine Operations Project work Cm11 Cm12 Cm 22 Cv 0 0 Ch 33 0 0 Ch 34 Ch 44 0 0 Ch 35 0 Ch 55 Cm16 Cm 26 0 Ch 46 Ch 56 Cm 66 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Figure 22: The mooring and hydrostatic stiffness In addition to the hydrostatic and mooring a stiffness related to the coupling between the template and vessel will occur. This stiffness may be written as: w l s Cvt 0 0 w ls 0 AE le w zt ls 0 w zt ls 0 AE yt le Cvl 44 AE xt le w yt ls w ls 0 w xt ls 0 0 0 0 0 w zt ls AE xt yt le w zt xt ls Cvl 55 w zt yt ls Cvl 66 w zt ls w yt ls w ls w ls 0 w xt ls 0 w ls 0 AE le AE yt le AE xt le 0 0 0 AE le 0 Figure 23: Coupled vessel-template stiffness The total stiffness of the system is the sum of mooring and hydrostatic stiffness and the coupled vessel-template stiffness. When we should do the analysis with the load hanging in the air, we first had to change some of the coefficient in the matrices. When the load is hanging in the air the added mass term can be neglected because of the low density of air compared to the mass. Therefore we sat these 23 Project work TMR 4225 – Marine Operations values equal to zero. In addition to this change we also had to change the values for stretch in the wire. Out of water there will be no buoyancy force working on the load, so we had to set the buoyancy force equal to zero too. Further we had to reduce the length and effective length of the wire so that the length of the wire is shorter than the distance from the top of the crane to the surface. The last thing we did was to set the forces that are working directly on the load equal to zero. This is because of the assumption that there is light wind when the operation is performed. 8.1 Calculation of eigenperiods and responses With mass and stiffness matrixes established we can compute the undamped eigenfrequencies and eigenvectors. The eigenfrequencies are given from, 0 M 1C , where M is the mass matrix and C is the stiffness matrix. The eigenvectors can be solved from the equation: x M 1Cx The eigenvectors tells us which degree of freedom that gives us contribution for the given eigenperiod. With a coupled system there will be many degrees of freedom that have a contribution. For each eigenperiod we can identify the degree of freedom that has the main contribution. In the case with the template hanging in the air, we get the following eigenmodes: Table 1: Response in air 24 TMR 4225 – Marine Operations Project work The case with the template hanging in the water gives the following eigenmodes: Table 2: Response in water For each eigenmode we have located the degree of freedom that gives the main contribution. When comparing the two cases we see that the most of the eigenperiods doesn’t change much. The greatest changes are in yaw-, load vertical-, load x- and load y-direction. This can be explained by the change inn mass- and stiffness matrix, where the template has got a contribution. If we look at eigenmode nr 9, we see that the motion has a connection to the load y-direction as well as the yaw-direction, and results in large period when changing the mass- and stiffness matrix. The eigenperiods that belongs to the load-directions are motions that are almost pure freedom of degree motions. That means that the eigenperiod of the motions are mainly dependent of the change of stiffness and mass related to that direction. When lowering the template below sea surface, the mass matrix gets a contribution from added mass in all directions. In addition the coupled stiffness matrix will decrease due to buoyancy of the template and a longer cable. This will result in larger periods, as the eigenperiod is given by: M T 2 C With the eigenperiods and eigenvectors established, we want to see what happens when adding a force vector to the system. We have looked at a sea state that gives beam sea on the crane vessel. The force is modelled as a harmonic load in the heave-, sway- and roll direction. We have based the force on the potential theory, but in lack of vessel data it’s, the wave force is simplified. In addition, forces on the template are ignored. This means that wind and wave forces that may occur are neglected on the template. We have used the following force vector for both cases: F Re 0 i * C22 C33 C33 * B 2 0 0 0 0 0 * eit We may no solve the response for the system, given by: 2 M i B C F 1 25 TMR 4225 – Marine Operations Project work The responses are solved and plotted as a function of the wave period. 8.2 Dynamic response Further we have plotted the responses inn all directions for case 1 and case 2. For each plot the peak periods are located, and we have compared the peak periods with the eigenperiods. Thus we can find the dominating motion that causes the responses for each direction. 8.2.1 Template hanging in the air Dynamic respons in direction 1 0.4 0.35 0.3 Respons 0.25 0.2 0.15 0.1 0.05 0 0 5 10 15 20 Periode 25 30 35 40 Figure 24: Dynamic response in direction 1 Peak periods: Related Eigenmode: Dominating mode of motion: 17,5 sec, 19,7 sec. 4, 6 pitch, heave Dynamic respons in direction 2 3.5 3 Respons 2.5 2 1.5 1 0.5 0 0 10 20 30 40 50 Periode 60 70 80 90 100 Figure 25: Dynamic response in direction 2 Peak periods: 17,5 sec, 21,7 sec, 62,5 sec. 26 TMR 4225 – Marine Operations Project work Related Eigenmode: Dominating mode of motion: 4, 8, 7 pitch, roll, sway Dynamic respons in direction 3 12 10 Respons 8 6 4 2 0 0 10 20 30 Periode 40 50 60 Figure 26: Dynamic response in direction 3 Peak periods: Related Eigenmode: Dominating mode of motion: 19,7 sec. 6 heave Dynamic respons in direction 4 0.14 0.12 Respons 0.1 0.08 0.06 0.04 0.02 0 0 10 20 30 40 50 60 70 Periode Figure 27: Dynamic response in direction 4 Peak periods: Related Eigenmode: Dominating mode of motion: 19,1 sec, 21,7 sec 9,8 load y-direction, roll 27 TMR 4225 – Marine Operations Project work Dynamic respons in direction 5 0.04 0.035 0.03 Respons 0.025 0.02 0.015 0.01 0.005 0 0 5 10 15 20 25 Periode 30 35 40 45 50 Figure 28: Dynamic response in direction 5 Peak periods: Related Eigenmode: Dominating mode of motion: -4 17,5 sec, 19,1 sec, 20,1 sec. 4, 9, 5 pitch, load y-direction, load x-direction Dynamic respons in direction 6 x 10 5 Respons 4 3 2 1 0 0 10 20 30 40 50 60 70 Periode Figure 29: Dynamic response in direction 6 Peak periods: Related Eigenmode: Dominating mode of motion: 5,3 sec, 19,1 sec, 21,7 sec. 4, 8, 7 yaw, load y-direction, roll 28 TMR 4225 – Marine Operations Project work Dynamic respons in direction 7 110 100 90 80 Respons 70 60 50 40 30 20 10 0 0 5 10 15 20 Periode 25 30 35 40 Figure 30: Dynamic response in direction 7 Peak periods: Related Eigenmode: Dominating mode of motion: 20,2 sec. 5 load x-direction Dynamic respons in direction 8 100 Respons 80 60 40 20 0 0 10 20 30 40 50 60 70 Periode Figure 31: Dynamic response in direction 8 Peak periods: Related Eigenmode: Dominating mode of motion: 19,1 sec, 21,7 sec, 62,5 sec. 9, 8, 7 load y-direction, roll, sway 29 TMR 4225 – Marine Operations Project work Dynamic respons in direction 9 11 10 9 8 Respons 7 6 5 4 3 2 1 0 0 10 20 30 Periode 40 50 60 Figure 32: Dynamic response in direction 9 Peak periods: Related Eigenmode: Dominating mode of motion: 17,5 sec, 19,7 sec. 4, 6 pitch, heave 8.2.2 Template submerged Dynamic respons in direction 1 0.4 0.35 0.3 Respons 0.25 0.2 0.15 0.1 0.05 0 0 20 40 60 80 100 120 Periode 140 160 180 200 Figure 33: Dynamic response in direction 1 Peak periods: Related Eigenmode: Dominating mode of motion: 17,7 sec, 36 sec, 161 sec. 4, 8, 7 pitch, load y-direction, surge 30 TMR 4225 – Marine Operations Project work Dynamic respons in direction 2 4.5 4 3.5 Respons 3 2.5 2 1.5 1 0.5 0 0 10 20 30 40 50 Periode 60 70 80 90 100 Figure 34: Dynamic response in direction 2 Peak periods: Related Eigenmode: Dominating mode of motion: 20,6 sec, 36 sec, 62,5 sec. 6, 3, 7 roll, load x-direction, sway Dynamic respons in direction 3 16 14 12 Respons 10 8 6 4 2 0 0 5 10 15 20 25 Periode 30 35 40 45 50 Figure 35: Dynamic response in direction 3 Peak periods: Related Eigenmode: Dominating mode of motion: 19,7 sec, 5 heave 31 TMR 4225 – Marine Operations Project work Dynamic respons in direction 4 0.25 0.2 Respons 0.15 0.1 0.05 0 0 10 20 30 40 50 60 70 Periode Figure 36: Dynamic response in direction 4 Peak periods: Related Eigenmode: Dominating mode of motion: 20,6 sec, 36 sec. 6, 8 roll, load y-direction Dynamic respons in direction 5 0.07 0.06 Respons 0.05 0.04 0.03 0.02 0.01 0 0 5 10 15 20 Periode 25 30 35 40 Figure 37: Dynamic response in direction 5 Peak periods: Related Eigenmode: Dominating mode of motion: 17,6 sec, 19,7 sec, 36 sec. 4, 5, 3 pitch, heave, load x-direction 32 TMR 4225 – Marine Operations Project work Dynamic respons in direction 6 0.1 0.09 0.08 0.07 Respons 0.06 0.05 0.04 0.03 0.02 0.01 0 0 100 200 300 400 500 600 Periode 700 800 900 1000 Figure 38: Dynamic response in direction 6 Peak periods: Related Eigenmode: Dominating mode of motion: 20,6 sec, 36 sec, 62,5 sec, 938,6 sec. 4, 8, 7, 9 roll, load y-direction, sway, yaw Dynamic respons in direction 7 9 8 7 Respons 6 5 4 3 2 1 0 0 20 40 60 80 100 Periode 120 140 160 180 Figure 39: Dynamic response in direction 7 Peak periods: Related Eigenmode: Dominating mode of motion: 17,7 sec, 19,7 sec, 36 sec, 161,2 sec 4, 5, 3, 2 pitch, heave, load x-direction, surge 33 TMR 4225 – Marine Operations Project work Dynamic respons in direction 8 70 60 Respons 50 40 30 20 10 0 0 10 20 30 40 Periode 50 60 70 80 Figure 40: Dynamic response in direction 8 Peak periods: Related Eigenmode: Dominating mode of motion: 20,6 sec, 36 sec, 62,5 sec. 6, 8, 7 roll, load y-direction, sway Dynamic respons in direction 9 12 10 Respons 8 6 4 2 0 0 5 10 15 20 25 Periode 30 35 40 45 50 Figure 41: Dynamic response in direction 9 Peak periods: Related Eigenmode: Dominating mode of motion: 17,7 sec, 19,7 sec. 4, 5 pitch, heave 34 Project work TMR 4225 – Marine Operations 8.3 Comments In the following sections we will discuss the results, possible improvements and further work. 8.3.1 Results When developing the MATLAB routine we based the calculations on the matrices defined in the lecture notes, [FinnG] These matrices are a bit simplified by assuming y=0 as a plane of symmetry and neglect insignificant terms. From this we assume that the model will give us good results if it is followed. In our case we defined all the terms, but when we should give them values we made some simplifications. Some of our simplifications are questionable, some of them might not be very accurate. Based on this it is clear that we would not get results of scientific standard. Even tough the results are not 100% correct we feel that the results give us a good indication of how the motions between the load and the vessel are coupled. This is because when we calculated and plotted the dynamic response for each DOF, we saw that the response curve had peaks at periods which responded to the eigenperiod for motions that seems natural to have an impact on the actual DOF. Even if the results give us an approximation of how the motions are coupled, some of the values for the eigenperiods and the responses seem to be unrealistic, for example the eigenperiod for load in water where the yaw motion is dominating. We assume that this comes from the simplification we have made, and that further work with finding more accurate values for the terms in the matrices, will give us better results. When we looked at the wavestatistics (Appendix D) for the summer period, we save that most of the registered waves had periods between 4 and 13 seconds. From the calculation of the eigenperiods we found that it is only the yaw-dominated period for the template in air that lies in this interval. From the response curve we saw that there were not any motions with significant values in the same region, so from this we can say that wave periods should not cause any problem. 8.3.2 Improvements Improvements will be to find out if the neglecting of terms will give us satisfactory results. We can also extend our work by finding more realistic values for the estimated terms. Many of these terms are defined by very complicated formulas, and for some of them model tests will be required for accurate results. Model testing is out of the question for our project due to the time-demand required. In addition, the information we need are most likely restricted and therefore not available. This leaves us with estimating the terms, and good estimations often demand a certain amount of experience, which again demands a lot of time. Since this analysis is just a part of the whole project, we decided to go on with the chosen values. Although we know that the correctness of these values might be questionable. 8.3.3 Further work When we have got sufficient results these can used to perform further calculations. By taking wave data in consideration, we can for example calculate the probabilities for resonance of the coupled system during the actual period in time. 35 Project work TMR 4225 – Marine Operations 9 Feasibility of the operation Since we have based our project on a real marine operation, the Ormen Lange project, there is no doubt that such operations are feasible. The installations at the Ormen Lange field was succesfull. There is no doubt that the Ormen Lange project has faced a lot of challenges. Two years was used for planning the installation phase[Hydro2]. When it comes to our project and our calculations, several improvements can be done. This has been commented in the previous chapter. The importance off planning the operations in great detail is indicated throughout our project. The Ormen Lange project is a very good example of this. 36 Project work TMR 4225 – Marine Operations 10 Kilder Websites: [Hydro1] http://www.hydro.com/ormenlange/en/about_ormen/facts_and_figures/index.html [Hydro2] http://www.hydro.com/no/press_room/news/archive/2005_09/templates_no.html [Hydro3] http://www.hydro.com/ormenlange/en/concepts_solutions/well_design/index.html [Map1] http://www.hydro.com/ormenlange/no/about_ormen/ormen_map.html [Map2] http://www.hydro.com/ormenlange/no/about_ormen/key_features/storegga_slide/ index.html [Water1] http://www.hydro.com/ormenlange/library/attachments/massive_gas_no.pdf [Water2] http://www.hydro.com/ormenlange/no/concepts_solutions/import_pipelines/ index.html [Golf]http://no.wikipedia.org/wiki/Golfstr%C3%B8mmen http://www.hydro.com/ormenlange/no/media_room/news/2005_03/ol_status_no.html http://hydro.no/no/press_room/news/archive/2005_08/templates_recorddeep_no.html http://www.grenlandgroup.com/CMS/CMSpublish.nsf/$all/F6DF9F14C3901B16C1256FDD0 0663656?open&qm=MainMenu,3,12,0 [Heerema] http://hmc.heerema.com/Default.aspx?tabid=437 http://www.vikingsupply.com/vess_tor_spec.asp http://www.vikingsupply.com/barges.asp http://hmc.heerema.com/Default.aspx?tabid=437 http://www.sonardyne.co.uk/News/PressReleases/2005/ormenlange.html http://www.sonardyne.co.uk/News/Newsletters/subsea_newsletter_2004.pdf http://geoasa.no/publish_files/PerryTritonXL37rev_03.2006.pdf [metoffice]http://www.metoffice.gov.uk/research/nwp/publications/nwp_gazette/dec01/nwp.h tml Literature: [FinnG] Lecture notes in marine operations by Finn Gunnar Nielsen. January 2007. Vindatlas for Nordsjøen og Norskehavet- Jan Aske Børresen Global wave statistics (complied and edited by British Maritime Technology limited), Primary contributors: N. Hogben, N. M. C. Dacunha, G. F.Olliver, Published for British Maritime Technology by Unwin Brothers Limited. 37 TMR 4225 – Marine Operations Project work Appendix A: Model of the template, and definitions of notations A model of the crane vessel with the template is showed below. We have used the following notations when establishing the equations: m: V: Mass of vessel Displaced volume of the vessel mL : Mass of load Aij : Added mass of vessel x G , yG , z G : Centre of gravity of vessel coordinates x B , yB , zB: Centre of buoyancy of vessel coordinates x t , yt , zt : Top of crane coordinates ls : Length of hoisting wire (From centre of load to top of crane) le : Effective length of wire VL : Submerged volume of load w=m L lg- gVL : Submerged weight of the load a ij: Added mass of the load AE: I nn : Stiffness of wire per unit length Moments of inertia Appendix B: MATLAB routine “waterresponse.m” Please see attached files. Appendix C: MATLAB routine “airresponse.m” Please see attached files. A Project work TMR 4225 – Marine Operations Appendix D: Wave statistics B