Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 Operator Installation Address UK Coal Mining Limited Huntington Lane Surface Mine Site (SMS), New Works, Telford, Shropshire TF6 5AP Grid Reference Registered Office UK Coal Mining Ltd Harworth Park Blyth Road Harworth Doncaster South Yorkshire DN11 8DB UK Coal Limited is hereby permitted by Telford & Wrekin Council to carry on coal processing under Section 3.5 of Schedule 1 Part 2 the Environmental Permitting (England & Wales) Regulations 2010 (as amended), and other activities as listed and described below within the installation boundary marked red on the attached plan on page 15, and in accordance with the following conditions. Provenance Date Application Made (Deemed application) Date ‘Duly Made’ Date Permit First Issued Date of Variations Date of Latest Variation Relevant Dates 27.04.10 07.05.10 17.11.10 None None This permit consists of 22 numbered pages Page 1 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 Description of the Installation The installation consists of a Surface Mine Site (SMS) where coal is extracted, crushed and graded to produce appropriate specifications. The mine comprises several basic elements, removal of coal from the rock strata (referred to as ‘winning’), crushing and size reduction, and transportation of coal within the site. The application included the operation of a coal washing plant where spoil is washed in order to reclaim further coal product, however technical difficulties on site may make this non viable. Coal washing therefore is not included in the permit at this time. The following text divides the Installation into its elements and activities both those scheduled under the above regulations and those non scheduled elements required to be regulated because of their polluting potential and that have a direct association and a technical connection to the scheduled activities: 1– 2– 3– 4– 5– 6– 7– The extraction of coal element The coal transportation activity The coal crushing and screening activity The coal storage element The load-out activity The waste treatment element. Water storage and treatment. 1. The extraction of coal element (winning the coal). The Surface mine site extracts shallow coal seams for the supply of high quality low sulphur coal for electricity generation at local power stations. The predominant method of extracting coal from the coal seam is through the use of hydraulic excavators. These vehicles are used to excavate the coal and load directly into dump trucks for internal transport to the coal processing area. However it is expected that limited blasting will be required onsite depending on localised geological conditions. Hard rock (i.e. Sandstone) is broken up to aid extraction using propriety explosives with blasting restricted to weekdays between 10.00 and noon (no blasting is carried out at weekends). After the explosives are detonated the won coal is then collected by back actor and transported to the coal processing area by dump trucks. Controls on the noise and vibration from blasting are present within the planning decision notice and not regulated by this permit. The winning of the coal is an element of the mining installation and is technically connected and directly associated with the activities falling within Schedule 1 of the Environmental Permitting (England and Wales) Regulations 2010. Page 2 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 2. Coal transportation Activity Extracted coal is loaded by hydraulic excavators into dump trucks and transported along a haul road to the processing area. In situ coal is transported to the coal process area and placed in stockpiles for storage. Vehicles entering and leaving the installation travel on haul roads surfaced with compacted backfill material, this is regularly graded to remove loose, dust generating materials and in times of dry weather are kept damp at all times if necessary by the use of a mobile water bowser. The haul road in extraction area A is constructed 3 metres below the adjacent backfilled overburden to maximise the wind sheltering effect and prevent wind whipping of dust. The main access and egress of the site up to the coal processing area is surfaced by tarmcadam; therefore all road going traffic including Lorries would not travel over any unsurfaced areas, thus minimising dust and mud being deposited on the public highway. Road transport coal carrying vehicles pass through a wheel and under body vehicle wash (where necessary) before being taken to the weighbridge where any overweight will be off loaded onto the overweight bay. All coal Lorries leaving the site are sheeted prior to leaving the site. The coal transportation activity of the mining installation and is technically connected and directly associated with the activities falling within Schedule 1 of the Environmental Permitting (England and Wales) Regulations 2010. 3. Coal crushing and screening Activity. Oversized coal requires size reduction before being ready for transportation off site. This is conducted by use of a crusher and associated screen. The crushed coal from the crusher and screen is collected and moved to stockpile by front loading shovel. The resulting size reduced material is then stored for transportation offsite. Coal of varying qualities, may be blended to coal stocks as required. Dust is controlled by enclosure of machinery and the application of water via sprinklers to the primary hopper, the primary jaw crusher and the discharge point from the primary crusher onto the screen. The crushing and size reduction of coal is an activity falling within section 3.5 of Schedule 1 of the Environmental Permitting (England and Wales) Regulations 2010. 4. Coal storage element. The following permanent stockpiles designated as such in Plan PPC10/00009/3 are used within the process to store coal that is either waiting further processing or is final product waiting for transport off site. Page 3 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 Primary excavated Coal Stock Pile Crushed Coal Stock Pile Blended Coal Stock Pile Fugitive emissions from stockpiles of wind raised dusts particularly at the time of disturbance of the stored coal during addition or removal of stored materials will be minimised by addition of water. The coal storage element of the coal processing installation and is technically connected and directly associated with the activities falling within Schedule 1 of the Environmental Permitting (England and Wales) Regulations 2010. 5. The Load out activity. Coal is taken from stockpile and placed into road going Lorries by front loading shovel. Fugitive emissions are of dust from the handling of the coal, release of dust by the wheels of vehicles. Dust control is achieved through water suppression and regular sweeping of roadways and yard areas. The load out activity falls within section 3.5 of Schedule 1 of the Environmental Permitting (England and Wales) Regulations 2010. 6. Waste storage Element. Very little waste is produced within the Installation; waste produced at the coal processing stage shall be disposed of complying with current relevant waste legislation. The waste storage element of the quarrying installation and is technically connected and directly associated with the activities falling within Schedule 1 of the Environmental Permitting (England and Wales) Regulations 2010. 7. Water Storage and Treatment Element. Storm water drainage from disturbed areas is managed by 3 water treatment areas. These consist of a system of primary and secondary treatment lagoons where solid materials are removed by settlement. The resulting water is utilised onsite for dust suppression. Stored water is used on the site as a primary means of suppressing dust. The water supply for the plant will be from site storage of storm water collected, this will be utilised by equipment as required and dust suppression water bowsers as necessary. Page 4 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 Process flow chart In situ coal dug and loaded into site wagons In situ coal stocked prior to crushing and sizing Coal loaded into crusher and associated screening plant Crushed coal stockpile Blended Coal stockpile Coal loaded into road wagons Any significant increase in the figures listed in Table 1, in the opinion of the regulator, results in detrimental consequences for the environment will require the operator to apply for a variation to the permit. Table 1 – Raw material usage The following table lists the quantities of raw materials used on an annual basis within the permitted installation. Raw Material Coal Usage (year) (tonnes/annum) 300,000 Fire clay Activity/Element 1, 2, 3, 4, 5 1 Control Water suppression Water suppression Page 5 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 Table 2 contains a list of all machinery used within the installation along with the identified emission points to atmosphere: Table 2. List of machinery within the Installation Plant and equipment Back-actor 1m3 capacity Front loading Shovel 1m3 capacity Drilling rig dust extraction Dump truck 35m3 capacity Loading shovel 4m3 capacity Primary crusher Water bowser and tractor Number of vehicles 4 2 Activity/Element 1 1, 2 8 2, 3, 4 4 3, 4, 5 1 2 3 1, 2, 3, 4, 5, 6 Emission Dust, Smoke Dust, Smoke Dust, Smoke Dust, Smoke Dust, Smoke Dust Dust, Smoke NOX, NOX, NOX, NOX, NOX, NOX, Table 3 Identity and function of stockpiles The following is a list identifying Stock piles and relating them to the plan Stock pile Purpose Location Primary excavated Coal Storage of coal before crushing or With excavation Stock Pile transportation area and Coal processing area Crushed Coal Stock Pile Storage of coal before mixing with Coal processing washed coal or transportation area Blended Coal Stock Pile Storage of final coal product Coal processing before transportation area Page 6 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 Permit Conditions 1.0 Authorised Plant 1.1 The permissible plant or equipment to be used within the installation shall be that mentioned in Table 2. No other plant or equipment shall be used without the prior written consent of the regulator. 1.2 The operator shall notify the regulator at least one week before the commencement of each phase of mining. 2.0 Emission Limits and Controls 2.1 There shall be no visible emissions of dust beyond the designated installation boundary marked on PPC10/00009/2 as perceived by the regulator. 2.2 Not withstanding condition 2.3, emissions from the installation, other than steam or condensed water vapour, shall be free from persistent mist and free from persistent fume. 2.3 Packaging materials that have been used to package explosives may be burned in the open provided such burning is done in accordance with the requirements of the Control of Explosives Regulations 1991. 2.4 Emissions from any vehicles or stationary plant with a combustion engine shall, not, in normal operation, exceed the equivalent of Ringleman shade 1 as described in British Standard BS 2742:1969. 2.5 Emissions from the installation, at the locations stipulated shall not exceed the limits set out in table 4 below. Table 4 Emission limit of dust Monitoring Location Lower Huntington Farm Western End of Plant Bay Eastern End of Coal Processing Area New Works Farm The Uplands Monitoring Method Sticky Pad Method Sticky Pad Method Sticky Pad Method Sticky Pad Method Sticky Pad Method Phase Frequency All Phases Weekly All Phases Weekly All Phases Weekly All Phases Weekly All Phases Weekly Limit 0.5% EAC/day 2% EAC/day 2% EAC/day 0.5% EAC/day 0.5% EAC/day Page 7 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 Table 4 (Continued) Emission limit of dust Monitoring Location Fairhaven Rozel Site boundary near T7 Monitoring Method Sticky Pad Method Sticky Pad Method Sticky Pad Method Phase Phase onwards Phase onwards Phase onwards Frequency 2C Weekly 2C Weekly 2C Weekly Limit 0.5% EAC/day 0.5% EAC/day 2% EAC/day Note: Continuous Emission Monitoring collected in accordance with condition 5.1 can be required at any of the above locations. 3.0 Emission monitoring 3.1 Whenever the Installation is operating it shall be observed for dust emissions at least once daily by a person appointed for this purpose or more frequently as may be prescribed in writing from the regulator. The place of observation shall provide an unimpeded view of all emission points, and, as necessary from the installation boundary. 3.2 A logbook shall be maintained which shall record the date, time, name and position of the person making the entry and all operations and actions taken in accordance with conditions of this permit. Also entered shall be details of the weather prevailing on every day that the mine operates to include an assessment of maximum wind speed, wind direction, temperature and the presence or absence of rain on the day of the record. These records shall be kept for a minimum period of 2 years and may be in an electronic format provided that a secure backup of the data is made and the information can be printed onto paper. 3.3 A weather station shall be installed onsite to monitor wind direction and wind speed on a continuous basis. The details (with data averaged over 30 minute periods) shall be recorded and kept onsite. 3.4 In the event of abnormal emissions, adverse monitoring results or a complaint from a member of the public the operator shall: Investigate the occurrence immediately In the event of a complaint from a member of the public assess whether the complaint could potentially relate to specific site conditions Adjust or stop the process or activity to minimise those emissions Undertake remedial work as soon as practical or before operation resumes after a scheduled shut down Page 8 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 Record the details of the cause and consequent action in the Logbook. Report to the Regulator as soon as practicable 3.5 Dust deposition monitoring shall be completed using the sticky pad method at locations detailed in table 4. The sticky surface media shall be exchanged on a weekly basis or at a frequency agreed in writing by the regulator. The sticky pad method and result obtained shall be in accordance with a method agreed with the regulator. Results shall be retained onsite for a minimum of 2 years. 3.6 The obscuration of the film of the sticky cylinder shall be analysed as a measure of dust deposition. The obscuration of the dust shall be expressed as percentage Effective Area Covered (EAC) per day. 3.7 The results of dust deposition monitoring including details of the prevailing weather conditions at the time shall be forwarded to the regulator upon request. A summary of the data shall be submitted to the regulator monthly. 3.8 Dust deposition monitoring utilising other methods and techniques shall be carried out as agreed with the regulator. 3.9 Areas around conveyors shall be inspected daily for overspill of material. Any overspill shall be removed and the area cleaned to prevent wind whipping of dust within 24 hours. 4.0 Process controls 4.1 At all times when the primary crusher is operational it shall be supplied with water to operate the dust suppression sprinklers, this supply shall be protected from freezing by adequate frost protection. 4.2 All plant and equipment shall be appropriately sized to reduce dust generation during loading and unloading of coal. 4.3 All drop heights of conveyed or excavated material shall be kept to a minimum during loading operations. 4.4 Spillages of finely divided or powdery materials shall be cleaned up immediately by vacuum cleaning using an industrial grade vacuum cleaner or by wet cleaning methods. Dry sweeping methods shall not be permitted. Sweeping and movement of powdery materials using uncovered containers is prohibited unless the material is thoroughly damped to prevent wind entrainment. Page 9 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 Conveying of materials 4.5 All conveyors shall be totally enclosed, or be situated within an enclosed building. 4.6 Belt scrapers shall be fitted to the head drum returns of all conveyors and the scrapings shall fall by enclosed chute to join the main material run. Stockpile management 4.7 All permanent uncontained stocks of crushed and processed coal shall be stored in the coal processing area designated on Plan PPC10/00009/3 and nowhere else within the installation. Any change to this plan shall be agreed in writing with the regulator 4.8 All coal product storage areas shall have a consolidated surface which should be kept in good repair. 4.9 Stockpiles shall be clearly delineated to deter vehicles from running over coal at the stock edge. 4.10 Stockpiles, stocking areas and roadways shall be managed to prevent wind entrainment of dust, such methods to be employed (as necessary) are: Aerodynamic profiling Compaction of stockpile Water suppression (by fixed system or water bowser) Addition of dust suppressants Fencing or bunding Strategic arrangement of stock piles comprising different sized materials Control of dust from roadways 4.11 Internal coal haul roads not constructed incorporating a Tarmacadam surface shall be regularly graded to remove loose dust generating materials and shall at all times, where necessary, be kept damp to prevent wind entrainment of dust. 4.12 All coal roadways surfaced with tarmaccadam or concrete shall be kept clean by the use of a road sweeper using irrigated brushes and where necessary kept damp to prevent wind entrainment of dust. No dry sweeping is to be carried out on site. 4.13 All Dusts arising from activities within the installation that cannot be recycled shall be considered wastes and be placed in covered containers. Page 10 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 4.14 Effective under-vehicle and wheel washing facilities shall be provided and used where necessary before vehicles exit the site on to the public highway. 4.15 All road going coal laden vehicles, or vehicles carrying other dusty materials, shall be effectively sheeted or the material should be stored in sealed containers prior to departure from site. 5.0 Air Quality 5.1 Continuous particulate monitoring of PM10 and PM2.5 size fraction dust shall be conducted as per table 5. The Continuous emission monitors (CEM’s) shall have an alarm set at the 1 hour average AQO limit for PM10 as detailed in table 5. Any breach of that limit shall alert onsite personnel via telemetry link. Any activated alarms shall be recorded, investigated and reported to the Regulator within 48 hours. Table 5 Air Quality Monitoring Monitoring Location Rose Villa* Lower Huntington Farm* The Uplands* New works Lane Junction* Monitoring Method Topas Osiris Osiris Osiris Phase of mining All phases Phases 1/2A Frequency AQO Limit Continuous Continuous Annual mean PM10 40 µg m-3 Pm2.5 25 µg m-3 Phases Continuous 2A/2C Phases 2D-3 Continuous 24 hour mean PM10 50 µg m-3 1 hour average trigger levels PM10 100 µg m-3 Pm2.5 50 µg m-3 *Or at other location(s) to be agreed with the regulator 5.2 Results of air quality monitoring shall be submitted to the regulator upon request. Any additional monitoring or sampling should be submitted at the request of the regulator and within time frames mutually agreed. The results shall be tabulated and submitted in MS Excel format and shall be sent to the following email address. Environmental.health@telford.gov.uk Page 11 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 6 General conditions 6.1 A schedule shall be submitted to the Regulator within 28 days of issuing the permit that gives details, such as the frequency and methods employed, of the regular cleaning of all plant, machinery, structures and roadways used within the Installation. 6.2 A list of key arrestment plant on site shall be maintained, and a written procedure for dealing with failure provided to the regulator within 28 days of the issue of the permit. 6.3 The Operator shall prepare a schedule of maintenance of plant, machinery and vehicles used in the activity and this be made available on request from the Regulator. It is expected that normally items shall be serviced in accordance with the manufacturer's recommendation or more frequently if local conditions indicate otherwise. 6.4 Effective operational, maintenance systems and cleaning shall be used for all aspects of the installation where failure could result in a release of visible dust across the Installation boundary. 6.5 Critical spares and consumables and in particular those subjected to continual wear and frequent replacement shall be kept on site or be available for replacement at short notice. 6.6 Relevant staff at all levels shall receive formal training and instruction in their duties relating to the control of emissions to air from the process. Such training shall include, but not be limited to, the following. Awareness of the regulatory requirements of the Permit. Minimising emissions during start up and shut down of the Installation. Actions required to minimise emissions during abnormal events. The operator shall record details of the training to include the name, position, and date of the trainer and trainee and content of the instruction. This record shall be kept until the trained person relinquishes their duties 6.7 At the end of an appropriate 12 month accounting period to be agreed with the Regulator the operator shall supply the regulator with the annual quantity of raw materials consumed and coal produced as detailed in Table 1. 6.8 The regulator shall be informed at least 4 weeks before any change to the prescribed installation described at the beginning of this permit or Page 12 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 any change to the process that may affect the nature of emissions to air or the concentration of substances being emitted. 6.9 Any malfunction which results in emissions to the environment which are likely to cause an adverse effect on the local community shall be reported to the regulator immediately, a record shall be made of the incident within the logbook. 6.10 The best available techniques shall be used to prevent or, where that is not practicable, reduce emissions from the installation in relation to any aspect of the operation of the installation which is not regulated by any other condition of this permit. In relation to this Permit any reference the local Authority or the Regulator shall mean the Borough of Telford and Wrekin. Any information required by this permit to be sent to the Local Authority shall be sent to: Environmental Health Telford & Wrekin Council, Darby House, PO Box 214 Telford TF3 4LE Signed…………………………………………….Date…………………………….. Officer authorised for that purpose Page 13 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 Appendix 1. Plan PPC10/00009/1 Location of Installation (outline in red). Page 14 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 Appendix 2. Plan PPC10/00009/2 The Installation Boundary (outlined in red) Page 15 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 Appendix 3 Plan PPC10/00009/3 Coal processing area and equipment Page 16 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 Glossary of Terms/Definitions: Activity One or more stationary technical units falling within the defined sections of the Schedule 1 of the Environmental Permitting (England and Wales) Regulations 2010 Bag filter These are fabric filters and are comprised of a filter medium, usually manufactured in the form of bags, through which material over a certain size cannot pass. There are three types: mechanical shakedown, reverse air jet and pulse jet. Bags are capable of filtration of finer particles than cyclones, but do not perform well with wet particulate such as wood with a moisture content > 20% (i.e. they clog up). Coating Means a preparation, including all the organic solvents or preparations containing organic solvents necessary for its proper application, which is used in a vehicle refinishing activity to spray onto a motor vehicle. Cyclone An inertial gas cleaning device, which separates dust from the gas stream when the direction of the gas flow is changed and the dust continues in the original direction by virtue of its inertia and is deposited on a collection surface / catch pot. The inlet gas is channeled into a spiral flow. Centripetal forces operating in the spiral provide the change of direction and the larger particles above a critical mass will be deposited on the cyclone walls. CEM Continuous Emission Monitor Dust Means any particulate matter in less than 3mm aerodynamic diameter EAC Effective Area Covered ELV Emission Limit Values, those values stipulated in the SED or in guidance for emission of particular pollutants to atmosphere. EPR Environmental Permitting Regulations 2010, the new pollution control regime replacing that under PPC. Page 17 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 Indicative Monitoring Monitoring which measures the performance of the abatement plant, rather than the quantity of dust etc emitted. In the case of bag filtration, this is normally achieved by alarming the pressure drop across the abatement plant, so that an alarm is set off should a bag / sleeve split. Installation One or more stationary technical units comprising at least one activity or activities falling within the description of Schedule 1 of the Environmental Permitting (England and Wales) Regulations 2010 within a defined area. LEV Local Exhaust Ventilation – ducting and hoods normally associated with small uncontained plant or equipment. PM10 Means particulate matter of 10microns or less PM2.5 Means particulate matter of 2.5 microns or less Regulator Means the Pollution Control Section of the Telford & Wrekin Council. When contacting the regulator it is not sufficient to contact any other part of the council other than the Pollution Control Section at the address specified in the additional notes or at the telephone numbers provided. Ringelmann Chart A chart set by British Standard B.S.2742:1969 based on obscuration which divides smoke into shades 1-4. Shades 2 to 3 are defined as dark smoke and shade 4 is black smoke. STU Stationary Technical Unit shall have the same meaning as in the Pollution Prevention and Control Regulations, but in summary shall mean, one machine used for the purpose of printing on flexible packaging or one machine used in connection with that activity, e.g. an RTO. There must be at least 1 STU per activity, but it is possible to have multiple STU’s still comprising only one activity. Page 18 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 ADDITONAL NOTES These notes do not comprise part of the permit, but contain guidance relevant to it. Inspections Regular inspections will be made by officers of Telford & Wrekin Council (without prior notice), in order to check and ensure full compliance with this permit. BAT (Best Available Techniques) Article 2(11) of the IPPC Directive defines “best available techniques” as follows: “the most effective and advanced stage in the development of activities and their methods of operation which indicates the practical suitability of particular techniques for providing in principle the basis for emission limit values designed to prevent, and where that is not practicable, generally to reduce emissions and the impact on the environment as a whole”. - - - “techniques” shall include both the technology used and the way in which the installation is designed, built, maintained, operated and decommissioned, “available” techniques shall mean those developed on a scale which allows implementation in the relevant industrial sector , under economically and technically viable conditions, taking into consideration the costs and advantages, whether or not the techniques are used or produced inside the Member State in question, as long as they are reasonably accessible to the operator, “best” shall mean most effective in achieving a high general level of protection if the environment as a whole. In determining the best available techniques, special consideration should be given to the items listed in Annex IV of the Directive. Health and Safety at Work and Other Statutory Requirements Compliance with this permit does not necessarily infer compliance with any other legislation. Page 19 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 Other Statutory requirements This permit, in that it regulated only air pollution matters, does not absolve you of the responsibility of any other statutory requirement, such as any need to obtain planning permission, hazardous substances consent or Building Regulations approval from the Council. Discharge consents from the local sewerage undertaker or a waste disposal licence from the Environment Agency may still be required as will compliance with health and safety legislation. Notification of Operation Changes The operator may be liable to prosecution if they operate otherwise than in accordance with the conditions and plant described in this permit. The operator should contact the regulator to discuss any proposed changes. Enforcement The operator will be liable to enforcement action where: 1. the operator fails to comply with or contravenes any permit condition; 2. a change is made to the installation operation without prior notification of the change to the regulator; 3. intentional false entries are made in any record required to be kept under the conditions of the permit; 4. a false or misleading statement is made. Any enforcement action is taken in accordance with the regulator’s enforcement policy. http://www.telford.gov.uk/NR/rdonlyres/240C3F4A-8E36-4C12-8311E4E57A3DF8CC/26214/MicrosoftWordEnvironmentalHealthandWellbeingEnf orc.pdf Annual Subsistence Charge A subsistence charge is payable on the 1st April each year. An invoice will be issued by the regulator providing further details of how to pay. The charges are based on a risk based system. Details of the risk assessment can be found at http://www.defra.gov.uk/environment/ppc/localauth/fees-risk/risk.htm Page 20 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 Appeal against Regulatory Action The operator can appeal against regulatory action by the regulator to the Secretary of State for Environment, Food & Rural Affairs. Appeals must be sent to the Secretary of State on a form found at http://www.planninginspectorate.gov.uk/pins/environment/environment/environmental_appeals/en vironmental_permitting_appeal_form.pdf Guidance on the appeal procedure can be found at http://www.planninginspectorate.gov.uk/pins/environment/environment/environmental_appeals/en vironmental_permitting_guidance_notes.pdf There are time limits for making an appeal as follows: a) in relation to an appeal against a revocation notice, before the notice takes effect; b) in relation to the withdrawal of a duly-made application under paragraph 4(2) of Schedule 5, not later than 15 working days from the date of the notice served under that paragraph; c) in relation to a variation notification, a suspension notice, an enforcement notice or a landfill closure notice, not later than 2 months from the date of the notification or notice; d) in any other case not later than 6 months from the date of the decision or deemed decision. Please note: An appeal will not suspend the effect of the conditions appealed against; the conditions must still be complied with. In determining an appeal against one or more conditions, the Act allows the Secretary of State in addition to quash any of the other conditions not subject to the appeal and to direct the local authority either to vary any of these other conditions or to add new conditions. Page 21 10/00009/PPCB Pollution Prevention Control Act 1999 Environmental Permitting (England & Wales) Regulations 2010 Contact Numbers for the Regulator The Regulator is the Pollution Control Section of Telford & Wrekin Council. They can be contacted on 01952 381818. You may also contact them by email at any time. Environmental.health@telford.gov.uk Correspondence Address All correspondence to Telford & Wrekin Council relating to this information shall be addressed to: Pollution Control Team, Environmental Health and Wellbeing, Environmental Health, Telford & Wrekin Council, Darby House, P.O. Box 214, Telford, TF3 4LE. Page 22 10/00009/PPCB