Cornell University

advertisement

<Logo of Organization>

Project Charter

Project Name:

Executive Sponsor:

Project Director (Sponsor):

Organization:

<Project Name goes here>

Project Manager:

Proposed Project Start Date:

Proposed Project End Date:

Key Contact, Phone #:

Date Submitted:

Date Approved:

Version:

Last Updated:

This template is annotated with notes to help authors when filling it out. You may want to delete text that is within <> with appropriate text specific to the project, particularly when you submit a formal form for signatures.

Project Charter

< >

Contents

Project Information .......................................................................................... 1

Business Case / Proposed Solution .............................................. 1

Consistency/Fit with Organizational Strategic Plan....................... 1

Major Alternatives Considered and Why Rejected ....................... 2

Known Project Constraints ........................................................... 2

Estimate for Overall Project .......................................................... 2

Information for Project Planning (High Level) ............................................... 3

High Level Schedule / Milestone’s for Project Planning ................ 3

Budget Summary for Project Planning (High Level) ..................... 3

Resource Requirements for Project Planning (High Level) ........... 4

Governance for Project Planning (High Level) .............................. 5

Signatures ........................................................................................................ 6

Project Charter i

< >

Project Information

Project Charter

The purpose of the Project Charter is to formally authorize the start of a new project. Specifically, the charter is intended to authorize the sponsor and project manager to apply resources to develop a Project Initiation Plan (PIP).

The Project Initiation Plan will provide the parameters for the project and includes: goals, objectives, success criteria, scope, high level schedule, with key deliverables and milestones, stakeholder roles, risk plan and other management plans for the project, along with resources needed and the project budget and benefits. The Project Initiation Plan will require approval prior to execution of the project.

===========================================================

This Project Charter requests approval for $_______________, funded from the following sources:

__________________, which will be used to develop the Project Initiation Plan.

Or

This Charter does not ask for the authority to spend funds at this time to develop the Project Initiation

Plan.

<Delete above choice not used>

===========================================================

*On large, complex projects, phases may need a new charter.

Business Case / Proposed Solution

What is the business need that gave rise to this project? Describe the business drivers (i.e. market demand, business need, customer request, technological advance, legal requirement, or social need) that created the problem, opportunity or business requirement. How did the project come about?

Provide any other necessary background.

Provide a description of the project that includes the key goals and objectives and what the project will deliver and any other high level expectations of the project. Identify if this is part of a larger project or if it has follow on projects.

Identify the customers and anticipated consumers of the project and why they will benefit from the project.

Product Need / Product Description / Customers

Consistency/Fit with Organizational Strategic Plan

Describe how this project and its objectives specifically support the organization’s current strategic plan.

Consistency/Fit with Organization’s Strategic Plan

Project Charter 1

< >

Major Alternatives Considered and Why Rejected

Explain what would happen if you do nothing. Describe other alternatives that were considered and why they were rejected.

Explain why chosen / not chosen Alternatives considered

1. Do Nothing <The Do Nothing option is to be addressed as an option in every Charter.

Ex: Current software is no longer supported and we need to upgrade software for mission critical application.>

2. <Selected Alternative>

3. <Other Alternatives considered>

If at this stage of the project you have not looked at alternatives or if considering alternatives does not apply, please describe the situation.

Alternatives do not apply because :

<Describe the situation: why alternatives do not apply at this time or at all.>

Known Project Constraints

Identify any constraints known about this project that will affect the “Triple Constraints” (budget, schedule, resources) or any other known constraints for this project. If there are no constraints, note that fact.

In order for the project initiation plan to be done successfully please list any known factors that limit the ultimate project’s execution. The most frequent constraint is the project end date. For each constraint listed, be sure to elaborate on how it is limiting the project and how the project would benefit from its removal.

Project Constraint Type

1. <Budget Constraint>

2. <Schedule Constraint>

3. <Resource Constraint>

Description of the Constraint

<Ex: $100,000 of funds has been identified for this project. No other funding is available.

Features that cannot fit into this constraint could be listed as future enhancements.>

<Ex: this project must be done by August 15,

2010>

<Ex: John Smith is the only person who has the skills to complete the work to build this system.>

Estimate for Overall Project

An estimated cost for the overall project is between ____________ and ____________. The estimated duration is approximately ________ months to ________.

This estimate is based on: <include here the basis of the estimate (e.g. historical information, other organizations that have done a similar project, expert judgment etc.)>

Project Charter 2

< >

Information for Project Planning (High Level)

High Level Schedule / Milestone’s for Project Planning

Any project milestones or major project activity that will happen during this period of time should be added to the High Level Schedule. The major deliverable for Project Planning (High Level) is the

Project Initiation Plan (PIP).

Milestone Start Date

Project Initiation

Develop Project Charter

Evaluate Project Charter

Approve Project Charter

Project Planning (High Level)

Completion

Date

Prepare for the Project

Conduct Project Kick – Off Meeting

Develop the Project Initiation Plan

Define the Goal, Specific Objectives, & Success Criteria

Define Project Scope

Develop the High Level Schedule and Document Assumptions

Identify and Document Stakeholder Involvement

Develop the Communication Plan

Establish the Project Budget

Define Governance and Resourcing

Define the Management Approaches

Develop the High Level Risk Plan

Submit the Project Initiation Plan for Approval

Confirm Approval to Proceed- Approved Project Initiation Plan

Assumptions that affect the High Level Schedule:

Budget Summary for Project Planning (High Level)

Provide below the estimated budget for Project Planning (High Level).

Type of Expense Cost ($) Account Number /

Funding Source

Staff Expense (internal)

Capital Expense

Operating Expense

Service (external)

Contingency

Total Budget for Project

Planning (High Level)

Project Charter 3

< >

Resource Requirements for Project Planning (High Level)

Define the make-up of the project resources for the development of the High Level Plan and any other activities that will be done during this period. Include those specific individuals that have been identified and also show those that need ‘To Be Determined’ (TBD).

Table 1: List the names of all individuals needed to perform the work described in the Project Charter and whose participation must be approved by the Manager of the Resource

Project Initiation

Team Role

No. Who

(if known) or TBD

%

Time or

Hours

Dates Needed

(Date Range)

Name of Manager

<Ex: Business

Analysts

<Ex: Project

Manager

<Ex: Technical

Analyst

<Ex: Subject Matter

Experts

1

1

1

TBD

TBD

TBD

5 TBD

30%

50%

30%

10 hrs ea

MM/DD/YY-

MM/DD/YY>

MM/DD/YY-

MM/DD/YY>

MM/DD/YY-

MM/DD/YY>

MM/DD/YY-

MM/DD/YY>

Resourcing comments, constraints, and/or issues:

Project Charter 4

< >

Governance for Project Planning (High Level)

Define the governance model for the project planning (high level) phase of the project. A sample is provided below. Include Actual Names

Project - <Project Name>

Project Governance Model

Executive Sponsor

Project Director / Sponsor Steering Committee

Focus Group / SME's

Project Manager

Technical Project Lead

Project Team

Business / Functional

Project Lead

Project Team

Project Charter 5

< >

Signatures

The Sponsor should indicate approval or rejection of the Project Charter by checking the Approve or

Reject box. If the Sponsor is rejecting the charter, he/she must indicate the reason in the comments field.

The Sponsor indicates final acceptance of the Project Charter (including securing individual resources) by providing his/her signature in the Project Sponsor Signature box and the approval date in the Date box.

Executive Sponsors

Name Action Comments Signature Date

Approve:

Reject:

 etc.

Approve:

Reject:

Project Directors and/or Sponsors

Name Action Comments etc.

Signature Date

Approve:

Reject:

 etc.

Approve:

Reject:

Approvers

Agreement to Secure Required Resources

The Approver is the person(s) or group that has the authority to commit resources for this project.

He/she indicates his/her agreement to provide required resources for Project Planning (High Level) by providing his/her Approver Signature and the approval Date.

Name Action Comments Signature Date

Approve:

Reject:

Approve:

Reject:

Project Charter 6

Download