COMMONWEALTH OF VIRGINIA COUNTY OF HENRICO DEPARTMENT OF FINANCE CECELIA H. STOWE, CPPO, C.P.M. PURCHASING DIRECTOR RFP #15-1096-12CS QUESTIONS AND ANSWERS LEASE OF CISCO NETWORKING HARDWARE & SERVICES DECEMBER 18, 2015 1. After reviewing the Cisco hardware requirements, could you verify if each school should have a Cisco WS-C4500X-32SFP+ as their core switch? There appears to be several schools that have left the Core portion of the school almost blank (with some cables and optics, but no switch). Can you find out if this is in error, or if they already have the equipment for those schools? The Schools in question are: Lot 5 Lot 7 Lot 12 Lot 13 Lot 22 Lot 26 Lot 44 Lot 46 Carver Elementary Crestview Elementary Echo Lake Elementary Fair Oaks Elementary Kaechele Elementary School Longan Elementary Twin Hickory Elementary Ward Elementary The 4500X core switches were omitted purposely due to the fact we performed a life cycle refresh of core switches for Lot 5, 7,12,13,26,44 and 46 in 2014 in support of a server farm refresh. At the time the core switches at these locations would not support the server farm refresh. Kaechele Lot 22 is a recently new school and was provisioned a new 4500X Core Router during its construction. 2. Kaechele Elementary only has the cables and optics, no core switch nor any IDF - Access switches. I just found it odd, so could you confirm this as well? Kaechele is a recently new school and was provisioned with a 4500X Core Router and 2960S Access switches during construction. Take note that the Wireless Access Points will be replaced as part of this RFP. 1 3. Can HCPS provide Heat Maps showing locations for the wireless AP’s HCPS does not have Heat Maps for all schools and some current heat maps do not reflect additional AP’s added during the course of the year. The Successful Offeror will be provided site maps after award of the contract reflecting desired Wireless Access Point placements based a wireless study and real world operational experience. 4. Can we have an inventory of existing Cisco equipment at each location where new equipment is being installed? This beneficial to both the vendor and HCPS when preparing the project plan. For the most part this a one to one replacement with a few augmentations of Access switches to address additional wireless needs. Please refer to the spread sheet “ES-Network Refresh per School Material List” (Attachment K) which provide a per school breaks down of the type and quantity of equipment that will need be installed in which the BOM was created from. 5. Will the contractor be responsible for installing all conduit raceway needed in each location. Thirty (30) of the locations state there will be raceway/conduit needed. a. Yes, it falls under the contractor responsibility to provision and install the conduit raceway and sleeves required as outlined in the RFP. b. Although the majority of schools have suspended ceilings installed it is estimated that this number of schools do not have suspended ceilings. No exposed cabling shall be permitted for this installation. Consequently, it will be necessary for the Successful Offeror to install raceway, either metal or plastic to enclose the cables from the access point location to the nearest IDF cabinet. In lieu of raceway, metallic conduit may be installed. 6. Please note that the Minuteman UPS part numbers are no longer available for sale. Corresponding Part #’s are replacements for the ones that have gone end of sale. a. b. c. d. e. Requested Part # Replacement Part # E1500RM2U E1500RTXL2U E2000RM2U E2000RTXL2U E750RM2U E750RTXL2U Please confirm that we can submit pricing for the replacement SKUs. Since this is a product line next generation life cycle equivalent, this would be permissible. 2 7. Is there a color preference for the Fiber and Copper patch cords? a. Yellow: To support new provisioned CAT 6A and Patch Panels for Wireless Access Points as outlined in Section H “Data Cabling Service Scope”. We would like to request that the patch cords be non-booted and 14 inches in length for the IDF and 3 foot in length at the AP. Panduit part numbers; UTP6ASD3YL (3 ft.) and UTP6ASD14inchYL (custom 14 in.) b. i. Gray: Copper Patch Cords for Patch Panel to Access Switch as outlined in the BOM. ii. Weltron #90-C6-8"AH iii. Weltron #90-C6-10"AH iv. Weltron #90-C6-1AH v. Weltron #90-C6-14"AH c. Fiber Patch Cords: Please Reference Patch Cord Description as stated in the BOM under Lot 49 section labeled “Fiber Patch Cables”. 8. Due to the upcoming holidays, and number of maps to review, we respectfully request the consideration of a one week extension. By Addenda, HCPS is extending the due date to January 8, 2016 at 2:00 p.m. 9. The drawings provided offered very good visualization of the required AP placements. However, there is inconsistency in the information provided by HCPS in those placement maps. The Rivers Edge placement map noted a) number of existing, b) number of new and c) number to be relocated. Can HCPS please make changes to all the maps to reflect the same level of information for each school? Updated Maps will be provided The site Maps and Dot representation being provided are specifically to show new wiring and coordinating IDF location. The site MAPS were not meant to provide a per school total count of AP devices and placements. HCPS newly provided spreadsheet labeled “ES-Network Refresh Materials Per School Materials List” will provide a per school representing and quantity of Core Routers, Access Switches, total number of AP’s and UPS’s being installed at each site. (Please see attachment “ES-NetworkRefresh-Per-School-Materials-List”) Please take note, HCPS will provide per school AP placement MAPS to the Successful Offeror after award of the contract during the initial planning meeting. 3 10. For existing Cisco access points, does HCPS want the vendor to provide new CAT6A cable runs for that equipment? No 11. ERATE – In what section would you like for the vendor to define its ERATE qualifications as it was not defined in the Proposal Response Format. Attachment B request the Offeror to document their SPIN number which validates that they are a qualified ERate participant. Offerors shall provide as part of their proposal submission evidence of their qualifications as an approved and certified ERate participant. 12. Resumes and references – the Proposal Response Format notes that both references and resumes are to be included in the Introduction – Attachment C and D – as well as in Section 3 – Response to the Scope of Work, subsection b and c. Can those sections be consolidated? Yes. 13. Will HCPS consider APC UPS devices as an equivalent to the MinuteMan solution listed in the RFP? No alternatives or equivalents will be accepted. 14. Training – Is this supposed to be Cisco certified training classes or is this hands-on training with vendor engineers? Cisco Certified Training classes. 15. Does the executed HCPS NDA need to be included in this response? Offerors interested in submitting proposals should follow the instructions included on page 54 of the RFP to obtain the site maps of the schools PRIOR to proposal submission. It is not necessary to include this form in the proposal response. 16. Would HCPS consider a one-week extension for the submission of our response, moving the due date to January 13, 2016 at 2:00 pm? By Addenda, HCPS is extending the due date to January 8, 2016 at 2:00 p.m. 17. Do patch cables need to be from a specific manufacturer? Patch cords to support the new wireless cable drops should be Panduit part numbers UTP6ASD3YL and UTP6ASD14inchYL for the three foot and fourteen inch patch cords, respectively. 4 18. What length should the cat6A patch cables be for the connections from the structured cabling outlet to the access point? Patch cords should be installed between the biscuit block at the end of the required service loop and the wireless access point. The length of the patch cord shall differ depending on whether the ceiling is an open, exposed ceiling or a suspended ceiling. Three (3) foot patch cords shall be used for suspended ceilings and fourteen (14) inch patch cords shall be used for open ceilings. 19. What length should the cat6A patch cables be for the connections from the cat6A patch panel to the switch? 14 inch Yellow Patch Cords (Panduit #UTP6ASD14inchYL) 20. Will wall mounted access points be positioned vertically and mounted directly to walls or will they require an additional mounting bracket to achieve proper orientation? MPR- AP’s will be mounted vertically on the wall inside of Oberon enclosures (#1015-C) Auditorium-will be mounted horizontally using Oberon wall mount #1009-00 21. For warranty purposes, is it correct to assume that existing patch panels receiving new cable runs are manufactured by Hubbell? Correct. All existing patch panels are manufactured by Hubbell. However, should space be a concern in an IDF cabinet, potentially precluding the installation of a new Category 6A patch panel, the Successful Offeror should contact Technology and accommodations will be made for a new Category 6A patch panel to be installed. 22. Do all proposed access point locations require new cabling? No. 23. Will existing AP locations utilize the existing cabling? Yes. 24. Will moved Access point locations utilize existing cabling or require new cabling? There are no AP moves as part of the RFP. However, there are situations where existing AP’s will need to be removed and no new AP will be installed in its location. 5 25. Attachment H specifies 4 new runs at colonial trail ES, the drawing shows 20 net new access points. How many cable runs should be quoted? Updated MAPs will be provided to provide better clarity of the new cabling locations. Please take note under section H labeled “Data Cabling Services Scope” we are requesting Offerors to provide a single and a double per run cabling option for price comparison. 26. Attachment H specifies 27 new cable runs are needed for Crestview ES, the drawings show a total of 26 APs in the design after one is removed from the current design along with cable moves. How many new cable runs are required? Updated MAPs will be provided to provide better clarity of the new cabling locations. Please take note, the site Maps and Dot representation being provided are specifically to show new wiring and coordinating IDF location. The site MAPS were not meant to provide a per school total count of AP devices and placements. HCPS newly provided spreadsheet labeled “ES-Network Refresh Materials Per School Materials List” (Attachment K) will provide a per school representing and quantity of Core Routers, Access Switches, total number of AP’s and UPS’s being installed at each site. (Please see attachment “ES-Network-Refresh-Per-School-Materials-List”) 27. For T1 at Davis elementary, are cable runs run underground through conduit, or aerial to trailer 2? Aerial, however Trailer cabling is not within the scope of cabling needs. 28. Are man lifts available at each site to reach locations with high ceilings like gyms, or do we need to account for them in our installation cost? As a matter of policy, HCPS owned lifts may not be used by non-HCPS staff. Please include these costs in your proposal submission. Gym AP’s will be mounted on the wall inside of enclosures no higher than 12 feet above finished floor. It is estimated that there will be less than 10 sites requiring the use of a lift. 29. How are cables fed from Trailer 1 to trailers 2 - 5 at Glen Allen ES? Trailer cabling is not within the scope of cabling needs. The cables from the school to the IDF trailer is routed underground and the drop cables to the remaining trailers are routed aerially. 6 30. Vendor has noted some inconsistencies in the BOM that are addressed by school below. Please review and provide clarification/validation for these observations. School Questions Need to know correct number of AP's - Map shows 2 red dots, 3 yellow dots and 2 green - Only 7 AP's for school? Updated MAPs will be provided to provide better clarity of the New cabling locations. Adams Elementary School Lot 2 Carver Elementary School Lot 5 Crestview Elementary School Lot 7 Please take note, the site Maps and Dot representation being provided are specifically to show new wiring and coordinating IDF location. The site MAPS were not meant to provide a per school total count of AP devices and placements. HCPS newly provided spreadsheet labeled “ES-Network Refresh Materials Per School Materials List” (Attachment K) will provide a per school representing and quantity of Core Routers, Access Switches, total number of AP’s and UPS’s being installed at each site. (Please see attachment “ES-Network-Refresh-Per-School-Materials-List”) No 4500X on BOM. Is this correct? By Design No 4500X on BOM. Is this correct? By Design Map shows 6 AP's. Is this correct? Updated MAPs will be provided to provide better clarity of the New cabling locations. Donahoe Elementary School Lot 10 Please take note, the site Maps and Dot representation being provided are specifically to show new wiring and coordinating IDF location. The site MAPS were not meant to provide a per school total count of AP devices and placements. HCPS newly provided spreadsheet labeled “ES-Network Refresh Materials Per School Materials List” (Attachment K) will provide a per school representing and quantity of Core Routers, Access Switches, total number of AP’s and UPS’s being installed at each site. (Please see attachment “ES-Network-Refresh-Per-School-Materials-List”) Map shows 6 AP's. Is this correct? Updated MAPs will be provided to provide better clarity of the New cabling locations. Dumbarton Elementary School Lot 11 Echo Lake Elementary School Lot 12 Please take note, the site Maps and Dot representation being provided are specifically to show new wiring and coordinating IDF location. The site MAPS were not meant to provide a per school total count of AP devices and placements. HCPS newly provided spreadsheet labeled “ES-Network Refresh Materials Per School Materials List” (Attachment K) will provide a per school representing and quantity of Core Routers, Access Switches, total number of AP’s and UPS’s being installed at each site. (Please see attachment “ES-Network-Refresh-Per-School-Materials-List”) No 4500X on BOM. Is this correct? Map shows 4 AP's - Is this correct? By Design 7 Fair Oaks Elementary School Lot 13 No 4500X on BOM. Is this correct? Map shows 6 AP's - Is this correct? By Design Map shows 4 AP's - Is this correct? Updated MAPs will be provided to provide better clarity of the New cabling locations. Glen Lea Elementary School Lot 16 Please take note, the site Maps and Dot representation being provided are specifically to show new wiring and coordinating IDF location. The site MAPS were not meant to provide a per school total count of AP devices and placements. HCPS newly provided spreadsheet labeled “ES-Network Refresh Materials Per School Materials List” (Attachment K) will provide a per school representing and quantity of Core Routers, Access Switches, total number of AP’s and UPS’s being installed at each site. (Please see attachment “ES-Network-Refresh-Per-School-Materials-List”) Map shows 4 AP's - Is this correct? Updated MAPs will be provided to provide better clarity of the New cabling locations. Johnson Elementary School Lot 21 Kaechele Elementary School Lot 22 Please take note, the site Maps and Dot representation being provided are specifically to show new wiring and coordinating IDF location. The site MAPS were not meant to provide a per school total count of AP devices and placements. HCPS newly provided spreadsheet labeled “ES-Network Refresh Materials Per School Materials List” (Attachment K) will provide a per school representing and quantity of Core Routers, Access Switches, total number of AP’s and UPS’s being installed at each site. (Please see attachment “ES-Network-Refresh-Per-School-Materials-List”) No new switches/hardware except for cables - Is this correct No map for this school By Design Map shows 6 AP's. Is this correct? Updated MAPs will be provided to provide better clarity of the New cabling locations. Laburnum Elementary School Lot 23 Please take note, the site Maps and Dot representation being provided are specifically to show new wiring and coordinating IDF location. The site MAPS were not meant to provide a per school total count of AP devices and placements. HCPS newly provided spreadsheet labeled “ES-Network Refresh Materials Per School Materials List” (Attachment K) will provide a per school representing and quantity of Core Routers, Access Switches, total number of AP’s and UPS’s being installed at each site. (Please see attachment “ES-Network-Refresh-Per-School-Materials-List”) 8 Map legend for Middle and Upper Floors states locations for 25 drops for new AP's. Dots on diagram only number 22 Updated MAPs will be provided to provide better clarity of the New cabling locations. Lakeside Elementary School Lot 24 Longan Elementary School Lot 26 Please take note, the site Maps and Dot representation being provided are specifically to show new wiring and coordinating IDF location. The site MAPS were not meant to provide a per school total count of AP devices and placements. HCPS newly provided spreadsheet labeled “ES-Network Refresh Materials Per School Materials List” will provide a per school representing and quantity of Core Routers, Access Switches, total number of AP’s and UPS’s being installed at each site. (Please see attachment “ES-Network-Refresh-Per-School-Materials-List”) No 4500X on BOM. Is this correct? By Design Map shows 4 AP's - Is this correct? Updated MAPs will be provided to provide better clarity of the New cabling locations. Pemberton Elementary School Lot 31 Please take note, the site Maps and Dot representation being provided are specifically to show new wiring and coordinating IDF location. The site MAPS were not meant to provide a per school total count of AP devices and placements. HCPS newly provided spreadsheet labeled “ES-Network Refresh Materials Per School Materials List” will provide a per school representing and quantity of Core Routers, Access Switches, total number of AP’s and UPS’s being installed at each site. (Please see attachment “ES-Network-Refresh-Per-School-Materials-List”) Map shows 6 AP's - Is this correct? Updated MAPs will be provided to provide better clarity of the New cabling locations. Pinchbeck Elementary School Lot 32 Please take note, the site Maps and Dot representation being provided are specifically to show new wiring and coordinating IDF location. The site MAPS were not meant to provide a per school total count of AP devices and placements. HCPS newly provided spreadsheet labeled “ES-Network Refresh Materials Per School Materials List” will provide a per school representing and quantity of Core Routers, Access Switches, total number of AP’s and UPS’s being installed at each site. (Please see attachment “ES-Network-Refresh-Per-School-Materials-List”) Map shows 6 AP's - Is this correct? Updated MAPs will be provided to provide better clarity of the New cabling locations. Ratcliffe Elementary School Lot 33 Please take note, the site Maps and Dot representation being provided are specifically to show new wiring and coordinating IDF location. The site MAPS were not meant to provide a per school total count of AP devices and placements. HCPS newly provided spreadsheet labeled “ES-Network Refresh Materials Per School Materials List” will provide a per school representing and quantity of Core Routers, Access Switches, total number of AP’s and UPS’s being installed at each site. (Please see attachment “ES-Network-Refresh-Per-School-Materials-List”) 9 Map shows 6 AP's - Is this correct? Updated MAPs will be provided to provide better clarity of the New cabling locations. Sandston Elementary School Lot 35 Please take note, the site Maps and Dot representation being provided are specifically to show new wiring and coordinating IDF location. The site MAPS were not meant to provide a per school total count of AP devices and placements. HCPS newly provided spreadsheet labeled “ES-Network Refresh Materials Per School Materials List” will provide a per school representing and quantity of Core Routers, Access Switches, total number of AP’s and UPS’s being installed at each site. (Please see attachment “ES-Network-Refresh-Per-School-Materials-List”) Map shows 6 AP's - Is this correct? Updated MAPs will be provided to provide better clarity of the New cabling locations. Seven Pines Elementary School Lot 36 Please take note, the site Maps and Dot representation being provided are specifically to show new wiring and coordinating IDF location. The site MAPS were not meant to provide a per school total count of AP devices and placements. HCPS newly provided spreadsheet labeled “ES-Network Refresh Materials Per School Materials List” will provide a per school representing and quantity of Core Routers, Access Switches, total number of AP’s and UPS’s being installed at each site. (Please see attachment “ES-Network-Refresh-Per-School-Materials-List”) Map shows 2 AP's - Is this correct? Updated MAPs will be provided to provide better clarity of the New cabling locations. Shady Grove Elementary School Lot 37 Springfield Park Elementary School Lot 39 Please take note, the site Maps and Dot representation being provided are specifically to show new wiring and coordinating IDF location. The site MAPS were not meant to provide a per school total count of AP devices and placements. HCPS newly provided spreadsheet labeled “ES-Network Refresh Materials Per School Materials List” will provide a per school representing and quantity of Core Routers, Access Switches, total number of AP’s and UPS’s being installed at each site. (Please see attachment “ES-Network-Refresh-Per-School-Materials-List”) Map shows 2 AP's - Is this correct? By Design Map shows 8 AP's - Is this correct? Updated MAPs will be provided to provide better clarity of the New cabling locations. Tuckahoe Elementary School Lot 43 Please take note, the site Maps and Dot representation being provided are specifically to show new wiring and coordinating IDF location. The site MAPS were not meant to provide a per school total count of AP devices and placements. HCPS newly provided spreadsheet labeled “ES-Network Refresh Materials Per School Materials List” will provide a per school representing and quantity of Core Routers, Access Switches, total number of AP’s and UPS’s being installed at each site. (Please see attachment “ES-Network-Refresh-Per-School-Materials-List”) 10 Map shows 6 AP's - Is this correct? Updated MAPs will be provided to provide better clarity of the New cabling locations. Ward Elementary School Lot 46 Please take note, the site Maps and Dot representation being provided are specifically to show new wiring and coordinating IDF location. The site MAPS were not meant to provide a per school total count of AP devices and placements. HCPS newly provided spreadsheet labeled “ES-Network Refresh Materials Per School Materials List” will provide a per school representing and quantity of Core Routers, Access Switches, total number of AP’s and UPS’s being installed at each site. (Please see attachment “ES-Network-Refresh-Per-School-Materials-List”) Attachment J Lot 49 lists 1420 new 3702i Wireless AP's. From a review of the maps, I show a total of 913 Wireless AP's. This is 507 short... Updated MAPs will be provided to provide better clarity of the New cabling locations. All Schools - Wireless AP's Please take note, the site Maps and Dot representation being provided are specifically to show new wiring and coordinating IDF location. The site MAPS were not meant to provide a per school total count of AP devices and placements. HCPS newly provided spreadsheet labeled “ES-Network Refresh Materials Per School Materials List” will provide a per school representing and quantity of Core Routers, Access Switches, total number of AP’s and UPS’s being installed at each site. (Please see attachment “ES-Network-Refresh-Per-School-Materials-List”) 31. The issuance of this RFP was 12/11. On page 65, Section VI the anticipated schedule outlines a RFP issuance date of 12/4. Is it possible to slide the schedule of the receipt of this RFP for one week? By Addenda, HCPS is extending the due date to January 8, 2016 at 2:00 p.m. 32. The anticipated schedule shows cabling to run from 5/30 - 7/1. Can cabling work be performed during working hours from 5/30 - 6/20? If not, what are the hours that can be worked during this timeframe? No work can be performed while school is in session. Cabling work will need to be performed after hours between the hours of 3:30PM – 8PM for the 5/30 – 6/20 time frames. Once schools are officially closed for the summer based on the 6/20 date, work can occur between 7AM – 5:30PM Mon – Thursday. 33. Can you provide us a list of the type and anticipated quantities of network equipment that will be decommissioned by school and need to be returned to Trampton? Please refer to attachment provided titled “HCPS-Current-ElemEquipment” (Attachment L) for a current inventory of Core Router and Access Switches. 11 34. Does HCPS desire a 6 year warranty on all MinuteMan UPS’? Not on UPS’s. 35. Does page 50, C, 1, b imply that staging should be done at Trampton or do we have the option to configure at Offeror’s facility, and then deliver to school? All equipment will need to be configured at the Offerors location. HCPS can provide temporary warehouse space for equipment predeployment staging that will need to be delivered to the schools. It is the Successful Offerors responsibility to transport the staged equipment from the warehouse to the school and return old equipment to the warehouse. 36. Does page 51, D; imply that the project manager is required to be on-site full time? The project manager will need to be geographically located in order to respond to any emergencies or required meetings. As part of your proposal response please submit information on the location of the project manager and their availability to be on site as requested. The PM will need to be able to meet in person with HCPS Project manager during scheduled meetings and be available within 24 hours to address any unforeseen events or issues. 37. Does HCPS require the new APs to be added into Cisco Prime and dropped on location maps? No, HCPS will add new AP’s into Prime and locations maps. Offeror will be responsible for adding AP’s to the Cisco wireless controller. 38. On page 57, xviii, is it possible to dispose of cardboard waste at HCPS facilities? Schools do not have sufficient waste disposal facilities to handle excessive amounts of cardboard. The Successful Offeror will be required to remove all trash from HCPS sites. Please take note, new equipment boxes will need to be reused to house the old equipment that will be transported to Trampton. 12 39. On page 61, f, i: in item xvi on the same page above terminates in CAT 5E, then CAT6A standards cannot be met. Can this requirement be modified by HCPS? As noted in the answer to question 21 above, should space be a concern in an IDF cabinet, potentially precluding the installation of a new Category 6A patch panel, the Successful Offeror should contact Technology and accommodations will be made for a new Category 6A patch panel to be installed. Category 6A cable should not be terminated on an existing Category 5 or 5e patch panel. PLEASE NOTE THE FOLLOWING The colored dots on all maps represent the general location of the new Cat 6A Cable drops. The dot color corresponds with the IDF color that the cable reports to. 13