CHAPTER NO. 12
STONE MASONRY
Notes :(i)
The labour rates include the cost of water, tools and plant, labour and materials for scaffolding and
centring and shuttering wherever required and cost of good earth for mud mortar where required.
(ii)
Unless otherwise stated, the labour rates include the rehandling of materials within 100 metres.
(iii)
The rates include the cost of water. Where the water is supplied free by the Department, rates shall
be decreased accordingly.
(iv)
The labour rates including the cost of dressing stones according to the relevent PWD Specifications.
(v)
The labour as well as through rates for item nos. 12.11, 12.12, 12.13, 12.16 to 12.24, 12.28 to 12.33
are applicable when quarried stone is used. When work is built with small boulders or with stone
obtained by breaking large boulders, the above rates will be increased by Rs. 30.00 per cum on
account of extra labour involved in dressing.
(vi)
The through rate of the stone masonry, include the cost of stone at the site of work irrespective of
the distance from the source, but stone masonry will normally be constructed in such area, where
stone is available locally, or in the vicinity of the site of the work. Variations in actual lead in such
cases will be taken care of, by premium/abatement over the schedule rates. Where, however stone
is not available near at hand but has to be brought from long distances, item of stone masonry should
not be specified, and if, some work has to be constructed in stone due to very special reasons, extra
provision for carriage of stone should be made in the estimates.
(vii)
If pumping is required in wet stone masonry work, it will be done departmentally.
Sr. No.
Description
1
Unit
2
3
Plains
Sub-Mountionus
Labour
Rate
Through
Rate
Labour
Rate
Through
Rate
4
5
6
7
ASHLAR MASONRY
12.1 Fine ashlar in cement mortar (1:3) up to 6 metres
above plinth level.
Cum.
1082.00 1227.00
1190.00 1325.00
12.2 Fine ashlar in cement mortar (1:6) up to 6 metres
above plinth level.
Cum.
1082.00 1204.00
1190.00 1302.00
12.3 Rough tooled bastard ashlar in cement mortar
(1:3) up to 6 metres above plinth level.
Cum.
744.00
923.00
818.00
988.00
12.4 Rough tooled or bastard ashlar in cement mortar
(1:6) up to 6 metres above plinth level.
Cum.
744.00
881.00
818.00
946.00
12.5 Rustic ashlar in cement mortar (1:3) upto 6 metres
above plinth level.
Cum.
714.00
893.00
786.00
956.00
12.6 Rustic ashlar in cement mortar (1:6) upto 6 metres
above plinth level.
Cum.
714.00
852.00
786.00
914.00
Page 74
CSR-1987 [Re-print]
Sr. No.
1
Description
Unit
2
3
Plains
Sub-Mountionus
Labour
Rate
Through
Rate
Labour
Rate
Through
Rate
4
5
6
7
12.7 Extra for above items for every additional storey of
height upto 4 metres above the top of structural
roof of lower storey.
Cum.
18.00
12.8 Extra for arch work including centring and
shuttering.
Cum.
62.00
12.9 Cut stone work in cornices, string courses, etc. in
cement mortar 1:3.
Cum.
1597.00 1742.00
1757.00 1892.00
12.10 Cut stone work in cornices, string courses, etc. in
cement mortar 1:4.
Cum.
1597.00 1729.00
1757.00 1879.00
18.00
68.00
19.00
68.00
19.00
75.00
Block in Course Rubble Masonry
12.11 Block in course upto 4 metres above plinth level in
cement mortar 1:4
Cum.
551.00
719.00
606.00
764.00
12.12 Block in course upto 4 metres above plinth level in
cement mortar 1:5
Cum.
551.00
702.00
606.00
748.00
12.13 Block in course upto 4 metres above plinth level in
cement mortar 1:6
Cum.
551.00
691.00
606.00
736.00
12.14 Extra for above items for every additional storey of
height upto 4 metres above the top of structural
roof of lower storey.
Cum.
13.00
12.15 Add extra for arch work including centring and
shuttering.
Cum.
57.00
61.00
63.00
67.00
Cum.
157.00
342.00
172.00
349.00
Cum.
157.00
321.00
172.00
328.00
Cum.
157.00
308.00
172.00
314.00
Cum.
133.00
203.00
146.00
208.00
13.00
14.50
14.50
Squared or Rectangular Pillars of Rubble
Masonry
12.16 Squared rubble masonry coursed (coursed rubble)
in foundations and plinth in cement mortar 1:4
12.17 Squared rubble masonry coursed (coursed rubble)
in foundations and plinth in cement mortar 1:5
12.18 Squared rubble masonry coursed (coursed rubble)
in foundations and plinth in cement mortar 1:6
12.19 Squared rubble masonry coursed (coursed rubble)
in foundations and plinth in mud mortar
12.20 Squared rubble masonry coursed (coursed rubble)
in foundations, plinth and superstructure laid dry.
Page 75
CSR-1987 [Re-print]
Sr. No.
1
Description
Unit
2
3
Plains
Sub-Mountionus
Labour
Rate
Through
Rate
Labour
Rate
Through
Rate
4
5
6
7
(a) Where building stone is specially arranged
by the contractor.
Cum.
96.00
(b) Where stone is available within 100 metres
from rock cutting already done.
Cum.
97.00
-
106.00
-
Cum.
71.00
-
78.00
-
12.21 Squared rubble masonry uncoursed or built to
courses in foundations and plinth in cement mortar
1:4 to a pattern if specified.
Cum.
174.00
359.00
191.00
367.00
12.22 Squared rubble masonry uncoursed or built to
courses in foundations and plinth in cement mortar
1:5 to a pattern if specified.
Cum.
174.00
338.00
191.00
347.00
12.23 Squared rubble masonry uncoursed or built to
courses in foundations and plinth in cement mortar
1:6 to a pattern if specified.
Cum.
174.00
324.00
191.00
333.00
12.24 Squared rubble masonry uncoursed or built to
courses in foundations and plinth in mud mortar to
a pattern if specified.
Cum.
141.00
211.00
155.00
216.00
12.25 Add for work in super structure up to 4 metres
above plinth level.
Cum.
27.00
27.00
29.50
29.50
12.26 Extra for above items for every additional storey of
height upto 4 metres above the top of structural
roof of lower storey.
Cum.
14.00
14.00
15.00
15.00
12.27 Extra for arch work including centring and
shuttering.
Cum.
62.00
66.00
68.00
73.00
12.28 Random rubble masonry or polygonal rubble
masonry (Kentish Rag) or random or polygonal
rubble built to courses in foundations and plinth in
cement mortar 1:8
Cum.
133.00
276.00
146.00
280.00
12.29 Random rubble masonry or polygonal rubble
masonry (Kentish Rag) or random or a polygonal
rubble built to courses in foundations and plinth in
cement mortar 1:7
Cum.
133.00
285.00
146.00
290.00
12.30 Random rubble masonry or polygonal rubble
masonry (Kentish Rag) or random or polygonal
rubble built to courses in foundations and plinth in
cement mortar 1:6.
Cum.
133.00
297.00
146.00
301.00
167.00
106.00
152.00
(c) Where stone is available within 100 metres
from dismantled or failed structure.
Random Rubble Masonry
Page 76
CSR-1987 [Re-print]
Sr. No.
1
Description
Unit
2
3
12.31 Random rubble masonry or polygonal rubble
masonry (Kentish Rag) or random or polygonal
rubble built to courses in foundations and plinth in
mud mortar
Plains
Sub-Mountionus
Labour
Rate
Through
Rate
Labour
Rate
Through
Rate
4
5
6
7
Cum.
86.00
157.00
95.00
156.00
(a) Where building stone is specially arranged
by the contractor.
Cum.
89.00
159.00
97.00
159.00
(b) Where stone is available within 100 metres
from rock cutting already done.
Cum.
54.00
(c) Where stone is available within100 metres
from dismantled or failed structure.
Cum.
80.00
12.33 Boulder masonry in cement mortar (1:6) in
foundations and plinth.
Cum.
133.00
320.00
146.00
314.00
12.34 Boulder masonry in mud mortar in foundations
and plinth.
Cum.
86.00
153.00
95.00
153.00
12.35 Add for work in super structure 4 metres above
plinth level.
Cum.
27.00
27.00
30.00
30.00
12.36 Extra for above items for every additional storey of
height upto 4 metres above the top of structural
roof of lower storey.
Cum.
11.00
11.00
12.00
12.00
(a) Quartezite stone 2-3 faces
cum. of
masonry
45.00
-
49.50
-
(b) Quartezite stone 4-5 faces
cum. of
masonry
73.00
-
81.00
-
(c) Sand stone 2-3 faces
cum. of
masonry
37.00
-
41.00
-
(d) Sand stone 4-5 faces
cum. of
masonry
59.00
-
65.00
-
12.38 Hammer dressing of stone for face work
sqm. of
face
area
14.00
-
15.50
-
12.39 Fine chisel dressing (three-line dressing) of
stones.
sqm. of
dressed
area
61.00
-
67.00
-
12.32 Random rubble masonry or polygonal rubble
masonry (Kentish Rag) or random or polygonal
rubble built to courses in foundations and plinth
and superstructure laid dry.
59.00
-
88.00
-
12.37 Rough hammer dressing of boulders :-
Page 77
CSR-1987 [Re-print]
Sr. No.
Description
1
Unit
2
Plains
Sub-Mountionus
Labour
Rate
Through
Rate
4
Labour
Rate
Through
Rate
5
6
7
12.40 Ordinary chisel dressing (two-line dressing) of sqm. of
dressed
stones.
area
32.50
-
36.00
-
12.41 Rough tooled dressing (one-line dressing) of sqm. of
dressed
stones.
area
23.00
-
25.50
-
3
12.42 Dry stone masonry for work of purely temporary
nature (excluding dressing)
Cum.
33.50
-
37.00
-
12.43 Stone filling behind retaining walls.
Cum.
14.00
46.00
15.50
47.00
DHAJJI WALLING
12.44 Walling 12.5cm thick deodar framing unwrought
with stone in cement mortar 1:6 with plaster and
white washing but including treatment of frame
work for plastering.
Sqm.
-
-
50.50
307.00
12.45 Walling 12.5cm thick deodar framing unwrought
with stone in mud mortar without plaster and
without white washing but including treatment of
frame work for plastering.
Sqm.
-
-
49.00
293.00
12.46 Deduct from rate of item no. 12.44 and 12.45 if kail
wood is used instead of deodar.
Sqm.
-
-
-
31.40
12.47 Deduct from rate of item no. 12.44 and 12.45 if chil
wood is used instead of deodar.
Sqm.
-
-
-
64.00