Contents 3A Borrow Pit Dimensions September 2010 Corriemoillie Wind Farm Environmental Statement Appendix 3A – Borrow Pit Dimensions Appendix 3A – Indicative Calculations of Rock and Peat Requirements Volume of Rock Required Borrow Pit Dimensions Borrow Pit No. 1 2 3 4 5 Easting Northing 233366 868054 233817 234553 234984 233941 867465 867342 866100 867243 New/ Existing new new new new new Dimensions 100m x 100m x 7m 50m x 50m x 7m 150m x 150m x 2.7m 70m x 70m x 3m 50m x 50m x 7m Total Yield* Total Volume Required** Potential Yield (m3) 70,000 17,500 60,750 14,700 17,500 180,450 Reinstatement Task total length of Wind Farm access access track track construction 11377m Assumptions Rock required (m3) of which existing = 1646m assume all roads etc are 1m depth (worst case) assume all requires widening/ upgrading at 1m depth x 2m width x1646m of which new (full width)=9508m assume 1m depth x 5m width x 9508m (assume all types of road need approx same amt of rock fill) of which new (borrow pits)=223m assume 1m depth x 3m width x 223m 669 Turning area construction ~64m x 10m x 10 dead ends - assume 1m depth 6400 Passing area construction ~64m x 5m every 500m - so assume 22.7 on site, at 1m depth 7264 Crane hardstanding construction ~50m x 25m - assume 1.3m depth - 19 in all Culvert installation ~1 culvert/500m x 6m - assume built in access track calculations Water crossing 1 construction ~8m x 5m- assume built in access track calculations Water crossing 2 construction ~8m x 5m- assume built in access track calculations Water crossing 3 construction ~8m x 5m- assume built in access track calculations Water crossing 4 construction ~8m x 5m- assume built in access track calculations Water crossing 5 construction ~8m x 5m- assume built in access track calculations Tree felling Tree felling access track construction assume incorporated into rest of access track construction Construction compound Parking area installation ~40m x 10m - assume 0.6m depth Concrete area for refuelling installation ~10m x 10m - assume concrete - from site batching full full full full full 177,640 * approximate value takes into account projected wastage & bulking factor of 15% and 25% respectively. ** approximate volume of rock required for on site works (internal tracks, upgrade of existing track turbine foundations, hardstanding etc). 3292 51950 30875 Notes: Coordinates – Easting and Northings, approximate location only. Exact location to be determined by ground truing, and subject to limitations imposed by archaeological, ecological, landscape factors etc. Borrow Pit Dimensions – these dimensions are estimated, require ground truthing and subject to limitations imposed by archaeological, ecological, landscape factors etc. Depth of Borrow Pit (approximate depth that material could practicably be won to, including depth of overburden) – Pits 3 and 4 have been trial pitted – other depths are estimated based on ground features and site visits Potential Stone Quantity (approximate volume of material that may be won) – derived from estimated values of borrow pit area and depth of borrow pit, with allowance made for overburden and other losses. Significantly more or less materials may be excavated. Corriemoillie Wind Farm Environmental Statement 240 Appendix 3A – Page 1 Appendix 3A – Borrow Pit Dimensions Concrete batching area installation ~15m x 50m - assume 0.6m depth 450 Laydown area installation ~100m x 100m - assume 1m depth 10000 Substation Turbine foundation construction 15m x 10m x 0.4m 2208-3500 m 3 stone per turbine - from carbon calc (assume 3500m3 as worst case) depth of peat over turbines=approx 1.3m x 419m3 area=545m3 peat removed per turbine Aggregate required TOTAL ROCK REQUIRED (m3) Borrow pits 1 3 4 5 100m x 100m x 7m 50m x 50m x 7m 150m x 150m x2.7m 70m x 70m x 3m 50m x 50m x 7m TOTAL ROCK PRODUCED (assuming no OB etc) Appendix 9A – Page 2 66500 177700 2 Additional vehicle movements needed 60 70000 17500 60750 14700 17500 180450 Assume 1m3 aggregate is 4 tonnes and wagons have a 29 tonne payload 0 Corriemoillie Wind Farm Environmental Statement Appendix 3A – Borrow Pit Dimensions Peat Depth Calculations Peat Depth Class - 0.2m intervals 0-0.2 ID Access tracks 0.2-0.4 0.4-0.6 0.6-0.8 0.8-1 1-1.2 1.2-1.4 1.4-1.6 1.6-1.8 1.8-2 2-2.2 2.2-2.4 2.4-2.6 >2.6 Assumed depth (m) Number proposed Volume of peat disturbed (m3) 185.417 % of track in depth or shallower 1.63 1280.204 8145.357 8044.972 7906.795 9970.002 7473.368 5678.248 3061.152 1901.41 1052.271 751.116 1381.77 132.272 7.26 31.12 48.80 62.70 77.31 86.69 92.93 95.92 97.59 98.43 98.98 99.92 100.00 0.2 Length (m) 185.4 Width (m) 5 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2 2.2 2.4 2.6 2.8 640.1 2715.1 2011.2 1581.4 1661.7 1067.6 709.8 340.1 190.1 95.7 62.6 106.3 9.4 5 5 5 5 5 5 5 5 5 5 5 5 5 1 64 10 10 6400 22.7 7264 1500 10000 Turning Areas 0.8-1 Passing Areas Construction Compound Laydown Area Substation and Control Building Crane Hardstanding Areas 0.8-1 0.4-0.6 0.6-1.4 1 0.6 1 64 50 100 5 50 100 0.2-0.4 0.4 15 10 60 0.4-0.6 0.4-0.6 0.8-1 0.8-1 0.4-0.6 1-1.2 1-1.2 1-1.2 0.4-0.6 2-2.2 0.4-0.6 >2.6 1.2-1.4 0.4-0.6 1-1.2 1.6-1.8 >2.6 1-1.2 1.2-1.4 0.6 0.6 1 1 0.6 1.2 1.2 1.2 0.6 2.2 0.6 2.8 1.4 0.6 1.2 1.8 2.8 1.2 1.4 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 50.0 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 750 750 1250 1250 750 1500 1500 1500 750 2750 750 3500 1750 750 1500 2250 3500 1500 1750 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Corriemoillie Wind Farm Environmental Statement Assumptions/ comments median track depth = 0.8-1m Total length of track (existing, new and borrow pits - but not Lochluichart)=11377m Assume same average depth as tracks (1m) as locations unknown Assume same average depth as tracks as location unknown - one every 500m, so 22.7 proposed covers several depth classes Assumed to be the same as turbine centre depths Appendix 3A – Page 3 Appendix 3A – Borrow Pit Dimensions Turbine foundations Met mast Borrow Pits 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 1 2 3 4 5 0.4-0.6 0.4-0.6 0.8-1 0.8-1 0.4-0.6 1-1.2 1-1.2 1-1.2 0.4-0.6 2-2.2 0.4-0.6 >2.6 1.2-1.4 0.4-0.6 1-1.2 1.6-1.8 >2.6 1-1.2 1.2-1.4 0.2-0.4 0.6-0.8 1-1.2 0-0.2 0-0.2 0.8-1 0.6 0.6 1 1 0.6 1.2 1.2 1.2 0.6 2.2 0.6 2.8 1.4 0.6 1.2 1.8 2.8 1.2 1.4 0.4 0.8 1.2 0.2 0.2 1 100 50 150 70 50 100 50 150 70 50 TOTAL PEAT DISTURBED 251.4 251.4 419 419 251.4 502.8 502.8 502.8 251.4 921.8 251.4 1173.2 586.6 251.4 502.8 754.2 1173.2 502.8 586.6 167.6 8000 3000 4500 980 2500 each turbine requires a cylindrical foundation of 25m diameter 419m2 assume foundation is same as turbines 141391.954 Indicative Peat Use in Restoration Reuse Assumption Amount Reused (m3) Road edge dressing assume peat is an average of 1m depth and 2m width on either side of the 11,377m of roadway allowing for a 45o batter to the roadway 22,754 Cable trenches assume these will have no net effect on peat excavation as they will be immediately backfilled with excavated peat Restoration of passing areas Replacement of excavated peat 7264 Restoration of construction compound Replacement of excavated peat 1500 Appendix 9A – Page 4 Corriemoillie Wind Farm Environmental Statement Appendix 3A – Borrow Pit Dimensions Restoration of laydown area Replacement of excavated peat 10,000 Covering turbine foundations with peat Assume 400m2 per turbine can be covered (hardstanding maintenance areas will be retained) 7600 Replacing excavated peat onto borrow pits Replacing excavated peat 18980 Engineering borrow pits to accept 2m of peat in total Excluding originally excavated peat 65820 Additional onsite uses (backfilling excavations, drain blocking, habitat restoration, further engineering of borrow pits etc) Unknown amounts TOTAL 111,164 Excess not used on site (approx) 30,228 –. Corriemoillie Wind Farm Environmental Statement Appendix 9A – Page 5