Surface Water Intakes

advertisement

EMERGENCY WATER SUPPLY   UNIT 5: SURFACE WATER INTAKES  

UNIT 5  

SURFACE WATER INTAKES 

What this unit is about

  emergency situations.

 

What you will learn

 

On completion of this unit you should:

·

·

A

FROM

WEDC designed and constructed to provide optimal raw water qualities and quantities,  and how they can be protected from physical damage;

· know how pumps can be used in surface water abstraction;

· understand how submerged weirs can be used to raise water levels at intake  points;

· be familiar with the potential impacts of emergencies on existing surface water  intake structures, and the tasks involved in the repair and rehabilitation of such  facilities; and

· be familiar with the arrangements that can be made for users to safely collect  water directly for surface water sources in the early stages of an emergency  response.

Edition 1.1  GJM  © WEDC  Loughborough University  UK   5.1

 

5.2

 

UNIT 5: SURFACE WATER INTAKES   EMERGENCY WATER SUPPLY  

Contents 

5.1 

5.2 

5.3 

5.3.1 

5.3.2 

5.3.3 

5.3.4 

5.4 

Introduction ....................................................................................... 5.3 

Siting and protecting intakes........................................................... 5.3 

Bulk intakes....................................................................................... 5.3

 

Single point intakes ............................................................................................... 5.4 

Sub­surface infiltration wells and galleries.......................................................... 5.10 

Weirs ................................................................................................................... 5.17 

Rehabilitation of existing intake structures.......................................................... 5.18

 

Individual collection........................................................................ 5.19 

Figures in this unit

 

Figure 5.1.  The problems caused if the pipe inlet is too near the surface or 

Figure 5.2. 

UNIT

Figure 5.3.  Intake using a side channel and screen................................................................ 5.7 

Figure 5.4. 

Figure 5.5. 

WEDC

Figure 5.6. 

Figure 5.7. 

Figure 5.8. 

Figure 5.9. 

Figure 5.10.  against the end of the pipe.................................................................................... 5.8 

A pumping unit mounted on a floating platform .................................................. 5.10 

A

TRIAL

FROM

Figure 5.11.  Infiltration well made of concrete rings sunk in the river bed.............................. 5.14 

Figure 5.12.  Infiltration well using a pipe with screened intake............................................... 5.15 

Figure 5.13.  Bank side infiltration gallery ................................................................................ 5.15 

Figure 5.14.  Temporary weir made of sand bags ................................................................... 5.17 

Figure 5.15.  Water supply intake on a small stream destroyed by floods .............................. 5.18 

Figure 5.16.  Examples of water collection platforms............................................................... 5.19 

Figure 5.17.  Support rail around water collection platform ..................................................... 5.20

Edition 1.1  GJM   © WEDC  Loughborough University  UK  

EMERGENCY WATER SUPPLY  

5.1 

UNIT 5: SURFACE WATER INTAKES  

Introduction

 

As we have seen in Unit 4, surface water sources such as rivers, streams, lakes and  ponds, can be good sources of water in emergency situations. In this unit we will look  at how intake structures can be used to abstract water from these sources.

 

5.2  Siting and protecting intakes

 

Intake sites should be selected where sufficient quantities of water can be abstracted  without adversely affecting downstream users: the techniques we have studies in Unit 

4 should be used for assessing surface water quantities; those described in Unit 2  can be used to investigate downstream use. 

Siting should also consider water quality: intakes should be located upstream of  potential sources of microbiological and chemical pollution (Unit 3). When ponds,  lakes, or reservoirs are used attention should be given to assessing the risk of algal  blooms, and where possible avoiding sources where such a risk is present (Unit 3). 

The catchment area above intake works should be protected from contamination, by  controlling upstream activities:

UNIT

· bathing, clothes washing, and animal watering should take place downstream of  intake works;

·

WEDC surface water, and other water intakes. 

Abstraction sites should, as much as possible, be selected in locations where water  A

TRIAL intakes on unstable swampy or sandy ground should also be avoided.

 

5.3  Bulk intakes

 

Bulk surface water intakes should be designed to reliably supply sufficient quantities  of good quality raw water. This can be achieved by designing intake works that allow  the abstraction of water with low sediment loads, at periods of low and high flow, and  that are protected from physical damage. In practice this involves:

· positioning inlets at  depths  that allow water to be abstracted throughout the year;

· using  channels or sub­surface structures  to direct flows, allowing lower intake  velocities (and consequently sediment loads) and inlets to be physically protected;  and

· using  screens  to reduce the intake of large sediments.

Edition 1.1  GJM  © WEDC  Loughborough University  UK   5.3 

UNIT 5: SURFACE WATER INTAKES  

5.3.1 

EMERGENCY WATER SUPPLY  

We will now to look at how these techniques are incorporated into two kinds of  surface water intake structure and at how pumps can be used in surface water  intakes.

 

Single point intakes 

Design  

Depth of inlet  

Inlet pipes should be positioned:

· at least 0.3 m below the surface of the water, in order to protect the inlet from  floating debris and, when pumping, to avoid the creation of vortices that result in  air being entrained into the intake pipe; and

· at least 0.3m above the source’s bed to reduce the intake of sediments (Figure 

5.1).

 

UNIT

A

TRIAL

FROM

WEDC

5.4

 

Figure 5.1.  The problems caused if the pipe inlet is too near the surface or  too close to the source bed  

Where water levels are not sufficient to meet these criteria, they can be raised by  constructing a temp subsurface weir or dam – discussed later. 

Inlets can be correctly positioned using a number of techniques including: suspending  the inlet from a float; securing the inlet in a rigid structure such as a bucket or crib;

Edition 1.1  GJM   © WEDC  Loughborough University  UK 

EMERGENCY WATER SUPPLY   UNIT 5: SURFACE WATER INTAKES   using rigid pipe work; or in freezing conditions, suspending the inlet through the ice 

(Figure 5.2). 

Suspending the inlet from a float has the advantage of allowing the inlet height to be  automatically adjusted with changes in water level. In deep water, such as lakes it  also allows the upper level of water (which will often have lower levels of sediments)  to be accessed. Floating inlets should be securely anchored to the bed and bank of  the water source. A variation of this technique is used when a floating pontoon is  used to support a pump (see later in this section). 

Securing the inlet in a perforated bucket, drum, crib, or concrete ring filled with coarse  stones allows the inlet to be protected against physical damage and can provide  coarse screening around the inlet reducing the intake of debris and detritus. 

Inlets can also be positioned using rigid pipe work secured to the bank or bed; a  technique which is likely to be more applicable for longer term installations.

 

Use of side channels  

Inlets can be positioned in a side channel offset from the main body of water, or in a  pond or tank fed by the channel. Side channels can be used to reduce the velocity of  the water around the inlet, and in doing so allow water with lower sediment loads to  UNIT by removing it from the main watercourse (Figure 5.3). 

WEDC is extremely sandy or porous. Where coarse screening using stones is combined with 

TRIAL

 

Screening  

· a coarse/primary screen positioned before/around the inlet

· a fine screen/strainer over the end of the inlet pipe. 

A coarse or ‘primary’ screen is used to remove larger floating and suspended debris. 

In conventional intake works bar screens (grates, often set at an angle) are often  used for primary screening. In and emergency a coarse screen can be improvised  using stones positioned around the inlet (Figure 5.2). 

Alternatively the open end of the inlet pipe can be fitted with a prefabricated strainer  to act as a coarse screen (Figure 5.4).

Edition 1.1  GJM  © WEDC  Loughborough University  UK   5.5

 

UNIT 5: SURFACE WATER INTAKES   EMERGENCY WATER SUPPLY  

UNIT

A

TRIAL

FROM

WEDC

5.6

 

Figure 5.2. Simple arrangements of pump suction inlets

Edition 1.1  GJM   © WEDC  Loughborough University  UK  

EMERGENCY WATER SUPPLY   UNIT 5: SURFACE WATER INTAKES  

UNIT

Figure 5.3.  Intake using a side channel and screen 

A

TRIAL

FROM

WEDC

Figure 5.4.  A prefabricated inlet strainer for a suction pipe

Edition 1.1  GJM  © WEDC  Loughborough University  UK   5.7 

UNIT 5: SURFACE WATER INTAKES   EMERGENCY WATER SUPPLY  

A fine screen can be made by securing fine­wire mesh over the end of the inlet pipe. 

When plastic pipe is used, the wire­mesh can be heat welded across the end of pipe  by placing a square of mesh onto a hot heating plate, and then pressing the end of  the pipe against the screen and heating plate (Figure 5.5). Alternatively the inside of a  prefabricated inlet strainer can be lined with fine mesh.

 

5.8

 

Figure 5.5. 

UNIT

 

Pumping from single point intakes   A higher ground. 

WEDC pumping efficiency. Make sure the inlet point is easy to access for cleaning.

  TRIAL and treatment facilities. More commonly, especially, in the initial stages of an  FROM

Different kinds of pumps can be used to draw water from inlets but most commonly  centrifugal pumps will be used (Units 11). These are able to draw water from up to 7m  below the pump (although pump performance will become inefficient at height  differences greater than 3m). Where the pump can be securely positioned within this  height range the pump can be mounted on the surface, with the suction pipe  connected to the inlet: (Figure 5.1). 

Where the height difference between the water surface level and the pump inlet is  greater than 0.7m, submersible centrifugal (or other) pumps, positioned in the water,  can be used (Figure 5.6).

Edition 1.1  GJM   © WEDC  Loughborough University  UK 

EMERGENCY WATER SUPPLY   UNIT 5: SURFACE WATER INTAKES  

Positioning surface mounted pumps  

Surface mounted pumping units can be positioned by the side of the water source, or  on a platform/pontoon floating on top of the water.

 

UNIT

WEDC

A

TRIAL

FROM

 

When positioned by the side of the water source, on a bank for example, a firm  section of land should be chosen, and one that is not liable to be flooded. The  pumping unit can be mounted on a wooden pallet, or a more permanent concrete  foundation can be installed (Unit 11). 

Pumps and pumping units can also be mounted on a floating platform/pontoon 

(Figure 5.7), an arrangement that will reduce the height between the pump and the  inlet, and in doing so increase pump efficiency. Where such an arrangement is used  the floating platform should be securely anchored, and the mooring ropes, and  pump’s delivery pipe must be long and well secured to allow for changes in water  level and, when used on a stream or river, increased flow rates.

Edition 1.1  GJM  © WEDC  Loughborough University  UK   5.9

 

UNIT 5: SURFACE WATER INTAKES   EMERGENCY WATER SUPPLY  

In freezing conditions the pumping unit can be positioned on the bank, and the inlet  placed through the ice. Alternatively if the ice is strong enough, the pump can be  mounted on the ice, and the power unit on the bank ­ Figure 5.2

 

5.3.2 

UNIT

Figure 5.7.  A pumping unit mounted on a floating platform   WEDC

Additional measures should be taken in freezing conditions to protect equipment from  the cold including:

·

· above the ground; removing

A

TRIAL

 around the pumping unit, and raising the unit 

FROM

· raising pipe work  above the ground/ice (on wooden blocks for example) at a  gradient that will allow pipe work to be drained when not in use.

 

Sub­surface infiltration wells and galleries

 

Infiltration well and gallery intake structures (Figure 5.8) typically have two  components:

· a collector well  – in the bank of the water source; and

· an inlet  – a well or gallery of perforated pipe work buried in the source’s bank or  bed. 

Although often involving longer construction times than the rapid installation intake  designs described above, such structures have the advantage of being able to access

5.10

  Edition 1.1  GJM   © WEDC  Loughborough University  UK 

EMERGENCY WATER SUPPLY   UNIT 5: SURFACE WATER INTAKES   sub­surface flows, which can allow water to be abstracted from apparently dry  ephemeral watercourses, and, in freezing conditions, from water sources where the  source is frozen above ground. 

We will now look in more detail at the collector well and inlet components of infiltration  wells and galleries.

 

UNIT

Figure 5.8. 

WEDC

Collector well   A

TRIAL inlet: additional depth should be given to allow the bottom of the well to act as a sump  for siltation. Collector wells can be constructed using the techniques for handdug well  construction: temporary well lining materials, such as corrugated steel rings, are well  suited to the rapid lining of collector wells (Unit 6). 

In some cases water can be pumped directly from the inlet without the need for a  collector well ­ for example screened infiltration inlets (see later in this unit) 

Although similar to a shallow well positioned in the bank of a surface water source 

(sometime called a ‘riverside well’), a collector well differs in that it is connected to the  source by a manmade inlet/conduit. However where bank soils have high levels of  hydraulic conductivity (i.e. are made up of coarse sand or gravel), simple wells  without manmade inlet/conduit structures, can be sunk (Figure 5.9).

Edition 1.1  GJM  © WEDC  Loughborough University  UK   5.11

 

UNIT 5: SURFACE WATER INTAKES   EMERGENCY WATER SUPPLY  

5.12

 

UNIT

A

TRIAL

FROM

WEDC

Figure 5.9.  Hand dug well close to river bank drawing water from the aquifer  connected to the river 

Infiltration inlets  

Sand and gravel filled trench inlet  

When a sand and gravel filled trench (Figure 5.10) is used:

· a trench is  dug  between the source and the collector well;

· the trench is then  backfilled  with coarse sand to allow basic filtration to take place 

­ the sand can be graded into coarser gravel closer to the collection well, in order  to minimise siltation inside the well.

Edition 1.1  GJM   © WEDC  Loughborough University  UK  

EMERGENCY WATER SUPPLY   UNIT 5: SURFACE WATER INTAKES  

UNIT

Figure 5.10.  Infiltration trench filled with sand and gravel   that, where necessary, temporary trench supports are used – Appendix 21 of Davis  excavations.

  A

 

TRIAL

Pre­cast concrete rings can be sunk into the bed of a water source (Figure 5.11) ­  techniques for the fabrication and sinking of rings are covered in Unit 6. Rings  positioned below the bed should ideally be porous, and graded layers of sand and  gravel placed in the base of the bottom ring to reduce the intake of sediments (to  prevent damage and encourage the intake of water that has been filtered by the river  bed). The top of the rings should be sealed with a concrete cover. Alternatively the  column can be extended above the top of the flood water level. 

A connector pipe or sand/gravel filled trench can be used to transmit flows to a  collector well, alternatively water can be pumped directly from inside the concrete  rings.

Edition 1.1  GJM  © WEDC  Loughborough University  UK   5.13 

UNIT 5: SURFACE WATER INTAKES   EMERGENCY WATER SUPPLY  

5.14

 

Figure 5.11. 

UNIT

 

Borehole screen inlet   surface water sources, and have been used particularly successfully to access sub­  inserted by manual excavation or drilling techniques such as hand auguring. The  A

TRIAL gravel pack around the screen by pumping, can all be applied to the design and  development of well screens sunk in the bed of surface water sources (Unit 6). 

Water can be abstracted from the inlet by connecting the suction side of a surface  mounted centrifugal pump.

Edition 1.1  GJM   © WEDC  Loughborough University  UK  

EMERGENCY WATER SUPPLY   UNIT 5: SURFACE WATER INTAKES  

Figure 5.12. 

UNIT

A

TRIAL

FROM

WEDC

Figure 5.13.  Bank side infiltration gallery

Edition 1.1  GJM  © WEDC  Loughborough University  UK   5.15 

UNIT 5: SURFACE WATER INTAKES   EMERGENCY WATER SUPPLY  

Infiltration galleries  

The inlet surface area, and therefore yield, can be increased by developing infiltration  galleries – sections of perforated or loosely jointed pipe laid in the source’s bank 

(Figure 5.13) or bed (Figure 5.8). 

Galleries in the bank can be constructed throughout the year, and should be used  where the hydraulic conductivity of river bank soil is high ­ i.e. in clay and silt free  sand and gravel. Test excavations and drilling can be used to assess bank soil type,  and select optimum sites. 

Where the hydraulic conductivity of the bank soil is low, infiltration galleries can be  constructed in the beds of ephemeral sources when water levels are low. 

Construction is unlikely to be feasible at other times of year, or in perennial  watercourses. 

Borehole screen, slotted, drilled or open jointed pipe can be used for the infiltration  gallery’s pipe work. The principles described in Unit 6 for borehole intake design can  be used for designing an infiltration gallery, these include:

· analysis of the  soil  to see if an artificial gravel pack is required (it may be possible  to use the sediments of the river bank/bed ­ if these sediments are too small and  UNIT sediments);

· selection of  screen slot size ; and

TRIAL

WEDC

· establishing a  diameter and length  of intake pipe where, in order to reduce head  m/s for the known slot size and  design abstraction rate . 

A a 100mm diameter infiltration pipe gives a yield of 1 litre/minute/meter of infiltration  pipe. This is equivalent to 6m³/10hours/10meters. 

It is recommended that pipes are:

· positioned between 0.5m and 1m  below  the source’s bed; and

· buried  on  0.3m of gravel media 

Trench width is recommended to be about twice the depth of the pipe (giving widths  of around 1.6m). When more than one pipe is laid in parallel in the source’s bed, the  pipes should be laid at least 3m apart to reduce interference (Davis and Lambert, 

2002). 

An example of an infiltration gallery design is given in the Self­Asessment Questions  for this Unit.

5.16

  Edition 1.1  GJM   © WEDC  Loughborough University  UK  

EMERGENCY WATER SUPPLY   UNIT 5: SURFACE WATER INTAKES  

Further reading:  Davis and Lambert (2002), Infiltration galleries, p.216­218.

 

5.3.3  Weirs

 

Submerged weirs positioned below a stream or small river intake, can be used to  increase the depth of water at the intake site, and reduce the flow velocity above the  weir, allowing heavier solids to settle out of the water (Figure 5.14). 

Temporary weirs can be constructed from dense impermeable media such as rocks,  boulders, sandbags, or gabion baskets. Woven fabric sacks, made from materials  such as hemp or jute, filled with a dry concrete mix (1:6:8, cement:sand:gravel) and  sewn shut can also be used: the sacks can be placed directly in the water; the  sacking will hold the concrete mix in place until it sets; the weight of the bags will  allow them to mould themselves together so that they interlock solidly (Jordon, 2000). 

Care must be taken when raising the water to level that land upstream of the weir will  not be flooded even during periods of high flow. Consideration should also be given to  the downstream impacts of structural failure.

 

UNIT

A

TRIAL

FROM

WEDC

Figure 5.14.  Temporary weir made of sand bags

Edition 1.1  GJM  © WEDC  Loughborough University  UK   5.17 

EMERGENCY WATER SUPPLY   UNIT 5: SURFACE WATER INTAKES  

5.3.4  Rehabilitation of existing intake structures

 

Existing surface water intake structures can be damaged or destroyed in  emergencies, reducing the capacity, or rendering inoperable, the supply systems that  are dependent on them (Figure 5.15). Structurally damaging disasters such as floods,  landslides, earthquakes and volcanic activity are particularly likely to cause damage  to intake works. Intake screens and inlets may be broken, blocked or buried by  debris; foundations may be eroded or destroyed, causing structural damage such as  cracking, subsidence or collapse to intake structures. 

Temporary rapid installation intakes, such as the ones that we have studied above,  can be set­up in parallel with damaged ones, in order to supplement, or substitute  supplies, while cleaning, repair and reconstruction takes place. 

Blockages should be cleared, and where possible structural damage made good. 

Foundations and protective structures may have to be strengthened. Longer term  rehabilitation should consider the causes of damage, and evaluate the possibility of  relocating and/or redesigning intake structures to take account of the damage that  has been caused, and the vulnerability that has been exposed.

 

UNIT

A

TRIAL

FROM

WEDC

5.18

 

Figure 5.15.  Water supply intake on a small stream destroyed by floods

Edition 1.1  GJM   © WEDC  Loughborough University  UK  

UNIT 5: SURFACE WATER INTAKES   EMERGENCY WATER SUPPLY  

5.4  Individual collection

 

Direct contact between users and surface water sources should be minimised in order  to reduce the risk of source contamination. Ideally this should be achieved by  developing water supply arrangements such as those previously described. However  in the initial stages of an emergency response, and in situations with a low density of  affected users, people may collect water directly from surface water sources. When  this is the case, collection areas should be designated as soon as possible and  structures such as platforms, steps and ramps constructed so that users can collect  water without coming in direct contact with the water source ­ Figure 5.16 

As we have seen, water collection points should be carefully located with  consideration given to water quantities, quality, the risk of physical damage, and the  impact of collection from these points on downstream users. 

Collection platforms can be constructed using a number of materials such as sand or  concrete filled bags, wood, or stone. Consideration should be given to the possibility  of fluctuating water levels ­ floating platforms can be used in these situations. The  needs of physically vulnerable users (children, elderly, disabled, pregnant women  etc.) should also be considered through such measures as providing a handrail for  safety and support (Figure 5.17).

  UNIT

A

TRIAL

FROM

WEDC

Figure 5.16.  Examples of water collection platforms  

In crowded situations water point supervisors may be needed to manage access. 

Supervisors can also be used to conduct bucket chlorination in order to disinfect  collected water (Unit 8).

Edition 1.1  GJM  © WEDC  Loughborough University  UK   5.19 

UNIT 5: SURFACE WATER INTAKES   EMERGENCY WATER SUPPLY  

Figure 5.17. 

A

FROM

UNIT

WEDC

5.20

  Edition 1.1  GJM   © WEDC  Loughborough University  UK  

Download