INTERNATIONAL MARITIME LAW ARBITRATION MOOT 2014 TEAM No. 9- CLAIMANT EAST CHINA UNIVERSITY OF POLITICAL SCIENCE AND LAW (CHINA) IN THE MATTER OF AN ARBITRATION HELD AT HONGKONG MEMORANDUM FOR THE CLAIMANT ON BEHALF OF: AGAINST: RELIABLE HOLDINGS INC. SUPER CHARTERS INC. “RELIABLE BUTTERLY” RESPONDENT/OWNERS CLAIMANT/CHARTERERS TEAM NUMBER 9 TAN WEN, SONG HONG, JIANG SHENGLI, FAN DI, ZHONG YAOYAO I MEMORANDUM FOR THE OWNERS TABLE OF CONTENTS Summary of Argument .......................................................................................................1 Summary of Facts ................................................................................................................ 1 ARGUMENTS PPESENTED ...........................................................................................3 1 The Charters’ claims against validity of arbitration proceeding must not be set up. ............................................................................................................................................ 3 1.1 The Charterers are not entitled to rely on Time Bar Clause........................................3 1.2 Even through the Charterers could be relied on Time Bar Clause (which we denied), discharge commencement date is not definitive. ....................................................4 1.3 Even through the Charterers could be relied on Time Bar Clause (which we denied), discharge commencement date should not be counted from 10 January 2012. ........................................................................................................................................................... 5 1.4 Even through the Charterers could be relied on Time Bar Clause (which we denied), the limitation time with 20 days is too short to comply with commercial practice............................................................................................................................................ 6 1.5 It is under general commercial intention and true construction that Owners commence the arbitration underlying Time Bar Clause......................................................6 2 The arbitration was duly commenced on 28 January and the Owners’ Claims was not time barred............................................................................................................. 8 2.1 The arbitration has jurisdiction to hear these proceedings and British law should be applied to this case. ................................................................................................................. 8 2.2 The appointment of Mr. Smith as the Owners’ arbitrator made in name of Reliable Tanker Inc (‘RTI’) is valid and the arbitration is validly commenced subsequently................................................................................................................................... 8 2.3 There was a clear misnomer in Owners’ notice of appointment, which did not impact the commencement of arbitration. ..............................................................................9 2.4 The behavior of Charterers’ filing Defence & Counterclaim Submissions should be regarded as its implied admission to the commencement of the arbitration...........10 3. The freight was duly earned by the Owners under the Charterparty and the Charterers are liable to pay the freight and the resultant interests.......................11 3.1 The Charterparty between the Owners and the Charterers was concluded on 19 November 2011. .......................................................................................................................... 11 3.2 The Owners’ Standard Terms are incorporated into the Charterparty as part of it. II ........................................................................................................................................................ 12 3.3 The approach voyage has commenced on 19 November 2011 and the Vessel heading to the bunker port is part of the voyage. ...............................................................13 3.4 The advance freight is earned in full discounteless and non-returnable upon lifting subjects that the Charterers are obliged to pay 95% of freight.......................................14 3.5 Even though the Charterparty was terminated by the Charterers thereafter, the Charterers are still liable to pay the due freight. ................................................................16 4. The Owners are not liable for any damages arising from the delayed arrival. ............................................................................................................................................... 17 4.2 The Charterers should not cancel the contract based on laycan clause. .................18 4.3 The Charterers should not cancel the contract based on the warranty clause of reasonable dispatch.................................................................................................................... 19 4.4 In presence of arguments above, the Owners are not liable for damages and losses arising from delayed arrival. ...................................................................................................23 5. If the Charterers elect to cancel the contract based on the Owners Standard Terms Clause 2, they should not claim any damages against the Owners. ..........23 5.1 The Owners’ Standard Terms Clause 2 applied...........................................................23 5.2 The Charterparty was cancelled in a “without recourse” way..................................23 5.3 The Charterers should not claim any damages against the Owners. .......................24 PRAYER FOR RELIEF ..................................................................................................25 III LIST OF AUTHORITIES CASES Odfjfell Seachem v. Continentale Des Petroles [2005] 1 Lloyd’s Rep. 275.............4, 5 Pera Shipping Corporation v Petroship SA [1985] 2 Lloyd's Rep 103......................5 A/S. Renal v. Arcos, Ltd. [1937] 58 Lloyd’s Rep. 287...............................................6, 7 Metalimex Foreign Trade Corporation v. Eugenie Maritime Co. Ltd. [1962] 1 Lloyd’s Rep. 378........................................................................................................................6 National Shipping Company of Saudi Arabia v. BP Oil Supply Company [2012] 1 Lloyd’s Rep. 18.............................................................................................................7 Bananaft International Co. S.A. v. Avant Petroleum Inc. [1982] 1 Lloyd’s Rep. 448.................................................................................................................................7 Bernuth Lines Limited v High Seas Shipping Limited [2005] EWHC 3020 (Comm).........................................................................................................................9 Dumford Trading AG v. Oao Atlantrybflot [2005] EWCA Civ 24...............................10 Investors Compensation Scheme Let v. West Bromwich Building Society (No.1) [1988] 1 W.L.R. 896. ..............................................................................................................10 Davies v. Elsby Brothers Ltd [1961] 1 WLR 170........................................................10 Vee Networks Ltd v Econet Wireless International Ltd [2004] EWHC 2909............11 Welex AG v Rosa Maritime Limited, [2002] EWHC 762 (Comm) ............................12 Sea Trade Maritime Corp v Hellenic Mutual War Risks Association (Bermuda) Ltd (The Athena), [2006] ..................................................................................................13 Automatic Electric Telephone Co. v. Union Steamship Co. Justice of Macdonald.....13 Compania Naviera General S.A. v. Kerametal Ltd. [1981] 2 Lloyd’s Rep. 559........14 The Karin Vatis, Vagres Compania Maritima S.A. v Nissho Iwai American Corporation [1988] 2 Lloyd’s Rep. 330....................................................................15 The Dominique: Bank of Boston Connecticut) v European Grain & Shipping Ltd. [1989] 1 Lloyd’s Rep 431......................................................................................15,16 Henriksens Rederi A/S v T.H.Z. Rolimpex [1973] 2 Lloyd’s Rep. 333........................15 The Aries: Aries Tanker Corporation v Total Transport Ltd. [1977] 1 Lloyd’s Rep. 334...............................................................................................................................15 The Alfa Nord: A/S Gunnstein & Co. K/S v Jensen, Krebs and Nielsen [1977] 2 Lloyd’s Rep. 434..........................................................................................................15 Mcdonald v Dennys Lascelles Ltd. [1933] 48 C.L.R. 457, 476-477............................16 The Simona [1988] 2 Lloyd's Rep. 199........................................................................18 Mihalis Angelos [1970] 2 Lloyd’s Rep. 43..................................................................18 Tidebrook Maritime Corporation v Vitol SA of Geneva [2006] EWCA Civ 944........18 The Mihalis Angelos [1971] 1 QB 164.........................................................................19 The Helvetia-S [1960] 1 Lloyd’s Rep 540. ..................................................................19 The Simona: Heymans v Darvins Ltd [1942] AC 356.................................................19 The Kriti Rex [1996] 2 Lloyd’s Rep 171......................................................................20 IV Hong Kong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha Ltd [1962] 2 Q.B. 26.......21 The Seaflower: BS&N Ltd (BVI)v Micado Shipping Ltd [2001] 1 Lloyd`s Rep.341...21 The Wickman v Schuler [1974] AC 235........................................................................21 Mersey Steel & Iron Co. v. Naylor, Benzon & Co. [1884] 9 App. Cas. 434................22 Heyman v. Darwin, Ltd., [1942] A.C. 356.....................................................................22 Suisse Atlantique Societe’d Armement Martime S.A. v. N.V. Kolen Centrale [1967] 1 A.C.361..............................................................................................................................22 Cehave N.V. v. Bremer Handelsgesellschaft, [1976], Q.B. 44......................................22 Federal Commerce & Navigation Co. Ltd. v. Molena Alpha Inc., [1979] A.C. 757....................................................................................................................................22 Jackson v Union Marine Insurance Co [1874] LR 10 CP 125...............................22,24 The Madeleine [1967] 2 Lloyd’s Rep 224...................................................................24 STATUTES Arbitration Act 1996(UK)..............................................................................................8 The Unfair Contracts Terms Act 197........................................................................24 OTHER AUTHORITIES Lewison, The Interpretation of Contracts, 2nd Edition paragraph 11.15. .....................7 McKendrick, Ewan (2007). Contract Law (7th ed.)..................................................12 Laurence Koffman and Elizabeth Macdonald, The Law of Contract, (Oxford University Press, 7th Edition) ....................................................................................13 John F Wilson , Carriage of Goods by Sea by 6th edition.....................................13,17 V Summary of Argument Reliable Holdings Inc. (‘Owners’) commenced arbitration against Super Charters Inc. (‘Charterers’) for freight earned by Owners according to the Charterparty and damages due to the cancellation of Charterparty by Charterers. Charterers excluded Owners’ arbitration rights in light of the Time Bar Clause, which ignored the validity of Time Bar Clause and proceeding of arbitration commencement. Further, the Charterers are liable to pay the freight and the resultant interests earned by the Owners under the Charterparty. Besides, the Owners should not bear liability of any damages arising from the delayed arrival. Summary of Facts 1. Reliable Tankers Inc (RTI, the Owners), a renowned and trusted shipowner, made a great deal with Super Charters Inc (the Charters) on 19 November 2011. Through several twists and turns with contracting parties, the formal charterparty got mutual consent and was attached to the E-mail sent by RTI on 19 November 2011. 2. The Charterparty required Owners to transport 260,000mt crude oil from Blueland (‘loading port’) to Indigoland (‘discharging port ’). 3. As contract commenced, the vessel Reliable Butterfly had finished discharging her last cargo a few days ago and started heading to her bunker port. Unfortunately, the vessel was arrested at the bunker port for RTI’s arrearage to the bunker suppliers. Despite constantly endeavor, the vessel could not be 1 released from arrest and the Owner was unable to give a revised laycan. 4. Through the E-mail sent by the Charters on 27 November, the Charters indicated that the Vessel could not meet her Laycan and they declined any revises ETA/Laycan, which leading the cancellation of Charterparty. Moreover, the Charters claimed for losses and damages due to the delay of vessel. 5. On 28 November, Owners rejected that they were in breach, argued that they were relieved of all liabilities by terms of “Cancellation Provision” in their Standard Terms, and reminded that freight remained outstanding. In addition, Owners suggested that they have a sister VLCC to Reliable Butterfly, which may be suitable to perform the fixture in her place a few days later. However, Charterers did not adopt this suggestion. 6. On 3 January 2012, RTI was merged with Reliable Holding Inc. (RHI). On 28 January, according to the terms of Charterparty, an arbitration was taken in the name of Reliable Tanker Inc. and appointed Mr. Smith as an arbitrator. 7. However, the Charters considered the arbitration appointment as an invalid one due to misnomer of Owners and the claims which were time-barred, while the Charters still appointed Mr. John as arbitrator in the E-mail replied on 12 February 2012. 8. On 24 February 2012, the Owners reiterated that notice of arbitration was a valid one and RHI was the new merged entity on behalf of the Charters’ contractual counterparty. 9. On 14 March 2012, Owners submitted the letter of claim to arbitration. Owners 2 claimed a declaration of cancellation as set out, the sum of USD 4,935,368.75 by the way of freight or damages, interest, costs, and further of other relief. Charterers, however, counterclaimed that there are two references, that the first reference commenced by Reliable Tanker Inc. was nullity, that Reliable Holding Inc. was precluded the right to bring counterclaim in the second reference due to the contractual time bar in Clause 4 of Charterers’ Stander Terms, and that RHI was liable for damages of increasing freight, about USD 824,000, extra payment to both loading port and discharging port for delayed arrival in amount of USD450,000, other interest and costs. ARGUMENTS PPESENTED 1 The Charters’ claims against validity of arbitration proceeding must not be set up. 1.1 The Charterers are not entitled to rely on Time Bar Clause. In light of the limitation defence by the Charters, arbitration should be commenced by at latest 20 days after discharge or discharge would have taken place.1 However, the Charters ignore whether Time Bar Clause2 should be applied to Owners, which rules that Charters could be released from all liability in respect of any claims Owners may have under this Charterparty unless an arbitration has been presented to Charters within 20 days from discharge or of the date discharge should have taken place.3 Due to Charters’ cancellation of the Charterparty4, no cargo discharge would be 1 Facts, p109: Claim Submissions by Respondent par 3. Facts, p 88: Standard Terms of Business by Respondent cl 4. 3 Facts, p 88: Standard Terms of Business by Respondent cl 4, Claimant’s letter dated 19 November 2011. 4 Facts, p 96: Respondent’s letter dated 27 November 2011. 3 2 finished or happened. Consequently, on the true construction of the charterparty the owners’ claim for freight is not within Time Bar Clause and in circumstances where there was no discharge and there was no contractual period within which the claim had to be presented with full supporting documentation.5 Furthermore, the Charterers have no prospect to defend the Owners’ claim on the grounds of the so-called limitation defence successfully. 1.2 Even through the Charterers could be relied on Time Bar Clause (which we denied), discharge commencement date is not definitive. It is obvious that when no cargo has been discharged under the Charterparty, commencement date under Time Bar Clause should be circulated from when discharge would have taken place. Nevertheless, Charters garbled the letter from the Owners sent on 19 November 2011 and unilaterally recognized the date when discharge would have taken place was 10 January 20126, which was just the estimation by Owners. Therefore, under the circumstance that no definitive discharge commencement date could not be affirmed, it is void to run from limitation of arbitration with an uncertainty date of laytime commencement. Furthermore, a time-bar clause must be clear and unambiguous if effect is to be given to it. Thus, if there is any residual doubt about the matter, the ambiguity is to be resolved in such a way as not to prevent an otherwise legitimate claim from being 5 6 Odfjfell Seachem v. Continentale Des Petroles [2005] 1 Lloyd’s Rep. 275. Facts, p 89: Claimant’s letter dated 19 November 2011. 4 pursued7. Consequently, a Time Bar Clause with uncertain discharging time is quite ambiguous and has no impediment to Owners’ proceeding right. 1.3 Even through the Charterers could be relied on Time Bar Clause (which we denied), discharge commencement date should not be counted from 10 January 2012. As to common business practice, there are various indeterminacies under carriage of goods by sea, such as heavy weather or government action, like present case. Thus, even if an experienced captain could not give a precise ETA without any revision. There is no evidence putting forward to suggest what speed is the average vessel sailing speed and warrant a probable length of contractual voyage.8 Moreover, as both parties affirmed9, the latest discharging finish time, due to shutdown of refinery, was 15 January 2012. Therefore, the discharging commencement date was between temporal intervals, which means, earliest start time was 10 January, while latest start time was 15 January. Accordingly, the arbitration was commenced at a proper time zone and not time barred. 1.4 Even through the Charterers could be relied on Time Bar Clause (which we denied), the limitation time with 20 days is too short to comply with commercial practice. To say the least, even though Time Bar Clause10 is applicable (which we denied), the 7 Pera Shipping Corporation v Petroship SA ("The Pera") [1985] 2 Lloyd's Rep 103. See Odfjfell Seachem v. Continentale Des Petroles [2005] 1 Lloyd’s Rep. 275. 9 Facts, p 89: Claimant’s letter dated 19 November 2011. 10 Facts, p 88: Standard Terms of Business by Respondent cl 4. 5 8 time limitation with 20 days is unconscionable. As to commercial customs, the time limitation under Time Bar Clause will be 90 days, 180 days11, or even longer 12 months12. For instance, the Aomoco Claims Clause where narrowing down Owners’ time limitation against Charterers, incorporated into the Charterparty, the claim limitation is reduced to more than 90 days. Comparatively, for the Owners’ perspective, 20 days time limitation with regard to Owners’ claims against Charterers is properly out of common business custom that the Owners consider such clause as invalid. 1.5 It is under general commercial intention and true construction that Owners commence the arbitration underlying Time Bar Clause 13. The commercial intention under Time Bar Clause seems to plainly ensure that claims were made by the Owners within a short period of final discharge so that the claims could be investigated and if possible resolved while the facts were still fresh.14 Moreover, the proper approach to the time bar clause was a requirement of clarity sufficient to achieve certainty rather than a requirement of strict compliance which, if applied inflexibly, could lead to uncommercial results.15 As a consequence, Owners commenced the arbitration and notified the Charterers promptly, which is compliance with the intention of Time Bar Clause. 11 See Odfjfell Seachem v. Continentale Des Petroles [2005] 1 Lloyd’s Rep. 275: “The limitation defence was based on cl.20 of the chater-party which provided: …the claim within 90 days of the completion of discharge of the cargo carried hereunder…with 180 days of the completion of discharge of the cargo carried hereunder.”. 12 See A/S. Renal v. Arcos, Ltd. [1937] 58 Lloyd’s Rep. 287: “Clause 24, which was as follow: Notice of any claim under this charter or under any bill of lading given hereunder must be given within 12 months of the date of the vessel’s arrival at final port of discharge otherwise all claims shall be deemed to be waived.”. 13 Facts, p 101: Claimant’s letter dated 28 January 2012. 14 Metalimex Foreign Trade Corporation v. Eugenie Maritime Co. Ltd. [1962] 1 Lloyd’s Rep. 378. 15 National Shipping Company of Saudi Arabia v. BP Oil Supply Company [2012] 1 Lloyd’s Rep. 18. 6 Furthermore, as we have discussed, the construction of Time Bar Clause should be much looser. The especially exacting principles of construction that apply to exemption clauses probably do not apply to time-bar provisions.16 Specifically, the owner would not, as a matter of common sense, be debarred from making factual corrections to claims presented in time, nor from putting a different legal label on a claim previously presented.17 Hence, the arbitration commenced by Owners dated on 28 January with misnomer is quite valid, due to the reason that notice of claim does not merely mean a precisely formulated claim with full details, but it must be a notice as will enable the party to whom it is given to take steps to meet the claim by preparing18. 2 The arbitration was duly commenced on 28 January and the Owners’ Claims was not time barred. 2.1 The arbitration has jurisdiction to hear these proceedings and British law should be applied to this case. By the terms of the Charterparty19, the parties agreed that any dispute arising under or in relation to or in connection with the Charterparty or the interpretation thereof or arising in or out of or in connection with the performance or the Charterparty shall be referred to arbitration in London in accordance with the 1996 Arbitration Act or amendments thereto and any such arbitration award shall be final and binding upon 16 Lewison, The Interpretation of Contracts, 2nd Edition paragraph 11.15. Bananaft International Co. S.A. v. Avant Petroleum Inc. [1982] 1 Lloyd’s Rep. 448. 18 A/S Rendal v. Arcos Ltd. [1937] 58 Lloyd’s Rep. 287. 19 Facts, p 49: ASBATANKVOY Part 2, CLS 24. 7 17 the parties thereto. Since the disputes here arisen by the Owner is the result of the Charterers’ being in breach of the Charterparty, they should be referred to arbitration according to the terms (namely the arbitration clause) of the Charterparty mentioned above, which is admitted by the Charterers and the Owners both. 2.2 The appointment of Mr. Smith as the Owners’ arbitrator made in name of Reliable Tanker Inc (‘RTI’) is valid and the arbitration is validly commenced subsequently. According to Article 14(4) of the 1996 Arbitration Act,20 when sending out the notice of appointment on 28 January, the arbitration (arbitral proceedings) should have already been commenced by the Owner.21 And the Charterers’ suggestion that the appointment is invalid and the arbitration has not been validly commenced because of the title of arbitration is totally an opportunistic and ill-conceived one. As at the time of commencement of the arbitration, RTI had merged by universal succession with Reliable Holdings Inc (‘RHI’). And as a result of merger, an action in the name of RTI was therefore necessarily an action by RHI. Besides, by way of universal succession, the new entity RHI should inherit all the rights and obligations from RTI, including substantive rights and procedural rights. 22 The arbitration was commenced using (very slightly) out of date headed notepaper in 20 Article 14(4) of the 1996 Arbitration Act,’Where the arbitrator or arbitrators are to be appointed by the parties, arbitral proceedings are commenced in respect of a matter when one party serves on the other party or parties notice in writing requiring him or them to appoint an arbitrator or to agree to the appointment of an arbitrator in respect of that matter.’ 21 Bernuth Lines Limited v High Seas Shipping Limited [2005] EWHC 3020 (Comm). 22 Facts, p 113: Expert Report of Tim Bowman. 8 the name of RTI. And this clear misnomer has already been corrected by the claims which the Owner submitted later23(on 14 March). 2.3 There was a clear misnomer in Owners’ notice of appointment, which did not impact the commencement of arbitration. There was a clear misnomer in Owners’ notice of appointment24 in that the Owners, in error, thought that RTI was the current name of the contractual party under the Charterparty. So the Owners just intended to appoint on behalf of the ‘owners’ under the Charterparty, and the Charterers could have been under no genuine misapprehension as to who was commencing the arbitration against it. The maxim falsa demonstratio non nocet cum de corpore constat has often been applied to correct a misnomer or mistaken designation25. Moreover, all that was required was that it should be clear that something had gone wrong with the language and that it should be clear what a reasonable person would have understood the parties to have meant.26 Furthermore, In English law as a general principle the question is not what the writer of the document intended or meant but what a reasonable man reading the document would understand it to mean; and that is the test which ought to be applied as a general rule in cases of misnomer.27 Thus, Owners mis-headed title of letter which commenced the arbitration, while, in light of commercial practice, there was no misunderstanding between mutual parties. 23 Facts, p 105: Claim Submissions by Claimant. Facts, p 101: Claimant’s letter dated 28 January 2012. 25 Dumford Trading AG v. Oao Atlantrybflot [2005] EWCA Civ 24. 26 Investors Compensation Scheme Let v. West Bromwich Building Society (No.1) [1988] 1 W.L.R. 896. 27 Davies v. Elsby Brothers Ltd [1961] 1 WLR 170. 9 24 2.4 The behavior of Charterers’ filing Defence & Counterclaim Submissions should be regarded as its implied admission to the commencement of the arbitration. The Charterers had already known the intact of the Owners’ appointment in the name of RTI on 12 February, by stating ’We therefore consider that your appointment is invalid.’ in the E-mail which it sent to the Owners. But it never submitted a formal objection to this appointment or the arbitration which was commenced on 28 January through the appointment mentioned above. Therefore, according to Article 73(1) of the 1996 Arbitration Act,28 although the Charterers counterclaimed that the so called ‘first reference’ claimed by the Owners was a nullity on 14 march, it had already lost the right to object to the arbitration which commenced on 28 January at that moment., and had no right to object to the validly commenced arbitration any longer.29 Moreover, the behavior of Charterers’ filing Defence & Counterclaim Submissions should also be regarded as its implied admission to the commencement of the arbitration claimed by the Owners through its appointment on 28 January on the other hand. 28Article 73(1) of the 1996 Arbitration Act,’If a party to arbitral proceedings takes part, or continues to take part, in the proceedings without making, either forthwith or within such time as is allowed by the arbitration agreement or the tribunal or by any provision of this Part, any objection(a) that the tribunal lacks substantive jurisdiction, (b) that the proceedings have been improperly conducted, (c) that there has been a failure to comply with the arbitration agreement or with any provision of this Part, or (d) that there has been any other irregularity affecting the tribunal or the proceedings, he may not raise that objection later, before the tribunal or the court, unless he shows that, at the time he took part or continued to take part in the proceedings, he did not know and could not with reasonable diligence have discovered the grounds for the objection.’ 29 Vee Networks Ltd v Econet Wireless International Ltd [2004] EWHC 2909. 10 3. The freight was duly earned by the Owners under the Charterparty and the Charterers are liable to pay the freight and the resultant interests. 3.1 The Charterparty between the Owners and the Charterers was concluded on 19 November 2011. The Charterparty was concluded on 19 November 2011. The contract is considered to be concluded when the fact is established that the two parties had come to a final and complete agreement, for, if not, there was no contract. The E-mail sent to the Owners by the Charterers on 10 October 2011 stating basic contractual requirements constituted the invitation of offer.30 Then the content if the E-mail and the attached recap sent to the Charterers by the Owners on 17 November 2011 constituted the offer.31 And the Charterers made the acceptance on 19 November 2011 through its E-mail by stating, ’You have a deal’ and asking for a drawn up charter32. At last, the Owners fully fixed with subjects by a revised recap before the deadline required by the Charterers on the same day. Moreover, the Charterparty was concluded on 19 November 2011 and was established and legally binding the Owners and the Charterers. Recap is a binding agreement. Since the Recap33 was appended to the Standard Charterparty, it also should be binding to both parties as part of the contract.34 30 See Facts, p2: Email of 10 October 2011. See Facts, p4-p45: Email of 17 November 2011. 32 See Facts, p46: Email of 19 November 2011. Gibson v Manchester City Council [1978] 2 All ER 583. Lord Denning, “but, as I understand the law, there is no need to llok for a strict offer and acceptance.” 33 Facts p51: Clean Recap. 34 Welex AG v Rosa Maritime Limited, [2002] EWHC 762 (Comm). Whilst a contract for chartering a ship is normally embodied, in due course, in a printed form, the parties agreement can remain in the written fax or telex exchanges: a signed Charterparty is unnecessary . In Welex AG v Rosa Maritime Limited, the court held that the charterparty was the agreement contained in a recap telex and the standard form to which it referred. And this explanation is consistent with the common commercial realities and accord with the duty on the Court to give an intelligent meaning to documents surrounding this commercial transaction. 11 31 3.2 The Owners’ Standard Terms are incorporated into the Charterparty as part of it. The Owners’ Standard Terms appended to the E-mail on 19 November 201135 are incorporated into the Charterparty that are binding to the Owner and the Charterer. Parties entered into agreement on 19 Nov. 2011 as mentioned above. All clauses of standard terms are under consideration by both parties pursuant to Clause 61 “Both parties special terms fully incorporated as per attached.” in recap36 and both parties are well acknowledged of all clauses of the Owner’s Standard Terms37. Furthermore, Standard terms incorporated into contract are accepted by usual practices in England. English law accepted incorporation of standard terms by the use of general words and particularly so when the terms were readily available and the question arose in the context of dealings between established players in a well-known market.38 Therefore, the Owners’ Standard Terms are incorporated into the Charterparty as part of it and all clauses are binding to both parties. 3.3 The approach voyage has commenced on 19 November 2011 and the Vessel heading to the bunker port is part of the voyage. The voyage under the Charterparty has commenced on 19 November. The Vessel 35 McKendrick, Ewan (2007). Contract Law (7th ed.). Palgrave Macmillan. The Standard Terms incorporation satisfies the three steps that are required by the valid incorporation of terms. 36 Facts p51: Clean Recap. 37 The Law of Contract 7th Edtion, by Laurence Koffman and Elizabeth Macdonald (Oxford University Press) 38 See Sea Trade Maritime Corp v Hellenic Mutual War Risks Association (Bermuda) Ltd (The Athena), [2006] EWHC 2530 (Comm) p735. In principle, English law accepted incorporation of standard terms by the use of general words and particularly so when the terms were readily available and the question arose in the context of dealings between established players in a well-known market. The principle did not distinguish between a term which was an arbitration clause and one which addressed other issues. 12 Relibale Butterfly has been ready for Super Charterers on 16 November. On the same day later of the Charterparty concluded, by email of 19 November sending from the Owners39, the Vessel started heading to her bunker port. Since then until the Vessel arriving the loading port, the Vessel was performed its preliminary voyage40. The words during the voyage cover a preliminary voyage to the port of loading which has been incorporated in the Charterparty.41 And that loading simply was part of the voyage, but seemed to consider, that a preliminary voyage to a port to load and thence to some objective port would, in the event of loading at some intermediate point, be part of a voyage, as to the goods first loaded42. Such preliminary voyage, heading to the bunker port was necessary and served for the Charterparty. Therefore, the approach voyage has still commenced since the Vessel heading to the bunker port. And the period from the Vessel at bunker port till arriving at loading port pertaining to a preliminary voyage, during when, the Owner initiated to fulfill its obligations under the Charterparty. 3.4 The advance freight is earned in full discounteless and non-returnable upon lifting subjects that the Charterers are obliged to pay 95% of freight. The freight is earned by the Owners in full discountless and non-returnable. On 19 November 2011, the Charterparty was concluded and therefore lifting subjects, which was also admitted by the Charterers by their Claim Submission43. Pursuant to the 39 See Facts p89: Email of 19 November. See Carriage of Goods by Sea by John F Wilson 6th edition (Pearson Longman). It will therefore be necessary for the vessel to undertake a preliminary voyage to the agreed port of loading, and this will form the first stage in the performance of the charterparty. 41 Automatic Electric Telephone Co. v. Union Steamship Co. Justice of Macdonald. 42 Ibid: Automatic Electric Telephone Co. v. Union Steamship Co. Justice of Macdonald. 43 See Facts p111: 19 of the Charterers’ Claim Submission. 13 40 Owners’ Standard Terms Clause 444, 95% of the freight was payable upon lifting subject in discountless and non-returnable. First, the freight was deemed earned in full upon lifting subjects. By case of the Lorna I45, Court held that there was no obligation to make any payment of or on account of freight until the expiration of the five-day period and if before the date of frustration advance freight has fallen due it remains payable despite the frustration of the contract. Analogous to our situations, the proper construction of the Freight Clause stipulated in the Owners’ Standard Terms is that the advance freight payment fell due on the date of lifting subjects. That is to say, the whole freight was deemed to earn46 on date of lifting subjects, the debt fell due and should be paid discountless and nonreturnable. Alternatively, Hobhouse J in case the Dominique47even hold that the debt existed and deemed earned from the moment the Bills of lading were signed, “prepaid within five days” nevertheless did not affect the accrual of the freight on the date of signing the Bills of lading. The contrast between the Lorna I and the Dominique does not conflict to our arguments. From another perspective, if the true construction of the freight clause is the Owners only can earn the freight by arriving discharge port or completing discharge, the consequence would be that there is no distinction between 44 Facts p87: Clause 4 of the Owners’ Standard Terms. The Lorna I: Compania Naviera General S.A. v. Kerametal Ltd. [1981] 2 Lloyd’s Rep. 559; [1983] 1 Lloyd’s Rep. 373. The freight clause is “16. Freight non-returnable cargo and/or vessel lost or not lost to be paid . . . to the Owners . . . as follows: 75% . . . within 5 . . . days after Master signed Bills of Lading and the balance after right and true delivery of the cargo and receipt of documents from discharging ports.” 46 “Deemed to earn” is the same of “earned”, see The Karin Vatis, Vagres Compania Maritima S.A. v Nissho Iwai American Corporation [1988] 2 Lloyd’s Rep. 330. 47 The Dominique: Bank of Boston Connecticut) v European Grain & Shipping Ltd. [1989] 1 Lloyd’s Rep 431 14 45 freight prepaid and freight collect, which went against the purposes of advance freight. Thus, 95% freight fell due on 19 November 2011 and it remains payable despite of the later frustration and termination of the contract. Secondly, such due freight payment is without discount. That means as long as the freight falls due and remains unpaid, even the Charterers are entitled to claim damages caused by the Owners, deduction from freight is not allowed by ordinary practice48 in the case that the freight is agreed to be paid without discount. In the Alfa Nord49, which is analogous to our case, the Judge hold that there is no right of set-off for claims for damages for breach of contract, whether for loss of or damage to goods or for alleged failure to prosecute a voyage with reasonable dispatch or otherwise (which we denied and we will elaborate in the following arguments), against a claim for freight. Therefore, in our case, “discountless” means that the Charterers should pay the due freight in full unconditionally from the moment of lifting subject even the Charterers filed a claim of damages thereafter, failure of which constitutes a repudiatory breach of contract, which is also affirmed by judgments of the Dominique50. 3.5 Even though the Charterparty was terminated by the Charterers thereafter, the Charterers are still liable to pay the due freight. Contract termination by the Charterers did not affect the facts that the outstanding freight still needs to be paid. “Both parties are discharged from further performance of 48 The Brede: Henriksens Rederi A/S v T.H.Z. Rolimpex [1973] 2 Lloyd’s Rep. 333; The Aries: Aries Tanker Corporation v Total Transport Ltd. [1977] 1 Lloyd’s Rep. 334. 49 The Alfa Nord: A/S Gunnstein & Co. K/S v Jensen, Krebs and Nielsen [1977] 2 Lloyd’s Rep. 434 50 Ibid: The Dominique: Bank of Boston Connecticut) v European Grain & Shipping Ltd. [1989] 1 Lloyd’s Rep 431 15 the contract, but rights are not divested or discharged which have already been unconditionally acquired. Rights and obligations which arise from the partial execution of the contract and causes of action which have accrued from its breach alike continue unaffected”51, quoted by the Judge in the Dominique52. The statement indicates that contract termination did not affect the rights that are acquired before the termination of contract. The reason of why the Charterparty is terminated or who is in repudiatory breach of contract should not be taken into account as hold by judges in the Dominique53, the Owner was repudiated the contract. Therefore, in accordance with the principles of law referred to above, even if the contract was rescinded by the Charterers, they should still pay the due freight the resultant damages. 4. The Owners are not liable for any damages arising from the delayed arrival. 4.1 The Charterers should not cancel the contract based on ETA clause. The Charterers should not cancel the contract based on ETA clause. By clean recap attached on email of 19 November 2011, the Owners and the Charterers agree that ETA LOADPORT 3 DECEMBER 2011.54 Concerning ETA in shipping practice, the starting point for any estimate of arrival time is to be found in information relating to the current position of the vessel and the time at which it will be free from any 51 Mcdonald v Dennys Lascelles Ltd. [1933] 48 C.L.R. 457, 476-477, by Dixon J. Ibid: The Dominique. 53 Ibid: The Dominique. 54 See Facts p47: Clean Recap. 16 52 existing commitments.55 That is to say, ETA is merely an approximate estimate time of arrival to loading ports, breach of which would not repudiate the contracts unless it fundamentally prevents the performance of the Charterparty or an express obligation for the owner has been incorporated into the Charterparty. Corresponding to our case, the Owners have never undertaken any commitments to ETA by the wording of relevant clauses of the Charterparty. Moreover, the Charterers cancelled the contract ahead of the stipulated ETA56 where the Owners did not actually breach of ETA clauses at the moments of the cancellation. Thus conversely, if the Charterers terminate the Charterparty resting on the grounds that the Owners violated the ETA clause, the Charterers’ unilateral termination of the Charterparty constitutes a repudiatory breach of contract. 4.2 The Charterers should not cancel the contract based on laycan clause. The Charterers should not cancel the contract based on laycan clause. The clean recap provides that ETA load port is on 3 December 2011 at the very start.57 During the Vessel in dispute performed its preliminary voyage, by reason of the Vessel being arrested in bunker port, the Owner was unable to meet its ETA and LAYCAN as prescribed in Charterparty. The Charterers cancelled the Charterparty prior to the cancelling date constituting anticipatory breach of contract. It is manifest that the right of cancellation could not be validly exercised until the arrival of the cancellation date and any premature notice 55 Carriage of Goods by Sea by John F Wilson 6th edition (Pearson Longman). See Facts p47: ETA clause of Clean Recap; p96: email on 27 November 2011. 57 See Facts p47: Clean Recap. 17 56 purporting to cancel the contract constitutes an anticipatory breach and repudiation of the Charterparty.58 Laycan is not specific feature of voyage charters only, it is habitually used in the negotiation of charterparties, to refer to the earliest date at which the laydays can commence and the date after which the charter can be cancelled if the vessel has not by then arrived.59By custom rules, the Charterparty would create a right of cancellation of contract for the charterer but only limited to a time period. The charterer is not allowed to prejudge the issue by repudiating the charter before the cancelling date even though it is physically impossible for the chartered vessel to arrive at the loading port by that date.60 By case of The Simona61, the judgments hold that the charterers constituted an anticipatory breach of the charter while the charterers refused and gave notice of cancellation of the charter when the owners request an extension of the cancelling date prior to stipulated laycan. Analogous to our situation, as agreed in recap, it provides that LAYCAN 5-6 December 2011 (0001-1500HRS) to be narrowed down to one day in chopt.62 And by email of 22 November 201163, the Charterers changed the laycan to 5th December. That means the Charterers could only cancel such charter party later than 5 December. However, by Notice of Cancellation on 27 November 2011 sending by the Charterers, the Charterers cancelled the Charterparty prior to the 5 December. Thus, the Charterers constitute an anticipatory breach of contract upon such Notice of 58 The Simona [1988] 2 Lloyd's Rep. 199; Mihalis Angelos (1970) 2 Lloyd’s Rep. 43. Tidebrook Maritime Corporation v Vitol SA of Geneva [2006] EWCA Civ 944 at para 38: Rix LJ. 60 The Mihalis Angelos [1971] 1 QB 164; The Helvetia-S [1960] 1 Lloyd’s Rep 540. 61 The Simona: Heymans v Darvins Ltd [1942] AC 356 at p361. 62 See Facts p48: Clean Recap 63 See Facts p92: Email of 22 November 2011. 18 59 Cancellation. Therefore, the Owners did not breach of contract because of the Vessel missing its laycan. Conversely, the Charterers cancelled the Charterparty prior to the cancelling date constituting a repudiatory breach of contract. 4.3 The Charterers should not cancel the contract based on the warranty clause of reasonable dispatch. Whether the Charterers are entitled to cancel the Charterparty based on Clause 1 of ASBATANKVOY64 subjected to two main issues. First whether the Owners are in breach of such obligation to proceed to the loading ports with reasonable dispatch. Second is in alternative, even the Owners breached such stipulation, does it sufficiently entitle the Charterers terminate the contract? First, the Owners do not consider the delay occurred in preliminary voyage as breach of reasonable dispatch. Performance of this obligation is judged, not on a strictly objective basis, but in relation to what can reasonably be expected from the shipowner under the actual circumstances existing at the time of performance65. So long as such delay is attributable to causes beyond his control, and he has neither acted negligently nor unreasonably, the shipowner is duly full his obligations notwithstanding protracted delay.66 In this present case, although the Owners were obligated to proceed to the loading port with convenient dispatch,67 the delay was caused by Charterers’ breach, which means that Owners would have enough funds to pay the 64 See Facts p54. Carriage of Goods by Sea by John F Wilson 6th edition (Pearson Longman). 66 The Kriti Rex [1996] 2 Lloyd’s Rep 171. 67 See Facts p54, at 1. 19 65 bunker fee if the Charterers had paid the freight on time strictly in accordance with the Charterparty.68 In addition, the delay was a fact of life and was totally out of Owners’ expectation. Therefore, Owners should not be considered as act negligently or unreasonably, and the delay in approach voyage cannot be deemed as breach of reasonable dispatch. Alternatively, even if the Owners breached the obligation of proceeding to the loading port with reasonable dispatch, the Charterers could not terminate the Charterparty. Pursuant to the Clause 1 WARRANTY-VOYAGE-CARGO of ASBATANKVOY69, it stipulates that the vessel shall with all convenient dispatch proceed as ordered to Loading Port named in accordance with Clause 4 thereof. Whether the clause pertains to a condition or warranty is in determination of the justification of the Charterers cancelled the Charterparty by reason of the Owners in breach of such clause. Even if the title of the Clause defines such clause as WARRANTY (the opposite of Representation not Condition), it does not entitle the Charterers a right of cancelling the Charterparty70 while the Owners fail to prosecute the preliminary voyage with reasonable dispatch. Such clause designates the Owners an obligation of sailing to the loading port with reasonable dispatch, however, breaching of which the Owners may not certainly constitute repudiation to the Charterparty. The essence of such clause 68 Fact P93 at Para2 See Facts p54. 70 The Seaflower: BS&N Ltd (BVI)v Micado Shipping Ltd [2001] 1 Lloyd`s Rep.341. Waller LJ concludes that the following term of a contract should be considered as a condition …(iii) if it is so designated in the contract or if the consequences of its breach, that is, the right of the innocent party to treat himself as discharged, are provided for expressly in the contract: or…; Another case distinguished from our case is the Wickman v Schuler [1974] AC 235 where the clause expressly allows the charterer to terminate the contract if the vessel is not delivered by a specific date. 20 69 does not always follow the parties’ intention or the wording of the terms, however, this is mostly a question of fact fit for the determination of a jury.71 Further and most importantly, by authoritative case The Hong Kong Fir72where the judgments admit the existence of intermediate clause in contract that falls into neither Condition nor Warranty, there are some terms, the consequences of the breach of which may range from the trivial to the very serious, for instance, seaworthiness is a typical intermediate clause. The essential criteria established in The Hong Kong Fir to determine that whether one party breach of an obligation entitles the other party to cancel the contract is that whether the occurrence of those events deprived the charterers of substantially the whole benefit which it was the intention of the parties as expressed in the charter-party that the charterers should obtain from the further performance of their own contractual undertakings.73 If the non-performance or defective performance in breach of contract goes against the whole root to the contract, the innocent party could terminate such clause, if not, he merely can claim for damages for such stipulation breach74. In connection with our situations, both parties knew that if Reliable Butterfly could not sail from the bunker port by 25 November, it could not meet the laycan.75 And Charterers chose to terminate the Chaterparty,76, it could not be concluded that Charterers thereupon were deprived of 71 The Hong Kong Fir: Hong Kong Fir Shipping Co Ltd v Kawasaki Kisen Kaisha Ltd [1962] 2 Q.B. 26, para 41. Ibid: supra 73 Ibid: supra, para 61. Also affirmed by Mersey Steel & Iron Co. v. Naylor, Benzon & Co. (1884), 9 App. Cas. 434, at P. 444; Heyman v. Darwin, Ltd., [1942] A.C. 356, at P. 397; Suisse Atlantique Societe’d Armement Martime S.A. v. N.V. Kolen Centrale [1967] 1 A.C.361, at P.422; Cehave N.V. v. Bremer Handelsgesellschaft, [1976], Q.B. 44, at PP.60, 73; Federal Commerce & Navigation Co. Ltd. v. Molena Alpha Inc., [1979] A.C. 757, at P.779. 74 Jackson v Union Marine Insurance Co (1874) LR 10 CP 125. 75 Fact P94 21 72 the substantial whole benefit under this Charterparty. Therefore, even though even if the Owners breached the obligation of proceeding to the loading port with reasonable dispatch, the Charterers thereon could not terminate the Charterparty. Since that the Charterers may not resort to contract cancellation, the only remedy is to claim for damages if any. However, in this case, the Charterers did not suffer any actual losses relying on the delay. Above all, the Charterers could not cancel the Charterparty based on Clause 1 of ASBATANKVOY, and if they did so, the cancellation constitutes a repudiatory breach of contract. 4.4 In presence of arguments above, the Owners are not liable for damages and losses arising from delayed arrival. Relying on all analysis above, if the Charterers elect to cancel the Charterparty based on the grounds that the Owners were in breached of ETA or laycan clause or the Owners failed to proceed to the loading ports with reasonable dispatched, the Charterers constitutes a repudiatory breach of contract if they cancelled the Charterparty based on grounds above. 5. If the Charterers elect to cancel the contract based on the Owners Standard Terms Clause 2, they should not claim any damages against the Owners. 5.1 The Owners’ Standard Terms Clause 2 applied. The Owners’ Standard Terms Clause 277 applied therefore since the Charterers should 76 77 Fact P96 “Super Charters Inc.’s E-mail” See Facts p87: The Owners Standard Terms. 22 not rescind the Charterparty based on the grounds mentioned above. 5.2 The Charterparty was cancelled in a “without recourse” way. The Charterers contend that the Owners’ Standard Terms Clause 2 is amended so as to displace the Owner’s usual regime of releasing them from liability.78 However, Clause 2 is not an exemption clause that it does not purport to exclude the Owner’s liability for breach of an obligation79. Since it is not permitted to rescind the charterparty prior to the cancelling date unless the result of the breach is so substantial to frustrate the object of the contract80, in commercial practice the solution to the problem is to insert a clause entitling the charterer to cancel the charter while the vessel have arrived by a specified later date81. Thus the Clause 2 of the Owners Standard Terms is a contractual option for the Charterers to cancel the Charterparty that is not subject to the cancelling date if the condition prescribed in the Clause 2 satisfies. Whereas, when the Charterers invoke such clause, the Charterparty could only be rescinded the Charterparty in a “without recourse” way. The construction of “without recourse” is that once the Charterers elects to cancel the contract by invoking such clause, they could not claim any damages against the Owners. The true construction goes to commercial custom. 78 Facts p111: The Charterer’s Submission. The Unfair Contracts Terms Act 1977, Clause 13:“To the extent that this Part of this Act prevents the exclusion or restriction of any liability it also prevents – (a) making the liability or its enforcement subject to restrictive or onerous conditions; (b) excluding or restricting any right or remedy in respect of the liability, or subjecting a person to any prejudice in consequence or his pursuing any such right or remedy; (c) excluding or restricting rules of evidence or procedure; and (to that extent) section 2 and 5 to 7 also prevent excluding or restricting liability to reference to terms and notices which exclude or restrict the relevant obligation or duty.” 80 Jackson v Union Marine Insurance Co (1874) LR 10 CP 125. 81 Ibid: The Madeleine [1967] 2 Lloyd’s Rep 224. 23 79 5.3 The Charterers should not claim any damages against the Owners. If the Charterers elect to cancel the Charterparty based on the Clause 2 of the Owners Standard Terms, the Charterers could not claim any damages resulting from the delayed arrival. Thus, above all, the Owners are not liable for damages and losses claimed by the Charterers. PRAYER FOR RELIEF For the reasons submitted above, the Owners respectfully request this Tribunal to: DECLARE that the Charterparty between Owners and Charterers is cancelled. Further, ADJUDGE that the Charterers are liable to the Owners for: The sum of USD 4,935,368.75 by way of freight or damages in the same amount, interest, costs, and further of other relief. Further, ADJUDGE that the Owners are not liable to the Charterers for increased freight USD 824,000; Further, ADJUDGE that the Owners are not liable to the Charterers for sums due and payable to the loadport terminal/sellers pursuant to the relevant sale contract for delayed arrival in USD 100,000. 24 Further and alternatively, ADJUDGE that the Owners are not liable to the Charterers for sums due and payable to the disport terminal/sellers pursuant to the relevant sale contract for delayed arrival in USD 300,000. 25