DEPARTMENT OF QUANTITY SURVEYING VARIATION CONTROL AFFECTING CONSTRUCTION WORKS FOR LEMBAGA KEMAJUAN TANAH PERSEKUTUAN(FELDA) NURUL UYUN BT MOHD YUNUS A report project submitted in partial fulfilment of the requirements for the award of the degree of Master of Science (Construction Management) Faculty of Civil Engineering University Teknologi Malaysia MAY,2007 ii Final Pr ct I declare that this Project Report entitled “Variation Control Affecting Construction Work For Lembaga Kemajuan Tanah Persekutuan(FELDA)” is the result of my own research except as cited in the references. This report has not been accepted for any degree and is not concurrently submitted in candidature of any degree. Signature : …………………………….. Name : Nurul Uyun Bt Mohd Yunus Date : …………………………….. fulfillment iii Specially Dedicated To My Parents My Beloved Mother “You have done all the best for my live” Beloved Husband Ahmad Fairuz B. Dato’ Ahmad Shamli “Thank you for your love and support” My Children “You’re the heart of my life’ iv ACKNOWLEDGEMENT With high gratitude to Allah S.W.T. who gave me the ideas and physical strength in preparing this final project. I wish to express my gratitude to the persons and all parties who responded to the survey and also offered their invaluable contributions in carrying out this final project. First of all, I would like to express my appreciation to my Supervisor for his guidance throughout the preparation of this thesis. Special thanks to those who agreed to be interviewed, formally and informally, because gave me the benefit of their knowledge, views and experience. I would like also to extend my sincere and deepest gratitude to all my friends who have helped me directly or indirectly. Finally, I would like to express my deepest love and appreciation to my family especially to my husband for his support. Thank you for all understanding given to me when I really need it. I am hoping this thesis will be a reward for all efforts of every contributing individual. Thank you. v ABSTRACT Variation means alteration, change or modification of design, quality or quantity of work omission, addition or substitution of the work including the alteration of the kind or standard of any of the materials or goods to be used in the work, and the removal from site of any work, materials or goods which are not in accordance in the contract. The aim is of this study research is to covering the initial planning, while works is in progress and until the completion of works to minimize the need for variation works right from the start . The method of this study involved literature review, interview and based on the case study and the analysis by qualitative method. The process of data collection involved obtaining primary data from the literature review and the secondary data was generated from the case study. From the analysis of this study type and factors influence to variation; problem that influence and the implication to variation; and the strategy action can be taken to minimize the variation were identified. In conclusion, the strategy action that can be taken were identified to minimize or control the variation works during planning stage until construction stage. vi ABSTRAK Perubahan kerja didefinasikan sebagai ubahsuai, perubahan rekabentuk, pembatalan dari kuantiti atau kualiti kerja, penambahan kerja termasuk perubahan terhadap spesifikasi bahan yang digunakan di dalam sesuatu kerja dan juga pembatalan kerja ditapak termasuk bahan yang tidak mengikut di dalam kontrak. Ianya terdapat di dalam kebanyakan di dalam kerja-kerja bangunan. Tujuan kajian ini adalah merangkumi peringkat awal semasa kerja di dalam kemajuan sehingga siap kerja untuk mengurangkan perubahan kerja bermula peringkat awal kerja lagi. Kaedah yang terlibat di dalam kajian ini adalah merangkumi kajian litaratur, temuduga dan juga kajian kes dan dinalisa melalui kaedah kualitatif. Proses mengumpulkan data diperolehi dari kajian litaratur dan dari kajian kes. Hasil daripada analisis yang dijalankan jenis-jenis perubahan kerja dan faktor-faktor yang mempengaruhi perubahan keja telah dikenalpasti; masalah-masalah yang mempengaruhi perubahan kerja dan kesan nya; dan akhir sekali tindakan yang boleh diambil bagi mengurangkan perubahan kerja juga telah dikenalpasti. Oleh yang demikian, kesimpulan dari kajian ini terdapat strategi tindakan boleh dilakukan bagi mengurangkan perubahan kerja bermula dari peringkat awal perancangan hingga ke peringkat pembinaan. vii TABLE OF CONTENTS CHAPTER 1 2 TITLE PAGES DECLARATION ii DEDICATION iii ACKNOWLEDGEMENT iv ABSTRACT v ABSTRAK vi TABLE OF CONTENTS vii LIST OF TABLES xii LIST OF FIGURES xiii LIST OF ABBREVIATIONS xiv INTRODUCTION 1.1 Introduction 1 1.2 Problem Statement 2 1.3 Aim And The Objective Of Study 3 1.4 The Scope And Limitation of Study 3 1.5 Research Methodology 4 1.6 Summary 6 TYPES AND FACTORS INFLUENCE VARIATION ORDER 2.1 Intoduction 7 2.2 Definition 7 2.3 Types Of Variation 9 2.3.1 Identity of the Initiator 10 viii 2.4 2.3.2 Nature of the Variation 10 2.3.3 Consequences/ Effect of Variation 11 Factors Influencing The Variation 11 2.4.1 Site Condition 12 2.4.2 Design 12 2.4.3 Client Requirement 13 2.4.4 Changes Of End User’s Management 13 2.4.5 Discrepancies Between The Works And 14 Statutory Requirement 2.5 3 2.4.6 Poor Management 14 2.4.7 Requested By The Contractor 15 Summary 15 PROBLEMS AND IMPLICATION OF VARIATION ORDER 3.1 Introduction 17 3.2 Development Outlines Invovle in 17 Pre-Contract Stage 3.3 3.2.1 Inception Stage 18 3.2.2 Feasibility Study 19 3.2.3 Outline Proposal 20 3.2.4 Scheme Design 21 3.2.5 Detail Design 21 3.2.6 Production Information 22 3.2.7 Bills Of Quantities 22 3.2.8 Tender Action 23 The Problems in Variation 24 3.3.1 Determining the rates to be used 24 3.3.2 Issuing instruction by S.O 25 3.3.3 Determining the quantities in variation 25 3.3.4 Design Changes 26 3.3.5 Communication 26 ix 3.4 3.5 4 3.3.6 Client 27 3.3.7 Consultant 27 3.3.8 Contractor 28 The Implications of Variations 28 3.4.1 Delays 28 3.4.2 Cost 29 3.4.2.1 The additional expenses 29 3.4.2.2 Financial charges and interest 30 3.4.2.3 Cost of site overheads 30 3.4.3 Quality of Works 30 3.4.4 Works Programmed and Activities 31 3.4.5 Inconveniences 31 3.4.6 Unsatisfied 32 Summary 32 STRATEGY ACTION ON MINIMIZING VARIATION ORDER 4.1 Introduction 33 4.2 Pre Contracr stage 33 4.2.1 Clear and Thorough Project Brief 34 4.2.2 Detailing Of Design 34 4.2.3 Adequate Time in Preparation of Documentation 35 4.2.4 Management Procurement Strategy 35 4.2.5 Detail and Adequate Investigation 36 4.2.6 Provision of Complete Documentation 36 4.3 4.4 Pre Construction Stage 37 4.3.1 Contractor’s Efficiency 37 4.3.2 Keeping Systematic Site Record 37 4.3.3 Daily Check 38 4.3.4 Fully Inspection 38 4.3.5 38 Comply With All Requirement Summary 39 x 5 6 7 RESEARCH METHODOLOGY 5.1 Introduction 40 5.2 Stage 1 : Literature Review 41 5.3 Stage 2 : Interview and Case Study 42 5.4 Stage 3 : Recommendation 43 5.5 Summary 43 DATA AND ANALYSIS 6.1 Introduction 44 6.2 Case Study 1 45 6.3 Case Study 2 50 6.4 Case Study 3 55 6.5 Result and Analysis 60 6.6 Findings and discussion 66 6.7 Summary 75 CONCLUSION AND RECOMMENDATION 7.1 Introduction 76 7.2 Conclusion 76 7.3 Recommendation 82 REFERENCES 83 xi LIST OF TABLES TABLE TITLE PAGE 6.1 List of variation works for case study 1 46 6.2 List of variation works for case study 2 51 6.3 List of variation works for case study 3 56 6.4 Types of variations 60 6.5 Factors that influence to the variations 61 6.6 Problem that influence to variations 62 6.7 The implication of variation – Cost Overrun 63 6.8 The implication of variation – Delay 64 6.9 Strategy action can be taken to minimise or control variation 66 6.10 The factors that influence the variations(%) 68 6.11 Cost Overrun for Case Study 1 71 6.12 Cost Overrun for Case Study 2 71 6.13 Cost Overrun for Case Study 3 72 6.14 Delay 72 xii LIST OF FIGURES FIGURE TITLE PAGE 1.1 The Methodology Flow Chart 5 3.1 Development Outline at Pre-Contract Stage 18 6.1 Percentage factors that influence to variations 61 6.2 Percentage the implication of variation – Cost Overrun 64 6.3 The implication of variation – Delay 65 xiii LIST OF ABBREVIATIONS S.O - Superintending Officer PWD 203 (10/83) - Standard Form of Contract to be used where Bills of Quantities Form Part of the Contract (Revised 10/83) IEM.CE 1/89 - Standard Form of Contract to be used where Bills of Quantities Form Part of the Contract of Civil Engineering Construction V.O - Variation Order BQ - Bills of Quantities M & E- Mechanical and Electrical TNB - Tenaga Nasional Berhad JBA - Jabatan Bekalan Air JKR - Jabatan Kerja Raya CHAPTER 1 INTRODUCTION 1.1 Introduction Today, small projects can be just as important if not more important than the larger projects. When unforeseen situations occur on site, it is important to first understand the situation and come up with suitable solutions and forecasts the probable consequences. One of the occurrences that make projects less profitable is the variation in the original works, leading to re-planning of the ongoing work. As clients are always known for their tall demands, they sometimes change their minds by varying the works while in progress. Changes are usually the major factors causing the delay on projects. The impact due to changes has been described as the adverse effect upon the unchanged work due to changes in the contract. Even though there are provisions on variation orders in a building contract, the variations works sometimes did not satisfy both of parties who felt disappointed to carry on the works. It will give impact on the cost of the project extend the completion period and it will bring inconveniences to all the parties involved in construction industry, which are client, consultants and also contractor. Besides that it also brings inconvenience for the end user. No matter how much effort to reduce the variation order in construction industry, it still happens and the final accounts remained unresolved after the building was occupied. These variations are directly attributable to matters not being as stated or as required in the contract documents. This is because circumstances actually change or because of misinterpreted in the contract documents. Other than that, it also occurs because of client’s choice thus will result creating a variation. For this, some strategies are needed to anticipate starting from the planning stage, so that as the project commences and programmed on site, they will be no variations or at least they can be minimized. Therefore, all parties involved should cooperate to assure that the efficiency of construction and thus will minimize the variation orders in construction industry. 1.2 Problem Statement Many program for development are being carried out rapidly for Lembaga Kemajuan Tanah(FELDA) to develop FELDA land. Therefore 5 years back many of building and infrastructure works been carried out which awarding the project to the experience and class A contractor but the problem of variation work is still occurring while construction in progress. Varies order from client and authority requirement makes the variations increased easily. Changes in the contract and misinterpreted in document contract will caused of additional cost and the impact of this variation and will impact on the completion of project. Most of the variation occurs when major changesT in the contract during construction and additional works. Variation can also occur when unexpected 3 condition such as climate changes which can causes damages project site as example flooded during construction in progress. While unforeseen condition and due to lack of supervision and poor in managing and planning the project can also causes of variation. 1.3 Aim and The Objective of Study . To achieve the aim, several objectives are defined, they are as follows:- 1) To identify the types of variation works commonly occur in construction projects and the factor influencing these. 2) To identify the problem that influence to variation and the implication of variation to the construction.. 3) To identify the strategy action that can be taken to minimize variations starting from planning stage until the construction are being carried out. 1.4 The Scope and Limitation of Study The scope of this study is focused Research starts from Pre-Contract practice on managing the design development process in construction. Study on the strategy action to be taken starting from planning stage until the Post Contract stage and its effectiveness in minimize the variations. The area of work of the study focused on the building construction works of Lembaga Kemajuan Tanah Persekutuan (FELDA) project and also interviews from professionals who are relevant to the topics. 4 1.5 Research Methodology The methodology is essential to enable the compilation of data and information from various sources. Thus, it involved three main stages starting from collection of data, analysis of data, conclusion and recommendation related to the topic. The study can be broadly divided into three stages. (i) The first stage include literature review which based on the primary data collected through reading and searching from related books, magazines, articles, web site and others. (ii) The second stage is including interview with relevant professional by face to face interview. Analysis of data by using qualitative methods is done through the collected reading materials and secondary data generated from the case study of FELDA’s projects. (iii) The final stage of this study is to define the conclusion and recommendation with reference to the objective, subsequent to the analysis from the case study and interviews. The process of research methodology can be summarized as Figure 1.1 below. This Figure 1.1 shows the process of research methodology starts from the literature review until to the conclusion and recommendation. 5 Literature review Collection of Information and data from related books, magazines, articles, Internet and others First Stage Collection of Data Case Study Second Stage Third Stage Interview Analysis of Data (based on qualitative method) Conclusion and Recommendation Figure 1.1: The Methodology Flow Chart 6 1.6 Summary This study provides some valuable insights in to the relative importance of to minimize or control the variation starts from the planning stage until the construction stage. The study consists of seven chapters. The first chapter is to introduction of the research, which includes the statement problem, the aim and objective of the study, the scope and limitation of the study, and research methodology. The second chapter is on literature review, focus on the identification the types of variation and the factor influence this.; Third chapter continue with the literature review on the problem in variation and its implication to the construction; Fourth chapter focus on the strategy action that can be taken to minimize or to control variation work in the construction. The fifth chapter is the research chapter that discusses the method of research. The data and analysis is discussed in chapter six and lastly the conclusion and recommendation is highlight in chapter seven. CHAPTER 2 TYPES AND FACTORS INFLUENCE VARIATION ORDER 2.1 Introduction This chapter identifies the types and the factors that influence the variation order, establish the definition of variation and classification of variation from the literature review. The factors that influence the variation order to be discussed in which related from the pre contract stage until construction stage. 2.2 Definition Variation order means the alteration, change or modification of design, quality or quantity of work omission, addition or substitution of the work. It is also including the alteration of the kind or standard of any of the materials or goods to be used in the work, and the removal from site of any work, materials or goods which are not in accordance in the contract. 8 In most form of contract used today for building work provision must be made for possible variations. At the same time when tenders are invited the employer and his architect and engineer should have crystallized all their ideas into a set of contract documents. According Standard Form Of Contract (IEM.CE 1/89, clause 23(a)), state that the term ‘variation’ means “increase or decrease the quantity of any works include in the contract; omit any such work; change the character or quality or kind of any such work; change the levels line position and dimensions of any part of the works; execute additional works of any kind necessary for the completion of the works. While according to Standard Form Of Contract (PWD 203 (10/83), clause 24(b)), state that the term of ‘variation’ means “the alteration or modification of the design, quality or quantity of the works as shown upon the Contract Drawings, Bills of Quantities and/or Specification, and includes the addition, omission or substitution of any work, the alteration of the kind of standard or any of the materials or goods to be used in the works and the removal from the site of any work, materials or good executed or brought thereon by the Contractor for the purpose of the works other than work, materials or goods which are not in accordance with this Contract.” Variation can be classified into two categories, which are active variations and passive variations (Hj. Hashim Sikan, 2003). Active variations come indirectly as a result of the issue of instructions. So much the instruction it become a norm that there is no variation without instruction. Instruction here refers to those instructions issued by the contract administrator for example Superintending Officer’s (S.O) instruction in the standard form of contract(PWD Form 203A and IEM.CE 1/89). Another aspect of variation deals with statutory regulations (clause 11(d) PWD Form 203A, and IEM.CE 1/89) requires the contractor to inform the S.O in writing of any change or amendment in statutory regulation and bye-laws taking effect after the Date of Tender which necessitated any variation to the works and apply for and S.O’s instruction before the S.O could issue the instruction. 9 The passive variation could be accepted as those that do not require the instructions to be issued directly to the contractor. For example re-measurement and valuation of those quantities of the work, which are stated as ‘provisional’ in the bills of quantity. Other than that the variations also comes in the form of the adjustment of items having Prime Cost or Provisional Sums in the contract. The variation work of these items shall be prepared and agreed by the contractor and the client in which to facilitate the finalization of accounts in the contract. After the both parties agreed with items and the rates that involve in variation works, then it should be prepared in the final account accordingly to the Variation Order format. 2.3 TYPES OF VARIATION According to Ir Harbans Singh K.S (2002), generally there are three types of variations. The types of variation can be classified according to their criteria, which are as list as follows: (i) The identity of the initiator. (ii) The nature of the variation. (iii) The consequences or effect of the variation. 10 2.3.1 Identity of the initiator Classification per identity of initiator is a change made by any one or more principal parties. This can be described as employer, contractor, nominated subcontractors, nominated suppliers, and also contract administrator. Employer is a person on behalf of the users, future occupants, and etc., while the contractor can make change on his own volition or behalf of sub-contractors, suppliers, etc. Nominated sub-contractors/ suppliers are in relation to their respective sub-contract; and contract administrator; on his own volition, on behalf of the employer, the designers, statutory bodies, third parties and etc. It is an undeniable fact that the bulk of the variations are initiated by the employer. The principal reasons for the employer to initiate variations are changes in the employer’s requirements post contract award, for example owing to a rethinking of the needs, change in the nature and use of the anticipated or future utilization of the finished works. Besides that, the changes are also in review or reassessment of the design by the designers due to issues such as safety, build ability, and correction of deficiencies or errors. While the contract administrator with the power is then implemented the provision of the contract unless the employer has retained such powers under the contract. 2.3.2 Nature of the variation The nature of the variation means changes according to the nature of the work itself. This means it not only changes to the work or matters appertaining to the work in accordance with the provisions of the contract, but also changes in the contract 11 condition itself. It is includes addition of the work, omission and also combination of both. 2.3.3 Consequences/ Effect of Variation Variations can also be classified by the consequences or effects of the change undertaken in labeling it by the financial consideration, or time implication. It is not considering the nature of the variation and the initiator. The financial consideration involved the monetary for example an adjustment in the Contract Sum, while the time implication is the flowing from a particular change being undertaken, (Ir Harbans Singh K.S) A variation may arise in construction contract in various ways. It arises more often during the progress of the work and seldom before the commencement of the work, but it will not be allowed at any cost after the practical completion has been certified. 2.4 Factors Influencing the Variation There are many factors that influenced the variations. It may come at the precontract stage and post-contract stage. The factors that influence the variation are due to the site condition; any design changes; client’s requirement; change of end user’s; discrepancies between the works and statutory requirement; poor management; and request by the contractor. 12 2.4.1 Site Condition The real conditions are not shown in the drawings and specifications and cannot be determined during preliminary investigation and therefore it is beyond expectation. If the Contractor finds any difference in soil condition such as old underground structure, hole underground, etc, he must inform to the S.O immediately in writing. This enables the S.O to give the appropriate instruction as described in the Form of Contract, (clause 8(b) of PWD Form 203A and IEM.CE 1/89). This clause provides the S.O’s instruction, which is considered to be a variation for unforeseen condition, and the Contractor is entitled to claim for the cost incurred and looses. 2.4.2 Design Only when a site is chosen, it will continue with the design stage. In this stage the client’s brief must be clear. A sophisticated client will already have seen to this stage. But a building employer may frequently be dissatisfied with the design of the project, and the seriousness of allegation of bad design can range from the little to the serious. Design problem may cause structural failure leading to personal injury or even loss of life. Producing a quality design is highly dependent upon effective coordination among the diverse discipline involved in the process. The consequences of most design coordination problems are not discovered until during construction, (Tarek Hegazy, Essam Zaneldin, Donald Grierson, 2001). 13 2.4.3 Client Requirement A client is an owner of the building. Clients are divided into three categories which are some clients have knowledge and experience in construction industry, have money but not have experienced in construction field and have money and have a little experienced in construction industry. The major factors that influenced the instruction of variation made come from the client itself. The client’s requirement always changes time to time. Usually only when the building has been constructed the client gets his sense of desire. The bulk of additional work is occasioned by revisions in the requirements of the employer during the course of contract, (Ir Harbans Singh K.S (2002)). The changes client’s requirement will affect the design. For example, an employer may require lift for the project thus the design team should redesigned the structure in order to fulfill the client’s requirement. In this case, whether the contractor should be entitled to compensation for loss of profit and loss of productivity will depend on the variation work either cause a delay to the project as a whole or any rate prevent the optimal deployment of plant and manpower resources on the site. Other than that, there are some situations where the Client do not even sure about his requirements and will follow the suggestion from the Architect. This situation always happens during construction stage and even after construction stage. Therefore it is sometimes very difficult to determine or to predict the needs of client requirement. 2.4.4 Changes of End User’s Management Construction project is lengthy thus a construction project may take one or two years time depending on the size of the construction. During that time, the 14 management of end user may have changed which will subsequently change the function and size of a department. In this situation variation is unavoidable. 2.4.5 Discrepancies Between The Works And Statutory Requirement The discrepancies between the works and statutory requirement are one of the factors of influenced of instruction of variations. There is a provision in the contract that allows the Contractor to make variation to comply with the requirement of the law and local authorities. In the case of compliance with a statutory requirement, there is the possibility of the S.O securing a waiver and thus reducing the cost, or of a measure of re-designing that achieves the same objective, (Turner, 1985) 2.4.6 Poor Management Planning is concerned with only the future. It is obvious that the past becomes history with the relentless passage of time. When construct a building, the optimistically expect the project to be successful, with the perhaps only one or two challenging surprises. It needs for proper planning and management of construction can never be over emphasized. But poor management will caused the unsatisfied result. 15 2.4.7 Requested by the Contractor It is uncommon for the contractor to request instructions in respect of works they wish to vary, (Hibbert, 1986). The variation that requested by the contractor is always happen during the construction stage. The reasons why the contractor request the variation is include: a) The Contractor finds that there is another construction method that is more convenient and advantageous to the contracting parties. b) Proposing for a more suitable design for material. c) The work priced is not practical and therefore applies it to be examined. From the above, it is necessary for the contractor to request approval in writing and propose the variation. The S.O’s that approves the variation also must give in writing. Then the contractor should execute the variation work as per requested and approved by the S.O’s. 2.5 Summary There are three types of variation, from the literature research that have been made by the author which were identified as identity of the initiator; nature of the variation; and consequences/ effect of variation. The initiator was identified such as employer, consultants, contractor and etc. The nature of variation was identified as omission, addition and combination of both. Lastly the consequences/effect of variation was identified as financial consideration or time implication. 16 There are also many factors that influence the variation order, from the literature research that have been made by the author. Some of the factor that influence the variation order were identified as site condition; client requirement; discrepancies design changes; between the changes works and management; and requested by the contractor. of end statutory user’s management; requirement; poor CHAPTER 3 PROBLEMS AND IMPLICATION TO VARIATION ORDER 3.1 Introduction This chapter discusses on the development outline involve in pre-contract stage which explained the process of the pre-contract stage in a building project. The important of this chapter is discussed on the problems that influence to variation and the implication of variation works to the construction. 3.2 Development Outlines Invovle in Pre-Contract Stage Development outlines involve in pre-contract stage based on the RIBA Plan of Work which is sequential progression through the stages of design and construction of a building project. This development outlines involve in pre-contract which involved in eight(8) stages, which are inception; feasibility study; outline proposals; scheme design; detail design; production information; bill of quantities; and tender action. 18 Inception Feasibility study Outline proposals Scheme design Detail design Production information Bills of quantities Tender action Figure 3.1 : Development Outline at Pre-Contract Stage This development process can be summarized in the Figure 3.1 above. The development outlines involve in pre-contract which involved in eight(8) stages, which are described as follows : 3.2.1 Inception Stage The main purpose of the inception stage is to prepare general outline of requirements and plan future actions. The difficulties inherent in establishing the 19 client’s brief are often substantial. The main problem is identifying the client’s needs and then reconciling these against a background of financial, technological and legislative constrains, the client’s personal requirements, and also a number of design variables including structural form, aesthetic and environment, (Ivor H. Seeley, 1982) In inception stage, the architect will start his work after the client decides what he wants. The architect will require as much information as possible from the client in order to avoid variation order in the future. It is important that the client should keep well informed of the various decisions as they are made. The basic details need by the architect are the nature, size and function of the proposed building, the time and financial limits relating to the project, information relating to ownership of the site, boundaries, and other related matters, current position with regard to any planning application, and other members of the design team to be appointed. The client’s requirement normally will reflect the design. 3.2.2 Feasibility Study The main objective at this stage is to examine all the technical, functional and financial aspects of the project and to advise the client as to its feasibility. The feasibility study stage comes after the inception where the general outline of requirement has been prepared. Normally the design team will meet and discuss to in detail regarding the client’s requirements and to make their recommendations thereon for submission to the client and established the design brief. The feasibility study will take into account a detail survey of the site and any adjoining building and capacity of the various services including gas, water, electricity, sewers and telephones. Consultation will take place with the Local 20 Authority and any relevant bodies. Any restriction on the use of the site must be investigated and their effect on the proposed development determined. The feasibility study normally will be based on the previous project with similar uses and similar specification to investigate the requirement and facilities. The quantity surveyor will calculate based on the findings and recommendations either the proposed development is feasible to build or not. The report must effectively assess the overall feasibility of the scheme having regard to all relevant factors, so as to give the client all the information he needs to make decision whether to proceed with the scheme or not. This report will be supported by conceptual designs and estimates of cost. 3.2.3 Outline Proposal At this stage alternative schemes are prepared and compared in order to determine the general approach to the layout, design and construction. This involved very close collaboration between all members of the design team and the client. At this stage all design team plays their important role to make sure the work carried out smoothly. The architect will be particularly concerned with functional and aesthetic aspect, the structural engineer with different structural forms and the services engineer with alternative services layouts. The quantity surveyor will maintain close contact with all the other professionals in order to determine the cost implications of the alternative proposals as they are prepared. 21 3.2.4 Scheme Design The main purpose at this stage is to critically examine the wider issues of appearance, method of construction, outline specification and the preparation of a cost plan, showing the proposed distribution of costs over the elements or components of the building. All the relevant design information is collated and a detailed report on the design and full cost implications can be supplied to the client before the scheme design is developed. The cost estimates will be provided by the quantity surveyor, desirably incorporating both initial and future cost. 3.2.5 Detail Design At this stage, the design will be in depth with the final decisions being taken in respect of all individual components which together make up the complete building. All members of the design team also will continue to work very closely together to secure an integrated and efficient scheme. The various ideas from the various professional will have contributed greatly to the final outcome. As the design moves into greater detail and hopefully towards finality, cost checks should be carried out to see that particular cost elements are not being distorted, or that, if they are, the resulting redistribution within the budget is acceptable, and if there are any changes in the design, it will result in abortive work and almost certainly in additional cost. 22 3.2.6 Production Information At production information process, the architect, engineers and any other specialists will now proceed with the preparation of the final drawings and schedules, and supporting specifications. Besides that, at this stage also to determine the preliminary tendering procedures and to prepare a list of potential main contractors, enquiries to subcontractors and suppliers, invitations to tender, and information to tender documents. 3.2.7 Bills Of Quantities At this stage, the bill of quantities and all other tendering documentation are finalized. It is important that the drawings, schedules, and specification particulars should be checked and steps taken to ensure all the particulars are in correct. If there are any discrepancies between the specification and drawings, then the query list will submitted to the architect in order to the architects to clarify these points and amend the documentation prior to tender stage. The bills of quantities are designed primarily as a tendering document, but it also provides a valuable aid to the pricing of variations and computation of valuations for interim certificates. It provides a good basic for cost planning and help in identification of work. 23 The bills of quantities contain preliminaries, preambles or description of material and workmanship, and the measured work. The preliminaries define the scope and nature of work; contain details of the contract condition, list of drawings and any special instructions to the contractor on pricing. In the bills of quantities also will be inserted the Prime Cost Sums and Provisional Sums. Preparation of bills of quantities must be in detailed in order to avoid any discrepancies and also variation works. One of the causes of variation is the discrepancies in the bills of quantities. 3.2.8 Tender Action Tendering procedures cover the various methods that may be used by the client and his advisers to obtain offers. There are some procedures in obtaining the tender which are open and selected tendering. This open tendering procedure is to advertise through the press, inviting any firm that wishes to do so to submit a tender. The advertisement will give outline details of the type of work, the programmed and other key features. The open tendering provides the longed for opening for some relatively unknown but capable firm. The selected tendering procedure is to call the selected qualified contractor based on the financial background and other features and asking them whether they wish to tender. If they do so, they must fill in the document and submit the contract document. Selected tenderers normally are approached about one month before the tender document is circulated. The purpose of the tender action is to select the suitable contractor to carry out the work diligently and competently. 24 3.3 The Problem in Variation There are some problems arising when there is a variation work in the construction. These problems might sometimes cannot be avoid but it can be managed in order to reduce the problems occur in the future. The common problems that occur in variation work can be categories as follows:- 3.3.1 Determining the rates to be used. Although in construction contract there is a provision in determining the rates when there is a variation work in the contract rate, agreed rate or day work rates, but in practice there is a problem in determining which rates are to be used. When there is variation work, the quantity surveyor needs to divide the rate to be used in pricing the variation work. If the work is similar nature and executed under the similar conditions then the contract rate is used. Where the work is not of a similar nature and executed under similar conditions in the contract, then the pro-rata rates is used. But if the work is totally different from anything contained in the contract, then the agreed rate or day work rate will be used. The problem is where the work is totally different with the contract, the contractor’s rate normally high because from that, he can get the profit. So it is hard to get the reasonable rate and it takes time to decide and solve this problems. 25 3.3.2 Issuing instruction by S.O Another problem is issuing of the S.O’s instruction sometimes in verbal and not confirmed in writing. The condition of contract states, instruction is not valid and the contractor has to confirm back with the S.O within the stipulated time in the contract. Normally in practice, whether the instruction is in verbal, the contractor still carried out the work as instructed by the S.O. The problem is at the end of construction, if the contractor carried out the work that instructed by the S.O in verbal, the work is not accepted because there is no evidence to proof the work and not including in the contract. Hence, the contractor not entitles to claim for the works. The S.O has a choice to accept the work or to reject the work. If the S.O chooses to accept the work, he may issue the written notice to the contractor for the variation works. If the S.O chooses to reject the work, the contractor must demolish the work at his own cost. To avoid this problem, any instruction issued by the S.O must in writing. If there is an instruction in verbal, the contractor must take an action to confirm with the S.O and the confirmation must be in writing. 3.3.3 Determining the quantities in variation Besides that, there is also a problem in determining the quantities in the variation works especially in Lump Sum Contract based on Drawings and Specification. For the lump sum contract, it only required contract document without the quantities, specifications and drawings. All the quantities are subject to remeasurement. The problems arise in determine the exact quantities in which the client may spend the extra cost by using this type of contract. This because, all items in the contract to be executed by the contractor which is lump sum is payable. The actual 26 quantities of the work executed by the contractor which exceed the quantities shown against in the contract, therefore it may constitute a variation and the client should pay for the work done by the contractor. 3.3.4 Design Changes Problem in bad design of the project always occur especially when there is poor communication between the client and the consultant. The client dissatisfied with the design made by the designer. For example, the client dissatisfied with the layout of the electrical fitting because it can cause the personal injury or even loss of life. If this problem occurs, the design must redesign the layout to modify and that is costly. Basically these problems will only discover until during construction. 3.3.5 Communication Communication is one of the problems in variations. If the communication failed, it will lead the bad performance and could cause variation. Communication is important to start from briefing stage until the completion of the work. In variation work, the communication problem between the S.O and the contractor is important, for example in issuing the instruction. If the contractor not understands the instruction and carries out the work then it fails to satisfactory the S.O, the work may accept or reject by the S.O. If the S.O rejects the work, then the contractor could rectify the works and it is costly to the contractor. This communication can lead the both parties feel unsatisfied for the works. 27 3.3.6 Client If there is a variation works, the client must bear the cost incurred in the works. In other words, the client’s budget has increase because there is a variation works especially for the contract based on the bills of quantities. Besides that, if there is any variation work and time of the construction has extend, the client loss of the profit because late in occupy the building. For example the construction for bungalow houses, building should complete at the end of the year as stated in the contract. If there is no variation works, the client may be can occupy the building, operate the building, and make the profit from the building; but when there are a variation works, the client cannot occupy the building and cannot make profit from the building. The client bears the loss of the operation of the building. 3.3.7 Consultant If the client request for the variation works, the Architect must produce the new design in order to meet the new requirement of the client. Sometimes the variation will affect the design, for example effect on the architecture view. It may lead the designer feel unhappy because their work has been disturbed by the numbers of variation. The quantity surveyor also has a problem when there is a variation work. For example, the quantity surveyor should produce the new bills of quantities if the new works not similar with the work in the original contract. 28 3.3.8 Contractor The other problem in the variations is on the contractor’s side. The contractor is difficult to claim for extra works or variations especially under the lump sum contract. According to Ir. Harbans Singh K.S (2003), it is difficult for the contractor to claim an extra/variation works unless the contractor satisfy the onerous burden of establishing a clear cut charge in the scope of work as originally contracted for. Besides that, when there are a numbers of variations, it may lead the contractor feeling unmotivated and this will result in poor quality of works. The contractor also faced the problem when there are variation works in the construction, the problem is the contractor should reschedule the work program and it will affect the activities in site. 3.4 The Implication Of Variations Order Variations in construction industry will lead the impact to all the parties involved in this sector. The main implication of variations is in term of time overrun and cost. 3.4.1 Delay Delay refers to the time taken in complete the work. There are in fact two types of delay, which must be taken into account when valuing the effect of variation. (Powell-Smith, 1990). 29 (i) Delay to a critical path of the work, which will affect the general of the work, thus the contractor retaining his general site overheads for the longer period. (ii) Delays to part of the work that will not affect the overall completion but the contractor still retain some particular item of plant on site longer than planned. (iii) Loss and expense flowing directly from the execution of the varied work. Standard Form Of Contract, (PWD Form 203 Rev. 10/83) provides a special provision for delay to ensures that if variation instructions are late and cause delay to the contractor then the client is entitled to grant of extension of time and enable the contractor to claim for loss and expense, thus avoiding putting time at large and unable to recover any liquidated and ascertain damages. 3.4.2 Cost Variation also will give the effect in terms of cost. This cost that can be identified such as additional expenses; financial charges and interest; and cost of site overhead. 3.4.2.1 The additional expenses, which are: a) Transportation expenses – the cost arising out of the moving and transporting materials and machinery, for example crane that has already been used and stores is transferred back to the site for additional works. 30 b) Cost of variation works preparation – the cost arises when some work elements have to be demolished including cost of removing materials and rectifying defects. c) Other cancellation expenses – is the cost of canceling orders. This is because the Contractor may have committed for certain charges making the order. 3.4.2.2 Financial charges and interest The cost incurred when the contractor wants to extend the project for a certain period of time due to massive and complex variation work. It involved a large amount of additional capital. Furthermore, the Contractor has to resort financial assistance from banks or other financial institutions whereby interests or charges encumbered upon the secured loan. (Chow Kok Fong, 1993) 3.4.2.3 Cost of site overheads The cost involved a large amount of additional cost for example the cost of supervision, machinery and equipment, site safety and other facilities that are needed to pay during extended time. 3.4.3 Quality of Works The quality of the work will be at risk. The question is either the quality of works achieves the standard requirement as per contract or not? If there are too many instruction changes by the Architect or S.O, it may lead the contractor feeling 31 unmotivated and afraid for the possibility of changes in completed works and this will result in poor quality of work and low productivity of the contractor. 3.4.4 Works Programmed and Activities Reprogramming and restructuring of the disrupted works will have to be done which will include demand for additional labour, overtime and additional machinery. Loss of productivity occurred where the labour resources must have been available and able to be used profitable. Besides that, variation also effect on the plant utilization because it will give the additional cost to contractor due to relocation of plant on or off site, the need of additional plant, additional tools, alterations of scaffolding and also standing time. 3.4.5 Inconveniences Variations will be bring inconveniences to all the parties involved in the construction project which are client, contractor and also design team. If there are variations, the design team will redo the work and it will cause inconveniences for example the Architect will redesign the drawings as the client’s requirement while the Contractor should pay extra cost for the delay caused by redesigning the work. 32 3.4.6 Unsatisfied Having variations may become unsatisfied or hassle among the parties involved in the construction project. For example, for the Client, the possibility of increasing budget for that particular project may cause high to restructure financing for the project. As for the Contractor, his work program will be disrupted, a new construction program needs to be submitted to the client and the relationships with relevant suppliers and subcontractors will need to be revised. For the design team, a new set of design may need to be submitted to the Client. The whole process of redesigning and re-measurement will be time consuming. 3.5 Summary From the literature research, therefore the outline of development in construction can be summarized as eight stages which are as follows, inception Stage; feasibility study; outline proposals; scheme design; detail design; production information; bills of quantities and tender. Problems that occur in variation can be identified as determining the rate to be used; issuing instruction by S.O’s; determining the quantities in variation; design changes; client; consultant; and contractor. The implication of variation from the literature research also can be summarized as delay; cost; quality of work; work program and activities; inconvenience; and unsatisfied. CHAPTER 4 STRATEGY ACTION ON MINIMIZING VARIATION ORDER 4.1 Introduction This chapter highlights the strategy action that can be taken in order to minimise or controlling the variation during pre-contract stage and post-contract stage. This chapter discussed on how the strategy action can be taken during precontract stage and post-contract in order to minimize variation order occur through out in the construction period. 4.2 Pre-Contract Stgae Variations can be avoided if there is prevention at the earlier stage of contract. The following are some strategy actions that can be taken in order to minimise the variation in pre-contract stage. 34 4.2.1 Clear and Thorough Project Brief Project brief is important at the initial stage because it represent the client’s needs and the objectives. At the inception stage, the communication is important between the client and the design team in order to avoid the poor contract performance later. The consultant must totally understand the client’s requirement and the client should clear their needs so that it will help to reduce the miscommunications between the parties. It is also to minimize the changes arise in the future as well as variations. 4.2.2 Detailing Of Design The important stage in the pre-contract is detail design because it is contain a full design of every part and component of the building by collaboration of all concerned. The detail design important normally for contract based on the drawings and specifications in order to avoid any dispute and claim arise in future. Furthermore, detail design also important in controlling the cost because it may affect cost of the future if not well prepared. The design team must work together and clear all the client’s requirement and needs in order to avoid any changes future. Any further change in location, size, shape, or cost after this time will result in abortive work. 35 4.2.3 Adequate Time In Preparation Of Documentation During preparation of the tender document, Quantity Surveying will prepare provisional item for the certain item that cannot measure accurately before the works being carried out. For example piling and plumbing installation. The Quantity Surveying need to make any assumption for the items that is not state in the drawing. These items are included under the provisional item and will be re-measuring during the construction. So, the Quantity Surveyor needs an adequate time in measurement of the works and also preparation of documentation. Thus through the detail design and adequate time for the Quantity Surveying to prepare the document, the total number of variations could be reduced. 4.2.4 Management Procurement Strategy The selection of the management procurement are important in order to ensure that the construction is running smooth and less variation occur during construction. Basically there are two procurement methods which are mostly used in Malaysia construction project are conventional method and design and build method. According the conventional method, the detail design can be prepare during the design stage. The client and designer will discuss together, so that there will be minimal changes during the construction stage. Compare to the design and build, all the design was prepared by the contractor based on the client’s brief. So the possibilities of increasing the number of variation works are high. Even though these both methods have their own pros and cons, this will depend on the client to select the best method which is suitable to apply for the project. 36 4.2.5 Detail And Adequate Investigation The detail in investigation is important even though it costly because it will help in the completion of the project within the budget and time specified. It will costly at the earlier stage but will reduce the cost at the construction stage. If the investigation is not adequate, it will result in additional cost future. This is because if the investigation is not done adequately, it will have problems at construction stage later when the site turns out to be not good as expected. This will involve an additional cost and also involve a variation works in the future. The investigation involves are a topographical survey and geotechnical investigation. In order to avoid variation works, the investigations must be in detail and adequate. This is one good way of reducing the variation claims. 4.2.6 Provision of Complete Documentation In order to minimize the variations, the provision of complete documentation must take into consideration before the parties enter into contract. It is important to make sure all the information in the document is complete. For example, for the contract based on the drawing and specification, the consultants must ensure that the document contract must completely attach the entire relevant document. The detail specifications are required for the lump sum contract. 37 4.3 Post Contract Stage The common issue arises in the construction and cannot be avoided is a variation works. Therefore there are some strategy actions that can be taken at post contract stage in order to minimize the variation works in construction. 4.3.1 Contractor’s Efficiency One of the causes of variation is contractor’s inefficiency in doing the job. In order to minimize the variations, the contractor must carry out the work with efficiency as stated in the condition of contract which is carry out the work regularly and diligently. Any instruction by the S.O’s which related to variation work, the contractor must follow the S.O’s instruction and if he fails to do so he will be considered breach the contract. The contractor shall proceed to carry out the work and not be delay and pending in doing the work to grant the extension of time for completion the work. 4.3.2 Keeping Systematic Site Record Site record is important as an evidence of the work. If there is a systematic site report, the work can be done properly without any disturbance. For example piling works, the record must be properly managed in order to avoid problems in future. Besides that, piling works is a provisional quantities and subject to re-measurement, so it important to keep a systematic record. 38 4.3.3 Daily Check Daily check is one of the actions to control the variation at post contract stage. It is important because if there is a daily check on the site, the variation arise from the contractor’s mistake can be reduced. The checking can be done by the S.O or S.O’s representative. The contractor should give a fully cooperation to them at this stage and a good communication is needed. 4.3.3 Fully Inspection Every works by the contractor must be inspected by the S.O or S.O’s representative. If the work is not inspecting by the S.O, the work may result a variation in future. Fully inspection also be done before the construction start and after the work completed before issuing the Certificate of Completion. Investigation before the construction includes the site investigation and also soil investigation, while investigation after work complete is inspection done by the all parties involved including Local Authority. This investigation is important to prevent the variations. If there is no investigation, it might be changes in work future. 4.3.4 Comply With All Requirement The contractor and the consultants must comply with all Local Authority’s requirement. All the works carried out by the contractor must according to the specifications by the Local Authority and the contract, for example requirements from Fire and Rescue Department, Drainage and Irrigation Department (JPS) and others. It 39 is important to comply with all requirements in order to control the variation work. If the works not follow the requirement, the work might be rectified or demolished and must reconstruct according to the specification. This will result variation works. 4.4 Summary From the literature review research above, therefore the strategy action that can be taken in order to minimize the variation can be summarized as two categories which during pre-contract stage such as clear and thoroughly project brief; detailing of design; adequate time in preparation of documentation; management procurement Strategy; detail and adequate investigation; and provision of complete documentation. While during post contract stage can be summarized as contractor’s efficiency; daily check; fully inspection; and comply with all requirement. CHAPTER 5 RESEARCH METHODOLOGY 5.1 Introduction The research methodology is essential in guiding the researcher to achieve the aim and the objectives of the study. This chapter will describe the methodology procedure was to ensure that the information obtained for this study was relevant and capable of qualitative evaluation. The necessary data for the analysis could not be found from the literature review. Therefore data collection had been carried out. The data collection based on the literature review could be collected in several ways. Buckley et all (1976) grouped the methodology of data collection under four headings; namely opinion research, empirical research, archival research and analytical research. Each method has its own strengths and limitations, and none could be considered superior that the others. The decision as to which methods to use must be based on the survey objectives, the nature of the information required and the resources available (Jobber, 1991). 41 The types of variation and the factors that influence the variation have been discussed in the previous chapter which covers the primary input of Variation Order. It has completing the objective to study what are the meaning of variation and and type of variation that cause of variation order. The development outline involve in pre-contract stage which is the sequence of progress through the stages of design and construction of a building project and problem in variation and the implication of variation identified through various sources such as reference book, journal, seminar’s paper, magazine and other sources by way of using internet. The question which need to be clarified is whether the theoretical practice and what is practicing by the parties which involve in the construction such as client, consultant and the contractor. This phenomenon will be determined through this research. 5.2 Stage 1 : Literature Review There are three sections under the literature review where the first section explained and discussed the types of variation and the factors influence the variation which begin with the definition of variation order. The second section describe the problem in variation order and the implication of variation order. And the third section described the strategy action that can be taken to control or minimize the variation order in the construction. The source of data is obtained from the reading materials and such as books, articles and seminar’s paper and other published information supporting the topic of variation order. 42 5.3 Stage 2 : Interview and Case Study The second stage consists of preparing and collecting of primary data through interview session and based on the case study. Generally the data is collected directly from the professional parties which are relevant to the topic and also from the professional parties whom directly involve in the case study. Analysis of data by using qualitative methods is required to determine the factors that influence the variation and the strategy action to be taken in order to control or minimize the variation start from pre-contract stage until post-contract stage. The case study were selected which the development of the project are similar and by using the same procurement method which is traditional method. The data collected from the case study and interview are gathered and analyzed by using percentage analysis and the qualitative method by comparing the three case studies in project background, project details and the list of variation occur in final contract in which to identify the major factors that influence variation, the problem in variation and the implication that related to variation order during pre-contract stage and post contract stage. The interviewing session is done to the personnel of the department who completely deal with refurbishment project and related case study is taken into account to gather facts about the problem related to refurbishment project. Set of questions is formulated during the interviewing session to highlight the process of refurbishment project as whole. All data will then be analysed and evaluated. The differences of refurbishment process by each organization will be summarized into table which it would be an effective ways to differentiate the data clearly. 43 5.4 Stage 3 : Recommendation In this stage is the final stage of the research methodology. The final stage of this study is to define the conclusion and recommendation with reference to the objective, subsequent to the analysis from the case study and interviews. 5.5 Summary For the conclusion, this chapter is discussing about the methods of collecting all data and analysis of the result from the interviews and case study. The data is analyzed by using qualitative methods to complete the requirement of the research. CHAPTER 6 DATA ANALYSIS AND RESULT 6.1 Introduction This chapter will look at the some project that involved the variation works. There are three (3) case study that have been selected in order to fully understand on the factors that influence to variation, the problems that influence to variation and the implication of variations work, and also to find out what are the strategy action taken in order to control or minimize the variations in the construction. All of three case study using the same procurement strategy, which are Standard Form of IEM.CE 1/89 and have completed with the final account. The completed project with final account has been choose in order to know the amount of variation works involved and how far the cost of variation works affected the cost of the original contract sum. The three case studies are as follows: (i) Case Study 1 : Cadangan Pembangunan Feldajaya Mempaga, Mukim Sabai Daerah Bentong, Pahang Darul Makmur. (ii) Case Study 2 : Cadangan Pembangunan Feldajaya Serting Negeri Sembilan. (iii) Case Study 3 : Cadangan Pembangunan Feldajaya Trolak Perak Darul Ridzuan. 45 6.2 Case Study 1 The case study 1 which summaries the background of the Project of Cadangan Pembangunan Feldajaya Mempaga, Mukim Sabai, Pahang Darul Makmur. The parties involved are the client which is Lembaga Kemajuan Tanah Persekutuan(FELDA), Felda Engineering Services Sdn. Bhd. as Project Manager and Quantity Surveyor, Arup Jururunding Sdn. Bhd. As Structural and M&E Engineer, the architecht are W&W Architect and Bauran Bina Sdn. Bhd. as the contractor. The contract no of this project is contract 100000445. The original contract sum is value at RM 32,747,987.00 and adjustment to Contract Sum RM16, 621,218.60 which made the final contract sum to RM 49,369,205.60. The contract period for this project is 72 weeks and the date of site possession is on 9thJune 2003 which the original of completion date on 15th March 2005, but the actual completion date is on 30th October 2006 with the defect Liability Period which on 30thApril 2007. List of the variation works as shown in Table 6.1 shows the factor that influence to the variation works and also the cost incurred for each variation work. For this project, there are forty four (44) variation works involved including re-measurement works. Table 6.1 : List of variation works for case study 1 V.O NO TOTAL(RM) DESCRIPTION FACTORS INFLUENCE V.O ADDITION VARIATION WORKS 1. Outside Drain To comply JPS requirement 2,705,545.00 2. Paip Retikulasi Kumbahan To comply JPP requirement 280,000.00 3. Side Drain Site Condition 294,765.00 4. To build Road & Car Porch To comply JKR requirement 1,889,946.00 5. Upgrading laluan masuk utama To comply JKR requirement 1,062,600.00 6. To prepare Road to Water tank To comply JBA requirement 860,000.00 7. Kolam takungan To comply JPS requirement 1,064,000.00 8. Changes Jajaran Paip Retikulasi To comply JPP requirement Kumbahan 9. Planting grass for awaken the slope (Behind Bungalow & TNB 3) 93,250.00 To comply Majlis Daerah requirement 1,378,545.00 OMISSION 10. Strengthening Bungalow Structure Site Condition 50,000.00 11. Changes Jubin at Car porch Error in BQ 80,000.00 Bungalow House 12. Dewan Makan Kolej KINI 13. Additional Tandas at Academic Changes on design 450,000.00 Changes on design 240,000.00 Kolej KINI Changes on design 651,260.00 15. Changes Rumah Kedai Error in BQ 353,000.00 16. Changes Building Tadika/Pusat IT. Error in BQ 148,600.00 17. Road crossing TNB To comply TNB requirement 12,348.00 18. Bungalows main entrance To comply TNB requirement 102,900.00 19. Bungalows driveway with crushed To comply TNB requirement 55,000.00 To comply TNB requirement 9,000.00 Block Kolej Kini (2 Unit) 14. Changes structure building design run & premix. 20. Portion of main road with crushed run and premix 21. Grouting ( Prelim, Medan selera, Site condition 347,807.00 Bungalow 6B,37C,72A) 22. Additional Tingkap pintu, Frosted Error in BQ glass (Bungalow A) 39,000.00 15,000.00 23. Changes lockset Client’s request 24. Additional Pintu D2 Kitchen Error in BQ 24,000.00 1,303,797.80 Bungalow 25. Changes Pipe HDPE to MS To comply JBA requirement 26. Preliminary Hoarding Remesurement 27. Ancillary Building (TNB, Dewan & Remesurement 35,375.00 146,000.00 60,000.00 41,000.00 Pasar) 28 Water Reticulation Remesurement 343,000.00 29. Electrical Works (Pasar, Dewan, Remesurement 107,536.00 Remesurement 330,783.52 Kolej & Tadika) 30. Additional Dewan & Pasar-M&E works 31. Prime Cost ( STP, Meru Tanda, Client’s request 30,000.00 959,971.30 Landscape Works, Playground Equipment) 32. Piling works Site Condition 33. TCT rolform Error in BQ 55,800.00 34. R.C concrete sump Error in BQ 21,000.00 35. Gutter and Flashing Error in BQ 150,000.00 36. Railing Error in BQ 301,000.00 37. Box culvert To comply JKR requirement 845,000.00 38. Change location of Kilang Bata Client’s request 39. Water proofing (banglow & building) Error in BQ 40. Change thk of crusher run To comply JKR requirement 41. Additional building- tandas awam Client’s request 82,000.00 42. Change size of surau Client’s request 280,000.00 43. Access car porch Client’s request 345,000.00 44. Perasmian Hari Peneroka Client’s request 426,478.00 18,000.00 71,000.00 1,000,000.00 Total 18,155,613.10 Net total 16,621,218.60 1,533,694.50 6.3 Case Study 2 The case study 2 which summaries the background of the Project of Cadangan Pembagunan Fasa 1 Feldajaya Selatan. Mukim Serting Daerah Jempol, Negeri Sembilan, Darul Khusus. The parties involved are the client which is Lembaga Kemajuan Tanah Persekutuan(FELDA), Felda Engineering Services Sdn. Bhd. as Project Manager and Quantity Surveyor, Arup Jururunding Sdn. Bhd. As Structural and M&E Engineer, the architect is W&W Architect and Prinseptek Sdn. Bhd. as the contractor. The contract no of this project is contract 100000464. The original contract sum is value at RM 45,000,000.00 and adjustment to Contract Sum RM12,983,300.00 which made the final contract sum to RM 57,983,300.00. The contract period for this project is 72 weeks and the date of site possession is on 23thJune 2003 which the original of completion date on 20th December 2004, but the actual completion date is on 4th September 2006 with the defect Liability Period which on 4thApril 2008. List of the variation works as shown in Table 6.2 shows the factor that influence to the variation works and also the cost incurred for each variation work. For this project, there are forty seven (47) variation works involved including remeasurement works. Table 6.2 : List of variation works for case study 2 V.O TOTAL(RM) NO DESCRIPTION FACTORS INFLUENCE V.O ADDITION VARIATION WORKS 1. Supply & lay UPVC Error in BQ 222,464.90 2. Construction & completion of Mercu Tanda Error in BQ 68,000.00 3. Excavation, Backfilling Sand & Crusher runs. Error in BQ ( Laluan A1,A2 & A3) 74,400.00 4. Road crossing Works ( Laluan B1) Error in BQ 5. Road Crossing Works ( Laluan Sesalur Error in BQ 6. Telekom) 7. Sand & Bricks ( Bungalow A, B, C, D, & E) Error in BQ 119,214.00 8. 60A 3 Phase Kiosk meter Error in BQ 57,200.00 9. Labour, tools & transportation for installation, 90,000.00 158,000.00 OMISSION excavation & other works. Error in BQ 73,920.00 10. Additional Pillar Board & Telephone Works Error in BQ 59,900.00 11. Relocate TNB & Telephone pit at ‘Hentian Bas’ To comply TNB requirement Block Drains To comply JPS requirement 12. Hose Reel Tank & Pump House at Tadika Error in BQ 67,814.21 13. Additional for Air (Kolej) Error in BQ 138,980.00 14. Main Switch Board (MSB) and Cable Error in BQ 392,750.00 15. Slope Trimming & Hydro seeding Works Error in BQ 81,143.05 16. Road Crossing for TNB To comply TNB requirement 20,477.60 17. Additional for 3 phase at Rumah Kedai Error in BQ 20,000.00 18. Paint Road Kerb using emulsion paint type Error in BQ 54,560.00 2,000.00 136,512.00 weather. 19. Banglow House ( A,B,C,D,E) Change in design 626,287.78 20. Tandas Kolej Client’s request 198,130.80 21. Medan Selera Remesurement 27,987.87 22. Pasar Change in design 54,926.76 23. Perhentian Bas & Teksi Change in design 19,173.35 24. Tadika/ IT Centre/Library S.O instruction, site condition 25. Surau Change in design 158,200.00 26. Kolej Intergrasi Ilmu Change in design 211,038.75 27. Dewan – TCT rolform Error in BQ 294,962.19 28. TNB Sub Station ( 44’ x 20’ & 44’ x 18’) To comply TNB requirement 225,000.00 29. External Works ( Precast Concrete Block Drain, Remesurement 61631.89 Brick wall to Drain/Rubble Wall, Box Culverts, Sewerage Pipe, Sewerage Manhole & Excavation) 30. JPS Upgrading To comply JPS requirement 31. Water Reticulation Remesurement 398,064.80 32. Elevated Water Tank & Fencing Remesurement 917,853.90 33. Suction Tank Remesurement 599,397.96 34. Pilling ( Dewan Makan) Remesurement 110,000.00 35. Junction ( Clearing, Drainage, Shoulder, Road Remesurement 6,609.00 Marking, Electrical Works) 8,342,637.67 763,891.08 36. Pilling Works Remesurement, Site condition 37. R.C Piles Remesurement 436,406.00 38. Transport, Handle, Pitch and Drive Remesurement 117.463.50 39. Extension Joints Remesurement 15,769.10 40. Cut-Off Piles Remesurement 32,752.00 41. Load Testing Remesurement 17,600,00 42. Static Load Test Remesurement 7,000.00 43. Subsequent Static Load Test and Drive Remesurement 6,000.00 44. Piling Record Remesurement 2,400.00 45. Mackintosh Probes Remesurement 9,000.00 46. Tandas Hentian Bas Remesurement 57,982.00 47. Dewan Makan Kolej Remesurement 48,556.00 10,000.00 Total 12,983,381.04 Net total 12,983,381.04 6.4 Case Study 3 The case study 3 which summaries the background of the Project of Cadangan Pembagunan Fasa 1 Feldajaya Utara, Felda Trolak, Mukim Sungkai Perak. The parties involved are the client which is Lembaga Kemajuan Tanah Persekutuan (FELDA), Felda Engineering Services Sdn. Bhd. as Project Manager and Quantity Surveyor, Arup Jururunding Sdn. Bhd. As Structural and M&E Engineer, the architect is W&W Architect and Aruz Zaman Sdn. Bhd. as the contractor. The contract no of this project is contract 100000464. The original contract sum is value at RM 38,000,000.00 and adjustment to Contract Sum RM15,820,340.00 which made the final contract sum to RM 53,820,340.00. The contract period for this project is 72 weeks and the date of site possession is on 23thJune 2003 which the original of completion date on 20th December 2004, but the actual completion date is on 15th August 2006 with the defect Liability Period which on 15th March 2008. List of the variation works as shown in Table 6.2 shows the factor that influence to the variation works and also the cost incurred for each variation work. For this project, there are thirty five (35) variation works involved including remeasurement works. Table 6.3 : List of variation works for case study 3 V.O TOTAL (RM) NO DESCRIPTION FACTORS INFLUENCE V.O ADDITION VARIATION WORKS 1. Gutter & Flashing (for Banglow type Error in BQ 130,954.50 A,B,C,D,E, Surau) 2. Diversion Main Drain (Section A,B, & C) To comply JPS requirement, changes in design, & Error in BQ 3. 2,053,206.00 TCT Rolform (for Dewan, Rumah Kedai, Kolej Kini, Tadika, Pasar, Tandas Awam, Asrama, Medan Selera, Perhentian Bas & Teksi & Dewan Makan) Error in BQ 656,554.48 4. Additional Unit Rumah Kedai Client’s request 209,950.00 5. Additional Tandas Kolej Kini (Pile cap Client’s request , changes in design design) 74,700.90 OMISSION 6. Additional Kolej Kini ( Pipe Footing Pad) Client’s request, changes in design 77,461.32 7. Additional Tandas Awam Client’s request 47,888.10 8. Additional Building Dewan Makan Client’s request 327,317.70 9. Additional Building IKS Client’s request 2,992,400.00 10. Additional Rock Excavation Suite site condition 11. Plate Bearing Test Client’s request 12. Additional Lampu isyarat for Persimpangan To comply JKR requirement Besout 593,396.00 13,800.00 2,000,000.00 13. Additional Jalan susur keluar To comply JKR requirement 1,200,000 14. Changes of design of road To comply JKR requirement 754,960.00 15. Additional Pilling Works Remesurement , site condition 1,250,00.00 16. Additional Earthwork at Suction Tank Remesurement 14,473.20 17. External Works Remesurement 2,300,750.00 18. Changes Pipe HDPE to MS To comply JBA requirement 8,140,000.00 19. Preliminary Hoarding Remesurement 43,000.00 20. Ancillary Building (TNB, Dewan & Pasar) Remesurement 585,000.00 Water Reticulation Remesurement 45,000.00 21. Electrical Works (Pasar, Dewan, Kolej & Remesurement 415,000.00 Tadika) 22. Additional Dewan & Pasar-M&E works Remesurement 150,000.00 23. Prime Cost ( STP, Meru Tanda, Landscape Client’s request 100,000.00 Works, Playground Equipment) 24. R.C concrete sump Error in BQ 48,528.00 25. Hose Reel Tank & Pump House at Tadika Error in BQ 65,000.00 26. Additional for Air-condition (Kolej) Error in BQ 100,000.00 27. Main Switch Board (MSB) and Cable Error in BQ 300,000.00 28. Slope Trimming & Hydro seeding Works Error in BQ 50,000.00 29. Additional for 3 phase at Rumah Kedai Error in BQ 20,000.00 30. Paint Road Kerb using emulsion paint type Error in BQ 50,000.00 weather. 31. Additional Tingkap pintu, Frosted glass Error in BQ 20,000.00 32. Water proofing (banglow & building) Error in BQ 70,000.00 33. Changes Jubin at Car porch Bungalow Error in BQ 80,000.00 34. House 35. Railing Error in BQ 200,000.00 Total Net total 15,820,340.00 60 6.5 Result and Analysis a. The result of the types of variation and the factors that influence to the variation From the three case studies above, the analysis and the result of the types of variations were tabulated in the Table 6.4. While the factors that influence the variation can be shown in the 6.5. Based on the Table 6.5 the percentage of the factors that influence the variation have been summaries in the Figure 6.1 Table 6.4 : Types of variations Item 1. 2. 3. Types of variation Example According to identity of the Client, consultant, authority initiator and contractor etc. According to nature of Addition, omission and variation combination of both. The consequence or effect of Financial consideration or time variation implication (adjustment in the contract sum) 61 Table 6.5 : Factors that influence to variations Item Factors influence the No. of variations variations Case Case Case Study 1 Study 2 Study 3 Total 1 Client’s request 7 1 5 13 2 Change in design 3 5 3 11 3 Errors in Bills of 10 16 14 40 15 5 4 24 Quantities 4 Change due to Local Authority requirement 5 S.O’s instruction - 1 - 1 6 Remeasurement 5 18 8 31 7 Suit site condition 4 1 1 6 5% 25% Client’s request 10% 9% Change in design Errors in Bills of Quantities 1% 19% 32% Change due to Local Authority requirement S.O’s instruction Remeasurement Suit site condition Figure 6.1 : Percentage factors that influence to variations 62 b. The result of the problems that influence and the implication to the variation From the three case studies above, many problems that influence to variation works. The variation works also give an implication to the construction itself. The result of the problem that influence to the variation was identified in two categories which during planning stage and construction stage as shown in Table 6.6. Table 6.6 : Problem that influence to variations List of problem that influence to variation Item 1. Planning Stage Construction Stage No feasibilities study of the No survey work project 2. No proper project brief No proper soil investigation 3. Time constraint for preparing Misunderstanding in communication design and contract between project team documentation 4. Lack of checking on detailing Unexpected condition during design and drawing construction such as climate changes such as heavy rain and lightening can cause damage to the site of construction. 5. Lack of checking on quality Unforeseen condition such as found tender documentation rock under ground level, high water table and fossil 63 The major implication was identified as cost overrun as shown in Table 6.7 and the percentage that summarized the cost overrun shows in Figure 6.2. While the delays of the construction work was identified as shown in Table 6.8. The percentage of implication to the variation was shown in the Figure 6.3 which the result shows the case study 1 was delay more than 51% compared to two case studies above. Table 6.7 : The implication of variation – Cost Overrun Bil Case Implication of variations Study Cost Overrun Original Final Variation Percent Contract Contract order (%) of Amount Amount total variation 1 Case 32,747,987.00 49,369,205.60 16,621,218.60 51% 45,000,000.00 57,983,300.00 12,983,300.00 42% 38,000,000.00 53,820,340.00 15,820,340.00 29% 115,747,987.00 161,172,845.60 45,424,858.60 Study 1 2 Case Study 2 3 Case Study 3 Total 64 42% 51% Case study 1 Case study 2 Case study 3 29% Figure 6.2 : Percentage implication to variation – Cost Overrun Table 6.8 : The implication of variation – Delay Bil 1 Case Implication of variations Study Delay Case Original Final Delay Percent Contract Contract (days) (%) of Period Period 504 700 196 39% 504 1,008 504 100% 504 952 448 89% 1,512 2660 1,148 total delay Study 1 2 Case Study 2 3 Case Study 3 Total 65 39% 89% Case Study 1 Case Study 2 Case Study 3 100% Figure 6.3 :The implication of variation – Delay c. The result of the strategy action that can be taken to minimize variation The last section of the case study is to identify the strategy action that can be taken to minimize or control the variation work. The result can be tabulated in table 6.9 as shown below. 66 Table 6.9 : Strategy action can be taken to minimise or control variation Item Strategy action can be taken to minimise or control variation Planning Stage 1. Construction Stage Proper feasibilities study of the Proper survey work project 2. Clear and thorough project Proper soil investigation brief 3. Appropriate use of all day check at site procurement strategy 4. More thorough detailing of fully investigate. design. 5. 6.6 Quality contract comply with all authority documentation requirement Finding s and Discussion This section discussed the findings of this study. The results of the study are analysed and discussed in the following sequence to answer the objectives mentioned in Chapter 1. The analysis sequence is organized and presented the data in some meaningful and logical order. After the data have been organized and presented into description manner, it is then analyses them in order to draw inference about the data obtained. The discussion are included the factor that influence the variation, the problems that can cause the problem and then followed by the implication of variation work. Finally, discuss on the strategy action that can be taken to minimize or control variation work. Discussion on the finding will be based on the case study and interview responding to the objectives. 67 a. First Objective : To identify the types of variation and the factor that influences the variation. This section will discuss the finding based on the results obtained from the interview and the case study in which the types of variation and the factors of variation were identified. Table 6.4 shows the result types of variation and the factors that influence this. Table 6.4 : Types of variation Item 1. Types of variation Example The identity of the initiator client, consultant, authority and contractor 2. The nature of variation Nature of the work, changes in the condition of contract and included omission and addition and combination of both 3. The consequence or effect of Financial consideration or time variation implication (adjustment in the contract sum) From the Table 6.4, it can be concluded that, there are three types of variation that can be categorized by the identity of initiator which can be change to one another such as client or employer, consultant such as architect or engineer, the authority requirement and also the contractor. The nature of variation such as the nature of work such as site condition or weather, any changes in the condition of contract and the variation by the omission or addition work during construction. The third type of variation shows that the financial consequence or effect of variation such as financial consideration or time implication such as adjustment in the contract sum during construction in progress. 68 Table 6.10 : The Factors that influence the variations(%) Item Factors influence the variations (%) 1 Client’s request 10 2 Change in design 9 3 Errors in Bills of Quantities 32 4 Change due to Local Authority 19 requirement 5 S.O’s instruction 1 6 Remeasurement 25 7 Suit site condition 5 From the Table 6.10, it can be concluded that, the major factor that influence the variation work is comes from the Error in Bill of Quantities. From the table 6.10 above, it shows that 32% of the variation works comes from the Error in Bill of Quantities. Almost every project has a variation from Error in Bill of Quantities. Besides that, the re-measurements of the work also contribute to the variation of works. From the Table 6.10 , it can see that the re-measurement contribute 25% and follow by Local Authority’s requirement which from the case studies above, it shows that the Local authority contribute 19% to variation works. It is important to follow the regulation from the Local Authority because if the requirement not properly followed, it may cause the variation works. From example from the case study above, variation works arise where the thick of the crusher-run of road used in the project not according to the specification from the JKR. Therefore the changes have to follow as the authority requirement. Beside that, the client request also contribute to the variation works which from the Table 6.10 shows 10%, and followed by the variation works which is 69 changes in design which is 9%, suit the site condition is 5%, and also from the case studies above, it shows that there is only 1% of S.O’s instruction that contribute to the variation works. b. Second Objective : To identify the problems and the implication to the variation of the construction starts from planning until construction stage. From the factor above, the problem that influence of variation has been identified which can be divided into two stages. The first stage was during planning stage and the second was during construction stage. The major problem that influences variation during planning stage and construction stage were identified as shown in table 6.5. Uncorrected planning during early stage of the project implementation will give implication to the construction especially in the variation work. No proper feasibility studies carried out during early stage of the projects. This problem occur when the client insist the project will be completed in certain dates due to sometimes political issues. This will influence to the variation. Therefore it is important that the feasibility studies of the project should be done in proper manner to minimize or control the variation to the construction. Besides that, no proper project brief can influence to the variation, followed by the time constraint for preparing design and contract document which can cause mistake and error in the drawing and documentation. The lacking of checking on detail design and drawing which also contribute to the variation and finally, the lacking of checking on the quality of tender document also can influence to the variation. 70 Table 6.6 : Problem that influence to variations List of problem that can cause of variation Item 1. Planning Stage Construction Stage No feasibilities study of the No survey work project 2. No proper project brief No proper soil investigation 3. Time constraint for preparing Misunderstanding in design and contract communication between project documentation team Lack of checking on detailing Unexpected condition during design and drawing construction such as climate 4. changes such as heavy rain and lightening can cause damage to the site of construction. 5. Lack of checking on quality Unforeseen condition such as tender documentation found rock under ground level, high water table and fossil While the implication of variation from the three case studies above, it can be seen that the variation works give an implication to the construction itself. The obvious implication of the variations is show in the Table 6.11 which cost overruns that carried by the contractor should be paid as extra work or variation. 71 Table 6.11 : Cost Overrun for Case Study 1 ITEM DESCRIPTION OMISSION 1. Original contract Amount 2. Net Addition ADDITION 32,747,987.00 16,6218.60 16,6218.00 Final Contract Amount 49,369,205.60 From the case study 1, it can be concluded that the total net of cost for variation works is RM 16,621,218.00 to the contract sum. This means that the contract sum must be added for amount of RM16,621,218.00 which increase 51% form the original contract amount. The final contract amount is RM49,369,205.60. The summary of this result show in the Table 6.11 above. Table 6.12 : Cost Overrun for Case Study 2 ITEM DESCRIPTION OMISSION 1. Original contract Amount 2. Net Addition ADDITION 45,000,000.00 12,983,300.00 12,983,300.00 Final Contract Amount 57,983,300.00 From the case study 2, have same implication which is cost overrun because of the variation works. The original contract amount increase 42% from RM45,000,000.00 to RM 57,983,300.00 which the total net of variation works are RM 12,983,300.00. The summary of this result shows in the Table 6.12. 72 Table 6.13 : Cost Overrun for Case Study 3 ITEM DESCRIPTION OMISSION 1. Original contract Amount 2. Net Addition ADDITION 38,000,000.00 15,820,340.00 15,820,340.00 Final Contract Amount 53,820,340.00 From the case study 3, it can be concluded that the variation works involved only in net additional works which cost of RM 15,820,340.00 to be added to the original contract amount. The original contract amount increase 29% from RM 38,000,000.00 to RM 53,820,340.00. The summary of this result shows in the Table 6.13. The other implication to the variation is delay of the project. From three case studies show that almost all the project was delay due to the variation order. Table 6.14 shown delay in the construction period due to the variation works. Table 6.14 : Delay Bil Case Study Implication of variations Delay Original Final Delay (%) of Contract Contract (days) total delay Period Period 1 Case Study 1 504 700 196 39% 2 Case Study 2 504 1,008 504 100% 3 Case Study 3 504 952 448 89% 73 From the Table 6.14 above, shows that the case study 2 was delay 100% of the original contract period which contribute about 1,008 days compare of cased study 3 which contribute 89% of delay about 952 days, then followed by the case study 1 which contribute 39% of delay about 700 days. This result shows that the case study 2 was delay the most in the construction work compared the other two case studies. c. Third Objective : To identify the strategy action that can be taken to minimize or control the variation. This section discussed the finding based on the result obtained from the cased study and interview to identify the strategy action that can be taken to minimize or control the variation works. The strategy action can be taken as early in planning stage and also construction stage there are identified as: Comprehensive site investigation; based on the case study above, there are a numbers of the variation occur caused due to suit the site condition. It is clear that before the construction start, it need a comprehensive site investigation. For example of site investigation is topographical survey and geotechnical investigation. Although the cost incurred in the site investigation is usually a small fraction of the total project, but the clients or related parties do not appreciate the importance of the survey and no investigation is carried out, the construction may turns out to be not good, if survey is properly done, the variation works might be reduced and cost is under control. Quality contract documentation; quality in contract documentation is important because it will influence the eventual outcome of the contract. The document must be complete in order to avoid problems in future. It must clearly define the task and works that need to be done by the contractor especially in bills of quantities. From the case studies above, the errors in bills of quantities contribute to the variation works. Poorly prepared documents will result in uncertainty future. 74 Besides that, if there is variation works, the contractor must ensure that he has clearly defined procedures for identifying variations and that he must conforms to full requirements of the contract. Hence the contract must be clearly presented. The implication if the contract document prepared is incomplete, it will be the causes of cost overruns. More thorough detailing in design; detail design can reduce variation in future. The design developed in depth at the pre-contract stage with the cooperation must be developed in order to avoid the claims and dispute. Any changes later will result in abortive works and almost certainly in additional cost. From the case studies above, changes in design will result the variation works. In order to control the variations, the design team must properly design with take all the consideration including site condition and requirement by the Local Authority into the design. Compliance with local authority’s requirement; Local authority involved in the construction such as Fire and Resque Department (BOMBA), Telecom, Tenaga Nasional Berhad (TNB), Jabatan Bekalan Air (JBA) and others. All these authority have their own regulation that must be followed during the construction. Most of the variation works are caused by the changes in Local Authority’s requirement. For example, in the case studies above, there are twenty four (24) variation works are caused by the Local Authority’s requirement. If the works are properly done and followed the entire requirement stated by the Local authority it will reduce the numbers of variation of works. 75 6.7 Summary The final result of the analysis was listed. According to the result analysis it shows that there are three types of variation and the most factor that influence the variation is Error in Bill of Quantities. And there are five problems that can cause variation during planning stage and construction stage. Therefore the implication of variation it shows that the cost overruns of the project and the delay in the construction period were the most implication of variation. Lastly, the strategy action that can be taken to minimize or control the variation is focusing during planning stage and also construction stage. 45 6.2 Case Study 1 The case study 1 which summaries the background of the Project of Cadangan Pembangunan Feldajaya Mempaga, Mukim Sabai, Pahang Darul Makmur. The parties involved are the client which is Lembaga Kemajuan Tanah Persekutuan(FELDA), Felda Engineering Services Sdn. Bhd. as Project Manager and Quantity Surveyor, Arup Jururunding Sdn. Bhd. As Structural and M&E Engineer, the architecht are W&W Architect and Bauran Bina Sdn. Bhd. as the contractor. The contract no of this project is contract 100000445. The original contract sum is value at RM 32,747,987.00 and adjustment to Contract Sum RM16, 621,218.60 which made the final contract sum to RM 49,369,205.60. The contract period for this project is 72 weeks and the date of site possession is on 9thJune 2003 which the original of completion date on 15th March 2005, but the actual completion date is on 30th October 2006 with the defect Liability Period which on 30thApril 2007. List of the variation works as shown in Table 6.1 shows the factor that influence to the variation works and also the cost incurred for each variation work. For this project, there are forty four (44) variation works involved including re-measurement works. Table 6.1 : List of variation works for case study 1 V.O NO TOTAL(RM) DESCRIPTION FACTORS INFLUENCE V.O ADDITION VARIATION WORKS 1. Outside Drain To comply JPS requirement 2,705,545.00 2. Paip Retikulasi Kumbahan To comply JPP requirement 280,000.00 3. Side Drain Site Condition 294,765.00 4. To build Road & Car Porch To comply JKR requirement 1,889,946.00 5. Upgrading laluan masuk utama To comply JKR requirement 1,062,600.00 6. To prepare Road to Water tank To comply JBA requirement 860,000.00 7. Kolam takungan To comply JPS requirement 1,064,000.00 8. Changes Jajaran Paip Retikulasi To comply JPP requirement Kumbahan 9. Planting grass for awaken the slope (Behind Bungalow & TNB 3) 93,250.00 To comply Majlis Daerah requirement 1,378,545.00 OMISSION 10. Strengthening Bungalow Structure Site Condition 50,000.00 11. Changes Jubin at Car porch Error in BQ 80,000.00 Bungalow House 12. Dewan Makan Kolej KINI 13. Additional Tandas at Academic Changes on design 450,000.00 Changes on design 240,000.00 Kolej KINI Changes on design 651,260.00 15. Changes Rumah Kedai Error in BQ 353,000.00 16. Changes Building Tadika/Pusat IT. Error in BQ 148,600.00 17. Road crossing TNB To comply TNB requirement 12,348.00 18. Bungalows main entrance To comply TNB requirement 102,900.00 19. Bungalows driveway with crushed To comply TNB requirement 55,000.00 To comply TNB requirement 9,000.00 Block Kolej Kini (2 Unit) 14. Changes structure building design run & premix. 20. Portion of main road with crushed run and premix 21. Grouting ( Prelim, Medan selera, Site condition 347,807.00 Bungalow 6B,37C,72A) 22. Additional Tingkap pintu, Frosted Error in BQ glass (Bungalow A) 39,000.00 15,000.00 23. Changes lockset Client’s request 24. Additional Pintu D2 Kitchen Error in BQ 24,000.00 1,303,797.80 Bungalow 25. Changes Pipe HDPE to MS To comply JBA requirement 26. Preliminary Hoarding Remesurement 27. Ancillary Building (TNB, Dewan & Remesurement 35,375.00 146,000.00 60,000.00 41,000.00 Pasar) 28 Water Reticulation Remesurement 343,000.00 29. Electrical Works (Pasar, Dewan, Remesurement 107,536.00 Remesurement 330,783.52 Kolej & Tadika) 30. Additional Dewan & Pasar-M&E works 31. Prime Cost ( STP, Meru Tanda, Client’s request 30,000.00 959,971.30 Landscape Works, Playground Equipment) 32. Piling works Site Condition 33. TCT rolform Error in BQ 55,800.00 34. R.C concrete sump Error in BQ 21,000.00 35. Gutter and Flashing Error in BQ 150,000.00 36. Railing Error in BQ 301,000.00 37. Box culvert To comply JKR requirement 845,000.00 38. Change location of Kilang Bata Client’s request 39. Water proofing (banglow & building) Error in BQ 40. Change thk of crusher run To comply JKR requirement 41. Additional building- tandas awam Client’s request 82,000.00 42. Change size of surau Client’s request 280,000.00 43. Access car porch Client’s request 345,000.00 44. Perasmian Hari Peneroka Client’s request 426,478.00 18,000.00 71,000.00 1,000,000.00 Total 18,155,613.10 Net total 16,621,218.60 1,533,694.50 6.3 Case Study 2 The case study 2 which summaries the background of the Project of Cadangan Pembagunan Fasa 1 Feldajaya Selatan. Mukim Serting Daerah Jempol, Negeri Sembilan, Darul Khusus. The parties involved are the client which is Lembaga Kemajuan Tanah Persekutuan(FELDA), Felda Engineering Services Sdn. Bhd. as Project Manager and Quantity Surveyor, Arup Jururunding Sdn. Bhd. As Structural and M&E Engineer, the architect is W&W Architect and Prinseptek Sdn. Bhd. as the contractor. The contract no of this project is contract 100000464. The original contract sum is value at RM 45,000,000.00 and adjustment to Contract Sum RM12,983,300.00 which made the final contract sum to RM 57,983,300.00. The contract period for this project is 72 weeks and the date of site possession is on 23thJune 2003 which the original of completion date on 20th December 2004, but the actual completion date is on 4th September 2006 with the defect Liability Period which on 4thApril 2008. List of the variation works as shown in Table 6.2 shows the factor that influence to the variation works and also the cost incurred for each variation work. For this project, there are forty seven (47) variation works involved including remeasurement works. Table 6.2 : List of variation works for case study 2 V.O TOTAL(RM) NO DESCRIPTION FACTORS INFLUENCE V.O ADDITION VARIATION WORKS 1. Supply & lay UPVC Error in BQ 222,464.90 2. Construction & completion of Mercu Tanda Error in BQ 68,000.00 3. Excavation, Backfilling Sand & Crusher runs. Error in BQ ( Laluan A1,A2 & A3) 74,400.00 4. Road crossing Works ( Laluan B1) Error in BQ 5. Road Crossing Works ( Laluan Sesalur Error in BQ 6. Telekom) 7. Sand & Bricks ( Bungalow A, B, C, D, & E) Error in BQ 119,214.00 8. 60A 3 Phase Kiosk meter Error in BQ 57,200.00 9. Labour, tools & transportation for installation, 90,000.00 158,000.00 OMISSION excavation & other works. Error in BQ 73,920.00 10. Additional Pillar Board & Telephone Works Error in BQ 59,900.00 11. Relocate TNB & Telephone pit at ‘Hentian Bas’ To comply TNB requirement Block Drains To comply JPS requirement 12. Hose Reel Tank & Pump House at Tadika Error in BQ 67,814.21 13. Additional for Air (Kolej) Error in BQ 138,980.00 14. Main Switch Board (MSB) and Cable Error in BQ 392,750.00 15. Slope Trimming & Hydro seeding Works Error in BQ 81,143.05 16. Road Crossing for TNB To comply TNB requirement 20,477.60 17. Additional for 3 phase at Rumah Kedai Error in BQ 20,000.00 18. Paint Road Kerb using emulsion paint type Error in BQ 54,560.00 2,000.00 136,512.00 weather. 19. Banglow House ( A,B,C,D,E) Change in design 626,287.78 20. Tandas Kolej Client’s request 198,130.80 21. Medan Selera Remesurement 27,987.87 22. Pasar Change in design 54,926.76 23. Perhentian Bas & Teksi Change in design 19,173.35 24. Tadika/ IT Centre/Library S.O instruction, site condition 25. Surau Change in design 158,200.00 26. Kolej Intergrasi Ilmu Change in design 211,038.75 27. Dewan – TCT rolform Error in BQ 294,962.19 28. TNB Sub Station ( 44’ x 20’ & 44’ x 18’) To comply TNB requirement 225,000.00 29. External Works ( Precast Concrete Block Drain, Remesurement 61631.89 Brick wall to Drain/Rubble Wall, Box Culverts, Sewerage Pipe, Sewerage Manhole & Excavation) 30. JPS Upgrading To comply JPS requirement 31. Water Reticulation Remesurement 398,064.80 32. Elevated Water Tank & Fencing Remesurement 917,853.90 33. Suction Tank Remesurement 599,397.96 34. Pilling ( Dewan Makan) Remesurement 110,000.00 35. Junction ( Clearing, Drainage, Shoulder, Road Remesurement 6,609.00 Marking, Electrical Works) 8,342,637.67 763,891.08 36. Pilling Works Remesurement, Site condition 37. R.C Piles Remesurement 436,406.00 38. Transport, Handle, Pitch and Drive Remesurement 117.463.50 39. Extension Joints Remesurement 15,769.10 40. Cut-Off Piles Remesurement 32,752.00 41. Load Testing Remesurement 17,600,00 42. Static Load Test Remesurement 7,000.00 43. Subsequent Static Load Test and Drive Remesurement 6,000.00 44. Piling Record Remesurement 2,400.00 45. Mackintosh Probes Remesurement 9,000.00 46. Tandas Hentian Bas Remesurement 57,982.00 47. Dewan Makan Kolej Remesurement 48,556.00 10,000.00 Total 12,983,381.04 Net total 12,983,381.04 6.4 Case Study 3 The case study 3 which summaries the background of the Project of Cadangan Pembagunan Fasa 1 Feldajaya Utara, Felda Trolak, Mukim Sungkai Perak. The parties involved are the client which is Lembaga Kemajuan Tanah Persekutuan (FELDA), Felda Engineering Services Sdn. Bhd. as Project Manager and Quantity Surveyor, Arup Jururunding Sdn. Bhd. As Structural and M&E Engineer, the architect is W&W Architect and Aruz Zaman Sdn. Bhd. as the contractor. The contract no of this project is contract 100000464. The original contract sum is value at RM 38,000,000.00 and adjustment to Contract Sum RM15,820,340.00 which made the final contract sum to RM 53,820,340.00. The contract period for this project is 72 weeks and the date of site possession is on 23thJune 2003 which the original of completion date on 20th December 2004, but the actual completion date is on 15th August 2006 with the defect Liability Period which on 15th March 2008. List of the variation works as shown in Table 6.2 shows the factor that influence to the variation works and also the cost incurred for each variation work. For this project, there are thirty five (35) variation works involved including remeasurement works. Table 6.3 : List of variation works for case study 3 V.O TOTAL (RM) NO DESCRIPTION FACTORS INFLUENCE V.O ADDITION VARIATION WORKS 1. Gutter & Flashing (for Banglow type Error in BQ 130,954.50 A,B,C,D,E, Surau) 2. Diversion Main Drain (Section A,B, & C) To comply JPS requirement, changes in design, & Error in BQ 3. 2,053,206.00 TCT Rolform (for Dewan, Rumah Kedai, Kolej Kini, Tadika, Pasar, Tandas Awam, Asrama, Medan Selera, Perhentian Bas & Teksi & Dewan Makan) Error in BQ 656,554.48 4. Additional Unit Rumah Kedai Client’s request 209,950.00 5. Additional Tandas Kolej Kini (Pile cap Client’s request , changes in design design) 74,700.90 OMISSION 6. Additional Kolej Kini ( Pipe Footing Pad) Client’s request, changes in design 77,461.32 7. Additional Tandas Awam Client’s request 47,888.10 8. Additional Building Dewan Makan Client’s request 327,317.70 9. Additional Building IKS Client’s request 2,992,400.00 10. Additional Rock Excavation Suite site condition 11. Plate Bearing Test Client’s request 12. Additional Lampu isyarat for Persimpangan To comply JKR requirement Besout 593,396.00 13,800.00 2,000,000.00 13. Additional Jalan susur keluar To comply JKR requirement 1,200,000 14. Changes of design of road To comply JKR requirement 754,960.00 15. Additional Pilling Works Remesurement , site condition 1,250,00.00 16. Additional Earthwork at Suction Tank Remesurement 14,473.20 17. External Works Remesurement 2,300,750.00 18. Changes Pipe HDPE to MS To comply JBA requirement 8,140,000.00 19. Preliminary Hoarding Remesurement 43,000.00 20. Ancillary Building (TNB, Dewan & Pasar) Remesurement 585,000.00 Water Reticulation Remesurement 45,000.00 21. Electrical Works (Pasar, Dewan, Kolej & Remesurement 415,000.00 Tadika) 22. Additional Dewan & Pasar-M&E works Remesurement 150,000.00 23. Prime Cost ( STP, Meru Tanda, Landscape Client’s request 100,000.00 Works, Playground Equipment) 24. R.C concrete sump Error in BQ 48,528.00 25. Hose Reel Tank & Pump House at Tadika Error in BQ 65,000.00 26. Additional for Air-condition (Kolej) Error in BQ 100,000.00 27. Main Switch Board (MSB) and Cable Error in BQ 300,000.00 28. Slope Trimming & Hydro seeding Works Error in BQ 50,000.00 29. Additional for 3 phase at Rumah Kedai Error in BQ 20,000.00 30. Paint Road Kerb using emulsion paint type Error in BQ 50,000.00 weather. 31. Additional Tingkap pintu, Frosted glass Error in BQ 20,000.00 32. Water proofing (banglow & building) Error in BQ 70,000.00 33. Changes Jubin at Car porch Bungalow Error in BQ 80,000.00 34. House 35. Railing Error in BQ 200,000.00 Total Net total 15,820,340.00 60 6.5 Result and Analysis a. The result of the types of variation and the factors that influence to the variation From the three case studies above, the analysis and the result of the types of variations were tabulated in the Table 6.4. While the factors that influence the variation can be shown in the 6.5. Based on the Table 6.5 the percentage of the factors that influence the variation have been summaries in the Figure 6.1 Table 6.4 : Types of variations Item 1. 2. 3. Types of variation Example According to identity of the Client, consultant, authority initiator and contractor etc. According to nature of Addition, omission and variation combination of both. The consequence or effect of Financial consideration or time variation implication (adjustment in the contract sum) 61 Table 6.5 : Factors that influence to variations Item Factors influence the No. of variations variations Case Case Case Study 1 Study 2 Study 3 Total 1 Client’s request 7 1 5 13 2 Change in design 3 5 3 11 3 Errors in Bills of 10 16 14 40 15 5 4 24 Quantities 4 Change due to Local Authority requirement 5 S.O’s instruction - 1 - 1 6 Remeasurement 5 18 8 31 7 Suit site condition 4 1 1 6 5% 25% 10% Client’s request 9% Change in design Errors in Bills of Quantities 1% 19% 32% Change due to Local Authority requirement S.O’s instruction Remeasurement Suit site condition Figure 6.1 : Percentage factors that influence to variations 62 b. The result of the problems that influence and the implication to the variation From the three case studies above, many problems that influence to variation works. The variation works also give an implication to the construction itself. The result of the problem that influence to the variation was identified in two categories which during planning stage and construction stage as shown in Table 6.6. Table 6.6 : Problem that influence to variations List of problem that influence to variation Item 1. Planning Stage Construction Stage No feasibilities study of the No survey work project 2. No proper project brief No proper soil investigation 3. Time constraint for preparing Misunderstanding in communication design and contract between project team documentation 4. Lack of checking on detailing Unexpected condition during design and drawing construction such as climate changes such as heavy rain and lightening can cause damage to the site of construction. 5. Lack of checking on quality Unforeseen condition such as found tender documentation rock under ground level, high water table and fossil 63 The major implication was identified as cost overrun as shown in Table 6.7 and the percentage that summarized the cost overrun shows in Figure 6.2. While the delays of the construction work was identified as shown in Table 6.8. The percentage of implication to the variation was shown in the Figure 6.3 which the result shows the case study 1 was delay more than 51% compared to two case studies above. Table 6.7 : The implication of variation – Cost Overrun Bil Case Implication of variations Study Cost Overrun Original Final Variation Percent Contract Contract order (%) of Amount Amount total variation 1 Case 32,747,987.00 49,369,205.60 16,621,218.60 51% 45,000,000.00 57,983,300.00 12,983,300.00 42% 38,000,000.00 53,820,340.00 15,820,340.00 29% 115,747,987.00 161,172,845.60 45,424,858.60 Study 1 2 Case Study 2 3 Case Study 3 Total 64 42% 51% Case study 1 Case study 2 Case study 3 29% Figure 6.2 : Percentage implication to variation – Cost Overrun Table 6.8 : The implication of variation – Delay Bil 1 Case Implication of variations Study Delay Case Original Final Delay Percent Contract Contract (days) (%) of Period Period 504 700 196 39% 504 1,008 504 100% 504 952 448 89% 1,512 2660 1,148 total delay Study 1 2 Case Study 2 3 Case Study 3 Total 65 39% 89% Case Study 1 Case Study 2 Case Study 3 100% Figure 6.3 :The implication of variation – Delay c. The result of the strategy action that can be taken to minimize variation The last section of the case study is to identify the strategy action that can be taken to minimize or control the variation work. The result can be tabulated in table 6.9 as shown below. 66 Table 6.9 : Strategy action can be taken to minimise or control variation Item Strategy action can be taken to minimise or control variation Planning Stage 1. Construction Stage Proper feasibilities study of the Proper survey work project 2. Clear and thorough project Proper soil investigation brief 3. Appropriate use of all day check at site procurement strategy 4. More thorough detailing of fully investigate. design. 5. 6.6 Quality contract comply with all authority documentation requirement Finding s and Discussion This section discussed the findings of this study. The results of the study are analysed and discussed in the following sequence to answer the objectives mentioned in Chapter 1. The analysis sequence is organized and presented the data in some meaningful and logical order. After the data have been organized and presented into description manner, it is then analyses them in order to draw inference about the data obtained. The discussion are included the factor that influence the variation, the problems that can cause the problem and then followed by the implication of variation work. Finally, discuss on the strategy action that can be taken to minimize or control variation work. Discussion on the finding will be based on the case study and interview responding to the objectives. 67 a. First Objective : To identify the types of variation and the factor that influences the variation. This section will discuss the finding based on the results obtained from the interview and the case study in which the types of variation and the factors of variation were identified. Table 6.4 shows the result types of variation and the factors that influence this. Table 6.4 : Types of variation Item 1. Types of variation Example The identity of the initiator client, consultant, authority and contractor 2. The nature of variation Nature of the work, changes in the condition of contract and included omission and addition and combination of both 3. The consequence or effect of Financial consideration or time variation implication (adjustment in the contract sum) From the Table 6.4, it can be concluded that, there are three types of variation that can be categorized by the identity of initiator which can be change to one another such as client or employer, consultant such as architect or engineer, the authority requirement and also the contractor. The nature of variation such as the nature of work such as site condition or weather, any changes in the condition of contract and the variation by the omission or addition work during construction. The third type of variation shows that the financial consequence or effect of variation such as financial consideration or time implication such as adjustment in the contract sum during construction in progress. 68 Table 6.10 : The Factors that influence the variations(%) Item Factors influence the variations (%) 1 Client’s request 10 2 Change in design 9 3 Errors in Bills of Quantities 32 4 Change due to Local Authority 19 requirement 5 S.O’s instruction 1 6 Remeasurement 25 7 Suit site condition 5 From the Table 6.10, it can be concluded that, the major factor that influence the variation work is comes from the Error in Bill of Quantities. From the table 6.10 above, it shows that 32% of the variation works comes from the Error in Bill of Quantities. Almost every project has a variation from Error in Bill of Quantities. Besides that, the re-measurements of the work also contribute to the variation of works. From the Table 6.10 , it can see that the re-measurement contribute 25% and follow by Local Authority’s requirement which from the case studies above, it shows that the Local authority contribute 19% to variation works. It is important to follow the regulation from the Local Authority because if the requirement not properly followed, it may cause the variation works. From example from the case study above, variation works arise where the thick of the crusher-run of road used in the project not according to the specification from the JKR. Therefore the changes have to follow as the authority requirement. Beside that, the client request also contribute to the variation works which from the Table 6.10 shows 10%, and followed by the variation works which is 69 changes in design which is 9%, suit the site condition is 5%, and also from the case studies above, it shows that there is only 1% of S.O’s instruction that contribute to the variation works. b. Second Objective : To identify the problems and the implication to the variation of the construction starts from planning until construction stage. From the factor above, the problem that influence of variation has been identified which can be divided into two stages. The first stage was during planning stage and the second was during construction stage. The major problem that influences variation during planning stage and construction stage were identified as shown in table 6.5. Uncorrected planning during early stage of the project implementation will give implication to the construction especially in the variation work. No proper feasibility studies carried out during early stage of the projects. This problem occur when the client insist the project will be completed in certain dates due to sometimes political issues. This will influence to the variation. Therefore it is important that the feasibility studies of the project should be done in proper manner to minimize or control the variation to the construction. Besides that, no proper project brief can influence to the variation, followed by the time constraint for preparing design and contract document which can cause mistake and error in the drawing and documentation. The lacking of checking on detail design and drawing which also contribute to the variation and finally, the lacking of checking on the quality of tender document also can influence to the variation. 70 Table 6.6 : Problem that influence to variations List of problem that can cause of variation Item 1. Planning Stage Construction Stage No feasibilities study of the No survey work project 2. No proper project brief No proper soil investigation 3. Time constraint for preparing Misunderstanding in design and contract communication between project documentation team Lack of checking on detailing Unexpected condition during design and drawing construction such as climate 4. changes such as heavy rain and lightening can cause damage to the site of construction. 5. Lack of checking on quality Unforeseen condition such as tender documentation found rock under ground level, high water table and fossil While the implication of variation from the three case studies above, it can be seen that the variation works give an implication to the construction itself. The obvious implication of the variations is show in the Table 6.11 which cost overruns that carried by the contractor should be paid as extra work or variation. 71 Table 6.11 : Cost Overrun for Case Study 1 ITEM DESCRIPTION OMISSION 1. Original contract Amount 2. Net Addition ADDITION 32,747,987.00 16,6218.60 16,6218.00 Final Contract Amount 49,369,205.60 From the case study 1, it can be concluded that the total net of cost for variation works is RM 16,621,218.00 to the contract sum. This means that the contract sum must be added for amount of RM16,621,218.00 which increase 51% form the original contract amount. The final contract amount is RM49,369,205.60. The summary of this result show in the Table 6.11 above. Table 6.12 : Cost Overrun for Case Study 2 ITEM DESCRIPTION OMISSION 1. Original contract Amount 2. Net Addition ADDITION 45,000,000.00 12,983,300.00 12,983,300.00 Final Contract Amount 57,983,300.00 From the case study 2, have same implication which is cost overrun because of the variation works. The original contract amount increase 42% from RM45,000,000.00 to RM 57,983,300.00 which the total net of variation works are RM 12,983,300.00. The summary of this result shows in the Table 6.12. 72 Table 6.13 : Cost Overrun for Case Study 3 ITEM DESCRIPTION OMISSION 1. Original contract Amount 2. Net Addition ADDITION 38,000,000.00 15,820,340.00 15,820,340.00 Final Contract Amount 53,820,340.00 From the case study 3, it can be concluded that the variation works involved only in net additional works which cost of RM 15,820,340.00 to be added to the original contract amount. The original contract amount increase 29% from RM 38,000,000.00 to RM 53,820,340.00. The summary of this result shows in the Table 6.13. The other implication to the variation is delay of the project. From three case studies show that almost all the project was delay due to the variation order. Table 6.14 shown delay in the construction period due to the variation works. Table 6.14 : Delay Bil Case Study Implication of variations Delay Original Final Delay (%) of Contract Contract (days) total delay Period Period 1 Case Study 1 504 700 196 39% 2 Case Study 2 504 1,008 504 100% 3 Case Study 3 504 952 448 89% 73 From the Table 6.14 above, shows that the case study 2 was delay 100% of the original contract period which contribute about 1,008 days compare of cased study 3 which contribute 89% of delay about 952 days, then followed by the case study 1 which contribute 39% of delay about 700 days. This result shows that the case study 2 was delay the most in the construction work compared the other two case studies. c. Third Objective : To identify the strategy action that can be taken to minimize or control the variation. This section discussed the finding based on the result obtained from the cased study and interview to identify the strategy action that can be taken to minimize or control the variation works. The strategy action can be taken as early in planning stage and also construction stage there are identified as: Comprehensive site investigation; based on the case study above, there are a numbers of the variation occur caused due to suit the site condition. It is clear that before the construction start, it need a comprehensive site investigation. For example of site investigation is topographical survey and geotechnical investigation. Although the cost incurred in the site investigation is usually a small fraction of the total project, but the clients or related parties do not appreciate the importance of the survey and no investigation is carried out, the construction may turns out to be not good, if survey is properly done, the variation works might be reduced and cost is under control. Quality contract documentation; quality in contract documentation is important because it will influence the eventual outcome of the contract. The document must be complete in order to avoid problems in future. It must clearly define the task and works that need to be done by the contractor especially in bills of quantities. From the case studies above, the errors in bills of quantities contribute to the variation works. Poorly prepared documents will result in uncertainty future. 74 Besides that, if there is variation works, the contractor must ensure that he has clearly defined procedures for identifying variations and that he must conforms to full requirements of the contract. Hence the contract must be clearly presented. The implication if the contract document prepared is incomplete, it will be the causes of cost overruns. More thorough detailing in design; detail design can reduce variation in future. The design developed in depth at the pre-contract stage with the cooperation must be developed in order to avoid the claims and dispute. Any changes later will result in abortive works and almost certainly in additional cost. From the case studies above, changes in design will result the variation works. In order to control the variations, the design team must properly design with take all the consideration including site condition and requirement by the Local Authority into the design. Compliance with local authority’s requirement; Local authority involved in the construction such as Fire and Resque Department (BOMBA), Telecom, Tenaga Nasional Berhad (TNB), Jabatan Bekalan Air (JBA) and others. All these authority have their own regulation that must be followed during the construction. Most of the variation works are caused by the changes in Local Authority’s requirement. For example, in the case studies above, there are twenty four (24) variation works are caused by the Local Authority’s requirement. If the works are properly done and followed the entire requirement stated by the Local authority it will reduce the numbers of variation of works. 75 6.7 Summary The final result of the analysis was listed. According to the result analysis it shows that there are three types of variation and the most factor that influence the variation is Error in Bill of Quantities. And there are five problems that can cause variation during planning stage and construction stage. Therefore the implication of variation it shows that the cost overruns of the project and the delay in the construction period were the most implication of variation. Lastly, the strategy action that can be taken to minimize or control the variation is focusing during planning stage and also construction stage. CHAPTER 7 CONCLUSION AND RECOMMENDATION 7.1 Introduction This chapter concludes the study by listing and summarized the result of the analysis. Based on the literature reviews, interview and the case study and result analysis, the three main objectives of this project report have been achieved. 7.2 Conclusions As a conclusion based on the study on variations control affecting the construction works, the study has identified and fulfill the three objectives that set out in Chapter 1 of this report. 77 First Objective : To identify the types of variation and the factor that influence the variation There are three types of variation that can be categorized by the identity of initiator which can be change to one another such as client or employer, consultant such as architect or engineer, by the authority requirement and also the contractor. The by the nature of variation such as the nature of work such as site condition or weather, any changes in the condition of contract and the variation by the omission or addition work during construction. The third type of variation shows that the financial consequence or effect of variation such as financial consideration or time implication such as adjustment in the contract sum during construction in progress. Based on the case studies in Chapter 6 on this project report, the factor that influence the variation has been identified which are as follows: 1. Client’s request; 2. Change in design; 3. Error in Bill of Quantity; 4. Change in Local Authority’s requirement; 5. S.O’s instruction; 6. Reameasurement; and 7. Suite site condition. 78 Second Objective : To identify the problems and the implication to variation of the construction starts from planning until construction stage The problem that was identified was during planning stage. It can be listed below which are: 1. No feasibility studies of the project; 2. No proper project brief; 3. The time constraint for preparing design and contract document; 4. Lack of checking on detail design and drawing; and 5. lack of checking on the quality of tender document While the problems during construction stage that influence to the variation was identified as: 1. No survey work 2. No proper soil investigation 3. Misunderstanding in communication between project team 4. Unexpected condition during construction 5. Unforeseen condition such as found rock under ground level, high water table and fossil The obvious implication of the variation is cost overrun. The works carried out by the contractor should be paid for an extra works or variation. This will result of cost overrun. Based on the case studies, all of the three project has increment on cost more that 30% of the original contract amount. The cost includes the additional expenses, which are transportation expenses, cost of variation works preparation, other cancellation expenses, financial charges and also cost of site overheads. 79 The common implication when there is variations work is delay in completion of the project, the case studies in Chapter 6, it shows that, all the three project complete the project due to variations. It can be concluded that, the variation also can cause or creates delay; it can be complete on time if it is managed in a proper manner, unless it is issued to critical tasks. Third Objective : To identify the strategy action that can be taken to minimize or control the variation. Based on the analysis and result above, it can be concluded that,the strategy action that can be taken to minimize or control variations during planning stage. This can be listed as below. 1. Clear project brief 2. Detailing in design 3. Adequate time in preparation of documentation 4. Management in procurement strategy 5. Provision of complete documentation Project brief is important at the initial stage because it represents the client’s needs and clear project brief will avoid the poor contract performance in future. It is also to minimize the changes arise in the future. Detail design is important to control and reduce variation because it is contain a full design of every part and component of the building. The design will developed 80 in depth at the pre-contract stage in order to avoid the claims and dispute later and any changes later will result changes of works and additional cost. Adequate time is important in measurement of the works and preparation of documentation. If there is adequate time in preparation of documentation, the total number of variations could be reduced. The selection of the management procurement are also important in order to ensure that the construction is running smooth and less variation occur during construction. Based on the analysis and result above, it can be concluded that strategy action also can be taken in order to minimize variation was during construction stage. The strategy action that cab be taken can be listed below. 1. Contractor efficiency’s 2. Keeping systematic site record 3. All day check before issue to contractor 4. Detail and adequate investigation 5. Comply with all requirements by statutory authority Variation works can be controlled by having a daily check and systematic site record on the works. The works carried out by the contractor must be check to make sure it is according to specification. If there is a systematic site record, it is indirectly can control the variation works and it depends on the technique of keeping the record and the management on the site. All day check before issue to the contractor is a checking made before the S.O issue the any instruction to the contractor consist of variation works. This is including checking for the originality of the works and the contractor’s scope of works either according to the contract or not in order to avoid the variation. 81 The detail in investigation is important because most of the variation caused by the work not suit to site condition. If the investigation is not adequate, it will result in additional cost and also involve a variation works in the future. So to control variation works, the investigations must be in detail and adequate. Complete documentation is important to make sure all the information in the document is complete in order to avoid problems in future. It must clearly define the task and works that need to be done by the contractor especially in bills of quantities. Poorly preparation of documents will result in uncertainty future such as cost overruns due to the variation works. Based on the case studies on Chapter 6, most of the variation works arise caused by the changes in Local Authority’s requirement. In order to reduce the variation works, the S.O must make sure that the design and specification of the works according to the requirement stated by the Local Authority. Besides that, the contractor should also carry out the work according to the specification given. If the works are properly done and followed all the requirement stated by the Local authority it will reduce the numbers of variation of works 82 7.3 Recommendation The recommendation has been made in controlling the variation works so as to achieve satisfaction to parties involved in construction project. Base on the previous chapter, the majority of the variation order is due to the Error in Bill of Quantity. It is important that during planning stage the strategy action could be taken is properly checking tender document in order to reduce mistake or error during preparing the documentation for the project. Therefore the strategy action that can be taken in order to minimize the variation were already discussed above could be recommended for general procedure that may need to be resolved in a typical variation process in actual practice. 83 REFERENCES Hibberd, Peter R. (1986), “Variations in Construction Contracts,” Collins. Wainwright, W Howard, (1970), “Variation and Final Account Procedure,” Hutchinson Technical Education. Sundra Rajoo, (1999), “The Malaysian Standard Form Of Building Contract”, The PAM 1998 Form (2nd Edition), Malayan Law Journal Sdn Bhd. James Frank, (1984), “ Building Sub-Contact Management”, Construction Press. Henry Naylor, “Construction Project Management”, Delmar Publisher. Ir. Harbans Singh K.S.,(2002), “Engineering And Construction Contract Management, Post-Commencement Practice”, Lexisnexis Business Solutions, J.W. Ramus, (1989), “Contract Practice for Quantity Surveyors”. Vincent Powell-Smith, (1989), “Some Building Contract Problems”, London. Chow Kok Fong, (1988), “An Outline of the Law & Practice of Construction Contract Claims”, Longman, Singapore. H. Seeley, Ivor (1982), “ Quantity Surveying Practice”, Macmillan. 84 Nor Ainah Abdullah, (2001) , “Pengenalan Kepada Kontrak Binaan”, UPENA Wan Maimunah Bt. Wan Abdullah, (1993), “Variation Works in a Contract”, (1st Quarter) The Malaysian Surveyor, Institutions of Surveyors Malaysia. Entrusty Group, (2002), “What Constitutes A Variation And How Does One Value Variations”, (2nd Quarter), Journal Of Master Builders. Hj. Hashim Sikan, (2003), “Variation Orders In Construction Contract”, The Malaysian Surveyor (3rd Quarter, Vol 38.3) Dennis F. Turner (1979), “Quantity Surveying Practice and Administration”,(2nd Edition)