RED RIVER DIVERSION FARGO – MOORHEAD METRO FLOOD RISK MANAGEMENT PROJECT, FEASIBILITY STUDY, PHASE 4 APPENDIX G – COST ESTIMATES EXHIBIT E – PRELIMINARY EARTHWORK ANALYSIS Report for the US Army Corps of Engineers, and the cities of Fargo, ND & Moorhead, MN By: Barr Engineering Co. FINAL – February 28, 2011 TABLE OF CONTENTS G-E1.0 PRELIMINARY EARTHWORK ANALYSIS ................................................... 2 ATTACHMENTS G-E1.0 Preliminary Earthwork Analysis Fargo-Moorhead Metro Feasibility February 28, 2011 Appendix G-EX-E-1 Cost Estimates-Exhibit E APPENDIX G COST ESTIMATES EXHIBIT E – PRELIMINARY EARTHWORK ANALYSIS G-E1.0 PRELIMINARY EARTHWORK ANALYSIS Attachment G-E1.0 of this Exhibit E presents the preliminary earthwork analysis used to develop crews and productivities in the MII cost estimates, including the following information, computations and assumptions: • Manitoba Floodway Expansion Images – Excavation & Haul • Work Analysis – City of Fargo Images – Borrow Pits • Work Analysis – Earthwork Crews • Work Analysis – Earthwork – Topsoil Stripping and Stockpiling • Work Analysis – Earthwork – Type 1 Non-Saturated Non-Brenna • Work Analysis – Earthwork – Type 2 Saturated Non-Brenna • Work Analysis – Earthwork – Type 3 Oxidized Brenna • Work Analysis – Earthwork – Type 4 Brenna Fargo-Moorhead Metro Feasibility February 28, 2011 Appendix G-EX-E-2 Cost Estimates-Exhibit E Exhibit_G-E1_0_Preliminary_Earthwork_Analysis Page 1 Job Number: 34-091-004.300.500 Barr Engineering Company Project: Subject: Task: Status: Fargo-Moorhead Metro Flood Risk Management Project Phase 3 Cost Estimate Work Analysis - Manitoba Floodway Expansion Images - Excavation & Haul draft Computed: Checked: Sheet: MRM MW1 1 Date Date of 7/26/2010 7/26/2010 10 Images courtesy of Manitoba Floodway Authority - Floodway Expansion 2005-2007 http://www.floodwayauthority.mb.ca/construction_status.html# Shallow material excavated with scraper fleet Working on stronger material to excavate weaker underlying material Articulated Dump Truck -CAT D400E, 28.6 cy heaped max capacity P:\Mpls\34 ND\09\34091004 Fargo Moorhead Metropolitan Feas. Study\WorkFiles\Project Data\Phase3\700_Cost_Est\Report_Exhibits\Exhibit_G-E1_0_Preliminary_Earthwork_Analysis Page 1 Exhibit_G-E1_0_Preliminary_Earthwork_Analysis Page 1 Job Number: 34-091-004.300.500 Barr Engineering Company Project: Fargo-Moorhead Metro Flood Risk Management Project Subject: Phase 3 Cost Estimate Task: Work Analysis - City of Fargo Images Status: draft Images courtesy of Nathan Boerboom of City of Fargo 2010 borrow pit (approx. 20 feet depth) for temporary levee construction. Computed: Checked: Sheet: MRM MW1 2 Date Date of 7/26/2010 7/26/2010 10 P:\Mpls\34 ND\09\34091004 Fargo Moorhead Metropolitan Feas. Study\WorkFiles\Project Data\Phase3\700_Cost_Est\Report_Exhibits\Exhibit_G-E1_0_Preliminary_Earthwork_Analysis Page 1 Exhibit_G-E1_0_Preliminary_Earthwork_Analysis.xls Page 1 Job Number: 34-091-004.300.500 Barr Engineering Company Project: Subject: Task: Status: Fargo-Moorhead Metro Flood Risk Management Project Phase 4 Cost Estimate Work Analysis - Earthwork Crews draft Computed: Checked: Sheet: MRM/ATS/PKN MW1 3 Date Date of 2/28/2011 2/28/2011 10 Exhibit G-E1.0 Preliminary Earthwork Analysis Note 1: For construction, equipment combinatations other than those shown could be configured. Information shown below is for cost estimate purposes only. Note 3: Instead of D9 dozers, D6 dozers may be preferable because of maneuverability. Assuming D9 dozers is conservative. Note 4: For Types 3 and 4, larger excavators or shovels could be feasible. Note 5: Crews and productivities based on conversations with contractors, index values in the 2008 equipment library, RS Means cost data, equipment manufacturer's data, and unit price data Constraints: (USACE email 6-8-2010) 1.15 1.00 1.08 0.85 Excavation to Haul swell LCY/BCY Excavation to Ordinary Compacted Spoil ECY/BCY Excavation to Top Dressed Spoil Pile ECY/BCY Excavation to Levee/Structural Fill ECY/BCY BCY = bank cubic yards in-situ LCY = loose cubic yards ECY = embankment cubic yards Table: Crew Summary SCRAPER, TANDEM POWERED, STANDARD LOADING, 20 CY, 24 TON, 9.1' CUT WIDTH, 4X4, PUSHPULL; MODEL 627-G PP (PUSH-PULL) HYDRAULIC EXCAVATOR, CRAWLER, 190,500 LB, 6.00 CY BUCKET, 27.83' MAX DIGGING DEPTH ; Model 385BL CAT TRUCK OFFHIGHWAY, ARTICULATED FRAME, 29 CY, 40 TON, 6X6 REAR DUMP; MODEL 400D TRUCK OFFHIGHWAY, ARTICULATED FRAME, 18 CY, 25 TON, 6X6 REAR DUMP; MODEL 250D TRACTOR, CRAWLER (DOZER), 240 HP, LOW GROUND TRACTOR, PRESSURE, CRAWLER (DOZER), W/7.70 CY 341-440 HP, STRAIGHT BLADE POWERSHIFT, W/ (ADD UNIVERSAL BLADE; ATTACHMENTS); MODEL D-9R MODEL D-7RIILGP LOADER/BACKH OE, WHEEL, 1.30 CY FRONT END BUCKET, 24" DIP, 7.1 CF, 21.5' DIGGING DEPTH, 4X4; MODEL 217S (4WS) GRADER, MOTOR, ARTICULATED, 6X4, 12' BLADE W/17 TEETH SCARIFIERS TRACTOR, AGRICULTURAL, CRAWLER RUBBER TRACK 267 HP; MODEL CH 65E TRACTOR ATTACHMENTS, POWER HARROW, 160" WIDE ROTERRA ROTARY HOE, MODEL 400-35 ROLLER, VIBRATORY, TOWED, SINGLE DRUM, SHEEPSFOOT, 25.5 TON, 72" WIDE (ADD 180 HP TOWING UNIT) LOADER, FRONT END, WHEEL, ARTICULATED, 2.75 CY (2.1 M3) Laborers (semiBUCKET, 4X4 skilled) Equipment Operators Medium Strip and Stockpile Topsoil - Channel 1650 BCY/HR 750 BCY/HR Topsoil - Strip Topsoil - Stockpile 5 1 2 1 1 6 2 8 Strip and Stockpile Topsoil - Spoil Berm 1500 BCY/HR Topsoil - Strip and Stockpile 5 2 1 1 1 0.5 0.5 1 7 0.5 1 4.5 Excavation and Embankment - Channel - Type 1 Non-Saturated Non-Brenna 1400 BCY/HR 1400 BCY/HR Earthwork - Non-Saturated Non-Brenna Excavate and Haul Earthwork - Non-Saturated Non-Brenna Spoil 5 4 Earthwork - Non-Saturated Non-Brenna Semicompact, Manage Moisture Content Earthwork - Non-Saturated Non-Brenna Levee Embankment 120 BCY/HR (LPP) Excavation and Embankment - Channel - Type 2 Saturated Non-Brenna 1000 BCY/HR 1050 BCY/HR Earthwork - Saturated Non-Brenna Excavate and Haul 1400 BCY/HR Earthwork - Saturated Non-Brenna - Spoil 2 5 1 0.5 4 Earthwork - Saturated Non-Brenna Semicompact, Manage Moisture Content Earthwork - Saturated Non-Brenna - Levee Embankment 120 BCY/HR (LPP) Excavation and Embankment - Channel - Type 3 Oxidized Brenna Earthwork - Oxidized Brenna - Excavate 690 BCY/HR 1000 BCY/HR 690 BCY/HR 1400 BCY/HR Earthwork - Oxidized Brenna - Haul Earthwork - Oxidized Brenna - Spoil 1000 BCY/HR Earthwork - Oxidized Brenna - Semicompact and Manage Moisture Content 2 1 1 2 1 1 1 3 1 3 1 2 1 6 0.5 1 7 0.5 1 4.5 3 1 2 1 1 1 1 3 1 2 1 6 1 3 1 1 4.5 4.5 2 3.5 1 4 0.5 1 2 1 1 1 3 1 1 1 3.5 4.1 4.5 Excavation and Embankment - Channel - Type 4 Brenna 500 BCY/HR 500 BCY/HR 1400 BCY/HR 1000 BCY/HR 1 Earthwork - Brenna - Excavate Earthwork - Brenna - Haul Earthwork - Brenna - Spoil Earthwork - Brenna - Semicompact and Manage Moisture Content 2.5 3.1 1 4 0.5 1 2 1 1 1 3 1 1 Excavation and Embankment - Channel - varies Earthwork - Haul 1650 BCY/HR Topsoil - Install from Stockpile 1500 BCY/HR Topsoil - Install from Stockpile 1 Topsoil Placement - Channel 5 3 1 1 1 2 10 1 1 1 2 9 Topsoil Placement - Berms 5 2 P:\Mpls\34 ND\09\34091004 Fargo Moorhead Metropolitan Feas. Study\WorkFiles\_Phase4\100 Cost Estimates\Work Analysis\Exhibit_G-E1_0_Preliminary_Earthwork_Analysis.xls Page 1 Exhibit_G-E1_0_Preliminary_Earthwork_Analysis Page 1 Job Number: 34-091-004.300.500 Barr Engineering Company Project: Subject: Task: Status: Fargo-Moorhead Metro Flood Risk Management Project Phase 3 Cost Estimate Work Analysis - Earthwork - Topsoil Stripping and Stockpiling draft MRM MW1 4 Date Date of 7/26/2010 7/26/2010 10 Note: Information shown below is for cost estimate purposes only. Reference: CAT Performance Handbook Edition 40 Wheel Tractor-Scrapers Computed: Checked: Sheet: p.8-4 Constraints: 1.25 1,800 Step 1 - Equipment Model Characteristics 627G 627G-PP 22 15.7 86,957 139,757 0.4 0.9 0.6 23 13 Material - Existing Topsoil Excavation to Haul swell LCY/BCY, CERM 11th Ed. LF wide corridor to strip, assume stockpiling at edges. level 0% grade CAT Wheel Tractor-Scraper Model w/ D8 or D9 push-load CAT Wheel Tractor-Scraper Model, Tandem Powered Push-Pull CY Scraper Capacity (heaped) CY Scraper Capacity (struck) LBS Operating Weight (empty) p. 8-30 LBS Operating Weight (full) p. 8-30 MIN. Load Time for push-load w/ dozer MIN. Load Time for scaper push-pull MIN. Maneuver and Spread or Maneuver and Dump MPH max at 5%, full load p. 8-18 MPH max at 10%, full load p. 8-18 Step 2 - Travel Charts - Wheel Tractor-Scrapers 0.9 750 4.0 0.0 4.0 0.6 750 4.0 0.0 4.0 0.5 0.6 2.6 Step 3 Calculate Effective Cycles per Hour Cycle time (Max from Step 2) 2.60 60 Minute hour Cycle time Operator Skill/Efficiency Machine Availability Gen Operational Efficiency Effective Cycles per Hour 23 MIN. Load Time for scaper push-pull LF Distance One Way % Typ. Rolling Resistance, rutted dirt roadway 2" tire penetration, no water, little maintenance, p. 27-1 % Grade existing grade (assumed) % Total Resistance MIN. on-way travel time (loaded), p. 8-32 LF Distance One Way % Typ. Rolling Resistance, rutted dirt roadway 2" tire penetration, no water, little maintenance, p. 27-1 % Grade existing grade (assumed) % Total Resistance MIN. on-way travel time (empty), p. 8-33 MIN. Maneuver and Spread or Maneuver and Dump MIN. TOTAL travel time per cycle (unfactored) Min 0.95 0.95 0.95 20 cycles/hour (95%) (95%) (55 min/hr) (cycles/hr) 0.95 Assume loading as % of heaped 2:1 capacity (1) downtime of 30min every 10hrs (1) downtime of 30min every 10hrs (1) equivalent downtime of 30min every 10hrs (1) total equivalent downtime of 1hr30min every 10hrs Step 4 Calculate Production Crew 20.9 413.5 330.8 LCY volume per load (assumed) LCY per hour productivity (single unit) BCY per hour productivity (single unit) 5 1 1654 Scrapers (push-pull) D9 Dozer (maintenance of haul areas, small amount of windrowing) BCY per hour total productivity (crew) Typical diversion corridor shown below (finish grade contours shown) P:\Mpls\34 ND\09\34091004 Fargo Moorhead Metropolitan Feas. Study\WorkFiles\Project Data\Phase3\700_Cost_Est\Report_Exhibits\Exhibit_G-E1_0_Preliminary_Earthwork_Analysis Page 1 Exhibit_G-E1_0_Preliminary_Earthwork_Analysis Page 1 Job Number: 34-091-004.300.500 Barr Engineering Company Project: Subject: Task: Status: Fargo-Moorhead Metro Flood Risk Management Project Phase 3 Cost Estimate Work Analysis - Earthwork - Type 1 Non-Saturated Non-Brenna draft MRM MW1 5 Date Date of 7/26/2010 7/26/2010 10 Note: Information shown below is for cost estimate purposes only. Reference: CAT Performance Handbook Edition 40 Wheel Tractor-Scrapers Computed: Checked: Sheet: p.8-4 Constraints: Material Type 1 Non-Saturated Non-Brenna Assumed Excavation to Haul swell LCY/BCY - USACE email 6-8-2010 Calculate Load Factor (L) Estimated California Bearing Ratio (CBR) 1.15 0.87 5 to 6 Equipment Model Characteristics 627G 627G-PP 22 15.7 86,957 139,757 0.4 0.9 0.6 23 13 CAT Wheel Tractor-Scraper Model w/ D8 or D9 push-load CAT Wheel Tractor-Scraper Model, Tandem Powered Push-Pull CY Scraper Capacity (heaped) CY Scraper Capacity (struck) LBS Operating Weight (empty) p. 8-30 LBS Operating Weight (full) p. 8-30 MIN. Load Time for push-load w/ dozer MIN. Load Time for scaper push-pull MIN. Maneuver and Spread or Maneuver and Dump MPH max at 5%, full load p. 8-18 MPH max at 10%, full load p. 8-18 Step 2 - Travel Charts - Wheel Tractor-Scrapers 0.9 1200 5.0 5.0 10.0 1.2 1200 5.0 0.0 5.0 0.5 0.6 3.2 MIN. Load Time for scaper push-pull LF Distance One Way % Typ. Rolling Resistance, rutted dirt roadway 2" tire penetration, no water, little maintenance, p. 27-1 % Grade (assumed max., likely conservative given shallow depths of Type 1 material) % Total Resistance MIN. on-way travel time (loaded), p. 8-32 LF Distance One Way % Typ. Rolling Resistance, rutted dirt roadway 2" tire penetration, no water, little maintenance, p. 27-1 % Grade % Total Resistance MIN. on-way travel time (empty), p. 8-33 MIN. Maneuver and Spread or Maneuver and Dump MIN. TOTAL travel time per cycle (unfactored) Step 3 Calculate Effective Cycles per Hour Cycle time (Max from Step 2) 3.20 Min 60 Minute hour Cycle time 19 Operator Skill/Efficiency Machine Availability Gen Operational Efficiency Effective Cycles per Hour 0.95 0.95 0.92 16 cycles/hour (95%) (95%) (55 min/hr) (cycles/hr) (1) downtime of 30min every 10hrs (1) downtime of 30min every 10hrs (1) equivalent downtime of 50 min every 10hrs (1) total equivalent downtime of 1hr50min every 10hrs Step 4 Calculate Production 0.9 Crew Assume loading as % of heaped 2:1 capacity 19.8 308.2 268.0 LCY volume per load (assumed) LCY per hour productivity (single unit) BCY per hour productivity (single unit) 5 1 0.5 0.5 1340 Scrapers (push-pull) D9 Dozer (maintenance of haul areas, occasional push) Dozer (maintenance of haul areas, occasional push) Grader (maintenance of haul areas) BCY per hour total productivity (crew) Route shown below is conservative, higher productivity could be assumed for shorter routes Typical diversion corridor shown below (finish grade contours shown) P:\Mpls\34 ND\09\34091004 Fargo Moorhead Metropolitan Feas. Study\WorkFiles\Project Data\Phase3\700_Cost_Est\Report_Exhibits\Exhibit_G-E1_0_Preliminary_Earthwork_Analysis Page 1 Exhibit_G-E1_0_Preliminary_Earthwork_Analysis Page 1 Job Number: 34-091-004.300.500 Barr Engineering Company Project: Subject: Task: Status: Fargo-Moorhead Metro Flood Risk Management Project Phase 3 Cost Estimate Work Analysis - Earthwork - Type 2 Saturated Non-Brenna draft MRM MW1 6 Date Date of 7/26/2010 7/26/2010 10 Note: Information shown below is for cost estimate purposes only. Reference: CAT Performance Handbook Edition 40 Wheel Tractor-Scrapers Computed: Checked: Sheet: p.8-4 Constraints: Material Type 2 Saturated Non-Brenna Assumed Excavation to Haul swell LCY/BCY - USACE email 6-8-2010 Calculate Load Factor (L) Estimated California Bearing Ratio (CBR) Type 2 material estimated depth 20', scrapers assumed feasible to 10'-15' depths or lower. 1.15 0.87 5 to 6 Equipment Model Characteristics 627G 627G-PP 22 15.7 86,957 139,757 0.4 0.9 0.6 23 13 CAT Wheel Tractor-Scraper Model w/ D8 or D9 push-load CAT Wheel Tractor-Scraper Model, Tandem Powered Push-Pull CY Scraper Capacity (heaped) CY Scraper Capacity (struck) LBS Operating Weight (empty) p. 8-30 LBS Operating Weight (full) p. 8-30 MIN. Load Time for push-load w/ dozer MIN. Load Time for scaper push-pull MIN. Maneuver and Spread or Maneuver and Dump MPH max at 5%, full load p. 8-18 MPH max at 10%, full load p. 8-18 Step 2 - Travel Charts - Wheel Tractor-Scrapers 0.9 1200 saturated material 8.0 5.0 13.0 1.6 1200 saturated material 8.0 0.0 8.0 1.0 0.6 4.1 MIN. Load Time for scaper push-pull LF Distance One Way % Typ. Rolling Resistance, rutted dirt roadway, soft under travel, 4" tire penetration, no maintenance, p. 27-1 % Grade (assumed max., likely conservative given shallow depths of Type 1 material) % Total Resistance MIN. on-way travel time (loaded), p. 8-32 LF Distance One Way % Typ. Rolling Resistance, rutted dirt roadway, soft under travel, 4" tire penetration, no maintenance, p. 27-1 % Grade % Total Resistance MIN. on-way travel time (empty), p. 8-33 MIN. Maneuver and Spread or Maneuver and Dump MIN. TOTAL travel time per cycle (unfactored) Step 3 Calculate Effective Cycles per Hour Cycle time (Max from Step 2) 4.10 Min 60 Minute hour Cycle time 15 Operator Skill/Efficiency Machine Availability Gen Operational Efficiency Effective Cycles per Hour 0.95 0.95 0.92 12 cycles/hour (95%) (95%) (55 min/hr) (cycles/hr) (1) downtime of 30min every 10hrs (1) downtime of 30min every 10hrs (1) equivalent downtime of 50 min every 10hrs (1) total equivalent downtime of 1hr50min every 10hrs Step 4 Calculate Production 0.9 Crew Assume loading as % of heaped 2:1 capacity 19.8 240.6 209.2 LCY volume per load (assumed) LCY per hour productivity (single unit) BCY per hour productivity (single unit) 5 1 1 0.25 1046 Scrapers (push-pull) D9 Dozer (maintenance of haul areas, occasional push) LGP Dozer (maintenance of haul areas) Grader (maintenance of haul areas) BCY per hour total productivity (crew) Route shown below is conservative, higher productivity could be assumed for shorter routes Typical diversion corridor shown below (finish grade contours shown) P:\Mpls\34 ND\09\34091004 Fargo Moorhead Metropolitan Feas. Study\WorkFiles\Project Data\Phase3\700_Cost_Est\Report_Exhibits\Exhibit_G-E1_0_Preliminary_Earthwork_Analysis Page 1 Exhibit_G-E1_0_Preliminary_Earthwork_Analysis Page 1 Job Number: 34-091-004.300.500 Barr Engineering Company Project: Subject: Task: Status: Fargo-Moorhead Metro Flood Risk Management Project Phase 3 Cost Estimate Work Analysis - Earthwork - Type 3 Oxidized Brenna draft Computed: Checked: Sheet: MRM MW1 7 Date Date of 7/26/2010 7/26/2010 10 Note: Information shown below is for cost estimate purposes only. Reference: CAT Performance Handbook Edition 40 Hydraulic Excavators Constraints: 1.15 2 to 3 Material Type 3 Oxidized Brenna Excavation to Haul swell LCY/BCY - USACE email 6-8-2010 California Bearing Ratio (CBR) - Saturated Non-Brenna Average Bucket Payload = (Heaped Bucket Capacity) x (Bucket Fill Factor) Bucket Fill Factor (% of heaped bucket capacity) Fill Factor Material Range low end high end Moist Loam or Sandy Clay 100-110% 100 110 Sand and Gravel 95-110% 95 110 Hard, Tough Clay 80-90% 80 90 Rock - Well Blasted 60-75% 60 75 Rock - Poorly Blasted 40-50% 40 50 p. 4-136 table Job Condition Description A Material types A B C Easy Digging (unpacked earth, sand, gravel, ditch cleaning etc.) Digging to less than 40% of machine's maximum depth capability. Swing angle less than 30°. Dump onto spoil pile or truck in excavation. No obstructions. Good operator. Medium digging (packed earth, tough dry clay, soil with less than 25% rock content). Depth to 50% of machine's maximum capability. Swing angle to 60°. Large dump target. Few obstructions Medium to hard digging (hard packed soil with up to 50% rock content). Depth to 70% of machine's maximum capability. Swing angle to 90°. Loading trucks with truck spotted close to excavator. Hard digging (shot rock or tough soil with up to 75% rock content). Depth to 90% of machine's maximum capability. Swing angle to 120°. Shored trench. Small dump target. Working over pipe crew Toughest digging (sandstone, caliche, shale, certain limestones, hard frost). Over 90% of machine's maximum depth capability. B C D E Swing over 120°. Loading bucket in man box. Dump into small target requiring maximum excavator reach. People and obstructions in the work area. Cycle Time Estimating Chart - per job condition CAT Machine Size Class Seconds per job condition M322D A Min Cycle Time (s) 10 A Max Cycle Time (s) 13 323D 324D 328D 329D 336D 345D 365C L 385C 10 11.5 NA 11.5 12.5 12 12 12.5 13 13 NA 14 15 15 15 15.5 B Min Cycle Time (s) 13 13 13 NA 14 15 15 15 15.5 B Max Cycle Time (s) 15.5 15.5 16 NA 16 18 18 20 21 C Min Cycle Time (s) 15.5 15.5 16 NA 16 18 18 22 21 C Max Cycle Time (s) 18.5 18.5 19 NA 19 21 20 26.5 27 D Min Cycle Time (s) 18.5 18.5 19 NA 19 21 20 26.5 27 D Max Cycle Time (s) 20 20 21 NA 22 23.5 23.5 31.5 32.5 E Min Cycle Time (s) 20 20 21 NA 22 23.5 23.5 31.5 32.5 E Max Cycle Time (s) 23 23 24 NA 26 26.5 29 34.5 42 Step 1 Material Fill Factor Hard, Tough Material Type Clay Range Low End High End 80-90% 80 90 p. 4-136 Step 2 Estimate Cycle Time Machine Class Size Job Condition B Min Cycle Time (s) B Max Cycle Time (s) 385C B 15.5 21 0.26 0.35 Min Min p. 4-188 Step 3 Calculate Effective Cycles per Hour Cycle time (Max from Step 2) 0.26 Min 60 Minute hour Cycle time 232 Operator Skill/Efficiency Machine Availability Gen Operational Efficiency Effective Cycles per Hour 0.95 0.95 0.95 199 p. 4-192 cycles/hour (95%) (95%) (57 min/hr) (cycles/hr) (1) downtime of 30min every 10hrs (1) downtime of 30min every 10hrs (1) equivalent downtime of 30min every 10hrs (1) total equivalent downtime of 1hr30min every 10hrs; (2) effective cycle bracketed by min/max cycle times Step 4 Calculate Required Bucket Capacity Nominal Bucket Size 5 cy Fill Factor 80 % Bucket Payload Volume= Nominal Bucket Size x Fill Factor 4 cy Bucket Payload Volume= Material Density / Loose= 2700 lb/cy Required Payload = Bucket Payload Volume x Material Density/Loose Required Payload = 10,800 lb Effective Cycles per Hour= 199 cycles/hr Step 5 Calculate Production Hourly Production Required= Required Payload x Effective Cycles per hour Hourly Production Required= 2,150,628 lbs/hr 1075 tons/hr 797 LCY/hr 693 BCY/hr Crew: 1 Hydraulic Excavator (crawler) 1 Dozer (crawler) to maintain load/unload area Reference Comparison: 2010 RS Means 31-23-16.43-5700 - Excavator, 4.5 CY bucket with truck loading, 80% fill factor, crew B-14A, daily output 2720 CY (340 CY/hr for 8 hours) $1.03/LCY or $1.18/BCY (no dozers) 2010 RS Means 31-23-16.43-5720 - Excavator, 6.0 CY bucket with truck loading, 80% fill factor, crew B-14B, daily output 4000 CY (500 CY/hr for 8 hours) $1.33/LCY or $1.53/BCY (no dozers) Note: Larger buckets or other methods could possibly be used, but are not included above. P:\Mpls\34 ND\09\34091004 Fargo Moorhead Metropolitan Feas. Study\WorkFiles\Project Data\Phase3\700_Cost_Est\Report_Exhibits\Exhibit_G-E1_0_Preliminary_Earthwork_Analysis Page 1 Exhibit_G-E1_0_Preliminary_Earthwork_Analysis Page 1 Job Number: 34-091-004.300.500 Barr Engineering Company Project: Subject: Task: Status: Fargo-Moorhead Metro Flood Risk Management Project Phase 3 Cost Estimate Work Analysis - Earthwork - Type 3 Oxidized Brenna draft Computed: Checked: Sheet: MRM MW1 8 Date Date of 7/26/2010 7/26/2010 10 Note: Information shown below is for cost estimate purposes only. Reference: John Deere manufacturer's literature for D-SERIES II ADTs (Articulated Dump Trucks) Constraints: 1.15 0.87 2 to 3 Model: Material Type 3 Oxidized Brenna Assumed Excavation to Haul swell LCY/BCY - USACE email 6-8-2010 Calculate Load Factor (L) Estimated California Bearing Ratio (CBR) John Deere 400D Articulated Dump Truck 29.4 22.1 22.7 147,530 5 8 15 CY Capacity (heaped 2:1) CY Capacity (struck) psi Max Ground Pressure (loaded, middle axle) lbs total operating weight (loaded) mph at 10% grade and total operating weight mph at 5% grade and total operating weight mph unloaded Haul Truck Productivity: Distance Slope LF % N/A N/A N/A N/A 135 <5 460 5 MAX 175 <5 250 <5 N/A N/A N/A N/A N/A N/A N/A N/A 700 -6 150 <5 N/A N/A Speed MPH 0 0 14 9 14 14 0 0 0 0 20 5 0 Time S 120 6 7 35 9 12 10 30 30 10 24 10 10 Factors: Machine Availability Gen Operational Efficiency Equipment: Time MIN 2.0 0.1 0.1 0.6 0.1 0.2 0.2 0.5 0.5 0.2 0.4 0.2 0.2 5.2 11.5 Activity Notes 0.70 21 1.00 0.95 11.0 226 797 693 Assume loading as % of heaped 2:1 capacity LCY per load per truck assumed (% * heaped 2:1 capacity) ( 100%) assume trucks are available as needed 3.5 1 0.5 trucks required small backhoe required (to periodically scrape beds) grader required (to manage the haul roads/rutting) load start level loaded uphill loaded level loaded level loaded stop unload bed scrape from loader (2 min. every 4 trips) start downhill unloaded return return zone stop total time per round trip (minutes) loads per hour (unfactored) (57 min/hr) loads per hour LCY/hour per truck LCY/hour excavator productivity match (from previous page) BCY/hour (from previous page) P:\Mpls\34 ND\09\34091004 Fargo Moorhead Metropolitan Feas. Study\WorkFiles\Project Data\Phase3\700_Cost_Est\Report_Exhibits\Exhibit_G-E1_0_Preliminary_Earthwork_Analysis Page 1 Job Number: 34-091-004.300.500 Barr Engineering Company Project: Subject: Task: Status: Fargo-Moorhead Metro Flood Risk Management Project Phase 3 Cost Estimate Work Analysis - Earthwork - Type 4 Brenna draft Computed: Checked: Sheet: MRM MW1 9 Date Date of 7/26/2010 7/26/2010 10 Note: Information shown below is for cost estimate purposes only. Reference: CAT Performance Handbook Edition 40 Hydraulic Excavators Constraints: 1.15 2 to 3 Material Type 4 Brenna Excavation to Haul swell LCY/BCY - USACE email 6-8-2010 California Bearing Ratio (CBR) - Oxidized Brenna Average Bucket Payload = (Heaped Bucket Capacity) x (Bucket Fill Factor) Bucket Fill Factor (% of heaped bucket capacity) Fill Factor Material Range low end high end Moist Loam or Sandy Clay 100-110% 100 110 Sand and Gravel 95-110% 95 110 Hard, Tough Clay 80-90% 80 90 Rock - Well Blasted 60-75% 60 75 Rock - Poorly Blasted 40-50% 40 50 p. 4-136 table Job Condition Description A Material types A B C Easy Digging (unpacked earth, sand, gravel, ditch cleaning etc.) Digging to less than 40% of machine's maximum depth capability. Swing angle less than 30°. Dump onto spoil pile or truck in excavation. No obstructions. Good operator. Medium digging (packed earth, tough dry clay, soil with less than 25% rock content). Depth to 50% of machine's maximum capability. Swing angle to 60°. Large dump target. Few obstructions Medium to hard digging (hard packed soil with up to 50% rock content). Depth to 70% of machine's maximum capability. Swing angle to 90°. Loading trucks with truck spotted close to excavator. Hard digging (shot rock or tough soil with up to 75% rock content). Depth to 90% of machine's maximum capability. Swing angle to 120°. Shored trench. Small dump target. Working over pipe crew Toughest digging (sandstone, caliche, shale, certain limestones, hard frost). Over 90% of machine's maximum depth capability. B C D E Swing over 120°. Loading bucket in man box. Dump into small target requiring maximum excavator reach. People and obstructions in the work area. Cycle Time Estimating Chart - per job condition CAT Machine Size Class Seconds per job condition M322D A Min Cycle Time (s) 10 A Max Cycle Time (s) 13 323D 324D 328D 329D 336D 345D 365C L 385C 10 11.5 NA 11.5 12.5 12 12 12.5 13 13 NA 14 15 15 15 15.5 B Min Cycle Time (s) 13 13 13 NA 14 15 15 15 15.5 B Max Cycle Time (s) 15.5 15.5 16 NA 16 18 18 20 21 C Min Cycle Time (s) 15.5 15.5 16 NA 16 18 18 22 21 C Max Cycle Time (s) 18.5 18.5 19 NA 19 21 20 26.5 27 D Min Cycle Time (s) 18.5 18.5 19 NA 19 21 20 26.5 27 D Max Cycle Time (s) 20 20 21 NA 22 23.5 23.5 31.5 32.5 E Min Cycle Time (s) 20 20 21 NA 22 23.5 23.5 31.5 32.5 E Max Cycle Time (s) 23 23 24 NA 26 26.5 29 34.5 42 Step 1 Material Fill Factor Hard, Tough Material Type Clay Range Low End High End 80-90% 80 90 p. 4-136 Step 2 Estimate Cycle Time Machine Class Size Job Condition B Min Cycle Time (s) B Max Cycle Time (s) 385C B 15.5 21 0.26 0.35 Min Min p. 4-188 Step 3 Calculate Effective Cycles per Hour Cycle time (Max from Step 2) 0.30 Min 60 Minute hour Cycle time 197 Operator Skill/Efficiency Machine Availability Gen Operational Efficiency Effective Cycles per Hour 0.95 0.95 0.80 142 p. 4-192 cycles/hour (95%) (95%) (48 min/hr) (cycles/hr) (1) downtime of 30min every 10hrs (1) downtime of 30min every 10hrs (1) equivalent downtime of 120min every 10hrs (1) total equivalent downtime of 3hr every 10hrs; (2) effective cycle above max. for Job Condition B Step 4 Calculate Required Bucket Capacity Nominal Bucket Size 5 cy Fill Factor 80 % Bucket Payload Volume= Nominal Bucket Size x Fill Factor 4 cy Bucket Payload Volume= Material Density / Loose= 2700 lb/cy Required Payload = Bucket Payload Volume x Material Density/Loose Required Payload = 10,800 lb Effective Cycles per Hour= 142 cycles/hr Step 5 Calculate Production Hourly Production Required= Required Payload x Effective Cycles per hour Hourly Production Required= 1,538,157 lbs/hr 769 tons/hr 570 LCY/hr 495 BCY/hr Crew: 1 Hydraulic Excavator (crawler) 1 Dozer (crawler) to maintain load/unload area Assume excavator, trucks can operate on Type 3 material to excavate the Type 4 Reference Comparison: 2010 RS Means 31-23-16.43-5700 - Excavator, 4.5 CY bucket with truck loading, 80% fill factor, crew B-14A, daily output 2720 CY (340 CY/hr for 8 hours) $1.03/LCY or $1.18/BCY (no dozers) 2010 RS Means 31-23-16.43-5720 - Excavator, 6.0 CY bucket with truck loading, 80% fill factor, crew B-14B, daily output 4000 CY (500 CY/hr for 8 hours) $1.33/LCY or $1.53/BCY (no dozers) Note: Larger buckets or other methods could possibly be used, but are not included above. Exhibit_G-E1_0_Preliminary_Earthwork_Analysis Page 1 Exhibit_G-E1_0_Preliminary_Earthwork_Analysis Page 1 Job Number: 34-091-004.300.500 Barr Engineering Company Project: Subject: Task: Status: Fargo-Moorhead Metro Flood Risk Management Project Phase 3 Cost Estimate Work Analysis - Earthwork - Type 4 Brenna draft Computed: Checked: Sheet: MRM MW1 10 Date Date of 7/26/2010 7/26/2010 10 Note: Information shown below is for cost estimate purposes only. Reference: John Deere manufacturer's literature for D-SERIES II ADTs (Articulated Dump Trucks) Constraints: 1.15 0.87 2 to 3 Model: Material Type 4 Brenna Assumed Excavation to Haul swell LCY/BCY - USACE email 6-8-2010 Calculate Load Factor (L) Estimated California Bearing Ratio (CBR) John Deere 400D Articulated Dump Truck 29.4 22.1 22.7 147,530 5 8 15 CY Capacity (heaped 2:1) CY Capacity (struck) psi Max Ground Pressure (loaded, middle axle) lbs total operating weight (loaded) mph at 10% grade and max operating weight mph at 5% grade and max operating weight mph unloaded Haul Truck Productivity: Distance Slope LF % N/A N/A N/A N/A 135 <5 460 5 MAX 175 <5 250 <5 N/A N/A N/A N/A N/A N/A N/A N/A 700 -6 150 <5 N/A N/A Speed MPH 0 0 10 9 10 10 0 0 0 0 15 5 0 Time S 120 12 9 35 12 17 10 30 60 10 32 10 10 Factors: Machine Availability Gen Operational Efficiency Equipment: Time MIN 2.0 0.2 0.2 0.6 0.2 0.3 0.2 0.5 1.0 0.2 0.5 0.2 0.2 6.1 9.8 Activity Notes 0.70 21 1.00 0.91 8.9 184 570 495 Assume loading as % of heaped 2:1 capacity LCY per load per truck assumed (% * heaped 2:1 capacity) ( 100%) assume trucks are available as needed (55 min/hr) (saturated clay) loads per hour LCY/hour per truck LCY/hour excavator productivity match (from previous page) BCY/hour (from previous page) 3.1 1 0.5 trucks required small backhoe required (to periodically scrape beds) grader required (to manage the haul roads/rutting) assume trucks are operating on Type 3 material load start level loaded uphill loaded level loaded level loaded stop unload bed scrape from loader (2 min. every 2 trips) start downhill unloaded return return zone stop total time per round trip (minutes) loads per hour P:\Mpls\34 ND\09\34091004 Fargo Moorhead Metropolitan Feas. Study\WorkFiles\Project Data\Phase3\700_Cost_Est\Report_Exhibits\Exhibit_G-E1_0_Preliminary_Earthwork_Analysis Page 1