Estimating Average Total Cost of Open Pit Coal Mines in Australia 1 2 S Shafiee , M Nehring and E Topal 3 ABSTRACT In preliminary feasibility studies mining project evaluators seek to estimate capital and operating costs of a proposed mining venture before mine layout design and general plant design. Mine planners often need to provide guidance on probable mine feasibility with insufficient cost information. There are two main methods for preliminary cost estimation. The first one relates to a few available sources that calculate the required cost information. The Mine and Mill Equipment Cost Calculator is an online exhaustive software tool which compiles capital and operating cost data for mining and milling purposes. Mine Cost is another online source which provides mine cost spreadsheets and operating cost information based on verifiable engineering and production data. The main shortcoming of these online sources is that they do not provide any detail about the methods for estimating mining cost and simply calculate total cost for a specific mine. The second one, which is more recognisable in industry, derives preliminary cost estimates by computing average total costs (ATC) of existing mining projects and operations. Since each mine has unique specifications, cost information should be estimated individually. This study focuses on establishing a range of ATCs according to previous mining projects and indices. This study endeavours to estimate an index and econometrics model for Australian coal mines to guide mining project evaluation to find the ATC in open pit coal mines. In other words, this paper reviews about 20 Australian open pit existing coal mines operated by different companies and categorises them by size of mine and deposit, coal quality parameters and production rate. It then, computers the ATC according to these existing open pit coal mines. After that, the ATC is expanded for the next 30 years by specific mining and milling indices. The study introduces an econometrics model to estimate mining and milling cost index via the Marshal and Swift equipment cost index for the future. Finally, this research provides an appropriate ATC for mine life which could be useful for preliminary feasibility studies of mining projects to find out general site conditions, mining methods, and milling processes. INTRODUCTION In mining project evaluation and decision making, the prediction of future volatility is a key input parameter. Capital and operating cost estimation on any proposed mining project is essential to evaluate a mining project for the whole of its mining life. Nowadays new project evaluation methods such as the 1. Postgraduate Student School of Engineering, CRC Mining, The University of Queensland, St Lucia Qld 4072. Email: s.shafiee@uq.edu.au 2. Postgraduate Student School of Engineering, CRC Mining, The University of Queensland, St Lucia Qld 4072. Email: m.nehring@uq.edu.au 3. Associate Professor/Head of Mining Engineering Department, Western Australia School of Mines, Curtin University of Technology. Email: e.topal@curtin.edu.au Australian Mining Technology Conference 27 - 28 October 2009 134 S SHAFIEE, M NEHRING and E TOPAL real option valuation (ROV) technique use cost estimation as a function to appraised mining projects (Shafiee and Topal, 2008; Shafiee, Topal and Micha, 2009). At the beginning of cost estimation, it is very difficult to find valuable data in all phases that project evaluators can use in their cost estimation. These data include a mining cost model, electric power costs, mining equipment costs, pertinent geologic, mineralogical, metallurgical variables, wages and benefits, cost indices, plus smelting and tax information (InfoMine, 2009). The economic evaluation components are based on information of the feasibility study, but engineers preparing feasibility studies never have all the engineering and economic information that is needed for accurate mining cost estimation. For instance, a small change in overburden and ore transportation costs in an open pit mine could have a significant effect on the cost that would shift the location of aggregate production away from the original location (Jaeger, 2006). Therefore, mining data plays a key role in mining project development to clearly feasible, doubtfully feasible or clearly uneconomic (Gentry and O’Neil, 1984). Most of the cost estimations and mining financial assets use past volatility in other mining projects as proxy for their cost estimation. Nevertheless, in practice this approach is not feasible because, historical data of some mining projects are not publicly released. This means volatility needs to be input as a variable in commodity price and operating cost measuring. For example, Lima and Suslick found that mining project volatility is independent of production capacity and depends on increment in price and cost (Lima and Suslick, 2006). Consequently, as an alternate solution each company use their own data sets and estimated operating costs according to previous similar projects. This paper initially discusses how mine cost can be calculated in two popular online sources: ‘Mine and Mill Equipment Cost Calculator’ and ‘Mine Cost’. Mining cost estimation using equations are also discussed. Moreover, the research introduces vital indices in different sections of mining projects and discusses their historical movements. The operating cost in 20 mines in Australia and some mines in Canada and the US are compared. Then according to important variables and reliable data, an econometrics model is estimated to calculate average operating cost. Finally, the estimated operating cost by econometrics model is validated using InfoMine operating cost estimation. HOW IS MINE COST CALCULATED? Uncertainty is attached in all the variables in mining project evaluation. For this reason, in order to take a conservative approach the mining project evaluator may tend to overestimate operating cost of the mine. High stripping ratio, seams with complex metallurgy characteristics, mines located in isolated regions, bad climate, lack of access to roads, electricity and water supply as well as mountainous topographic challenges, all contribute to uncertainty in the project. As projects move forward and greater certainty about crucial variables becomes more important, operating costs should be revised. For instance, knowledge of the deposit in regards to electricity and water consumption as well as metallurgical characteristics can be assessed through borehole sampling. A more accurate estimate of overall project capital cost and operating cost can be made from a summation of items of costs after judging the local specific effect conditions on each item of capital and operating cost. Another main variable affecting capital and operating cost is the process plant throughput rate. The greatest influence over mine revenue is produced by production rate, although, other variables such as coal quality, stripping ratio, as well as other possible explanatory variables is less important. Estimation of the daily run-of-mine is based on operating time periods of the process plants, mining operations, crushing plants and maintenance services. There is a general agreement that the size of the deposit has a strong influence on production rate (Smith, 1997), even though coal reserves are available up to 2112, and will be the only fossil fuel remaining after 2042 (Shafiee and Topal, 2009). 135 27 - 28 October 2009 Australian Mining Technology Conference ESTIMATING AVERAGE TOTAL COST OF OPEN PIT COAL MINES IN AUSTRALIA This means that the ratio of coal production to coal reserve is very low in comparison to other non-renewable resources. There are two main methods for preliminary cost estimation. The first one is an online software called ‘Mine and Mill Equipment Cost Calculator’ that calculate all equipment cost in feasibility. This software provides a comprehensive reliable data for equipment cost in detail. All data is based on InfoMine US’s complete equipment cost database, along with the mechanism to extract and adjust the data for specific projects. InfoMine US is dedicated to providing the cost data and advice mining projects need to make informed mining decisions. This software draws on its extensive background in mine planning, cost estimation, and project evaluation to understand mining projects’ cost data (InfoMine, 2009). The second one is ‘Mine Cost’, which is an online source that provides mine cost spreadsheets and operating cost information based on verifiable engineering and production data. This site is a source of mine cost spreadsheet models and operating cost information based on verifiable engineering, production data and peer reviewed by mining industry analysts. It presents some spreadsheet model containing detailed production and mine economics data, in many cases back to 1991 as well as projections for future years up to 2012. All models have cost curves showing the operation’s comparative cost ranking against all other mines in the industry (Mine Cost, 2009). Consequently, these two available methods estimate mining cost based on their own data bases, then provide an overview for future mining. The main shortcoming of these two methods is that they do not provide any details about the methods for estimating mining cost and simply calculate total cost for a specific mine. Since each mine has unique specifications, then cost information should be estimated individually. This study focuses on establishing a range of ATCs according to previous mining projects and available indices. Some studies according to previous mining projects data generate an exponential function for daily production and operating cost. The set of Equation 1 shows some of the main equations that were estimated in 1980 by O’Hara based on his data collection (O’Hara, 1980): Capital cost (US$ M) = $400 000 (tons mined and milled daily) 0.6 (1) Stripping cost (US$ M) = $800 (millions tons of overburden soil)0.5 Stripping cost (US$ M) = $8500 (millions tons of overburden rock)0.5 Equipment cost (US$ M) = $6000 (tons of deposit and waste mined daily)0.7 + $5000 (tons of deposit and waste mined daily)0.5 Maintenance cost (US$ M) = $150 000 (tons of deposit and waste mined daily)0.3 Labour cost (US$) = $58.563 (tons of deposit and waste mined daily)-0.5 + $3.591 (tons of deposit and waste mined daily)-0.3 Supplies cost (US$) = $13.40 (tons of deposit and waste mined daily)-0.5 + $1.24 (tons of deposit and waste mined daily)-0.3 + $0.90 (tons of deposit and waste mined daily)-0.2 Australian Mining Technology Conference 27 - 28 October 2009 136 S SHAFIEE, M NEHRING and E TOPAL The main shortcoming of O’Hara’s estimation relates to the expansion of Equation 1 over the mining project life; however, these equations are still one of the best approaches in cost estimation literature. This paper estimates cost function according to some of O’Hara’s variables. COST INDICES FOR MINING PROJECTS Cost indices in the mining industry provide a general overview and a mechanism for adjusting outdated cost information. One of the advantages of cost indices is that they show the effect of inflation on mining costs. Figures 1 to 4 illustrate a variety of crucial indices for specific mining scenarios as computed by InfoMine in 2009 (CostMine, 2009). These indices are measured based on general inflation in the US economy. InfoMine claims those indices serve as a comparison to the inflation experienced by the mining industry. This section will discuss the fluctuations in cost indices from 1965 to 2008. Figure 1 illustrates two labour indices ‘mine and mill operation labour’ and ‘mill construction labour’. Both labour indices move together throughout the periods. As shown the labour index over the last 40 years has increased by around six times. Figure 2 depicts ‘machinery, heavy equipment, repair parts’, ‘trucks tyres, scrapers, loaders, etc’ and ‘line haul railroads (all services)’ from 1965 to 2008. The trends of these three indices were similar to each other from 1965 to 1982. After 1982 ‘machinery, heavy equipment, repair parts‘ and ‘line haul railroads (all services)’ indices increased by relatively the same slope as the previous period to 2008,while the 'truck tyres, scrapers, loaders, etc’ index decreased until early 2000s and slightly increased in late 2000s. Figure 3 shows the trend of ‘gasoline, diesel, propane, fuel oil and lubricants’, ‘coal fuel’, ‘natural gas fuel’ and ‘electric power’. As can be seen in Figure 3 ‘gasoline, diesel, propane, fuel oil and lubricants’ and ‘natural gas fuel’ got more expensive in comparison to the two other indices. ‘Natural gas’ has risen by 50 times over the last 40 years, this index increased the most in comparison to all other indices. Figure 4 demonstrates five operation indices from 1965 to 2008. ‘Explosives and accessories’, ‘miscellaneous materials and 25 Mine and mill operating labour Mill construction labour 20 15 10 5 2007 2008 2005 2006 2003 2004 2001 2002 1999 2000 1997 1998 1995 1996 1993 1994 1991 1992 1989 1990 1987 1988 1985 1986 1983 1984 1981 1982 1979 1980 1977 1978 1975 1976 1973 1974 1971 1972 1969 1970 1967 1968 1965 1966 0 FIG 1 - Mine and mill operating labour and mill construction labour for coal mining processing cost indices (source of data: CostMine, 2009). 137 27 - 28 October 2009 Australian Mining Technology Conference ESTIMATING AVERAGE TOTAL COST OF OPEN PIT COAL MINES IN AUSTRALIA FIG 2 - Machinery, heavy equipment, repair parts, tires of trucks, scrapers, loaders, etc and line haul railroads (all services) for coal mining and processing cost indices (source of data: CostMine, 2009). 400 Gasoline, diesel, propane, fuel oil, and lubricants Coal fuel Natural gas fuel Electric power 350 300 250 200 150 100 50 2007 2008 2005 2006 2003 2004 2001 2002 1999 2000 1997 1998 1995 1996 1993 1994 1991 1992 1989 1990 1987 1988 1985 1986 1983 1984 1981 1982 1979 1980 1977 1978 1975 1976 1973 1974 1971 1972 1969 1970 1967 1968 1965 1966 0 FIG 3 - Gasoline, diesel, propane, fuel oil, and lubricants, coal fuel, natural gas fuel and electric power for coal mining and processing cost indices (source of data: CostMine, 2009). supplies not otherwise covered’, ‘drill bits and steel, mill balls, rods and liners, track’ and ‘mill reagents, mining chemicals’ fluctuated together over the period. ‘Mine timber’ fluctuated the same as other operation indices from 1965 to 1991, then after 1991 this index nearly doubled in less than four years in 1995. From 1995 to 2008 this index was relatively stable with minor oscillations. Consequently all fourteen indices over that period increased for coal mining and processing cost. Australian Mining Technology Conference 27 - 28 October 2009 138 S SHAFIEE, M NEHRING and E TOPAL FIG 4 - Explosives and accessories, miscellaneous materials and supplies not otherwise covered, drill bits and steel, mill balls, rods and liners, track mill reagents, mining chemicals and mine timber for coal mining and processing cost indices (source of data: CostMine, 2009). Table 1 shows some statistical calculation for all coal mining and processing indices from 1965 to 2008. The labour index in the coal mining industry is the minimum amount of mine cost while mine timber is the maximum amount. Coefficient of variance demonstrates fuel indices had the most volatility and the labour index had minor volatility. Entire indices increased over the time period between six to ten times. With the exception of operating labour that increased just 40 per cent over the last 40 years, as well as oil and natural gas fuel which soared 22 and 51 times respectively from 1965 to 2008. The Coal Cost Guide (CCG) is an internally generated index that provides a reliable means for tracking the cumulative effect of cost inflation on mining projects in the US and Canada (CostMine, 2009). In 2006 and 2007, the US had 802 surface and 559 underground mining activities. The largest producer of coal in 2007 was Wyoming with 411.5 million tonnes followed by West Virginia, Kentucky, Pennsylvania and Texas. Moreover, Alberta and British Columbia coal mines are the largest coal producing states in Canada (CostMine, 2009). In Australia, Queensland and New South Wales are the largest coal producers. The Hunter Valley coal operations in NSW is one of the biggest single open pit mines in the world producing around 12 - 15 million tonnes per year. Unfortunately, there is not any reliable data for coal mines in Australia in comparison to US and Canada. Table 2 endeavours to collect operating cost, capital cost and production rate for 20 Australian open pit coal mines. As can be seen in Table 2 real data for Australian mines was not readily available. However, the authors estimated a reliable range for those variables. An estimated combined capital and operating cost was used where expansions of projects had taken place since initial start up. The authors believe that the non-availability of mine data is the main reason for lack of research in cost estimation in Australia. The CCG indices are used as proxy for estimating the cost of each item in Australian surface coal mining cost. Figure 5 depicts the CCG indices for the US and Canadian mining industries individually from 1999 to 2008 and from 1991 to 2008, respectively. The figures show that Canadian operating cost and 139 27 - 28 October 2009 Australian Mining Technology Conference ESTIMATING AVERAGE TOTAL COST OF OPEN PIT COAL MINES IN AUSTRALIA TABLE 1 Mean, standard deviation, coefficient of variance, maximum and minimum of coal cost indices from 1965 to 2008 (source of data: CostMine, 2009). Coal cost index names Mean Standard Coefficient Increasing deviation of variance (times) (CV) Max Min 15.5 Mine and mill operating labour 18 1.82 10.00 1.4 22.0 Mill construction labour 12 5.41 45.66 6.8 21.9 3.2 Machinery, heavy equipment, repair parts 102 48.90 47.74 6.8 185.4 27.2 Drill bits and steel, mill balls, rods and liners, track 99 48.68 49.04 8.5 246.8 28.9 Mine timber 122 56.86 46.73 5.4 209.8 28.9 Gasoline, diesel, propane, fuel oil, and lubricants 70 54.83 77.81 22.1 272.0 12.3 Explosives and accessories 105 49.04 46.77 6.0 199.7 32.8 Tires of trucks, scrapers, loaders, etc 80 24.39 30.64 3.3 120.8 36.2 Miscellaneous materials and supplies not otherwise covered 98 43.97 45.00 6.2 192.4 30.9 Electric power 97 50.43 52.15 8.9 189.7 21.1 Mill reagents, mining chemicals 100 56.71 56.74 10.3 284.1 27.7 Coal fuel 82 33.05 40.11 9.0 157.7 17.5 Natural gas fuel 101 91.51 90.79 51.4 390.3 7.6 Line haul railroads (all services) 94 37.17 39.52 6.6 175.2 26.7 FIG 5 - Capital and operating cost indexes for the US and Canadian coal surface mine (source of data: CostMine, 2009). Australian Mining Technology Conference 27 - 28 October 2009 140 S SHAFIEE, M NEHRING and E TOPAL TABLE 2 The main Australian surface coal mines, production rate (million tonne per annum), capital expenditure (million Australian dollars), operational expenditure (Australian dollars per tonne), reserve and resources (million tonne) and mine life. Source: data was taken from a variety of sources including company annual reports, company websites and media reports (Anglo, 2009; BHP, 2009; Ensham, 2009; Felix, 2009; Gloucester, 2009; Idemitsu, 2009; Macarthur, 2009; New Hope, 2009; Peabody, 2009; Rio Tinto, 2009; Wesfarmers, 2009; Whitehaven, 2009; Xstrata, 2009). Estimates were made on all data items that were unavailable. No Mine Location Company Start Prod rate (Mt/a) CAPEX OPEX (AU$ M) (AU$/t) Reserves/ Mine life Resources (Mt) 1 Acland Acland New Hope 2003 2.7 - 3.9 110 - 170 50 - 70 109/679 2045 2 Bengalla Muswellbrook Rio Tinto 1999 5.5 - 6.5 50 - 65 200/369 2042 3 Blair Athol Clermont Rio Tinto 1984 8.0 - 12.0 190 - 230 35 - 50 50/70 2016 4 Boggabri Boggabri Idemitsu 2007 70 - 85 100/120 2075 5 Burton Mackay Peabody 1996 4.0 - 5.5 165 - 220 55 - 70 54/164 2021 1.5 450 38 6 Canyon Boggabri Whitehaven 2000 1.0 - 1.5 22 70 - 80 10/45 2009 7 Clermont Clermont Rio Tinto 2013 12.0 950 50 189/220 2030 8 Coppabella Nebo Macarthur 2000 2.1 - 4.2 145 - 180 55 - 75 67/207 2031 9 Curragh Blackwater Wesfarmers 1984 4.0 - 9.0 270 - 320 50 - 65 120/350 2025 10 Drayton Muswellbrook Anglo 1983 4.5 - 5.5 140 - 185 50 - 65 61/85 2021 11 Ensham Emerald Ensham 1994 7.0 - 9.5 340 - 290 35 - 55 600/900 2084 12 Foxleigh Middlemount Anglo 2000 2.5 - 3.3 130 - 160 55 - 65 60/290 2029 13 Hail Creek Nebo Rio Tinto 2003 5.0 - 6.0 250 - 290 40 - 60 224/420 2046 14 Jeebropilly Amberley New Hope 2006 0.5 - 0.85 15 - 25 60 - 75 5/7 2018 15 Mangoola Muswellbrook Xstrata 2012 10.5 1100 55 230/280 2033 16 Millenium Coppabella Peabody 2006 1.5 - 3.3 130 65 - 85 40/100 2021 17 Minerva Emerald Felix 2005 2.5 68 60 - 70 29/78 2020 18 Norwich P Dysart BHP 1979 45 - 55 120/423 2029 19 Rolleston Rolleston Xstrata 2005 6.0 291 49 173/600 2036 20 Stratford Gloucester Gloucester 1995 2.0 - 2.8 40 69 38/209 2024 4.0 - 5.5 180 - 250 capital cost mine indices are much greater than the US mine indices. Canadian operating cost index and capital cost index movements are similar to each other from 1991 to 2003, then the operating cost index rose more than its capital cost index since 2003. The capital cost and operating cost index in the US increased according the same trend over the last ten years. As a result, the operating cost and capital cost indices in both Canada and the US increased. Figure 6 illustrates Marshall and Swift index, which is another index to represent mining and milling equipment cost. Marshall and Swift is one of the most comprehensive databases in industrial economics. This index does regular surveys on material prices, labour rates and equipment prices in different industries, resulting in more than 2500 databases of location-specific costs throughout Canada and the US Marshall and Swift provide quarterly data in mining and equipment cost indices. This index in comparison to previous indices has advantages and disadvantages. The main advantage of this index is availability and frequency. However, the Marshal and Swift index provides just one figure for all subcosts in mining projects and ignores other sections of mining cost. Figure 6 illustrates the historical movement plus an econometrics linear trend of Marshal and Swift from 1980 to 2009. Another advantage of this index is expanding the liner econometrics trend for estimating mining and 141 27 - 28 October 2009 Australian Mining Technology Conference ESTIMATING AVERAGE TOTAL COST OF OPEN PIT COAL MINES IN AUSTRALIA 1800 MARSHALL & SWIFT EQUIPMENT COST INDEX (Mining, milling) Linear (MARSHALL & SWIFT EQUIPMENT COST INDEX (Mining, m illing)) 1500 1200 y = 6.1812x + 671.64 R2 = 0.9406 900 600 300 2009 2008 2006 2007 2004 2005 2003 2001 2002 1999 2000 1998 1996 1997 1994 1995 1993 1991 1992 1989 1990 1988 1986 1987 1984 1985 1982 1983 1980 1981 0 FIG 6 - Historical movement and liner trend of Marshall and Swift equipment cost index for mining and milling (source of data: CHE 1980 - 2009). milling equipment cost in the future. For example operating cost for the next ten years will be close to the same trend of econometrics liner trend. Consequently, Figure 6 verifies again that mining and milling cost equipment increased over that last 30 years. OPERATING COST ESTIMATION FOR AUSTRALIAN OPEN PIT COAL MINES In this section the operating cost for Australian open pit coal mines is estimated according to InfoMine data. InfoMine has computed operating and capital costs in US dollars based on American and Canadian mines. As can be seen in Table 3, operating costs and capital costs are based on deposit average thickness; stripping ratio and daily production rate are converted to Australian dollars. Table 3 shows that as deposit average thickness decreases and stripping ratio increases with a fix coal production rate, operating costs and capital costs increase. Moreover, in constant deposit average thickness and stripping ratio as long as production rate is increasing, operating cost and capital cost are increasing as well. The developed econometrics model for estimating operating cost focuses on deposit average thickness, stripping ratio, capital cost and daily production rate as the independent variables and operating cost as dependent variable. This model has been developed to explain the influence of independent variables on estimating operating cost. This model is estimated by ordinary least square approach for InfoMine data in 2008 (Table 3). The result is derived by Equation 2 as follows: EOC = 8.744955 - (0.041556) DAT + (1.658269) SR - (0.000459) CC - (0.041408) PR 2 R = 95%, F = 60.70 Australian Mining Technology Conference 27 - 28 October 2009 (2) 142 S SHAFIEE, M NEHRING and E TOPAL TABLE 3 Surface coal mine operating cost, capital cost, production rate, deposit average thickness and stripping ratio in different scenarios (source of data: CostMine, 2009). Deposit average thickness (metres) 12.3 3.1 1 10.2/1 20.2/1 40.6/1 Operating cost† 31.28 49.27 84.95 Capital cost‡ 60.9 105.4 213.7 Operating cost† 23.94 39.50 73.01 Stripping ratio, tonnes overburden/tonnes coal 1800 7300 Daily coal production (tonnes) 21 800 65 300 196 000 Capital cost‡ 178 196.7 354.4 Operating cost† 20.84 37.43 70.67 Capital cost‡ 361.9 551.5 1026 Operating cost† 18.87 34.94 67.77 Capital cost‡ 863.9 1500.8 2911.7 Operating cost† 16.95 34.25 65.68 Capital cost‡ 2373.1 4348.4 8492.9 † Operating cost is calculated based on A$ per tonne in 2008. ‡ Capital cost is computed based on million A$ in 2008. where: EOC estimated operating cost (per tonne) DAT deposit average thickness (metres) SR stripping ratio (tonnes overburden per tonne coal) CC capital cost (A$ M in 2008) PR daily production rate (1000 tonnes) The econometrics model estimates the relationship between DAT, SR, CC and PR with EOC. This model shows that the CC and PR has a positive effect on EOC and DAT and SR has a negative effect on EOC. For example, the model indicates that if stripping ratio increases by one tonne overburden per tonne coal, the operating cost will be increased by a factor of 1.66 Australian dollars per tonnes, ceteris paribus. Table 4 depicts, EOC based on econometrics model and compared with operating cost (OC) calculated by InfoMine and Australian coal mine in Table 2. As can be seen in Table 4, the model estimation has ±20 per cent range of accuracy with real data. Additionally, the developed model has 95 per cent significance and neither multicollinearity, heteroscedasticity nor autocorrelation problems. CONCLUSION In the mining industry most of the cost estimations are based on past volatility in other mining projects as proxy for current mining projects. Moreover, uncertainty is attached in all the main variables in mining project evaluation for estimation. As projects move forward and certainty about crucial variables needs to increase, operating cost should be revised. For this reason, in order to take a conservative approach the mining project evaluator may tend to overestimate operating cost of the mine. The accuracy of estimation of capital costs and operating costs depend on the quality of the technical assessment and knowledge of expected mining and mineral processing conditions. Consequently, mining companies extensively investigate alternative available methods and reliable data with intention of reducing cost. 143 27 - 28 October 2009 Australian Mining Technology Conference ESTIMATING AVERAGE TOTAL COST OF OPEN PIT COAL MINES IN AUSTRALIA TABLE 4 Surface coal mine deposit average thickness, stripping ratio, capital cost, production rate, InfoMine operating cost estimation, econometrics operating cost estimation and validity range of two estimations (source: data collected from InfoMine, 2009 and modellings computed in Eviews). DAT SR CC PR OC EOC Validity range 12.3 10.2 60.88 1.8 31.28 25.05 -20% 3.1 20.2 105.37 1.8 49.27 41.99 -15% 1 40.6 213.75 1.8 84.95 75.86 -11% 12.3 10.2 177.96 7.3 23.94 24.76 3% 3.1 20.2 196.66 7.3 39.50 41.72 6% 1 40.6 354.44 7.3 73.01 75.56 3% 12.3 10.2 361.96 21.8 20.84 24.08 16% 3.1 20.2 551.50 21.8 37.43 40.96 9% 1 40.6 1026.00 21.8 70.67 74.66 6% 12.3 10.2 863.82 65.3 18.87 22.05 17% 3.1 20.2 1500.77 65.3 34.94 38.72 11% 1 40.6 2911.74 65.3 67.77 71.99 6% 12.3 10.2 2373.08 196 16.95 15.94 -6% 3.1 20.2 4348.44 196 34.25 32.00 -7% 1 40.6 8492.86 196 65.68 64.02 -3% This paper discusses some main indices in different sections of mining projects and analyse their historical movements. Cost indices in the mining industry provide a general overview and a mechanism for adjusting outdated cost information. One of the advantages of cost indices is to show the effect of inflation in mining cost estimation. This study addresses the fluctuation of cost indices in InfoMine from 1965 to 2008 and Marshal and Swift index from 1980 to 2009. As a result, all indices over this period increased between six to ten times for coal mining and processing cost. While, the operating labour index increased just 40 per cent over the last 40 years, in contrast with the oil and natural gas fuel index which soared 22 and 51 times respectively from 1965 to 2008. In addition, the operating cost in 20 mines in Australia and some mines in Canada and the US are discussed. The availability of mine data in Australia is limited in comparison to US and Canada. The CCG indices are used as proxy for estimating the cost of each item in Australian surface coal mining cost. Then according to main variables and reliable data, an econometrics model is estimated to calculate average operating cost. The econometrics model for estimating operating cost focuses on deposit average thickness, stripping ratio, capital cost and daily production rate as the independent variables and operating cost as dependent variable. This model has been developed to explain the influence of independent variables on estimating operating cost. The model shows that the capital cost and production rate has a positive effect on estimated operating cost and deposit average thickness and strip ratio has a negative effect on estimating operating cost. Estimated operating cost based on the model is compared by operating cost calculated in InfoMine, and proves that the model estimation has ±20 per cent range of accuracy with real data. Finally, the econometric model could be calculated for the future by expanding indices for the future. Accordingly, accurate estimation for mining project cost is very difficult; nevertheless these types of techniques could supply a view for one of the main uncertainty variables in mining projects. Australian Mining Technology Conference 27 - 28 October 2009 144 S SHAFIEE, M NEHRING and E TOPAL REFERENCES Anglo, 2009. Anglo coal in Australia [online]. Available from: <http://www.anglocoal.com.au/>. BHP, 2009. BHP Billiton [online]. Available from: <http://www.bhp.com.au>. Chemical Engineering (CHE), 1980 - 2009. Economic indicators [online], Chemical Engineering. Available from: <http://www.che.com>. CostMine, 2009. Coal cost guide: A subscription cost data service, Spokane Valley, WA, InfoMine USA Inc. Ensham, 2009. Ensham [online]. Available from: <http://www.ensham.com.au/>. Felix Resources Ltd, 2009. Felix Resources Ltd [online]. Available from: <http://www.felixresources.com.au/>. Gentry, D W and O’Neil, T J, 1984. Mine Investment Analysis (Society of Mining Engineers of American Institute of Mining, Metallurgical and Petroleum Engineers Inc: New York). Gloucester, 2009. Gloucester Coal [online]. Available from: <http://www.gloucestercoal.com.au/>. Idemitsu, 2009. Idemitsu [online]. Available from: <http://www.idemitsu.com/>. InfoMine, 2009. Cost mine [online], Mining Intelligence and Technology. Available from: <http://www.info mine.com>. Jaeger, W K, 2006. The hidden costs of relocating sand and gravel mines, Resources Policy, 31(3):146-164. Lima, G A C and Suslick, S B, 2006. Estimating the volatility of mining projects considering price and operating cost uncertainties, Resources Policy, 31(2):86-94. Macarthur, 2009. McArthur Coal Limited [online]. Available from: <http://www.macarthurcoal.com.au/>. Mine Cost, 2009. World mine cost data exchange [online]. Available from: <http://minecost.com/>. New Hope, 2009. New Hope Corporation Limited [online]. Available from: <http://www.newhopecoal.com.au>. O’Hara, T A, 1980. Quick guide to the evaluation of orebodies, CIM Bulletin, February, pp 87-89. Peabody, 2009. Peabody Energy [online]. Available from: <http://www.peabodyenergy.com.au/>. Rio Tinto. 2009. Biodiversity action plans [online]. Available from: <http://www.riotintocoalaustralia.com.au/>. Shafiee, S and Topal, E, 2008. Applied real option valuation (ROV) in a conceptual mining project, in Proceedings Australian Mining Technology Conference (CRC Mining: Brisbane). Shafiee, S and Topal, E, 2009. When will fossil fuel reserves be diminished?, Energy Policy, 37(1):181-189. Shafiee, S, Topal, E and Micha, N, 2009. Adjusted real option valuation to maximise mining project value a case study using century mine, in Proceedings Project Evaluation 2009, pp 125-134 (The Australasian Institute of Mining and Metallurgy: Melbourne). Smith, L D, 1997. A critical examination of the methods and factors affecting the selection of an optimum production rate, CIM Bulletin, February, pp 48-54. Wesfarmers, 2009. Wesfarmers [online]. Available from: <http://www.wesfarmers.com.au/>. Whitehaven, 2009. Whitehaven Coal Limited [online]. Available from: <http://www.whitehaven.net.au/>. Xstrata, 2009. Xstrata [online]. Available from: <http://www.xstrata.com/>. 145 27 - 28 October 2009 Australian Mining Technology Conference