B.C.’s Watershed Restoration Technical Bulletin Feature Melton, M.A. 1965. The geomorphic and paleoclimatic significance of alluvial deposits in southern Arizona. J. Geol. V. 73. pp1-38. Oliver, C.D. and B.C. Larson. 1996. Forest Stand Dynamics. John Wiley and Sons, Inc. New York. 520p. Ritter, J. and 16 others. 1993. Quaternary evolution of Cedar Creek alluvial fan, Montana. Geomorphology 8:287-304 Ritter. D.F., R.C. Kochel and J.R. Miller. 1995. Process Geomorphology. Third edition. Wm. C. Brown Publishers. Dubuque, IA, U.S.A. 546p. Ryder, J.M. 1971a. The stratigraphy and morphology of paraglacial alluvial fans in south-central British Columbia. Can. J. Earth Sci. 8: 279-98 Ryder, J.M. 1971b. Some aspects of the morphometry of paraglacial alluvial fans in south-central British Columbia. Can. J. Earth Sci. 8: 1252-1264 Schweingruber, F.H. 1996. Tree Rings and Environment Dendroecology. Paul Haupt Publishers. Berne. 609p. Wells, S.G. and A.M. Harvey. 1987. Sedimentologic and geomorphic variations in storm-generated alluvial fans, Howgill Fells, northwest England. Geol. Soc. Amer. Bulletin. v.98:182-198. For further information, contact: David Wilford or Matt Sakals BC Ministry of Forests, Bag 5000, Smithers, B.C., Canada, V0J 2N0. email: dave.wilford@gems3.gov.bc.ca email: matt.sakals@gems7.gov.bc.ca John Innes UBC Faculty of Forestry, 2424 Main Mall, Vancouver, B.C., Canada, V6T 1Z4. email: innes@interchange.ubc.ca Murder Creek: Instream Works to Improve Fish Spawning and Rearing Habitat Jason Paquette, Jessica Chaplin and Lisa Torunski Introduction Murder Creek is an S2 stream located approximately 35km northeast of Old Hazelton in the Kispiox Forest District. It drains an area of 50 km2. Murder Creek flows under the historic Kispiox Trail and through private land to its confluence with the Kispiox River (Figure 1). The Kispiox River is a migration corridor for thousands of fish each year including sport, native food fishery and commercial species. From 1980 to 1986, over 13,000 coho (Oncorhynchus kisutch) fry were released into Murder Creek by Fisheries and Oceans Canada (FOC). Subsequent inventories list the following species in Murder Creek: coho (O. kisutch), and pink salmon (O. gorbuscha), cutthroat trout (O. clarki), rainbow trout, steelhead (O. mykiss) and Dolly Varden char (Salmo malma) (KWRP, 1995; KWRP, 1997). Development impacts during the past 75 years have included forestry in the upper watershed and agricultural land clearing, road development, grazing and riparian vegetation removal in the lower reaches and the floodplain. Agricultural land use has confined the stream to its current location. Murder Creek has been identified as a high priority stream within the Skeena Region WRP Resource Management Plan. For this reason, restoration activities were carried out to Streamline 8 Project Location Figure 1. Location Map. enhance the quality of existing fish habitat in Murder Creek, reducing the impacts that have occurred as a result of land use activities. B.C.’s Watershed Restoration Technical Bulletin Feature Cr N P8 ee k BC Environment (now the Ministry of Water, Land and Air Protection) approved four prescriptions for construction in 2001 (Figure 2). Permission for access on private land was obtained from the landowner. An Authorization for Works In and About a Stream was obtained from Water Management Branch. A Fish Collection Permit and Scientific Collection License were obtained from Provincial and Federal government agencies. er Background In 1999, AMEC Earth and Environmental Ltd. prescribed instream treatments for eight sites along the lower two reaches of Murder Creek. Reach I was a straight, uniform low gradient channel with fine uniform substrates and a long continuous riffle habitat (305 m). Reach II was described as a low gradient, meandering stream section. Both reaches had low functional LWD and limited potential for future LWD recruitment into the stream. Since mature riparian vegetation had been removed, bank erosion of the Sbends was significant. At bankful flows, side channels, gravel bars, and shallow pools were prone to flooding. rd The project objectives were to: • use tree revetments in four locations to reduce bank erosion, create instream habitat complexity and to slow the velocity of the stream around the meander bend; • use a log cluster diversion structure to reduce the rate of lateral channel migration and streambank erosion into the stream; and to • remove an abandoned bridge, which contained hazardous materials (creosote) and could become a barrier to fish passage if it collapsed into Murder Creek. Mu Project Goals and Objectives The goals of this project were to build instream structures of LWD that would reduce streambank erosion, create instream cover and increase habitat complexity for fish. Grazing Pasture Reach 2-2 P7 P6 Kisplox Trail Drainage Ditch Hay Field Hazelton 38 km P2 Reach 1-1 Hay Field Kisplox R. Figure 2. Site Plan. Sediment control measures: To minimize instream disturbance, work sites were isolated from the main stream flow using silt fabric and sandbags. Silt fabric was used to isolate a portion of the channel (Figure 3). Sandbags anchored the silt fabric and delivered flow outside the isolation area. This effectively separated the work area from the rest of the stream. Sandbags were also used on the outside of the isolated area to provide extra support to the silt fencing and to ensure the main channel flow was directed away from the McElhanney Consulting Services Ltd. (MCSL) was contracted as the construction supervisor for the instream prescriptions. The Kispiox Band Council was contracted to provide the equipment, materials and labour. Work was initiated in September 2001 and took approximately nine days to complete. Environmental protection Fish salvage: Fry removal prior to construction was done using a Coffelt backpack electroshocker and dip netting. Stream sections were isolated using silt fencing and sandbags. Over seventy-five fry (coho, rainbow trout/steelhead) were removed from the isolated sections of stream. Figure 3. Isolation of stream sections using silt fencing and sandbags. Streamline 9 B.C.’s Watershed Restoration Technical Bulletin Feature isolated section. However, the sandbags themselves did generate some sediment. It is recommended that on future projects clean sources of silt and clay-free sands are used to fill the sandbags. Two three-inch pumps were used to pump dirty water from the isolation areas and to minimize sediment in the stream. Erosion control measures: Along the stream banks and in the landowners hay fields straw was used to cover all exposed soils and the disturbed areas were seeded with fall rye to protect against surface soil erosion into the stream. Prescription P2 – At the top of the Kispiox River floodplain, Murder Creek is forced to turn hard left. Freshet floods caused increasing bank erosion and downcutting of the stream. A typical tree revetment of six logs, 20 m in length along the outside bend was installed to reduce bank erosion, create instream habitat complexity and to slow the velocity of the stream around the bend. Rehabilitation Work: Six revetment logs were added to the right bank starting at the existing fence line extending around the sharp eroding bank. A riprap groin and large angular ballast rock was constructed upstream of the revetments to prevent scour behind the revetments and to protect them from erosion. A large rock (>1 m diameter) was keyed in immediately downstream of the last revetment near the fence to protect the work from back eddy scour. Figures 4 and 5 show the site pre- and post-construction. Prescription P6 - Upstream of the landowner’s pump house a flood channel was forming, thus Murder Creek could potentially bypass (via lateral channel migration) the pump house. A log cluster diversion structure was prescribed to absorb flood flows and deflect them down the original channel. A pullback of a 4 m vertical right bank for a distance of 2 m and a lateral distance of approximately 10 m was proposed to reduce bank erosion from over-steepened banks. Construction was conducted without the pullback being necessary and post-construction bank disturbance was minimal. Rehabilitation Work: A log cluster flow diversion structure was installed using two revetment logs, four footer logs, seven cluster logs and 16 large ballast rocks. The log cluster was designed to slow the stream velocity around the bend during higher flows and to prevent the channel from shifting. It was placed at the bottom of the eroding bank with footer logs and large ballast rocks to provide bank stabilization. Downstream of the log cluster two revetment logs with the rootwads facing upstream were situated to direct flows back into the existing channel. Large rocks Figure 4. Site P2 pre-construction. Figure 5. Site P2 post-construction. were anchored and cabled using a Hilti rock drill, 316 steel grade cables and a Hilti HIT RE500 epoxy system, securing the tree revetments and footer logs (Figure 6). Prescription P7 – An abandoned bridge, which was in an advanced state of decay, was removed using an excavator and hand labour with little disturbance to the stream. The waste wood was stockpiled for future burial away from the stream by the landowner. Prescription P8 – Lateral channel migration was occurring in a cleared area (length 50 m) caused by livestock crossing and grazing on and about the streambanks. Nineteen tree revetment logs with rootwads, 15 footer logs, 40 ballast rocks (>1 m in diameter), 350 feet of steel cable, and 17 Duckbill anchors were used to construct tree revetments in three locations to reduce the rate of lateral channel migration Figure 6. Sketch showing revetment ballast. Streamline 10 Continued on page 11... B.C.’s Watershed Restoration Technical Bulletin Feature ...continued from page 10. and to reduce streambank erosion into the stream (Figure 7). In addition to the tree revetments, log clusters were added to the stream to provide in-stream habitat. Figure 9. Increasing complexity and cover at site P8. Figure 7. Site P8 showing the length of the prescription site. Rehabilitation Work: First, 20 m of streambank was rehabilitated with eleven revetment trees. Trenches were dug with the excavator for the 5 m long revetment tree boles. Duckbill anchors were used to anchor the ends of the revetment logs. The rootwads faced into the stream and were spaced approximately 3 m apart so that each rootwad overlapped the next by approximately 0.5 m (Figure 8). Footer logs were lashed to the revetment trees with the footer logs alternating over or under the boles. Large boulders were cabled on either side of each revetment tree for ballast and the trench was re-filled. Fall rye was hand-seeded over the disturbed area and loose hay was spread over the disturbed area to reduce streambank erosion. Further downstream, 12 m of streambank was rehabilitated using the same tree revetment process described above. In addition, two trees 15 m long, with branches and rootwads intact and lashed together were placed parallel to the bank to support an undercut bank. At the upstream end, at 1/3 the length and at 2/3 the length, two large boulders were cabled to the trees as anchors (Figure 9). Figure 8. Revetments installed at Site P8. At a large scour pool (depth 0.9 m) downstream of the cleared area, Murder Creek turns a hard left. At this location, 15 m of bank was stabilized using one tree revetment and three logs anchored parallel to the bank. Construction was conducted in such a way as to minimize the disturbance to the pool while adding LWD and increasing habitat complexity. Riparian Zone Protection and Re-vegetation The landowner installed riparian fencing prescribed by OIKOS Ecological Services (OIKOS, 2000) along both sides of the stream for the protection of the riparian zone and new instream works. Willow staking and conifer planting is to be completed in a separate contract in the spring of 2002. Summary and Conclusions Through the stream enhancement efforts described above, these two reaches of Murder Creek are now more complex and stable during flood flows. A key element in the long-term recovery of Murder Creek is the reestablishment of a functional riparian corridor. This project has completed the channel and bank stabilization and fencing. In time, after the riparian area planting is complete, riparian function will be restored. Project Proponent and Cost Summary The project was carried out under the Forest Renewal BC Watershed Restoration Program, directed jointly between Ministry of Forests and Ministry of Water, Land and Air Protection. The total cost of the project was estimated at $65,000. Acknowledgements The works could not have been completed without the co-operation from the Allen family. Special thanks to Patrick Hudson, Jeff Lough and Troy Larden for their hard work and technical assistance at the site. Grateful thanks are also due to Al Harrison of the Kispiox District. Streamline 11 B.C.’s Watershed Restoration Technical Bulletin Feature References AMEC, 2000. Murder Creek Watershed Restoration Prescription. Submitted to Kispiox Band Council, Kispiox, British Columbia. Submitted by AMEC Earth & Environmental Limited, Prince George, BC (KS00120). KWRP, 1995. Overview Fish and Fish Habitat Assessment Report for the Kispiox River Watershed. Prepared for the Ministry of Environment, Lands and Parks, Skeena Region. KWRP, 1997. Level 1 Fish and Fish Habitat Assessment of the Kispiox River Watershed. Prepared for the Ministry of Environment, Lands and Parks, Skeena Region. OIKOS Ecological Services Inc. March 2000. Riparian Rehabilitation Prescriptions for the Lower Reaches of Murder Creek (the Allen Farm) Kispiox Watershed. Prepared for Jeff Lough, MELP, Skeena Region, Smithers, BC. For more information contact: Jason Paquette, Design Technician Jessica Chaplin, R.P.Bio. Lisa Torunski, R.P.Bio. McElhanney Consulting Services Ltd. 3578 Victoria Drive Smithers B.C. V0J 2N0 or P.O. Box 787 Smithers B.C. V0J 2N0 Tel: 250-847-4040 Fax: 250-847-4160 jpaquette@mcelhanney.com jchaplin@mcelhanney.com ltorunski@mcelhanney.com Riparian Restoration at the Narrowlake Creek Demonstration Watershed Andrew Wilson, Beryl Nesbit and Ray Pillipow Introduction The Narrowlake Creek restoration project represents one of the Province’s five Demonstration Watersheds. Narrowlake Creek is located 80 km southeast of Prince George and is a tributary to the Willow River. Since 1997, instream restoration has been completed over approximately four kilometres of mainstem channel to provide a demonstration of watershed restoration in the central interior. Riparian restoration has also been undertaken in the drainage. Riparian restoration was initiated at Narrowlake Creek in the spring of 1999 to address issues relating to future channel stability, fisheries and wildlife concerns which resulted from pre-Forest Practices Code streamside forest harvesting. The project was evaluated in 2001 to determine the short-term success or failure of the restoration work and to identify requirements for any remedial work. Riparian restoration is becoming an increasingly topical and important component of watershed restoration (Naiman et al. 2000, Poulin et al. 2000). Choosing appropriate, cost-effective restoration techniques to best meet multi-resource objectives can be a challenging task. In many areas, especially along the coast where growing seasons are long and conifer regeneration rapid, the most effective restoration prescriptions may involve thinning or spacing Streamline 12 deciduous dominated, mixed, or overstocked conifer stands to facilitate the release of already established conifers (e.g. Poulin and Simmons 2001). However other areas such as the central interior, where growing seasons are short and conifer regeneration slow, may require alternative techniques. An alternative riparian restoration technique for use where variable density thinning is not viable is the direct planting of conifers. This technique is appropriate for those areas where conifers have not become adequately established (Koning 1999). While this technique has merit, often conifers have not become established for good reasons (e.g. excessive shrub competition, inhospitable site conditions or elevated water tables). Poulin et al. (2000) note that direct planting of conifers is an expensive and higher risk restoration treatment compared with thinning or brushing. However, in the Narrowlake Creek riparian restoration project, there was little alternative due to the paucity of conifers that had re-established along the floodplain following extensive streamside logging. To overcome some of the difficulties associated with direct planting of conifers at Narrowlake Creek, several different planting trials were undertaken in an attempt to identify the most effective means of addressing long-term riparian restoration objectives in