Key Implementation Activities and Deliverables:
AcceleratedSAP
Table D.2-1 ASAP Phases
AcceleratedSAP Phases
Phase 1 – Project Preparation
Phase 2 – Business Blueprint
Phase 3 – Realization
Phase 4 – Final Preparation
Phase 5 – Go Live and Support
The ASAP Roadmap was developed by SAP to help customers implement SAP software in a
quick, cost-effective manner. Utilizing this approach:
 minimizes the length of implementation,
 maximizes the utilization of TeamSAP and customer resources,
 results in a “Repetitive Model” that can be used with other implementations of SAP modules
or systems, and
 provides a process-oriented approach to Product Training.
EI Toolkit Reference
Document version 1.0, June 2003
Last validated: June 2003
0
EITK0304
Key Implementation Activities and Deliverables:
AcceleratedSAP
Table D.2-2 Project Preparation Key Activities and Deliverables
Key Activities
Deliverables
 Finalize Project Team Organization
 Project Team Structure Organization Chart

Finalize Project Team Training Plan

Project Team Training Schedule

Define Team Facilities Requirements

Project Team Seating Chart (including
required equipment)

Develop Project Plans

Develop Project Strategies and Scope





Review Existing Implementations

Define Project Management Standards and
Procedures


Develop Benefits Realization Strategy
Develop Project Risk Assessment


Define Post-Implementation Support

Perform Technical Requirements Gathering 

Procure Hardware




Define System Landscape Strategy

Define Project Methodologies, Tools and

Project Governance Standards
Define Quality Assurance Plan

Develop Communication Strategy and Plan 
Baseline Project Plans
Initial Activities Planned
Resource Plan
Draft:
o Implementation Strategy
o End-User Training Strategy
o Development Strategies
o Testing Strategy
o Technical Strategies
o Security and Controls Strategy
o High-level Project Scope Document
List of Lessons Learned
Project Management Standards and
Procedures (Issue Mgt Plan, Status Report
Format, Change Control Forms,
Documentation standards, etc,)
Benefits Realization Approach
Risk Management Plan, Report and
recommendations to mitigate project risks,
and summary of Critical Success Factors
Post-Implementation Support Approach
Complete Technical Questionnaires
Define Technical Infrastructure Needs
Size Initial Hardware
Approve Sizing Results
Order Initial Hardware and Software
Order Remote Network Connection
System Landscape Strategy
Established Project Methodologies, Tools
and Governance Standards
Quality Assurance Plan
Communication Plan/Strategy





EI Toolkit Reference
Document version 1.0, June 2003
Last validated: June 2003




1
EITK0304
Key Implementation Activities and Deliverables:
AcceleratedSAP




Confirm Process, Organization and
Technical Scope
Develop and perform Change Readiness
Assessment
Produce and Deliver Program Management
Status Reports
Prepare for Project Kickoff
EI Toolkit Reference
Document version 1.0, June 2003
Last validated: June 2003

Sign-off by Customer

Change Readiness Assessment Results and
Report
Completed Status Report
Updated Issues Log
Kickoff Meeting



2
EITK0304
Key Implementation Activities and Deliverables:
AcceleratedSAP
Table D.2-3 Business Blueprint Key Activities and Deliverables
Key Activities
Deliverables
 Conduct Project Team Training
 Execute Project Team Training Schedule



Define SAP Organizational Structure
Define Global Parameters
Prepare for Blueprint Workshops

SAP R/3 Hierarchy Definitions
Conduct Blueprint Workshops





Finalize Project Scope



Finalize Development Scope


Finalize End-User Training Strategy

Blueprint Workshop Schedule
List of Blueprint Workshop Participants
Blueprint Workshop Agendas
Business Blueprint Report
o Business Process Flows
o Policies and Procedures
o Gaps Identified
Business Process Master List (BPML)
Finalized Scope Document Signed off by
Customer
Development Scope: Reporting, Interfaces,
Conversions, Enhancements
End-User Training Strategy Signed-Off by
Customer
End User Training Requirements and
Materials Standards document



Conform to DoD RICE Concept of
Operations
Perform Cycle Planning for Prototyping
Develop Knowledge Transfer Plan






Develop Communications and Key
Stakeholder Management Plans
Define Business Organization Structure
and Identify Impact Areas
Complete SAP Bolt-On Evaluation
Identify Process Ownership
Create Technical Design
Develop Non-functional Requirements

Develop Security Requirements


Setup and Install Development
Environment
Risk Assessment Measurement

Evaluation Results of SAP Bolt-Ons
Benefits and Process Owner Organization
Technical Design Document
Non-functional Requirements
Specifications Documentation
Security Requirements Specifications
Documentation
Installed Development System

Revised Risk Assessment





EI Toolkit Reference
Document version 1.0, June 2003
Last validated: June 2003







Cycle Plan for Prototyping
Knowledge Transfer Plan signed off by
Customer
Communication and Key Stakeholder
Management Plans
Business Organization Impacts
3
EITK0304
Key Implementation Activities and Deliverables:
AcceleratedSAP

Conduct Peer/Solution/Technical Reviews


Produce and Deliver Program Management
Status Reports
Business Blueprint Sign-off




EI Toolkit Reference
Document version 1.0, June 2003
Last validated: June 2003
Solution/Technical Review Findings
Reports
Completed Status Report
Updated Issues Log
Business Blueprint Documentation and
Phase completion signed-off by Customer
4
EITK0304
Key Implementation Activities and Deliverables:
AcceleratedSAP
Table D.2-4
Realization Key Activities and Deliverables
Key Activities
Deliverables
 Define Master Data
 Master Data Definitions
 Baseline Configuration Completed
 Baseline Configuration and Documentation
 Conduct Unit Testing
 Completed Unit Testing and Associated
Scripts and Results

Final Configuration Completed



Create Security Authorizations
Develop Custom Design Specifications
(functional spec’s)
Develop Technical and Functional
Specifications
Coding and Unit Test for Conversions,
Reports, Interfaces and Enhancements







Conversion Planning (Cutover) and
Preparation
Develop New Procedures and Policies





Finalize Implementation Strategy





Finalize End-User Training Strategy
Establish Training Environment
Train Power Users
Plan SAP early watch Go-Live Quality
Assurance / Check
Plan and Execute System Test













Execute Cycle Testing
Develop Integration Test Plan(s)
Execute Integration Test
Design and Deliver Instructor Training
Material (if applicable)
Create End-User Training Programs and
Training Materials
Create Technical Design
Establish Data Archiving Plan
EI Toolkit Reference
Document version 1.0, June 2003
Last validated: June 2003
Configured SAP System and Related
Documentation
Configured SAP User Profiles and Roles
Functional Specifications
Technical and Functional Specifications
Documentation and Associated Approvals
Completed Unit Testing for Development
Objects
Object Code for Development Objects
Initial Conversion (Cutover) Plan
Draft Legacy Retirement Plan
New Procedures and Policies
Documented/Approved
Implementation Strategy, including Site
Readiness Assessment and Change Process
Improvement
Approved End-User Training Strategy
Installed Training System
Trained Power Users and Trainers






System Test Plan
Volume and Stress Tested System
Cycle Testing Complete
Integration Test Plan
Integration Test Complete
Instructor Training Material






End-User Training Curriculum
End-User Training Materials
End-User Training Schedule
Facilities Reservations
Technical Design Document
Data Archiving Plan
5
EITK0304
Key Implementation Activities and Deliverables:
AcceleratedSAP


Installed Quality Assurance System
Revised Risk Assessment



Setup and Install Quality Assurance (QA)
Environment
Risk Assessment Measurement
Deliver Knowledge Transfer Status
Execute Communications Plan

Conduct Peer/Solution/Technical Reviews






Produce and Deliver Program Management
Status Reports


EI Toolkit Reference
Document version 1.0, June 2003
Last validated: June 2003
Presentations
Newsletters
Solution/Technical Review Findings
Reports
Completed Status Report
Updated Issues Log
6
EITK0304
Key Implementation Activities and Deliverables:
AcceleratedSAP
Table D.2-5
Key Activities
 Perform System Tests




















Final Preparation Key Activities and Deliverables
Deliverables
 Execute Stress, Volume, Disaster Recovery
and Backup Tests
 Technical Processes Tested
Assess Going-Live Check
 Implement Going-Live Check
Recommendations
Recommendations
Finalize Cutover (Conversion) Plan
 Cutover Workplan
Develop Contingency Plan
 Contingency Plan
Refine and Execute Production Support
Plan
Execute Change Plan
Production Readiness Review
Obtain Cutover Approval
Refine and Execute Legacy Retirement
Plan
Perform Training Program Evaluation
Deliver End-User Training
Complete Process and Organizational
Changes
Execute SAP Going-Live Check
Develop Technical Operations Manual
Setup and Install Production
Environment(s)
Configure and Execute System
Administrator Functionality
Establish Service Level Agreements
Risk Assessment Measurement
Conduct Peer/Solution/Technical Reviews

Produce and Deliver Program Management
Status Reports
Final Preparation Sign-off



EI Toolkit Reference
Document version 1.0, June 2003
Last validated: June 2003







Commence Initial Production Support
Activities (which occur prior to go-live)
Organization Change Plan
Execute Cutover/Conversion Plan
Legacy Retirement Plan



Training Program Evaluation
Trained End Users
Process and Organizational Changes
Performed
Going Live Check Assessment
Technical Operations Manual
Installed Production System(s)

Tuned SAP System



Service Level Agreements
Revised Risk Assessment
Solution/Technical Review Findings
Reports
Completed Status Report
Updated Issues Log
Go-Live Approved
7
EITK0304
Key Implementation Activities and Deliverables:
AcceleratedSAP
Table D.2-6 Go-Live and Support Key Activities and Deliverables
Key Activities
Deliverables
 Provide Production Support (Help Desk)
 Production Support (Help Desk)
Established
 Execute Daily Operation Support and
 Production-Ready Systems Environment
Administration
 Optimize System Tuning
 Validate Live Business Process Results
 Business Process Results
 Monitor Transactions, Interfaces and
 System tuning and Procedural Updates
Procedures
 Execute Ongoing Security Administration
 Security Administration
 Provide Ongoing Training Support
 Execute Ongoing Training Support
 Develop Continuous Improvement Plan
 Continuous Improvement Plan
 Produce and Deliver Program Management  Completed Status Report
Status Reports
 Updated Issues Log
 Post Implementation Review
 Post Implementation Findings Reports
EI Toolkit Reference
Document version 1.0, June 2003
Last validated: June 2003
8
EITK0304
Download