Risk Management Policy Statement & Strategy

advertisement
Appendix 1
LONDON BOROUGH OF CROYDON
Practical Guide to Risk
Management
Contents
Page Number
Section 1: Importance of Risk Management
3

What is Risk Management?
3

Why risk management is important?
4

Benefits of successful risk management
4
Section 2: Roles & Responsibilities

5
What is your role?
6
Section 3: Risk management process
6

Five steps of risk management
7

Opportunity Risk Management
14

Risk Register
14

JCAD RISK management system
15
Section 4: Corporate Governance and internal control
17

Performance
17

Partnerships
17

Project Management
18
Appendixes

Appendix 1: Risk Management Policy Statement & Strategy
19

Appendix 2: Role of Risk Champions and Risk Support Staff
21

Appendix 3: Risk Management Steering Group: Terms of Reference22

Appendix 4: Categories of Risk
24

Appendix 5: Impact and Likelihood Classification
25
2
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012

Appendix 6: Example risk register
27
3
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
Section 1:
This document describes the London Borough of Croydon risk management
strategy and policy.
The aim of the guidance is to ensure all staff employed by London Borough of
Croydon:

have a common understanding about the purpose, structure and approach to
risk management;

are aware of their roles and responsibilities;

can identify, minimise and manage risk effectively and;

are able to undertake risk management in an open, supportive and
transparent environment.
What is Risk Management?
Risk can be defined as the effect of uncertainty on objectives” ISO 31000 Risk
Management (Guide 73)
Risk can be a negative ‘threat’ or positive ‘opportunity’ or a deviation from the
expected, and that risk is often described by an event, a change in circumstances
or a consequence.
The risk is assessed in respect of the combination of the likelihood of something
happening, and the impact which arises if it does actually happen.
Historically, risk management has been regarded primarily as threat management.
However the management of opportunities is also important because it will
maximise the benefits to the organisation if a course of action is taken. Some
opportunities present themselves as pure chances but others need to be sought out
by the organisation. This indicates that in order to maximise benefits, organisations
needs to be proactive in identifying and managing potential threats as well as
looking for possible opportunities.
(See more detail in Section 2)
The effective management of risk therefore is very important in the public sector.
Croydon Council defines risk management as a process by which risks are
identified, evaluated and controlled. Good risk management will also help us to
explore and take opportunities as they are identified.
Risk management is relevant at any level of the organisation. At the operational
level it ensures the ongoing continuity of business and the mitigation of physical
hazards or incidents.
4
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
At the strategic level it is concerned with achieving high level corporate objectives
and long term goals. An operational risk is concerned with localised priorities and
areas.
Why is risk management is important?
.
The risks associated with the business need to be managed to ensure the
achievement of objectives. Government requires public services to promote best
practice in service delivery and risk management as an integral part of good
business practice.
However risk management is not just a statutory requirement but also an essential
element of good management. Effective risk management will have several benefits
for the organisation.
Benefits of successful risk management
•
Enhanced performance: by identifying barriers to achievement there is an
increased likelihood of achieving corporate objectives. More efficient use of
resources; reduction in business interruptions; added value across service
areas and improved service delivery that matches organisational priorities.
•
Become less risk averse and hence more innovative. There is a smarter
awareness of where opportunities are and ability to exploit them fully within
our overall priorities.
•
Improve business planning through a risk based decision making process
•
Reduction in legal liabilities: risk management can highlight areas of high
risk where the council needs to follow set procedures to ensure the likelihood
of non-compliance and therefore legal liability is reduced.
•
Better outcomes for residents as risk management focuses you to consider
potential impacts if the risk where to occur for the council and the wider
Borough. Therefore if risks are successfully managed this could lead to
improved customer relations and increased public satisfaction.
•
Improved insurance management: reduced cost of insurance premiums
and number/level of claims and reduced uninsured losses.
5
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
Section 2:
Roles and Responsibilities
The practical guide defines what roles and responsibilities different employee
groups have for the effective management of risk within the organisation. In the
London Borough of Croydon, the Deputy Chief Executive & Executive Director of
Resources & Customer Services and Deputy Leader (Statutory) and Cabinet
Member for Housing, Finance & Asset Management, has overall responsibility for
embedding and championing risk management throughout the Council.
All Employees, Managers and Councillors are expected to have a level of
understanding of how risk and opportunities could affect the performance of the
Council and should regard the management of those risks and opportunities as part
of their everyday activities.
In addition key individuals such as the Risk management team and Risk Champions
have specific leadership roles for risk management within the Council. It is also
important that the management of risk is regarded when setting up the strategic
objectives and long, medium and short term goals for the organisation.
Roles and responsibilities of risk management in detail:

Members: to oversee the effective management of risk throughout the
Council; to challenge the extended management team accountable on the
effectiveness of risk management.

Extended Management Team: to ensure that the Council manages risk
effectively through the development of a comprehensive risk management
strategy; to monitor high level strategic risks by receiving the corporate risk
register on a regular (typically monthly) basis.

Risk management team: to support the council and its departments and
services in the effective development, implementation and review of the risk
management framework; to provide adequate training to other groups of the
Council to enable them to carry out their responsibility in risk management.
To provide guidance on risk issues such as strategic and operational risk
management.

Risk Champions: to champion the cause of risk management within each
department, particularly at the strategic level; to take personal responsibility
for ensuring that the risk management objectives set out in the policy are
achieved and to encourage a risk aware culture in all areas of the
organisation. (See Appendix 2 for detailed roles and responsibilities)

Risk Management Steering Group: to develop a formal framework to assist
the Council to manage risks to the achievement of the Council's strategic
priorities and the delivery of services to the community. (See Appendix 3)

Audit Advisory Committee: responsible to review the corporate risk register
periodically; to endorse risk management annual action plan which outlines
the strategic direction of risk management within the council.
6
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012

Risk Owners: Directors and Heads of service: responsible for identifying,
assessing, managing and reviewing all risks assign to them. To ensure that
all risks are added where appropriate to the corporate risk register and that
those which regarded as red risks are reported to DMT regularly.

Departmental Management Teams: to ensure that risks are identified and
managed effectively in each service area within the agreed risk management
strategy; to review strategic risks in timely fashion.

Corporate Project Office: to devise and implement effective, proportionate
and auditable project and programme management standards, This can
include guidance on risk management in projects and programmes. For
further information please refer to CPO Intranet Homepage

Project Managers: identify and assess risks at the outset of any new or
proposed projects as part of the project initiation document. Timely review of
risks throughout the life cycle of the project.

Partnership Managers: identify, assess and manage key risks which may
prevent successful joint working and the achievement of agreed objectives.
The continual review of risks within the partnership should be encouraged.

All Employees: to manage risks effectively in their jobs and report hazards
and risks to their service managers.
Section 3: Risk Management Process
Risk management should be a part of normal business processes and should
become the basis for a number of activities such as:

Setting strategic aims→ Corporate Plan

Setting business objectives →Service Plan

Part of budget process→ Budget Planning Cycle

Project planning & key project stages→ Project Initiation Document, Project
Highlight Reports

Governance arrangement for→ Local Strategic Partnership (LSP) reporting
partnership working
The Risk Management Process is not just a scoring or measurement process, it
requires judgements and informed decisions to be made. It is best done as a group
exercise such as a workshop to involve those who understand the key issues in
delivering a service, and to form a shared understanding regarding the key risk
areas, the level of risk and the control measure actions that are required.
7
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
The five steps of risk management:
THE ORGANISATION’S STRATEGIC
OBJECTVES
RISK
IDENTIFICATION
MONITORING
AND REVIEW
RISK ANALYSIS
RISK
MANAGEMENT
RISK
PRIORITISATION
8
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
Step 1: Risk Identification
The first step of the risk management process involves the identification of risks.
However prior to this step the organisation has to make sure that it’s corporate
objectives, priorities and/or targets have been clearly communicated and
understood. These are identified in the corporate plan, the sustainable community
strategy and departmental service plans which should outline specific objectives and
expected outcomes.
Risks can be identified in three categories: strategic, operational and governance.
 Strategic risks (or opportunities) are most likely to affect the performance and
delivery of business services; e.g. change in legislation may affect Authorities
ability to deliver a service or create a new income generating stream.

Operational risks (or opportunities) are primarily concerned with continuity of
service delivery. Strategic and operational risks are not mutually exclusive
and a risk might escalate from an operational risk to a strategic risk; for
example a fire in school is an operational risk which may be related to the
strategic risk around the possible breakdown in relationship between the
Local Authority and schools.

Governance risks (or opportunities) relate to risks which might affect the
organisation’s reputation, decision making ability and the effectiveness of its
strategy; e.g. risk of employee fraud.
(See Categories of Risk in detail in Appendix 4).
There are several methods which can be used to identify risks such as document
examination, flow chart analysis (to identify interdependencies within a business),
physical surveys, workshops and interviews with key personnel. The method used
will depend on the nature of risk; e.g. physical/operational risks may be identified
through physical surveys plus flow chart analysis while strategic and governance
risks may be better identified through interviews or workshops.
Once risks are identified, a risk register should be created. Croydon Council uses a
specific risk management information system called JCAD RISK as a database to
record risks which can then form a Risk Register Report. This database allows other
useful information to be added such as the risk owner, cost analysis, proximity of
risk. The system and the risk register will be described in the section: JCAD RISK
management system.
9
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
Step 2: Risk Analysis and Rating
The next step is to define the identified risk in detail. Croydon Council use a 2 part
risk scenario: Likeihood and Impact. Risk refers the possible event which you
would want to mitigate if it was a threat or maximise if it was an opportunity. Impact
refers to the consequence the risk may have on the service/project/partnership/
wider council and the Borough.
Examples:
 Operational risk example:
Risk: Fire in Taberner House, resulting in the evacuation of central complex
Impact: Unable to provide council services including face to face services in
Access Croydon.

Strategic risk example:
Risk: Failure to meet local area agreement targets due to uncoordinated
strategies.
Impact: Not achieving desired outcomes for the benefit of local residents and
damage to the Council’s reputation for failing to meet LAA targets.
Once risks have been analysed they need to be rated in order to prioritise the risks
that pose the greatest threat (or opportunity). This is done by looking at both the
likelihood and impact of the risk. Impact means thinking about the effect of the risk if
it should become a reality (what would the consequence be?). Likelihood is looking
at the possibility of the risk materialising.
Croydon has adopted a 5 by 5 likelihood and impact matrix as it shown below to
assess the value of the risk. (Link to One Page Guide to Risk Management & Risk
Scoring)
10
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
Assessing Likelihood
5. Almost Certain
4. Likely
3. Possible
2. Unlikely
1. Rare
Assessing Impact
5. Extreme
4. Very High
3. Medium
2. Low
1. Negligible
The impact of the risk is calculated by using the following Impact Classification
Matrix. This helps users in Croydon to decide the seriousness of the impact.
Impact/Benefi
t
Classification
Treat or Opportunity
Service
Financial
disruption/im
Loss/Gain
provement
Reputation
both positive
and negative
Threat
Failure to provide
statutory
service/meet legal
obligations
Multiple civil or
criminal suits.
Litigation, claim or
fine above £5m
People
Extreme
5
Total failure of
service/ major
service
improvement
Over £5m
National
publicity >
than 3 days..
Very high
4
Serious
disruption to
service/service
development
£500k- £5m
National public
or press
interest.
Litigation, claim or
fine £500k - £5m
Serious injury.
Permanent
disablement of one
of more clients/staff
Medium
3
Disruption to
service/positiv
e service
delivery
change
£50k -£500k
Local public/
press interest
Litigation, claim or
fine £50k - £500k
Major injury to
individual
Low
2
Some minor
impact on
service –
positive or
negative
£5k
- £50k
Contained
within
department
Litigation, claim or
fine £5k - £50k
Minor injuries to
several people
Negligible
1
Annoyance but
does not
disrupt service
< £5k
Contained
within
unit/section
Litigation, claim or
fine less than £5k
Minor injury to an
individual
Fatality of one of
more clients/staff
The likelihood of risk occurring is estimated following these guidelines below:
Likelihood Classification For An Event Occurring In A Given Year:
5. Almost Certain–Expected to occur in most circumstances (> 80%).
4. Likely - Will probably occur in most circumstances (51% - 80%).
3. Possible – Fairly likely to occur (21% - 50%).
2. Unlikely - Could occur at some time (6% - 20%).
1. Rare May occur only in exceptional circumstances (0 – 5%).
Once the level of impact and likelihood has been identified a risk score can be
calculated using the following equation:
Risk Rating (Scoring) = Impact * Likelihoo
(See Impact and Likelihood classification document in Appendix 5)
11
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
Step 3: Risk Prioritisation
Once the risk rating has been calculated the risk owner can prioritise between the
different risks to ensure the correct risks receive immediate attention.
Croydon Council uses the following risk prioritisation matrix:
Risks with the highest score are treated as priority and require immediate
management and monitoring.
The following table shows how risks with the different score levels are managed:
Green rated risks are deemed an acceptable tolerance level.
20-25
9-19
1-8
Those risks requiring immediate management and monitoring
Those risks requiring management and monitoring but less time
critical
Those risks which require ongoing monitoring
The above process will be automatically calculated when using JCAD risk software
12
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
Step 4: Risk management
Once the high level identification and prioritisation of risk areas has been completed
control measures need to be identified which will hopefully mitigate the risks.
It is important to keep in mind that most risks cannot be eliminated altogether which
means a crucial part of risk management is making judgements about what level of
risk is acceptable.
There are four categories of response that the Council can take:

Transfer: the organisation can decide to shift the responsibility or burden for
the loss to another party or to share risks in part or full with another
stakeholder. The main method of transferring risk is through contract
management for example insurance or outsourcing a service to a third party.
However it should be noted that in reality it is not possible to transfer a risk
entirely, as the statutory obligation to provide certain services remain with the
local authority even if the delivery of the service is outsourced. Therefore
legal liability risks cannot be completely transferred.

Treat: put procedures and controls in place to reduce the likelihood and/or
impact of the risk.
For example the impact of fire risk in Taberner house can be treated by
applying control measures such as: fire alarms, regular fire drills, sprinkler
systems.

Terminate: eliminate or avoid the risk by ceasing the activity or choosing an
alternative approach or process which makes the risk no longer relevant.

Tolerate: the organisation may decide to retain risks, monitor the situation
and bear losses out of normal operational costs.
An informed decision is made to accept the likelihood and impact of a particular risk.
The reason for this action may be due to the council’s ability to manage the risk
might be limited or the cost of taking any action may be disproportionate to the cost
of the risk occurring.
As a part of the process of applying control measures the risk owners should weigh
up the cost/benefit of investing in control measures. If the cost of a control measure
exceeds the benefits of mitigating the risk, then maybe a reasonable judgement can
be made to tolerate the risk. It should be noted however that the cost of a risk
occurring is not just financial but can also be reputational, effect the wellbeing of
staff or be result in a claim or fine. Therefore the probability and impact of the risk
should be evaluated when making this decision. In practice the expectation is that
managers will continue to develop and implement control measures until the risk has
reached a score which is considered to be acceptable.
In Croydon the JCAD RISK system enables the risk owners to capture the cost of
the resources required to set in place the control measure(s).
13
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
Step 5: Monitor and Review
The monitoring of risks is key to the successful management of risks. Departments
are responsible for the effective monitoring of their risks, risk assessments, controls,
assurances and the accuracy of risk entries and related material on JCADrisk. The
risk landscape needs to be regularly monitored since no risks remain static.
Departments should review their risks at least once on a monthly basis for hgh rated
risks and on a 3 monthly basis for all other risks. This is to ensure new risks are
identified, and existing ones are continually reassessed.
Croydon Council’s review process:
•
Audit Advisory Committee review red risks
•
Cabinet Members receive risk reports in their portfolio
•
Leadership review red risks on a regular basis
•
Red risks are reviewed to EMT on the regular basis as a part of Corporate
Performance Dashboard.
•
Departmental Management Teams review high level risks regularly and all
risks at least annually
•
All reports to Members should include a section on Financial and Risk
Assessment Considerations, where any potential strategic, operational or
governance risk which may prevent the achievement of objectives should be
identified.
In addition to the review process outlined above, the entire risk register should be
reviewed annually, possibly during the strategic planning period.
Project, Programme and Partnership risks should also be reviewed by the
appropriate stakeholders on a regular basis. This is current set as 30 days for high
rated risks, 3 months for mediums rated risks and annually for low rated risks. The
reminder system within the JCAD system.is set for these parameters.
The JCAD RISK system provides support for the review process by sending
automatic e-mail reminders to the risk owners when a review is required.
14
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
Opportunity Risk Management
The effective management of opportunities is also an important feature of risk
management. Opportunities should be managed in the same way as negative risks
The five step Risk Management Process outlined above can also be applied to
opportunities which may arise. This is particularly relevant for projects, programmes
and partnership working.
Example of an opportunity:
Opportunity: Working with another local authority to deliver a future strategic
programme.
Impact: Delivering the programme in partnership will lead to:
- economies of scale savings
- reduction in administrative support
- sharing of best practice across both authorities
Opportunities and the risk of missed opportunities should be entered on the
departmental risk register in the same way you would a threat. Control measures
should aim to maximise the opportunities and/or minimise the threat of missing
opportunities.
The Risk Register
The information identified during the risk management process should always be
recorded. Most organisations use a risk register to do this. A risk register provides a
central point to log all of the identified risks against business objectives and to
capture detailed information about each risk such as brief description, its likelihood,
its impact, control measures used, name of risk owner etc.
The purpose of a risk register is to collect sufficient information to enable risk
response planning and subsequent control. Croydon Council uses an online
database called JCAD RISK.
Croydon Council’s risk register contains the following headings:







Risk reference: identifies every risk entered into the risk register
Risk Scenario: describe the risk and identifies the possible impact.
Assigned to: identifies the risk owner (this has to be only one person and not
a group of people)
Existing controls: details the existing control measures already
implemented.
Current risk rating: shows the risk rating which is calculated taking the
existing control measures into consideration.
Future control measures: identifies future actions which are planned for the
future in order to control the risk further.
Future risk rating: shows the possible target risk rating which can be
achieved if future control measures are applied.
15
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
Disruption to
service
delivery,
increased
spending on
temporary staff
John
Smith
Construct a
Business
Continuity
plans in
place for the
department
4
3
12
Future
Control
Measures
Future
Risk
Rating
Total
A flu pandemic
results in 25%
of the
workforce
absent at any
one time
Current Risk
Rating
Likelihood
Impact
Existing
Controls
Impact
Risk
Assigned
to
Total
RCS000
Risk Scenario
Likelihood
Risk
Ref.
Impact
Example of Croydon Council’s Risk Register:
Cross
training of
personnel
3
3
9
This template while in Excel follows the same format as used in the JCAD RISK.
Link to Risk Register Template (Excel) (or see Appendix 6: Risk Register Template)
JCAD RISK management system & risk escalation
The JCAD RISK system allows both the recording of individual risks and information
about them, and also provides the facility to produce reports which can be used to
manage risk both individually and collectively.
This tool is user-friendly and contains all the functionality required to record and
dynamically monitor, audit, analyse, and manage by exception the entire risk
register.
The system also sends reminder emails to all users when the review of the risk
assigned to them is due which makes the review and monitoring process more
effective. It ensures that if action required alternative measures can be applied to
manage risks on time. Red risk (score 20 and above) are reviewed monthly at EMT.
These risks are in turn reported to leadership and to audit advisory committee.
Departments are also advised to review high amber (score 15 and above) monthly
and all other risks at least annually.
By these means a formalised escalation
process for any corporate risk is provided for within the risk management policy and
strategy of the Council.
When using the JCAD RISK system it is possible to link identified risks to different
corporate objectives, identify the nature of risks and assign them to the relevant risk
category.
The system also has a powerful reporting facility which makes monitoring and
review easier. The most commonly used report is the Croydon Risk Register which
displays risks by department, project or programme (see example below) and the
Risk Status Report which gives an overview of the changes in rating over a period of
time and the number of control measures applied.
16
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
JCAD risk can be accessed via the web https://croydon.jcadrisk.com/
and is used by risk owners such as directors or heads of service, project,
programme and partnership managers and Cabinet Members. This version allows
users to view risks and control measures and if authorised change, add or withdraw
risks and control measures and generate basic reports such as the risk register and
dashboard.
Internal Audit conduct a programme of risk based auditing and therefore use the
JCAD Risk system to inform their annual audit programme. In addition most audit
reports contain a risk management level of assurance in appendix of the reports.
This includes assurance around the risk register and any recommendation.
17
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
Section 4: Corporate Governance and Internal Control
Risk management in any organisation should form an important part of its corporate
governance and internal control process. Corporate governance can be defined as
the ongoing activity of maintaining a sound system of internal control to ensure that
effective management systems, including financial monitoring and control system
have been put in place to protect assets, earnings capacity and the reputation of the
organisation. A sound system of internal control and corporate governance will help
the Council to achieve its corporate objectives and lead to improved performance.
Performance
All risks in the JCAD system have been linked to the high level corporate visions
and strategies. This allows easy identification of risks which may impact key
performance areas.
The Council’s Performance Dashboard assesses performance in delivering the
corporate priorities and the targets that underpin them within Corporate Plan and
Departmental Service Plans. It is a strategic level report which provides a ‘birds eye
view’ of how the council is performing. The report is submitted quarterly and
monitors the Council’s National Indicators, Finances, Projects, Customer Indicators,
HR indicators and Risks. It highlights areas which are underperforming so they can
be dealt with promptly. Currently this report is reviewed by EMT.
Risk management is also important when the organisation tries to achieve its
strategic and medium term goals. Partnerships play an increased role in achieving
strategic goals and medium terms are usually addressed through programmes and
projects. Croydon Council have already achieved great results in developing an
integrated risk management approach for its significant partnerships and working
towards accomplish a similar strategy for major projects as well.
Partnerships
It is important that public sector organisations work together to maximise their
service delivery across the borough. The government also places emphasis to
improve partnership working between local authorities, other public bodies business,
community groups and the voluntary sector. In order to achieve these goals
organisations need to commit resources, in terms of officer time or direct financial
funding to develop and deliver the desired outcome. Part of this process should
involve identifying the risks and opportunities which might prevent or help maximise
the partnership to achieve it’s objectives.
Croydon Council developed a joint risk management framework with their significant
partners via the Local Strategic Partnership (LSP) using the Council’s risk
management system.
The Council has key streams each with its own partnership manager:
18
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
Each key stream has developed a joint risk register which was developed during a
multi-agency risk workshop. A good example of effective partnership management is
the use of joint partnership risk registers.
It is recommended that a joint risk register approach is developed for all major
partnerships which the council enters into. Facilitation of this process can be
conducted by the Risk Management Team.
Project management
Effective project management is crucial for an organisation’s success because any
organisation can only achieve its goals through the delivery of some fundamental
projects. It was estimated by the Employee’s Organisation for Local Government
that up to 70 % of local authority work is project based. This indicates that
organisations spend a significant amount of resources on project work.
Efficient project management will ensure that projects are delivered at the right time,
within budget and to the agreed scope. In order to minimise losses and maximise
chances of success risks (threats and opportunities) associated with project have to
be recognised and managed.
Advantages of effective risk management in projects:









Prioritise actions and management focus
Support decision making
Identify required contingency plans
Improve communication
Team involvement
Governance compliance
Minimise overspend
Reduce the change for overruns
Improve the quality of service delivery
In Croydon Council all corporately significant projects have risk registers on the
Council’s JCAD risk management system.
A council wide project management framework is in place. Details can be found on
the Councils intranet and using this link;
Link to CPO Homepage
This involves the creation of a Corporate Programme Management Office to support
and provide information to all project and programme boards.
The Council’s well developed project risk management approach also includes the
consideration of possible opportunities that relate to major projects.
19
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
Appendix 1
Risk Management Policy Statement & Strategy
Croydon Council (the Council) is aware that risks will always arise from its
various duties and functions. Some risks will always exist and will never be
eliminated.
However, the Council recognises that it has a responsibility to manage its
significant business risks and supports a structured and focused approach to
managing risk by approval and support of the Council's risk management strategy.
In this way the Council will better achieve its corporate objectives and enhance the value of
the services it provides to the community whether directly or via its many partnership
arrangements.
The Council's risk management strategy's objectives are to:
Identify corporate and operational risks
Assess the risks for likelihood and impact
Identify mitigating controls
Allocate responsibility for the mitigating controls
The Council maintains and reviews a register of its corporate business risks linking them to
strategic business objectives and assigning ownership of each risk.
The Executive Director of Resources & Customer Services and the Cabinet Member for
Economic Development & Corporate Services will jointly champion and take overall
responsibility for imbedding risk management throughout the Council.
The Council will embed risk management in its corporate business processes including:
Strategic planning
Financial planning
Policy making and review
Performance management
Partnership working
Project management
Reports to support strategic policy decisions and project initiation documents will include a
risk assessment.
Croydon will also consider positive risks (opportunities) as well as negative risks (threats) in
relation to its business planning.
Members
All members will receive risk management awareness training in relation to their role. In
addition the member committee with responsibility for risk management reviews reports
quarterly and takes appropriate action to ensure that corporate business risks are being
actively managed including detailed reporting from officers on key risks. Cabinet Members
will be trained on, and given access to the Council's corporate risk management software.
20
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
Officers
All staff will be given appropriate training and guidance to enable them to take responsibility
for managing risk within their own working environment. All named risk owners have access
to the corporate wide risk register system and will be required to update and maintain their
entries on the system. The risk management strategy will allow for a formalised route for the
escalation of risk with risks rated as ‘high amber’ (rated 16) escalated from departments to
the extended management team on a quarterly basis and ‘red risks’ (rated at 20+) escalated
to extended management team on a monthly basis and reported onwards to members in the
form of leadership and the audit advisory committee.
Councillor Dudley Mead - Deputy Leader (Statutory) and Cabinet Member for Housing,
Finance & Asset Management
Jon Rouse, Chief Executive
Nathan Elvery, Deputy Chief Executive and Executive Director of Resources & Customer
Services
21
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
Appendix 2
Role of Risk Champion and Risk Support Staff:
-
To act as the main contact for their department on risk management matters,
and ensuring that corporate information and requirements are communicated
through out the department.
-
To represent their department at the Risk Management Steering Group.
-
To provide support on risk management to directors, heads of service and
other managers across the department.
-
To promote the benefits of risk management across the department.
-
To identify their department’s risk management training needs and reporting
these to the Risk and Insurance Team.
-
To maintain on behalf of the Department, a risk register that complies with
corporate guidelines and includes encouraging the identification of new risks.
-
To act as the main contact for risk management with regards to the reporting
requirements to EMT, Leadership, Cabinet Members and Audit Advisory
Committee.
-
Risk Champions to update the departmental risk register on behalf of other
Directors.
22
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
Appendix 3
Risk Management Steering Group: Terms of Reference
The Risk Management Steering Group will develop a formal framework to assist the Council to
manage risks for the achievement of the Council's strategic priorities and the delivery of services
to the community.
The Group will consist of risk champions from every department (at second tier level), a
representative from Internal Audit, Head of Risk Management & Insurance, Risk management
team and other seconded staff as required from time to time.
Aims and objectives
The Group will:
1. Draw upon the recognised risk management skills from across the Council and from
external advisors or consultants to provide a more cohesive service to the corporate
body and service departments.
2. Encourage a comprehensive approach to the management of hazards and risks in
order that these can be assessed at the outset of any project, during the delivery of
a service and also where adaptations need to be made because of experience
and/or the emergence of new technology, legislation or trends.
3. Maintain a formal framework for the management risks in respect of strategic and
operational hazards linking back to strategic business objectives. This process to
consider positive risks (opportunities) as well as negative risks (threats).
4. Provide advice and guidance in relation to partnership risk.
5. Develop methods to inform the Council's Management Team and Members of the
total cost of risk, including costs of crime and other insured and uninsured losses.
6. Analyse and collate departmental reports on self-assessment of risks and every
quarter to produce a summary for the Council Management Team and Members.
This analysis will identify hazards and risks that affect a number of departments and
the corporate body. It will also forward the departmental reports to the Council
Management Team.
7. Make recommendations to the Council's Management Team as to how:
o
generic and cross-departmental hazards and risks identified by departmental risk
assessments can be addressed corporately;
o
Legislative changes and trends affect the Council and ensure that, where action
is required, it is carried out in a timely and effective manner.
8. Take responsibility for embedding risk management in corporate business
processes including strategic planning, financial planning, policy making and review
and performance management.
9. Train and support the Group members as 'champions' for risk management within
their own departments.
23
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
10. Further develop existing and new sources of partnerships with external agencies or
other bodies to assist the Council and its staff, the community and visitors to
Croydon by managing hazards and risks.
11. Introduce training on risk management to Group members, departmental teams and
throughout the Council by harnessing existing methods of training and, where
required, developing new training schemes.
12. Design and maintain a system to disseminate information throughout the council and
establish a corporate intranet site containing guidance and information to enable
colleagues to access information.
13. Disseminate information and guidance to departments, Council Management Team
and Members on regular basis, including information on initiatives, developments
and action plans.
14. Provide advice via 'champions' and other means on any changing requirements in
the reporting or assessment of risk, arising from HM Treasury requirements, Audit
Commission, or reports of private or public sector best practice.
15. Review the completeness and accuracy of risks included in the corporate risk
register through discussions with relevant individual managers.
16. Report to the Chief Executive, the Council Management Team and Members on the
management of risk throughout the Council.
It is acknowledged that it is the responsibility of every department to implement Croydon
Council's Risk Management Policy and support the Group in its activities, and that departments
have responsibility and accountability for identifying, assessing and managing the risks that
could impact on their areas of activity.
Councillor Dudley Mead - Deputy Leader (Statutory) and Cabinet Member for
Housing, Finance & Asset Management
Jon Rouse, Chief Executive
Nathan Elvery, Deputy Chief Executive and Executive Director of Resources &
Customer Services
24
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
Appendix 4
STRATEGIC
(external drivers)
CATEGORIES OF RISK
Source of Risk
Risk Examples
Infrastructure
Functioning of transport, communications and utilities infrastructure. The impact of
storms, floods, pollution. Development in Borough render infrastructure
inadequate.
Effects of changes of government policy, UK or EC legislation, national or local
political pressure or control, meeting the administration’s manifesto commitments.
Effects of changes in demographic, residential and social trends on ability to
deliver objectives. Excess demands on services.
Capacity to deal with obsolescence and innovation, product reliability,
development and adaptability or ability to use technology to address changing
demands.
Affecting the competitiveness (cost & quality) of the service &/or ability to deliver
Best Value and general market effectiveness.
Satisfaction of: citizens, users, central and regional government and other
stakeholders regarding meeting needs and expectations.
Environmental consequences of progressing strategic objectives (eg in terms of
energy efficiency, pollution, recycling emissions etc.)
Politics & Law
Social Factors
Technology
Competition &
markets
Stakeholder-related
factors
Environmental
Finance
OPERATIONAL
(internal drivers)
Human Resources
Contracts
Partnerships
&
Tangible Assets
Environmental
Processes &
professional
judgements
GOVERNANCE
Integrity
Leadership
Policy & strategy
Data & information for
decision making
Risk Management
Associated with accounting and reporting, internal financial delegation and control,
failure to prioritise or allocate budgets. Insufficient resources or lack of investment.
Recruiting and retaining appropriate staff and applying and developing skills in
accordance with corporate objectives, reliance on consultants, employment
policies, health & safety, and absence rates. Migration of staff to contact centre.
Failure of contractors to deliver services or products to the agreed cost &
specification. Issue surrounding working with agencies. Procurement, contract and
relationship management. Overall partnership arrangements, eg for pooled
budgets or community safety. PFI, LSVT and regeneration. Quality issues.
Inadequate building/assets. Security of land and buildings, safety of plant and
equipment, control of IT hardware. Issue of relocation.
Relating to pollution, noise or the energy efficiency of ongoing operations.
Errors and omissions associated with professional judgement. Inspection
compliance, project management, performance management, benefits system,
environmental management system (EMS). Not achieving targets, failure to
implement agendas and service failure. Also risks inherent in professional work.
Fraud and corruption, accountability and openness, legality of actions and
transactions and limits of authority.
Reputation, publicity, authority, democratic renewal, trust and identity.
Ensuring clarity of purpose and communication. Policy planning, community
planning and monitoring and managing overall performance. Not seeking or
following advise from the centre.
Data protection, data reliability and data processing. Information and
communication quality. Effective use and interpretation of information. Control of
data and information. E-government and service delivery. Inappropriate and/or lack
of software. Storage issues.
Incident reporting and investigation, risk measurement, evaluation and monitoring.
Internal Control and Business Continuity Issues.
Link to Guide to risk categorisation
25
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
Appendix 5
Impact and Likelihood Classification
Impact Classification
RISK IDENTIFICATION & ASSESSMENT
Treat or Opportunity
Impact/Benef
it
Classification
Service
disruption/impr
ovement
Financial
Loss/Gain
Extreme
Total failure of
service/ major
service
improvement
Over £5m
5
Very
high
4
Serious
disruption to
service/service
development
£500k- £5m
Medium
3
Disruption to
service/positive
service delivery
change
Low
2
Negligibl
e
1
Threat
Reputation
both
positive
and
negative
National
publicity >
than 3
days..
Failure to provide
statutory service/meet
legal obligations
People
Multiple civil or criminal
suits. Litigation, claim or fine
above £5m
Fatality of one of more
clients/staff
National
public or
press
interest.
Litigation, claim or fine
£500k - £5m
Serious injury.
Permanent disablement
of one of more
clients/staff
£50k £500k
Local
public/
press
interest
Litigation, claim or fine £50k
- £500k
Major injury to individual
Some minor
impact on
service –
positive or
negative
£5k
- £50k
Contained
within
department
Litigation, claim or fine £5k £50k
Minor injuries to several
people
Annoyance but
does not disrupt
service
< £5k
Contained
within
unit/section
Litigation, claim or fine less
than £5k
Minor injury to an
individual
Select the highest category to score the risk.
Likelihood Classification For An Event Occurring In A Given Year
5. Almost Certain–Expected to occur in most circumstances (> 80%).
4. Likely - Will probably occur in most circumstances (51% - 80%).
3. Possible – Fairly likely to occur (21% - 50%).
2. Unlikely - Could occur at some time (6% - 20%).
1. Rare - May occur only in exceptional circumstances (0 – 5%).
Risk Rating/Scoring = Impact*Likelihood
RISK MANAGEMENT
Prioritisation of Risks
20-25
9-19
1-8
Those risks requiring immediate management and monitoring
Those risks requiring management and monitoring but less time critical
Those risks which require ongoing monitoring
Approaches that can be adopted for the management of risk:

Eliminating or avoiding: Changing or abandoning goals specifically associated with the risk in question, or
choosing alternative approaches or processes that
make what was a risk no longer relevant.
26
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012

Risk sharing: Sharing risks in part or full with another stakeholder who could be
involved solely to facilitate risk treatment.

Reducing the probability: Changing approach identifying causal links between threat and impact, or
causes of threat, and intervening to mitigate occurrence,
acting to reduce the threat.

Reducing the impact: Developing contingency plans for responding to the threat if it occurs, even if other
steps have been taken to minimise risk.
27
Version 2
Owner: Malcolm Davies
Last Updated: October 2011
Next Review Date: April 2012
APPENDIX 6
Risk Register Template (Excel)
RISK
REFERENCE
RISK
SCENARIO
RISK
IMPACT
ASSIGNED
TO
EXISTING
CONTROLS
CURRENT RISK RATING
IMPACT
LIKELIHOOD
TOTAL
FUTURE
CONTROL
MEASURES
FUTURE RISK RATING
IMPACT
LIKELIHOOD
TOTAL
Download