Questions to answer for a proper quote - NO CHANGE

advertisement
ADCC, Inc. STRUCTURED CABLING SYSTEMS - PRE-BID AND JOB COMPLETION CHECK LIST
Customer Name: _________________________________________ Date of Site Visit: ___________
Site address:________________________________________________________________________
City, State, Zip:______________________________________________________________________
Contact name:_______________________________________________________________________
Contact phone number:________________________________________________________________
Pre-bid completed by:_________________________________________________________________
Job Completion completed by:__________________________________________________________
Number of Buildings: ________________ Number floors per building: ________________________
Number of Closets per building: ____________
Per Floor ________________________________
Number of Copper locations to be cabled _________ Number cables per outlet ________ Avg. Wire
Run length _____
Installation is: Copper Only _________
Fiber Only __________
Copper & Fiber ___________
Type of fiber and strand count (s)___________________ Length (s)___________________________
Installation is to conform to the EIA/TIA Standards and NEC Code for:
Category 5e_____ Category 6_____T568A _____ T568B _____ Fiber ______
1.
Check here if Conduits are used for horizontal distribution
______
Conduits are no longer than 100 feet, with two or fewer 90 degree bends between pulling points
______
Inside bend radius is no greater than 6 times the conduit diameter
2.
(10 times for conduits 2” and over).
______
Check here if Ceiling Space is used for horizontal distribution
______
All horizontal cables are plenum rated.
______
Cables are not laying directly on ceiling tiles or T-bars.
______
1
Cable support devices (J hooks, rings) are in use and are spaced no more than 5 feet apart.
______
3.
4.
5.
Twisted Pair Cable Terminations
Outlets are installed right side up.
______
Cables are not wrapped or twisted around mounting collars.
______
Correct connectors used (T568A/T568B).
______
The jackets are maintained right up to the connectors.
______
Pairs are terminated in the correct positions.
______
Check here if Patch Panels are installed.
______
Cables are properly routed and dressed.
______
Jackets remain up to edge of connecting blocks.
______
Pairs are terminated in the correct positions.
______
Twists are maintained, and are undistorted to the point of termination.
______
Check here if 110 Patch Panels are installed.
______.
Cables are terminated in the correct positions.
______
Pairs are terminated in the correct positions.
______
There is no visible conductor insulation damage
______
Pair twists are maintained up to the point of termination.
______
Bends in pairs are tight and conductors are not spread apart.
______
Check here if any Consolidation Points exist.
______
There is only one consolidation point or Multi-User TO to any horizontal link.
______
Labeling is complete and accurate at all work area outlets, all telecommunication closets, and in all
equipment rooms.
______
Check here if intra-building Backbone Cables are installed.
______
All twisted pair backbone cable shields are properly grounded at both ends.
______
Unshielded backbone cables are tie-wrapped to a 6AWG insulated wire at regular intervals and the
6.
6AWG wire (coupled bonding conductor) is properly grounded at both ends.
______
Check here if inter-building Backbone Cables are installed.
______
All pairs in twisted pair inter-building backbone cables are equipped with approved gas tube or
solid state over voltage protection at both ends.
______
(Make sure no digital modules for analog use are installed)
Ground lugs on protector panels are properly connected to an acceptable ground with 6AWG
7).
conductors.
______
All twisted pair cable shields are properly grounded at both ends.
______
Metallic elements of fiber optic cables are properly grounded at both ends.
______
Hanging supports are within 5 ft. (1.5 meters) centers.
______
Cable spans between hanging supports exhibit visible sag as an indication of acceptable tension.
______
Visible sag is seen between hanging supports.
______
2
Tie wraps are tight enough to snugly hold cables together, but do not deform cable jackets.
______
Cable bends in outlet boxes are no tighter than 0.87 inch
______
Cable folds are no greater than 90 degrees.
______
Cables in outlet boxes are not longer than 1 foot.
______
In high-density patch panel terminations, cables are routed such that 12 cables are terminated on
the left side of the panel and 12 cables are terminated on the right side of the panel.______
8.
9.
Modular Outlets
Conductors are seated according to color chart on the outlet.
______
Caps are seated securely on top of the conductors.
______
Jacket is maintained as close as possible to the outlet.
______
Open loops are not in evidence in outlet channel.
______
Pair twist is maintained right up to the point of termination.
______
Fiber Terminations
All fiber cables are properly routed and secured.
______
At all termination locations, fiber slack is properly stored, without exceeding minimum bend
10.
radius.
______
Fiber connectors have been properly installed.
______
Testing
All pairs in all twisted pair cables have been tested for continuity and position.
______
Documentation of the test results is available.
______
All connector zed fibers have been tested for continuity, position and loss.
______
Documented loss requirements and test results available for each fiber
______
Each fiber’s measured loss meets or exceeds the design requirements.
______
Additional information about site:
3
Download