JRCruz Corp. v. Dep't of Design and Construction OATH Index No. 123/07, mem. dec. (Dec. 20, 2006) Petitioner sought review of the Department’s denial of a claim for incurred costs due to an unanticipated subsurface condition. The Board found that the condition was foreseeable and manageable had petitioner used due diligence in investigating the area of construction. _________________________________ -2- NEW YORK CITY OFFICE OF ADMINISTRATIVE TRIALS AND HEARINGS CONTRACT DISPUTE RESOLUTION BOARD In the Matter of JRCRUZ CORP. Petitioner - against DEPARTMENT OF DESIGN AND CONSTRUCTION Respondent _________________________________ MEMORANDUM DECISION KARA J. MILLER, Administrative Law Judge/Chair KENNETH JOCKERS, Deputy General Counsel, Mayor's Office of Contracts JACK MINOFF, Prequalified Panel Member INTRODUCTION Presently pending before the Contract Dispute Resolution Board ("CDRB" or "the Board") is the petition of JRCruz, Corp. (“JRCruz"). JRCruz is seeking compensation from respondent, the Department of Design and Construction (“DDC”) in relation to contract number 20040224184 (“the contract”). JRCruz seeks $318,019.18 for additional costs related to an unforeseen subsurface condition. DDC denied the above claim on June 22, 2005. Petitioner appealed this denial to the Comptroller on October 12, 2005. The Comptroller denied JRCruz’s claim on May 26, 2006. In accordance with Procurement Policy Board (“PPB”) rules and Article 27 of the above contract, JRCruz invoked the jurisdiction of this Board to resolve the contract dispute at issue. The Board heard oral arguments on November 9, 2006, at which time the record was closed. After considering the parties' submissions, the Board denies JRCruz’s claim for the reasons provided below. BACKGROUND This dispute arises out of a contract between JRCruz and DDC to reconstruct the combined sewers on Fort Hamilton Parkway and 92nd Street in Brooklyn, which included installing a concrete chamber (“the Chamber”). The contract required petitioner to inspect the area before making a bid, and to make a thorough investigation before imposing a method of -3construction (Information for Bidders § 8(A)). The contract also required petitioner to avoid damage to existing structures and maintain an 11-foot traffic lane for the duration of construction (Addendum No. 4 § 1.06.29(11)(2)). Included in the pre-bid materials provided by DDC was Contract Drawing Sheet 4, “Plan and Profile of Ft. Hamilton Parkway,” (“Sheet 4”) which depicts a 54-inch sewer that clears the chosen location of the Chamber by approximately 5 feet. Sheet 4 states, “accuracy of the utility data is not guaranteed, nor is there any guarantee that all existing utilities and substructures, whether functional or abandoned, are shown on this map” (Contract Drawing Sheet 4). Also included in the pre-bid materials was Contract Drawing Sheet 1 (“Sheet 1”), which states that “The exact location of existing sewers is unknown, but is plotted from the best available information. However, accuracy is not guaranteed. The contractor shall determine the exact location.” (Contract Drawing Sheet 1). On April 1, 2005, during the construction of the Chamber, petitioner discovered that the 54-inch brick sewer is approximately 7 feet northeast of the location shown on Sheet 4. The sewer encroaches 28 inches into the proposed location of the Chamber. This discovery halted all work. As of the date of the argument before this Board, petitioner claimed to have incurred $318,019.20 in extra work costs associated with the mistaken sewer location (Pet. Book 1). Petitioner sought reimbursement for the extra work, claiming that the discrepancy in the location was an unanticipated subsurface condition, which materially differed from that depicted in the contract documents and from what could be determined by reasonable investigation. DDC denied petitioner’s request for reimbursement finding that the subsurface condition did not materially differ from the contract drawings. Furthermore, the drawings contained disclaimers as to their accuracy and petitioner was contractually required to do its own investigation of subsurface conditions. DISCUSSION As a general proposition, “clear, complete writings should generally be enforced according to their terms.” W.W.W. Associates, Inc. v. Giancontieri, 77 N.Y.2d 157, 162, 565 N.Y.S.2d 440, 443 (1990). Contract provisions requiring a contractor to do independent investigations, coupled with specifications stating contract drawings are not definitive, have been held to be valid. Owners Realty Management & Construction Corp. v. Bd. of Education, 192 A.D.2d 471, 596 N.Y.S.2d 416 (1st Dep’t 1993) (claim for additional compensation denied where -4bidders were warned terms of the contract were only approximate quantities and each bidder was responsible for making a pre-bid inspection). Contractors must not necessarily rely solely on contract plans. Due diligence requires contractors to examine contract project specifications and investigate areas and conditions relevant to construction. Barash v. Bd. of Education, 226 A.D. 249, 235 N.Y.S. 30 (1st Dep’t 1929), aff’d, 255 N.Y. 587 (1931). The contract in question repeatedly required the contractor to do its own investigation of the area prior to bidding and prior to choosing a method of construction. Indeed, one section of the contract places an affirmative duty on the contractor by stating, The Contractor admits [it] has carefully examined the location of the work . . . has inspected the public records of various City Departments having cognizance and control of the City’s water pipes, conduits and sewers, and [it] has made further personal inspection and investigation as [it] deemed proper to determine the correctness of the information so obtained . . . All of the aforementioned investigations must be performed prior to the start of construction and the cost thereof shall be deemed included in the bid for all items of work. DDC Standard Sewer Specifications § 1.06.13. The Contract also contains provisions that bar claims for damages for extra work resulting from reliance on the accuracy of public records, reports, or information. Specifically, the contract states, …the City does not ensure accuracy of such records, reports or information, and [the contractor] agrees [it] will not make any claims against the City for damages or extra work caused or occasioned by [its] relying upon such records, reports or information furnished by any City Department or any companies, either as a whole or in part. DDC Standard Sewer Specifications § 1.06.13. Respondent argued that that contract explicitly places the onus on the contractor to conduct a thorough inspection. Moreover, the express disclaimers regarding the accuracy of the drawings should be given great weight. Where a construction contract between the government and an individual describes existing conditions affecting the work to be done, as well as an exculpatory clause relieving the government of liability, and where the contract requires personal inspection of the contract site, liability may attach to the government only if the actual conditions are not represented and (1) inspection would have been unavailing to reveal the incorrectness of the representations, or (2) the representations were made in bad faith. Grow Construction Co., Inc. v. State of New York, 56 -5A.D.2d 95, 98, 391 N.Y.S.2d 726, 728, (3d Dep’t 1977); Foundation Co. v. State of New York, 233 N.Y. 177, 185, 135 N.E. 236, 238 (1922); American Wrecking Corp. of New Jersey v. Dep’t of Sanitation, OATH Index No. 229/04, mem. dec. at 7 (Dec. 22, 2003). Petitioner asserted that prior to construction, it investigated all of the available information regarding the sewer in accordance with the contract, including examining available “as built” records for city-owned facilities on the project site, taking measurements of all existing surface features, and investigating elevations and locations of inlet and outlet sewers. There were no discrepancies between petitioner’s individual findings and the contract documents. Thus, petitioner argued that a reasonably prudent contractor would conclude the contract drawings were accurate. Petitioner further denied responsibility for determining the exact location of the sewer, given the sewer’s extreme depth below street level and the fact that the sewer was active. Because the sewer was built on a radius and is approximately 46 feet deep, petitioner maintained that it was impossible to ascertain the sewer’s exact location. The only method of determining the exact location of the sewer that petitioner was aware of, was excavating an exploratory test hole to uncover the sewer. Petitioner argued that this would not have been the typical or expected procedure for a contractor to follow because of the expense and its belief that a test hole would have threatened the contractual obligation not to damage any of the surrounding structure, so it was not done. See Addendum No. 4 § 5.39.4. Respondent argued that petitioner did not conduct a proper inspection. The contract language was intended to require a pre-bid survey of the premises, including inspection of traffic conditions, physical parameters, and other surface conditions. Respondent asserted that petitioner should have conducted a more thorough post-bid investigation, which would include learning the exact location of the sewer before formulating its construction plans (See Contract Drawing Sheet 1). Respondent indicated that another method for calculating the location of the sewer, other than excavating a test hole in the pre-bid process, would have been appropriate under the circumstances. This alternative method would involve lowering equipment and men into the manhole to physically measure the sewer. Respondent argued that despite the unpleasant nature and expense of conducting such tests, this is a known method of measuring a sewer built on a radius. When questioned as to the feasibility of the above testing procedure, petitioner -6maintained it was unfamiliar with such a method. Petitioner contended that it did not know that this was a viable option because DDC never advised them about it. It did not, however, ever inquire of DDC or any other City agency as to how it could have properly measured the curved sewer. The contract put petitioner on notice of his duty to acquire all information pertinent to construction, stating that, Bidders . . . will be conclusively presumed to have full knowledge of any and all conditions on, about or above the site relating to or affecting in any way the performance of the work to be done under this contract which were or should have been indicated to a reasonably prudent bidder. Information for Bidders § 8(A). Petitioner was aware that the sewer was curved prior to bidding on the contract. It should have known that it was impossible to determine the sewer’s exact location by measuring the distance between surface objects. Nevertheless, petitioner failed to address this issue, and sought no guidance from DDC on the matter. Petitioner was not constrained by its pre-bid inspection. Indeed, it had an additional opportunity to conduct a more thorough inspection post-bid, but failed to do so. Accordingly, the mistaken location of the sewer was not an unanticipated subsurface condition, it was an undetermined condition that upon further inspection could have been ascertained. Respondent did not guarantee the location of the sewer, instead it placed the burden of inspection and calculation on the contractor. See DDC Standard Sewer Specifications §1.06.13; Contract Drawing Sheet 1. A reasonably prudent contractor would have established the exact location of the sewer before attempting to install the Chamber. -7Accordingly, petitioner’s claim for compensation for extra work is denied. ALL CONCUR. KARA J. MILLER Administrative Law Judge/Chair December 20, 2006 APPEARANCES: TREACY SCHEAFFEL MOORE & MUELLER Attorneys for Petitioner BY: GARY J. MUELLER, ESQ. MICHAEL A. CARDOZO, ESQ. NYC Corporation Counsel Attorneys for Respondent BY: BARBARA PEABODY, ESQ.