TRIANA CONCEPT DESIGN STUDY AA 4831 SPACECRAFT SYSTEMS II DR. I. MICHAEL ROSS DESIGN TEAM LT Rick Behrens LT Christian Dunbar LT Michael Larios Capt Darin Powers 10 JUNE 1998 2 TABLE OF CONTENTS I. INTRODUCTION ..................................................................................................................... 7 II. MISSION DESIGN .................................................................................................................. 9 A. LAUNCH VEHICLE .................................................................................................................. 9 1. Launch Vehicle Selection .................................................................................................. 9 2. Launch Vehicle Integration .............................................................................................. 10 B. ORBITOLOGY....................................................................................................................... 11 1. Initial Conditions .............................................................................................................. 11 2. L1 Transfer Trajectory ..................................................................................................... 11 3. Halo Orbit ......................................................................................................................... 12 V REQUIREMENTS ........................................................................................................................ 13 1. First Estimate ................................................................................................................... 13 2. SWINGBY Estimate ......................................................................................................... 14 V Budget ................................................................................................................................ 15 4. Propellant Budget ............................................................................................................ 15 5. Kick Motor Sizing ............................................................................................................. 15 D. MISSION TIMELINE ............................................................................................................... 16 III. SPACECRAFT DESCRIPTION............................................................................................. 19 A. 1. 2. 3. 4. 5. 6. 7. 8. 9. B. 1. 2. 3. C. 1. 2. 3. 4. 5. STRUCTURE AND MECHANISMS SUBSYSTEM ......................................................................... 19 Initial Design .................................................................................................................... 19 Design Approach ............................................................................................................. 19 Requirements .................................................................................................................. 20 Primary Load Bearing Structure ...................................................................................... 21 Main Payload Deck & Bay Dividers ................................................................................. 22 Outer Drum ...................................................................................................................... 22 Mechanisms..................................................................................................................... 23 Equipment Placement ..................................................................................................... 23 Structure Weight Estimate ............................................................................................... 23 THERMAL CONTROL SUBSYSTEM ......................................................................................... 24 Requirements .................................................................................................................. 24 Final Design ..................................................................................................................... 25 Design Approach ............................................................................................................. 25 ELECTRICAL POWER SUBSYSTEM......................................................................................... 29 Requirements .................................................................................................................. 29 Final Design ..................................................................................................................... 29 Design Approach ............................................................................................................. 30 EPS Purpose ................................................................................................................... 30 Power Sources ................................................................................................................ 30 a) Phase 1: Launch and Transit ..................................................................................................... 31 b) Phase 2: On-orbit ....................................................................................................................... 34 c) Power Distribution, Regulation and Control ............................................................................... 40 D. COMMUNICATIONS SUBSYSTEM............................................................................................ 41 Requirements .................................................................................................................. 41 Final Design ..................................................................................................................... 41 Evolution of Design .......................................................................................................... 42 Link Analysis .................................................................................................................... 43 E. PROPULSION SUBSYSTEM ........................................................................................... 48 1. Requirements .................................................................................................................. 48 2. Components .................................................................................................................... 48 3. Subsystem Operation ...................................................................................................... 51 F. ATTITUDE CONTROL SUBSYSTEM ......................................................................................... 52 1. 2. 3. 4. 3 1. Requirements .................................................................................................................. 52 2. Final Design ..................................................................................................................... 52 3. Design Approach ............................................................................................................. 53 a) b) c) d) e) G. H. IV. Normal Operation ...................................................................................................................... 53 Total Moment of Inertia ............................................................................................................. 53 Characterizing Roll Motion. ....................................................................................................... 54 Momentum and Torque Requirements. ..................................................................................... 54 Reaction Wheel Size ................................................................................................................. 56 COMMAND AND DATA HANDLING SUBSYSTEM ....................................................................... 56 FLIGHT AND MISSION SOFTWARE ......................................................................................... 57 1. Final Design ..................................................................................................................... 57 2. Requirements .................................................................................................................. 57 3. Evolution of Design .......................................................................................................... 57 MISSION PAYLOADS ........................................................................................................... 59 A. EARTH SENSOR................................................................................................................... 59 1. Requirements .................................................................................................................. 59 2. Final Design ..................................................................................................................... 59 3. Design Approach ............................................................................................................. 61 B. ALTERNATE SENSORS ......................................................................................................... 64 1. Requirements .................................................................................................................. 64 2. Recommendations ........................................................................................................... 64 a) Geocorona ................................................................................................................................ 64 b) Solar Wind................................................................................................................................. 64 V. COST ..................................................................................................................................... 65 A. B. C. REQUIREMENT .................................................................................................................... 65 ESTIMATED TOTAL COST ..................................................................................................... 65 COSTING APPROACH ........................................................................................................... 66 a) b) c) d) e) f) VI. Parametric Cost Model Description ........................................................................................... 66 The Triana Cost Estimation ....................................................................................................... 67 Space Segment Costs............................................................................................................... 68 Launch Segment Costs ............................................................................................................. 70 Ground Segment Costs ............................................................................................................. 71 Operations and Support Costs .................................................................................................. 71 APPENDIX ............................................................................................................................ 73 A. SPACE SHUTTLE PRICING ALGORITHM .................................................................................. 73 V BUDGET ................................................................................................................................... 74 C. SWINGBY MISSION FILE .................................................................................................... 76 D. PROPELLANT MASS ESTIMATION .......................................................................................... 77 E. KICK MOTOR COMPARISON .................................................................................................. 78 F. STRENGTH AND RIGIDITY ESTIMATIONS ................................................................................ 79 G. STRUCTURE SUBSYSTEM W EIGHT ESTIMATE ........................................................................ 82 H. PROPELLANT TANK SIZING ................................................................................................... 84 VII. REFERENCES ...................................................................................................................... 85 4 ACKNOWLEDGEMENTS The Naval Postgraduate School TRIANA Design Team would like to thank the following individuals and corporations for their willing and energetic assistance. Ball Aerospace & Technologies Corp Aerospace Systems Division Lockheed Martin Athena Government Marketing Mr. William P. Carter, Director Lockheed Martin NASA Civil Space Programs Mr. Tim Malloney NASA Goddard Space Flight Center Mr. Jay Smith Ms. Susie Smith Mr. Tom Stengle Mr. Dave Weidow Satellite Power Corporation Swales Composite Structures, Inc. 5 6 I. INTRODUCTION This design project was completed as part of the AA 4831, Spacecraft Systems II, course at the Naval Postgraduate School, which is one if the capstone courses in the Space Systems Operations curriculum. The stated goal of the course is to complete the systems analysis and design of a generic spacecraft, and thereafter apply the "tools of the trade" to a selective project. The TRIANA Earth Observing mission was selected as that project because it represents a relevant, real-world mission that was within scope of the course. TRIANA's prime mission is to provide "real time", HDTV color images of the sunlit disk of the Earth for educational outreach opportunities. Images from the spacecraft will then be made available to the world through the Internet. The TRIANA concept was initially conceived by the Vice President of the United States, the Honorable Albert Gore. NASA had posted a Request for Information (RFI) concerning the concepts for educational outreach and the results of a preliminary feasibility study. This information provided the initial requirements used in the study and bounded many of the subsequent system trades. TRIANA Requirements include: 100 kg (dry), 175W Spacecraft Launched to the Solar Lagrangian Point, "L-1" Planned five year operational mission Total mission cost less than $50M, including launch and operations Free worldwide, 24-hr access to the updated image via the Internet Potential Users: General Public, Educators, Students, Non-profit Groups, Weather Forecasters 7 8 II. A. MISSION DESIGN Launch Vehicle 1. Launch Vehicle Selection Launch vehicle selection process began with a survey of currently available U.S. expendable launch vehicles and the Space Transportation System (i.e., Space Shuttle). Four launch vehicles were then selected for further consideration: Space Shuttle, Lockheed Martin Athena II (formally the LLV2), Orbital Sciences Taurus XL, and McDonnell Douglas Delta II (7925). The Space Shuttle option is very attractive considering cost as estimated in Appendix A. However, current NASA practices discourage Shuttle missions from performing nonessential satellite operations, other than Get-Away-Specials, when other commercial means are available. Also, the availability of cargo bay space in the Space Shuttle during the next two years is unlikely with the scheduled Space Station missions. The next best option is the Athena II based upon performance margin, payload volume, and cost. The Taurus XL is a close alternative and the Delta II was found to be much more capable than necessary and correspondingly too expensive. Calculations for both the Space Shuttle and Athena II options were carried through V estimates and considered for kick motor sizing. For launch vehicle comparison, the Spacecraft Dry Weight was taken as the design goal of 100 kg. Estimating 50 kg for propellant yielded a Loaded Spacecraft Weight of 150 kg. Initially from the RFI and then later validated from V calculations, the use of a Morton Thiokol STAR 30C Motor (626.1 kg) was added for a total of 776.1 kg. Finally an adapter weight of 15 kg was estimated for a final Boosted Weight of 791.1 kg. Table II-1 Launch Vehicle Comparison Launch Vehicle Space Shuttle Athena II Taurus XL Delta II (7925) Payload Volume Dia / Height 4.6m / 18.3m 1.98m / 4.64m 1.37m / 3.3m 2.8m / 4.2m 9 Cost Payload to LEO Margin $10M $24M $26M $45M 23090 kg 1300 kg 1389 kg 5045 kg 96% 34% 43% 84% 2. Launch Vehicle Integration For the Space Shuttle option, in addition to the spacecraft and kick motor, consideration of the Space Shuttle’s cargo bay must be taken into account. A system similar to the STS PAMD system depicted below must be used consisting of a cargo bay cradle assembly, spin table and separation system, and a special payload attach fitting (PAF) that attaches to the forward restraints of the cradle assembly. Figure II-1 Launch Vehicle Integration For the Athena II option, the Model 92 Payload Fairing (1.98m x 4.64m) was estimated to provide adequate volume for the spacecraft and kick motor. The standard Model 24 Payload Adapter (attached to the Model 66 Payload Adapter) with a 591mm diameter bolt circle was chosen for the STAR 30C kick motor interface. An option to consider is to have Lockheed Martin provide the STAR 30C kick motor and interface as part of the Athena II contract. This would increase launch costs by about $3M (cost of the kick motor alone is about $1.5M) but would reduce design load of the spacecraft to just the spacecraft-kick motor interface. 10 B. Orbitology 1. Initial Conditions The initial orbital parameters depend on the launch vehicle and date of launch. For example, the inclination relative to the ecliptic plane is directly related to the time of year and must be accounted for in the transfer trajectory design. For the Space Shuttle case, a typical parking orbit is taken to be a 28.5 inclined, circular orbit at 300 km altitude. The estimation for the Athena II provided a 28.5 inclined, circular orbit at 1200 km altitude. Considering the Athena II’s launch margin, it may be possible to use “dog legs” to make a plane change at LEO to save energy for the kick motor. In either case, precise timing is required to ensure proper phasing of the transfer orbit. An additional consideration is the benefit of performing a swingby of the Moon to pick up additional energy or adjust orbital planes. A lunar swingby would require additional phasing constraints that would also limit launch windows. 2. L1 Transfer Trajectory The solar Lagrangian point L1 lies on the Earth-Sun line where the forces of gravity from the two bodies are nearly equal, approximately 1.5M km from Earth (about four times the distance to the Moon). In Keplarian, two-body motion, a body’s angular velocity is greater the shorter the radius of the orbit. However, the L1 point orbits the Sun with the Earth, so it’s angular velocity is actually less than the Earth’s rather than greater. Restricted three-body approximations must be used to design the transfer trajectory to take this and other unique properties of this point into account. The actual interplanetary trajectory TRIANA will use to get to solar L1 will be the same as that used by the Solar and Heliospheric Observatory (SOHO) spacecraft in July 1995. The transfer trajectory will begin with a large tangential burn of the STAR 30C kick motor that will place the spacecraft in a hyperbolic escape trajectory relative to the Earth. Anticipate several mid-course corrections will be necessary to correct for kick motor dispersion errors. The actual orbit insertion maneuvers are very complex and involve both radial and normal components to the burns as well as tangential. The transfer will take approximately 106 days to complete. 11 3. Halo Orbit The Earth-Sun L1 Lagrange point is actually unstable. If TRIANA were to be precisely stationed there, any disturbance force would cause the spacecraft to steadily drift away. Frequent small corrections would be required to maintain a stable orbit. That is why TRIANA will follow a “halo” orbit about the L1 point just as SOHO. The circular acceleration of the halo orbit compensates for the gravitational difference between the Sun and Earth. However, the halo orbit is also unstable so periodic orbit maintenance is required. The SOHO spacecraft performs orbit maintenance maneuvers every 2 to 3 months. Following the SOHO mission profile, the halo orbit will have a period of 180 days. This allows for smooth Sun-spacecraft-Earth velocity changes and also avoids direct conjunction with the Sun that would make receiving telemetry from the spacecraft very difficult. Also note that the halo principally lies in a plane that is perpendicular to the Sun-Earth line. However, the Earth’s orbit is not perfectly circular so the position of L1 actually moves along the Sun-Earth line during the course of Earth’s obit. This relates to a third dimension to the halo orbit along the Sun-Earth line. There is much ongoing research in the area of restricted three body problems and halo orbit trajectory design. A depiction of the SOHO orbit schematic is shown below. Figure II-2 SOHO Orbit Schematic 12 C. V Requirements 1. First Estimate The mission calls for an interplanetary trajectory from Earth to the solar Lagrangian point L1. For the first estimate, a patched conic approach was taken with a hyperbolic escape transfer from Earth’s sphere of influence (SOI) and a heliocentric Hohmann transfer from Earth orbit to L1 orbit. Vse Vse Vsl1 Vsa Vsp Vs1 Vs2 = Earth velocity wrt Sun = L1 velocity wrt Sun = Apogee velocity of transfer orbit wrt Sun = Perigee velocity of transfer orbit wrt Sun = Hohmann transfer insertion velocity = L1 insertion velocity Vs1 Vsa L1 Vsl1 SUN EARTH Vsp Vs2 Figure II-3 Heliocentric Hohmann Transfer The Vs1 calculated for the heliocentric Hohmann transfer insertion was used as V, the velocity relative to the Earth at the edge of the SOI (~145 Earth radii), for the hyperbolic escape transfer calculations. The Vs2 calculated for L1 insertion was used in the estimation of propellant requirements. Within the Earth’s SOI, hyperbolic escape trajectories were considered with perigee of the hyperbola based on typical Space Shuttle parking orbits and estimated performance of the Athena II launch vehicle. V requirements for both launch vehicle cases were used for kick motor sizing. See Appendix B for details. 13 V Vei Vep V Ve1 Ve1 = Initial s/c velocity wrt Earth = Hyperbola perigee velocity wrt Earth = s/c escape velocity wrt Earth = Hyperbolic escape insertion velocity Vep Vei EARTH Figure II-4 Hyperbolic Escape Transfer 2. SWINGBY Estimate The V requirements were then refined from the use of SWINGBY, Release 98.01, a mission analysis and trajectory design computer program that was provided by the Flight Dynamics Division of NASA’s Goddard Space Flight Center. A mission file, listed in Appendix C, was developed to estimate the V requirements for the major trajectory events such as transfer orbit insertion, mid-course corrections, and halo orbit insertion maneuvers. Below is a depiction of the transfer: Figure II-5 SWINGBY Transfer 14 3. V Budget From the above calculations and estimates for stationkeeping based upon correspondence with NASA’s Goddard Space Flight Center, the V budget below was calculated: Table II-2 V Budget Event Transfer Orbit Insertion (Shuttle / Athena II) Mid-Course Corrections Halo Orbit Insertion Stationkeeping (5 yr Mission Life) 4. Patched Conic 3201 m/s / 3006 m/s SWINGBY 3180 m/s / 2982 m/s 60 m/s 385 m/s 20 m/s 434 m/s 20 m/s Propellant Budget From the above V budget, the required mass of propellant necessary for the mission life of the spacecraft is estimated. The final dry mass of the spacecraft is taken to be the design goal of 100 kg. Assuming a simple anhydrous hydrazine (N 2H4) propulsion system with a conservative specific impulse of 220 seconds, the required propellant mass is calculated to be 24.04 kg. Considering the level of confidence in the V estimations, a propellant margin of 50% was deemed necessary to then make the design propellant mass equal to approximately 50 kg. See Appendix D for details. 5. Kick Motor Sizing Again, considering the typical parking orbit of the Space Shuttle and estimated performance of the Athena II launch vehicle with the V required for the hyperbolic escape trajectory, a comparison of the Thiokol STAR 27E, STAR 30C, and STAR 37XFP kick motors was done. Loaded Spacecraft Weight was estimated as before to be 150 kg with an additional adapter weight of 15 kg was added to the corresponding weights of the motors to calculate the effective V capability. See Appendix E for details. The table below lists the performance margins of the three motors in each launch vehicle case. 15 Table II-3 Kick Motor Margin Comparison Launch Vehicle Space Shuttle Athena II V Required 3201 m/s 3006 m/s STAR 27E -19% -12% STAR 30C 15% 20% STAR 37XFP 27% 32% As readily seen, the STAR 27E does not produce enough energy for the mission. A performance margin of 15% in the Space Shuttle case for the STAR 30C kick motor is deemed more than adequate for this phase of the mission and is considered to have validated earlier assumptions and the RFI’s initial feasibility study. D. MISSION TIMELINE The major phases for the TRIANA mission are the launch, transfer orbit insertion, cruise, and halo orbit insertion. The mission begins with the launch of either the Space Shuttle or an Athena II launch vehicle from the Eastern Test Range. The spacecraft is initially turned OFF throughout the launch phase. In the Space Shuttle case, the spacecraft will typically be placed into a 28.5 inclined, circular parking orbit at approximately 300 km altitude. When scheduled, the spacecraft will be spun to 60 rpm on it’s spin table and separation springs will release to impart 0.76 m/s velocity with respect to the Shuttle. Once clear, the STAR 30C kick motor will fire for approximately 51 seconds to inject the spacecraft into the transfer trajectory. In the Athena II case, launch trajectory will be tailored to achieve a 28.5 inclined, circular orbit at approximately 1200 km altitude. Following the third stage burn, the Athena II’s Orbital Assist Module (OAM) will orient the spacecraft in the proper direction, spin it up to 60 rpm, and then separate. The STAR 30C kick motor will then fire as in the Shuttle case. Approximately one minute after the STAR 30C burns out, the spacecraft will separate from the kick motor. The spacecraft will then be turned ON. On-board system checks will be conducted, inertial position determined, and telemetry established via the low gain omni-direction antennas. Approximately 30 minutes later, the thrusters will be fired to de-spin the spacecraft and re-orient to the cruise attitude with the aid of the reaction wheel system. The solar panels will 16 then be deployed. Expect that the first major mid-course correction will occur approximately 1.5 days later to account for launch vehicle/kick motor dispersion errors. Halo orbit insertion will occur approximately 105 days later. While during the cruise phase, the payload and high gain antenna will be checked out and operated. Once established in the Halo orbit, mission operations will commence. Anticipate that periodic orbit maintenance and momentum dumping of the reaction wheel system with the thrusters will be necessary to account for secular disturbance torque accumulation and inherent halo orbit instability. Design life is for 5 years, though with propellant margins and hopefully good health of the spacecraft, a considerably prolonged actual mission life will be possible. 17 18 III. A. SPACECRAFT DESCRIPTION Structure and Mechanisms Subsystem 1. Initial Design The initial design for the structure subsystem consists of a cylindrical kick motor adapter attached to a conical support structure that supports both the propellant tanks and main payload deck. The outer drum of the spacecraft is a 1m x 1m octagonal cylinder. Four solar arrays attach to the base of the outer drum and are supported by spars connected to the adapter-conical support structure interface. Graphite epoxy honeycomb sandwich is used for most of the spacecraft structure based upon its light weight, and high strength/stiffness properties. Figure III-1 TRIANA Cut-Away 2. Design Approach A survey of recent spacecraft missions was made and used to make early decisions regarding spacecraft form. The Lunar Prospector mission was found to be very similar to TRIANA in scope and its spacecraft design was used as a starting point. Also, the NRAD Clementine mission was found to be very useful in early concept exploration. Consideration of the estimated size of the payload telescope, required antenna diameter, and estimated volume of propellant tanks initiated the design process. Consideration of standard kick motor interfaces and launch vehicle payload fairing envelopes helped bound the dimensions of the thrust tube and load bearing structures. Multiple iterations were accomplished as more knowledge of power and propulsion requirements became known. Extensive use of AutoCAD enabled more precise 19 design of dimensions and configuration layout. Mass and moments of inertia of individual and collective components were also estimated with AutoCAD. 3. Requirements The structure must maintain TRIANA’s critical dimensions and alignments during all phases of operation including ground handling, test, storage, launch, and on-orbit operations. The table below summarizes the loading and frequency environment for both launch vehicles: Table III-1 Launch Vehicle Constraints Launch Vehicle Space Shuttle Athena II Load Envelope Axial / Lateral +6.7 g / +5.9 g -2.0 to +8.0 g / 2.5 g Fundamental Frequency Axial / Lateral 13 Hz / 13 Hz 30 Hz / 12 Hz (45-70 Hz) The payload envelope of the Model 92 Payload Fairing with the Model 24 and 66 Payload Adapters for the Athena II was taken as the most limiting case. As depicted below, TRIANA with the STAR 30C kick motor attached has plenty of clearance. Figure III-2 Payload Fairing Clearance 20 Additional constraints that need to be addressed in future iterations of design besides load factors and low frequency vibration are the spectral density of random vibration, acoustics, shock, thermal stress, pressure venting, and contamination effects. The material properties of composites vary depending on the fiber fraction, fiber type selected, textile weave type, and individual material properties of the fibers and matrix materials. Typical properties of graphite epoxy composites are listed below: Table III-2 Typical Composite Properties Property Elastic Modulus (Gpa) Tensile Strength (MPa) Compressive Strength (MPa) Fine Grained Graphite 10-15 40-60 110-200 Unidirectional Fibers 120-150 600-700 500-800 3-D Fibers 40-100 200-350 150-200 Initial analysis considered only compressive/tensile loads for strength and natural frequency for rigidity. From commercial market survey of composite honeycomb panels and specifications of recent spacecraft such as Lunar Prospector, assumed core thickness of 1.1 cm and face sheets of 1 mm. See Appendix F for details. Even using the most conservative estimates for Elastic Modulus and Strength, the required thickness of the face sheets is only 0.03554 mm. This is largely due to the small mass of the spacecraft. The real driver then is the availability, cost, and ease of manufacture/fabrication of the designed structures. 4. Primary Load Bearing Structure Kick motor adapter is 14 cm height x 61 cm diameter, cylindrical tube made of 1.3 cm thick graphite-epoxy honeycomb. An additional 1 cm lip is added for integration with the kick motor separation system. Load bearing structure is 48.7 cm height x 61 cm inner diameter and 100 cm outer diameter conical tube. Four circular cutouts are made for support of the propulsion tanks. Material is also made of 1.3 cm thick graphite-epoxy honeycomb. 21 Figure III-3 Primary Load Bearing Structure 5. Main Payload Deck & Bay Dividers The main payload deck is a 100 cm diameter, circular panel that is attached to the top of the load bearing structure and supports the majority of the internal equipment. The bay is further divided by four 50 cm x 50 cm square panels that together with the deck provide approximately 2.785 m2 of mounting area. The deck and dividers are made of graphite-epoxy honeycomb. Figure III-4 Main Payload Deck & Bay Dividers 6. Outer Drum The outer drum is a 1 meter height x 1 meter diameter, octagonal, cylindrical drum. The base of the drum is attached to the kick motor adapter at eight points with four spars that provide additional support to the solar arrays and thruster modules. The mid-section of the drum is attached to the top of the load bearing structure at eight points near the center of each rectangular panel. The top panel of the drum is a 1 meter diameter, octagonal panel with a 22 cm diameter cutout for the payload telescope. It is attached to the drum at eight points and provides stability for the telescope and support for the antennas and thruster modules. 22 Figure III-5 Outer Drum 7. Mechanisms The only mechanisms are the solar panel hinges. Estimate that a hook latch arrangement with redundant torsion springs could be utilized to keep the solar panels in the stowed position. The solar panels would then be deployed with pyrotechnic release devices. Further analysis on the loads and torsion of the hinges and joints is necessary. 8. Equipment Placement Initial placement of internal equipment was based roughly on balancing center of mass of the spacecraft. Additionally, we endeavored to mount subsystem components in the same payload bay for ease of access during testing and integration. Additional analysis of the thermal requirements of each component is necessary. Figure III-6 Equipment Placement 9. Structure Weight Estimate To estimate weight, a figure of merit was calculated assuming 1 mm graphite-epoxy face sheets on 11 mm honeycomb core. Approximate densities for the materials were obtained from Swales Composite Structures of Newark, DE and are 1937.59 kg/m 3 for the face sheets and 23 32.036 kg/m3 for the honeycomb core making the figure of merit equal to 325 kg/m 3. This very conservative estimate includes the weights of adhesive, fittings, and potting. See Appendix G for details. The table below lists structure subsystem weights by component. Table III-3 Structure Subsystem Weights Component Kick Motor Adapter Load Bearing Structure Main Payload Deck Payload Bay Dividers Outer Drum Top Panel Support Spars Weight 1.27 kg 4.02 kg 3.31 kg 4.07 kg 14.18 kg 3.33 kg 0.4 kg Total 30.58 kg Generally, the structure subsystem is over-designed for strength and stiffness. Estimate that the areas of greatest concern will be the stress about the fittings and attachment points. Finite element analysis is necessary to properly determine shearing energy and failure modes. There is great potential for weight and size reduction of the spacecraft. B. THERMAL CONTROL SUBSYSTEM 1. Requirements The most restrictive temperature ranges are listed below. Since the propellant tanks will be controlled separately using MLI, the overall temperature bounds are from 5 to 20 °C. Table III-4 Temperature Ranges by component. Component Temperature Range °C Source Electronics 0 to 35 SMAD p. 410 Sensor 0 to 20 Kodak Batteries 5 to 20 SMAD p. 410 Propellant 7 to 53 SMAD p. 410 24 2. Final Design TRIANA will use a passive thermal control subsystem consisting both of gold multilayer insulation and optical solar reflectors (OSR’s) on the body of the spacecraft and localized use of multi-layer insulation (MLI) for components with higher temperature limits. Below is a plot of one cycle of the spacecraft’s equilibrium temperature using the combination of gold MLI and OSR. Figure III-7 TRIANA's Temperature Profile Since TRIANA will be continuously exposed to solar radiation, the spacecraft will always be at equilibrium temperature. For that reason, a mixture of gold MLI and quartz-over-silver OSR’s were used for thermal control. The propulsion end (bottom) of the spacecraft would absorb the majority of the solar radiation while the sensor/coms end (top) would receive none. The table below depicts the placement of the thermal control materials on the spacecraft. Table III-5 Thermal control composition. 3. Design Approach Spacecraft equilibrium temperatures were determined by estimating the solar flux at L1 and applying it to the appropriate surface area of the spacecraft. Since TRIANA would circle L1 in three dimensions, it is necessary to consider how solar incidence angle varies over the period of the halo orbit. The angle the incident energy makes with the halo itself is negligible (0.13°). Instead, spacecraft pointing causes the largest variation in incidence angle. The below table lists 25 pointing and incidence angles for a complete halo orbit (180 days). The spacecraft’s maximum pointing angle is 22.44° when it crosses the major axis of the ellipse. The solar angle of incidence (on the sides of the spacecraft) at that point is 67.43° which also accounts for the angle the sun makes with the halo at that point in the orbit. Likewise, the minimum pointing angle occurs when the spacecraft is at the top of the halo (positive z direction) because the halo is inclined with its top closer toward the Sun. The minimum pointing angle is 5.31°, thus the angle of incidence on the side of the spacecraft body is 84.56°. Table III-6 Pointing and incidence angles for one halo orbit. Day 0 45 90 135 180 Pointing Angle 5.31 22.44 -6.87 -22.44 5.31 AOI 84.56 67.43 83.26 67.69 84.56 Equilibrium temperature was determined for each angle of incidence after estimating internal power dissipation to be 87 watts (50% efficiency) and solar flux at L1 to be 1418 w/m 2. The following equation was used to calculate equilibrium temperature for the first iteration. Equation III-1 1 4 Gs s Acos s A cos s Acos90 BOTTO M TOP SIDE TE IR ATOP IR ASIDE IR ABOTTO M Where TOP, SIDE, and BOTTOM denote a position on the spacecraft over which the material would cover. This assumed that each position would be covered by only one material; however, this was insufficient for controlling spacecraft temperature within the specified limits. The figure below is a temperature plot of one of the early iterations. Changing the material type for each part of the structure caused large, discrete changes in the temperature profile. To provide finer control over equilibrium temperature, it became necessary to redesign the model to accommodate multiple materials on a given structural component. Then smaller adjustments could be made to the amount of each material used. 26 Equilibrium Temperature Profile Top: OSR; Bottom : Gold; Sides: Gold Equilibrium Temp. (Celcius) 50.0 40.0 30.0 20.0 10.0 0.0 0 50 100 Tim e (Days) 150 Figure III-8 Equilibrium Temperature for Single Material Faces Equilibrium Temperature Profile T o p :OSR ( .5) / Go ld ( .5) ; B o t t o m OSR ( .5) / Go ld ( .5) ; Sid es:OSR ( .5) / Go ld ( .5) 30.0 Equilibrium Temp. (Celcius) 20.0 10.0 0.0 -10.0 0 50 100 150 -20.0 -30.0 Tim e (Days) Figure III-9 Temperature Profile for OSR/Gold Combination Equilibrium Temperature Profile T o p :B lk( .6 ) / W ht ( .4 ) ; B o t t o m:B lk( .6 ) / W ht ( .4 ) ; Sid es:B lk( .5) / W ht ( .5) Equilibrium Temp. (Celcius) 25.0 20.0 15.0 10.0 5.0 0.0 0 50 100 Tim e (Days) 150 Figure III-10 Temperature Profile for Black/White Mixture 27 Equilibrium Temperature Profile 30.0 Top:Gold(1.0); Bottom :Gold(.6)/White(.4); Sides:Black(1.0) Equilibrium Temp. (Celcius) 25.0 20.0 15.0 10.0 5.0 0.0 -5.0 0 50 100 150 Tim e (Days) Figure III-11 Temperature Profile for Gold MLI/White Epoxy/Black Paint Combination Equilibrium Temperature Profile T o p :A lum( .6 ) / B lk( .4 ) ; B o t t o m:A lum( 1.0 ) ; Sid es:A lum( .4 5) / B lk( .55) Equilibrium Temp. (Celcius) 25.0 20.0 15.0 10.0 5.0 0.0 0 50 100 Tim e (Days) 150 Figure III-12 Temperature Profile for Aluminum/Black Paint Mixture Several iterations were attempted using different materials and by changing the combination ratios of each. Most of the combination could suit the specification by adjusting the combination ratios. The Gold/White/Black represents a nonhomoginous combination where incidence angle causes large variations in temperature. An improvement was made by replacing gold with aluminum which conforms to the temperature limits but leaves no margin for changes in solar flux throughout the mission. The two best combinations are the black paint and white enamel combination and the gold MLI and OSR combination. The gold/OSR combination was chosen as the optimum because its standard deviation was 1.65°C vise 2.9°C for the black/white combination. 28 C. ELECTRICAL POWER SUBSYSTEM 1. Requirements Total spacecraft power is not to exceed 175W. 2. Final Design Source: Four identical GaAs solar arrays on graphite epoxy substrate. Physical dimensions: Each solar panel is 0.355m x 1m, with a surface area of 0.355m2. Total solar panel surface area = 4*0.355 =1.42m 2 Weight: Each solar panel weighs approximately 1kg, for a total array weight of 4kg. Power: Per solar panel BOL power = 67.30W, per solar panel EOL power = 54.88W, with total array BOL power = 269.20W, and total array EOL power = 219.50W. Storage: A single secondary nickel cadmium (NiCd) battery consisting of 24 sealed rechargeable cells, provides 28VDC, at a depth-of-discharge of less than 80%, a capacity of 7.5 A-hr, to a 87W load for a period of 1.5 hours. Physical Dimensions: Estimated to be 42 cm long, by 9 cm wide, by 11 cm high. Weight: Estimated to weigh less than 9kg. Commercial product used for design calculations: Sanyo Canada Inc., High Capacity, sealed and rechargeable, CADNICA battery model number KR-7000F. ( www.sanyo.ca ) Distribution: A dual bus using redundant, shielded cabling and mechanical relays, is used for power distribution and switching. Regulation and Control: A +28V standard bus direct energy transfer (DET) employing array shunt regulators. Weight of the Power Distribution, Regulation and Control systems is estimated at 7kg, which is 7% of spacecraft design goal weight (.07*100kg) = 7kg. Total EPS weight is 20kg. 29 3. Design Approach Development of the Triana EPS concept was performed iteratively. Most trades centered on the quantity, placement and size of the solar arrays. Battery type and quantity was also a major element of concept development. Ultimately the Team decided on the use of four solar arrays a NiCd battery. Discussion of the considerations that produced this design are described below. 4. EPS Purpose The primary function of the Electrical Power Subsystem (EPS) is to control and distribute a predictable and continuous source of electrical power to the spacecraft’s subsystems throughout the spacecraft’s lifetime. In order to ensure completeness of design it is useful to subdivide the EPS into the four sub-components as indicated below. Electrical Power Subsystem Power Source Energy Storage Power Distribution Power Regulation & Control NiCd Battery NiCd Battery 28V bus Unregulated Solar array Figure III-13 Spacecraft's Power Subsystem Functional Breakdown (SMAD, p. 391) 5. Power Sources Design of the EPS is begun with an identification of the spacecraft power requirements. Top-level power requirements are driven by mission profile, orbital parameters, desired mission life, spacecraft configuration and payload power needs. It is important to further divide power requirements in accordance with the mission profile. In the case of Triana there are two mission 30 phases each having distinct power requirements. These two phases are, launch and transit to L1, and the at L-1 (on-orbit) operational phase. a) Phase 1: Launch and Transit Launch and transit power requirements are driven by the need to communicate and control the spacecraft bus while making the trip to L-1. During the 3 month transit the primary energy users will be the propulsion subsystem, the attitude control subsystem, and the communications subsystem. Throughout this time the spacecraft will be operating on a combination of battery and solar power. Initial systems startup and power required for solar array deployment will be provided by pre-charged secondary batteries (charged prior to launch). A detailed mission timeline is provided in Chapter I Section E Mission Timeline, a general Phase 1 timeline with associated power requirements is presented below. Launch & PMF, then PKM separation Despin & Reorient ACS Comms C&DH Deploy Arrays Total Power = 40.0W 17.5W 9.5W 10.0W 77.0W On-orbit 175W .25hr .5hr S/C Turn on & Checkout Comms 17.5W C&DH 9.5W Star Trackers 20.0W Total Power = 47.0W Coasting, Transfer Firing, Orbit Injection ACS 40.0W Comms 17.5W C&DH 9.5W Total Power = 77.0W Figure III-14 Phase 1 Estimated Power Requirements The decision to use secondary batteries was based on a desire to optimize battery utility by incorporating a level of fault response flexibility. While on-orbit at L-1 the spacecraft will not experience eclipse, and therefore batteries are not required for spacecraft operation. However, the flexibility provided by having secondary batteries dramatically increases the operator’s courses of action should the solar array go into a fault mode. The down side is that 31 use of pre-charged secondary batteries may prohibit (due to safety concerns) the spacecraft from being launched from the Shuttle. Design of the spacecraft battery began with a comparison of nickel hydrogen (NiH2) and NiCd. Initially the Team was attracted to NiH 2 due to its high specific energy density (45-60W-hr/kg vs. 25-30W-hr/kg for NiCd) and its successful use of on spacecraft such as Lunar Prospector, Clementine and IntellSat (SMAD pp. 403). Despite this benefit and given the Triana's low power requirement the Team choose to take advantage of the numerous commercially available rechargeable NiCd batteries. The risk of using a non-space qualified battery can be mitigated through careful vendor selection and by verifying cell seals by x-raying each cell prior to use. This technique has been employed on numerous low cost, small satellites to include the Naval Postgraduate School's Petite Amateur Satellite (PANSAT). In order to perform as accurate of an estimation as possible, calculation of battery capacity, battery weight and number of cells was performed using NiCd cells sold by Sanyo Canada Inc ( www.sanyo.ca ) as examples. Given the small size and weight of the NiCd batteries the decision was made to include a significant amount of margin in the design of the spacecraft battery. Therefore the design parameters were to provide for 50% of full system power (87W at 28VDC), for a duration of 1.5 hours, at a depth-of-discharge of not to exceed 80%. The choice to use 80% DOD (trading life cycle for DOD) is validated by the fact that once on-orbit the battery is not required (an 80% DOD limits battery cycle life to less than 1000 cycles, SMAD pp. 404). This trade is justified by the on-orbit availability of solar power and the projected limited (if any) use of batteries at L-1. Table III-7 Sanyo Canada Inc. High-Capacity, NiCd Rechargeable Cells Model KR-7000F Voltage (V) 1.2 Capacity (A-hr) 7.5 Diameter (mm) 33.0 1) Determine the number of cells required for a 28V battery # of cells/battery = 28V/(1.2V/cell) = 24 cells 32 Height (mm) 91.0 2) Characterize battery capacity (A-hr) over a range of powers and DODs Battery requirements: Provide 87W for 1.5 hours at less than 80% DOD Capacity (A-hr) = (Power * Time)/(# of cells * Cell Voltage * DOD) As the chart below demonstrates use of the KR-7000F provides a 25% capacity margin at 80% DOD and 87W. Where capacity margin = [1 - (5.66/7.5)] A-hr Table III-8 Battery capacity in A-hr, as a function of power and DOD (using the Sanyo Model KR-7000F). Required Power W 80 81 82 83 84 85 86 87 88 89 90 DOD 0.6 6.94 7.03 7.12 7.20 7.29 7.38 7.47 7.55 7.64 7.73 7.81 0.7 5.95 6.03 6.10 6.18 6.25 6.32 6.40 6.47 6.55 6.62 6.70 0.8 5.21 5.27 5.34 5.40 5.47 5.53 5.60 5.66 5.73 5.79 5.86 0.9 4.63 4.69 4.75 4.80 4.86 4.92 4.98 5.03 5.09 5.15 5.21 3) The resulting physical characteristics of a generic rectangular packing of the cells to form a battery are: Assuming 2 rows of 12 cells each and 2cm added to each dimension to account for the container Length = 39.6+2 = 41cm, Width = 6.6+2 = 9cm, Height = 9.1+2 = 11cm. Volume = 41*9*11 = 4059cm 3 Weight is estimated using a gram/volume factor derived from the measurement a standard commercial NiCd D-cell. i) D-cell characteristics: (1) Weight = 150g, Height = 5.8cm, Diameter = 3.2cm, Volume = 93.3cm 3 (2) Resulting gram/volume factor = 1.61g/cm 3 ii) Estimation of Triana battery weight = 4059cm 3 * 1.61g/cm3 = 6535g = 6.5kg iii) Addition of 30% overhead for wiring and packaging = 8.45kg (less than 9kg). 33 Battery recharging will be performed throughout the transit to L-1. Once deployed the solar panels will provide power for both the bus and battery recharging. During transit spacecraft attitude will be maintained so that minimum sun incident angle is acquired ( 0 degs).When maneuvers are required the spacecraft will transition to battery power, execute the maneuver, then reorient for solar radiation collection. It is important to note that with the solar panels deployed full system power will be available. This allows controllers to perform system checks to include verification of the mission sensor. b) Phase 2: On-orbit Once in position at L-1 the spacecraft will never go into eclipse and therefore power requirements can be met by solar arrays, allowing the batteries to be used as a backup power source until they surpass their cycle life. Initially the Team considered collecting solar radiation using a single array placed on the top (northern, positive z-axis) of the spacecraft. Also at this stage of the design process the negative axis or south face of the spacecraft was going to have a boom mounted 1-meter parabolic high gain communications antenna. When the Team decided to body mount the high gain antenna the single solar array was divided into two panels with one on each of the north and south faces. Finally as presented in earlier portions of this report the Team decided to create four separate panels. Each panel is outwardly facing and body mounted (attached at the aft end of the spacecraft) in such away that when deployed the solar panels look like flower pedals around the spacecraft body. Single Panel with Single Axis (EastWest) Driver Two Panels with Single Axis (EastWest) Driver Four Fixed Panels Figure III-15 Evolution of Solar Array Design 34 In the original plan the solar array would have had a single axis, bi-directional drive (east-west) that would maintain the solar array perpendicular to incident solar rays. A single axis drive was chosen to increase reliability, to decrease weight and cost and it was decided that a dual spin (north-south and east-west) drive was not required. Justification for not using a northsouth capable drive is derived from the geometry of the halo orbit about L-1. Optimal solar energy transfer occurs when the sun incident angle is 0 degrees and maintaining a 0 degree incident angle is a function of the satellite’s position relative to the sun. Once the Team began reviewing the sun angle and the orbit geometry it was further decided that a single axis driver was not required. Therefore, the final concept was to fix the solar array position relative to the spacecraft. Using this concept the maximum sun angle cosine loss was calculated to be 8.62%. A factor which the Team considered acceptable and did not warrant the extra complexity, cost and weight required for a single or dual axis driver. The table below provides data representative of the saving in weight and power by doing away with a single axis driver. Table III-9 Single Axis Solar Array Driver (from Ball Aerospace & Technologies Corporation) (www.ball.com/aerospace/ptmech.html ) Parameter Drive application Speed (RPM) Design life (years) Supported loads (lbs) Step size Input power (W) Position accuracy (deg) Temperature (deg C) Length (in) Diameter (in) Weight (lb) Model: EMS 221 Solar Array 0.004 - 0.04 5 94 0.15 1.4 +/- 1 -25 to +60 7.5 7.0 9.5 (4.275kg) The following figures and calculations describe the solar array driver trade. 35 6 1.5x10 km A view of the Triana orbit as seen from the sun. Earth Halo orbit plane B B L-1 8 1.4849x10 km = .9926au 120000km B 666672km Sun Figure III-16 Halo Orbit Parameters Top View of Triana at western edge of halo orbit. Earth B = 23.96 deg 6 1.5x10 km -1 B 6 B = tan (666672/1.5x10 ) 666672km B Sun Figure III-17 Calculation of Maximum Cosine Loss Using Fixed Arrays 36 Critical to the sun angle analysis is the assumption that the sun's rays are perpendicular to all points within the halo orbit plane. This assumption is valid because (treating the sun as a point source) the angle formed between sun and the rays extending out to the 1 666672 ) 0.2572 degrees . western point of the halo orbit is approximately zero, tan ( 1.4849 x10 8 Therefore the incident rays on the western edge of the halo orbit are parallel to those incident on the center of the orbit. The calculation of the cosine losses for the minor axis extremes (northern most and southern most halo points) are analogous to the calculation of the major axis extremes. These losses are: Major axis extremes cosine losses = 8.62% Minor axis extremes cosine losses = 0.3% given: 1 120000 tan (1.5 x10 6 ) 4.57 degrees cos(4.57) 0 .9968 resulting in a 1- 0.9968 = 0.003 = 0.3% The next step in the process was to size the solar arrays to meet on-orbit power requirements. Solar array sizing was performed using the maximum power requirements (175 W) as indicated in the RFI. Gallium Arsenide (GaAs) was chosen due to its greater efficiency over silicon and a graphite epoxy substrate was assumed. The final design results were: Physical dimensions: Each solar array is 0.355m x 1m, with a surface area of 0.355m2. Total solar array surface area = 4*0.355 =1.42m 2 Weight: Each solar array weighs approximately 1kg, for a total weight of 4kg. Power: Per solar panel power BOL = 67.30W, per solar panel power EOL = 54.88W, with total array power BOL = 269.20W, and total array power EOL = 219.50W. Sizing was conducted by first calculating a single array area that met the power requirements and then dividing that area into four equally sized panels. The sizing calculations follow. 37 PeTe Pd Td Xe Xd Required output power of the solar array = Psa = Td Pe = 175, powered required during eclipse Pd = 175W, powered required during daylight Te = 0, time in eclipse Td = 1, time in daylight (the spacecraft is always in daylight) Xe , Xd “represent the efficiency of the paths from the solar arrays through the batteries to the individual loads and the path directly form the arrays to the loads, respectively.” (SMAD pp. 396) For first iteration calculations the Team used values X e = 0.60 and Xd = 0.80. therefore Psa = Pe = 218.75W Xd Power at the beginning of life = PBOL = ( G s ) I d cos .19 GaAs efficiency (a selected representative value) Table III-10 Solar Array Efficiency and Cost (from Satellite Power Corporation) Parameters Panel Efficiency (%) Cost Silicon (Si) 15.1 $9-$17 per centimeter Gallium Arsenide (GaAs) 19 $27-$51 per centimeter Gs = 1418 W/m2 , solar flux. Solar flux at L-1 is greater than the solar flux at the earth (1358W/m2) due to reduced distance and lack of the magnetosphere. Derivation of the L1 solar flux follows: L-1 is 0.9926au = 1.4849x108km from the sun. Sun temperature = 5800K, radius = 6.98x108m, surface area = 6.12x1018m2 Sun blackbody radiation = T4 = 64.17x106W/m2 Total power of the sun = 3.9288x1026W 38 Surface area at L-1 = 2.7708x1023m2 Gs = Flux at L-1 = Total power/Surface area = 1418W/m 2 I d .77 inherent degradation (a selected representative value, SMAD chapter 11) therefore PBOL= 189.58 W/m2 (note using 1358W/m 2 PBOL= 181.56 W/m2) 23.96 degrees, worst case angle of incidence Lifetime degradation = Ld (1 Yd ) Satellitelife where yearly degradation =Yd = .04, selected based on a degradation in LEO of 0.0275 for GaAs and the assumption that degradation at L-1 is greater than that at LEO. (SMAD chapter 11) Radiation at L-1 is higher than LEO therefore yearly degradation should be increased. satellite life = 5 years therefore Ld = .8154 Power at end of life = PEOL = PBOL Ld = 154.58 W/m2 Area of the Solar Array = Asa = Psa / PEOL = 1.42m2 Given this area PBOL=269.20W and PEOL= 219.50W Which equates to a 54% power margin at BOL and a 25% power margin at EOL. Division of the single array into four equal panels results in the following: Each panel has an area of 0.355m2 Each panel has a PBOL= 67.30 W/m2 and a PEOL= 54.88 W/m2 Note: Degradations due to dividing the solar array into four separate panels where not consider in these calculations. These inefficiencies will only slightly reduce the already large power margins so meeting spacecraft power will not be a problem. Total number of cells per panel was calculated using a cell size of 2cm x 4cm (an estimate based on a standard silicon cell size). Cell area = 0.02m * 0.04m = .0008m 2/cell Number of cells/panel = Panel area/Area per cell = 444 cells per panel Total number of cells = 444 * 4 = 1776 cells 39 A survey of commercially available solar arrays was conducted. The following information is representative of the responses the Team received. Table III-11 Solar Array Power and Weight (from Tecstar) Parameter Power (Watts/m2) Power Density (Watts/kg) GaAs/Ge 218 (at 28 deg C) 110.6 (on graphite epoxy substrate) Panel weight = Solar Panel PBOL /Power Density = 0.61kg per panel Total weight for all four panels = 4 * 0.61 = 2.43kg These values were rounded up to 1kg/panel and 4kg for all four combined. A final note concerning the solar panels is that the commercial data indicates that it should be possible to decrease the size of the solar array given a 19% efficiency and a power per unit area of 218 W/m 2 for a GaAs panel. If this were the case the total array size could decrease to at least 1m2 and the weight would decrease to approximately 2kg, (assuming a 1m 2 solar array with PBOL=218W.) c) Power Distribution, Regulation and Control Given Triana’s low power requirements the Team decided that use of a standard 28V bus would be appropriate. Power distribution aboard the spacecraft is accomplished using redundant, shielded wire and where required mechanical relays are used as power switches. Mechanical relays are preferred due to their proven space history and due to the increased radiation environment at L-1. The spacecraft structure will have a single power ground point. Control of the EPS will be performed by a direct energy transfer (DET) system employing solar array mounted shunt regulators. First iteration design values indicate that the solar array will provide a 25% EOL power margin. The DET sub-system will ensure that unneeded power is dissipated and therefore bus voltage will be maintained at a predetermined level. On Triana DET shunts are positioned at each solar panel to prevent internal power dissipation and heat generation. Initially the design Team had calculated that the ambient temperature at L-1 would be to low for efficient operation of all spacecraft components. As a result the original design included 40 a plan to generate heat by shunting excess power through radiators placed inside on the main deck of the spacecraft. Of course this trade comes with the potential cost of over designing the solar array. That is use of a 1.42m 2 aggregate array provides excess power and therefore the system as presented is over designed. Efforts to optimize the solar array would decrease the utility of shunting power inside the spacecraft. If however heating is required internal shunting is certainly an option. Regardless of where shunting is performed “a shunt regulated sub-system has advantages of: fewer parts, lower mass, and higher total efficiency at EOL.” (SMAD pp.407) Lastly the combined weight of the components comprising the power distribution, regulation and control sub-systems was estimated at 7% of the spacecraft (goal) dry weight, or 7kg (0.07 * 100kg). D. COMMUNICATIONS SUBSYSTEM 1. Requirements The satellite carries a 1-meter X-band antenna and is capable of downlinking data at 200 Kbits/sec; it will require approximately 3 minutes to send a full image. Three 3-meter X-band ground stations are required to receive data. 2. Final Design The satellite communications subsystem is comprised of: A single 1m diameter parabolic high gain antenna mounted on the "earth pointing" side of the spacecraft. Two omni-directional 12cm diameter low gain antennas mounted on opposing ends of the spacecraft. Two less than 5kg, and less than 17.5W transponders. One transponder is configured for X band the other for S band. Each transponder can transmit on any of the three antennas. The system is designed to meet the RFI on-orbit data rate of 200kbps. Total sub-system weight is estimated at less than 17kg. 41 Motorola’s Cassini X-band transponder a commercially available item that in general conforms to the stated design. (www.mot.com/GSS/SSTG/SATCOM/GSSD/Products.html ) Table III-12 Communications Subgroup Component High Gain Antenna Low Gain Antennas X-band Transponder S-band Transponder 3. Description 1m diameter, estimated weight <5kg, mounted on earth pointing side 2, 12cm diameter, omni-directional antennas, estimated weight <1kg each <5kg, <17.5W, Uplink 7.1GHz, Downlink 8.5GHz <5kg, <17.5W, Uplink 2.5GHz, Downlink 2.6GHz Evolution of Design Using an approach similar to the design of the EPS the Team segregated the development of the communications subsystem into Phase 1 and Phase 2. Phase 1 corresponds to spacecraft launch and transit and Phase 2 corresponds to on-orbit operations. The driving requirement during Phase 1 was the Team's desire to communicate with, and command the spacecraft throughout launch and transit. This desire coupled with restrictions imposed by the attitude control system and EPS implied the use of a low power omni-directional antenna. Additionally given that the sensor would not be operating the Phase 1 data rate would be small compared to the required on-orbit rate of 200kbps. It was the 200kbps requirement that drove the Phase 2 communications sub-system design. To achieve the required data rate without a significant increase in power the Team choose to take advantage of the earth sensor pointing requirements and employ a high gain directional antenna. Another significant design consideration was the Team's desire to provide a measure of communications robustness. Three options were discussed in response to this requirement. These options were: 1) A non-redundant system consisting of A high gain antenna Two omni-directional low gain antennas A single X-band transponder 2) A physically redundant system consisting of A high gain antenna 42 Two omni-directional low gain antennas Two X-band transponders 3) A spectrally diverse and physically redundant system consisting of A high gain antenna Two omni-directional low gain antennas An X-band transponder An S-band transponder Obviously the only difference between the options is the number and frequency of the transponders. Option 1 was ruled out since it fails to provide even a basic level of redundancy. Option 2 while providing physical redundancy fails to provide any spectral flexibility, an option that the Team considered valuable. Therefore, although the use of S-band is not called out in the RFI the Team considers Option 3 to be the most favorable and therefore link analysis was performed for both S and X band. Of further critical importance was the Team's choice to give each transponder access to any of the three antennas. This presents the user with different employment options based on available power and ground communications assets. Given the decision to use Option 3 the Team progressed in the design process by using basic link equations to characterize key parameters. A search for applicable commercial items was performed using the key parameters. Each of the steps are described below. 4. Link Analysis Given that the Team was developing a concept design, Phase 1 TT&C downlink data rate requirements were estimated to be less than 10% of the required on-orbit data rate, or (.1)*(200kbps) = 20kbps. The uplink data rate which should consist only of command data was estimated to be 1% of the required on-orbit data rate, or 2000bps. The Team also restricted transponder peak power requirements to 10% of the total power requirements, or (.1)*(175W) = 17.5W. Although both the S and X band transponders can transmit via either the high or low gain antennas it is unlikely that the high gain antenna, due to pointing requirements, would be used during launch and transit. Therefore Phase 1 calculations were performed only using the omni- 43 directional antenna. Lastly, the Team took the liberty to model the omni-directional antennas after an S-band antenna taken from a proposed Lunar Prospector design. Basic characteristics of this antenna are, 12cm diameter, 20cm length, 0.3kg weight and efficiency is estimated at .6 (Lunar Prospector, p. 44). Phase 2 link calculations follow those conducted for Phase 1, the only difference is in the increased data rate due to the need to transmit the sensor image. Because the omni-directional antennas are not the primary antenna for on-orbit transmission link calculations using the omnidirectional antennas for Phase 2 operations are not presented. Link calculations and associated notes are presented in the tables below. A search to identify commercially available transponders that could potentially meet the requirements uncovered Motorola’s Cassini X-band transponder. Lastly it is important to note that due to its position relative to the sun communications with Triana may not always be possible. In general solar noise becomes prohibitive when solar conjunction is less than 7 degrees for a noisy sun, and less than 3 to 5 degrees for a quiet sun. As shown in the EPS solar array calculations (see accompanying figures) when Triana is on the extreme points of its major axis the sun angle is 23.96 degrees however when the spacecraft is at the extreme points of the minor axis the sun angle is 4.57degrees. Therefore it is probable that when at the northern and southern points of the orbit with a noisy sun, Triana will have intermittent communications. Table III-13 Link Equations and Units Item Frequency Transmitter Power Transmitter Power Transmitter Line Loss Transmit Antenna Diameter Transmit Antenna Efficiency Transmit Antenna Gain Equivalent Isotropic Radiated Power Propagation Path Length Space Loss Receive Antenna Diameter Receive Antenna Efficiency Receive Antenna Gain Required Receiver Power Data Rate Source Input parameter Input parameter 10log(P) Input parameter Input parameter Input parameter 10*log(nt*(pi*Dt*f/c)^2) Pt+Gt-LI Input parameter 10*log((c/4*pi*S*f)^2) Input parameter Input parameter 10*log(nr*(pi*Dr*f/c)^2) ERIP+Gr-Ls Input parameter 44 Symbol f Pt Pt Ll Dt nt Gt EIRP S Ls Dr nr Gr Pr R Units GHz Watts dBW dB m dB dBW km dB m dB dB bps Desired Bit Error Rate Eb/N0 (given BPSK) Sky Noise Temperature Receiver Noise Temperature System Noise Temperature Noise Figure Carrier-to-Noise Density Ratio Receiver Gr/T Input parameter Input parameter Input parameter Input parameter Tsky+Tr 10*log(1+Tr/290) (Eb/N0)+10logR Gr(dB) - Tsys(dB) BER Eb/N0 Tsky Tr Ts NF C/N0 Gr/T dB K K K dB dB-Hz dB/K Table III-14 Phase 1 Downlink From Omni-directional Antenna to Ground Stations Item Units Frequency Transmitter Power Transmitter Power Transmitter Line Loss Transmit Antenna Diameter Transmit Antenna Efficiency Transmit Antenna Gain GHz Watts dBW dB m dB Downlink S- Downlink band band 2.6 8.5 17.50 17.50 12.43 12.43 1.00 1.00 0.12 0.12 0.60 0.60 8.07 18.35 Eq Isotropic Radiated Power Propagation Path Length Space Loss Receive Antenna Diameter Receive Antenna Efficiency Receive Antenna Gain Required Receiver Power Data Rate Desired Bit Error Rate Eb/N0 (given BPSK) Sky Noise Temperature Receiver Noise Temperature System Noise Temperature Noise Figure Carrier-to-Noise Density Ratio Receiver Gr/T dBW km dB m dB dB bps dB K K K dB dB-Hz dB/K 24.57 1.50E+06 -69.03 3.00 0.60 36.02 129.62 20000.00 1.00E-05 9.50 8 290 298 3.01 52.51 11.28 34.85 1.50E+06 -79.32 3.00 0.60 46.31 160.49 20000.00 1.00E-05 9.50 8 290 298 3.01 52.51 21.57 X- Notes 10% overall power estimated modeled after Lunar Prospector estimated Distance to L1 from Triana RFI 10% of 200kbps requirement estimated tolerable error BPSK is assumed 20deg elev angle (quiet sun) No cooling, room temp assumed Table III-15 Phase 1 Uplink From Ground Stations to Omni-directional Antennas Item Frequency Transmitter Power Transmitter Power Transmitter Line Loss Transmit Antenna Diameter Transmit Antenna Efficiency Transmit Antenna Gain Eq Isotropic Radiated Power Propagation Path Length Units GHz Watts dBW dB m dB dBW km Uplink S-band 2.5 100.00 20.00 1.00 0.12 0.60 7.72 106.72 1.50E+06 45 Uplink X-band 7.1 100.00 20.00 1.00 0.12 0.60 16.79 115.79 1.50E+06 Notes estimate estimated modeled after Lunar Prospector estimated Distance to L1 Space Loss Receive Antenna Diameter Receive Antenna Efficiency Receive Antenna Gain Required Receiver Power Data Rate Desired Bit Error Rate Eb/N0 (given BPSK) Sky Noise Temperature Receiver Noise Temperature System Noise Temperature Noise Figure Carrier-to-Noise Density Ratio Receiver Gr/T dB m dB dB bps dB K K K dB dB-Hz dB/K -68.69 3.00 0.60 35.68 211.10 2000.00 1.00E-05 9.50 290 287 577 2.99 42.51 8.07 -77.76 3.00 0.60 44.75 238.30 2000.00 1.00E-05 9.50 290 287 577 2.99 42.51 17.14 from Triana RFI 1% of 200kbps requirement estimated tolerable error Ambient temp of earth Ambient temp of spacecraft Table III-16 Phase 2 Downlink From High Gain Antennas to Ground Stations Item Units Frequency Transmitter Power Transmitter Power Transmitter Line Loss Transmit Antenna Diameter Transmit Antenna Efficiency Transmit Antenna Gain Eq Isotropic Radiated Power Propagation Path Length Space Loss Receive Antenna Diameter Receive Antenna Efficiency Receive Antenna Gain Required Receiver Power Data Rate Desired Bit Error Rate Eb/N0 (given BPSK) Sky Noise Temperature Receiver Noise Temperature System Noise Temperature Noise Figure Carrier-to-Noise Density Ratio Receiver Gr/T GHz Watts dBW dB m dB dBW km dB m dB dB bps dB K K Downlink S-band 2.6 17.50 12.43 1.00 1.00 0.60 26.48 42.98 1.50E+06 -69.03 3.00 0.60 36.02 148.04 200000.00 1.00E-05 9.50 8 290 K dB dB-Hz 298 3.01 62.51 dB/K 11.28 46 Downlink X-band 8.5 17.50 12.43 1.00 1.00 0.60 36.77 53.27 Notes 10% overall power estimated from Triana RFI estimated 1.50E+06 Distance to L1 -79.32 3.00 from Triana RFI 0.60 46.31 178.91 200000.00 full data rate 1.00E-05 estimated tolerable error 9.50 BPSK is assumed 8 20deg elev angle (quiet sun) 290 No cooling, room temp assumed 298 3.01 62.51 21.57 Table III-17 Phase 2 Uplink From Ground Stations to High Gain Antenna Item Units Uplink X-band 7.1 100.00 20.00 1.00 1.00 0.60 35.21 134.21 Notes GHz Watts dBW dB m dB dBW Uplink S-band 2.5 100.00 20.00 1.00 1.00 0.60 26.14 125.14 Frequency Transmitter Power Transmitter Power Transmitter Line Loss Transmit Antenna Diameter Transmit Antenna Efficiency Transmit Antenna Gain Eq Isotropic Radiated Power Propagation Path Length Space Loss Receive Antenna Diameter Receive Antenna Efficiency Receive Antenna Gain Required Receiver Power Data Rate km dB m dB dB bps 1.50E+06 -68.69 3.00 0.60 35.68 229.52 2000.00 1.50E+06 -77.76 3.00 0.60 44.75 256.72 2000.00 Distance to L1 Desired Bit Error Rate Eb/N0 (given BPSK) Sky Noise Temperature Receiver Noise Temperature System Noise Temperature Noise Figure Carrier-to-Noise Density Ratio Receiver Gr/T dB K K 1.00E-05 9.50 290 287 1.00E-05 9.50 290 287 K dB dB-Hz 577 2.99 42.51 577 2.99 42.51 dB/K 8.07 17.14 47 estimate estimated from Triana RFI estimated from Triana RFI 1% of 200kbps requirement estimated tolerable error Ambient temp of earth Ambient temp of spacecraft E. PROPULSION SUBSYSTEM 1. Requirements The propulsion subsystem provides the spacecraft the necessary V for midcourse corrections, halo orbit insertion and maintenance, and momentum dumping of the reaction wheel system for the mission lifetime with substantial design margin. Several different systems were evaluated including electric and bipropellant systems. However, due to the weight, power, and cost constraints of the mission, a simple monopropellant hydrazine system was selected. As calculated in the V section, a propellant mass of 50 kg is estimated for the total V budget including a 50% margin. 2. Components ENGINES: The engines have to provide enough impulse to efficiently produce the comparably larger V’s required for mid-course corrections and halo orbit insertion and the much finer impulses of momentum dumping in all three axis. Initial design considered a combination of multiple, small 1.12 N engines for attitude control and a single 22.24 N engine for V maneuvers. However, analysis of stability control over estimated worst case error dispersion during prolonged firing favored the use of larger 5.34 N (1.0 lbf) engines for both attitude control and V impulse. Analysis also compared burn times for desired V maneuvers and minimum impulse bit. Additional analysis would consider cost versus complexity trades, reliability issues, and failure modes of operation. For this design iteration, twelve Rocket Research MR-111C 1.0 lbf monopropellant engines were selected. Specific engine characteristics are shown below. Figure III-18 Thruster Depiction 48 Table III-18 Thruster Characteristics MR-111C (1.0-lbf Engine) Design Characteristics Propellant Thrust, Steady State Feed Pressure Valve Power Weight (Engine + Valve) Demonstrated Performance Specific Impulse Total Pulses Minimum Impulse Bit Steady State Firing Hydrazine 1.3345 - 5.3378 N 80-400 psi 9 Watts @ 28VDC 0.33 kg 226-229 sec 5970 0.08451 Ns (20 ms) 330 sec Single Firing 14400 sec Cumulative A simple thruster module scheme was also selected for initial design. The engines would be mounted in four modules located on the top and base of the spacecraft structure with effective moment arms of 50 cm in the X and Z directions. This arrangement provides attitude control in all directions for momentum dumping and V capability in the X and Z directions. Additionally, the X direction thrusters could be aligned slightly in the Y direction to provide some V capability, otherwise, a rotation about the Z-axis would be necessary. The exact thruster module locations will definitely change as better knowledge of the center of mass location and halo orbit maintenance requirements are known. B X 1 2 Z A Y D 3 C Figure III-19 Thruster Module Arrangement PROPELLANT TANKS: Design propellant mass is estimated to be 50 kg of hydrazine. For simplicity and cost, a helium blowdown pressurization system was selected. The size of the 49 propellant tank can be estimated assuming a typical blowdown ratio of 3:1 and average hydrazine density of 1.004 gm/cm 3. See Appendix H for details. Survey of commercially available propellant tanks resulted in the selection of four spherical tanks rather than a single spherical tank. Actual comparison of number of tanks and combined weight favored the four tank arrangement and allowed for additional system reliability. The propellant tanks selected are Pressure Systems, Inc. 80290-1 spherical tanks. Each tank is approximately 16.36 cm in radius, made of 6Al-4V titanium, and utilizes a rubber diaphragm pressurized by helium for positive expulsion. Additional characteristics are shown below: Table III-19 Propellant Tank Characteristics Tank Characteristics Diameter: 32.7152 cm Material: 6AI-4V Titanium Tank Type: Diaphragm Operating Pressure: 396 psig Total Volume: 17698.029 cm3 Prop Volume: 12454.168 cm3 Max. Design Wt: 2.54 kg Min. Wall Thickness: 0.05 cm The propellant tanks are arranged equidistantly about the spacecraft’s supported by the main load bearing structure as depicted below. graphite-epoxy structure securely support each tank. Figure III-20 Propellant Tank Arrangement 50 x-axis and Actual cut-outs from the 3. Subsystem Operation Key elements such as maximum propellant flow rate and operating pressure would be calculated for selecting the proper feed lines and components such as the latch valve, cavitating venturi, fill and drain valve, and filter. A simplified schematic of the propulsion subsystem is depicted below. Tank 1 Tank 2 Tank 3 P Fill/Drain Valve Tank 4 Pressure Transducer Filter Latch Valve Solenoid Valves A1 A2 A3 B1 B2 B3 C1 C2 C3 D1 D2 D3 Figure III-21 Propulsion Subsystem Schematic Operation of the propulsion subsystem is controlled by simple ON/OFF commands sent by telemetry or calculated by the onboard flight computer. The reaction wheel system will be responsible to orient the spacecraft in the proper direction. Large V maneuvers would be performed by firing all number four modules in the X direction. Assuming a large midcourse correction of 60 m/s, approximately 7 minutes of continuous firing would be required. Since the engine’s maximum single firing period is only 5.5 minutes, the maneuver would be broken into two parts. For the large halo orbit insertion, a total of approximately 41 minutes of continuous firing would be required. The nominal firing scheme is shown below: 51 Table III-20 Propulsion Subsystem Operation Propulsion Subsystem Operation Reorientation X Axis Y Axis Z Axis Translation X Axis Y Axis Z Axis F. Positive A1/B3 or C1/D3 A2/D2 A1/C3 or B1/D3 Negative A3/B1 or C3/D1 B2/C2 A3/B1 or C3/D1 C2/D2 A1/B1/C1/D1 (A1/A3/C1/C3) A2/B2 A3/B3/C3/D3 (B1/B3/D1/D3) ATTITUDE CONTROL SUBSYSTEM 1. Requirements Table III-21 Attitude control requirements. Disturbances Torque (Nm) Momentum (Nms) Solar Insertion Thrust 1.87E-07 0.013 1.451 4.404 Pointing Accuracy 2.91 mrad Pointing x y z 2. Range 0° Tolerance ±0.25° Rate 0• 45° 9° ±0.25° ±0.25° .5°/day 0.1°/day Final Design Table III-22 ADCS, www.ball.com . Star Tracker Quantit y Accurac y Sun Sensor Quantit y Accurac y Reaction Wheels Quantit y Max Momentum 2 10 arc sec 1 30 arc sec 4 8 Nms 52 Prior to kick motor firing, TRIANA would be spin-stabilized by the perigee kick motor. During transfer, the spacecraft would be despun to deploy the solar arrays and pointed using the thrusters. The reaction wheels would make small attitude adjustments and provide momentum storage. Since mid-course corrections and orbit insertion maneuvers will require multiple longduration burns of two attitude thrusters, angular momentum caused by the center-of-gravity offset and thruster misalignment must be stored by the reaction wheels. The torque created during these maneuvers is sufficiently large to drive the sizing requirements for the reaction wheels. Since the total momentum during orbit insertion is too great to be stored over the entire maneuver, momentum must be dumped after each burn. Once on station, attitude control would be provided by the reaction wheels. A sun sensor and orthogonal star tracker would provide attitude determination. 3. Design Approach a) Normal Operation Since it is necessary to continually point the telescope toward Earth, the pointing angle will change in a cyclic manner. Unbiased reaction wheels are best suited to this type of attitude control. Roll (z-axis) and yaw (y-axis) requirements were based on the change in pointing angle over one half the period of the halo “orbit”. In that 90 day period, the spacecraft must roll 8.58° and yaw 23.33°. Only minor pitch adjustments would be required to maintain spacecraft attitude. b) Total Moment of Inertia Moment of inertia about each axis was estimated by assuming the body to be a uniform cylinder of radius 0.521 m. Flat, continuous plates were assumed for the solar arrays. Mass was distributed between the body and solar arrays based on NASA data (64 kg for the body and 36 kg for the arrays). 53 Table III-23 Moments of Inertia. Body 8.686 Arrays 97.882 Is y 9.676 Is z 9.676 14.130 Is x c) 14.130 Total 2 106.568 kgm 2 23.806 kgm 2 23.806 kgm Characterizing Roll Motion. Roll and yaw motion were characterized to determined the torque requirements during normal operations when the telescope must be pointed toward Earth. The following example is applied to roll motion. Table III-22 summarizes the remaining results. 120,000 km Sun x Earth y z Pointing Angle Deviation 2sin 1 z - axis displacement altitude 120,000 km 2sin 1 1.6 106 km 8.58 Mean Rate d) 8.58 0.10 / day 90 days Momentum and Torque Requirements. Initially, consideration was given to external disturbance torques as the driver for reaction wheel selection. Gravity gradient and aerodynamics are neglected at L1, so the only source of toque come from the sun. Table III-24 characterizes solar disturbances. The net disturbance torque in this table has been doubled to account for torque caused by the solar wind. Even so, the torque and stored momentum are very small. 54 Further design iterations revealed that the largest disturbance will come from the attitude thrusters during the mid-course and insertion maneuvers. The propulsion design considered three thruster sizes. Table III-25 depicts torque and momentum requirements for the three thrusters. The momentum values in this table are based on the duration of burn for each thruster to produce the required delta-v (for insertion) in nine burns. The smallest thruster introduces the least torque and momentum; however, they must be fired 26 minutes per burn to produce the same delta-v in nine burns. Therefore, the 0.5 and 1.0 lbf thrusters are more suitable, and the maximum momentum value was chosen as the momentum requirement for the reaction wheels. Table III-24 On-station disturbance torque (solar). Design Factors Solar Array (North) Lever Arm Reflectivity Surface Area Solar Array (South) Lever Arm Reflectivity Surface Area 1.03 m 0.6 2 0.42 m 1.00 m 0.6 2 0.42 m Solar Force (North) Solar Force (South) 3.10912E-06 3.10912E-06 N N Solar Torque (North) Solar Torque (South) 3.20239E-06 3.10912E-06 Nm Nm Net Disturbance Torque Stored Momentum over 90 days 55 1.87E-07 Nm 1.45 Nms Table III-25 Disturbance torques caused by various thrusters during insertion and mid-course maneuvers. Thrust Cg Offset Trust Difference Insertion Torque Stored Momentum over Insertion Time e) .2 lbf 0.890 3 0.089 0.002669 .5 lbf 2.224 3 0.222 0.006672 1 lbf 4.448 3 0.445 0.013345 N cm N Nm 4.164 5.805 4.404 Nms Reaction Wheel Size A 38% margin was added to the momentum requirements from Table III-25. Final reaction wheel size is 8 Nms. G. COMMAND AND DATA HANDLING SUBSYSTEM The command and data handling subsystem (C&DH) “provides stored and ground command capability, science and engineering data formatting and packetizing, and controls all spacecraft subsystems.” (Lunar Prospector pp.53) In general C&DH weight and size is proportional to spacecraft complexity. Due to the simplicity of the Triana design the Team projects that a single-unit system that performs both telemetry and command functions is appropriate. Using the size, weight and power parametric estimation process described in SMAD (pp.390) the Triana C&DH system has the following parameters: Size: 4250cm3 Weight: 4.125kg Power: 9.5W Details required for a more robust description of the C&DH system are dependent on the refinement of the other spacecraft sub-systems. Therefore no further specification of the C&DH system will be provide for this first iteration design. 56 H. FLIGHT AND MISSION SOFTWARE 1. Final Design Limited capability on-board computer, responsible for sub-system commanding (flight software). Processing of sensor data will be performed by ground based computers located at the mission operations centers. Injection of sensor information onto the Internet will be conducted by the ground station computers. 2. Requirements Control the spacecraft sub-systems and format sensor data for transmission and processing. 3. Evolution of Design The decision to limit the capability of the spacecraft computer to sub-system controlling (flight software) was primarily made to increase reliability and decrease cost. Furthermore, manipulation of the sensor data is greatly enhanced by performing data processing at the ground stations. Unlike orbiting spacecraft, ground stations have the significant advantage of being able to upgrade hardware, and software upgrades are not limited to the amount of available processor memory, (you just add more as you need it). The primary function of the flight software is to react to and "distribute" the commands sent to the spacecraft by the ground controllers. The flight software also conducts numerous health and welfare calculations using data provided by spacecraft sub-systems. Examples of these tasks include, Attitude and spin rate computations Ephemeris computations Electrical power sub-system monitoring (battery charge, power output) Other monitoring functions associated with spacecraft health and welfare. 57 The results of these calculations are transmitted to the ground control center by the C&DH system. Mission sensor data is not processed by the spacecraft computer. Instead the "raw" data is transmitted to the ground control stations for local processing. Although the Team does not define the information transfer protocols it is projected that the raw data will be sent to a onboard buffer, and transmitted as continuous stream to the three ground stations equally spaced around the globe. In an attempt to further characterize the flight and mission software the Team chose to use ADA as the programming language. ADA was chosen due to NASA's use of the language on other spacecraft development efforts. (Lunar Prospector pp. 56) Prior use of and familiarity with ADA increases the potential of software reuse, (ADA reuse was performed on the Lunar Prospector Program). Without having conducted a detailed analysis it is estimated that Triana software will consist of approximately 100,000 lines of code (LOC) (per conversation with L. Scaglione NASA Chair, NPS). It is predicted that the Ground Software would comprise 75% of the total (75,000 LOC) , and the Flight Software would comprise 25% (25,000 LOC). 58 IV. A. MISSION PAYLOADS EARTH SENSOR 1. Requirements TRIANA’s primary mission is to provide recent images of the sun-lit side of the Earth at regular intervals displayed on the Internet. The requirements for this mission are simple. The image must be “high definition” quality at a resolution of approximately 7 km. It must also be full color (24-bit red, green and blue). Finally, a new image of the Earth must appear on the Internet “every few minutes”. Intitially, this was taken to mean approximately three minutes, but this is a surprisingly short interval since very little will change in a 7 km image in that interval, but it would be achievable under current bandwidth constraints. The refresh rates appear to be flexible, so the final design reflects a more reasonable rate. 2. Final Design TRIANA will employ three high-resolution charged coupled devices (CCD’s) in a redgreen-blue (RGB) color configuration. The optics will consist of a 22 cm schmidt-casegrain telescope with a 2.74 meter focal length. This will allow the spacecraft to achieve its primary mission of acquiring 7 km (30 arc minute) resolution Earth images. Table IV-1 Earth sensor specifications. Optics Aperture Focal Length F-number GSD IFOV FOV 0.22 2.74 12.3 7 4.37E-06 0.00896 Sensor Pixels Pixel Size Pixel Depth Sepectral Response 2048 x 2048 9.0 8 0.35 - 1.00 Weight Size Length Diameter Power m m km rad rad pixels µm bit µm 20 kg 1.01 m 0.22 m 24 W 59 Space-qualified cameras of similar specifications have already been designed and implemented in other space missions. To provide a simple, inexpensive design, the telescope would be similar to that of the narrow-angle sensor for the Mars Orbital Camera currently flying on the Mars Global Surveyor (MGS). The figure below illustrates the telescope design for the MGS mission. The aperture is twice that needed for TRIANA (40 cm), but it is conceivable to use an identical, scaled design for this mission. In order to accommodate the three CDD arrays, however, dichroic beam splitters must be placed at the end of the optical path to direct the appropriate spectral range to the proper sensor. Figure IV-1 The Mars Orbital Camera for the Mars Global Surveyor Mission, www.msss.com/mars/global_surveyor/mgs.html The 2048 X 2048 24-bit image has a raw file size of 12.6 MB. No compression is required to transmit an image of that size every three minutes over the 180 Kbps bandwidth allotted by the communications payload. It is important to note, however, that the disk of the Earth captured by the sensor occupies only 60% of the square image (2.6M pixels). Therefore, it is possible to provide some processing that would transmit only pixels illuminated by the disk of the Earth, but even this is not necessary to achieve the over-conservative requirement of 3 minutes per image. It is also more likely that a refresh interval of 10 to 15 minutes is better suited 60 to internet viewing because terrestrial activity at this resolution is not noticeable in less than 10 minutes. Extending the interval also prevents unnecessary data exchange on the Internet. Figure IV-2 The Mars Orbital Camera prior to vibration testing 3. Design Approach The TRIANA telescope would employ schmidt-casegrain reflective optics with a 0.7° field of view (FOV) similar to that of the Mars Orbital Camera. The 22 centimeter aperture would provide a resolution of 7 km. Optical specifications were determined by the following equations (SMAD, p.145). Equation IV-1 Instantaneous Field of View GSD h WhereGSD is the ground sample distance (resolution) IFOV andh is the distance from the Earth to the sensor 10 (1.6 km). 6 61 Equation IV-2 Field of View FOV N Where N is the number of pixels in one dimension on a sensor and is the instantaneous field of view (IFOV). Equation IV-3 Telescope Aperture D 1.22 Where is the center wavelength and is the instantaneous field of view (IFOV). Equation IV-4 Telescope Focal Length dh GSD Where d is the photosite dimension (one pixel), f h is the distance from the Earth to the sensor 10 (1.6 km), 6 and GSD is the ground sample distance (resolution). Equation IV-5 F-Number f D Wheref is the focal length and D is the aperture. F Two designs were considered for the focal plane. The first was a three-plane design where dichroic beam splitters would separate the image into red, green, and blue bands – each band collected by a separate 2048 x 2048 CCD array. The second alternative was a single plane design where the CCD would have the red, green, and blue bands integrated together on one array through microfiltration techniques. The second design would be simpler and could provide savings in cost, weight and power consumption provided a space-qualified product of the required size is currently available. The single plane design is the preferred choice, however, a spacequalified chip is not available at this time. The single-chip technology is patented by Eastman Kodak Company and used in commercial digital camera production. become available, it must be three times If a single-chip should the size of the three-chip design to match the 62 resolution. The savings comes in less redundancy in optics and processing since the three-chip design requires beam-spitting optics and processing for each chip. In either case, the image would be eight bits per channel, and the overall image size would be 12.6 MB per image - uncompressed. The stated requirement for transmission is to update the image of the Earth on the Internet every 3 minutes. It would take 70 seconds to transmit uncompressed image over the 180 Kbps bandwidth allotted by the communications payload. Allowing for propagation time, 105 seconds would be available for ground processing and dissemination. This may not be enough time to manage a 12.6 MB image file. It is unlikely that the casual user will be able to view a new 12.6 MB file every three minutes (nor should they want to). Two options are available to fix this problem. First, most users (including most educational institutions) have little need for a new image of the Earth every three minutes. An object on the Earth would have to travel 140 km/hr (86 mph) to move one adjacent pixel in that three minute interval. The object would also have to be 14 km in size just to notice it. It is more likely that a refresh interval of 10 to 15 minutes is better suited to Internet viewing. 2048 pi els x Ea th ril l min u tesa 2.6 mill i opix nls.e 4.2 mill i opix nls e are u n in u s e e ryv imag e e . d Figure IV-3 A typical image of the Earth from TRIANA Second, the disk of the Earth occupies only 62% of the complete 12.6 MB image. Therefore, the user is only interested in 7.8 MB of the 12.6 MB file. It is possible to use encoding schemes either in the spacecraft or at a ground station to transmit only the pixels illuminated by the Earth. Both GIF and JPEG encoding schemes would be well suited to this operation. 63 Exact weight and size values were not available at this time. Weight and size of the camera were scaled from the Mars Orbital Camera. Power consumption was based on typical values from similar imaging systems. B. ALTERNATE SENSORS 1. Requirements In a sense, once TRIANA is on orbit is on orbit, most of its mission is already over since a large part of the educational value will be in the design and construction of the spacecraft and mission architecture. Placing slightly more than a video camera one million miles from the Earth provides little additional educational value to the scientific community. To justify the expense for science education, other scientific sensors should be considered as secondary payloads. 2. Recommendations a) Geocorona The Geocorona photometers are designed to measure the Hydrogen Lymanalpha (0.12 µm) emission of the neutral atmosphere. Two geocorona sensors exist currently. Placing a third sensor from a different perspective (as TRIANA provides) would allow for threedimensional analysis of the Earth’s corona. It could be possible to use TRIANA’s telescope to provide a complete UV image of the geocorona while adding little weight to the spacecraft. b) Solar Wind Solar wind sensors provide indications of solar activity by measuring the flow of charged particles in space. Most solar wind sensors currently in operation collect solar wind data near Earth to monitor the condition of the Earth’s exoatmosphere. Having such a sensor between the sun and the Earth could provide warning of the effects of solar anomalies. Currently the Advanced Composition Explorer (ACE) has been providing solar wind data at L1 for less than a year and will continue to do so during TRIANA’s lifetime. A solar wind instrument on TRIANA could provide information supplemental to that provided by ACE. 64 V. A. COST REQUIREMENT Total mission cost less than $50 million, including launch and operations. B. ESTIMATED TOTAL COST Use of a parametric model resulted in an estimated cost as presented below. Table V-1 Total cost. Segment Space Segment Launch Segment Ground Segment Operations & Support Total (FY92$K) Triana Costs (FY92$K) $332,540.50 $24,000.00 $30,100.00 $11,125 $397,765.50 Obviously this cost projection is not within the RFI requirement of $50M and the Team does realize that this projection ($400M) is a significant overstatement of potential Triana costs. Detailed refinement of this estimate is not within the scope of this concept study, however during the conduct of the concept development the Team gained considerable insight into the actual hardware costs of particular items. Not surprisingly the actual hardware costs of particular items were relatively low, however the additional overhead associated with system integration often resulted in a 100 to 300% increase in costs. This statement is not intended to degrade the required element of system integration it is indeed a critical component of design and manufacture, however it is intended to highlight the high costs associated with program level overhead. A method that could be used to reduce that overhead is to allow a University or other educational institution to partner with NASA and industry on the actual design, construction and launch of the spacecraft and ground operations centers. The primary trade in using this approach is that labor costs are traded for schedule. That is students and faculty are the primary designers and constructors of the spacecraft, and they receive technical guidance and oversight from NASA 65 and industry representatives. Given that the academic environment is focused on learning and not production it is anticipated that this method would lengthen the Triana development schedule., however it would also better meet the education goals set forth in the RFI. Regardless of who is chosen as the prime developer the following cost analysis is presented as a point of departure for future cost discussion and it is by no means intended for use in any formal design proposal. C. COSTING APPROACH During the concept development process the Triana Concept Team considered cost as a design variable. That is while searching for and selecting components to use within the design, the Team chose the lowest cost technologies which met the performance requirements. Given that the goal was to produce a first iteration design the Team did not actively identify and then conduct in-depth cost comparisons for each proposed design solution. Instead, as previously described the Team made "cost conscious" design decisions and included cost by completing an overall system level cost estimate. a) Parametric Cost Model Description To frame the system level cost estimate the Triana Concept Team employed the parametric cost model as described in SMAD, which is a derivative of the 5 th edition of the USAF Unmanned Spacecraft Model. (SMAD Chapter 20) Fundamental to the employment of a parametric cost model is the use of cost estimating relationships (CER). CERs are mathematical functions that determine component cost from historically derived parameters. Through analysis and case study research of previously constructed satellite systems these parameters have been shown to correlate to the RDT&E and production of the theoretical first unit (TFU) cost. (SMAD pp. 723) When producing multiple spacecraft a learning curve factor/parameter would be applied to the TFU in order to account for cost decreases due to efficiencies associated with increased 66 unit production. (SMAD pp. 718) Given that Triana is a one spacecraft constellation, cost estimation beyond the TFU was not required. The primary advantage of parametric cost estimation is that it is relatively quick to execute and provides a traceable and logical path for "outsiders" to follow. The ability to quickly and accurately communicate cost relationships facilitates trade studies, design comparisons and identifies areas that may require more detailed cost analysis. Therefore, the primary benefit of parametric modeling is that system designers and users can receive direct answers to the question of "Why does the system cost this much?" Despite this significant advantage the primary downfall of parametric cost estimation is that the range of historical data used to create the CERs bound its usefulness. Given that CERs are derived from case studies of previously completed systems, they inherently can not account for systems that fall outside the historical bounds. Parameters exist that can be used to predict, based on historical evidence, the cost impact to programs that attempt to employ emerging state of the art technologies, but these values are highly situation dependent and can lead to reduced cost accuracy. Furthermore, since it is difficult to model the exact mix of components and technologies cost prediction accuracy is further degraded. Despite these draw backs, cost estimation must be performed and a method for doing so must be employed. The Team determined that use of the parametric cost method would provide a system focused cost value that would be easily traceable by outsiders. b) The Triana Cost Estimation The overall system cost estimate used a cost breakdown structure as described below. 67 Production RDT&E Space Mission Architecture Space Segment Launch Segment Ground Segment Operations & Support Figure V-1 Cost breakdown structure (after SMAD pp. 718). Costs for each of the four segments, Space, Launch, Ground, and Operations & Support were calculated for both RDT&E and TFU production. The final overall system cost is the sum of RDT&E and TFU production costs. It is also important to note that all cost values were calculated in constant year 1992 dollars. c) Space Segment Costs Space segment costs are sub-divided into three primary categories, hardware, software and program level costs. The hardware category includes cost components which make up the spacecraft itself. The CERs for these cost items are predominantly weight based. The software category provides an estimate of RDT&E costs for coding spacecraft applications. The program level cost are "associated with labor-intensive activities where a level of manpower is operating over some period of performance" and includes functions such as management, systems engineering, product assurance, and system tests. (SMAD pp. 725) The results of the space segment cost estimation are described in the following tables. Table V-2 Hardware RDT&E. Cost Component Parameter X (unit) CER (FY92$K) 68 Triana X Value Triana CER Value (FY92$K) Payload Visible Comm Antenna Comm electronics Subtotal Spacecraft Bus Structure/Thermal TT&C Attitude Control Attitude Reaction Control Power Subtotal Apogee Kick Motor 3-axis stabilized Total (FY92$K) Aperture dia. (m) 0+110791*X^0.56 .22 $47,452.73 Wt (kg) Wt (kg) 20+1015*X^0.59 0+917*X^1.0 7 10 Dry Wt (kg) Wt (kg) Wt (kg) Dry Wt (kg) Dry Wt (kg) EPS Wt X BOL Pwr (kgW) 16253+110*X^1.0 2640+416*X^.66 1955+199*X^1.0 0+3330*X^0.46 935+153*X^1.0 5303+.108*X^0.97 87.12 38.2 4 20.92 28 5384 $3219.44 $9170.00 $59,842.17 $ 25,836.20 $7,245.27 $ 2,751.00 $13,486.60 $5219.00 $5754.60 $60,292.67 Total Imp (Ns) 0+0.0156*X^1.0 48663 $759.14 $120,893.98 Table V-3 Hardware Theoretical First Unit Cost. Cost Component Parameter X (unit) CER (FY92$K) Payload Visible Aperture dia. (m) Comm Antenna Wt (kg) Comm electronics Wt (kg) Subtotal Spacecraft Bus Dry Wt (kg) Structure/Thermal Wt (kg) TT&C Wt (kg) Attitude Control Dry Wt (kg) Attitude Reaction Control Dry Wt (kg) Power EPS Wt X BOL Pwr (kgW) Subtotal Apogee Kick Motor 3-axis stabilized Total Imp (Ns) Launch Operations and Orbital Support with AKM Satellite Wet Wt (kg) Total (FY92$K) 69 Triana X Value Triana CER Value (FY92$K) 0+44263*X^0.56 0.22 $18,958.20 20+230*X^0.59 0+179*X^1 7 10 $1,630.00 $1,790.00 $ 22,378.20 $5,768.49 $3,285.20 $ 688.33 $4,072.3 $1,754.06 $ 2210.40 $17,465.06 0+185*X^0.77 0+86*X 93+164*X^0.93 0+1244*X^0.39 -364+186*X^0.73 0+183*X^0.29 87.12 38.2 4 20.92 28 5384 0+0.0052*X^1 48663 64+1.44*X^1 150 $253.01 $280.00 $40,376.27 Table V-4 Space Segment Software Development Costs (RDT&E Costs only, using ADA). CER LOC Flight Software 375*LOC Ground Software 190*LOC Total 25k 75k Cost (FY92$K) $4,750 $28,125 $32,875 This software estimate appears grossly inaccurate and therefore a selected value of $10M will be used for software development costs. Table V-5 Program Level Costs. Program Level Component Program Management Systems Engineering Product Assurance System Test & Evaluation Total RDT&E Factor % 20 40 20 20 RDT&E TFU Cost Factor (FY92$K) % $24,178.80 30 $48,357.59 20 $24,178.80 30 $24,178.80 20 $120,893.98 TFU Cost (FY92$K) $12,112.88 $8,075.25 $12,112.88 $8,075.25 $40,376.27 Triana Total (FY92$K) $36,291.68 $56,432.84 $36,291.68 $32,254.05 $161,270.25 Table V-6 Space Segment Costs. Component Hardware RDT&E Hardware TFU Software Program Level Total d) Cost (FY92$K) $120,893.98 $40,376.27 $10,000.00 $161,270.25 $332,540.50 Launch Segment Costs Launch costs were determined using values obtained from literature and Internet surveys and are $24M as described in the Launch Vehicle Section of the Mission Design chapter of this report. 70 e) Ground Segment Costs Ground segment costs vary considerably and are a function of such things as the use of legacy or in-use systems and mission unique infrastructure needs. For the Triana concept the Team chose to estimate ground segment development costs based on a "distribution of costs between software, equipment, facilities" and program level costs. The development costs were derived from a CER that relates software development costs to ground segment development costs. (SMAD pp. 729) Table V-7 Ground Segment Development Cost Model. Ground Station Element Facilities (FAC) Equipment (EQ) Software (SW) Logistics Management Systems Engineering Product Assurance Integration and Test Total f) Development Cost as % of Software Cost 18 81 100 15 18 30 15 24 Triana Cost (FY92$K) $ $ $ $ $ $ $ $ $ 1800.00 8100.00 10000.00 1500.00 1800.00 3000.00 1500.00 2400.00 30,100.00 Development Cost Cost Distribution % 6 27 33 5 6 10 5 8 Operations and Support Costs Operations and support costs were estimated using the approach set forth in SMAD (pp. 730). This approach presents cost as a function of contractor and government personnel labor rates (overhead included) as "well as the maintenance costs of the equipment, software, and facilities." (SMAD pp. 729). Table V-8 Operations and Support Cost. CER Maintenance Contractor Labor Government Labor Total 0.1*(SW+EQ+FAC)/Year $140K/Staff Year $95K/Staff Year 71 # of Years Triana 5 year Cost (FY92$K) 5 $9950.00 5 $700.00 5 $475.00 $11125.00 72 VI. A. APPENDIX SPACE SHUTTLE PRICING ALGORITHM SpaceSystemWeight CostByWeight $210 M 0.75 ShuttleCapability Space System Weight = 791.1 kg Shuttle Capability = 23090 kg 7911 . kg CostByWeight $210 M $9.59 M $10 M 0.75 23090kg 73 V BUDGET B. Heliocentric Hohmann Transfer sun = 1.327x1011 km3/s2 r1 = 1 AU = 1.495978x108 km r2 = 0.9926 AU = 1.485x108 km Vse Vse Vsl1 Vsa Vsp Vs1 Vs2 V se V sl1 = Earth velocity wrt Sun = L1 velocity wrt Sun = Apogee velocity of transfer orbit wrt Sun = Perigee velocity of transfer orbit wrt Sun = Hohmann transfer insertion velocity = L1 insertion velocity sun r1 1327 . 1011 km Vs1 Vsa L1 Vsl1 SUN EARTH Vsp Vs2 3 s2 29.783 km s 1495978 . 10 8 km 2 r2 . 10 8 km 29.564 km s 1485 365.256day 86400 s day Vsa Vsp 3 2 1327 . 1011 km 2 1485 . 10 8 km 2 sun r2 s 29.728 km s 8 8 8 r1 r1 r2 1495978 . 10 km 1495978 . 10 km 1485 . 10 km 3 2 1327 . 1011 km 2 1495978 . 10 8 km 2 sun r1 s 29.949 km s r2 r1 r2 1485 . 10 8 km 1495978 . 10 8 km 1485 . 10 8 km Vs1 Vse Vsa 29.783 km s 29.728 km s 0.055 km s Vs 2 Vsp Vsl1 29.949 km s 29.564 km s 0.385 km s Hyperbolic Earth Transfer earth = 3.986x105 km3/s2 SOI = 9.24x105 km 74 V Vei Vep V Ve1 Ve1 = Initial s/c velocity wrt Earth = Hyperbola perigee velocity wrt Earth = s/c escape velocity wrt Earth = Hyperbolic escape insertion velocity Vep Vei EARTH Vis-Viva Equation: 2 earth 2 2 1 V 2 V ep V 2 r a rep 1) Space Shuttle rep = 6678 km (300 km altitude) Vei = 7.725 km/s Vep 2 3 2 3986 . 105 km s2 0.055 km 2 s 6678km Vep 10.926 km s Ve1 Vep Vei 10.926 km s 7.725 km s 3.201 km s 2) Athena II rep = 7578 km (1200 km altitude) Vei = 7.25 km/s Vep 2 2 3986 . 105 km 7578km Vep 10.256 km s 3 s2 0.055 km 2 s Ve1 Vep Vei 10.256 km s 7.25 km s 3.006 km s 75 C. SWINGBY MISSION FILE START 0: Initial State a = 6676.93 km e = 0.000245 i = 28.5 = 0 = 337.8 TA = 142.2117 x = -3340 km y = 5106 km z = 2715 km Vx = -6.69 km/s Vy = -3.41 km/s Vz = -1.81 km/s EVENT 1: Maneuver (Earth) Impulsive/Thrust Vector (VBN) Tvelocity = 3.12 km/s Tnormal = 0 Tbinormal = 0 EVENT 2: Propagate (LunarTran model) Dist From Body = 1300000 km; Earth EVENT 3: LHLV Burn (Sun) Radial V = 0.236 km/s Tangential V = 0 Normal V = 0.05 km/s EVENT 4: Propagate (LunarTran model) XZ Cross: Earth-Centered Mean of J2000.0 EVENT 5: LHLV Burn (Sun) Radial V = -0.0055 km/s Tangential V = 0.12 km/s Normal V = -0.025 km/s EVENT 6: Propagate (LunarTran model) Duration 140 days EVENT 7: LHLV Burn (Sun) Radial V = -0.07 km/s Tangential V = 0.005 km/s Normal V = 0 V Summary: Transfer Orbit Insertion = 3120 m/s Halo Orbit Insertion LHLV Burn 1 = 241.24 m/s LHLV Burn 2 = 122.7 m/s LHLV Burn 3 = 70.2 m/s Total = 434.14 m/s 76 D. PROPELLANT MASS ESTIMATION Assumptions: mf = 100 kg (“Dry”) N2H4 Thrusters, Isp = 220 sec g = 9.81 m/s2 Estimated Total V = 465 m/s (mid-course, halo orbit insertion, stationkeeping) V I g m p m f e sp 1 465 m s 220 s 9.81m 2 s m p 100kg e 1 24.04kg 50% m arg in 50kg 77 E. KICK MOTOR COMPARISON Table VI-1 Kick Motor Comparision STAR 27E STAR 30C STAR 37XFP Performance Burn Time Total Impulse Effective Isp Burn Time Tavg Max Thrust Spin Capability 33.46 s 8.662e5 Ns 287.4 s 2.7e4 N 2.864e4 N 100 rpm 51 s 1.652e6 Ns 284.6 s 3.196e4 N 3,703e4 N 40-100 rpm 66.5 s 2.537e6 Ns 289.9 s 3.727e4 N 4.205e4 N 65-90 rpm Weight Total Loaded Propellant Diameter Length 330.76 kg 304.63 kg 0.6934 m 1.237 m 626.1 kg 586.9 kg 0.762 m 1.493 m 956.08 kg 883.68 kg 0.933 m 1.502 m Assumptions: ms/c = 100 kg (“Dry”) + 50 kg (propellant) = 150 kg madapter = 15 kg mo = ms/c + madapter + mkick motor STAR 27E mo = 150 kg + 15 kg + 330.76 kg = 495.76 kg mf = 495.76 kg - 304.63 kg = 191.13 kg m V g I sp ln mf 495.76kg 9.81 m 2 287.4s ln 2687.27 m s s 19113 . kg STAR 30C mo = 150 kg + 15 kg + 626.1 kg = 791.1 kg mf = 791.1 kg - 586.9 kg = 204.2 kg m V g I sp ln mf 7911 . kg 9.81 m 2 284.6s ln 3781 m s s 204 . 2 kg STAR 37XFP mo = 150 kg + 15 kg + 956.08 kg = 1121.08 kg mf = 1121.08 kg - 883.68 kg = 237.4 kg m V g I sp ln mf 112108 . kg 9.81 m 2 289.9s ln 4414 m s s 237.4kg 78 F. STRENGTH AND RIGIDITY ESTIMATIONS r2 r1 STRENGTH: Compression - Kick Motor Adapter Assumptions: Max Load = 8 g’s Mass = 150 kg F.S. = 1.25 cu = 110 MPa 150kg 11772 N s2 110MPa design cu 88MPa F .S . 1.25 Load Load 11772 N Area 1.3377 10 4 m 2 6 N Area 88 10 m2 Area 1.3377 10 4 m 2 t 3.554 10 5 m 0.03554mm 2 r1 r2 2 0.305m 0.294m Load 8.0 9.81 m STRENGTH: Tensile - Kick Motor Adapter Assumptions: Max Load = -2 g’s Mass = 150 kg F.S. = 1.25 tu = 40 MPa 79 Dimensions: R1 =30.5 cm R2 = 29.4 cm Area = 2t(r1 + r2) 150kg 2943N s2 40 MPa design tu 32 MPa F. S. 125 . Load Load 2943N Area Area 32 10 6 N Load 2.0 9.81 m t Area 2 r1 r2 9196 . 10 5 m 2 m2 9196 . 10 5 m 2 2.443 10 5 m 0.02443mm 2 0.305m 0.294m RIGIDITY: Fundamental Frequency - Kick Motor Adapter r1 Dimensions: R1 = 30.5 cm R2 = 29.4 cm L = 14 cm I = t(r13 - r23) r2 14 cm Axial: Assumptions: Fnatural = 30 Hz Mass = 150 kg E = 12 GPa 2 Fnat 0.250 A E Area m L Fnat m L 0.25 E 2 30 Hz . m 150kg 014 0.25 Area 2.52 10 5 m 2 9 N 12 10 m2 Area 2.52 10 5 m 2 t 6.696 10 6 m 0.006696mm 2 0 . 305 m 0 . 294 m 2 r1 r2 Lateral: Assumptions: Fnatural = 13 Hz Mass = 150 kg E = 12 GPa 80 2 Fnat 0.560 EI I m L3 Fnat 3 m L 0.56 E 2 13Hz 3 . m 150kg 014 0.56 I 1848 . 10 8 m 4 9 N 12 10 m2 I 1848 . 10 8 m 4 t 1987 . 10 6 m 0.001987mm 3 3 3 3 r1 r 2 0.305m 0.294m 81 G. STRUCTURE SUBSYSTEM WEIGHT ESTIMATE Thrust Tube (Adapter & Load Bearing Structure) Mass: 5.29 kg Volume: 0.016285.71 m3 Bounding box: X: -50.00 -- 50.00 cm Y: -50.00 -- 50.00 cm Z: -64.40 -- -1.63 cm Centroid: X: 0.00 cm Y: 0.01 cm Z: -31.29 cm Moments of inertia: X: 1.1268 kg m2 Y: 1.1268 kg m2 Z: 0.7984 kg m2 Principal moments and X-Y-Z directions about centroid: I: 0.6091 kg m2 along [0.76 -0.65 0.00] J: 0.6091 kg m2 along [0.65 0.76 0.00] K: 0.7984 kg m2 along [0.00 0.00 1.00] Outer Drum Mass: Volume: Bounding box: 14.18 kg 0.04363823 m3 X: -51.30 -- 51.30 cm Y: -51.30 -- 51.30 cm Z: -50.33 -- 49.67 cm Centroid: X: 0.00 cm Y: 0.00 cm Z: -0.33 cm Moments of inertia: X: 3.1055 kg m2 Y: 3.1055 kg m2 Z: 3.8471 kg m2 Principal moments and X-Y-Z directions about centroid: I: 3.1054 kg m2 along [1.00 0.00 0.00] J: 3.1054 kg m2 along [0.00 1.00 0.00] K: 3.8471 kg m2 along [0.00 0.00 1.00] Top Panel Mass: Volume: Bounding box: 3.33 kg 0.01027538 m3 X: -49.97 -- 50.03 cm Y: -50.02 -- 49.98 cm Z: 48.42 -- 49.72 cm Centroid: X: 1.81 cm Y: -0.02 cm Z: 49.07 cm Moments of inertia: X: 1.0349 kg m2 Y: 1.0129 kg m2 Z: 0.4395 kg m2 Principal moments and X-Y-Z directions about centroid: I: 0.2308 kg m2 along [1.00 0.00 0.00] J: 0.2076 kg m2 along [0.00 1.00 0.00] K: 0.4384 kg m2 along [0.00 0.00 1.00] 82 Main Deck Shelf Mass: Volume: Bounding box: 3.318 kg 0.01021018 m3 X: -50.00 -- 50.00 cm Y: -50.00 -- 50.00 cm Z: -1.47 -- -0.17 cm Centroid: X: 0.00 cm Y: 0.00 cm Z: -0.82 cm Moments of inertia: X: 0.20766 kg m2 Y: 0.20766 kg m2 Z: 0.41478 kg m2 Principal moments and X-Y-Z directions about centroid: I: 0.20744 kg m2 along [1.00 0.00 0.00] J: 0.20744 kg m2 along [0.00 1.00 0.00] K: 0.41478 kg m2 along [0.00 0.00 1.00] Equipment Bay Dividers Mass: 4.0775 kg Volume: 0.01254628 m3 Bounding box: X: -35.82 -- 35.81 cm Y: -35.82 -- 35.81 cm Z: -0.17 -- 48.40 cm Centroid: X: 0.00 cm Y: 0.00 cm Z: 24.12 cm Moments of inertia: X: 0.48839 kg m2 Y: 0.48839 kg m2 Z: 0.34207 kg m2 Principal moments and X-Y-Z directions about centroid: I: 0.25119 kg m2 along [1.00 0.00 0.00] J: 0.25119 kg m2 along [0.00 1.00 0.00] K: 0.34207 kg m2 along [0.00 0.00 1.00] Bottom Support Spars Mass: 0.4048 kg Volume: 0.00124558 m3 Bounding box: X: -50.05 -- 49.95 cm Y: -50.02 -- 49.98 cm Z: -50.28 -- -48.98 cm Centroid: X: -0.05 cm Y: -0.02 cm Z: -49.63 cm Moments of inertia: X: 0.14524 kg m2 Y: 0.14524 kg m2 Z: 0.09105 kg m2 Principal moments and X-Y-Z directions about centroid: I: 0.04553 kg m2 along [1.00 0.00 0.00] J: 0.04553 kg m2 along [0.00 1.00 0.00] K: 0.09105 kg m2 along [0.00 0.00 1.00] 83 H. PROPELLANT TANK SIZING Requirements: Mass of propellant = 50 kg Hydrazine density = 1.004 gm/cm3 Blowdown ratio = 3:1 50kg Volume of propellant; Vp Volume of tank; Vt 2 Vp 74700cm 3 3 1004 . g / cm 3 49800cm 3 4 r 3 r 2613 . cm 3 1 4 Vt r 3 r 16.45cm Radius of four tanks; 4 3 Radius of single tank; Vt 84 VII. REFERENCES Wiley J Larson and James R Wertz , Space Mission Analysis and Design, Second Edition, Microcosm, Inc. Roger L. Freeman, Telecommunication Transmission Handbook, Third Edition, John Wiley & Sons, Inc., 1991. John E. Prussing and Bruce A. Conway, Orbital Mechanics, Oxford University Press, 1993 LMLV Mission Planner's Guide, Lockheed Martin PAM-D User's Requirements Document, McDonnell Douglas Commercial Delta II Payload Planner's Guide, McDonnell Douglas Space Rocket Motor Catalog, Morton Thiokol, Inc. Commercial Taurus Launch System, Orbital Sciences Hydrazine Handbook, Rocket Research Company Robert Thurman and Patrick A. Worfolk ,"The geometry of halo orbits in the circular restricted three-body problem" University of Minnesota, October 25, 1996. 85