KORBA MUNICIPAL CORPORATION KORBA AUGMENTATION WATER SUPPLY SCHEME PART I UNDER UIDSSMT TENDER DOCUMENTS FOR PACKAGE III Form-“A” Name of work – Providing, laying, jointing, interconnection, testing, commissioning of Clear water Pumping main of DI pipe class K-9 & Clear water Gravity main of D.I. pipe class K-7 with valves and specials and all allied civil works Under Augmentation Water supply Scheme for Korba town Part - I under UIDSSMT Clear water pumping main : 250- 800 mm dia – 14004 m Clear water Gravity main : 200- 800 mm dia – 9322 m Including laying of pipes by push through method for railway crossings & providing and installation of full bore electromagnetic bulk flow meters to gravity mains and pumping mains including utilization of existing laid DI pipes with interconnection (Estimated Cost Rs. 2301.50 Lacs) FORM - A COST OF TENDER DOCUMENT - Rs. Office of the Commissioner Municipal Corporation, Korba Chhattisgarh Web Site : www.korbamuncipal.in E-mail : corporationkorba@gmail.com D:\533577160.doc -1- /- EXPLANATORY NOTES ON SOME IMPORTANT ISSUE RELATED TO WORKS (This is part of Tender Document) Name of work – Providing, laying, jointing, interconnection, testing, commissioning of Clear water Pumping main of DI pipe class K-9 & Clear water Gravity main of D.I. pipe class K-7 with valves and specials and all allied civil works Under Augmentation Water supply Scheme for Korba town Part - I under UIDSSMT Clear water pumping main : 250- 800 mm dia – 14004 m Clear water Gravity main : 200- 800 mm dia – 9322 m Including laying of pipes by push through method for railway crossings & providing and installation of full bore electromagnetic bulk flow meters to gravity mains and pumping mains including utilization of existing laid DI pipes with interconnection 1. Security Deposit : 2. Mobilization Advance : 3. Water for testing, trial run : and construction 4. Price escalation 5. Right of way for laying of : pipe line and constructions 6. Permissions from other. Department 7. Excise. exemption D:\533577160.doc : The Security deposit shall be deducted as per clause 1 of form A given in NIT The mobilization advance shall be paid as per the conditions of the contract. The water for testing and trial run of pipe line will be made available by the department. free of cost. In case of delay in making available the water for testing the extension in time will be granted to the contractor without penalty for such period. The water for construction shall be arranged by the contractor at his cost. The price variation condition shall not be applicable in this contract. The department. shall provide hindrances free alignment and required space for laying of pipe lines and construction of allied works. The department shall pay the land acquisition charges, if required : The CONTRACTOR shall obtain the permissions for Railway crossing, Telephone line crossing, road cuttings, road crossings from t he concerning Authority in case the shifting of Electric Pole is found necessary the same Shall be got shifted by the department. through CGPDCL. The service connections shall not be removed, the contractor will have to lay the pipe lines without any damage to the service lines. In case the shifting of existing water pipe lines/sewage lines is considered necessary, the same Shall be shifted by the contractor for which the payment shall be made for actual work done as per tender rate. In case there is damages to service lines, the same shall be restored by the contractor or it will be got restored through concerning agency and the cost will be recovered from the contractor's bills In case there is delay in obtaining the permission fr om Others .including local and private agencies, the extension in time shall be granted, but no claim shall be entertained on this account. No revised rate shall be given for any item of work given in schedule of quantity and Applicable SORs. The department will not provide the underground utility drawings for Water lines, electric lines, telephone cables and other utility services. The contractor should see the location of these utility services at site prior submitting the revised offer. to The certificate for exemption of excise duty for items in Govt . of India Notification No.6-Central Excise dt.01.03.2006 with all amendments -2- up to the date of issue of N.I.T. shall be provided by the Department . Deviation in Length, dia The deviation in length of pipe line, dia of pipe line and pipe fittings etc. shall be paid/deducted on the approved tender rates As per class of pipe line and pipe gff 13 of form-A given in the NIT. fittings etc. Secured Advance The Secured advance against the security of materials brought at site shall be sanctioned up to an amount not exceeding 75% of the value but 90% in case of steel (assessed by the Executive Engineer) provided the material are of imperishable nature and a formal agreement is drawn up with the contractor under which KMC secures a lien on the material and is safe guarded against losses Due to the contractor postponing the execution of the work or to the shortage or misuse of the materials, and against the expense entitled for their proper watch and safe custody. The recoveries of advance shall be made from the running account bills, for work done as the materials are used, the necessary deductions being made whenever the item of work in which they are used are billed for The contractor shall sign the prescribed indenture bond in the Prescribed form. The provisions of clause 11 "B"of form "A" given in NIT and CPWA code para 10.2.22 (a) shall apply for the sanction and recovery of secured advance. 8. 9. 10. : The Plan showing the location of pipe line, Nallah crossing, lines, road crossing is already enclosed in the compact disk (CD) issued with tender documents. Sluice valves, air valves and scour valves shall be Location of valves & Nallah crossing provided at location as per guide lines given in CPHEEO Manual 1999 11. : The period of completion is 18 months including rainy season as given Period of completion in NIT. 12 : No separate payments shall be made on account of changes in site Changes as per site conditions condition. The payments shall be made as per condition of contract. 13. Inspection of pipes, valves & DI Specials 14. Taxes All pipes, valves and specials shall be ISI mark duly inspected by DGS & D/SGS/RITES "All dues regarding taxes including the service tax, sales tax, labour welfare tax other duties etc. levied on the contractor works by Govt. and local bodies or private individuals will be payable by the contractor. The Engineer'-in-charge will grant a certificate for the quantities actually used on the work, but will not entertain any claim on this account 15. Break up schedule of payment This is a percentage rate tender and the intermediate payment shall be paid as per clause 7 and 8 of form "A" given in the NIT. 16. Change in Technical 17. Submission of completion drawing with hard & soft copies in necessary three sets. D:\533577160.doc : It shall be as per clause -13 of form A of NIT Specification : Contractor will submit progress of the work every month a l o n g wi t h s h o wi n g d i a m e t e r & c e n t e r l i n e alignment of completed pipe line reference to boundary of houses on each road incorporating all details & land-mark in 3 hard copies accompanied with soft copy. -3- 18. Restoration of roads The road restoration work shall be as per clause 14.00 of annexure -E 19. Rates of non scheduled The rates of non schedule items of work shall be decided as per Items of work and rates for RCC chambers 20 Back filling & testing of provision given in clause 12 of form `'A" given in NIT. SOR rate The SOR rates should be seen by the contractor in SOR's made applicable in this contract before submitting the revised offer The back filling of trenches as per IS 12288-1987 specification shall be . Done as early as possible after completion of laying of pipe lines. The The joints shall not be kept opened for inspection. However in road sand Crossing the back filling shall be done by totally dry or fully saturated : pipe line/joints for which payment shall be made for actual work done as per instruction of Engineer-in-Charge. 21. Construction of valve Chamber : Construction of valve chamber and providing and fixing of valve should be done simultaneously along with the work of laying of pipe line as per CFHEEO Manual 1999. 22. Space required for : The department Shall not provide the space for storage of pipes Excavated soils and valves. It will be the responsibility of the contractor storage of excavated to arrange the space for storage of such materials. soils, pipes etc . 23. . Issues of Pipes, valves and specials : . The pipes, valves and specials shall be procured by the contractor as per enclosed schedule. The labour rate shall be given for laying and fixing of these items. The transportation charges for these materials will not be payable to the contractor. 24 B ot t om wi dt h of tr enc h : T h e wi d t h of t he tr e nc h at b ot t om s h a ll be s uc h as t o provide not less than 300 mm clearance on either side of the pipe except where rock excavation is involved. 25 Insurance : 26. Procurement of Pipe valve : Insurance on total contract price for the period of contract shall be done by the contractor. Department. shall make payment for the quantities of fitting and other material executed, measured and valued as per the conditions of contract. The contractor should procure the materials after making assessment of the quantities of materials actually required as per site condition. Deptt shall not be responsible for extra quantities brought at site by the contractor. The thrust block shall be designed for a pipe line pressure of 15kg/sq cm. 27. Thrust block : 28. Quantities of valves and DI Specials 29. Excavation in Concrete : : Approximate quantities of C I sluice valves and D I fitting shall be as given in schedule of quantity in NIT. All excavation in concrete road shall be done compulsorily by using blade type Concrete cutter or needle cutter (needle size not more than 32 mm dia) for cutting of concrete portion. Commissioner Municipal Corporation Korba (C.G.) D:\533577160.doc -4- I N D E X S. No. 1. Contents Pages From – To 6 Salient Feature of Tender 2 Notice Inviting Tender (In English) 7-11 3 Detailed Notice Inviting Tenders 12-21 4 Annexure - “A”- Model Rules relating to labour, water 22 supply and sanitation etc 5 Annexure - “B”- Contractor’s Labour Regulations 23 6 Annexure “C” - Statement showing the lead of 23 materials 7 Annexure - “D”- Form of Income Tax Clearance 24 Certificate (Applicable to works costing more than Rs.2.00 Lakhs) 8 Form – A 25-26 9 Annexure “E”- Brief specifications 53-60 10 Annexure “F” - Schedule of quantity 61-78 11 Annexure “G” - Form of Bank Guarantee & Special Conditions of the Contract 12 Annexure “H” - INFORMATION & INSTRUCTIONS TO THE BIDDERS FOR ONLINE ELECTRONIC GOVERNMENT PROCUREMENT SYSTEM (eGPS). D:\533577160.doc -5- 79- SALIENT FEATURE OF TENDER 1. Name of work 2. Name of contractors Providing, laying, jointing, interconnection, testing, commissioning of Clear water Pumping main of DI pipe class K-9 & Clear water Gravity main of D.I. pipe class K-7 with valves and specials and all allied civil works Under Augmentation Water supply Scheme for Korba town. (i) Clear water pumping main : 250- 800 mm dia – 14004 m (ii) Clear water Gravity main : 200- 800 mm dia – 9322 m Including laying of pipes by push through method for railway crossings & providing and installation of full bore electromagnetic bulk flow meters to gravity mains and pumping mains including utilization of existing laid DI pipes with interconnection A. Class of Contractor registered in Appropriate Class B. Postal Address C. Telephone Number & Fax number if any 3. Probable amount of contract Rs. 2301.90 Lacs 4. Earnest Money Rs. 1155000.00 5. Date of Issue 05.09.2014 6. Money receipt no. and date Note - This tender document with Annexure and notice inviting tender shall be part of the agreement. Signature and seal of contractor/firm Or his authorized representative Commissioner Municipal corporation Korba, Chhattisgarh D:\533577160.doc -6- Office of the Commissioner Municipal Corporation Korba (C.G.) NIT No. 879/2014/SAC Korba, dated 05.09.14 SHORT NOTICE INVITING TENDERS Online tender are invited from the Commissioner, Municipal Corporation, Korba for the following work in form “A” contract from the contractors registered in unified registration (single window) in force from C.G. Govt. for similar work on Go C e-Procurement System (https://cgeprocurement.gov.in) through Sub Portal https://uadd.cgeprocurement.gov.in S. no . 1 1 Name of work Probable amount of contract Earnest money 2 3 2301.90 Lacs 4 11.55 Providing, laying, jointing, interconnection, testing, commissioning of Clear water Pumping main of DI pipe class K-9 & Clear water Gravity main of D.I. pipe class K-7 with valves and specials and all allied civil works Under Augmentation Water supply Scheme for Korba town. (i) Clear water pumping main : 250- 800 mm dia – 14004 m (ii) Clear water Gravity main : 200- 800 mm dia – 9322 m Including laying of pipes by push through method for railway crossings & providing and installation of full bore electromagnetic bulk flow meters to gravity mains and pumping mains including utilization of existing laid DI pipes with interconnection Time allowed for completion (including rainy season) 5 18 months Bid submission Fees 6 4240/payable at the time of Bid Preparation and Hash Submission through online payment Gateway Validity of offer (from the date of opening of financial offer) 7 120 days Excluding the code of conduct period Clas of Contractor 8 In Appropriat e Class The tender documents containing detailed terms & conditions are available for free download on Goc eProcurement portal http://cgeprocurement.gov.in through sub portal of Urban Administration & Development Department http://uadd.cgeprocurement.gov.in Bidders have to quote online their prices along with Technical and Commercial bids in prescribed formats on the above mentioned portal only. The Bidders intending to participate in this Tender are required to get enrolled on the above mentioned website and get empanelled on the Sub – Portal of Urban Administration & Development Department. Enrolment on the above mentioned Portal is mandatory. As the online Bids are required to be digitally signed, Bidders are required to obtain Class – II Digital Signature Certificates (DSCs). The Bidders may contact M/s NexTenders (India) Pvt. Ltd., for obtaining Class – II Digital Signature Certificates at M/s NexTenders (India) Pvt. Ltd. 'Saket', B-31, Shailendra Nagar, Raipur - 492001, Tel. No. +91 771 4079400, +91 711 4221020, Fax No. +91 711 4221023or through Email ID – raipur@nextenders.com. D:\533577160.doc -7- The Bidders are also invited to get themselves trained on the operations of the e-Procurement System. Bidders may get in touch with the Service Provider of the e-Procurement System for confirming the time and date for their training session. All the contractors are required to submit Envelope “A” physically containing the following:The Earnest Money, of Rs. 11.55 Lacs (Rs. Eleven Lacs Fifty Five Thousand Only) in favour of the Commissioner, Municipal corporation, Korba. The Earnest Money of the successful tenderer will be retained as part of the Security Deposit. The Earnest Money deposit will be returned to the unsuccessful tendered after award of contract. fufonk izi= izkIr djus gsrq vgZrk ekin.M %& 1- iath;u %& (a) mi;qDr Js.kh esa iath;u vko';d gS vFkok fof'k"V izd`fr (Sepcialised nature) ds dk;Z@dk;ksZ gsrq lacaf/kr izd`fr ds fof'k"V Js.kh@Jsf.k;ksa esa iath;u vko';d gSA (b) lkeku izd`fr ds dk;Z djus okys vuqHkoh fufonkdkj@QeZ fufonk esa Hkkx ys ldrs gS] fdUrq vuqca/k ds iwoZ N-x-'kklu }kjk izpfyr ,dhd`r iath;u iz.kkyh esa iath;u djkuk vko';d gksxkA 2- dk;Z dk fu"iknu {kerk %& dk;Z fu"iknu {kerk = A x N x 2.0 Where (A) – fiNys 10 o"kksZ esa fd;s x;s dk;Z dh vf/kdre jkf'k ¼10 izfr'kr vf/kHkkj izfro"kZ lfgr½ Where (N) – dk;Z iw.kZ djus dh fu/kkZfjr vof/k ¼o"kksZ esa½ 3- dk;Z dk vuqHko %& Loa; ds uke ij vFkok QeZ ,oa daiuh ds uke ij dk;Z dk uke de ls de lkekU;r% 60 izfr'kr ek=k dk fufonkdkj dks vuqHko gksuk pkfg,A fdlh ,d vuqca/k ds varxZr fufonk esa nf'kZr ikbi ykbu ds vf/kdre O;kl ds de ls de 50 izfr'kr O;kl yEckbZ vFkok fufonk nLrkostksa esa nf'kZr ikbi ykbZu dk;Z dh dk;Z jkf'k ls 40 izfr'kr dk ¼10 izfr'kr vf/kHkkj izfro"kZ lfgr½ ,d vuqca/k ds varxZr djus ds vuqHko vFkok foLr`r fufonk ds ¼3½ ds fooj.k vuqlkjA TECHNICAL PREQUALIFICATIONCRITERIA PACKAGE IIII Clear Water Pumping Mains, Pipe Pushing For Railways, Clear water gravity Main & Bulk Flow Meters Sr. Particulars Component Pre Qualification Cost of No. Capacity Capacity Compone nt 1 Clear Water 14004m Firstly 400mm Dia DI 1235.76 Pumping Mains K-9 Pipes 7000m Lacs Onwards Shall be considered, if there is less response then following sub breakup shall be considered 800mm Dia DI K-9 2487m 400mm Dia DI K-9 Pipes Pipes 1244m Onwards 400mm Dia DI K-9 5132m 200mm Dia DI K-9 Pipes Pipes 3590 m Onwards 350mm Dia DI K-9 2043m Pipes 300mm Dia DI K-9 2707m 150mm Dia DI K-9 Pipes Pipes 2173m Onwards 250mm Dia DI K-9 1635m Pipes D:\533577160.doc -8- 2 Railway Pipe Pushing 3 Clear Water Gravity Main 4 800mm Dia DI K-7 Pipes 700mm Dia DI K-7 Pipes 600mm Dia DI K-7 Pipes 500mm Dia DI K-7 Pipes 450mm Dia DI K-7 Pipes 400mm Dia DI K-7 Pipes 350mm Dia DI K-7 Pipes 300mm Dia DI K-7 Pipes 250mm Dia DI K-7 Pipes 200mm Dia DI K-7 Pipes Full Bore Electromagnetic Bulk Flow Meters Note:- a) b) c) Carrier Pipe 600mm Dia MS Pipe & Casing Pipe 1200mm Dia MS Pipe 230m Total Length 9322m 477m 371m 28m 1715m Carrier Pipe 300mm Dia MS Pipe & Casing Pipe 600mm Dia MS Pipe 115m 170.39 Lacs Firstly 400mm Dia DI Pipes 4661m Onwards shall be considered, if there is less response then sub breakup shall be considered 400mm Dia DI Pipes 240m & Onwards 350mm Dia DI Pipes 185m & Onwards 300mm DI Pipes 14m & Onwards 250mm DI Pipes 885m Onwards 832.99 Lacs 45m 700m 200mm DI Pipes 936m Onwards 1176m 4717m 150mm DI Pipes 2390m Onwards 57m 36m 100mm DI Pipes 18m Onwards 100 to 300mm Dia 23 Nos 46 Nos 62.76 Lacs No Joint ventures shall be allowed for the bidding process The experience for last ten years shall only be considered for prequalification criteria Regarding above tender details information available in water supply section Municipal Corporation Korba (C.G. Commissioner Municipal Corporation Korba D:\533577160.doc -9- CLEAR WATER PUMPING MAINS, GRAVITY MAINS, PIPE PUSHING & BULK FLOW METERS FINANCIAL PREQUALIFICATION AS PER LATEST NORMS To qualify in the Tender each Tendered must have in last Ten years Cost of Rs. In Package I Lacs 2301.90 1 Rs. In 1380.90 (a) Achieved in "any one financial year" a financial turnover (in all Lacs classes of construction works related to water pipelines) value of construction work of at least 60% (Sixty percent) the amount equal to the probable amount of contract for which bid has been invited. & 2 Rs. In (b) Satisfactorily completed at least one similar work equal in value 40% (forty percent) of the Probable amount of contract as on date of Lacs submission of financial offer. 920.76 OR 3 Rs. In Lacs 920.76 (iii) Satisfactorily executing at least one similar work having received Rs. In Lacs payment of value not less than 40% (forty percent) OR two similar works having received aggregate payment of value not less than 40% (forty percent) of the value of probable amount of contract as on date of submission of financial offer. 920.76 (ii) Satisfactorily completed at least two similar works total costing equal to value 40% (forty percent) of the probable amount of contract for which the tender is invited as on date of submission of financial offer. OR 4 OR 5 6 7 (iv) One similar work completed & satisfactorily executing one similar work Total aggregate value in both the works shall be minimum 40%(forty percent) of the value of probable amount of contract for which tender is invited as on date of submission of financial offer. Note :- 1) The turn over shall be indexed at the compounded rate of 10% (Ten percent)for each earlier years. (ii) The value of completed work shall be updated to the value of current financial year @ compounded rate of 10% (Ten percent) per year from completion year of work, Rs. In Lacs (iii) Similar work mean Pipe lines/Water treatment Plant/Building/ Over Head Tanks as the case may be. The Tender should be accompanied by the following Pre-Qualification Documents duly attested. 1. Proof of registration in commercial tax department. 2. Valid registration certificate. D:\533577160.doc - 10 - 920.76 3. Experience certificate of successful completion of work of same nature in contractor’s/firm’s/company’s own name indicating agreement no., work order no. and date, amount of contract, stipulated period of completion, actual period of completion during last ten year i.e. 2004-2005 to 2013-2014. The certificate should be issued by an officer not below the rank of Executive Engineer. 3(a) futh@lkoZtfud miØe {ks=ksa esa fd, x, dk;Z gsrq foHkkxh; vf/kdkjh& dk;Zikyu vfHk;ark ;k mPp Lrj }kjk tkjh izek.k i= dks lacaf/kr Bsdsnkj fufonk dh izfØ;k esa dk;Z vuqHko izek.k i= ds :i esa izLrqr dj ldsaxs] ftls fufonk izfØ;k esa ekU; fd;k tkosxkA 4. The details of works in hand indicating name of work, Agreement no., work order no., and date, amount of contract, period of completion, value of work and balance work in hand with details of work on the date of submission of Tender. 5. Financial turn over during last five years i.e. 2009-10 to 2013-14. 6. List of available tools and plants for successful completion of work. 7. The Department reserves the right to change the Key dates of the Tender Process. 8. Registration Certificate “Chhattisgarh Building and other construction welfare Board” A) Cess @ 1% (One percent only) shall be deducted at source, from every bill of contractor by Executive Engineer under “Building and other Contraction for workers welfare, cess Act1996” B) It is mandatory for the contractor (s) to get himself theme selves registered with “Chhattisgarh Building and other construction welfare Board” for work amounting to Rs. 10.00 lakhs (Rs. Ten Lakhs) and above and enclosed a true copy of such registration certificate along with the tender, otherwise his/their tender shall not be considered for qualification. Note:- For details on tendering procedure through the electronic tendering system, please refer to “Instructions for Using the Electronic Tendering System” document available along with the tender documents. Commissioner Municipal corporation Korba, Chhattisgarh Endt. No.879/2014 Korba/Dated : 05.09.14 Copy forwarded to :1. ....................................................................................... 2. ....................................................................................... 3. ....................................................................................... 4. Notice Board. Commissioner D:\533577160.doc - 11 - Municipal corporation Korba, Chhattisgarh APPENDIX 2.10 (CHAPTER II) (Appendix 2.10) (See paragraph 2.079) MUNICIAL CORPORATION KORBA DETAILED NOTICE INVITING TENDERS (In Form A.B.C. ) DATE OF ISSUE OF N.I.T… 05.09.2014 DATE OF RECEIPT OF TENDER … - 30.09.2014 1. INTRODUCTION 1.1 Online tender are invited from the Commissioner, Municipal Corporation, Korba for the following work in form “A” contract and will be received up to 30.09.2014 of 5.30 P.M. from the contractors registered in unified registration (single window) in force from C.G. Govt. for similar work on Go C g e-Procurement System (https://cgeprocurement.gov.in) through Sub Portal https://uadd.cgeprocurement.gov.in Sr. No 1 1 Name of work Probable amount of contract Earnest money Time allowed for completion (including rainy season) Bid submission Fees 2 3 2301.90 Lacs 4 11.55 5 18 months 6 4240/payable at the time of Bid Preparation and Hash Submission through online payment Gateway Providing, laying, jointing, interconnection, testing, commissioning of Clear water Pumping main of DI pipe class K-9 & Clear water Gravity main of D.I. pipe class K-7 with valves and specials and all allied civil works Under Augmentation Water supply Scheme for Korba town. (i) Clear water pumping main : 250- 800 mm dia – 14004 m (ii) Clear water Gravity main : 200- 800 mm dia – 9322 m Including laying of pipes by push through method for railway crossings & providing and installation of full bore electromagnetic bulk flow meters to gravity mains and pumping mains including utilization of existing laid DI pipes with interconnection Validity of offer (from the date of opening of financial offer) 7 120 days Excluding the code of conduct period Class of Contractor 8 In Appropriate Class Registration and subsequent empanelment on the above mentioned website and department’s sub-portal is mandatory. D:\533577160.doc - 12 - The Bidders have to digitally sign their bids before submitting the bids hashes online. Thus the Bidders are advised to obtain Digital Certificates. The registered contractors may obtain information required for issuance of a Class II Digital Signature Certificate from the Controller of Certifying Authorities (www.cca.gov.in) or the Service Provider of Procurement System for Government of Chhattisgarh: Wipro Limited in consortium with NexTenders (India) Pvt. Ltd. M/s NexTenders (India) Pvt. Ltd. 'Saket', B-31, Shailendra Nagar, Raipur - 492001, Tel. No. +91 771 4079400, +91 711 4221020, Fax No. +91 711 4221023or through Email ID – raipur@nextenders.com. Validity of offer - 120 days (Excluding the code of conduct period) from date of opening of financial offer 1. The Technical offer shall be opened in presence of the Bidders or their authorized representatives, who may choose to be present. The date and place of opening of financial offer will be intimated to the Bidders subsequently after opening of technical offer. 2. The contractors are required to submit ‘Envelope “A” physically as per dates Indicated in Key Dates. The Physical Envelope’A’ should contain the following: The Earnest Money, of Rs. 11.55 Lacs (Rs. Eleven Lacs Fifty five Thousand only) in favour of the Commissioner, Municipal Corporation, Korba which will be returned to the unsuccessful Bidders. The Earnest Money of the successful Bidders will be retained as part of the Security Deposit. fufonk izi= izkIr djus gsrq vgZrk ekin.M %& 1- iath;u %& A(a) mi;qDr Js.kh esa iath;u vko';d gS vFkok fof'k"V izd`fr (Sepcialised nature) ds dk;Z@dk;ksZ gsrq lacaf/kr izd`fr ds fof'k"V Js.kh@Jsf.k;ksa esa iath;u vko';d gSA (b) lkeku izd`fr ds dk;Z djus okys vuqHkoh fufonkdkj@QeZ fufonk esa Hkkx ys ldrs gS] fdUrq vuqca/k ds iwoZ N-x-'kklu }kjk izpfyr ,dhd`r iath;u iz.kkyh esa iath;u djkuk vko';d gksxkA 2- dk;Z dk fu"iknu {kerk %& dk;Z fu"iknu {kerk = A x N x 2.0 Where (A) – fiNys 10 o"kksZ esa fd;s x;s dk;Z dh vf/kdre jkf'k ¼10 izfr'kr vf/kHkkj izfro"kZ lfgr½ Where (N) – dk;Z iw.kZ djus dh fu/kkZfjr vof/k ¼o"kksZ esa½ 3- dk;Z dk vuqHko %& Loa; ds uke ij vFkok QeZ ,oa daiuh ds uke ij dk;Z dk uke de ls de lkekU;r% 60 izfr'kr ek=k dk fufonkdkj dks vuqHko gksuk pkfg,A fdlh ,d vuqca/k ds varxZr fufonk esa nf'kZr ikbi ykbu ds vf/kdre O;kl ds de ls de 50 izfr'kr O;kl yEckbZ vFkok fufonk nLrkostksa esa nf'kZr ikbi ykbZu dk;Z dh dk;Z jkf'k ls 40 izfr'kr dk ¼10 izfr'kr vf/kHkkj izfro"kZ lfgr½ ,d vuqca/k ds varxZr djus ds vuqHko vFkok foLr`r fufonk ds ¼3½ ds fooj.k vuqlkjA 3. The Key Dates of Tender are :- Seq PHD Stage No 1 Release of NIT 2 - 3 - 4 Close Expiry Date & Time - 22.08.2014 04.09.2014 Tender Download 05.09.2014 30.09.2014 05.09.2014 30.09.2014 30.09.2014 03.10.2014 Submission of Bid Hash and Payment Bidding Conditions D:\533577160.doc Start Date & Time Supplier Stage for General - - 13 - 5 - Bid Submission Online 04.10.2014 07.10.2014 6 Opening of Envelope - PQ - 08.10.2014 10.10.2014 7 Short listing of Envelope -PQ - 10.10.2014 20.10.2014 - 21.10.2014 23.10.2014 - 21.10.2014 23.10.2014 - 23.10.2014 30.10.2014 31.10.2014 03.11.2014 31.10.2014 03.11.2014 03.11.2014 05.11.2014 06.11.2014 10.11.2014 - 11.11.2014 18.11.2014 - 11.11.2014 18.11.2014 8 9 10 Opening of EMD & T and C. & Short listing of EMD Short listing of Terms and Conditions Preparation of Common set of Conditions Download of common set of 11 - 12 - 13 Close for Bidding Revised Offer. - 14 - 15 16 conditions. Submission of Bid Hash of Revised Offer. Bid Submission Online of Revised Offer. Opening of Acceptance of Common set of conditions Short listing of Common set of conditions 17 Opening of Revised offer - 11.11.2014 18.11.2014 18 Short listing of revised offer - 11.11.2014 18.11.2014 19 Opening of Original Offer - 11.11.2014 18.11.2014 20 Short listing of Original Offer - 11.11.2014 18.11.2014 21 Tender Award - 19.11.2014 18.12.2014 4. Other condition including qualification and details of work can be seen in the office of the undersigned during office hours and downloaded online directly from the portal http://cgeprocurement.gov.in through Urban administration & Development Department sub portal and shall be submitted online on or before 30.09.2014 up to 17:30 P.M. This NIT shall also form the part of agreement. The details can be viewed on the website http://uadd.cgeprocurement.gov.in from 05.09.2014, 17:31 PM onwards. 5. For details on tendering procedure through the electronic tendering system, please refer to “Instructions for Using the Electronic Tendering System” document available along with the tender documents. The Bidders are also invited to get themselves trained on the operations of the e-Procurement System. Bidders may get in touch with the Service Provider of the e-Procurement System for confirming the time and date for their training session. 2. R A T E S : 2.1 The schedule of items :The schedule of main items of work to be executed is enclosed as Annexure (F). D:\533577160.doc - 14 - 2.2 Percentage rate tender in form “A” or “C” 2.2.1 In respect of percentage rate tenders, contractor should quote his separate tender percentage rate above or below the following schedules of rate "Unified schedule of rates (Part-I) for water supply, sewerage works issued by Engineer-in-Chief, PHED, Raipiur Chhattisgarh in force from 07.02.2013 with up to date amendments." “The S.O.R. for building works issued by Engineer-in-Chief P.W.D. Raipur in force from 01.06.2009 for and adopted by Engineer-in-Chief, P.H.E.D., C.G. vide his letter no. 156/Estt dated 19.08.2009 with all amendment issued up to date of issue of N.I.T.” 2.2.2 (For Form “A” only) The percentage of tender above/below or as per with the relevant schedule rates inclusive of amendments and correction slips issued up to the date of the notice inviting tenders should be expressed on the tender form itself both in words and figures in such a way that interpolation is not possible and all over writings should be neatly scored out and rewritten and the corrections should be duly attested prior to the submission of tender. Tenders not specifying percentage in words will summarily be rejected. Any amendments to the schedule of rates after the date of issue of this tender notice or the date of issue of any amendments to the N.I.T., specifically notifying the said amendment to the current schedule of rates, shall not apply to this tender. 2.2.3 The percentage tendered by the contractor will apply to those rates which find place in the current schedule of rates mentioned in clause 2.2.1, or have been derived from the said current schedule of rates and not to other items of work. 2.2.4 The percentage quoted by the contractor shall not be altered by the contractor during the terms of contract. The deduction or addition as the case may be of the percentage will be calculated on the amount of the bill for the work done, after deducting the cost of materials supplied departmentally at rates specified in the agreement. 2.3.1 Items Rate Tenders in form “B”. In respect of items rate tenders, contractor should quote his rates for the items mentioned in the schedule of item in Annexure-F of this N.I.T. Only rates quoted shall be considered. The rates should be expressed in figures as well as words and the unit should be as given by the Department. The contractor will not have the freedom to change the unit. No percentage above or below the schedule be quoted. 2.3.2 The rates quoted in the tender for various items of work will not be altered by the contractor during the term of contract. 2.4 LEAD AND LIFT OF WATER - No lead and lift for carting of water will be paid. 2.5 LEAD AND LIFT OF MATERIALS - No lead and lift for carting of materials shall be payable to the contractor except in case of such items for which specific lead and lift are provided in the current schedule of rates mentioned in clause 2.2.1 of the N.I.T. or in the schedule of items in respect of item rate tenders. 2.6 NON SCHEDULE ITEMS OF WORKS - During the execution of the work there is likelihood of such items of work, which do’not find place in the current schedule of rates, referred to above in respect of percentage rate contracts or such items which are given in the schedule of items in respect of item rate contracts, for which contractor has not quoted his rates. Contractor will have to carry out these items of work. Rates of such items of work which do not find place in the current schedule of rate referred to above, in respect of percentage rate contracts or such items in respect of item rates contracts shall be decided by the Commissioner, municipal corporation, Korba and the decision of the Commissioner, municipal corporation, Korba shall be binding on the contractor. The quantum of such work will not exceed 10% of amount of contract unless accepted by the department and the contractor. D:\533577160.doc - 15 - 3.0 SUBMISSION OF TENDER : 3.1 The Physical Earnest money which is to be submitted manually in Physical Envelope - A where it should be clearly written on the envelope as under :ENVELOPE - A EARNEST MONEY From - (… Name of Contractor…) and should reach Commissioner, municipal corporation, Korba, as per date and time mentioned in the key dates. 3.2 ENVELOPE – B The Second online envelope shall contain terms and conditions and all the technical details and specifications, Scanned copy of terms and conditions, technical specifications and drawings etc. should be submitted online in envelope "B". ENVELOPE – C This Envelope should contain only the Percent Rate Offer. The Tenderer shall fill their Percent Rate in the online form. 3.3 Rate (At par SOR or ...............percent below/above SOR) From - (… Name of Contractor…) D:\533577160.doc - 16 - 3.4.1 EARNEST MONEY IN SEPARATE COVERS: The Earnest Money in one of the prescribed forms should be produced/sent separately and not kept in the covers containing the tender and if the earnest money is not found in accordance with the prescribed mode the tender will be returned unopened to the tendered. In shape of Demand Draft/ Bankers Coequal/ FDR of minimum 12 months duration from Nationalist bank or scheduled bank drawn in the favors of “The Commissioner, Korba Municipal Corporation, Korba” payable at Korba. 3.5 ADJUSTMENT OF EARNEST MONEY :Earnest money, which has been deposited for a particular work, will not, ordinarily, be adjusted towards the earnest money for another work, but if the tender of contractor for a work, in the same department has been rejected and the earnest money has not been refunded to him due to any reason, it may be so adjusted by the Executive Engineer. 3.6 SECURITY DEPOSIT :(a) The security deposit shall be recovered from the running bills @ 5 percent as per clause-1 of the agreement read with para 3.5 of the N.I.T. (b) The amount of the E.M. shall not be adjusted when value of work done reaches the limit of the amount of contract or exceeds the probable amount of contract. 3.7 IMPLICATION OF SUBMISSION OF TENDER: Tenderness are advised to visit site sufficiently in advance of the date fixed for admission of the tender. A tenderer shall be deemed to have full knowledge of the relevant documents, samples, site etc., whether he inspects them or not. 3.8 The submission of a tender by a contractor implies that he has read the notice, conditions of tender and all other contract documents and made himself aware of the standards and procedure, in this respect, laid down in the National Building Code of India 1970/Indian Standards the scope and specification of the work to be done and the conditions and rates at which stores, tools and plants etc., will be issued to him by the Executive Engineer has seen the quarries with their approaches, site of work, etc. and satisfied himself regarding the suitability and availability of site of work etc. and satisfied himself regarding the suitability and availability of the materials at the quarries. The responsibility of opening new quarries and construction and maintenance of approaches there to shall lie wholly with the contractor. 3.9 Income Tax clearance certificate – A tendered purchasing tender documents for works exceeding Rs.2.00 Lacs shall submit either an Income Tax Clearance Certificate in the form printed as annexure D or a certificate from the Income Tax authority that the assessment is under consideration. No tender documents can be issued/sold to him unless such certificate is submitted. 3.10 List of works in progress – Tenders must be accompanied by a list of contracts already held by the tenderer at the time of submitting the tender, in the Department and elsewhere showing therein. 1. The amount of each contract. 2. Balance of work remaining to be done, and 3. The amount of solvency-certificate produced by him at the time of enrollment in the……………………………………………….. 3.11 Relationship – The contractor shall not be permitted to tender for works in the corporation, (responsible for award and execution of contract ) in which his near relative is posted. He shall intimate the names of his near relative working in Chattisgarh. State and Municipal corporation, Korba. He shall also intimate the name of person working with him in any capacity or subsequently employed by him and who are near relatives to any Gazette Officer in the Chattisgarh. State. Any breach of this condition by the contractor D:\533577160.doc - 17 - would render him self liable to be removed form the approved list of contractors of the UADD apartment. …………………………………………………… Note - By the terms near relative is meant wife, husband, parents and son, grand son, brothers, sisters, brothers in laws, father in law and mother in law. 3.11 The tender for the works shall be witnessed by a contractor. Failure to observe this condition shall render the tender of the contractor liable to rejection. 4. Opening and Acceptance of tender 4.1 Place and time of opening – First the Online Prequalification envelope will be opened. Then the online envelope A containing details of "Earnest Money" shall be opened on the fixed date and time by the Commissioner, municipal corporation, Korba, If the Earnest money is found in proper form, then Envelope-"B" containing terms and conditions shall be opened thereafter on the same day. If earnest money of any tenderer is not found in approved form as para 3.4.1 to 3.4.3 of the detailed NIT, his tender will not be entertained and Envelope "B" and "C" shall remain unopened. The Commissioner, under the unavoidable circumstances, may depute another officer in his absence to open tenders on his behalf. The tenders shall be opened at time and place stated in para 1. A common set of conditions would then be drawn by the Executive Engineer., after hearing the views of all the contractors, who choose to be present. After this, the contractors will be directed to submit their revise offers in two online envelopes, envelope - CT containing acceptance of the common terms and conditions and envelope-RB containing revised offer. The tenderer shall have to duly fill their revised offer in appropriate online form meant for it. The Bid hashes of revised offer and revised offer shall be submitted on or before a date and time specified. 4.2 Powers of Executive Engineer – The Executive Engineer does not bind himself to accept or recommend for the acceptance to the Commissioner, municipal corporation, Korba, or other higher authority, the lowest or any tender or to give any reasons for his decision. 4.3 Conditional Tender – Conditional tenders are liable to be rejected. 4.4 CANVASSING – Canvassing for support in any form for the acceptance of any tender is strictly prohibited. Any tenderer doing so will render himself liable to penalties which may include removal of his name from the register of approved contractors or penal action under section 8 of the M.P. Vinirdishtta Bharasta Acharan Nivaran Vidheyak, 1982. 4.5 UNSEALED TENDER – The tender shall be rejected, if not properly sealed. 4.6 AUTHORITY OF MUNICIPAL CORPORATION – The authority competent to accept a tender, reserve the right of accepting the tender for the whole work or for a distinct part of it, or distributing the work between one or more tenderness. 4.7 VALIDITY OF OFFER – Tender shall remain open up to 120 days .(Excluding the code of conduct period) from the date of opening of financial offer and in the event of the tenderer withdrawing the offer before the aforesaid date, for any reason whatsoever, earnest money deposited with the tender shall be forfeited by the Commissioner, municipal corporation, Korba, SPECIFICATIONS : 5.1 BRIEF SPECIFICATION A brief note on construction and specifications of the work is enclosed in Annexure-E. D:\533577160.doc - 18 - 5.2 Material of Construction - The materials of construction to be used in the work shall be governed by the provision of part V of the National Building code of India, 1970 and the relevant Indian Standard Specification with amendments & revisions issued up to the date of tender notice. 5.3 WORKMANSHIP – The work shall be carried out according to the specifications referred to hereinafter and according to sound engineering practice. The decision of the Executive Engineer, in respect of workmanship will be final. 5.4 SPECIFICATION FOR BUILDING WORKS - (Including water supply and sanitary fittings) 5.4.1 The contractor shall execute the work in conformity with the standards and procedure laid down in the National Building Code of India, 1970, and as per Chhattisgarh P.W.D. specification or specifications in force or special specification wherever enclose separately, and in accordance with the approved drawings. 5.4.2 CONCRETE – All concrete shall be mixed in concrete mixers and compacted by mechanical Vibrators. Slumps test shall be carried out during concreting and sample test cubes prepared and tested in due course. The testing will be carried out by the Corporation. The results of the tests shall confirm with the required standard and if the Engineer-in-charge considers that a structural test is necessary, the same shall be carried out as instructed by the Engineerin-charge at the contractors expense and should the result of this be unsatisfactory the contractor will be bound to take down and reconstruct the particular portion of work which has given unsatisfactory test results. 5.4.3 BRICKS – The contractor should use the bricks manufactured on the metric measures as for as possible. 5.4.4 All timber used in the wood work for all new works must be properly seasoned. In case of important buildings mechanical seasoning should be done in good seasoning plants. In case the contractor does not procure good seasoned wood, he may be asked to get it seasoned in plant at his own expense but no certificate is required where no additional rate is paid. 5.4.5 MAINTENANCE OF ROOFS – Subject to the provision in the agreement, it will be the responsibility of the contractor to see that the building does not leak, during the period of the first rainy season in respect of tile and sheet roofing and two consecutive rainy seasons in respect of lime concrete and cement concrete terraced roof, after its completion and he will make good and replace all the defective work on this account. 5.5 SPECIFICATION OF ELECTRICAL WORKS 5.5.1 The work will be carried out as per the approved drawing and as directed by the…Engineer in Charge The work will be governed by “General Specifications” for the Electrical Works in Government buildings in CHHATTISGARH as mentioned in PWD SOR in force. 5.5.2 All samples of electrical accessories should be got approved from the Engineer-in-charge. Contractor will have to arrange and afford all facilities for their inspection and rectify the defects pointed out by them. A list of accessories is enclosed as Annexure E. 5.5.3 The period of testing and refund of deposit will be 6 months after completion of work. 5.5.4 5.5.5 D:\533577160.doc In case of supply of ceiling fan, table fan, exhaust fan, cabin fan, tube light fixtures will be made by …………………………………… as mentioned in the C.S.R. As such labour rates only as per C.S.R. will be paid for fitting such items in position as per C.S.R. The contractor should submit wiring diagram on tracing cloth showing the point position of switch, length of point, position of D.B. and Main switch circuit no. in which points fall at the - 19 - time of final bill. Otherwise deduction of ½ percent (half percent) will be made from the bill. 5.6 SPECIFICATION FOR WORKS (Excluding bridges and culverts) The road works and collection of materials for road works shall be carried out according to the Chhattisgarh P.W.D. specifications, as adopted for……………………………… or specifications in force or special specifications, wherever enclose separately, or the relevant specifications published by the Indian Road Congress. 5.7 CONTRADICTIONS OR AMENDMENTS – In the event of contradictions between the stipulations of the current schedule of rates (vide part of this N.I.T.) and aforesaid specification (vide para 5.1 to 5.6 above) the stipulation of the current schedule of rates shall gain precedence. In the event of contradictions, if any between different specifications and or codes of practice, refer to above, the decision of the Commissioner shall be final subject to appeal in case of dispute before Competent Authority within one month of such decision. 6. SUPPLY OF MATERIALS : No Material shall be supplied by KMC 7. MISCELLANEOUS CONDITIONS : 7.1 SUBLETTING - The contractor shall not, without the prior approval of the competent authority in writing, sublet or assign to any other party or parties, the whole or any portion of the work under the contract. Where such approval is granted, the contractor shall not be relieved of any obligation or duty or responsibility which he undertakes under the contract. 7.1 TAXES - All dues regarding taxes, including the sales tax, other duties etc., levied on the contractor’s work by Government and local bodies or private individuals will be payable by the contractor. The Engineer-in-charge will grant a certificate for the quantities actually used on the work but will not entertain any claim on this account. 7.2 Mineral extracted for works carried out on behalf of the Government of India, from the quarries in possession of controlled by the State Government is subject to payment of Royalty by the contractor to whom it shall not be refundable. The KMC shall not also issue any certificate in respect of such materials extracted for Government of India work (Applicable to Government of India works only) 7.3 RULES OF LABOUR CAMPS - The contractor will be bound to follow the Chhattisgarh Model Rule relating to layout water supply and sanitation on labour camps (vide Annnexure-A) and the provision of the National Building Code of India, in regard to constructions and safety. 7.4 FAIR WAGES - The contractor shall pay not less than fair wages to labourers engaged by him on the works(rules enclosed vide Annexure-B) 7.5 WORKS IN THE VICINITY - The Executive Engineer reserves the right to take up departmental work or to award work on contract in the vicinity without prejudice to the terms of contract. 7.6 BEST QUALITY OF CONSTRUCTION MATERIALS - Materials of the best quality will be used as approved by the Executive Engineer. 7.7 REMOVAL OF UNDESIRED PERSONS - The contractor shall on receipt of the requisition from the Executive Engineer at once remove any person employed by him on the work who, if in the opinion of the Executive Engineer is unsuitable or undesirable. 7.8 AMOUNT DUE FROM CONTRACTOR - Any amount due to KMC from the contractor on any account concerning works may be recovered from him as arrear of land revenue. 7.9 TOOLS AND PLANTS - The contractor shall arrange at his own cost tools and plant required for proper execution of the work. Certain plants may however be issued to the contractor as a special case. D:\533577160.doc - 20 - 7.10 RIGHT TO INCREASE OR DECREASE WORK - The competent authority reserve the right to increase or decrease work. The competent authority reserves the right to increase or decrease any item of the work during the currency of the contract and the contractor, will be bound to comply with the order of the competent authority without any claim for compensation. 7.12 TIME SCHEDULE - The work shall be done by the contractor according to the time schedule fixed by the competent authority. 7.12 TIME OF CONTRACT - Time allowed for carrying out the work as entered in the N.I.T. shall be strictly observed by the contractor and shall be reckoned from the date of work order to commence the work. 7.13 PAYMENT BY CHEQUES / ONLINE ACCOUNTING SYSTEM - The payment will be made by chouse on the State Bank of India Korba only. No Bank commission charges on realizing such payment will be burned by the department 7.14 TRANSPORT OF MATERIALS - The contractor shall make his own arrangement for transport of all materials. The department is not bound to arrange for priority in getting wagon or any other material through all possible assistance by way of recommendation will be given if it is found necessary in the operation by the Engineer-in-charge. If it proves to be in effective, the contractor shall have no claim for any compensation on that account. 8. SPECIAL CONDITIONS :8.01 (a) No Reimbursement/refund on variation in prices of D.I. Pipes/materials/POL and Labour wages shall be made in this contract. (b) The tenderer should quote his rates duly considering the excise exemption certificate. Department will issue excise exemption certificate to the contractors on their request for pipes & fittings as applicable vide excise notification no.12/2014 date 17th march 2014. (c) In case, the shifting of any existing, water pipe line/sewage line is considered necessary by the Deptt./Municipal Corporation, such service lines will have to be shifted by the contractor for which the payment shall be made for the actual work done as per approved rate of this contract. (d) Any other specials which do not appear in the schedule of work shall be fabricated with MS pipes for execution of works. As per direction of the engineer-in-charge for which necessary provision has also been made in the schedule of work. 8.2 AGREEMENT 8.2.1 EXECUTION OF AGREEMENT - The tenderer whose tender has been accepted herein after referred to as the contractor, shall produce on appropriate solvency certificate, is so required by the Executive Engineer and will execute the agreement in the prescribed form, within a fortnight of the date of communication of the acceptance of his tender by competent authority. Failure to do so will result in the earnest money being forfeited to KMC and tender being cancelled. 8.2.2 (a) The Contractor shall employ as per norms of PQ Document, Graduate Engineers during the execution of the work :- (i) One Graduate Engineer when the work to be executed is more than Rs.5 Lakhs (a) One Diploma Holder, Sub Engineer when the cost of work to be executed is from Rs.2 Lakhs or more but not more than Rs.5 Lakhs. (b) The technical staff should be available at site whenever required by the Engineer-in-charge to take instructions. (c) In case the contractor fails to employ the technical staff as aforesaid, the E.E. shall have the right to take suitable remedial measures. (d) The contractor should give the names and other detail of the Graduate Engineer/Diploma Holder Sub Engineer whom he intends to employ or who is under employment on the work at the time he commences the work. D:\533577160.doc - 21 - (e) The contractor should give a certificate to the effect that the Engineer/Diploma Holder Sub Engineer is exclusively in his employment. Provided that :(i) An Engineer or Sub-Engineer may look after more than one work in the same locality but the total value of such work under him should not exceed Rs.25 Lakhs in the case of an Engineer and Rs.5 Lakhs in the case of a Sub Engineer. (ii) It is not necessary for the contractor’s partner in case of firm/company, who is himself an Engineer/Sub-Engineer to employ another Engineer, Sub-Engineer for the Supervision of work. (iii) The Retired Assistant Engineer who is holding a Diploma may be treated at per with a Graduate for the operation of the above clause. In case the contractor fails to employ the Technical staff as aforesaid he shall be liable to pay the department sum of Rs.20000.00 (Twenty thousand only) for each month of default in the case of graduate Engineer and Rs.12000 (Twelve thousand only) for each month of default in the case of Diploma holder Sub Engineer. 8.3 CONDITIONS APPLICABLE FOR CONTRACTOR All the conditions of the tender notice will be binding on the contractors in additions to the condition of the contract in the prescribed form :Following documents annexed with this N.I.T. shall form a part of contract. Annexure “A” : Model Rules relating to labour, water supply etc. Annexure “B” : Contractors labour regulations. Annexure “C” : Statement showing the lead of materials. Annexure “D” : Form of Income Tax Clearance Certificate (Applicable to works costing more than Rs.2.00 Lakhs) Annexure “E” : Brief specifications Annexure “F” Annexure “G” : : Schedule of items Form of Bank Guarantee Annexure “H” : INFORMATION & INSTRUCTIONS TO THE BIDDERS FOR ONLINE ELECTRONIC GOVERNMENT PROCUREMENT SYSTEM (eGPS). : Pre contract integrity pact. Annexure “I” 8.4 10% of bill amount shall be deducted from each bill for hydraulic testing of work done (as per clause 7.2 of annexure E) and 5% as secutrity deposit of bill amount shall be deducted from each bill for successful commissioning of the work. the same will be passed and paid when the work got completed successfully. Commissioner, Municipal corporation, Korba D:\533577160.doc - 22 - ANNEXURE - “A” Model Rules Relating to Labour water supply and sanitation in labour camps. NOTE - These model rules are intended primarily for labour camps which are not of a permanent nature. They lay down the minimum desirable standard which should be adhered to. Standards in permanent or semipermanent labour camps should not obviously be lower than those for temporary camps. 1. LOCATION - The camps should be located in elevated and well drained ground in the locality. 2. Labour huts to be constructed for one family of 5 persons each. The lay out to be shown in the prescribed sketch. 3. HUTTING - The huts to be built of local materials. Each hut should provide at least 20 sq.mt. of living space. 4. SANITARY FACILITIES - Latrines and urinals shall be provided at least 15 meters away from the nearest quarters separately for men and women and specially so marked on the following scale. 5. LATRINE - Pit provided at rate of 10 users or two families per seat, separate urinals as required as the privy can also be used for this purpose. 6. DRINKING WATER - Adequate arrangements shall be made for the supply of drinking water. If practicable filtered and chlorinated supplies shall be arranged, when supplies are from intermittent sources over head storage tanks shall be provided with a capacity of 5 Litres a person per day. Where the supply is to be made from a well it shall confirm to the sanitary standard laid down in the report of Rural Sanitation Committee. The well should be at least 30 metres away from any latrine or other source of pollution. If possible hand pump should be installed for drawing the water from well. The well should be effectively disinfected once every month and the quality of the water should be got tested at the Public Health Institution between each work of disinfecting. 7. BATHING AND WASHING - Separate bathing and washing place shall be provided for men and women for every 25 persons in the camp. There shall be one gap and space of 2 sq. meters for washing and bathing, proper drainage for the waste water should be provided. 8. WASTE DISPOSAL - Dustbin shall be provided at suitable places in camp and the residents shall be directed to throw all rubbish in to those dustbins. The dustbins shall be provided with cover. The contents shall be removed every day and disposed off by trenching. 9. MEDICAL FACILITIES (A) Every camp where, 1,000 or more person reside shall be provided with whole time doctor and dispensary. If there are women in the camp a whole time nurse shall be employed. (B) Every camp where less than 1000, but more than 250 person reside shall be provided with a dispensary and part time nurse/midwife. (C) If there are less than 250 persons in any camp a first aid kit shall be maintained in charge of whole time persons, trained in first aid. All the medical facilities mentioned above shall be for all residents in the camp including a dependent of the worker if any, free of cost. SANITARY STAFF - For each labour camp there should be qualified sanitary inspector and sweeper should be provided in the following scales : (1) For camps with strength over 200but not exceeding 500 persons one sweeper for every 75 persons above the First 200 for which 3 sweepers shall be provided. (2) For campus with a strength over 500 persons one sweeper for every 100 person above first 500 for which 6 sweepers should be provided.. D:\533577160.doc - 23 - ANNEXURE - “B” CONTRACTORS LABOUR REGULATION The contractor shall not pay less than fair wage to labours engaged by him in the work. EXPLANATION - (a) “Fair wages” means wages whether for time or piece works as notified on the date of inviting tenders and where such wages have not been so notified the wages prescribed by the……………………………………………. department for the division in which the work is done. (b) The contractor shall notwithstanding the provision of any contract to the contrary, cause to be paid a fair wage to labourers indirectly engaged on the work including any labour engaged by his sub-contractors in connection with the said work as if labourers had been immediately employed by him. (c) In respect of all labour directly or indirectly employed on the works or the performance of his contract, the contractor shall comply with or cause to be complied with the Labour Act in force. (d) The Executive Engineer/Sub Divisional Officer shall have the right to deduct from the money due to the contractor any sum required or estimated to be required for making good the loss suffered by a worker or workers by reason of non fulfillment of the conditions of the contract for the benefit of the workers, non payment of wages or of deductions made from his or their wages which or not justified by their terms of the contract or non observance of regulations. (e) The contractor shall be primarily liable for all payments to be made under and for the observance of the regulations aforesaid without prejudice to his right to claim indemnity from his sub contractors. (f) The regulations aforesaid shall be deemed to be a part of this contract and any breach thereof shall be deemed to be a breach of this contract. (g) The contractor shall obtain a valid license under the contract (Regulation and Abolition) Act, in force and rules made there under by competent authority from time to time before commencement of work, and continue to have a valid license until the completion of the work. Any failure to fulfill this requirement shall attract the penal provisions of this contract arising out of the resulted non-execution of the work assigned to the contractor. S.No. ANNEXURE - C Statement showing the Lead of Materials Description Lead 1. …………………………………………………………………………………… 2. …………………………………………………………………………………… 3. …………………………………………………………………………………… 4. …………………………………………………………………………………… 5. …………………………………………………………………………………… Note - This statement is only for guidance of the contractor. The tenderer should satisfy himself regarding the availability of the required quality and quantity of materials. D:\533577160.doc - 24 - ANNEXURE - D Form of certificate on Income Tax to be submitted by contractor. Tendering for works costing Rs2.00 Lakh or more. (i) Name and style (of the company, firm, H.U.F. or individual) in which the applicant assessed to income tax and address for purposes of assessment. (ii) The income tax Circle/Ward/District in which the applicant is assessed to income tax. (iii) Following particulars concerning the last Income tax assessment made :(a) Reference No. (Or. G.I.R.No.) of the assessment. (b) Assessment year and accounting year. (c) Amount of total income assessed. (d) Amount of tax assessed IT,ST.EPT,BPT. (e) Amount of tax paid IT,ST,EPT,BPT. (f) Balance being tax not yet paid and reasons for such arrears. (g) Whether any attachment or certificate proceeding pending in respect of the arrears. (h) Whether the company or firm or H.U.F. on which the assessment was made has been or is being liquidated, wound up, dissolved, partitioned or being declared insolvent, as the case may be. (i) The position about later assessment namely, whether returns submitted under section 22 (1) of (2) of the income-tax act and whether tax paid under section 18 A of the act. and the amount of tax so paid or in arrears. (iv) In case there has been no income tax assessment at all in the past, whether returns submitted under section 21 (1) or (2) and 18-A (3) and if so, the amount of income tax returned or tax paid and the income tax circle/ward/district concerned. (v) The name and addresses of branch(es) verified the particulars set out above and found correct subject to the following remarks. Signature of I.T.O. Dated………………………. D:\533577160.doc Circle/Ward/District - 25 - APPENDIX 2.13 (See Paragraph 2.091) Issued vide Govt. no. 8231/8275/04/19/nivida/B Raipur dated 31/10/05 APPENDIX 2.13 (See Paragraph 2.019) FORM 'A' NAGAR PALIK NIGAM KORBA KORBA AUGMENTATION WATER SUPPLY SCHEME PART I (Under UIDSSMT) Issued to Shri/M/s. Class of Contractor. ………………………………………………...………………………………… ..................Registration No.....................................Date..................... Name of work - Providing, laying, jointing, interconnection, testing, commissioning of Clear water Pumping main of DI pipe class K-9 & Clear water Gravity main of D.I. pipe class K-7 with valves and specials and all allied civil works Under Augmentation Water supply Scheme for Korba town. (i) Clear water pumping main : 250- 800 mm dia – 14004 m (ii) Clear water Gravity main : 200- 800 mm dia – 9322 m Including laying of pipes by push through method for railway crossings & providing and installation of full bore electromagnetic bulk flow meters to gravity mains and pumping mains Amount of Contract Rs.2301.90 Lacs Amount of E.M.D Rs. 1155000.00 Cost of Tender Form Rs. Rs. ……………. to be paid online Vide M.R. No. & Date ……………………………………………………………………… Time allowed for Completion -------------- from the reckoned date Including rainy season (16th June to 15th October) Date of opening Tender ----------------PERCENTAGE RATE TENDER AND CONTRACT FOR WORKS (Based on applicable Schedule of Rates) General Rules and Direction for the Guidance of Contractors 1. Tenders must be invited for all works proposed to be given on contract unless the amount of works proposed to be given on contract is Rs 50,000 or less. The N.I.T. shall be posted in public places signed by the authority inviting the tenders. N.I.T. will state the work to be carried out as well as the date for submitting and opening tenders and the time allowed for carrying out the work, also the amount of earnest money to be deposited with the tender and the amount of the security deposit to be deposited by the successful tenderer & the percentage, if any to be deducted from bills, it will also state whether a refund of quarry fees, royalties and ground rents will be granted. Copies of the specifications, designs and drawings and a schedule of items quantities and rates of the various description of work and any other documents required in connection with the work signed for the purpose of identification by the authority competent to approve the tender shall also be open for inspection by the contractor at the office of the authority selling the tender forms during office hours. D:\533577160.doc - 26 - Further that the schedule of items along with the quantities and rates payable shall be attached to the tender documents and in the event of variation in rates given in such list with the schedule of Rates the rates given in the S.O.R. approved by the competent authority shall prevail. 2. 3. 4. 5. 6. 7. In the event of the tender being submitted by a firm it must be signed separately by each member thereof, in the event of the absence of any partner it must be signed on its behalf by a person holding a power of attorney authorizing him to do so, such power of attorney should be produced with the tender and it must disclose that the firm is duly registered under the Indian partnership Act. Any person who submits a tender shall fill up above or below the S.O.R. specified in rule he is willing to undertake the work. Only one rate of percentage above or below the S.O.R. on all the scheduled terms shall be named. Tenders that propose any alteration in the work specified in the said N.I.T. or in the time allowed for carrying out the work or which contain any other conditions of any sort will be liable to rejection. No single tender shall include more than one work but contractors who wish to tender for two or more works shall submit a separate tender for each Tenders shall have the name and number of the work to which they refer written outside the envelope. The authority receiving tenders or his duly authorised assistant will open tenders in the presence of any intending contractors who may be present at the time and will enter the amount of the several tenders in a comparative statement in a suitable form. Receipts for earnest money will be given to all tenderers except those whose tenders are rejected and whose earnest money is refunded on the day the tenders are opened. The Officers competent to dispose of the tenders shall have right of rejecting all or any of the tenders without assigning any reason thereof. The receipt of a clerk for any money paid by the contractor will not be considered as any acknowledgement of payment to the KMC selling the tender form and the contactor shall be responsible for seeing that he procures a receipt signed by that authority or any other person duly authorised by him. The memorandum of work tendered for be filled in and completed before the tender form is issued. If a form is issued to an intending tenderer without having been so filled in and completed he shall request the office to have this done before he completes and delivers his tender. TENDER FOR WORKS I/We hereby tender for the execution, for the Municipal Corporation of Korba For the work specified in under written memorandum within time specified in such memorandum at (In Figures): (In Words Percent below / above/at par with the applicable Schedule of Rates and in accordance in all respects with the specifications, designs, drawings and instructions in writing referred to in rule 1 thereof and in clause 12 of the annexed conditions and with such materials as are provided for by, and in all other respects in accordance with such conditions as far as applicable. D:\533577160.doc - 27 - Memorandum (a) Name of work : Providing, laying, jointing, interconnection, testing, commissioning of Clear water Pumping main of DI pipe class K-9 & Clear water Gravity main of D.I. pipe class K-7 with valves and specials and all allied civil works Under Augmentation Water supply Scheme for Korba town. (i) Clear water pumping main : 250- 800 mm dia – 14004 m (ii) Clear water Gravity main : 200- 800 mm dia – 9322 m Including laying of pipes by push through method for railway crossings & providing and installation of full bore electromagnetic bulk flow meters to gravity mains and pumping mains including utilization of existing laid DI pipes with interconnection b) Cost of work put to Tender: Rs. 2301.90 Crores (c) Earnest money : Rs. 11.55 Lacs (d) Security deposit (including earnest money) : 5% (e) Percentage, if any to deducted from bills : 5% (f) Time allowed for the work 18 Months from the reckoned date including / excluding rainy season (From 16th june to 15th october) (Delete which ever is not applicable.) Should this tender be accepted I/we hereby agree to abide by and fulfill all terms and provisions of the said condition of the contract annexed hereto as far as applicable or in default, thereof to forfeit & pay to the Commissioner, KMC or his successors in office the sums of money mentioned in the said conditions. A separate sealed cover duly super scribed containing the sum of Rs. 1155000/- as earnest money the full value of which is to be absolutely forfeited to the said Commissioner or his successors in office without prejudice to any other rights or remedies of the said Commissionerr or his successors in office should I/we fail to commence the work specified in the above memorandum or should I/we not deposit the full amount of security deposit specified in the above memorandum, in accordance with clause 1 of the said conditions of the contract, otherwise the said sum of Rs. 1155000/- shall be retained by KMC on account of such security deposit as aforesaid or the full value of which shall be retained by KMC on account of the security deposit specified in clause 1 of the said conditions of the contract. Signature of witness to Contractor’s Signature Dated the ………………………………… day of 201 Signature of the Contractor before submission of tender (with name and seal) Dated the day of …………………………….. 201 Name and Address of the witness: ……………………………………………………………………… Occupation of the witness:…………………………………………………………………… The above tender is hereby accepted by me for and on behalf of the Commissioner, KMC Dated the …………………. day of ………………… 201 …………………………………………….. Signature of the Officer by whom accepted With designation and seal of office D:\533577160.doc - 28 - CONDITIONS OF CONTRACT Definition A. The contract means the documents, forming the notice inviting tenders and tender documents submitted by the tenderer and the acceptance thereof including the formal agreement executed between the KMC and the contractor. B. In the contract the following expressions shall unless otherwise required by the context have the meanings hereby respectively assigned to them:- (a) The expression “works” or “work” shall unless thereby mean something either in the subject or context repugnant to such construction be construed and taken to mean the works or by virtue of the contract contracted to be executed whether temporary or permanent and whether original, altered, substituted or additional. (b) The “site” shall mean the land and/or other places on, into or through which work is to be executed under the contract or any adjacent land path or street through which work is to be executed under the contract or any adjacent land, path, or street which maybe allotted or used for the purpose of carrying out the contract. (c) The “Commissioner” means Commissioner of Korba Municipal Corporation (d) The “Engineer-in-Charge” means the Executive Engineer or the Assistant Engineer as the case may be who shall supervise and be in charge of the work and who shall sign the contract on behalf of the Commissioner. (e) “Municipal Corporation Korba” shall mean the KMC. Competent Authority means Commissioner of Korba Municipal Corporation/UADD C.G. as the case may be. (f) (g) The term “Chief Engineer” means the Competent Authority from UADD. The term "Superintending Engineer" means the Superintending Engineer of the concerned UADD as the case may be. The term "Executive Engineer"/"Engineer-in-Charge"/"Divisional Officer" means the Executive Engineer of KMC. The term "Assistant Engineer" means the Assistant Engineer KMC. The word "Sub Engineer" shall mean "Section Officer" of the KMC. (h) (i) (j) Note: - “Words” importing the singular number include plural number and vice-versa, Clause 1 - D:\533577160.doc SECURITY DEPOSIT The person whose tender may be accepted (hereinafter called the contractor which expression shall unless excluded by or repugnant to the context include his heirs executers, administrators representatives and assigns) shall permit Nagar Nigam Korba at the time of making any payments to him for the value of work done under the contract to deduct the security deposit as under. The Security Deposit to be taken for the due performance of the contract under the terms & conditions printed on the tender form will be the earnest money plus a deduction of 5 (Five) percent from the payment made in the running bills, till the two together amount to 5 (Five) - 29 - percent of the cost of work put to tender or 5 (Five) percent of the cost of the works executed when the same exceeds the cost of work put to tender COMPENSATION FOR DELAY Clause 2 - The time allowed for carrying out the work, as entered in the tender form, shall be strictly observed by the contractor and shall be deemed to be the essence of the contract and shall be reckoned from the fifteenth day after the date on which the order to commence the work is issued to the contractor, for a work where completion is up to 6 months 1.0 FOR WORKS, FOR WHICH THE COMPLETION PERIOD IS BEYOND SIX MONTHS: The period will be reckoned from the thirtieth day after the date on which the order to commence the work is issued to contractor. The work shall throughout the stipulated period of contract be proceeded with all due diligence, keeping in view that time is the essence of the contract. The contractor shall be bound in all cases, in which the time allowed for any work exceeds one month, to complete 1/8th of the whole work before 1/4th of the whole time allowed under the contract has elapsed, 3/8 th of the work before 1/2 of such time has elapsed and 3/4th of the work before 3/4th of such time has elapsed. In the event of the contractor failing to comply with the above conditions, the Executive Engineer shall levy on the contractor, as compensation an amount equal to: 0.5% (zero point five percent) of the value of work (contract sum) for each week of delay, provided that the total amount of compensation under provision of this clause shall be limited to 6% (six percent) of value of work. (Contract sum) Provided further that if the contractor fails to achieve 30% (thirty percent) progress in 1/2 (half) of original or validly extended period of time (reference clause 5 below) the contract shall stand terminated after due notice to the contractor and his contract finallised, with earnest money and or security deposit forfeited and levy of further compensation at the rate of 10% of the balance amount of contract left incomplete, either from the bill, and or from available security/performance guarantee or shall be recovered as "Arrears of land revenue". 2.0 D:\533577160.doc THE DECISION OF THE COMMISSIONER KMC IN THE MATTER OF GRANT OF EXTENSION OF TIME ONLY (REFERENCE CLAUSE 5 BELOW) SHALL BE FINAL, BINDING AND CONCLUSIVE. BUT HE HAS NO RIGHT TO CHANGE EITHER THE RATE OF COMPENSATION OR REDUCE AND OR CONDONE THE PERIOD OF DELAY- ONCE SUCH AN ORDER IS PASSED BY HIM (ON EACH EXTENSION APPLICATION OF THE CONTRACTOR) IT SHALL NOT BE OPEN FOR A REVISION. WHERE THE COMMISSIONER KMC DECIDES THAT THE CONTRACTOR IS LIABLE TO PAY COMPENSATION FOR NOT GIVING PROPORTIONATE PROGRESS UNDER THIS CLAUSE AND THE COMPENSATION IS RECOMMENDED DURING THE INTERMEDIATE PERIOD, SUCH COMPENSATION SHALL BE KEPT IN DEPOSIT AND SHALL BE REFUNDED IF THE CONTRACTOR SUBSEQUENTLY MAKES UP THE PROGRESS FOR THE LOST TIME, WITHIN THE PERIOD OF CONTRACT INCLUDING EXTENSION GRANTED, IF ANY FAILING WHICH THE COMPENSATION AMOUNT SHALL BE FORFEITED IN FAVOUR OF THE KMC. - 30 - Action when the work is left incomplete abandoned or delayed beyond the time limit permitted by the commissioner Clause 3:- (i) (ii) (a) (b) (c) (d) (e) (f) (g) (h) The Commissioner may terminate the contract if the contractor causes a fundamental breach of the contract. Fundamental breach of contract shall include, but not be limited to, the following: The contractor stops work for four weeks, when no stoppage of work is shown on the current programme or the stoppage has not been authorised by the Commissioner. The Commissioner gives notice that failure to correct a particular defect is a fundamental breach of contract and the contractor fails to correct it within reasonable period of time determined by the Commissioner in the said notice. The contractor has delayed the completion of work by the number of weeks [12 (Twelve) weeks] for which the maximum amount of compensation of 6% of contract sum is exhausted. If the contractor has not completed at least thirty percent of the value of construction work required to be completed in half of the completion period (Including validly extended period if any). If the contractor fails to appoint the technical staff and if appointed do not function properly for 4 weeks even after due written notice by the Commissioner. If he violates labour laws and or State/ Central Government statutory regulations and laws, the reason for action can be taken by the Commissioner. If the Contractor fails to set up field laboratory with appropriate equipments, within 30 day from the reckoned date. (* for each contract valued more than Rupees 3 crores). Any other deficiency which goes to the root of the contract Performance (iii) If the contract is terminated, the contractor shall stop work immediately, make the site safe and secure and leave the site as soon as reasonably possible. (iv) The Executive Engineer shall cause recording and checking of measurements of all items of work done (taking in to account quality and quantity of items actually executed) and prepare the final bill after adjusting all pervious outstanding dues. Such recording of measurements shall be done after due notice regarding time and date of recording measurement and directing the contractor to either remain present himself or his authorised representative so as to satisfy himself that the recording of measurement is just and proper. Failure on his parts either to attend and or refusing to acknowledge the measurement so recorded in the department measurement book, shall be at his sole risk and responsibility. In addition to the provision contained in clause 2 above the Commissioner shall forfeit the earnest money and or security deposit and further recover/deduct/adjust a compensation equal to difference of amount the balance value of work left incomplete which is required to be completed from another contractor at the risk and cost of the original contractor either from the bill, and or from available security/performance guarantee or by any other means and shall be recovered as "Arrears of land revenue" (v) D:\533577160.doc - 31 - Power to take possession of or require removal of Materials Tools and Plants or sale of Contractor’s Plants etc Clause 4: In any case in which any of the powers, conferred upon the Commissioner by clause - 3 hereof shall have become exercisable and the same shall not be exercised, the non-exercise thereof shall not constitute a waiver of any of the conditions hereof and such powers shall notwithstanding be exercisable in the event of any future case of default by the contractor for which by any clause or clauses hereof he is declared liable to pay compensation shall remain unaffected. In the event of the Commissioner putting in force either of the power clause 3 vested in him under the preceding clause he may, if he so desires, take possession of all or any tools, plant materials, and stores in or upon the works, or the site thereof or belonging to the contractor or procured by him and intended to be used for the execution of the work or any part thereof paying or allowing for the same in account at the contract rates, or in case of these not being applicable, at current market rates to be certified by Commissioner, whose certificate thereof shall be final; otherwise the Commissioner may by notice in writing to the contractor or his clerk of the works foreman or authorised agent require him to remove such tools plant, materials or stores from the premises (within a time to be specified in such notice) and in the event of the contractor failing to comply with any such requisition, the Commissioner may remove them at the contractors expense sell them by auction or private sale on account of the contractor & at his risk in all respects and the certificate of the Commissioner as to the expense of any such removal and the amount of the proceeds and expense of any such sale shall be final and conclusive against the contractor. EXTENSION OF TIME Clause 5 5.1 - If the Contractor shall desire an extension of time for completion of work on ground of his having been "UNAVOIDABLY" hindered in its execution or on any other ground, he must apply giving all and complete details of each of such hindrances or other causes in writing, to the Commissioner positively within 15 days of occurrence of such hindrance(s) and seek specific extension of time (period from .................... to ................) In case the grounds shown by the contactor are reasonable, the Commissioner shall be competent to grant the extension himself as under :If the extension of time sought is more than above period mentioned, then the Executive Engineer shall refer the case to the Commissioner with his recommendation and only after his decision in this regard, the Executive Engineer shall sanction extension of such time as decided by the Commissioner, . Once the Commissioner/ Competent Authority has decided the case of extension of time with reference to the particular application of the contractor, it will not be competent for them to review/change such a decision later on. However, the Commissioner and the Executive Engineer shall give the contractor an opportunity to be heard (orally and or in writing), before taking any final decision either of granting extension of time or permitting the contractor to complete the work by the delayed date (under clause 2 of the contact) or before refusing both. Provided further where the Commissioner has recommended grant of extension of particular time under clause 5.1 of the contract or has refused to recommend extension of D:\533577160.doc - 32 - time but has recommended permitting the contractor for delayed completion, (clause 2) the contractor shall continue with the work till the final decision by Competent authority/ Commissioner. Failure on the part of the contractor for not applying extension of time even within 30 days of the cause of such an hindrance, it shall be deemed that the contractor does not desire extension of time and that he has "Waived" his right if any, to claim extension of time for such cause of hindrance. Once the Competent Authority / Commissioner has heard (oral and or in writing) the contractor on this subject matter of extension of time and if Executive Engineer/ Commissioner fails to communicate his decision within a period of 30 days of such hearing, it shall be deemed that the contractor has been granted extension of time for the period as applied by him. 5.2 Compensation Events: - Compensation Events for consideration of extension of time without penalty. Clause 5.2 Not Applicable The following mutually agreed Compensation Events unless they are caused by the contractor would be applicable; (a) The Executive Engineer does not give access to a part of the site. (b) The Executive Engineer modifies the schedule of other contractor in a way, which affects the work of the contractor under the contract. (c) The Executive Engineer orders a delay or does not issue drawings, specification or instructions /decisions/approval required for execution of works on time. (d) The Executive Engineer instructs the contractor to uncover or to carry out additional tests upon work, which is then found to have no defects. (e) The Executive Engineer gives an instruction for additional work required for safety or other reasons.1 (f) The advance payment and or payment of running bills (complete in all respect) are delayed. (g) The Executive Engineer unreasonably delays issuing a Certificate of Completion (h) Other compensation events mentioned in contract if any Clause 5.3 Not Applicable Incentive bonus :-Not Applicable D:\533577160.doc - 33 - FINAL CERTIFICATE: Clause 6 - On completion of the work the contractor shall be furnished with a certificate by the Commissioner / Executive Engineer (hereinafter called the Commissioner) of such completion in the form appended at the end, but no such certificate shall be given, nor shall the work be considered to be complete until the contractor shall have removed from the premises on which the works shall be executed, all scaffolding surplus materials and rubbish, and cleaned off the dirt from all wood-work, doors windows walls, floors or other parts of any building in upon or about which the work is to be executed or of which he may have had possession for the purpose of the execution there of nor until the work; shall have been measured by the Engineer-in-charge whose measurements shall be binding and conclusive against the contractor. If the contractor shall fail to comply with the requirements of this clause as to removal of scaffolding surplus materials and rubbish and cleaning of dirt on or before the date fixed for the completion of the work, the Engineer-in-charge may, at the expense of the contractor remove such scaffolding, surplus materials and rubbish and dispose of the same as he thinks fit and clean off such dirt as aforesaid and the contractor shall forthwith pay the amount of all expenses so incurred, and shall have no claim in respect of any such scaffolding or surplus materials as aforesaid, except for any sum actually realised by the sale thereof. PAYMENT ON INTERMEDIATE CERTIFICATE TO BE REGARDED AS ADVANCES: Clause 7 - D:\533577160.doc No payments shall ordinarily be made for work estimated to cost less than Rs. 1,000/- (Rs. One Thousand) till after the whole of the works shall have been completed and certificate of completion given but if intermediate payment during the course of execution of works is considered desirable in the interest of works, the contractor may be paid at the discretion of the Commissioner But in the case of works estimated to cost more than rupees one thousand, the contractor shall on submitting the bill therefore be entitled to receive a monthly payment proportionate to the part thereof then approved and passed by the Commissioner whose certificate of such approval and passing of the sum so payable shall be final and conclusive against the contractor. But all such intermediate payments shall be regarded as payments by way of advance against the final payment for works actually done and completed and shall not preclude the requiring of bad unsound and imperfect or unskillful work to be removed and taken away and reconstructed or erected or be considered as an admission of the due performance of the contract or any such part thereof, in any respect, or the accruing of any claim, nor shall it conclude determine, or affect in any way the powers of the Commissioner under these conditions or any of them as to the final settlement and adjustment of the accounts or otherwise or in any other way vary or affect the contract. The final bill shall be submitted by the contractor within one month of the date fixed for completion of the work, otherwise the Engineer -in-charge’s certificate of the measurement and of the total amount payable for work accordingly shall be final and binding on all parties. - 34 - Bills to be submitted monthly: Clause 8 - "A bill shall be submitted by the contractor by 15th day of each month for all works executed by him till the end of previous month less the gross amount received by him till the last previous month. This bill must be supported by records of detail measurement of quantities of all executed items of work along with true copies of record and result of all tests conducted in the previous month (date wise). The Executive Engineer shall take or cause to be taken the requisite measurement for purpose of having the same verified/checked by the sub Engineer and Asstt. Engineer concern for quantity, quality and specification and examining all the "test results" and record the same in the Departmental measurement, book. Based on above record measurement bill shall be corrected /prepared afresh. The contractor shall sign the measurement and the bill. The Commissioner shall pay running bills by 25 th day of the month subject to availability of the funds If the contractor fails to submit, the bill on or before the day prescribed, the Executive Engineer after waiting for another 15 days shall depute a subordinate to measure the said work in the presence of contractor and or his authorized Engineer/Representative, whose counter signature to the measurement recorded with quantity and quality remark will be sufficient proof for acceptance of the same and shall be binding on the contractor All such running bill payments are by way of "Advances" and shall be subject to final adjustment. BILLS TO BE ON PRINTED FORMS: Clause 9 - The contractor shall submit all bills on printed forms to be had on application at the office of the Engineer– in– charge, and the charges in the bills shall always be entered at the rates specified in the tender or in the case of any extra work ordered in pursuance of these conditions, and not mentioned or provided for in the tender at the rates hereinafter provided for such work. The deduction or addition as the case may be of the percentage will be calculated on the amount of the bill for the work done, after deducting the cost of materials supplied departmentally at rates specified in the agreement. RECEIPTS TO BE SIGNED BY PARTNERS OF PERSONS HAVING AUTHORITY TO DO SO: Clause 10 - D:\533577160.doc Receipts for payments made on account of a work when executed by a firm must also be signed by the several partners, except where the contractors are described in their tender as a firm in which case the receipt must be signed in the name of-the firm by one of the partners, or by some other person having authority to give effectual receipt for the firm. - 35 - ADVANCES TO CONTRACTORS: Clause 11 (A) :- (i) The provision for advances in clause 11 A( i ) and ( ii ) will apply to contract above Rs. one crore only Mobilization advance: - Mobilization advance up to 5 % (Five percent) of the contract value shall be given if requested by the contractor with in one month of the date of order to commence the work. In such a case the contractor shall furnish Bank Guarantee from schedule bank for the amount Rs. 110% of advance in favour of the Commissioner before sanction and release of the advance. This advance shall be Interest free. This 5% (Five percent) advance shall be given in the two stages Stage -1: - 2 %( Two percent) of the contract value payable after signing of the agreement Stage-2: - 3%(Three percent) of the contract value payable on receipt of the certificate from the contractor that he has established complete central and field testing laboratories and has engaged workers/technicians and have brought requisite plants and machineries at work site, the work is physically started and only after construction programme is submitted by the contractor and is duly approved by the Executive Engineer. The following condition shall apply on modification advance (i) The Bank guarantee etc. taken towards security of Mobilization advance should be at least 110% advance so as to enable recovery of not only principal amount but also the interest portion, if so required (ii) The mobilization advance should not be paid in less than two installments except in special circumstances for the reasons to be recorded. This will keep check on contractor mosutilizing the full utilization advance when the work is delayed considerably (iii) The mobilization advance shall be however interest free if the contact is terminated due to default of the contractor the mobilization advance would be deemed as interest bearing advance at an interest rate of 14.75% to be compounded quarterly (ii) D:\533577160.doc Advance on plant and machinery: - Not Applicable - 36 - (iii) "Recovery of advances: The Recovery of above advances (mobilization, plants and machineries) shall be recovered in equal monthly installments on pro-rata basis (after 15% (fifteen percent) of contract work is executed) from each of the further running bills. However, all these advances shall be fully recovered when 80% (Eighty percent) contract sum is complete or when 75% (Seventy Five percent) of stipulated or validly extended period is over - which ever event is earlier." Secured advance Clause 11 (B) Advances to contractor are as a rule prohibited, and every endeavor should be made to maintain a system, under which no payments are made for unmeasured work except for work actually done. Exceptions are, however permitted in the following cases. Cases in which a contractor whose contract is for finished work, requires an advance on the security of materials brought to site, Commissioner may in such cases sanction advances up to an amount not exceeding 75% of the value of material and 90% in the case of steel (as assessed by the Executive Engineer) provided that the rate(s) of allowed in no case is/are more than the rate payable for the finished item as stipulated in the contract of such materials, provided that they are of imperishable nature and that a formal agreement is drawn up with the contractor under which Nagar Nigam Korba secures a lien on the materials and is safeguarded against losses due to the contractor postponing the execution of the work or to the shortage or misuse of the materials, and against the expense entitled for their proper watch and safe custody. Payment of such advances should be made only on the certificate of an officer not below the rank of Executive Engineer, that the quantities of materials upon which the advances are made have actually been brought to site, that the contractor has not previously received any advance on that security and that all the materials are required by the contractor for use on items of work for which rates for finished work have been agreed upon. Recoveries of advances so made should not be postponed until the whole of the work entrusted to the D:\533577160.doc - 37 - contractor is completed. They should be made from his bills for work done as the materials are used the necessary deductions being made whenever the item of work in which they are used; are billed for. Before granting the above-secured advance the contractor shall sign the prescribed Indenture Bond in the prescribed form. Escalation CLAUSE 11(C) Not Applicable Work to be executed in Accordance with Specification, Drawing, Order, etc.: Clause 12: The contractor shall execute the whole and every part of work in the most substantial and workman like manner, and both as regards materials and otherwise in every respect in strict accordance with the specifications. The contractor shall also conform exactly fully and faithfully to the designs, drawings and instructions in writing relating to the work signed by the Engineer – in – charge and lodged in his office and to which the contractor shall be entitled to have access at such office or on the site of the work for the purpose of inspection during office hours and the contractor shall, if he so requires, be entitled at his own expense to take or cause to be made copies of the specifications, and of all such designs, drawings and instructions as aforesaid. CPHEEO Manual 1999 (current Revision) for various water supply components/I.S.I. codes for various components of scheme or special specifications whenever enclosed separately shall apply in the case of any variance the following. Order of precedence shall prevail: 1. Specifications as per NIT. 2. Specifications as per S.O.R. 3 Specifications mentioned in CPHEEO Manual 1999 (current Revision) for various water supply components/I.S.I. codes for various components of scheme or special specifications whenever enclosed separately 4 Mode of measurements shall be as provided in the S.O.R. applicable to the contract. Where such mode of measurement is not specified in the S.O.R. it shall be done as per the instructions of the Commissioner KMC on the basis of prevailing market rates. However if any mode of measurement is specifically mentioned in the N.l.T. the same will get precedence over all the above. D:\533577160.doc - 38 - Variations Clause 13 - Additions, Alterations in Specifications and Designs. The Commissioner shall have power to make any alterations in, omissions from, additions to, or substitutions for, the original specifications, drawings, designs and instruction, that may appear to him to be necessary or advisable during the progress of the work, and the contractor shall be bound to carry out the work in accordance with any instruction which may be given to him in writing, signed by the Commissioner and such alterations, omissions, additions or substitution shall not invalidate the contract and any altered, additional works, or substituted work, which the contractor may be directed to do in the manner above specified as part of the work; shall be carried out by the contractor on the same conditions in all respects on which be agreed to do the main work and at the same rates as are specified in the tender for the main work, provided the total value of all such increased or altered or substituted work does not exceeds 25% (Twenty five percent) of the amount of administrative approval. If such total value exceeds 25% (Twenty five percent) it shall be open to the contractor either to determine the contract or apply for extension. But in no case the contractor shall be entitled to any rate other than the accepted rate. 13.1 For rate of any extra item, Commissioner shall pay 75% of the provisional rate till such time as the rates are finally determined by the Executive Engineer. Note: - Such additions, alterations, substitution, shall have to be within the Scope of work tendered for. Rates for works not in schedule of rates If during the course of execution, where it is found necessary that certain item/items of work not provided for in the S.O.R. required to be carried out then the Engineer in Charge shall identify such item / items including approximate quantity of the contract and ask the contractor to submit his rates in writing supported by the requisite data within a period of 7 days. The Engineer – in – charge shall obtain approval / modification of the proposed rate from the Commissioner and communicate the same within a period of 4 weeks to the contractor, in case the contractor agrees to the above rates as fixed by the Commissioner then they shall form a part of supplementary schedule of the contract agreement .lf the contractor does not agree to the rate of the Commissioner then it shall be open for the Competent authority to get the work executed through any other agency. The contractor will D:\533577160.doc - 39 - not however be entitled to any compensation due to delay or hindrance or loss of profit accruing on account of this extra work executed by alternative agency. If the contractor commences non-schedule work or incur expenditure in regard thereto before the rates shall have been determined by the Commissioner, then he shall be entitled for payment for the work done as may be finally decided by the Commissioner. In the event of dispute, the decision of the Competent Authority shall be final. Such a decision shall be given by the C.E. within a period of 30 (Thirty) days and it shall be open to the contractor not to continue that item further. In such an event that item shall be got executed by other agency at such an approved rate by Commissioner Contractor may either determine his contract if variations exceeds 25 (Twenty five) % of the Administrative approval, or may apply for extension. Extension of time in consequence of variations The time for the completion of work shall be extended in proportion of the variation of the work bear to the original contract work and certificate of Commissioner shall be conclusive as to such proportion. NO CLAIM TO ANY PAYMENT OR COMPENSATION FOR ALTERATION IN OR RESTRICTION OF WORKS: Clause 14 - If at any time after the execution of the contract documents, the Commissioner shall for any reason whatsoever require the whole or any part of the work as specified in the tender to be stopped for any period or shall not require the whole or part of the work to be carried out at all or to be carried out by the contractor he shall give notice in writing of the fact to the contractor who shall there upon suspend or stop the work totally or partially, as the case may be. If any such case, except as provided hereunder, the contractor shall have no claim to any payment or compensation what so ever on account of any profit or advantage which he might have derived from the execution of the work in full, but which he did not so derive in consequence of the full amount of the work not having been carried out, or on account of any loss that he may be put to on account of materials purchased or for unemployment of labour recruited by him. He shall not also have any claim for compensation by reason of any alteration having been made in the original specifications, drawing, designs and instructions, which may involve any curtailment of the work as originally contemplated. Where, however, materials have already been purchased or agreed to be purchased by the contractor shall be D:\533577160.doc - 40 - paid for such materials at the rates determined by the Commissioner, provided they are not in excess of requirement and of approved quality and / or shall be compensated for the loss, if any that he may be put to, in respect of materials agreed to be purchased by him, the amount of such compensation to be determined by the Commissioner whose decision shall be final. If the contractor suffers any loss on account of his having to pay labour charges during the period during which the stoppage of work has been ordered under this clause, the contractor shall, on application be entitled to such compensation on account of labour charges as the Commissioner, whose decision shall be final, may consider reasonable provided that the contractor shall not be entitled to any compensation on account of labour charges, if in the opinion of the Commissioner, the labour could have been employed by the contractor else where for the whole or part of the period during which the stoppage of the work has been ordered as aforesaid. If the total duration of suspension of the work is more than the six months, then this suspension of the work will be considered as permanent stoppage of the work, and the contractor can determine the contract, if he so desires. ACTION AND COMPENSATION PAYABLE IN CASE OF BAD WORK: Clause 15 - If at any time before the security deposit is refunded to the contractor, it shall appear to the Commissioner or his subordinate in charge of the work, that any work has been executed with unsound, imperfect or unskillful workmanship or with material of inferior quality or that any materials or articles provided by him for the execution of the work are unsound, or of a quality inferior to that contracted for, or are otherwise not in accordance with the contract, it shall be lawful for the Commissioner ge to intimate this fact in writing to the contractor and then notwithstanding the fact that the work, materials or articles complained of may have been Inadvertently passed, certified and paid for contractor shall be bound forthwith to rectify, or remove and reconstruct the work so specified in whole or in part, as the case may require, or if so required, shall remove the materials or articles so specified and provide other proper and suitable materials or articles at his own proper charge and cost, and in the event of his failing to do so with in a period to be specified by the Commissioner in the written intimation aforesaid ,the contractor shall be liable to pay compensation at the rate of one percent on the amount of contract put to tender every day not exceeding ten days, during which the failure so, continues and in the case of any such failure the Commissioner may D:\533577160.doc - 41 - rectify or remove and, re-execute the work or remove and replace the materials or articles complained of as the case may be at the risk and expense in all respects of the contractor. Should the Commissioner consider that any such inferior work or materials as described above may be accepted or made use of it shall be within his discretion to accept to the same at such reduced rates as he may fix therefore WORK TO BE OPEN FOR INSPECTION-CONTRACTOR OR RESPONSIBLE AGENT TO BE PRESENT: Clause 16- All work under or in course of execution or executed in pursuance of the contract shall at all time be open to the inspection and supervision of the Commissioner and his subordinates and the contractor shall at all time during the usual working hours, and at all other times at which reasonable notice of the intention of the Commissioner or his subordinate to visit the work shall have been given to the contractor, either himself be present to receive orders and instruction or have a responsible agent duly accredited in writing present for that purpose. Orders given to the contractor’s agent shall be considered to have the same force as if they had been given to the contractor himself. NOTICE TO BE GIVEN BEFORE WORK IS COVERED UP: Clause 17 - The contractor shall give not less than five days notice in writing to the Commissioner or his subordinate in charge of the work before covering tip or otherwise placing beyond the reach of measurement any work in order that the same may be measured, and correct dimensions thereof be taken before the same is so covered up or placed beyond the reach of measurement, any work without the consent in writing of the Commissioner or his subordinate in charge of the work and if any work shall be covered up or placed beyond the reach of measurement with out such notice having been given or consent obtained, the same shall be uncovered at the contractors expenses, or in default thereof, no payment or allowance shall be made for such work or the materials with which the same was executed. CONTRACTOR LIABLE FOR DAMAGE DONE AND FOR IMPERFECTIONS AFTER CERTIFICATE OF COMPLETION D:\533577160.doc - 42 - Clause18- If the contractor or his work people or servants shall break, deface injure or destroy any part of building in which they may be working or any building, road, road curbs, fences, enclosures, water pipes, cables drains, electric or telephone posts or Wires trees grass or grassland or cultivated ground continuous to the premises on which the work or any part of it is being executed, or if any damage shall happen to the work while in progress, from any cause whatever, or any imperfections become apparent ,the contractor shall make good the same at his own expense or in default, the Commissioner may cause the same to be made good by other workmen and deduct the expense of which certificate of the Commissioner shall be final) from any sums that may be then or at any time thereafter, may become due to the contractor or from his security deposits, or the proceeds of sale thereof or of a sufficient portion thereof. The security deposit of the contractor to the extent of 50% shall be refunded on his getting the completion certificate, provided that all the recoveries outstanding against him are realised. Balance 50% of the amount shall be refunded after four months of completion of work or final bill paid which ever is earlier CONTRACTOR TO SUPPLY PLANT, LADDERS, SCAFFOLDING, ETC.: Clause 19 - The contractor shall supply at his own cost materials (except such special materials if any, as may in accordance with the contractor be supplied from the Engineer – in – charge’s Stores) plants, tool, appliances, implements, ladders, cordage, tackle, Scaffolding and temporary work requisite for the proper execution the work whether original, or altered or substituted, and whether included in the specification or other documents forming part of the contractor referred to in these condition or not or which may be necessary for the purpose of satisfying or complying with the requirement of the Commissioner as to any matter as to which under these conditions he is entitled to be satisfied, or which he is entitled to require together with carriage there for to and from the work . The contractor shall also supply without charge requisite number of persons with the means and materials necessary for the purpose of setting out works, and counting, weighing& assisting in the measurement or examination at any time and from time to time of the work, or materials. Failing his so doing the same may be provided by the Commissioner at the expenses of the contractor and the expenses may be deducted from any money due to the contractor under the contract, or from his security deposit or the proceeds of sale thereof, or of a sufficient portion thereof. D:\533577160.doc - 43 - Contractor is liable for damages arising from non-provision of lights fencing etc. The contractor shall also provide at his own cost except when the contract specifically provides otherwise and except for payments due under clause all necessary fencing and lights required to protect the public from accident and shall be bound to bear the expenses of defence of every suit, action or proceedings at law that may be brought by any person for injury sustained owing to neglect of the above precautions & to pay any damage and costs which may be awarded in any such suit, action or proceedings to any such person or which may with the consent of the contractor be paid to compromise any claim by any such person. COMPENSATION UNDER SECTION 12 SUB-SECTION (1) OF THE WORKMAN’S COMPENSATION ACT 1923: Clause 20 - ln every case in which by virtue of the provisions of section 12 sub-section (1) of the workman’s compensation Act 1923 KMC is obliged to pay compensation to a workman employed by the contractor in execution of the works, Commissioner will recover from the contractor the amount of compensation so paid and without prejudice to the rights of KMC under section (1) sub-section (2) of the said Act. Commissioner shall be at liberty to recover the amount or any part there of by deducting it from the security deposit or from any sum due by KMC to the contractor whether under this contract or otherwise. KMC may not be bound to contest any claim made against them under section - 12 sub-section (1) of the said Act except on the written request of the contractor and upon his giving to KMC full security for all cases for which KMC might become liable in consequence contesting such claim. LABOUR: Clause 21 - The contractor should get himself registered under contract - labour regulations and abolition Act 1970 including its amendments after getting a certificate from the principal employer, who will be the Commissioner KMC Clause 22 - Labour below the age of 14 years - No labour below the age of 14 years shall be employed on the work. FAIR WAGE: Clause 23 - The contractor shall pay not less than fair wage to labour engaged by him on the work. Explanation (a) Fair wage’ means wage(s) whether for time or piece work notified during the period of execution of contract for the work and where such wages have not been so notified, the wages prescribed by the Works Department SOR for that period D:\533577160.doc - 44 - (b) The contractor shall, notwithstanding the provisions of any contract to the contrary cause to be paid a fair wage to labourers indirectly engaged on the work including any labour engaged by his subcontractors in connection with the said work, as if the labourers had been immediately employed by him. (c) In respect of labour directly or indirectly employed on the work for the performance of the contractors part of this agreement the contractor shall comply with or cause to be complied with the Labour Act in force. (d) The Commissioner/ Executive Engineer shall have the right to deduct, from the moneys due to the contractor, any sum required or estimated to be required for making good the loss suffered by a worker or workers by reasons of non-fulfillment to the conditions of the contract for the benefit of the workers nonpayment of wages or deductions made from his or their wages, which are not justified by the terms of the contract or non observance of the regulations. (e) The contractor shall be primarily liable for all payments to be made under and for observance of the regulations afore said with out prejudice to his right to claim indemnity from his sub-contractors. (f) The regulations aforesaid shall be deemed to be a part of this contract and any breach thereof shall be deemed to be a breach of this contract. Clause 24 :- D:\533577160.doc Subletting of works (Not Applicable) - 45 - Clause 25: All sums payable by way of compensation under any of these conditions shall be considered as reasonable compensation to be applied to the use of KMC without reference to the actual loss or damage sustained, and whether or not any damage shall have been sustained. CHANGE IN THE CONSTITUTION OF FIRM: Clause 26 - In the case of tender by partners any change in the constitution of the firm shall be forthwith notified by the contractor to the Commissioner for his information, and contractor shall initiate steps for fresh & new registration which shall be assessed & decided by the competent authority for fresh registration D:\533577160.doc - 46 - WORK TO BE UNDER DIRECTION OF COMMISSIONER Clause 27 - All works to be executed under the contract shall be executed under the direction and subject to the approval in all respect of the Commissioner for the time being who shall be entitled to direct at what point or points and in what manner they are to commenced and from time to time carried on. ARBITRATION CLAUSE: Clause 28 Except as otherwise provided in this contract all question and dispute relating to the meaning of the specification, designs, drawings and instruction herein before mentioned as to thing whatsoever in any way arising out of or relating to the contract designs, drawings, specification, estimate, concerning the works, or the execution or failure to execute the same, whether arising during the progress of the work, or a after the abandonment there of shall be referred to the Commissioner for his decision, within a period of 30 (thirty) days of such an occurrence (s). There upon the Commissioner shall give his written instructions and/or decisions, after hearing the contractor and Engineer in Charge within a period of 15 (fifteen) days of such request. This period can be extended by mutual consent of parties. Upon receipt of written instructions or decisions, of Commissioner the parties shall promptly proceed without delay to comply such instructions or decisions. If the Commissioner fails to give his instruction or decisions in writing within a period of 15 (fifteen) days or mutually agreed time after being requested and/or, if the party (es) is/are aggrieved against the decision of the Commissioner, the aggrieved party may within 30 days prefer an appeal to the Competent Authority, who shall afford an opportunity to the parties of being heard and to offer evidence in support of his appeal. The, CG UADD will give his decision within 30 (thirty) days, or such, mutually agreed period. If any party not satisfied with the decision of the CG UADD, they can file a petition for resolving the dispute through arbitration tribunal. A reference to the arbitration tribunal shall be no ground for not continuing the work on the part of the contractor’s payment. LUMP SUM IN ESTIMATE: Clause 29 - When the estimate on which a tender is made includes lump sums in respect of part of the works, the contractor shall be entitled to payment in respect of the items of work involved or D:\533577160.doc - 47 - the part of the work in the question at the same rates as are payable under this contract for such items, or if the part of the work in question is not, in the opinion of the Commissioner, capable of measurement, the Commissioner may at the his discretion pay the lump sum amount entered in the estimates , and the certificate in writing of the Commissioner shall be final and conclusive against the contractor with regard to any sum or sums payable to him under the provisions of this clause. Action where no specification: Clause 30 - In the case of any class of work for which there is no specification as is mentioned in Rule such work shall be carried out in accordance with the specification approved by Commissioner / Competent Authority for application to works Contractor’s Percentage whether Applied to Net or Gross Amounts of Bills: Clause 31 - The percentage referred to at Para 7 of the tender will be deducted from/added to the gross amount of the bills for work done after deduction of the cost of materials supplied by the department. Claim for Quantities Entered in the Tender or Estimate: Clause 32 - Quantities shown in the tender are approximate and no claim shall be entertained for quantities of work executed being either more or less than those entered in the tender of estimate. This is subject to the limitations as provided for in clause 13 and 14 above Claim for Compensation for Delay In Starting the Work: Clause 33 - No compensation shall be allowed for any delay caused, except as provided under clause 5.3, in starting of the work on any other ground or reasons whatsoever. EMPLOYMENT OF SCARCITY LABOUR: Clause 34- If Government declare a state of Scarcity or famine to exist in any village situated within sixteen kilometers of the work the contractor, shall employ upon such parts of the work as are suitable for unskilled labour, any person certified to him by the Competent authority or by any person to whom the Competent authority may have delegated this duty in writing to be in need of relief and shall be bound to pay to such persons wages not below the minimum which The Government may have fixed in this behalf. Any dispute, which may arise in connection with the implementation of this D:\533577160.doc - 48 - clause, shall be decided by the Competent authority whose decision shall be final and binding on the contractor. Royalty on Minor Minerals Clause 35: - The contractor shall pay all quarry, Royalty charges etc. If the contractor fails to produce the royalty clearance certificate from concerned department then the Commissioner shall deduct the royalty charges from his bills and keep in deposit head, which shall be refunded to the contractor on production of royalty clearance certificate from the concerned department. If he fails to produce the royalty clearance certificate with in 30 days of submission of final bill, then royalty charges which was keep under deposit head by the Commissioner shall be deposited to the concerned department and his final bill payment shall be released Any change in the royalty rates of minor minerals notified by the state government, after the date of submission of financial offer by the bidder/contractor, then this increase/decrease in the rates shall be reimbursed/deducted on actual basis. TECHNICAL EXAMINATION Clause 36 - The KMC shall have the right to cause Audit and Technical Examination of the works and the final bills of the contractor including all supporting vouchers, abstracts etc. to be made as per payments of the final bills and if as a result of such Audit & Technical Examination the sum is found to have been overpaid in respect of any work done by the contractor under the contract or any work claimed by him to has been done under contract and found not to have been executed, the contractor shall be liable to refund the amount of over payment and it shall be lawful for the KMC to recover the same from the security deposit of the contractor or from any dues payable to the contractor from the KMC account if it is found that the contractor was paid lesser than what was due to him under the contract in respect any work executed by him under it, the amount of such under payment shall be duly paid by the KMC to the contractor. D:\533577160.doc - 49 - In the case of any audit examination and recovery consequent on the same the contractor shall be given an opportunity to explain his case and decision of the Competent Authority shall be final. In the case of Technical Audit, consequent on which there is a recovery from the contractor, no recovery, should be made without orders of the Competent Authority whose decision shall be final. AII action under this clause should be initiated and intimated to the contractor within a period of Twenty four months from the date of completion of work DEATH OF PERMANENT INVALIDITY OF CONTRACTOR: Clause 37 - If the contractor is an individual or a proprietary concern, partnership concern, dies during the currency of the contract or becomes permanently incapacitated, where the surviving partners are only minors the contract shall be closed without levying any damages/compensation as provided for in clause 3 of the contract agreement. However, if competent authority is satisfied about the competence of the surviving, then the competent authority shall enter into a fresh agreement for the remaining work strictly on the same terms and conditions, under which the contract was awarded. PENALTY FOR BREACH OF CONTRACT: Clause 38 - On the breach of any term or condition of this contract by the contractor the said KMC shall be entitled to forfeit the Security deposit or the balance thereof that may at the time be remaining, and to realize and retain the same as damages and compensation for the said breach but without prejudice to the right of the KMC to recover further sums as damages from any sums due or which may become due to the contractor by KMC or otherwise howsoever. Clause 39 - From the commencement of the works to the completion of the same they are to be under the contractor's(s) charge. The contractor(s) is/are to be held responsible for and to make good all injuries, dameges and repairs, occasioned or rendered necessary to the same by fire/ natural calamity or any other causes and they are to hold the Corporation harmless from any claims for injuries to persons or for structural damage to property happening from any neglect, default, want of proper care of misconduct on the part of the contractor(s) or any one in his/their employ during the execution of the works. D:\533577160.doc - 50 - D:\533577160.doc - 51 - Notice to the Contractor to Start Work Your contract for the work __________________ has been accepted by me/Executive Engineer / Competent Authority on behalf of the Municipal Corporation Korba on the ___________________ day of _____________ 201_______ and you are, hereby ordered to commence the work. The commencement date reckoned shall ----------------------------------------------------- be -------------------------------------------- Signature Commissioner Nagar Nigam Korba The above notice to the contractor (s) to commence work from the reckoned __________ day of __________(month) ___________200__________ (year) was issued vide this office memorandum No. _______________ dated the ________ 200 _____ Signature Commissioner Nagar Nigam Korba Signature of Contractor D:\533577160.doc - 52 - COMPLETION CERTIFICATE In pursuance of clause 7 of the agreement in form A, No.-------------/Dt of--------) dated ____/_____/________ between the contactor Shri/Ms. ........................................... __________________________________ and the Commissioner, KMC; it is hereby certified that the said Contractor has duly completed the execution of the work under; taken by him there under on this __________ day of _______ 200 and this certificate was issued to the contractor vide office memo No. ...................................................... Dt............ Signature of Commissioner Nagar Nigam Korba D:\533577160.doc - 53 - ANNEXURE - “E” CLEAR WATER PUMPING MAIN & GRAVITY MAIN SCOPE OF WORK 1.0 SCOPE OF WORK : The scope of work shall be as below : 1.1 Providing, laying, jointing & interconnection of socket and spigot centrifugally cast (spun) Ductile Iron Pressure pipes with inside cement mortar lining (class K-9 & K-7) conforming to IS:8329-2000 with valves and specials duly inspected by DGS & D/SGS/RITES with suitable ISI mark, rubber gasket (Push on) joints as per IS:5382-1985 and all ductile iron fittings conforming to IS 9523-2000 duly inspected by DGS & D/SGS/RITES including testing, commissioning with all allied civil works. (i) Clear water pumping main - 250 mm dia – 1635 m, 300 mm dia – 2707 m, (Class K-9) 350 mm dia – 2043 m, 400 mm dia – 5132 m, 800 mm dia – 2487 m (ii) Clear water gravity main - 200 mm dia – 36 m, 250 mm dia – 57 m, 300 mm dia– 4717 m, (Class K-7) 350 mm dia – 1176 m, 400 mm dia –700 m, 450 mm dia – 45 m, 500 mm dia – 1715 m, 600 mm dia – 28 m, 700 mm dia-371m, 800 mm dia – 477 m 1.2 1.3 1.4 1.5 Excavation in trenches in all types of strata for above pipe line for in-line and grade with required depth and width as per specification including cleaning of land due to all vegetation trees, up to Girth 100 cm including shoring, dewatering the trenches providing pedestal crossing whenever necessary including of disposal excavated stuff. Providing and fixing following cast iron double flange sluice valve fitted with cast iron cap including jointing and testing with cost of jointing materials (Stainless steel spindle) Class PN 1.6 up to 600 mm & class PN 1.0 above 600 mm dia conforming to IS 14846-2000 duly inspected by DGS & D/SGS/RITES Score Valves 200 mm 5 Nos. 100 mm 17 Nos. Isoleting Sluice Valves 800 mm 5 Nos. 400 mm 4 Nos. 350 mm 3 Nos. 300 mm 3 Nos. 250 mm 2 Nos. Make - IVI/IVC, Kirloskar or VAG Valves as per specification. Providing & fixing double acting air valve as per to IS 14845:2000 with Isolating sluice valve class PN 1.6 as per IS 14846-2000 duly inspected by DGS & D/SGS/RITES :80 mm dia 18 Nos. Make - IVI/IVC, Kirloskar or VAG Valves as per specification. Construction of RCC valve chambers in all the places where sluice valve, Air valve and nonreturn valve are provided, Anchor Blocks, Pedestal etc. as required as per specification. The internal dimension of R.C.C. chamber shall have clear space of 500 mm all around in valve. This clearance can be modified only after with instruction issued by the Engineer in charge looking to the site conditions. D:\533577160.doc - 54 - 1.6 Back filling of trench as per IS:12288-1987. Making the road surface enough for motorist movement for traffic. 1.7 Restoration of roads making it smooth for traffic and other existing services back to normalcy, damaged during the execution of work. The restoration of bituminous surface/CC roads is also included in the scope of work. 1.8 Disposal of surplus excavated stuff within a distance of 10 Km. 1.9 Operation and Maintenance / Trial run of raw & clear water pumping main for a period of 6 months from the date of commissioning. 1.10 Hydraulic testing of pipelines to the desired pressure Providing lowering laying jointing of MS pipeline by push through method below the railway line including getting permissions from Railways and other concerned Departments, the work to include providing casing pipe, carrier pipe, pushing the pipes by jacking, interconnection to the existing pipes Interconnection to the existing DI pipes which are to be utilized for this project and rehabilitation of existing pipes if necessary Providing and installation of full bore electromagnetic bulk flow meters for measurement of flow at each inlet of the gravity main and pumping main with complete fixtures and accessories 1.14 2.0 STANDARD SPECIFICATIONS OF CLEAR WATER PUMPING MAIN: Except where otherwise specified pipe, material and workmanship shall comply with the requirement of the relevant Indian standard (hereinafter referred to as IS) issued by the Bureau of Indian standards. The following specifications, standards and code are part of this specification. IS:11906 - Recommendation for cement mortar lining for cast iron, mild steel and ductile iron pipes and fittings for transportation of water IS:432 (Part 1) – Mild steel and medium tensile bars and hard drawn steel wire for concrete reinforcement part 1. Mild steel and medium tensile bars. IS:432 (Part 2) – Mild steel and medium tensile bars and hard drawn steel wire for concrete reinforcement part 2. Hard drawn steel bars. Specification for cement - ordinary port land cement/portland slag cement/concrete special cement as per relevant ISS. IS:383 - Specification for coarse and fine aggregate from natural source. IS:456 - Code for practice for plain and reinforced concrete. IS:800 - Code of practice for general construction in steel. IS:5822 - Code of practice for laying electrically welded steel pipes for water supply. IS:14846-2000 - Specification for sluice valve IS:14845-2000 - Specification for air valve IS:12288-1987 - Code of practice for back filling of trenches. D.I. PIPES 2.1 MANUFACTURE :- 2.2 The pipes shall be ISI Mark and confirming to IS:8329:2000. The pipes should be duly inspected by D.G.S. & D./SGS/RITES before supply. HYDROSTATIC TEST 2.2.1 2.3 Pipes shall be tested at manufacturer end at factory as per relevant IS codes. TOLERANCES : D:\533577160.doc - 55 - 2.3.1 2.4 The tolerance shall be permissible as per IS:8329-2000. COATING : 2.4.1 All the D.I. pipes should be internally in lined with cement mortor and externally out coated with metallic zinc coating having finishing layer as indicated in Annexure A, as per IS 8329-2000. 2.5 MARKING : Each pipe shall have cast, stamped or indelibly painted on it the following appropriate marks : 2.5.1 a) b) c) d) e) a) b) 2.5.2 Indication of the source of manufacture. The nominal diameter. Class reference Mass of Pipe, and The last two digits of the year of manufacture. Marking may be done : On the socket faces of pipe centrifugally cast in metal mould, and On the outside of the socket or on the barrel of pipe centrifugally cast in sand mould. Any other marks required by the purchaser may be painted on. 3.0 DUCTILE IRON FITTINGS : 3.1 The Ductile Iron fittings shall be ISI mark conforming to IS 9523-2000. 3.2 COATING : 3.2.1 Fittings and accessories shall be normally delivered internally and externally coated. 3.2.2 The external coatings shall be applied with zinc rich paint with finishing layer as included in Annexure “A” of IS 9523:2000. 3.2.3 The internal Linings shall be applied with portland cement mortor (with or without additions) as included in Annexure “B” of IS 9523:2000. 3.3 MARKING : 3.3.1 Each fittings shall have as cast, stamped or indelibly painted on it, the following appropriate marks : a) Indication of the source of manufacture, B) The nominal diameter, C) The last two digits of the year of manufacture, d) PN rating flanges when applicable, and e) Any other mark required by the purchaser. 3.3.2 Marking may be done on the barrel of castings or on the outside of the sockets. 3.4 BIS Certification Marking The fittings may also be marked with the Standard Mark. 4.0 LAYING AND JOINTING : 4.1 SITE PREPARATION : 4.1.1 Preliminary work required to be done before laying of pipe lines includes pegging out, clearing and disposal of all shrubs, grasses, large and small bushes, trees, hedges, fences, gates, portions of old masonry, boulders, and debris from the route. 4.1.2 Where trees have been felled, the resulting timber shall be stacked properly and disposed of as directed by the authority. Tree roots within a distance of about 0.5 metre from either side of the pipeline should be completely removed before laying pipe lines. 4.1.3 All other serviceable materials, such as wood, bricks and stones, recovered during the operation and clearing the site, shall be separately stacked and disposed of as directed by the authority. 4.2 FORMATION : D:\533577160.doc - 56 - 4.2.1 GENERAL : Before pipe line is laid, proper formation be prepared for pipe line 4.3 Excavation and Preparation of Trenches for Laying Underground Pipe Lines. 4.3.1 Excavation work is to be carried as per relevant IS code. 4.3.2 Special consideration should be given to the depth of the trench. In agricultural land, the depth should be sufficient to provide a cover of not less than 900 mm so that the pipe line will not interfere with the cultivation of the land. In rocky ground, rough grazing or swamps, the cover may be reduced provided the water in the pipe line is not likely to freeze due to frost. 4.3.3 It may be necessary to increase the depth of pipe line to avoid land drains or in the vicinity of roads, railways or other crossings. 4.3.4 Care should be taken to avoid the spoil bank causing an accumulation of rain water. 4.3.5 Where pipes are to be bedded directly on the bottom of the trench, it should be trimmed and levelled to permit even bedding of the pipe line and should be free from all extraneous matter which may damage the pipe or the pipe coating. Additional excavation should be made at the joints of the pipe so that the water main is supported along its entire length. 4.3.6 Where excavation is through rocks or boulders or at locations of B.C. soils the pipe line should be bedded on concrete bedding or on at least 150 mm of fine grained material, or other proper means are used to protect the pipe and its coating. Material harmful to the pipe line should not be used. 4.3.7 Temporary under pining, supports and other protective measures for building structures or apparatus in or adjacent to the trench should be of proper design and sound construction. 4.4 ROCK EXCAVATION - The term “rock” wherever used in this standard, shall have the same meaning as given in terminology in IS:1200 (Part 1)- 1974. 4.4.1 Blasting - Blasting for excavation shall be permitted only after securing the approval of the authority and only when proper precautions are taken for the protection of persons and property. The hours of blasting shall be fixed by the authority. The procedure of blasting shall conform to the requirements of the authority. 4.5 Stacking Excavated Material - All excavated material shall be stacked in such a manner that it will not endanger the work or workmen and it will avoid obstructing footpaths, roads and driveways. Hydrants under pressure, surface boxes, fire or other utility controls shall be left unobstructed and accessible during the construction work. Gutters shall be kept clear or other satisfactory provisions made for street drainage, and natural water-courses shall not be obstructed. 4.6 Barricades, Guards and Safety Provisions - To protect persons from injury and to avoid damage to property, adequate barricades, construction signs, torches, red lanterns and guards, as required, shall be placed and maintained during the progress of the construction work and until it is safe for traffic to use the roadways. All materials, piles equipment and pipes which may serve as obstruction to traffic shall be enclosed by fences or barricades and shall be protected by illuminating proper lights when the visibility is poor. The rules and regulations of the local authorities regarding safety provisions shall be observed. 4.7 Maintenance of Traffic and Closing of Streets - The work shall be carried including closing of road/street in such a manner which will cause the least interruption to traffic. Where it is necessary for traffic to cross the open trenches, suitable bridges shall be provided. 4.7.1 Suitable signs indicating that a street is closed shall be placed and necessary detour signs for the proper maintenance of traffic shall be provided. 4.8 Protection of Property and Structures - Trees, shrubbery, fences, poles, and all other property and surface structures shall be protected unless their removal is shown on the drawings or authorised by the authority. When it is necessary to cut roots and tree branches, cutting shall be done under the supervision and direction of the authority. D:\533577160.doc - 57 - Temporary support, adequate protection and maintenance of all underground and surface structures, drains, sewers and other obstructions encountered in the progress of the work, shall be provided under the direction of the authority. The structures, which may have been disturbed, shall be restored after completion of the work. 4.9 Protection of the Existing Service - As far as possible, the pipe line shall be laid below existing services, like water and gas pipes, cables, cable ducts and drains but not below sewers which are usually laid at greater depth. Where it is unavoidable, pipe line should be suitably protected. A minimum clearance of 150 mm shall be provided between the pipe line and such other services. Where thrust or auger boring is used for laying pipe line across roads, railways or other existing utilities, large clearance as required by the existing utilities, as required shall be provided. Adequate arrangements shall be made to protect and support the existing services during the laying operations. The pipe line shall be so laid as not to obstruct access to other services for inspection, repair and replacement. When such utilities are met with during excavation, the authority concerned shall be intimated and arrangements should be made to support and protect the utilities in consultation with them and in case of such damaged services will be repaired at the cost of contractor himself. 4.10 Back-Filling - For the purpose of back-filling, the depth of the trench shall be considered as divided in to the following three zones from the bottom of the trench to its top : a) Zone A : From the bottom of the trench to the level of the centre line of the pipe. b) Zone B : From the level of the centre line of the pipe to a level 300 mm above the top of the pipe, and c) Zone C : From a level 300 mm above the top of the pipe to the top of the trench. 4.10.1 Back-filling in Zone A shall be done by hand with sand, fine gravel or other approved material placed in layers of 80 mm and compacted by tamping. The back-filling material shall be deposited in the trench for its full width of each side of the pipe, fitting and appurtenances simultaneously. 4.10.2 Back-filling in Zone B shall be done by hand or approved mechanical methods in layers of 150 mm special care being taken to avoid injuring or moving the pipe. The type of back-fill material to be used and the method of placing and consolidating shall be prescribed by the authority to suit individual locations. 4.10.3 Back-filling in Zone C shall be done by hand or approved mechanical methods. The types of back-fill material and method of filling shall be as prescribed by the authority. Back-fill under permanent Pavement - Where the excavation is made through permanent pavements, curbs, paved footpaths, or where such structures are undercut by the excavation, the entire back-fill to the sub grade of the structures shall be made with sand in accordance with 5.10.4.1 Paved footpaths and pavements consisting of stone, gravel, slag or cinders shall not be considered as being of a permanent construction. Method of placing and consolidating the backfill material shall be prescribed by the authority. 4.10.4 5.0 LAYING OF PIPES : 5.1 Laying Underground - Pipes should be lowered in to the trench with tackle suitable for the weight of pipes. For smaller sizes, up to 250 mm nominal bore, the pipe may be lowered by the use of ropes but for heavier pipes, either a well designed set of shear legs or mobile crane should be used. When lifting gear is used, the positioning of the sling to ensure a proper balance, should be checked when the pipe is just clear of the ground. If sheathed pipes are being laid, suitable wide slings or scissors dogs should be used. All construction debris should be cleared from the inside of the pipe either before or just after a joint is made. This is done by passing a pull-through in the pipe, or by hand, depending on the size of the pipe. When laying is not in progress, a temporary end closure should be securely fitted to the open end of the pipe line. This may make the pipe buoyant in the event of the trench becoming flooded, in which case the pipes should be held down either by partial refilling of the trench or by temporary strutting. All persons should vacate any section of trench in to which the pipe is being lowered. 5.2 Pipe Line Anchorage - D:\533577160.doc - 58 - This shall be provided as per relevant BIS 5330:1984 with up to date amendments. 6.0 TRANSPORTATION, HANDLING AND INSPECTION : 6.1 General – Ductile iron pipes are less susceptible to cracking or breaking on impact but the precautions set out should be taken to prevent damage to the protective coating and brushing or damage of the jointing surfaces. 6.2 Transportation - Pipes should be loaded in such a way that they are secured and that no movement should taken place on the vehicle during transit. 6.3 Off-Loading - Cranes should be preferred for off-loading. However, for pipe up to 400 mm nominal bore, skid timbers and ropes may be used. HYDRAULIC TESTING : After a new pipe line is laid and jointed, testing shall be done for : 7.1 a) mechanical soundness and leak tightness of pipes and fittings ; b) leak tightness of joints; and c) soundness of any construction work, in particulars that of the anchorages 7.0 7.2 The completed pipe line shall be tested for a pressure of 15kg/cm2.in all section of work done. 7.3 10% amount of complete work shall be withheld till successful hydraulic of the pipe line 8.0 FLUSHING AND DISINFECTION OF MAINS BEFORE COMMISSIONING : 8.1 The distribution mains shall be disinfected before commissioning as per provisions given in CPHEEO manual and IS 5822:1970. 9.0 REMOVAL, RESTORATION AND MAINTENANCE OF PAVED FOOTPATHS ETC. AFTER LAYING OF PIPE : 9.1 Allowable Removal of Pavement - Pavement and road surfaces may be removed as a part of the trench excavation, and the amount removed shall depend upon the width of trench specified for the installation of the pipe and the width and length of pavement area required to be removed for the installation of gate valves, specials, manholes or other structures. The width of pavement removed along the normal trench for the installation of the pipe shall not exceed the width of the trench specified by more than 150 mm on each side of trench. The width and the lengths of the area of pavement removed from the installation of gate valves, specials, manholes or other structures should not exceed the maximum linear dimensions of such structures by more than 150 mm on each side. Wherever, in the opinion of the authority, existing conditions make it necessary or advisable to remove additional pavement, it shall be removed as directed by the authority. 9.2 Restoration of Damaged Surface and Property - Where any pavement, shrubbery, fences poles or other property and surface structures have been damaged, removed or disturbed during the course of work, such property and surface structures shall be replaced or repaired after completion of work. The permanent pavement shall not be restored to a condition equal to that before the work began but the top surface of the removed pavement shall be levelled and finished in such a manner as the traffic may pass smoothly. After proper compaction and settlement only it shall be made to original as per the type of road top is existing 9.3 Cleaning-up : All surplus materials, and all tools and temporary structures shall be removed from the site as directed by the authority. All dirt, rubbish and excess earth from the excavation shall be hauled to a dump and the construction site left clean to the satisfaction of the authority. 10.0 APPURTENANCES : The following appurtenances shall be suitable designed and fixed on the suitable points on the distribution mains. 10.1 SLUICE VALVES (Shaft seated) : D:\533577160.doc - 59 - The sluice valve shall be installed on pumping mains as indicated on the enclosed drawing. The sluice valve shall be class PN 1.6 up to 600 mm dia & class PN 1.0 above 600 mm dia conforming to IS 14846:2000 duly inspected by DGS & D/SGS/RITES & shall be of IVC/Kirloskar/VAG/IVI make. 10.2 KINETIC AIR VALVES : Double orifice type Kinatic Air Valves shall be fixed on the pumping mains at the points indicated on the attached Drawing coupled with isolating sluice valve. The Air valves shall conform to IS 14845-2000. The valves shall be IVC/Kirloskar/VAG/IVI make duly inspected by DGS & D/SGS/RITES. 10.3 BRANCH CONNECTIONS : “T” outlet with manually operated sluice valves shall be provided in the distribution pressure Main for Branch connections. 10.4 The appurtenances shall be located in such a way that these are clearly and easily accessible for operation and maintenance. 11.0 CONSTRUCTION OF CHAMBERS FOR APPURTENANCES : 11.1 CHAMBER FOR APPURTENANCES : The suitable RCC chambers shall be constructed around the appurtenances and valves fixed on the line, the minimum working space shall be 500mm on all sides are as directed by the Engineer-in-Charge The chamber shall have Pre cast RCC cover conforming to IS:456-2000 suitable for heavy traffic loads. 11.2 CIVIL WORKS : All the allied civil works necessary for laying and jointing of pipeline shall be a part of this contract; therefore, the contractor shall design and carry out the necessary civil works such as thrust blocks, anchor blocks, chambers for appurtenances and necessary earth work. All the civil works shall be designed and carried out as per the relevant Indian Standard Code of practice. All the materials used on civil work should be of a quality approved by Executive Engineer. Rejected material shall be removed from the site immediately at the cost of contractor. 12.0 TESTING, COMMISSIONING OF PIPE LINE, TRAIL RUN AND DEFECT LIABILITY PERIOD:After completing the job of laying and jointing of pipe line the contractor will do testing, commissioning including trial run for 6 months . The repairing of bursting and leakage of pipeline during this period shall be done by the contractor at his cost including cost of all materials. The water for testing and commissioning of pipe line will be made available by the Deptt. free of cost at the time when convenient to the deptt. In case of delay in making available the water for testing the time extension will be given to the contractor without penalty for such period. Defect liability period shall be 6 months from the date of completion of work. 13.0 14. Inspection of Pipes, valves & fittings Inspection of the pipes, valves & fittings will be done by the DGS&D/SGS/RITES. The departmental officials may also inspect at factory site. THRUST BLOCKS 14.1 Thrust blocks are required to transfer the resulting hydraulic thrust from the fitting or pipe on to a larger load bearing soil section & shall be designed as per ISS. 14.2 Thrust blocks shall be installed wherever there is a change in the direction of the pipe line, size of the pipe line or the pressure-line diagram, or when the pipe line ends at a dead end. If necessary, thrust blocks may be constructed at valves also. D:\533577160.doc - 60 - 14.3 Thrust blocks shall be constructed taking into account the pipe size, water pressure, type of fitting, gravity component shell when laid on slopes and the type of soil. The location of thrust blocks for various types of fittings is given. 14.4 When a fitting is used to make a vertical bend, it shall be anchored to a concrete thrust block designed to have enough weight to resist the upward and outward thrust. Similarly at joints, deflected in vertical plane, it shall be ensured that the weight of the pipe, the water in the pipe and the weight of the soil over the pipe provide resistance to upward movement. If it is not enough, ballast or concrete shall be placed around the pipe in sufficient weight to counteract the thrust. 14.5 When the line is under pressure there is an outward thrust at each coupling. Good soil, properly tamped is usually sufficient to hold pipe from side movement. However, if soft soil conditions are encountered, it may be necessary to provide side thrust blocks or other means of anchoring. In such cases only the pipe on each side of the deflected coupling shall be anchored without restricting the coupling. 14.6 Pipes on slopes need be anchored only when there is a possibility of the backfill around the pipe sloping down the hill and carrying the pipe with it. Generally for slopes up to 30 0 good well drained soil, carefully tamped in layers of 100 mm under and over the pipe, right up to the top of the trench will not require anchoring. 14.7 For steeper slopes, one out of every three pipes shall be held by straps fastened to vertical supports anchored in concrete. 15 DISINFECTION OF PIPE LINE BEFORE COMMISSIONING: 15.1 Pipeline carrying potable water shall be suitably disinfected before commissioning as per guidelines given in CPHEEO Manual & relevant IS codes. 16 The firms/contractors are directed to submit the details plan and elevation of all the pipelines showing the dimensions of all components and other details. 17 The contractor shall set up an office with an access to KMC official with proper seating arrangements. 18 The contractor shall provide one AC Bolero/ Scorpio vehicle with driver and POL for inspection work during the entire work period exclusively for KMC officials. 19 The contractor shall propose colour scheme with atleast three alternatives and after approval only the workshall be started. 20 All the valves and electromechanical fittings shall be SCADA & PLC compatible with actuators for implementation of SCADA in future. 21. The successful bidder shall assist the KMC in the process of getting the grants from State/ Central KMCs. 22. The contractor has to procure and install informatory board’s displaying Name of work at the location given by KMC at his own cost. D:\533577160.doc - 61 - ANNEXURE - F Providing, laying, jointing, interconnection, testing, commissioning of Clear water Pumping Mains of D.I. pipe class K-9 with valves and specials and all allied civil works Under Augmentation Water supply Scheme for Korba town. SCHEDULE OF QUANTITY (i) Clear water pumping main - S.N. PARTICULARS QTY RATE PER Excavation: Earthwork in excavation for pipe trench in all kinds of soil in areas including dressing, watering and ramming and disposal of excavated earth lead upto 50m & lift upto 1.5, disposal earth to be levelled, neathly dressed for Both the Zones Dia 800mm dia D.I pipe class K-9 Length Width 2487.00 1.4 3761.00 700mm dia D.I pipe class K – 9 0.00 1.3 0.00 600mm dia D.I pipe class K – 9 0.00 1.2 0.00 500mm dia D.I pipe class K – 9 0.00 1.1 0.00 450mm dia D.I pipe class K – 9 0.00 1.05 0.00 400mm dia D.I pipe class K – 9 5132.00 1 4311.00 350mm dia D.I pipe class K – 9 2043.00 0.95 1572.09 300mm dia D.I pipe class K – 9 2707.00 0.9 1900.32 250mm dia D.I pipe class K – 9 1635.00 0.85 1042.32 200mm dia D.I pipe class K – 9 0.00 0.8 0.00 150mm dia D.I pipe class K – 9 0.00 0.75 0.00 12587 (CG PHE SOR P.19 It.No. 2.1) 12586.73 Earth work in excavation for pipe trench in all kinds of soft rock in areas i/c dressing, watering and ramming and disposal of excavated earth lead upto 50 meters & lift upto 1.5m, disposal earth to be leveled, neatly dressed, including dismentaling of CC Road. Dia 2 Length Width 800mm dia D.I pipe class K – 9 2487 1.40 2506.90 700mm dia D.I pipe class K – 9 0 1.30 0.00 600mm dia D.I pipe class K – 9 0 1.20 0.00 500mm dia D.I pipe class K – 9 0 1.10 0.00 450mm dia D.I pipe class K – 9 0 1.05 0.00 400mm dia D.I pipe class K – 9 5132 1.00 2873.92 350mm dia D.I pipe class K – 9 2043 0.95 1048.06 D:\533577160.doc - 62 - Cum S.N. PARTICULARS QTY 300mm dia D.I pipe class K – 9 2707 0.90 1266.88 250mm dia D.I pipe class K – 9 1635 0.85 694.88 200mm dia D.I pipe class K – 9 0 0.80 0.00 150mm dia D.I pipe class K – 9 0 0.75 0.00 (CG PHE SOR P.19 It.No. 2.5a) 8390.64 RATE PER Cum Pumping out water caused by springs, tides or river 3 seepage, broken water mains. 20000 KL 800mm dia D.I pipe class K – 9 2487.00 Mtr 700mm dia D.I pipe class K – 9 0.00 Mtr 600mm dia D.I pipe class K – 9 0.00 Mtr 500mm dia D.I pipe class K – 9 0.00 Mtr 450mm dia D.I pipe class K – 9 0.00 Mtr 400mm dia D.I pipe class K – 9 5132.00 Mtr 350mm dia D.I pipe class K – 9 2043.00 Mtr 300mm dia D.I pipe class K – 9 2707.00 Mtr 250mm dia D.I pipe class K – 9 1635.00 Mtr 200mm dia D.I pipe class K – 9 0.00 Mtr 150mm dia D.I pipe class K – 9 0.00 Mtr (CG PHE SOR P.20 It.No. 2.9) Providing, laying and jointing socket & spigot centrifugally cast (Spun) Ductile Iron pressure pipes with inside cement mortar lining (class K-9) Conforming to IS 8329/2000 with suitable Rubber Gasket (Push on) joints as per IS:5382/85 including testing of joint (laying Conforming to IS 12288 : 1987) 4 (CG PHE SOR P.74 It.No. 6.3) Providing & Laying Ductile Iron Double Socket branch flange Tee Conforming to IS-9523/2000 having dimension as per table 21 of IS-9523/2000 in the nominal diameter/sizes with external bitumen coating and internal cement mortar lining with finishing as per clause 13 of IS9523/2000. (laying Conforming to IS 12288 : 1987) (All 5 sizes in mm) 800x800x200 mm 18.00 Each 400 X 400 X 80 mm 7.00 Each 350x350x80 mm 7.00 Each 350x350x300 mm 1.00 Each 300x300x80 mm 6.00 Each 300 x 300 x 250 mm 2.00 Each D:\533577160.doc - 63 - S.N. PARTICULARS QTY 250x250x80 mm RATE PER 3.00 Each 400 x 350 2.00 Each 350 x 300 mm 1.00 Each 300 x 250 mm 2.00 Each 200 mm 5.00 Each 100 mm 17.00 Each 800 mm 5.00 Each 400 mm 4.00 Each 350 mm 3.00 Each 300 mm 3.00 Each 250 mm 2.00 Each 10.00 Each (CG PHE SOR P.88 It.No. 6.23) Providing & Laying Ductile Iron Double Socket Reducer Conforming to IS-9523/2000 having dimension as per table 21 of IS-9523/2000 in the nominal diameter/sizes with external bitumen coating and internal cement mortar lining 6 with finishing as per clause 13 of IS-9523/2000. (laying Conforming to IS 12288 : 1987) (All sizes in mm) (CG PHE SOR P.91 It.No. 6.25) Supply of DI D/F Sluice Valves Slanted/Straight seated with metallic, corrosion proof and wear resistant seat faces, body and disc of ductile cast iron GGG 50/SG Iron 420/12 or equivalent grade as per IS 3896 (part-2) - 1985 and subsequent revisions. Shafts of stainless steel, shaft bearing of zinc free bronze and seat faces with nickel weld over lay, micro finished. All the inside and outside of the body is to be coated with double coating of Epoxy liquid. Drilled as per IS:1538. 7 Scour Valves Isoleting Sluice Valves (CG PHE SOR P.124 It.No. 8.9) Providing and Laying ductile iron PN-1.0 type flanged spigot Conforming to IS-9523/2000 having dimension as per table 8 24 of IS-9523/2000 in the nominal diameter/sizes with external bitumen coating and internal cement mortar lining with finishing as per clause 13 of IS-9523/2000. (laying Conforming to IS 12288 : 1987) Scour Valves 200 mm D:\533577160.doc - 64 - S.N. PARTICULARS 100 mm QTY RATE PER 34.00 Each 800 mm 10.00 Each 400 mm 6.00 Each 350 mm 5.00 Each 300 mm 4.00 Each 250 mm 4.00 Each 18.00 Each 800 mm 5.00 Each 400 mm 4.00 Each 350 mm 3.00 Each 300 mm 3.00 Each 250 mm 2.00 Each 800 mm 4.00 Each 400 mm 4.00 Each 350 mm 4.00 Each Isoleting Sluice Valves (CG PHE SOR P.94 It.No. 6.29 Providing & fixing cast iron double air valves, flanged 9 without in-built isolating valve as per IS : 14845-2000 including jointing & testing with cost of jointing material and rubber insertion all complete as per IS :13095-1991 80 mm (CG PHE SOR P.127 It.No. 8.17 Providing and Supply of C.I. Mechanical Compression flanged /socket tail piece (Popularly known as 1TM Flanged/ Socket Tailpiece) suitable for making flanged connection with the plain barrel of C.I. Spun Pipes (as per IS1536/2001) and D.I. Pipes (as per IS 8329/2000). The Tailpiece to be supplied complete with sealing rubber gasket of S.B.R., C.I. Follower Glands and M.S. Nut Bolts. The 10 whole assembly should be mechanically and hydraulically tested to the provisions as laid down in IS : 1538/1993. (CG PHE SOR P.129 It.No. 8.24 Providing and Laying ductile iron PN-1.6 type flanged sockets Conforming to IS-9523/2000 having dimension as per table 23 of IS-9523/2000 in the nominal diameter/sizes 11 with external bitumen coating and internal cement mortar lining with finishing as per clause 13 of IS-9523/2000. (laying Conforming to IS 12288 : 1987) D:\533577160.doc - 65 - S.N. PARTICULARS QTY RATE PER 300 mm 4.00 Each 250 mm 4.00 Each 800 mm 4.00 Each 350 mm 4.00 Each 300 mm 3.00 Each 250 mm 2.00 Each 800 mm 6.00 Each 400 mm 3.00 Each 350 mm 2.00 Each 300 mm 2.00 Each 250 mm 3.00 Each 800 mm 8.00 Each 400 mm 4.00 Each 350 mm 5.00 Each 300 mm 8.00 Each 250 mm 2.00 Each (CG PHE SOR P.78 It.No. 6.7 Providing & Laying Ductile Iron Double Socket 90° Bends Conforming to IS-9523/2000 having dimension as per table 15 of IS-9523/2000 in the following nominal diameter/sizes with external bitumen coating and internal cement mortar lining. (laying Conforming to IS 12288 : 12 1987) (CG PHE SOR P.79 It.No. 6.13 Providing & Laying Ductile Iron Double Socket 45° Bends Conforming to IS-9523/2000 having dimension as per table 16 of IS-9523/2000 in the nominal diameter/sizes with external bitumen coating and internal cement mortar lining. 13 (laying Conforming to IS 12288 : 1987) (CG PHE SOR P.80 It.No. 6.15 Providing & Laying Ductile Iron Double Socket 22.5° Bends Conforming to IS-9523/2000 having dimension as per table 17 of IS-9523/2000 in the nominal diameter/sizes with external bitumen coating and internal cement mortar lining. 14 (laying Conforming to IS 12288 : 1987) (CG PHE SOR P.81 It.No. 6.17 D:\533577160.doc - 66 - S.N. PARTICULARS QTY RATE PER Providing & fixing cast iron double flanged multi door reflux (non return) valves including jointing & testing with cost of jointing material such as bolts, nuts and rubber insertion all complete as per IS : 5312 (Part II) 15 800 mm 1.00 Each 400 mm 1.00 Each 350 mm 1.00 Each 300 mm 1.00 Each 250 mm 1.00 Each 3000.00 Kg 25.00 Cut (CG PHE SOR P.125 It.No. 8.10b Steel work is welded in built-up section tee & frame i/c 16 cutting hoisting/fixing and painting with red lead paint. (i) In R.S. Joint in flat iron /angle / channel / bar. (CG PHE SOR P.23 It.No. 2.25.4) Labour for cutting following Ductile iron pipes of any type 17 and class. 600 mm (CG PHE SOR P.125 It.No. 8.10b Filling available excavated earth in trenches, plinth sides of foundation in layers not exceeding 20cm. in depth including consolidation of each layer by ramming watering, lead up to 18 50m and lift up to 1.5m in all kinds of soils Quantity of Excavation Deduct volume 20977.37 of pipe & Moorum Quantity Deduct Volume of Pipe 2361.97 Deduct Volume of Concrete 1335.30 (CG PHE SOR P.20 It.No. 2.10.1) 17280.10 Cum Providing & laying mechanically mixed cement concrete 20mm nominal size graded crushed stone excluding cost of 19 centering & shuttering. 500 x 1.4 x 0.15 120.00 50 x 1.4 x .15 10.50 (CG PHE SOR P.21 It.No. 2.21.1.1) 130.50 Providing and laying mechanically mixed reinforced cement concrete of grade M-20 excluding centering, shuttering and 20 reinforcement in foundation, plinth and in superstructure. for Encasing pipe in road crossings 500 D:\533577160.doc m x 1.4 x 1.4 - 67 - 1120 Cum S.N. PARTICULARS QTY Less pipe volum of 800mm pipe 251.2 Net Quantity of Concrete 868.8 RATE PER For thrust blocks 50 Nos. 1.4 1.6 (CG PHE SOR P.21 It.No. 2.21.1.3) 336 1204.8 Cum 47288.4 per Kg 29 each 8601.00 Cum 2867 Sq.m Providing and placing in position cold twisted steel and hot rolled deformed steel reinforceement for RCC work i\c 21 cutting, bending, binding etc. complete i/c cosat of binding wire and wastage 1204.8 x (.5/100)*7850 (CG PHE SOR P.23 It.No. 2.25.1.2 Construction of Rcc valve chamber with Rcc precast cvers 22 100mm to 600mm dia For 300mm - 800 mm dia (cost as per annexure I enclosed) Restoring the W.B.M. Road excavated for laying of pipeline by providing laying and compacting of WBM sub-base/base course including preparation and compaction of sub-base and spreading of clean and crushed aggregate to proper 23 grade and camber including application of screenings for interlocking, sprinkling of water and rolling with power roller with grading material (63 mm to 45 mm size) with moorum as screenings. Restoring of CC Roads Excavation, filling moorum and compaction, watering etc 24 complete then placing the M-20 concrete, making rough finish for road top etc complete (As per rate analysis Annexure II D:\533577160.doc - 68 - (ii) Clear water Gravity main S.N. PARTICULARS QTY RATE PER Excavation: Earthwork in excavation for pipe trench in all kinds of soil in areas including dressing, watering and ramming and disposal of excavated earth lead upto 50m & lift upto 1.5, disposal earth to be levelled, neathly dressed for Both the Zones Dia 1 Length Depth 800mm dia D.I pipe class K - 7 186 1.08 1.40 282.00 700mm dia D.I pipe class K - 7 719 1.02 1.30 954.00 600mm dia D.I pipe class K - 7 0 0.96 1.20 0.00 500mm dia D.I pipe class K - 7 430 0.90 1.10 426.00 450mm dia D.I pipe class K - 7 0 0.90 1.05 0.00 400mm dia D.I pipe class K - 7 3104 0.84 1.00 2608.00 350mm dia D.I pipe class K - 7 1444 0.81 0.95 1112.00 300mm dia D.I pipe class K - 7 3558 0.78 0.90 2498.00 250mm dia D.I pipe class K - 7 3208 0.75 0.85 2046.00 200mm dia D.I pipe class K - 7 0 0.72 0.80 0.00 160 mm HDPE 0 0.69 0.75 0.00 110 mm HDPE 0 0.66 0.70 0.00 Total Length Width 12649 9926.00 Earth work in excavation for pipe trench in all kinds of soft rock in areas i/c dressing, watering and ramming and disposal of excavated earth lead upto 50 meters & lift upto 1.5m, disposal earth to be leveled, neatly dressed , including dismentaling of CC Road. 2 D:\533577160.doc Dia Dia Length Depth Length Width Width 800mm dia D.I pipe class K - 7 186 0.72 1.40 188.00 700mm dia D.I pipe class K - 7 719 0.68 1.30 636.00 600mm dia D.I pipe class K - 7 0 0.64 1.2 0.00 500mm dia D.I pipe class K - 7 430 0.60 1.1 284.00 450mm dia D.I pipe class K - 7 0 0.60 1.05 0.00 - 69 - Cum S.N. PARTICULARS QTY 400mm dia D.I pipe class K - 7 3104 0.56 1 1739.00 350mm dia D.I pipe class K - 7 1444 0.54 0.95 741.00 300mm dia D.I pipe class K - 7 3558 0.52 0.9 1666.00 250mm dia D.I pipe class K - 7 3208 0.50 0.85 1364.00 200mm dia D.I pipe class K - 7 0 0.48 0.8 0.00 160 mm HDPE 0 0.46 0.75 0.00 110 mm HDPE 0 0.44 0.7 0.00 12649 0.44 0 0.00 Total Length (CG PHE SOR P.19 It.No. 2.5a) 6618.00 RATE PER Cum Pumping out water caused by springs, tides or river 3 seepage, broken water mains or drains. 15000 KL (CG PHE SOR P.20 It.No. 2.9) Providing, laying & jointing following socket & spigot centrifugally cast(spun) Ductile iron pressure pipes with inside cement motor lining (class K - 7) conforming to IS 8329/2000 with suitable Rubber Gasket (Push on ) joint as per IS : 5382/85 4 800mm dia D.I pipe class K - 7 186.00 Mtr 700mm dia D.I pipe class K - 7 719.00 Mtr 600mm dia D.I pipe class K - 7 0.00 Mtr 500mm dia D.I pipe class K - 7 430.00 Mtr 450mm dia D.I pipe class K - 7 0.00 Mtr 400mm dia D.I pipe class K - 7 3104.00 Mtr 350mm dia D.I pipe class K - 7 1444.00 Mtr 300mm dia D.I pipe class K - 7 3558.00 Mtr 250mm dia D.I pipe class K - 7 3208.00 Mtr 200mm dia D.I pipe class K - 7 0.00 Mtr 160 mm HDPE 0.00 Mtr 110 mm HDPE 0.00 Mtr Total Length 12649 (CG PHE SOR P.73 It.No. 6.1) Specials D:\533577160.doc - 70 - S.N. PARTICULARS QTY RATE PER Providing & Laying Ductile Iron Double Socket branch flange Tee Conforming to IS-9523/2000 having dimension as per table 21 of IS-9523/2000 in the nominal diameter/sizes with external bitumen coating and internal cement mortar lining with finishing as per clause 13 of IS9523/2000. (laying Conforming to IS 12288 : 1987) (All sizes in mm) 5 800 x 300 2.00 Each 700 x 600 1.00 Each 700 x 400 1.00 Each 700 x 80 6.00 Each 600 X 600 8.00 Each 500 x 400 1.00 Each 500 X 100 26.00 Each 450 X 450 16.00 Each 400 X 400 1.00 Each 400 X 300 1.00 Each 28.00 Each 1.00 Each 350 X 80 74.00 Each 300 X 80 60.00 Each 250 X 250 58.00 Each 200 X 200 2.00 Each 700 X 400 1.00 Each 500 x 450 1.00 Each 450 x 350 2.00 Each 400 x 350 1.00 Each 350 x 250 1.00 Each 300 x 250 3.00 Each 44.00 Each 400 X 80 350 X 250 (CG PHE SOR P.88 It.No. 6.23) Providing & Laying Ductile Iron Double Socket Reducer Conforming to IS-9523/2000 having dimension as per table 21 of IS-9523/2000 in the nominal diameter/sizes with external bitumen coating and internal cement mortar lining with finishing as per clause 13 of IS-9523/2000. (laying Conforming to IS 12288 : 1987) (All sizes in mm) 6 80 x 50 (CG PHE SOR P.91 It.No. 6.25) D:\533577160.doc - 71 - S.N. PARTICULARS QTY RATE PER Supply of DI D/F Swing Check Valves Slanted/Straight seated with metallic, corrosion proof and wear resistant seat faces, body and disc of ductile cast iron GGG 50/SG Iron 420/12 or equivalent grade as per IS 3896 (part-2) 1985 and subsequent revisions. Shafts of stainless steel, shaft bearing of zinc free bronze and seat faces with nickel weld over lay, micro finished. All the inside and outside of 7 the body is to be coated with double coating of Epoxy liquid. Drilled as per IS:1538. 800 mm 1.00 Each 700 mm 1.00 Each 500 mm 2.00 Each 400 mm 1.00 Each 350 mm 2.00 Each 300 mm 8.00 Each 600 mm 10.00 Each 500 mm 4.00 Each 450 mm 16.00 Each 400 mm 20.00 Each 350 mm 12.00 Each 300 mm 10.00 Each 250 mm 20.00 Each 200 mm 16.00 Each 150 mm 16.00 Each (CG PHE SOR P.123 It.No. 8.8) Providing and Laying ductile iron PN-1.0 type flanged spigot Conforming to IS-9523/2000 having dimension as per table 24 of IS-9523/2000 in the nominal diameter/sizes with external bitumen coating and internal cement mortar lining with finishing as per clause 13 of IS9523/2000. (laying Conforming to IS 12288 : 1987) 8 (CG PHE SOR P.94 It.No. 6.29 Providing & fixing cast iron double air valves, flanged without in-built isolating valve as per IS : 14845-2000 including jointing & testing with cost of jointing material 9 and rubber insertion all complete as per IS :13095-1991 200 MM 1.00 Each 100 MM 25.00 Each (CG PHE SOR P.127 It.No. 8.17 D:\533577160.doc - 72 - S.N. PARTICULARS QTY RATE PER Providing and Supply of C.I. Mechanical Compression flanged /socket tail piece (Popularly known as 1TM Flanged/ Socket Tailpiece) suitable for making flanged connection with the plain barrel of C.I. Spun Pipes (as per IS- 1536/2001) and D.I. Pipes (as per IS 8329/2000). The Tailpiece to be supplied complete with sealing rubber 10 gasket of S.B.R., C.I. Follower Glands and M.S. Nut Bolts. The whole assembly should be mechanically and hydraulically tested to the provisions as laid down in IS : 1538/1993. 200 MM 8.00 Each 100 MM 58.00 Each 600 mm 10.00 Each 500 mm 4.00 Each 450 mm 16.00 Each 400 mm 20.00 Each 350 mm 12.00 Each 300 mm 10.00 Each 250 mm 20.00 Each 200 mm 16.00 Each 150 mm 16.00 Each 800 mm 1.00 Each 700 mm 10.00 Each 600 mm 7.00 Each 500 mm 16.00 Each 450 mm 2.00 Each (CG PHE SOR P.129 It.No. 8.24 Providing and Laying ductile iron PN-1.6 type flanged sockets Conforming to IS-9523/2000 having dimension as per table 23 of IS-9523/2000 in the nominal diameter/sizes with external bitumen coating and internal cement mortar lining with finishing as per clause 13 of IS9523/2000. (laying Conforming to IS 12288 : 1987) 11 (CG PHE SOR P.78 It.No. 6.7 Providing & Laying Ductile Iron Double Socket 90° Bends Conforming to IS-9523/2000 having dimension as per table 15 of IS-9523/2000 in the following nominal diameter/sizes with external bitumen coating and internal 12 D:\533577160.doc cement mortar lining. (laying Conforming to IS 12288 : 1987) - 73 - S.N. PARTICULARS QTY RATE PER 400 mm 3.00 Each 350 mm 3.00 Each 300 mm 0.00 Each 250 mm 2.00 Each 200 mm 2.00 Each (CG PHE SOR P.79 It.No. 6.13 Providing & Laying Ductile Iron Double Socket 60° Bends Conforming to IS-9523/2000 having dimension as per table 16 of IS-9523/2000 in the nominal diameter/sizes with external bitumen coating and internal cement mortar lining. (laying Conforming to IS 12288 : 1987) 800 mm Each 700 mm Each 600 mm 0.00 Each 500 mm 3.00 Each 450 mm 0.00 Each 400 mm 1.00 Each 350 mm 5.00 Each 300 mm 0.00 Each 250 mm 2.00 Each 200 mm 0.00 Each 150 mm 0.00 Each 600 mm 1.00 Each 500 mm 1.00 Each (CG PHE SOR P.80 It.No. 6.14 Providing & Laying Ductile Iron Double Socket 45° Bends Conforming to IS-9523/2000 having dimension as per table 16 of IS-9523/2000 in the nominal diameter/sizes with external bitumen coating and internal cement mortar lining. (laying Conforming to IS 12288 : 1987) 13 450 mm Each 400 mm Each 350 mm 1.00 300 mm Each 250 mm Each 200 mm Each (CG PHE SOR P.80 It.No. 6.15 D:\533577160.doc Each - 74 - S.N. PARTICULARS QTY RATE PER Providing & Laying Ductile Iron Double Socket 22.5° Bends Conforming to IS-9523/2000 having dimension as per table 17 of IS-9523/2000 in the nominal diameter/sizes with external bitumen coating and internal cement mortar lining. (laying Conforming to IS 12288 : 1987) 14 600 mm 1 Each 500 mm 6 Each 450 mm 4 Each 400 mm 4 Each 350 mm 14 Each 300 mm 4 Each 250 mm 11 Each 200 mm 1 Each 600 mm 1.00 Each 500 mm 2.00 Each 450 mm 2.00 Each 400 mm 1.00 Each 350 mm 2.00 Each 300 mm 1.00 Each 250 mm 1.00 Each 200 mm 5.00 Each 1000.00 Kg 100.00 Cut (CG PHE SOR P.81 It.No. 6.17 Providing & fixing cast iron double flanged multi door reflux (non return) valves including jointing & testing with cost of jointing material such as bolts, nuts and rubber insertion all complete as per IS : 5312 (Part II) 15 (CG PHE SOR P.125 It.No. 8.10b Steel work is welded in built-up section tee & frame i/c 16 cutting hoisting/fixing and painting with red lead paint. (i) In R.S. Joint in flat iron /angle / channel / bar. (CG PHE SOR P.23 It.No. 2.25.4) Labour for cutting following Ductile iron pipes of any type 17 and class. Various Dia (CG PHE SOR P.324 It.No. 32.4 Filling available excavated earth in trenches plinth sides of foundation in layers not exceeding 20cm. In depth 18 including consolidation of each layer by ramming, watering, lead up to 50m & lift up to 1.5m in all kinds of soils D:\533577160.doc - 75 - S.N. PARTICULARS QTY Total Quantity of Excavation RATE PER 16544.00 Deduct volume of pipe & moorum Quantity (CG PHE SOR P.20 It.No. 2.10.1) 4166.57 12377.43 Cum Providing & laying mechanically mixed cement concrete 20mm nominal size graded crushed stone excluding cost 19 of centering & shuttering. 3795 x 1.05 x 0.15 597.71 30 x 1.05 x .15 4.73 (CG PHE SOR P.21 It.No. 2.21.1.1) 602.44 Cum Providing and laying mechanically mixed reinforced cement concrete of grade M-20 excluding centering, shuttering and reinforcement in foundation, plinth and in superstructure. for Encasing pipe in road crossings 20 3795 m x 1.05 x 0.8 3187.8 Less pipe volum of 450mm pipe 444.61 Net Quantity of Concrete 2743.19 For thrust blocks 30 Nos. 1.05 1 (CG PHE SOR P.21 It.No. 2.21.1.3) 31.5 2774.69 Cum Providing and placing in position cold twisted steel and hot rolled deformed steel reinforceement for RCC work i\c 21 cutting, bending, binding etc. complete i/c cosat of binding wire and wastage 2774.69 x (0.35/100)*7850 (CG PHE SOR P.23 It.No. 2.25.1.2 Providing and constructing RCC valve chamber with 15cm thick 1:3:6 proportion PCC bedding excluding excavation, cement concrete grade M-15 (Nominal mix) with stone aggregate 20 mm Nominal size for benching, precast RCC 22 frame as directed by Engineer-in-Charge. (Note :- Wall thickness : 0.2 M for depth of 1.2M and 0.35 M for balance depth exceeding 1.2M. 12 mm plaster 1:3 inside chamber). Size 1.8m x1.8m, depth 1.8 M with cover (cost as per annexure I D:\533577160.doc - 76 - per 76234.608 Kg S.N. PARTICULARS QTY RATE PER enclosed) For 300mm & above dia 15.00 each 20.00 Each 5692.05 Sq.m. 8538.075 Sq.m. Providing and constructing Brick masonry valve chamber with 15cm thick 1:3:6 proportion PCC bedding excluding excavation, Brick masonry in C.M. 1:6 proportion, cement concrete grade M-15 (Nominal mix) with stone aggregate 23 20 mm Nominal size for benching, precast RCC as directed by Engineer-in-Charge. (Note :- Wall thickness : 0.23 M for depth of 1.2M and 0.35 M for balance depth exceeding 1.2M. 12 mm plaster 1:3 inside chamber). For less than 300 mm dia (CG PHE SOR P.259 It.No. 23.10.1.6 Restoring the W.B.M. Road excavated for laying of pipeline by providing laying and compacting of WBM subbase/base course including preparation and compaction of 24 sub-base and spreading of clean and crushed aggregate to proper grade and camber including application of screenings for interlocking, sprinkling of water and rolling with power roller with grading material (63 mm to 45 mm size) with moorum as screenings. Restoring of CC Roads Excavation, filling moorum and compaction, watering etc 25 complete then placing the M-20 concrete, making rough finish for road top etc complete (CG PHE SOR P.21 It.No. 2.21.1.3) D:\533577160.doc - 77 - (iii) Railway Crossing by Push Through Method SER.NO. 1 2 3 4 5 6 7 D:\533577160.doc Discription of Item Quantity. Excavation in all types of soils including all lifts and leads. (CG PHE SOR P.19 It.No. 2.1) 288 Cum. Providing and laying PCC in situ Concrete of grade M-150 for bed concreting. (CG PHE SOR P.20 It.No. 2.20.1.4) 14.4 Cum. 130 130 100 100 Rmt. Rmt. Rmt. Rmt. 1952.82 Sqm. 230 Rmt. 2300 Kgs. Proving and supplying of MS Pipe as per relevent IS of following Diameters. (CSR I.No.2 P,no. 162) a) 1600 mm Dia. / 12 mm Tk. b) 800 mm Dia / 12mm Tk. c) 1000 mm Dia. / 12 mm Tk. d) 500 mm Dia / 12mm Tk. (CG PHE SOR P.214 It.No. 17.2.9 & 20 ) Providing and applying of anti corrosive Epoxy painting to outer and inner surface of the casing and carrier pipe of approved make in two coats. (MJP CSR I.No.6 P,no. 255 Non Scheduled) Jacking of MS casing pipe with all necessacery men and machinery with all the arrangements such as jacks etc. complete. (MJP CSR I.No.14 P,no.47 Non Scheduled) For pipe upto 1000 mm dia Steel work is welded in built-up section tee & frame i/c cutting hoisting/fixing and painting with red lead paint. (i) In R.S. Joint in flat iron /angle / channel / bar. (CG PHE SOR P.23 It.No. 2.25.4 ) Lowering and laying of MS pipe inside casing pipe of various Dia. Including pulling/pushing of carrier pipe. - 78 - Rate Unit (CG PHE SOR P.217 It.No. 17.9.2 ) Carrier Pipe 600 mm Dia. 8 Refilling the surplus excavated stuff to the place as directed by the Engineer-Incharge. (CG PHE SOR P.23 It.No. 2.25.4) 230 Rmt. 288 Cum. (iii) Providing and Installing Electromagnetic Bulk Flow Meters Diameter Description Electromagnetic Bulk Quantity Flow Meters Supply of Electromagnetic full bore meter complete as per specification including transportation to site, storage, safety, installation, testing, commissioning, making connections with existing pipe line, including excavation at site, cuts in the existing pipe system, dewatering and reinstating the same after completion of installation as per specification and drawings including all taxes. Accuracy of meter + 0.3% of measured value, Flange connection as per AWWA & IS, Liner: Hard Rubber, Fully welded sensor housing complying to IP 68 standard, Electrodes SS 316, Sensor housing SS 304, Cable gland 1/2" NPT, Sensor housing fully welded SS 304 housing with protective Polyurethane paint, Flow Transmitter/ Converter: Microprocessor based, modular design display 2 line back lit LCD for indication of actual flow rate, forward, reverse, sumtotalizer, Perfection category:IP65 Output : One current output (4-20 mA) one scalable pulse output with remote reading facility. 150mm (CG PHE SOR P.309 It.No. 30.5) 0 200 mm 17 250 mm 9 300 mm 11 400mm 4 500 mm 3 600 mm 2 Total Nos. D:\533577160.doc 46 - 79 - Rate ANNEXURE - G Guarantee Bond (To be used by approved schedule banks) 1. In consideration of the Corporation/Commissioner KMC (herein after called the KMC) having agreed to exempt……………………. (hereinafter called the said contractors) from the demand under the terms and conditions of an agreement dated………………… ………………………………………………. and made between………………….. …………………for ……………………………. (hereinafter called the said Agreement) of earnest money deposit for the due fulfilment by the said contractor(s) of the terms and conditions contained in the said agreement on production of a Bank Guarantee for Rs……………………….. (Rs……………………………………………………………only). We …………………………… Bank limited (hereinafter referred to as the Bank) do hereby undertake to pay to KMC an amount not exceeding Rs……………………………….. against any loss or damage caused to or suffered or would be caused to or suffered by the KMC by the reason of any breach by the said contractor(s) of any terms or conditions contained in the said agreement. 2. We ………………………………………………… Bank Limited do hereby undertake to pay the amounts due and payable under this guarantee without and demur merely on a demand from the KMC stating that the amount claimed is due by way of loss or damage caused to or suffered by the KMC by reason of any breach by said contractor (s) of any of the terms or conditions contained in the said agreement or by reason of the contractor(s) failure to perform the said agreement. Any such demand made on the Bank shall be conclusive as regards the amount due and payable by the Bank under this guarantee. However our liability under this guarantee shall be restricted to an amount not exceeding Rs…………………………………. 3. We………………………………………………….. Bank Limited further agree with the guarantee herein contained shall remain in full force and effect during the period that would be taken for the performance of the said agreement and that it shall continue to the enforceable till all due of KMC under or by virtue of said agreement have been fully paid and its claims satisfied or till……………………… department of ……………………………….. certifies that the terms of the said agreement have been fully and properly carried out by the said contractor (s) and accordingly discharges the guarantee. Unless a demand or claim under this guarantee is made on us in writing on or before the …………………………….. We shall be discharged from all liability under this guarantee thereafter. 4. We………………………………………………………. Bank Limited further agree with the KMC that the KMC shall have the fullest liberty without our consent and without effecting in any manner our obligation hereunder or vary any of the terms and conditions of the said agreement or to extend time of performance by the said contractor (s) from time to time or the postpone for any time or from time to time any of the powers exercisable by the KMC against the said contractor(s) and to forebear or in force any of the any of the terms D:\533577160.doc - 80 - and condition relating to the said agreement and we shall not be relieved from our liability by reason of any such variation of extension having granted to the said contractor (s) for any forbearance act or commission on the part of the KMC or any indulgence by the KMC of the said contractors or by any such matter or thing whatsoever which under the law relating to sureties would but for this provision have effects of so relieving us. We……………………………………………………… Bank Limited, lastly undertake not to revoke this guarantee during its currency except with the previous consent of the KMC in writing dated the……………………… day of…………………. 20 for………………. Bank Limited. SPECIAL CONDITIONS OF N.I.T (Reference Clause 8 of NIT) (1) (2) (3) (i) (a) (b) (C) (d) (ii) “Additional performance security (APS) shall be deposited by the successful bidder at the time of signing of agreement when the bid amount is seriously unbalanced i.e. less than the estimated cost by more than 10% in such an event the successful bidder will deposit the Additional performance security (APS) to the extent of difference of 90 % of the PAC and bid amount in the shape of FDR, in favor of the Executive Engineer before signing the agreement. The same shall be refunded along with the normal S.D. after completion of the work. If the contractor fails to complete the work or left the work incomplete, & the additional performance security (APS), Shall be forfeited by the department, & the agreement shall be terminated and action shall be taken in accordance with clause 3 of the agreement. In case the tendered/contractor refuses to deposit Additional performance security (APS) then his bid will be rejected by the sanctioning authority and earnest money shall be forfeited” If the tendered, whose tender has been accepted, and after signing the agreement, (i) does not start regular actual physical items of work within 25% (twenty five percent) of the time allowed for completion, or abnormally slowdown the work or (iii) abandons the work, or (iv) merely goes on applying for extension or time, the Executive Engineer shall serve a “show cause” notice with details to the contractor in this regard and if the contractor dose not reply, or if his reply is considered not satisfactory (at the sole discretion of the Executive Engineer), his earnest money and the performance security money or the Bank Guarantee in this regard shall be forfeited in favour of the KMC if the contractor has committed a similar default on earlier occasion (s) in previous three consecutive years the contractor shall be debarred from participating in any future tender of KMC for a period of 2 (two) years from the date of such order, by the authority which had registered him/her. Such orders & action shall be final binding and conclusive Detailed program Construction: Within 15 days of issue of order to star work, the contractor shall submit in the prescribed Performa a detailed construction programme month wise mentioning start and completion or each item/event involved in the due performance of the contract for contract more than 10 Crores Contractor shall also submit detailed proramme month wise for Materials procurement Their transport arrangement to work site with details of No. of truck/tippers Detailing of construction plants & equipments Cash flow/revised Cash flow The contractor shall submit in the first week of each month a statement of “target vis-à-vis actual performance” of each item/event with slippage, if any mentioning reasons of slippage and proposal for revised construction programme to complete the same in targeted date or validly extended date. Failure to submit this monthly statement for 4 (Four) months can be treated as “Fundamental Breach of Contract” and can result in invoking clause 3 of the conditions of contract. D:\533577160.doc - 81 - If Contractor Fails To Submit Bank Guarantee of 5% Amount of The Gross Bill, Then 5% Amount of Bill shall be Deducted form his Running and Final Bill Payment. However, The Constructor Can Gat Refund of Such Performance Cash Security Amount Deducted If He Submits Appropriate Bank Guarantee Valid For The Period As Stated Above or 36 (Thirty Six) Month of one Year (As The Case May Be) After Actual Completion. If require, the Executive Engineer shall ask the contractor to extend the validity period of the bank guarantee (s) for such period which be consider it proper and the contractor shall extend the validity period of such bank guarantee accordingly. If the contractor fails to extend the period accordingly, the executive engineer shall encase the B.G. before the expiry of the validity period. (i) The contractor shall have to carry out all necessary “ Rectification” of defects noticed, caused due to any reasons at his own cost within such reasonable period mentioned in such communication notice from the Executive engineer to him. (ii) Failure of the contractor to rectify the defects properly in the given period, it shall be open for the Executive Engineer to get the defect (s) rectified either departmentally or through other agency (without calling any tender/quotation) and recover the actual cost plus 15% (Fifteen Percent) of such cost from the contactor from any sum, in any form, and available with the department or can be recovered as “Arrears of Land Revenue” (iv), (v) Deleted in case form date of completion of work (one year) (iii) After two years of completion of construction, 50% (Fifty Percent) of available performance Bank Guarantee shall be returned to the contractor subject to the satisfaction of the Executive Engineer. (vi) Remaining performance Bank Guarantee as would be remaining (after recovery all cost plus 15% (Fifteen percent) shall be returned after 3 years of completion. The performance guarantee will be in addition to the normal security to be deducted as per clause 1 of agreement for the execution of contract. (4) The tendered/contractor shall give in advance authority letter (s) in favour of the Executive Engineer, authorizing him to get all bank’s fixed deposit receipts, Bank Guarantees (either normal security deposit and or for performance security) to get these bank receipts and guarantee deeds verified and got confirmed from the concerned bank. It will be only after getting such confirmation that the Executive Engineer shall pay any amount accordingly or refund the equal amount for which BG submitted has been duly verified and confirmed. (5) The contractor shall no remove minor mineral form borrow areas, quarries without prior payment of Royalty charges. KMC ……………………………….......... Name of Contractor ……………………… Date or work order …………………………………… Due date of completion Detail work programme – Original/1st Revision/2nd Revision/ …………….. Revision) Work Items Sr. Items No. Unit Months 1 2 3 4 5 6 7 1 2 3 4 5 6 Approved D:\533577160.doc Executive Engineer - 82 - Signature 8 MONTHLY TARGET Vs. ACTUAL ACHEVEMENT Cumulative Achievement of item of work for the month ending of Agt. No. …………………………………………Name of Work Length Date of W.O.……………………………… ……………………………………………………................. Sr. No. 1 Items Cumulative Work Programme As per 1St Last No. Original Revison Revision 2 3 (a) 3 (b) 3C Date of Completion………….. Cumulative Achievemtnt actual Slipage if any (Period) 4 5 Reason for slippage (Use add sheet if needed) 6 Comments of Executive Engineer if any Cash Flow for performing the contract (applicable fro works cost) Name of Division ………………………………. Name of Contractor …………………………... Period of Contract ……………………………… (A) Investment (I) Initial (E.M.) P.G. Insurance (Establish Site Office) (II) D:\533577160.doc 1st Month Value 2nd Month Advance for Procurement of Material (if any) - 83 - 3rd Month 4th Month 5th Month 6th Month (III) Advance for Procurement of labour (if any) (IV) Purchase of New Equipment (if any) (V) Other overheads staff including head office (VI) Other if any (Furnish details) (B) (I) A B C D (x) Total Investment Receipt Gross Bill Amount Deductions. S.D. Advance TDS Other recoveries if any (y) Total Receipt Net cash flow (x-y) Note :- (1) This Should co-relate to work programme/progress of work during the month. (2) Running bill will be expected to be paid within 15 days of the receipt and checking of measurement, quality and quality of items (3) Investment less net receipt for 1st 15 days and then during. (4) (Final bills is expected to be paid within 2 months of satisfactory completion work. (5) Total investment less Total Receipt (-) be shown in bracket. D:\533577160.doc - 84 - INFORMATION & INSTRUCTIONS TO THE BIDDERS FOR ONLINE ELECTRONIC GOVERNMENT PROCUREMENT SYSTEM (e-GPS) ANNEXURE-H Special Conditions & instructions for online Electronic Government Procurement System (online e-GPS) as given in the subsequent pages will over-rule the conditions stated in the tender documents, wherever relevant and applicable. 1. Registration of the Contractors/Bidders on Chhattisgarh Government e-Procurement Portal http://cgeprocurement.etenders.in: All the contractors in order to participate in the tenders floated using the Electronic Procurement System are require to be registered on http://cgeprocurement.etenders.in and get empanelled in the Portal http://uadd.cgeprocurement.etenders.in in the relevant category. Only after the concerned officer Commissioner, municipal corporation, Korba approves the empanelment of the contractor/bidder online, the contractor/bidder shall be allowed to participate in the tenders floated by the department using the electronic Procurement System. The empanelment of the contractor is also required to be renewed in the system as and when registration is renewed with the department. 2. Set-up of Machine: In order to operate on the electronic procurement system, setting of User’s machine is required. For which User has to install some utilities in his machine as per the instructions given in Help Manual for ‘Machine Setup’ (Available for download on the e-GPS portal). The copy of the same may be obtained from Wiper NexTenders. 3. Obtaining a Digital Certificate: The bids submitted online should be signed electronically with a Digital Certificate to establish the identity of the bidder bidding online. These Digital Certificates are issued by an approved certifying authority, authorized by the Controller of Certifying Authorities, Government of India. A Digital Certificate is issued upon receipt of mandatory identity proofs and verification letters attested by Gazette Officer. Only upon the receipt of the required documents, a digital certificate can be issued. The registered contractors may obtain information required for issuance of a Digital Signature Certificate from the Service Provider of procurements System of Government of Chhattisgarh: Wipro Limited in consortium with NexTenders (India) Pvt. Ltd. “Skate” B-31, Opp. Gulab Industries, Shailendra Nagar, Raipur 13 492 001 Tel. No. +91 771 320 79 96, 320 49 97, 402 21 020 Fax No. : + 91 771 402 21 023 Email: Korba@nextenders.com Important Note: Bid for a particular tender may be submitted only using the digital certificate, which was used to purchase the tender document online. In case, during the process of a particular tender, the user looses his Digital Certificate (i.e. due to virus attack, hardware problem, operating system problem etc.); he may not be able to submit the bid online. Hence, the users are advised to back up the certificate and keep the copies at safe places under proper security to be used in case of emergencies. In case of online tendering, the digital certificate issued to the authorised user of a firm and used for electronic tendering will be considered equivalent to a no-objection certificate/power of attorney to that user. The firm has to authorize a specific individual via an authorization certificate signed by all partners to use the digital certificate as per Indian IT Act 2000. Unless the certificate is revoked, it will be assumed to represent adequate authority of the user to bid on behalf of the firm for Directorate of Medical Education tenders as per Information Technology Act 2000. The digital signature of this authorized user will be binding on the firm. It shall be the responsibility of management/partners of the registered firm to inform the Certifying Authority or Sub Certifying Authority, if the authorized user changes, and apply for a fresh digital certificate and issue a fresh ‘authorization certificate’ for the new user. The same procedure holds true for the authorized users in a private/public limited company. In this case, the authorization certificate will have to be signed by the directors of the company. D:\533577160.doc - 85 - 4. Opening of an Electronic Payment account: For Submitting the bids online Contractors/ Bidders are required to make online payment using the electronic payments gateway service as mentioned in the NIT. Arrangements have been made for Contractors/Bidders to make payments online via Credit Card / Cash Cards / Internet Banking. The List of modes of electronic payments accepted on the electronic Procurement System is available online on the website. The Interested bidders can view the list of payment modes from website http://cgeprocurement.etenders.in. 5. Payment for submission of bids online: The tender documents may be downloaded online directly by eligible Contractors/Bidders. The Contractors/Bidders are required to make the payment for bid submission through online payment modes mentioned in Point No. 3 above. In online tendering, the "application form" for the issue of tender documents shall not be required. The suppliers can submit the bids by making online payment of submission fees using the service of the secure electronic payments gateway, and should print out the system generated receipt for their reference which can be produced whenever required. The secure electronic payments gateway is an online interface between Contractors/Bidders and credit card / online payment authorization networks. Submission of bids, EMD and other documents will be governed by the time schedule given under “Key Dates” on the online e-Procurement System portal for the particular tender. [Please refer to the Help Manual for viewing of New Tenders Online on the procurements Portal.] 6. Tender Download: Eligible Bidders can download the Tender Document online. 7. Submission of Bid Seal (Hash) of online bids: The online submission of bids will be preceded by submission of the "digitally signed bid seal (hash)" as stated in the tender time schedule (Key Dates) published in the NIT. The contractor cannot change any bid data after the generation of bid seal (Hash). 8. Generation of Super Hash: After the time of submission of Bid Seal (Hash) by the Contractors/Bidders has lapsed, the bid round will be closed and a "digitally signed tender Super-Hash" which will be prepared by concerned Department official. This is equivalent to sealing the tender box. 9. Submission of actual online bids: Suppliers have to submit and sign their encrypted bids (by their user PublicKey) online using their digital certificate after the generation of Super Hash within the date and time as stated in the tender schedule (Key Dates). The electronic bids of only the suppliers who have submitted their bid seals (hashes) within the stipulated time, as per the tender time schedule (Key Dates), will be accepted by the system. A supplier who does not submit his bid seal (hash) within the stipulated time will not be allowed to submit his bid. 10. Submission of Earnest Money Deposit: The supplier will also submit their Earnest Money Deposit as usual in a sealed physical "Cover - A" and the same should reach the stipulated department office as stated in the Tender Document, by post. The Supplier will also upload scanned copy of EMD instrument along with other details during online bidding. 11. Opening of Tender documents: The authority receiving the tenders or his duly authorized officer shall first open the "Envelope A" of all the contractors/bidders and check for the validity of EMD and documents submitted in the “Envelope A”, as required by Korba Municipal Corporation. In case, the requirements are incomplete, the Technical Bid of the concerned supplier received shall not be opened. The authority shall then open the tenders submitted by the suppliers online through the website. He will match the hash of each tender with the hash submitted by the contractors prior to bid submission. In the event of a mismatch, the tender in question will be rejected after a due process of verification by Korba Municipal Corporation. 12. Fill Negotiated Rates: The successful bidder may have to fill in Negotiated Rates if so required during this Process. In case of no negotiation or no change in rates successful bidders need to complete the Fill Negotiated Rates stage. 13. Key Dates: The suppliers are strictly advised to follow the tender schedule (Key dates) for their side of tasks and responsibilities to submit their bids, as the system is time and date locked. D:\533577160.doc - 86 - PQ for More Than 10 Crores. Issued by Urban Administration £ Development Department Govt. Of Chhattisgarh Nagar Palik Nigam Korba KORBA AUGMENTATION WATER SUPPLY SCHEME PART I UNDER UIDSSMT Pre Qualification Document For WORKS Name of Work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Probable Amount of Contract Rs. ................... Lac Issued by Commissioner Nagar Palik Nigam Korba Issued to: . ............................................................... . ............................................................... D:\533577160.doc - 87 - . ............................................................... Name of Work: - Probable amount of contract : Rs............... Lacs. Cost of Pre qualification and tender form: Rs. ................................. /- Only {For tenders online} Time allowed for Completion ……………………………………… Months from the reckoned d including / Excluding rainy seas (16th June to 15th October) Date of issue of Pre qualification and tender form :- Commissioner Nagar Palik Nigam Korba D:\533577160.doc - 88 - Qualification criteria 1 To qualify for award of the Contract, each tendered in its name should have in the last five years (a) Achieved in "any one financial year" a financial turnover (in all classes of civil engineering construction works) value of construction work of at least 60% (Sixty percent) the amount equal to the probable amount of contract for which bid has been invited. (b) Satisfactorily completed at least one similar work equal in value 40% (forty percent) of the Probable amount of contract as on date of submission of financial offer. OR (ii) Satisfactorily completed at least two similar works total costing equal to value 40% (forty percent) of the probable amount of contract for which the tender is invited as on date of submission of financial offer. OR (iii) Satisfactorily executing at least one similar work having received payment of value not less than 40% (forty percent) OR two similar works having received aggregate payment of value not less than 40% (forty percent) of the value of probable amount of contract as on date of submission of financial offer. OR (iv) One similar work completed & satisfactorily executing one similar work Total aggregate value in both the works shall be minimum 40%(forty percent) of the value of probable amount of contract for which tender is invited as on date of submission of financial offer. Note :- 1) The turn over shall be indexed at the compounded rate of 10% (Ten percent)for each earlier years. (ii) The value of completed work shall be updated to the value of current financial year @ compounded rate of 10% (Ten percent) per year from completion year of work, (iii) Similar work mean Pipe lines/Water treatment Plant/Building/ Over Head Tanks as the case may be. 2 (a) Each tendered must enclose. (i) Either the latest income-tax clearance certificate; (not later than 12 month old) or Certified Copies of Income Tax Returns for the last 5(Five)years together with Balance sheet, Profit and Loss Account statement duly audited by Chartered Accountant including his audit report. (ii) Other certificates as required by department (iii) An affidavit that all the information furnished with the pre qualification document is correct in all respects; and (b) Each tendered MUST submit detail information regarding (i) D:\533577160.doc a) Availability for construction Plants and machineries, Key equipment required for establishing laboratories to perform mandatory tests at the prescribed frequency owned/lease/on hire, as stated in the enclosed list - 89 - b) The contractor shall also submit a certificate from the E.E. that the plants had been established as per MORT&H specifications. In the absence of this certificate the contractor may disqualify for the work. (ii) Availability of consultancy firm/technical personals for construction supervision and quality control of the work as stated in the enclosed list 3. Tendered who meets the minimum qualification criteria will be qualified only if their available bid capacity for construction work is equal to or more than the probable amount of contract. The available bid capacity will be calculated as under: Assessed Available Bid capacity = (A*N*M - B) where, A - Maximum value of all civil engineering work executed in " any one financial year" during the last Ten year (updated to the price level at the current financial year at the compounded rate of 10% (Ten percent)a year taking into account the completed as well as work in progress. N = Number of years prescribed for completion of the works for which tender is invited (period up to 6 months to be taken as half-year and more than 6 months as one year). Any period beyond 12 months, the period actually mentioned in the N.I.T. shall be considered. M = 2.5 B = Value, of existing commitments and on-going works be completed during the period of completion of the work for which tender is invited (period up to 6 months to be taken as half-year and more than 6 months as one year). Any period beyond 12 months, the period actually mentioned in the N.I.T. shall be considered. Note: 4. (i) The statements showing the value of existing commitments and on-going works, a well as the stipulated period of completion remaining, for each of the works so listed should be countersigned by the Engineer-in-charge, not below the rank of at Executive Engineer or equivalent. Even though the tendered meet the above qualifying criteria, they are subject to be disqualified if they have: Made misleading, incorrect or false representations in the forms, statements affidavits and attachments submitted in proof of the qualification requirements. And/or (ii) Record of poor performance such as abandoning the works, not properly completing the contract, unsatisfactory quality of work, inordinate delays in completion, chair and litigation history, or financial failures etc in any department of Govt. of Chhattisgarh or the state Govt. organization/services/corporations/local body etc.(by whatever names these are called) within State territory of Chhattisgarh. And/or (i) Participated in the previous bidding for the same work and had quoted unreasonable high or low bid prices and could not furnish rational justification for it to the D:\533577160.doc - 90 - ANNEXURE-1 Qualification Information 1.1 Constitution or legal Biddcr/attach copy] status of Place of registration of Firm/ Company (in case of other than individuals) Principal place of business: Name of Power of attorney holder of signatory of Bid (bidder)/«//ac7? copy] 1.2 Total annual volume of civil engineering Financia (Rs. in crores) construction work executed and l Year payments received each year in the "Civil engineering Add for immediate five years preceding construction work" Turn over indexing the year in which tenders are invited. in the year (Attach certificate from Chartered Accountant)indexed @ 10% (ten percent) compounded per year Total Note : 1.1 Preparatory firm, partnership firm with the certificate of registration by register/artocle and Memorandum of Association with Certificate of Incorporation. 1.2 Mention and highlights the year, which the tendered considers for evaluation for the Committee D:\533577160.doc - 91 - ANNEXURE - 2 Information regarding minimum one similar work (i) One Work completed as similar work during last ten years (ii) Or being executing one such similar work Sno Project Name of Employer 1 2 3 D:\533577160.doc Value of Contract Contract No. Date of Issue of Work Order Stipulated Date of Completion Actual Date Of Completion Value of Work Done 4 5 6 7 8 9 - 92 - Remarks Explaining reasons for Delay, if any and the amount of Deductions due to delay Also mention if any Claim or dispute is Pending in any forum. 10 Note :(i) Attach certificates from the Engineer in change not believe the rank of Examiner or equivalent. (ii) Tendered may attach certified copies of work order and completion certificate issued by Engineer in charge not below the rank of Executive Engineer ANNEXURE - 3 Work Performed on all classes of Civil Engineering Construction Works over the last ten years D:\533577160.doc - 93 - Sno Project Name Name of Emolo yer Descript Ion of Work Value of Contra ct Conteact No. 1 2 3 4 5 6 Date Of Issue Work Order Stipulated Date of Completion Actual Date Of Completion 7 8 9 Year wise value of work done as per certificate of employer Rs. In Lacs 10 11 12 13 14 15 Remarks explaining Reasons for Delay if Any and the amount Of deductions due to Delay also mention if Any claim or dispute Is pending in any Forum. 16 Note :(iii) Attach certificates from the Engineer in change not belie the rank of Examiner or equivalent. (iv) Tendered may attach certified copies of work order and completion certificate issued by Engineer in charge not below the rank of Executive Engineer D:\533577160.doc - 94 - ANNEXURE - 4 Existing commitments and on going all classes of civil engineering construction works. Sn o Project Name Descri pt ion of Work Contr act No & Year Name& Adders Of the Employer Value of Contract (Rs. Lakhs.) Date of Issue of Work Order Stipulate d Date of Completi on Stipulated period of Completion in Months Anticipate A date of Completion Value of Work done Up to date Of issue Of N.I.T (Rs. Lakhs)** Probable value of Works Remaining To be Completion (Rs. Lakhs) ** Anticipate Months Required Completion Of balance works Value of Claims Or Dispute If Any pending 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Note – 1. ** Enclose certificates from Engineer (s) in charge (Not below the rank of Executive Engineer or equivalent) for value of work remaining to be completed, value of work done, anticipated date of completion. 2. Tendered may attach certified copies of work order issued by Engineer in charge not below the rank of Executive Engineer D:\533577160.doc - 95 - ANNEXURE - 5 Availability of Major items of Contractor's Equipment proposed for carrying out the Works. List all information requested below. Item of Total number Description n, Condition Nos. If these are in No. of equipments equipment available make, and (new, good, (i)Owned, (ii) use in some proposed to be age (Years), poor) and leased, or (iii) work, utilized in this and capacity number to be mention the work (Out of total available purchased details. Nos.) 1 D:\533577160.doc 2 3 4 - 96 - 5 6 7 ANNEXURE – 6 Qualifications of consultants /each technical personnel proposed for the Contract. Position 1 Name 2 Qualify action 3 Date from which they are working in the bidders organization 4 Years of experience Remark Road Works Building Works Bridge works Others 5(a) 5(b) 5(c) 5(d) 6 Note : I. If any personal is proposed to be engaged, furnish details here under:- (if necessary use separate sheet for each -for C. V.) (Enclose certificates) II. If any technical persons are to be changed during the construction periods, than it can be changed with prior intimation to the Engineer in charge. D:\533577160.doc - 97 - ANNEXURE – 7 Financial reports for the immediate previous five years: balance sheets, profit and loss statements, audited auditors’ reports, etc., list below and attach copies. Year 1 D:\533577160.doc Income Tax Clearance Certificate (optional) Balance Sheet Profit & loss statement 2 3 4 - 98 - Auditors Reserve brought forward in any Net credit Balance if any [for debit show (-)] 5 6 7 , Report Other information if the bidder wishes to submit 8 ANNEXURE – 8 Information on current claims, arbitration, litigation in which the Bidder is involved. SI. no. Name of Other Agt. No. date party(s) year and Deptt. Brief of cause of claims, arbitration /dispute (give reference of contract details ) Can use separate sheets for each agreements if necessary. D:\533577160.doc - 99 - Where Litigation pending (in the department/Court/a arbitration) (mention Deptt./Court /Arbitration) Amount Involved/ claimed ANNEXURE – 9 List of key plant & Equipment to be deployed on Contract Work to be filled by the Contractors SI. 1 Type of Equipment From Rs. 3 Crores to Rs.10 Crores From Rs. 10 Crores to Rs.30 Crores From Rs. 30 Crores to Rs.50 Crores 2 3 4 5 6 Total D:\533577160.doc Contract Package Size Maximum age as on 1.04.14 (years) - 100 - From Rs Rs.50 Crores , above 7 ANNEXURE – 10 List of key plant & Equipment to be deployed on Contract Work Sr. No. Type of Equipment Contract Package Size Maximum age as on From Rs. 3 From Rs. 10 From Rs. Fron Rs..5 1.04.12 Crores to Crores to 30Crores to (years) Rs.10 Crores Rs.30 Crores Rs.50 Crores Crores abov' 1 1 2 3 4 5 6 7 8 9 10 11 12 Total Note: - The list & other Details of the equipment and plants as mentioned above are tentative. S.E. of the Nagar Nigam/Joint Director Office/ Directorate can modified the above list of the plant and equipment as per their requirements. D:\533577160.doc - 101 - ANNEXURE – 11 List of Technical person to be deployed on Contract work 1 2 3 4 SI. Personnel Qualification 1 2 3 Project Manager Site Engineer Plant Engineer Quantity Surveyor 5 Soil & Material Engineer 6 Survey Engineer Contract Package Size From Rs. 3 From Rs. 1 From Rs. 31 Crores 1 Crores to Crores to toRs.10 Rs.30 Rs.50 Crores Crores Crores 4 B.E. Civil+15years Exp. (5 years as manager) From Rs. Rs.51 Crores & above 5 6 7 1 1 1 B.E. Civil+lOyears Exp. (5 years in roads construction 1 1 2 4 B.E. Mech.+lO Years Exp. or Dip. Mech+15 years Exp. 1 1 1 2 1 1 1 2 1 1 1 2 1 1 1 2 B.E. Civil+7 Years Exp. or Dip. Civil+ 10 Years Exp. B.E. Civil +10 years Exp. B.E. Civil +5 years Exp. or Dip. Civil+8 years Exp. Total Note' - The list of (he Technical persons Qualification & Experience as mentioned above are tentative. S.E. of the Nagar Nigam/Joint Director Office/ Directorate can modified the above list as per their requirements. D:\533577160.doc - 102 - ANNEXURE – 12 CONTACT PERSONS SI Name of Executive Engineer No. of the Division 1 D:\533577160.doc 2 Divisional STD Code Phone No. Office/ residence Name District 3 4 5 6 - 103 - ANNEXURE- 13 Affidavit I.................................... S/o.................................................................................................. A.ged........ .years.........resident....................................... ..of................................................... ..................................(address.................................................................................................................. ...................................................................................................................................) (For and on behalf of......................................................................................), do here by and herewith solemnly affirm / state on oath that: 1. All documents and Information’s furnished are correct in all respects to the best of my knowledge and belief 2. I have not suppressed or omitted any information as is required. 3. I am/ We are neither black listed nor debarred by Govt. of India / Other State Govt. Departments/ Chhattisgarh State Govt. Departments/Urban Local Body. 4. I hereby authorize the Nagar Nigam/Nagar Palika/Nagar panchayat Officials to get all the documents verified from appropriate source(s). Deponent (…………………………………….……….) Authorized signatory / for and on behalf of ………………… (affix seal) Verification I.................................... S/o................................................................. do here by affirm that the contents stated in Para 1 to 4 above are true to the best of my knowledge and believe and are based on my / our record. Verified that this ......................... date of ....................... 200... at (Place).......................... Deponent Seal of attestation by a Public Notary with date Authorized signature / for and on behalf of................. (Affix seal) NIT Clear water pumping & gravity main 104