The Open University of Sri Lanka P.G. Diploma in Construction Management Programme – Level 7 CEX 7101 – Planning and Control in the Construction Industry Assignment 2- Academic year 2016 Submit answers to: Course Coordinator CEX 7101, Department of Civil Engineering, The Open University of Sri Lanka, Nawala, Nugegoda. ______________________________________________________________________ Date of submission as indicated in the Activity Schedule or amended thereafter. Answer all questions with assumptions stated clearly. Refer your hand out on General Information. Type written answers are expected. Q1. An oil refinery is planning the installation of a gas turbine based combined heat and power system. The gas turbine will be housed in a new building next to a furnace which uses the exhaust gas for pre-heating its air supply. The layout and activities are shown below. Turbine House Ducting Furnace Fuel Tank Table 1 No 1 2 3 4 5 6 7 8 9 10 11 12 13 Task Finalise design Procure generating set Procure switch gear and control system Manufacture ducting Procure fuel tank Build turbine house Erect support structure for ducting Erect support structure for fuel tank Install ducting Install fuel tank Install generator Install switch gear and control system Commission 1 Duration (weeks) 6 20 24 6 2 8 3 3 1 1 2 2 2 Design work can start immediately. The following conditions apply with regard to precedence requirements. The design work can start immediately and must be complete before procurement tasks can start The building work must be completed before the generator and switchgear can be installed and the support structures started The generator must be installed before the ducting The respective support structures must be installed before the fuel tank and ducting can be installed Commissioning takes place when all other tasks are completed (a) Draw a activity-on-node diagram for the project and indicate the earliest start times, latest start times, earliest finish times and latest finish times for each activity. (b) Calculate the total floats for each activity and comment on the events that have longest float (c)Identify the critical path and state the minimum duration for the project. (Total 40 marks) Q2. (a) Illustrate the usefulness of deviating from the conventional presentation of bar charts to more dynamic and innovative forms. (b) A set of activities for a project are given below. The man power requirement per day of activity is also given. Table 2 Activity A B C D E F G Duration (days) 2 4 8 5 7 2 3 Preceding activity A A B,C D E,F Labour requirement per day 4 3 11 7 3 3 6 (i) Draw the complete activity-on-arrow network diagram indicating the activity times and the critical path. (ii) Prepare bar charts based on early start time and late start time. (iii)Perform resource smoothening and draw the histogram for Labour after leveling (Total 35 marks) 2 Q3. Write short notes on all five of the following: (a) Citing an example explain the use of ‘Work breakdown structures & Work packages’ in the management of a small construction project (b) State the advantages of using sub-nets in network construction (c) Explain how you can exercise Progress Control on a project where the work programme is based on the critical path method (d) State the factors which affect the choice of a ‘planning technique’ for a construction project giving reasons (e) There are several dimensions to the problem of ‘underemployment’. State them in brief. (5 marks each = 25 marks) 3