Design of Hardened Containment Vent Systems for Decay Heat Removal and Severe Accident Conditions by Matthew James Fallacara An Engineering Project Submitted to the Graduate Faculty of Rensselaer Polytechnic Institute in Partial Fulfillment of the Requirements for the degree of MASTER OF ENGINEERING IN MECHANICAL ENGINEERING Approved: _________________________________________ Ernesto Gutierrez-Miravete, Project Advisor Rensselaer Polytechnic Institute Hartford, Connecticut August, 2013 i CONTENTS CONTENTS ...................................................................................................................... ii LIST OF TABLES ............................................................................................................ iv LIST OF FIGURES ........................................................................................................... v LIST OF ACRONYMS .................................................................................................... vi ACKNOWLEDGMENT ................................................................................................. vii ABSTRACT ................................................................................................................... viii 1. Introduction and Background ...................................................................................... 1 1.1 Review of the Events at Fukushima Dai-ichi ..................................................... 1 1.2 Boiling Water Reactors ...................................................................................... 2 1.3 Current HCVS Licensing Requirements ............................................................ 6 1.4 Potential Future HCVS and FCVS Licensing Requirements ............................. 9 1.5 HCVS/FCVS Installed in Foreign Countries ..................................................... 9 2. Theory and Methodology .......................................................................................... 11 2.1 HCVS Design Requirements for EA-13-109 ................................................... 11 2.2 HCVS Wetwell Sizing for Decay Heat Steam/Energy Release ....................... 14 2.2.1 Mass Flow Rate Requirements ............................................................ 17 2.2.2 Required HCVS Pipe Sizing ................................................................ 19 2.3 Severe Accident Conditions in Containment ................................................... 21 2.4 Drywell Venting ............................................................................................... 27 2.5 Effects of Filtering ........................................................................................... 28 2.5.1 Decontamination Factors for Suppression Pools ................................. 29 2.5.2 Engineered Filter Designs .................................................................... 30 3. Results and Discussion .............................................................................................. 33 3.1 Design of HCVS for Decay Heat Removal and Severe Accidents .................. 33 3.1.1 Non-Severe Accident Calculations ...................................................... 35 3.1.2 Severe Accident Calculations .............................................................. 37 ii 3.2 Discussion of Filter Benefits ............................................................................ 41 3.3 Additional Considerations for Severe Accidents ............................................. 43 4. Conclusion ................................................................................................................. 46 5. References.................................................................................................................. 47 6. Appendix.................................................................................................................... 50 6.1 Mass Flow Rate Requirements Spreadsheet – Non-Severe Accidents ............ 50 6.2 Required HCVS Pipe Sizing Calculation Spreadsheet-Non-Severe Accidents 52 6.3 Mass Flow Rate Requirements Spreadsheet – Severe Accidents .................... 54 6.4 Required HCVS Pipe Sizing Calculation Spreadsheet – Severe Accidents .... 55 6.5 Properties of Hydrogen Vapor – Excerpted from [26] .................................... 57 6.6 Properties of Hydrogen – Interpolation Table ................................................. 58 6.7 Specific Volume Chart - Hydrogen.................................................................. 59 6.8 Enthalpy Chart - Hydrogen .............................................................................. 60 iii LIST OF TABLES Table 1: Decay Heat Power Following Shutdown [4] ..................................................... 15 Table 2: Hydrogen Flammability Limits [17] ................................................................. 24 Table 3: Mass Flow Rate Requirements .......................................................................... 35 iv LIST OF FIGURES Figure 1: GE Mark I Containment, Modified from [3] ..................................................... 2 Figure 2: Simplified Diagram of a BWR [11] ................................................................... 3 Figure 3: GE Mark II Containment, Modified from [2] .................................................... 5 Figure 4: Mark I Containment with Wetwell and Drywell HCVS [8] ............................ 16 Figure 5: Volume % Hydrogen vs. % Metal-Water Reaction Following a LOCA [17] . 26 Figure 6: IMI Nuclear (CCI) Filter Technology [2 - Enclosure 4] .................................. 31 Figure 7: Simplified HCVS/FCVS Design [2 - Enclosure 4] .......................................... 33 Figure 8: Suppression Pool Bypass for Mark II [19] ....................................................... 44 v LIST OF ACRONYMS AC – Alternating Current BWR – Boiling Water Reactor BWROG – BWR Owners’ Group CNS – Cooper Nuclear Station CS – Core Spray DC – Direct Current DF – Decontamination Factor ECCS – Emergency Core Cooling Systems EDG – Emergency Diesel Generator EPRI – Electric Power Research Institute EPU – Extended Power Uprate FCVS – Filtered Containment Vent System GE – General Electric GL – Generic Letter HCVS – Hardened Containment Vent System HPCI – High Pressure Coolant Injection IPE – Individual Plant Examination ISG – Interim Staff Guidance LOCA – Loss of Coolant Accident LPCI – Low Pressure Coolant Injection LWL – Low Water Level MWt – Megawatts Thermal NRC – Nuclear Regulatory Commission PCPL – Primary Containment Pressure Limit PR – Pressure Ratio PWR – Pressurized Water Reactors RCIC – Reactor Core Isolation Cooling RHR – Residual Heat Removal SBO – Station Blackout SRV – Safety/Relief Valve TMI-2 – Three Mile Island Unit 2 Nuclear Plant vi ACKNOWLEDGMENT I would like to thank Dr. Ernesto Gutierrez-Miravete for his guidance and help in completing this project and the Rensselaer professors and staff for assisting me complete this degree. I would also like to thank Zachry Nuclear Engineering, Inc. for their support and financial assistance in helping me obtain my Master of Engineering. In addition, I would like to thank Tom Driscoll for his willingness to spend a weekend reading and commenting on this paper. Finally, I would like to thank Andie and my family for their assistance and encouragement. vii ABSTRACT Hardened Containment Vent Systems (HCVS) for Boiling Water Reactor (BWR) Mark I and II containments are designed and sized to prevent potential containment failure due to overpressurization during accident conditions. This paper calculates the energy from both decay heat following reactor shutdown and zirconium/steam reactions in terms of a mass flow rate for steam and gas at the containment design pressure limit. In addition, the allowable mass flow rates for different sized piping systems with a range of total resistance coefficients are calculated. This paper then compares the results of the two different mass flow rate calculations and determines required HCVS design sizing. HCVS for both wetwell and drywell venting conditions are evaluated. Finally, this paper provides discussion on the use of wet and dry filters in conjunction with wetwell venting through suppression pools. viii 1. Introduction and Background 1.1 Review of the Events at Fukushima Dai-ichi On March 11, 2011, a magnitude 9.0 earthquake struck off the coast of Japan. This earthquake resulted in a tsunami, approximately 45 feet tall, striking the Japanese coast approximately 40 minutes following the earthquake. The earthquake and subsequent tsunami caused extensive damage across northeastern Japan, including to the Fukushima Dai-ichi nuclear power plant. At the time of the earthquake, Fukushima Nuclear Units 1, 2, and 3 were in operation and Units 4, 5, and 6 were shutdown for routine refueling and maintenance outages. Following the earthquake, the operating units automatically shut down and offsite power was lost for all units. The emergency diesel generators (EDG) at all of the units started, as designed, to provide alternating current (AC) power to critical systems to cool and shutdown the cores. However, the tsunami damaged the EDGs at Units 1-5 such that all AC power was lost, and the units entered a condition known as Station Blackout (SBO). Note that one of the EDGs for Unit 6 was still operational following the tsunami. In addition to the loss of AC power, direct current (DC) power for all of the units was lost early on following the earthquake/tsunami [1]. Due to the loss of all power, the cores and containments at Units 1, 2, and 3 could not be cooled. This led to the rise of pressure and temperature inside the primary containment, which includes the drywell, wetwell, and interconnecting vent piping, for the applicable units (refer to Figure 1). These units were equipped with hardened containment vents from the wetwell, which were designed to open and relieve high pressure/temperature in containment to prevent containment failure. Operators at Units 1, 2, and 3 considered operating each unit’s hardened containment vent; however, the systems were not able to be operated remotely, due to the loss of all power, or manually, due to temperatures and radioactivity levels near the systems. This lead to the pressure and temperature inside the three units’ containments exceeding their design limits, which lead to core damage, high radiation levels, hydrogen production, and containment failure. The containment failure allowed for the uncontrolled release of radiation to the environment. In addition, containment failure led to the release of hydrogen to other 1 buildings, where it was able to create flammable mixtures and cause detonations and additional damage to the units [1]. Figure 1: GE Mark I Containment, Modified from [3] 1.2 Boiling Water Reactors There are two basic types of nuclear reactors that are utilized in the United States to produce electricity: BWRs and Pressurized Water Reactors (PWR). This paper will focus only on BWRs; see the NRC website for information on PWRs [11]. Figure 2 below shows a simplified BWR. In a BWR, the reactor vessel houses the fuel rods, which is located inside of a structure called containment. The fuel rods produce a 2 substantial amount of power in the form of heat through a process known as nuclear fission. Fission is the process of splitting atoms. The fuel rods consist of pellets contained in metal tubes, which consist of an approximate mix of 3.5% Uranium-235 and 96.5% Uranium-238. Uranium-235 is considered a fissile material, in that it is capable of sustaining a chain reaction. Neutrons are utilized to split or fission a Uranium-235 atom, and in the process, additional neutrons are released in conjunction with the daughter products of the atom and heat/energy. These neutrons then find other Urainum-235 atoms and continue the fission process, which is self-sustaining [5]. The reactor vessel for a BWR is filled with a water-steam mixture. Water (also called coolant) enters the reactor vessel and is directed to the bottom of the fuel rods, or reactor core. The coolant flows up through the reactor core and is heated to form steam (thereby “cooling” the core). The steam exits the top of the reactor through main steam piping and flows out of containment and into a turbine. The turbine converts the thermal energy of the steam into mechanical energy, through the spinning of the turbine blades. The turbine then turns the electrical generator and creates electricity. The steam that has passed through the turbine is condensed back into water in the condenser, and finally is pumped back into the reactor [5]. Figure 2: Simplified Diagram of a BWR [11] 3 In a nuclear power plant, containment is extremely important for protecting the health and safety of the public, since it provides the last barrier against the uncontrolled release of radiation. For BWRs, containment has three functions: 1) condense steam and contain fission products released during a loss of coolant accident (LOCA) so that the radiation release rates do not exceed the government limits, 2) provide a heat sink for certain safety related equipment, and 3) provide a source of water for cooling systems [15]. The major components of BWR primary containment are the drywell, suppression pool/wetwell, and the interconnecting vent pipe system (see Figure 1). Secondary containment consists of the reactor building located around primary containment; however, it does not have the same functions as primary containment. This paper refers to primary containment as containment and secondary containment as the reactor building. The drywell houses the reactor vessel, piping, recirculation pumps and other equipment. Its purpose is to contain steam released during a LOCA and direct it to the wetwell, along with preventing any radioactive material from leaking out. The wetwell consists of a free volume that is approximately half-filled with water and located lower than the drywell. In a Mark I containment, the wetwell (also called the torus) is toroidal or donut shaped, with the bottom of the drywell located above the center. In a Mark II containment, the wetwell is cylindrical, located directly below the drywell (see Figure 3 below). The wetwell’s purpose is to condense steam from a LOCA, along with preventing any radioactive material from leaking out. The interconnecting vent system provides the path that connects the drywell and the wetwell. This allows for steam and water to pass to the suppression pool for condensing and allows non-condensable gases to be released to the wetwell gas space. In a Mark I, eight large vent pipes connect the drywell and wetwell. Inside the wetwell, the pipes exhaust into a vent header. This header extends circumferentially around the torus. Downcomer pipes extend from the bottom of this header into the pool. In a Mark II containment, downcomer pipes connect the drywell and wetwell [15]. In addition, there is piping that branches off the main steam piping in containment and is routed to the wetwell. For conditions of high pressures in the reactor vessel, the safety relief valves (SRV) in this branch piping will open and allow steam to pass directly to the wetwell and suppression pool for pressure relief. 4 Figure 3: GE Mark II Containment, Modified from [2] BWRs have many safety systems that are utilized to remove heat either when the reactor is shutdown or during accident conditions. During normal plant operation, heat is removed from the reactor by the generation of steam, which exits the reactor vessel, and is utilized to create electricity. When the reactor is shutdown, the fission process stops; however, the fuel along with the metal in the reactor vessel is still extremely hot. Therefore, the residual heat removal (RHR) system is utilized to remove this heat, called decay heat. The water in the reactor vessel is circulated through RHR heat exchangers, which cool the water. The reactor core isolation cooling (RCIC) system provides makeup water to the reactor vessel for core cooling during abnormal or accident 5 conditions, when the main steam piping is isolated or when the normal supply of water to the reactor vessel is lost. Water, from both dedicated tanks and the suppression pool, is available to be pumped into the reactor vessel from RCIC. Turbine driven pumps are utilized to pump the water into the reactor vessel and the pumps are powered by steam supplied from the main steam lines. This steam exhausts to the wetwell. Finally, the emergency core cooling systems (ECCS) provide core cooling under LOCA conditions. There are multiple systems that are part of the ECCS: high pressure coolant injection (HPCI), low pressure coolant injection (LPCI), and core spray (CS). HPCI supplies makeup water to the reactor vessel under small and intermediate sized breaks or LOCAs, where the pressure in the reactor vessel remains high. Similar to RCIC, HPCI utilizes turbine driven pumps. LPCI utilizes many of the same components as RHR and provides cooling water from the suppression pool to the reactor vessel under large break LOCAs where the pressure in the reactor vessel quickly decreases. In addition to injection into the reactor vessel, LPCI provides spray into containment (both drywell and wetwell sections), which reduces pressure and temperature inside containment. CS pumps water from the suppression pool and sprays it onto the top of the reactor core to cool the fuel [5]. All six of the Fukushima reactors are BWRs, and here in the United States, approximately one-third of all operating reactors are BWRs. Fukushima Dai-ichi Units 1, 2, 3, 4, and 5 use the General Electric (GE) Mark I containment design, which is the same design as 23 of the nuclear power plants in the United States. This design has the smallest containment volume of all operating plants in the United States. In addition, Fukushima Unit 6, along with eight of the plants in the U.S., is a GE Mark II containment design, which is slightly larger in containment volume than the Mark I design. 1.3 Current HCVS Licensing Requirements Following the accident at the Three Mile Island Unit 2 Nuclear plant (TMI-2) in 1979 in Pennsylvania, the NRC and the nuclear industry evaluated many changes to nuclear plants across the country. One topic that was evaluated was how to reduce the vulnerability of BWR Mark I containments to severe accident challenges (i.e., accidents 6 with core damage). Many of the areas that were investigated were allowed to be evaluated by the individual plants under the Individual Plant Examination (IPE) program; however, one area that the NRC felt should be required by all Mark I units was the installation of hardened wetwell vents. The NRC only singled out Mark I nuclear plants for installation of hardened containment vent because they have the smallest containment free volume. The free volume is the space that would be pressurized during a LOCA or severe accident. The average containment free volume for a Mark I reactor is between 250,000 and 300,000 ft3 [2 – Enclosure 2]. A Mark II design has an average containment free volume slightly larger than a Mark I (up to 25%) [16]. However, all of the other types of reactors operated in the United States have containment free volumes that are greater than 1,000,000 ft3. The BWR Mark III reactor averages a containment free volume of approximately 1,500,000 ft3, and the large dry PWR containments (which is a majority of containments in the United States), have containment free volumes of approximately 2,000,000 ft3 [2 – Enclosure 2]). The type of reactor does not determine the power level of the reactor. BWR Mark I power levels range from some of the smallest (slightly less than 2000 MWt) to some of the largest (3500 to 4000 MWt). Therefore, since the power levels are comparable between the different reactor types, an accident at a Mark I reactor could pressurize containment quicker and at a higher level than the other reactor types, which could create a greater chance of containment failure due to overpressurization. Although not issued as an Order, the NRC prepared Generic Letter (GL) 89-16 [6], which provided instructions along with an example of an already installed hardened wetwell vent to all U.S. nuclear plants with Mark I containments. The major reason for the request for installing a hardened wetwell vent was to avoid exceeding the primary containment pressure limit (PCPL) during severe accidents. Prior to GL 89-16, all of the plants had procedures that instructed them to vent containment if the PCPL limit was to be reached; however, it would be through non-hardened/duct vents that would not be able to handle the high pressures, potentially fail, and cause an uncontrolled release of radiation. Following the issuance of this GL, all facilities with Mark I containments installed a hardened wetwell vent. The NRC found all of the installed designs to be acceptable and did not issue an Order with detailed design requirements. The NRC did 7 not request that owners with Mark II containments provide feedback to GL 89-16, nor did they recommend installation of hardened wetwell vents due to their larger volume containments [6]. The NRC only requested that owners evaluate the use of hardened vents as part of their IPE program. As part of this program, three of the eight Mark II reactors installed a hardened vent [16]. As evaluated following the events at Fukushima, the installed hardened vents could have been quite beneficial in mitigating the consequences of the event if the vents were able to be operated. The NRC issued Order EA-12-050 [1] in March of 2012 along with an Interim Staff Guidance (ISG) on the Order (JLD-ISG-2012-02 [7]) in August of 2012 requiring all facilities with Mark I and Mark II containments in the United States to install new HCVS or justify the installation of their existing hardened vents, to meet the new design requirements. The purpose of these design requirements is to allow for the removal of decay heat, preventing core damage, and maintaining control of containment pressure following an event that causes a loss of heat removal systems, such as SBO. Following the issuance of EA-12-050, the NRC continued to evaluate HCVS and how to maintain containment integrity if the vents are required to be used during severe accidents (i.e., accidents with damage to the core). SECY-12-0157 [2] was issued by the NRC Staff, which evaluated additional requirements for venting. The options listed for consideration were as follows: 1) maintain status quo as documented in EA-12-050 and not issue any additional requirements, 2) require HCVS be capable of operating under severe accident conditions, 3) install engineered filters as part of HCVS, and/or 4) develop severe accident confinement strategies (i.e., venting in conjunction with the use of other heat removal systems such as RCIC or ECCS). The five NRC Commissioners determined that Option 2 would be a requirement at the current time and additional options would require further evaluation (see Section 1.4) [28]. Order EA-13-109 was issued in June of 2013 and superseded EA-12-050. All of the original requirements from EA-12-050 are included in EA-13-109 along with additional requirements to ensure that venting functions are available during severe accident scenarios. A severe accident is classified as an accident involving extensive core damage, including accidents involving a breach of the reactor core by the molten core debris. During these accidents, expected 8 conditions in containment include elevated pressures, temperatures, radiation levels, and combustible gas concentrations (including hydrogen). 1.4 Potential Future HCVS and FCVS Licensing Requirements As discussed above, Option 3 (engineered filters) and Option 4 (confinement strategies) from SECY-12-0157 are not required to be addressed at the current time by BWR Mark I and II nuclear plants. The major difference between the existing requirements in EA-13-109 and Option 3 from SECY-12-0157 is the installation of an engineered filter that is a capable of reducing the release of radioactive materials passing through the HCVS by certain standards. This is called a filtered containment vent system or FCVS. Different types of radioactive releases, mainly aerosols and iodine, would be required to be reduced by certain decontamination factors (DF). A number of companies, including Areva and Westinghouse, have filtering systems that would be capable of being installed to meet additional requirements issued by the NRC. Option 4 (confinement strategies) is different from the rest of the options since it would involve establishing technical acceptance criteria and not just installation of new equipment. Options 2 and 3 would have defined attributes (venting capability to not exceed maximum containment pressure and DF). Confinement strategies involve extensive interactions with all stakeholders (plants) and different strategies would most likely be employed by different plants depending on their best solution. This solution involves utilizing different heat removal systems (RCIC and ECCS) at different times following an accident and certain actions may be different for different types of accidents. Since very few plants could be considered the same, and based on the availability of public information on specific plants, this option is only discussed in this paper in general terms and is not evaluated. 1.5 HCVS/FCVS Installed in Foreign Countries As part of the preparation of SECY-12-0157, the NRC researched containment venting strategies for nuclear plants in other countries. It was found that many countries in Europe, including Sweden, Finland, Germany, France, Switzerland, and the Netherlands, installed FCVS following the accidents at TMI-2 and Chernobyl (in 1986 9 in Ukraine). These countries determined that based on operating experience from severe core damage, FCVS were necessary to increase defense in depth in regards to minimizing accident fission product releases, along with the management of the production of hydrogen. These countries deemed the installation of engineered filters as essential safety enhancements. The NRC and the nuclear industry in the U.S. studied filtered vents, but they determined the installation of filtered vents were not considered essential safety enhancements; therefore, not required to be installed. Vents installed following issuance of GL 89-16 were intended to help prevent core damage from occurring and not mitigating core damage if it occurred as part of a severe accident. Following Fukushima, many countries have determined that FCVS will be required to be installed in order to mitigate the events of severe accidents and limit the potential release of radiation following a severe accident. These countries include Japan, Taiwan, Belgium, Romania, South Korea, and Canada. Note that one Canadian plant already installed a FCVS in 2007 prior to Fukushima. Other countries, including the United States, Mexico, China and others are still evaluating what types of venting strategies will be required to be installed, including potential for FCVS. As part of the evaluation process, the NRC has performed cost-benefit analyses based on the cost of filters, probability for a severe accident, and cleanup cost [2 – Enclosure 2]. Many foreign countries did not perform cost-benefit analyses on FCVS on which strategies to implement. 10 2. Theory and Methodology 2.1 HCVS Design Requirements for EA-13-109 The current licensing requirements for HCVS for BWR Mark I and II nuclear plants in the United States are listed in Order EA-13-109. As discussed above, Order EA-12-050 was originally issued and required plants to install HCVS to prevent core damage when heat removal capability was lost due to conditions such as extended loss of electric power. However, this Order was superseded by EA-13-109 so that the HCVS will not only function during these conditions, but also during severe accidents (i.e., when core damage has occurred). All of the original requirements listed in EA-12-050 are reflected in EA-13-109, in addition to the new requirements for severe accidents. This paper will first examine the requirements of the design of HCVS. Mark I and II reactors are obligated to comply with the listed requirements in Attachment 2 to EA-13-109. These requirements are broken down into two phases. In Phase 1, licensees are required to install a HCVS from the wetwell that can provide venting capability during severe accidents. In Phase 2, licensees are required to either install a HCVS to provide the same venting capabilities during severe accident conditions from the drywell or develop and implement a strategy that makes it unlikely that a licensee would need to vent from the drywell during a severe accident. The first grouping of functional requirements for Phase 1 for HCVS (Section 1.1 of Attachment 2 to EA-13-109) discuss the operational requirements of the new HCVS. These focus on the actions of nuclear plant operators. The system is required to be accessible and functional for conditions during times when there is a severe accident and potential loss of electric power. If a nuclear plant operator is required to perform certain actions in order to make the system function, minimal actions should be necessary to lower the risk of failure. Operators need to have the ability to operate the system during these accident conditions. Venting from a remote location, such as the Control Room, is preferable and allows an Operator to be more responsive, since this is where Operators perform the majority of actions for operating nuclear plants. If the valves will be operated manually, the potential environmental conditions, including radiation and temperature, need to be evaluated to ensure that Operators can access the areas. At 11 Fukushima, the operators could not utilize their hardened containment vents. After the plants lost all AC and DC power, alternate sources of power were not available to operate the valves remotely in the system. In addition, they could not operate the valves manually due to radiation and temperature [1]. The second grouping of functional requirements for Phase 1 (Section 1.2 of Attachment 2 to EA-13-109) focus on the design features of the HCVS. The first major design feature is that HCVS shall have the capacity to vent steam/energy equivalent to one percent of the licensed thermal power. This vent must be able to restore and maintain containment pressure below the design pressure limit of containment. The discharge of the vent needs to be such that it is released above main plant structures and minimizes any potential cross flow of vented fluids for sites that have multiple units. These two objectives are in place so that venting does not cause adverse effects elsewhere onsite. Venting above the main plant structures will limit the potential impact on personnel at the site. At Fukushima, there was an explosion in Unit 4 and hydrogen leaking from Unit 3 to Unit 4 is believed to have caused this explosion [7]. The HCVS shall be powered so that it can be operated from a remote location and it shall also have the ability to be operated manually. As discussed above for Operator actions, it is much preferred if the HCVS can be operated from a remote location, since it will keep the Operators out of more hazardous conditions. However, having two means of operation will provide defense in depth so that if for some reason the valve cannot be remotely operated, another option is available. The manual operator may require shielding to be installed so personnel can access the required locations. Also similar to above, instrumentation shall be installed such that not only is the status of the vent system known (opened or closed), but also potential radiation that is released from the vent is known. In addition, the system shall be designed such that is can withstand the effects of severe accidents. The system shall be able to cope with high temperature, pressure, and radiation while venting steam, hydrogen and other non-condensable gases that may be generated during accidents where the core is damaged. For combustible gases, such as hydrogen, the flammability limit shall not be reached while venting or the system shall be able to withstand the dynamic loading resulting from detonation or deflagration. 12 Finally, the HCVS shall be inspected, tested, and maintained such that it will be able to function if required to during accident conditions. The HCVS is required to meet two quality standards for Phase 1. The piping for the system will be routed from the wetwell to the outside atmosphere. All piping that penetrates containment is required to meet special conditions, such that it cannot fail and cause a breach/uncontrolled opening of containment. This requires that there are two isolation barriers installed as close to the containment penetration as possible, so that containment can be isolated. There are two barriers in case one barrier fails, and the barriers are subject to stringent inspection and testing criteria. The HCVS will be no different from any other containment penetration, and the system up to and including the second containment isolation barrier needs to meet these requirements. In addition, all of the HCVS components are required to be designed such that they can withstand a seismic event (i.e., earthquake) and still be functional. At Fukushima, the earthquake struck the plant first. This did not cause the SBO condition, because the EDGs (which all nuclear plants in the United States have) started as designed and provided the units with AC power. However, the tsunami struck the plant following the earthquake and the put the units into the SBO condition. Therefore, the HCVS has to be able to withstand seismic conditions. For Phase 1, there are two programmatic requirements. Each plant will be required to develop, implement, and maintain procedures that are necessary for the operation of the HCVS. In addition, operators will be required to be trained on how to operate the system through all situations. These will not be discussed further in this paper. For Phase 2, if a HCVS is installed from the drywell, the system will be required to meet all of the conditions listed for the wetwell HCVS. In addition, this vent path must be capable of venting the drywell atmosphere, which may be different from the wetwell atmosphere. If it is determined that a drywell vent is not required, it will then need to be proven why. Any instrumentation and equipment that will be required to accomplish this task will need to be installed and procedures developed, along with training. 13 2.2 HCVS Wetwell Sizing for Decay Heat Steam/Energy Release One of the major requirements for HCVS is that they are capable of relieving the energy inside containment in order to prevent or to mitigate the consequences of a severe accident. Requirement 1.2.1 of EA-13-109 states that HCVS for both Mark I and II containments shall have the capability to vent steam/energy equivalent to one percent of licensed/rated thermal power (unless a lower value is justified by analyses) and be able to maintain containment pressure below the primary containment design pressure. This was an original requirement for EA-12-050 and JLD-ISG-2012-02 provided additional guidance on meeting this Requirement. Note, an ISG has not yet been prepared for EA13-109, and one is expected by October 31, 2013 for Phase 1 requirements and another by April 30, 2015 for Phase 2 requirements. The HCVS shall be capable of keeping the containment pressure below both the PCPL and primary containment design pressure. These two limits may be different and the vent will be required to be capable of limiting containment pressure so neither limit is exceeded. A limit of one percent of the rated thermal power was chosen based on studies that have shown that suppression pools are capable of absorbing the decay heat generated during the first three hours following shutdown. Decay heat continues to decrease well under one percent as time passes. Table D.1 of ANSI/ANS-5.1-2005 [4] presents the approximate decay heat power relative to the operating power following the shutdown of a reactor (partial shown below in Table 1). At 1.00 x 104 seconds (2.78 hours) following reactor shutdown, the decay heat power is approximately 1.04%. 14 Table 1: Decay Heat Power Following Shutdown [4] Time After Shutdown (Seconds) Time After Shutdown (Hours) % Reactor Power 1.00 x 100 1.00 x 101 1.00 x 102 1.00 x 103 1.00 x 104 1.00 x 105 1.00 x 106 1.00 x 107 1.00 x 108 1.00 x 109 2.78 x 10-4 2.78 x 10-3 2.78 x 10-2 2.78 x 10-1 2.78 x 100 2.78 x 101 2.78 x 102 2.78 x 103 2.78 x 104 2.78 x 105 7.669% 5.442% 3.426% 2.077% 1.044% 0.5838% 0.2633% 0.09436% 0.03891% 0.01105% The ISG states that Licensees may use a value lower than one percent if analyses can justify that primary containment and the suppression pool can handle it. In addition, the location where venting will occur needs to be considered (drywell vs. wetwell). Finally, the pressure difference between the drywell and the wetwell needs to be taken into account. As part of this section, a generic HCVS for the wetwell shall be designed. This design will need to perform two calculations: 1) determine the mass flow rate required to be vented in order to remove a minimum of one percent of the rated thermal power from a nominal sized reactor and 2) determine the size of the pipe to remove the required mass flow rate. It is assumed that the suppression pool is capable of absorbing the decay heat following the shutdown of the reactor until the decay heat power level reaches one percent. For the purposes of this paper, design information from the Cooper Nuclear Station (CNS) in Brownville, NE will be utilized to size a HCVS. CNS is a BWR Mark I nuclear plant, making it very similar to the Fukushima units that sustained extreme damage. CNS installed a hardened vent from its wetwell in the early 1990’s following the issuance of GL 89-16. All of the information that will be utilized is taken from publically available records. Some of the information is taken from the response of Cooper to EA-12-050 and the NRC [9] (Note: responses for how plants will meet the 15 requirements of EA-13-109 will not be prepared until after the ISGs are issued). The calculations will be compared to results from this response for the wetwell. The calculations in this paper do not constitute a calculation or design basis for CNS, but are used to demonstrate the approximate sizing of a HCVS for a nuclear plant the size of CNS. Figure 4 below provides a depiction of a Mark I containment with the HCVS installed coming off the top of the wetwell. A drywell HCVS is shown for reference for Section 2.4. Figure 4: Mark I Containment with Wetwell and Drywell HCVS [8] 16 2.2.1 Mass Flow Rate Requirements The current power level for CNS is 2419 MWt [11]; however, CNS is preparing to increase the power level of the reactor as part of an Extended Power Uprate (EPU) to approximately 2915 MWt [9]. This value is equal to the thermal power generated by the reactor during one hour. One percent is equivalent to 29.15 MWt, which is equal to 9.95 x 107 BTU using a conversion factor of 1 MWt = 3.412 x 106 BTU. This is the required power that the HCVS will be required to vent out of containment. As discussed in the JLD-ISG-2012-02, the containment vent shall be sized to be rated for the lower of the PCPL and primary containment design pressure. For CNS, the primary containment design pressure (56 psig) is less than the PCPL (62 psig), and therefore will be utilized [9]. Steam/gases will be vented to the wetwell through two possible routes: 1) from the reactor vessel/main steam piping, through the SRVs, and into the bottom of the torus or 2) through the interconnecting piping of the drywell and torus, into the header, and through the downcomers. The first scenario occurs as long as there is no LOCA or breach of the reactor vessel and the second scenario occurs if a LOCA or breach of the reactor vessel occurs. Both the downcomers and SRV discharge piping are lower in the suppression pool than the inlet to the HCVS, which is designed to be at the top of the torus. The pressure of the vented flow that enters the HCVS will be reduced due to the static head of the water in the torus. The dimensions of torus and water levels are as follows (reference dimensions and heights taken from [10]): Minor diameter of the torus is 28.75 ft. Low Water Level (LWL) is 12.583 ft above the torus bottom. Bottom of downcomers is 9.583 ft above the torus bottom. The assumed maximum water level in torus is 28 ft above the bottom of the torus. The SRV discharge piping is located at the bottom of the wetwell. An assumed maximum water level is set at 28 ft, which is just below the top of the torus and thus the HCVS entrance. This is necessary because if the torus was full of water, the vent would not be able to properly vent steam and remove pressure (at which point venting would only be able to be performed through a drywell vent – see Section 2.4). 17 For this calculation, three different scenarios will be considered. The first scenario (Low) is when water in the torus is at LWL and venting is through the downcomers. The static head of water would be the minimum (3 ft) when steam/energy from the drywell enters the wetwell and the pressure at the downcomer exit is equal to the drywell pressure. The second scenario (High) is if the water level is at the assumed maximum, venting is again through the downcomers, and the pressure at the downcomer exit is equal to drywell pressure, which will give a static head of 18.417 ft. Finally a third scenario (Max) will consider if the water level in the torus is at the maximum and the steam/gas enters the wetwell at the bottom through the SRV discharge piping. In this scenario, the full height of the water (28 ft) reduces the pressure. Note the scenario of the steam/gas entering at the bottom through the SRV discharge piping, while the wetwell is at LWL is not evaluated; however, this scenario would develop a head between the Low and High cases (12.583 ft). The reduction of the pressure that will enter the HCVS entrance due to the static head of water in the torus is calculated as follows: (1) Where: Pv = Pressure at HCVS entrance, psia PD = Pressure of Drywell, psia LT = Static Water Height in the Torus, ft DW = Density of water at saturated conditions and pressure of Drywell, lb/ft3 Mass flow will be relieved from containment using the following energy balance relationship: (2) Where: Q’ = 1% of rated thermal power, Btu Q’V = rate of heat removal that is vented, Btu Q’I = rate of heat injected into containment, Btu w = flow rate (vented and injected), lb/hr h = enthalpy at specific pressure/temperature (vented and injected), Btu/lb 18 For this paper, two different scenarios will be evaluated: 1) during venting, no flow from any safety systems (RCIC and ECCS) is injected into containment and 2) during venting, water from safety systems is injected into the drywell and/or reactor vessel. The following assumptions are made as part of the mass flow calculations: Vented steam is at saturated vapor conditions with a quality of 1.0 at the vent entrance, not superheated. No heat loss from the drywell or wetwell. For Scenario 2 only, during venting, the volume of fluid in primary containment (drywell and wetwell) remains constant. This means that WV = WI. For Scenario 2 only, the injection fluid is water at 100°F. At this temperature, h I = 68.05 Btu/lb. This is an assumed temperature based on potential water flow from safety systems into containment. This water could either be from dedicated tanks located outside of the reactor building, or it could be water pumped from the suppression pool, cooled through heat exchangers and returned to primary containment. For Scenario 1, Q’I goes to zero and WV is solved based on the enthalpy of the steam exiting through the HCVS at the exit pressure. For Scenario 2, the enthalpy of water injected into containment is subtracted from the enthalpy of the steam exiting through the HCVS, and WV is solved for. 2.2.2 Required HCVS Pipe Sizing Once the mass flow rate is determined, the required pipe size for the HCVS can be calculated. As part of this scenario, the pipe size will be calculated based upon a range of total resistance coefficients (K) for the system. When steam is vented from the HCVS, there will be a number of pressure losses from the exit of the wetwell until the discharge. Through the HCVS, the pressure will drop as the steam passes through valves, elbows, tees, and potentially, different sized pipes. Since the specific design of the flowpath for the existing CNS HCVS pipe is unavailable, the pipe sizes will be based upon a total resistance coefficient. In addition, as discussed in [9], the current CNS vent is a 10-inch pipe. As part of this calculation, three different pipe sizes will be considered: 8-inch, 10-inch and 12-inch. Although CNS has a 10-inch line, 8-inch will be considered 19 since there are BWRs that installed this size piping (see Enclosure 1 to GL 89-16 for discussion of the Pilgrim Nuclear Power Station hardened vent). A 12-inch pipe will be evaluated in case the 10-inch pipe is not sufficient. All pipes will be designed as standard schedule or thickness and carbon/stainless steel. Per ASTM A524 [12], piping of this size is subject to hydrostatic pressures of 1200 psi and higher, so the maximum pressure that will be vented through the HCVS will not be a concern. The pipe sizing calculation will be calculated using the Modified Darcy Formula from Crane Technical Paper No. 410 [13]: (3) [13] Where: Y is the net expansion factor for compressible fluid v is the specific volume of steam, ft3/lb K is the total resistance coefficient for the HCVS system d is the internal pipe diameter, inch ΔP is the pressure difference, psig The first objective is to determine if the flow through the HCVS will reach sonic velocities when the steam exits the HCVS. Per A-22 of [13], the specific heat ratio for water is approximately 1.3. The pressure ratio (PR) is required to be calculated and is equal to the pressure drop in the vent piping, ΔP (entrance pressure minus atmospheric pressure) divided by the absolute pressure (in psia) of the pressure at the entrance to the vent, P’1. A chart is then created using the information from the chart on page A-22 of [13] for k = 1.3. Additional nominal total resistance coefficients are added (12, 14, 16, and 18) and the ΔP/P’1 and Y are interpolated. Then, K and Y are interpolated for the calculated PRs. For these specific PRs for that size pipe, when the K value is greater than the interpolated value, the fluid that exits the HCVS will be sub-sonic. When the K value is less than the interpolated value, the fluid that exits the HCVS will be at sonic velocity. If the steam will be exiting at sonic velocity, ΔP will be required to be recalculated and multiplied by the factor ΔP/P’1 at that specific K value (which reduces the ΔP). Once all of the parameters are known, the Modified Darcy Formula can be used 20 to calculate the flow capacity of each of the different sized pipes for different total resistance coefficients. Note the calculations for Mark II containments would follow the same methodology and assumptions used for Mark I containments. The only major difference would be specific information for the suppression pool depth and injection/discharge elevations. 2.3 Severe Accident Conditions in Containment One of the biggest concerns in a nuclear plant that occurs during severe accident conditions is the production of hydrogen. Hydrogen has multiple concerns if generated in containment. The first concern is it will cause an increase in pressure and energy in containment. Up to 20% of the pressure in containment during severe accidents can be the result of the production of hydrogen and other non-condensable gases [19]. Secondly, there is a big risk of potential combustion and detonations from hydrogen reactions that can cause damage to containment, along with the equipment/components inside, and potentially cause the uncontrolled release of radiation. At Fukushima, it is believed that Units 1, 2, 3, and 4 all experienced detonations due to hydrogen [1 and 16]. Hydrogen Production During severe accidents, the major source of hydrogen production is generated from the reaction of steam and the fuel rod metal (zirconium) that contains the fuel pellets. When the plant is normally operating, the core is surrounded by water (Note the transition from water to steam occurs above the fuel rods in the upper part of the reactor vessel). In the event of a LOCA, the main purpose of the safety systems is to pump water back into the reactor to keep the reactor core covered and cool. In the event of an accident in which the safety systems cannot provide water to the core (similar to what happened at Fukushima when all electric power was lost), the temperature of the water in the reactor vessel will increase due to the decay heat of the fuel. Some of this steam will be discharged through the SRVs to the suppression pool. While this is happening, the water level in the reactor vessel will lower until the core becomes uncovered. When this occurs, steam will react with the zirconium. In order to produce hydrogen from this 21 reaction, the zirconium temperature is required to be greater than 1832°F, which occurs when the core is partially or fully uncovered. The chemical formula for the steam/zirconium reaction is as follows from NUREG/CR-2726 [17]: (4) [17] The reaction is exothermic, which means that the energy that is released creates a chain reaction, similar to the fission process. The creation of energy increases the temperature of the zirconium in that area, which then causes the reaction to keep occurring. In addition to the steam/zirconium reaction, there are other reactions in containment that can produce hydrogen. Similar to zirconium, the steel that is in the reactor, along with the reactor walls itself can produce hydrogen. For this to occur, the temperature is required to be higher (~2200°F). This is much less likely than for zirconium since the steel in the vessel does not contain fuel pellets, which can create substantial amounts of heat and energy. Like the zirconium reaction, the process is exothermic, but to a much smaller degree (~277.6 Btu/lbm produced or 10% the amount of heat/energy released for zirconium/steam) [17]. Also, during both normal and accident conditions, hydrogen can be produced through what is known as the radiolysis of water. The radiation in the reactor can cause water molecules to break down into many different forms, but among these are hydrogen and oxygen. Note that this happens at a much slower rate than the zirconium and steel reactions with steam [17]. In addition, hydrogen is produced during potential molten core-concrete interactions. If the fuel melts during a severe accident, penetrates the reactor vessel, and falls to the drywell floor, it will react with the concrete. Steam and carbon dioxide will be released from the concrete and will react with the metallic constituents of the melted core to produce hydrogen and carbon monoxide. Other gases such as methane and hydrocarbons can also be generated in a process called hydrogenation. Similar to hydrogen, the other non-condensable gases that are produced will cause pressure increases inside of containment [17]. Finally, three other sources of materials in containment can react with water and generate hydrogen: zinc-based paint, aluminum, and galvanized material. When these 22 materials corrode due to the presence of water, hydrogen can be produced. These reactions generate less hydrogen than the other reactions, and are slower than radiolysis of water [17]. The calculations discussed above (Mass Flow Rate Requirements and Required HCVS Pipe Sizing) will be performed again to account for the energy that could be generated for the production of hydrogen. As discussed in [27], the energy from metalwater reaction can represent several times the energy from decay heat. Therefore, this will most likely require larger piping systems (~18-inch diameter). This calculation will only focus on the energy produced during the zirconium steam reaction (in addition to the decay heat energy) since the energy from zirconium/steam reaction is ten times higher than for the steel/steam reaction (2765 Btu/lb vs. 277.6 Btu/lb). In addition, the steel/steam reaction will not produce nearly the amount of hydrogen or energy since the temperatures of most of the steel in containment will not be capable of reaching 2200°F. This calculation conservatively assumes that all of the available zirconium reacts, creating approximately 4400 lbm of hydrogen along with the associated energy [17]. In addition, the methodology above for venting decay heat only through the HCVS only considered the properties of steam when venting; however, for this scenario, hydrogen will also have a significant presence and its properties also need to be considered. Hydrogen Combustion/Flammability/Deflagration/Detonation Once hydrogen is produced in containment, the next concern is combustion. The chemical formula for the combustion of hydrogen is : (5) [17] A great deal of energy is produced when hydrogen and oxygen are allowed to combust. From this energy come both high pressure, which can cause damage to containment along with equipment inside, and high temperature [17]. In order for substantial combustion of hydrogen to take place, two conditions are required: 1) the mixture must be flammable and 2) ignition source must be present. The flammability limits are defined as a combustible mixture with a limiting molar fraction of fuel that will cause a 23 flame to propagate indefinitely [18]. Table 2 below shows the required concentrations of hydrogen in air in order for hydrogen combustion to occur. Table 2: Hydrogen Flammability Limits [17] Hydrogen Concentration in Air 0% - 4% 4% - 14% 14% - 59% 59% - 75% 75% - 100% Possible Reaction Noncombustible Combustible Combustible (Possibly Detonable) Combustible Noncombustible The 4% value is termed the lower flammability limit, in that this is approximately the minimum hydrogen concentration that is required for combustion. The 75% is termed the upper flammability limit. In addition to the hydrogen concentration needing to meet these requirements, the oxygen concentration also is required to be approximately 5% by volume or greater to enable the reaction. Note that in an atmosphere that is altered by the presence of another gas that is not combustible (such as steam, nitrogen, carbon dioxide, etc.), the lower flammability limit will increase and the higher flammability limit will decrease. If a significant volume of this third gas exists, there comes a point when the atmosphere is considered inert. A mixture is considered inert if a flame is not able to propagate through it. During a LOCA, the amount of steam produced from the break in the reactor vessel/main piping could cause an atmosphere to be considered inert. However, this would be a temporary condition, since following a LOCA, the steam will condense and the atmosphere would no longer be inert. In addition, plants can purposefully add a third gas to inert an atmosphere (see below on inerting containment) [17]. Once a flammable mixture is present, an ignition source is required for combustion. Hydrogen/air mixtures only require a small input of energy in order to spark. Sources such as electrical equipment or small static electrical charges are sufficient. The closer the mixture is to one of the flammability limits, the more energy is required for ignition. Similar to how a third gas can shrink the flammability region, a third gas also increases the amount of energy required for ignition [17]. 24 Combustion waves are classified as either deflagrations or detonations. Deflagrations are waves/flames that travel at subsonic speeds relative to unburned gas and then propagate through thermal conduction. Deflagrations that occur in containment will create loads that are quasi-static on the containment walls and equipment. These types of combustions cause gradual rise in pressure and temperature. In addition, all of the hydrogen may not be burned in these types of combustions [18]. A hydrogen jet that is injected through a pipe (such as a HCVS) with steam could create a turbulent diffusion flame. In a diffusion flame, the burning rate is controlled by the rate of mixing oxygen and fuel (hydrogen). A mixture that has reached its flammability limit can be ignited through either an outside ignition source or spontaneous ignition temperature. The spontaneous ignition temperature is in the range of 959-1076°F. These can be quite useful since the mixture of fuel and oxygen can be more controlled, and deliberate ignition schemes can be used to initiate combustion [17]. Detonations are combustion waves that travel at supersonic speeds relative to the unburned gas in front of it (can be as high as 6600 ft/sec). The compression of the unburned gas by the shock waves raises the gas temperature high enough to initiate rapid combustion. The detonation wave can create pressures that can be as much as 15 times the initial pressure; however, when shock waves reflect off rigid walls, they can be almost 30 times the original pressure, and cause catastrophic damage to containment walls, pipes, and equipment [17]. Inerting of Mark I and II Containments As discussed in Section 1.3 above, Mark I and II containments have the smallest free volumes among the operating reactors in the United States. Figure 5 below shows the production of hydrogen in containment based on the percent of metal-water reactions that takes place. 25 Figure 5: Volume % Hydrogen vs. % Metal-Water Reaction Following a LOCA [17] As the figure demonstrates, approximately 1-2% metal-water reaction will produce enough hydrogen to create a flammable environment. A Mark III would require approximately 10% metal-water reaction, while a dry PWR takes up to approximately 40% metal-water reaction to create a flammable concentration. Therefore, all Mark I and II BWRs in the United States are inerted during operation. These containments are filled with nitrogen prior to operating to decrease the oxygen concentration by volume below 4-5%. This essentially guarantees that deflagration and detonation will not take place. Nitrogen is used in this application since it is relatively cheap for the size of containment, it does not cause corrosion, and it can be stored as a pressurized liquid. 26 However, even with inerted containments, oxygen concentrations have to be monitored. Leakage of air from the outside, leakage from compressed air systems, and radiolysis of water can introduce oxygen into containment. Due to the inerting of containment, the energy that could be produced from the hydrogen/oxygen reaction (5.2 x 104 Btu/lb for every 2 lb of hydrogen that reacts) will not be considered as part of the pipe sizing calculation for an HCVS. It is assumed that significant quantities of oxygen will not be either generated either through radiolysis during the accident sequence or through inleakage. 2.4 Drywell Venting The requirement of adding a HCVS that will relieve pressure from the drywell, in addition to the wetwell, was included as part of Phase 2 of EA-13-109. During venting situations, there are concerns that the wetwell vent may not be available at certain times or effective at reducing pressure or the concentrations of hydrogen and other noncondensable gases in containment. Injection of water from safety systems to cool the core (with the fuel either in the reactor vessel or relocated to the containment floor) can cause the wetwell to overfill. This would prevent the wetwell HCVS from performing its function. The concern with the use of a drywell vent and the reason why wetwell venting is the much-preferred path is because of the reduction in radioactivity. In order to vent out of the HCVS from the wetwell, the steam/gas mixture must pass through the pool in the wetwell. The water is able to scrub out some of the radioactive materials and hold them in the water before the steam/gas is vented. The effectiveness of reducing the release fraction for radioactive materials from containment is defined as the decontamination factor (DF) (see Section 2.5.1 for additional discussion of DF for suppression pools). A drywell vent will not have the added benefit of reducing the radioactivity in the steam prior to release, and drywell venting would release significantly more radioactivity than wetwell venting. The preferred location for the drywell vent would be near the top of the drywell. This location is expected to have higher temperatures and concentrations of hydrogen, which would make the vent more beneficial. In addition, the reactor building (secondary 27 containment) surrounds the upper part of the drywell. Venting from here will reduce the potential leakage from the drywell to the reactor building [2]. This was an issue at Fukushima in which Units 1, 3, and 4 had detonations in their reactor buildings. This paper will perform the same calculations for Mass Flow Rate Requirements and Required HCVS Pipe Sizing for both decay heat only and decay heat + zirconium/steam energy to calculate the maximum flow rate requirement for discharging steam/energy from a drywell HCVS. This calculation is not as complex as for the wetwell vent since the calculations do not consider the pressure reduction due to the static head of the suppression pool. These calculations consider many of the same assumptions, including the steam/gas inside the drywell at saturated conditions. 2.5 Effects of Filtering Following the issuance of SECY-12-0157, the five NRC Commissioners voted and approved that HCVS shall be capable of operation under severe accident conditions. However, Options 3 (FCVS) and 4 (severe accident confinement strategies) were not approved and additional research was requested to be performed before the approval of additional rulemaking [28]. As part of Enclosure 7 to SECY-12-0157, proposed Draft Orders were prepared to show that if approved, what the rulemaking would consist of for Option 3, installation of filtered containment vents. These requirements were very similar to the requirements for HCVS capable of operating during severe accidents (Option 2), with the additional requirement that the containment vent system would be required to include an engineered filter. This filter would need to be capable of reducing the release of radioactive material by an amount that is reasonably achievable. The specified decontamination factors are approximately 1000 for aerosols and 100 for iodine using filters that are currently available. The filters are required to be sized for severe accident conditions and all of the parameters that these would entail (e.g., radioactive and non-radioactive aerosols, containment pressure and temperature, flow rates, gas composition, and decay heat). This filter shall be capable of passive operation with no operator action for 24 hours following initiation of venting. During accident conditions, the reactor core releases radiation in many different forms and elements; however, the major forms that are of concern are aerosol particulate 28 (containing cesium (CS) and iodine (I)), gaseous forms of elemental and organic iodine, and noble gases [20]. One of the main functions of containment is to contain these radioactive particles and gases and prevent their release. However, HCVS will release radioactive materials if venting is required to prevent the overpressurization of containment and reduce the concentrations of hydrogen and other non-condensable gases. In order to curtail the release of these materials and reduce the potential adverse effects on the population and environment, engineered filters can be installed as part of the HCVS (creating a FCVS). Foreign nuclear plants have installed filtered vents, as discussed in Section 1.5. Although nuclear plants in the United States have not installed filters as part of hardened containment vents, they have taken advantage of filtering through the suppression pool to reduce the release of radioactivity if venting is required. Note that engineered filters and suppression pool filtering methods are only effective for reducing aerosol and gaseous iodine releases; they do not have any effect on the release of radioactive noble gases [19]. 2.5.1 Decontamination Factors for Suppression Pools As part of GL 89-16, hardened containment vents were originally proposed to be installed off the wetwell to take advantage of the natural filtering through water. Steam/gases that are vented either from the reactor vessel/piping through the SRVs or from the drywell through the interconnecting piping to the suppression pool, will be filtered as they pass through the pool before they reach the wetwell atmosphere and are vented out. A DF quantifies the efficiency of venting, and it is calculated based on the aerosol mass concentration that initially enters the pool divided by the concentration that leaves the pool [22]. NUREG-1150 [23] first calculated decontamination factors for suppression pools. Prior to breach of the reactor vessel, the median DF for aerosols for suppression pools was found to be between 60 and 80. After the breach of the reactor vessel, these values were reduced to 7-10 (median). Further research into DF for suppression pools has shown that it is inappropriate to characterize a DF as just one value for all accident conditions. The particle size distribution will vary for different accident scenarios and the efficiency of the pool is highly dependent on this particle size. Particles can range from <0.1 μm to greater than 29 10 μm and are removed by different mechanisms. The smaller particles can be removed by diffusion, intermediate particles removed by interception with bubbles in the pool, and larger particles through gravitational settling [2 - Enclosure 5]. In addition there are a number of other factors that affect the DF. A larger DF will be achieved by maximizing the pool height, increasing the mass flow rate into the pool, keeping the pool subcooled (i.e., temperature below saturated conditions), and having steam included in the gas stream that is inlet to the pool [20 and 21]. As part of the MELCOR analysis in Enclosure 5a to SECY-12-0157, the NRC defines a DF for suppression pools between 100 and 300. This is a conservative estimation and is based on pool depth, pool temperatures, and other factors as discussed above. 2.5.2 Engineered Filter Designs There are two different major types of engineered filters that either have been installed or are available for installation today: wet filters and dry filters. All filters are designed to be in standby and ready for use when required. Wet Filters Wet filters use the same generic principle as suppression pools by using water as the fundamental medium for filtering. The two Beznau nuclear power plants in Switzerland chose to install the Sulzer-EWI system in the early 90’s. This system consists of a water tank with nozzles and baffles. In this arrangement, steam/gas is vented out of containment through a pipe, through the containment isolation barriers and into the filter. The steam/gas is discharged through nozzles into the bottom of the tank and directed upwards where the gas expands. As the gas travels, it is subjected to numerous changes in direction through baffles. The gas then exits through the top of the filter unit. The reduction in the radioactivity of aerosols is due to breaking the gas/steam mixture into small bubbles to increase their surface area, and a DF of greater than 1000 is achieved. The breakdown and many changes of direction causes even energy dissipation in the filter. The filter capacity is large such that there is no risk of flow obstruction. The unit is capable of passing 0.5-1% of the steam/energy from the reactor 30 at the design pressure of containment, and up to double that with minimal efficiency reductions. Chemical conditioning of the water with chemicals such as sodium carbonate (Na2CO3), sodium hydroxide (NaOH), and sodium thiosulfate (Na2S2O3) convert volatile iodine to non-volatile iodine [24]. Many other existing engineered filters (e.g., FILTRA-MVSS by ABB, sliding pressure venting system at Gosgen in Switzerland) along with newer versions (e.g., Westinghouse’s FILTRA-MVSS, AREVA FCVS, IMI) are very similar in design to the Sulzer-EWI. Figure 6 below shows the IMI filter design. All designs consist of tanks of water located outside of containment. The steam/energy is discharged through nozzles or venturis at the bottom of the tank, and passed through impingement/baffle plates to break down the gases. This creates changes in direction, which enables for a long dwell time and maximum diffusion capture of aerosol products. Some of the older designs use gravel beds at the top of the filter, while newer designs use metal-fiber beds to remove water droplets and additional micro-aerosol products before exiting. These designs use chemical conditioning to capture elemental iodine. The designs of these filters allow for venting the required flow rates at maximum containment pressures. The systems are passive so that no actions are required for a minimum of 24 hours following the start of venting activities. The piping upstream and downstream of the filter is inerted to eliminate hydrogen concerns. The DF for these filters has been found to be greater than 1000 for aerosols and greater than 100 for elemental iodine capture [2 – Enclosure 4, 22, and 24]. Figure 6: IMI Nuclear (CCI) Filter Technology [2 - Enclosure 4] 31 Dry Filters Dry filters are different from wet filters in that they utilize no water. Older designs in Sweden (FILTRA) and France vent through either large beds of gravel and/or sand. As the steam and gas pass through these materials, the filters hold up and capture the radioactive particles, and condense the steam. Per [24], for FILTRA, the DF for aerosols and iodine is said to be greater than a 1000; however, during testing the DF was found to be between 2.3 and 5 [22]. For the sand beds, aerosols were tested to have a DF of >6000 [22]. The DF for elemental and organic iodine is approximately 10 [2 – Enclosure 4]. Neither of these designs is currently marketed for new installations. The dry filter systems that are marketed (in Germany by FZK and around the world by Westinghouse) is a metal-fiber filter. In the German design, the steam/gas is passed through pads of stainless steel fibers that get continuously smaller and have a DF for aerosols >60,000. In the Westinghouse design, the steam/gas is passed through metal fibers with silver zeolite beds and have DFs ~10,000 for aerosols and 10-100 for elemental and organic iodine. In these designs, the venting strategy requires delays of more than a day after shutdown such that the heat loading on the filter is less and a longer time for particulate to settle in containment. Based on these limitations, wet filters appear to be a better design for venting BWRs, which may require early venting times [2 – Enclosure 4, 22, and 25]. 32 3. Results and Discussion 3.1 Design of HCVS for Decay Heat Removal and Severe Accidents Figure 7 shows a simplified diagram of a potential FCVS design. In this design, there are two hardened vents connected by a common header that discharges to a wet filter: one vent from the wetwell/torus and one vent near the top of the drywell. Without the filter installed on the common discharge, Cooper and other nuclear power plants in the United States with Mark I and II containments will install similar arrangements to comply with EA-13-109. Drywell Vent Wet Filter Wetwell Vent Figure 7: Simplified HCVS/FCVS Design [2 - Enclosure 4] Phase 1 of this Order requires installation of the wetwell vent, and this design would meet the requirements listed in Attachment 2 of the Order as follows: The sizing and capacity of the HCVS would meet the 1% reactor thermal power at maximum containment pressure or PCPL if it were designed per Section 3.1.1 below. The pipe has two isolation barriers to provide containment isolation. These valves are required to be operated both remotely (with designated power sources, such as batteries), and manually. Shielding would need to be provided along with manual valve operators to allow for personnel to open these valves when required. The system would need to be designed and supported such that it can withstand the effects of a seismic event. 33 Instrumentation would be provided such that the positions of the valves, radiation levels in the piping, and other conditions such as pressure temperature are known. Discharge of the vent would need to be above the elevation of all main plant structures along with minimizing cross flow to other units for multi-unit sites. Finally, for severe accidents, the system would be required to cope with high temperature, pressure, radiation, hydrogen, and other non-condensable gases. The vent shall ensure the flammability limit in containment or the venting system during venting, or the system shall be designed to withstand the dynamic loading from deflagration and detonation. Section 3.1.2 presents discussion of these conditions, including pipe size calculations. The installation of the drywell vent as shown above would meet the requirements of Phase 2 of Attachment 2 to EA-13-109. Many of the requirements discussed above would need to be designed the same as the wetwell vent. The same sections that present calculations for HCVS wetwell pipe sizing also present calculations of drywell pipe sizing. The location of the drywell vent is shown being near the top of containment, which will allow for venting of the higher temperature gasses in containment, including hydrogen. The figure shows two pathways with double isolation. One pathway is considered completely passive (no operator action required to vent), with both valves open, but a rupture disc installed. A rupture disc is a non-reclosing pressure relief disc that is a one-time use component. This would only allow for venting when the pressure in containment exceeds the set pressure of the rupture disc (i.e., containment design pressure). The second pathway is setup the same as the wetwell path with two normally closed isolation valves. This double pathway arrangement could be installed on the wetwell HCVS as well. The double arrangement eliminates the operator action to vent containment when pressure reaches its limit, and operator action would only be required if early venting was desired or if the pathway needed to be closed following venting. The installation of an engineered filter is not required as part as EA-13-109, however, it may be required as part of future Orders. Section 3.2 discusses the benefits of filters along with the deficiencies. 34 3.1.1 Non-Severe Accident Calculations Mass Flow Rate Requirements Appendix 6.1 presents the full spreadsheets and results for mass flow rate requirements; however, Table 3 shows the summarized results below: Table 3: Mass Flow Rate Requirements WV (lb/hr) Wetwell - Torus Water Level Low High Max Drywell - No Injection/Makeup Flow Into Containment 8.43 x 104 8.44 x 104 8.45 x 104 8.42x 104 Injection/Makeup Flow Into Containment 8.94 x 104 8.96 x 104 8.97 x 104 8.94 x 104 In this table, the torus water levels are as follows: Low is if the static head of the water in the torus is 3 ft, High is if the static head is 18.417 ft, and Max is if the static head is at 28 ft. The fourth column calculates the drywell HCVS required flow rates. As presented in the table, the most conservative scenario for the wetwell HCVS is when the pressure is reduced by the largest static head in the torus (Max) and when it is assumed that makeup flow is available and is injected when the wetwell is vented. The static head has a small effect on flow requirements comparatively (~0.2% increase in lb/hr from the Low case to the Max case). The availability of makeup/injection of water into containment has a much bigger effect (comparatively) on the maximum mass flow rate out of the HCVS (~6% increase). The temperature of the assumed makeup/injection drives this difference. The required drywell flow is slightly less the Low case, since there is no pressure reduction taken due to static head. If the makeup temperature was assumed at 130°F (enthalpy of 98.0 Btu/lb) rather than 100°F (enthalpy of 68.1 Btu/lb), the required flow for Max conditions would increase to 9.21 x 104 lb/hr. This would be an approximate 3% increase above water at 100°F. Knowing the maximum temperature of makeup fluid injected by the safety systems into containment is a critical parameter for obtaining conservative results. The mass flow rate calculations for the wetwell HCVS are slightly less than the mass flow rate provided by CNS to the NRC (90,853 lb/hr) [9]; however, the results are very similar. Note that the flow rate in the CNS submittal was calculated based on a 35 containment pressure of 41.3 psig rather than the maximum containment design pressure of 56 psig (it is stated that was to allow for use of RCIC, which requires venting at a lower pressure – see additional discussion in Section 3.3). This reduction in pressure would slightly increase the flow rate. In addition, some of the design parameters that CNS utilized to calculate their flow rates, such as water level in the torus and temperature of makeup/injection water, are not documented in their response and remain assumptions for the calculations in this paper. Required HCVS Pipe Sizing The required HCVS pipe sizing calculations utilize the results from above assuming there is makeup/injection flow (at 100°F) into the primary containment when venting. The wetwell pipe sizing considers all three static head conditions (Low, High, and Max). The drywell pipe sizing does not consider any static head conditions. As discussed in Section 2.2.2, it is important to calculate the critical value of K (system resistance coefficient) based on the pressure ratio (PR) for each case. The critical values of K are as follows: 1) Low case, K = 12.282, 2) High case, K = 9.573, 3) Max case, K = 8.285, and 4) Drywell case, K = 12.806. These values determine if the flow out of the pipe will be at sub-sonic or sonic velocity. If the K value is greater than the calculated critical value, the flow will be sub-sonic, while a K value less than the critical value will lead to sonic flows and the differential pressure will be required to be reduced. The Modified Darcy Formula is then calculated to determine the maximum mass flow rates allowable for a certain pipe size with a range of resistance coefficients. These are then compared with the mass flow rates calculated above. Appendix 6.2 presents the full spreadsheets and results for HCVS pipe sizing. Four tables present the flow capacity for three different pipe sizes (8-inch, 10-inch, and 12-inch NPS) at a range of resistances. The pipe size is based on “Standard” pipe sizes (STD) from Table B-18 of [13]. The results are summarized as follows: For the “Low” condition and the drywell pipe vent, the 8-inch pipe will be acceptable if K ≤ 6. The 10-inch and the 12-inch pipe will be acceptable for all K values up to 20. Note that flow capacities for higher K values may be acceptable 36 and can be calculated if required, but a maximum of 20 will allow for a system with a significant number of losses. For the “High” condition, the 8-inch pipe will be acceptable if K ≤ 4. The 10inch will be acceptable if K ≤ 16. The 12-inch pipe for this condition will be acceptable for all K values up to 20. For the “Max” condition, the 8-inch pipe will be acceptable if K ≤ 4. The 10-inch will be acceptable if K ≤ 14. The 12-inch pipe for this condition will be acceptable for all K values up to 20. The CNS response to the NRC states the 10-inch wetwell vent is capable of venting the specified flow of 90,853 lb/hr. Therefore, the total system resistance would be expected to be less than or equal to 14 (Max case), depending on the pressure of the steam/gas that enters the vent and assuming max water level in the torus. The results of this section provide design criteria to consider for installation of a venting line. Note that this same philosophy can be applied for Mark II containment with changes for the physical design of the suppression pool. A specific path with valves and other piping components would need to be designed based on the specific plant parameters and interferences. Once a specific design and path is decided upon, the total system loss coefficient can be calculated. Based on this calculation the results from the tables can be utilized to determine what size pipe would be necessary meet Requirement 1.2.1 of EA-13-109. 3.1.2 Severe Accident Calculations Mass Flow Rate Requirements Appendix 6.3 presents the results of the mass flow rate calculation for severe accident conditions. For this calculation, the “Max” condition for a wetwell vent was the only case utilized, since it envelops the other cases for wetwell (Low and High) and drywell vents as presented above. In order to produce 4400 lbm of hydrogen, 100,000 lbm of zirconium is required [17], and this will create 2.77 x 108 Btu. This energy is 2.78 times the amount of energy from 1% decay heat (9.95 x 107 Btu). In the calculations above that only considered 1% decay heat energy, the calculations utilized the properties of steam (enthalpy and specific volume), which 37 would be the dominant gas that is vented. For severe accident conditions, there will be other non-condensable gases, including hydrogen, which will be generated and will affect the flow rate that is required to be vented. The mixture of gases in containment will depend on numerous factors and this paper cannot fully evaluate different gas mixtures. However, this paper evaluates the effect on venting if hydrogen was dominant in terms of venting and compare this to steam. Appendix 6.5 presents an excerpt from [26] that provides vapor properties of hydrogen. A venting pressure of 70.7 psia is equal to 4.81 atm, so the values will need to be interpolated between the 2 atm and 5 atm columns. In addition, at 70.7 psia with saturated conditions in containment (which has been assumed for these calculations for steam), the temperature would be 303.6°F. The hydrogen table only presents data up to 300K (80.6°F); therefore, the properties of hydrogen need to be extrapolated. To calculate the enthalpy and specific volume of hydrogen at 70.7 psia and 303.6°F, the last six values in the table were utilized to create charts, and linear trend line equations were found using Excel. Linear trend lines were found to be acceptable since the R2 values were 1 and 0.999 for specific volume and enthalpy, respectively. See Appendices 6.6, 6.7, and 6.8 for the interpolation table and the charts with trend lines. The calculated enthalpy of 2564 Btu/lb was utilized to calculate the maximum flow rate of 1.51 x 105 lb/hr (based on hydrogen properties). The maximum calculated flow rate for steam properties is 3.39 x105 lb/hr, which is more than twice as much as for hydrogen. Both are significantly higher than the 8.97 x 104 lb/hr calculated for this case only considering decay heat and based on steam properties. Required HCVS Pipe Sizing The calculated mass flow rates for severe accident conditions are utilized to calculate the required pipe size and Appendix 6.4 presents these results. The required pipe size for steam conditions was calculated the same as above, except that the higher calculated flow rate of 3.39 x 105 lb/hr was utilized. For this energy, a 12-inch STD NPS pipe will not be adequate for venting. An 18-inch pipe system would be acceptable if K ≤ 8.285 (critical K value). A 20-inch pipe allows for K ≤ 12, which would be a 38 reasonable total resistance for a pipe system. For 22-inch and 24-inch systems, flow resistance coefficients up to 20 (and possibly higher) would be acceptable. To evaluate the required pipe size conditions based on hydrogen properties, the calculated specific volume of 60.64 ft3/lb at 70.7 psia and 303.6°F is utilized. The results show that even though the required mass flow rate based on hydrogen conditions is less than half of steam conditions, the required pipe sizes are more restrictive based on hydrogen properties. An 18-inch pipe system would be acceptable if K ≤ 4. A 20-inch pipe system would be acceptable if K ≤ 6, while a 22-inch pipe system would be acceptable for K ≤ 10. Finally, a 24-inch pipe system would be acceptable for K ≤ 16. These conditions require either systems with flow resistance coefficients that are less than for steam, or larger sized pipes. These calculations considered maximum energy conditions, which was very conservative. As part of the NRC study in Enclosure 5a of SECY-12-0157, the in-vessel hydrogen produced during severe accident conditions (zirconium/steam reaction) was between 500 and 750 kg-mol, or 1000 to 1500 kg, which is equivalent to approximately 2000 to 3000 lb. This is less than the 4400 lb of hydrogen considered to be produced for these calculations. More detailed analyses could determine the maximum quantity of hydrogen produced from this reaction for specific reactors, which could allow for consideration of lower energy production and therefore, smaller piping systems. The calculations only evaluated saturated conditions at maximum containment design pressure for venting (pressure at 70.7 psia, temperature = 303.6°F). Due to the rapid production of hydrogen and increase in energy in containment, it is possible that the temperature could be higher at the time of venting. Calculations were performed for both mass flow rate and required pipe size for a temperature of 500°F to evaluate the effect of higher temperatures in containment for hydrogen conditions, and the results are shown in Appendix 6.3 and 6.4. At a higher temperature, the mass flow rate is reduced to 1.19 x 105 lb/hr. This has a minor effect on the pipe size calculations. There was no change to the allowable size based on flow coefficients up to 18” pipe; however, for larger pipe systems, the allowable flow resistance coefficient is increased. Therefore, a lower temperature is more conservative when sizing a pipe system. 39 Note that if a pressure above the containment design pressure is expected at the time of venting (due to potential delays/difficulties in opening the system), the system may not be able to handle the energy based on hydrogen properties. In the calculations that considered steam properties, a higher differential pressure between the inlet to the HCVS and the outside atmosphere allowed for either a smaller pipe system or a system with a higher total resistance coefficient. However, this will not be the case based on hydrogen properties. The mass flow rate is based upon the enthalpy, and increasing pressure causes a negligible increase in the enthalpy. The mass flow rate will be nearly constant for increasing pressure. However, there is a much larger effect on specific volume (decreases) with increasing pressure. The Modified Darcy Formula is inversely proportional to the square root of the specific volume, so a smaller specific volume will decrease the amount of flow through a pipe with a certain flow resistance. Therefore, a larger pipe system or a system with less flow resistance may be required if it is expected that the pressure in containment could exceed containment design pressure prior to venting. Additional Severe Accident Discussion The calculations above demonstrate the magnitude of the piping system that would be required to vent the energy that could be in containment during severe accidents. Since Mark I and II containments are inerted, this paper is not concerned with deflagration and detonation in containment prior to venting; however, this could be an issue during and following venting. As the steam/gas is discharged from containment through the vent line, oxygen will mix and create a flammable mixture either in the piping system or at the HCVS discharge. At this point, the system would need to be able to withstand potential detonation. The system would also be required to be capable of handling a diffusion flame from a hydrogen jet. Following venting, if the vent is not closed, air (i.e., oxygen) could flow back into containment and create potential flammable conditions. One suggestion is that a check valve or back draft damper be installed in the line near the discharge. Either would allow flow out of the HCVS, but would not allow for flow of air back into containment. The HCVS could be inerted up to either of these devices, and would not allow mixing until the steam/gas discharge. This 40 would limit the section of piping that would need to be evaluated for deflagration and detonation. Another suggestion is the use of igniters in the HCVS. During venting, it is possible to know the percentages of hydrogen and oxygen and determine when the gas mixture would be considered flammable. At the time when the gas mixture becomes flammable but not yet detonable, igniters could be used to burn the hydrogen (deflagration). This would increase the pressure/temperature in the system, but at a much slower rate than if the mixture were to detonate. Instrumentation to detect the volumetric percentages of hydrogen and oxygen are currently utilized in containments and could also be used as part of HCVS. 3.2 Discussion of Filter Benefits The NRC performed studies on the consequences of severe accidents based on different mitigation strategies [2 – Enclosure 5B]. These strategies included both wetwell and drywell venting, with and without core and containment spray. Two of the cases specifically evaluated the effects of wetwell venting (Case 3) and drywell venting (Case 12) without any spray. In these two cases, both filtered and unfiltered cases were evaluated. As would be expected, filters had a beneficial impact on the dose to the population, contaminated area, and economic cost of recovery. The effects were evaluated radially up to 50 miles from the site. For the wetwell venting case, a filter (with a DF of 10) reduced the dose to the population and the cancer fatality rate by approximately 60%, while the contaminated area and economic cost of recovery was reduced by approximately 85%. The drywell venting case evaluates filters with DFs of 1000 and 5000. Both filters reduced the dose to the population and the cancer fatality rate by approximately 95%, while the contaminated area and economic cost of recovery was reduced by approximately 99%. Note a filter with a DF of 5000 did not provide significantly better results than the filter with a DF of 1000. The consequences on the area and population when comparing wetwell and drywell venting with filters demonstrated that the drywell venting with filters were more efficient than unfiltered wetwell venting through the suppression pool (population dose, cancer fatality rate and contaminated area were approximately double, while the economic cost was more than 41 four times as high for unfiltered wetwell venting). However, filtered wetwell venting produced the lowest consequences (20% lower for population dose and cancer fatality rate, 70% lower for contaminated area and 30% lower for economic cost when compared to drywell filtering). This study did not evaluate any cases using both wetwell and drywell venting, with and without filters. This would be useful since it is expected that the suppression pool may completely fill due to injection of water by the safety systems and make wetwell venting not possible later on in the accident. Another benefit of filter installation is that the piping from containment to the filter can be inerted. This would prevent meeting and exceeding the lower flammability limit in the system. In addition, the filter would also prevent the backflow of air/oxygen into containment. One of the unknowns with adding filters to wetwell vents is how much of a benefit it achieves. Filter performance is very dependent on the particle size distribution, and suppression pool filtering will greatly affect the particle size distribution that passes through and reaches the filter. The NRC study utilizes an assumption that the DF would be reduced from 1000 or greater (nominal value) down to 10 (following the suppression pool); however, further research and testing should be performed to evaluate the particle sizes that would pass through the suppression pool and how efficient a filter would be further reducing the radioactivity [19]. However, note that as saturation conditions in the suppression pool are reached, the particle size distribution that will pass to the filter will shift back towards the distribution that would be seen without the suppression pool, thus making the filters more beneficial. Another concern is that many of the filters are designed to accept a flow rate up to the 1% decay heat energy. It is unclear if the filters would be able to accept the higher flow rates associated with severe accident conditions, which could be up to an equivalent of 4% of the decay heat. Finally, one of the big concerns for plants is the cost-benefit analysis. Installation of filters is expected to cost at least $15 million, with some plants believing that the cost could range up to $45 million. When evaluating the chances of a severe accident occurring at a unit and the difference in the current cost for cleanup (with and without a filter) versus the cost of the filter (materials, installation, and maintenance), the NRC 42 study demonstrates that filter installation is not cost beneficial. There is discussion in this study that the assumed cleanup cost is too low and when doubled, filter installation becomes cost beneficial if filter costs are equal to or less than $15.353 million. Although the cost-benefit analysis does not favor filter installation, the foreign countries that either have installed filters or will require filter installation going forward have not considered cost-benefit analyses. Instead, they have only focused on the benefits of installed filters from a defense-in-depth perspective and considered filters to be essential safety enhancements to protect against potential severe accidents [2 – Enclosure 2]. 3.3 Additional Considerations for Severe Accidents The following discussion topics are not currently included in the requirements of EA-13-109; however, they could have a large effect on HCVS that are capable of handling severe accident conditions. Suppression Pool Bypass For Mark II containments, there is a concern regarding what is called “suppression pool bypass”. During severe accidents with breach of the reactor vessel, the barrier between the drywell and the wetwell for a Mark II containment could be breached and the effective DF through a wetwell HCVS filter is greatly reduced. Unlike the Mark I, where the wetwell is a torus located outside of the drywell and connected only by piping, the Mark II drywell is located directly above the wetwell. During a severe accident where the core melt breaches the reactor vessel and falls to the floor of the drywell, there is the potential that the floor or some of the piping that passes from the drywell to the wetwell could fail. This would cause the atmosphere in the wetwell to be the same as the drywell. Figure 8 below shows this condition, where containment is equipped with both a wetwell and a drywell HCVS. This is not a major concern if a filter is installed at the end of the vent piping (FCVS); however, it is a major concern if a filter is not installed. The DF for the suppression pool would be made obsolete following this failure since the wetwell atmosphere would not be “filtered” through the pool. EA-13109 discusses this issue; however, no requirements are provided currently for utilities. This loss of filtering capability is an issue that will be resolved as part of the NRC 43 rulemaking addressing broader severe accident management and filtering strategies. As part of EA-13-109, the NRC states that utilities with Mark II containments may install engineered filters to address this issue. Figure 8: Suppression Pool Bypass for Mark II [19] Confinement Strategies Both the NRC [2 – Enclosure 5a] and EPRI [19] performed studies on the consequences of severe accidents based on different mitigation strategies. These strategies included both wetwell and drywell venting, with and without core and containment spray, and containment flooding. One of the “key insights” that was seen in both studies is that venting alone (wetwell or drywell, with or without a filter) is not enough to mitigate the worst-case scenario for severe accidents: breach of containment, which allows for uncontrolled release of radioactivity and contamination. Other 44 strategies, such as core or containment spray, or containment flooding, are necessary in conjunction with venting to prevent breach of containment. The injection of water will prevent either breach of the reactor vessel or containment failure, if the reactor vessel has been breached and the core has relocated to the drywell floor. Venting will only prevent containment failure due to potential overpressurization in containment. Therefore, it is necessary that confinement strategies (Option 4 discussed in [2]) are further analyzed to determine what safety systems will be required to be available in order to cope with severe accidents, in addition to venting, with or without filters. Following the events of Fukushima, the NRC and the nuclear industry are evaluating strategies to ensure that safety systems are available to allow for injection of water into containment for accident scenarios. These strategies will be required to be evaluated in conjunction with containment venting during severe accidents. Venting Pressure/Cycling This paper assumes that all venting occurs at containment design pressure of 56 psig/70.7 psia. However, the BWR Owners’ Group (BWROG) is proposing venting earlier (at 25 psig) rather than waiting for the containment design limit. This would be necessary to allow for use of RCIC along with other safety systems [2 – Enclosure 4]. EPRI on the other hand proposes only venting near the containment design pressure and cycling of the vents. In EPRI’s study, containment would first be vented when the pressure limit is reached until the pressure in containment was reduced to approximately 40 psig, and then the vent would be shut until the pressure increased again to the pressure limit. The vent would be cycled opened and closed for the remainder of the accident. The reasoning is that the higher pressure maximizes the scrubbing performed by the suppression pool for the following reasons: 1) increased timing before venting, 2) increased velocity of the gas injected into the suppression pool (similar theory venturis in wet filters), and 3) decreased chances of reaching saturation conditions in the wetwell (with reduced DF) due to greater subcooling [19]. Both proposals have their benefits, but further research is required to determine which strategy is superior. 45 4. Conclusion As demonstrated in this paper, venting through HCVS is necessary in order to help mitigate the consequences of severe accident conditions at nuclear power plants with Mark I and II containments. The calculations performed present pipe sizes and flow resistance coefficients that would be required in order to design HCVS to relieve steam/gas in containment based on both decay heat only and decay heat + energy generated from severe accidents. Much larger piping systems are required to mitigate severe accident conditions. These calculations rely on some conservative assumptions, but other assumptions regarding timing of venting and atmosphere in containment during venting need to be further analyzed to verify that the results are bounding. Review of literature and studies on the effectiveness of venting through engineered filters demonstrate that they are beneficial in reducing the effects on population and land contamination. However, the effectiveness of filters in conjunction with suppression pool “filtering” for wetwell HCVS is unknown. In addition, filter installation is very expensive and current cost-benefit analyses do not demonstrate they are beneficial in this regard. Finally, although vents/filters are beneficial in preventing overpressurization of containment, they alone do not prevent the worst-case scenario from occurring following a severe accident: containment failure leading to the uncontrolled release of radiation. If containment fails, filters would prevent the uncontrolled release of radiation. Confinement strategies must be evaluated further so they can be used in conjunction with venting to prevent the uncontrolled release of radiation and contamination and mitigate the consequences of severe accidents. 46 5. References [1] EA-12-050, March 12, 2012, “Issuance of Order to Modify Licenses with Regard to Reliable Hardened Containment Vents”, NRC ADAMS Accession Number ML12054A694 [2] SECY-12-0157, November 26, 2012, “Consideration of Additional Requirements for Containment Venting Systems for Boiling Water Reactors with Mark I and Mark II Containments”, NRC ADAMS Accession Number ML12345A030 [3] Mark I Containment Report, March 19, 2011, http://files.gereports.com/wpcontent/uploads/2011/10/NEI-Mark-1-White-Paper.pdf [4] ANSI/ANS-5.1-2005, American Nuclear Society, Decay Heat Power in Light Water Reactors [5] Reactor Concepts Manual, Rev. 0200, United States Nuclear Regulatory Commission Technical Training Center, NRC ADAMS Accession Number ML023020519 [6] Generic Letter 89-16, Installation of a Hardened Wetwell Vent, September 1, 1989, NRC ADAMS Accession Number ML13017A234 [7] JLD-ISG-2012-02, Compliance with Order EA-12-050, Reliable Hardened Containment Vents, Interim Staff Guidance, Rev. 0, NRC ADAMS Accession Number ML12229A475 [8] BWR Mark I Containment Figure, Modified from http://upload.wikimedia.org/wikipedia/commons/a/a0/BWR_Mark_I_Containment%2C _diagram.png [9] Overall Integrated Plan in Response to March 12-2012, Commission Order Modifying Licensees with Regard to Reliable Hardened Containment Vents (Order EA12-050), Cooper Nuclear Station, Docket No. 50-298, DPR-46, February 28, 2013, NRC ADAMS Accession Number ML13070A094 [10] GE NE-T23-00786-00-09, Evaluation of Steam Ingestion in the ECCS Suction Strainers for Cooper Nuclear Station, Non-Proprietary Report, NLS2001079 Enclosure 3, NRC ADAMS Accession Number ML012640451 [11] Nuclear Regulatory Commission Website, http://www.nrc.gov/ [12] ASTM A524-96 (Reapproved 2012), Standard Specification for Seamless Carbon Steel Pipe for Atmospheric and Lower Temperatures 47 [13] Crane Technical Paper No. 410, Flow of Fluids Through Valves, Fittings and Pipe, 1980 [14] EA-13-109, June 6, 2013, “Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions”, NRC ADAMS Accession Number ML13130A067 [15] Chapter 6.5, Primary Containments, General Electric Advanced Technology Manual, NRC ADAMS Accession Number ML11263A359 [16] SECY-11-0093, July, 12, 2011, “Recommendations for Enhancing Reactor Safety in the 21st Century; The Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident,” NRC ADAMS Accession Number ML111861807 [17] Camp, A. L., et al., NUREG/CR-2726, “Light Water Reactor Hydrogen Manual”, Sandia National Laboratories, August 1983, NRC ADAMS Accession Number ML071620344 [18] Sherman, M. P., “Hydrogen Combustion in Nuclear Plant Accidents and Associated Containment Loads,” Nuclear Engineering and Design, Volume 82, Issue 1, October 1, 1984, Pages 13-24 [19] EPRI Technical Report, Investigation of Strategies for Mitigating Radiological Releases in Severe Accidents, BWR Mark I and Mark II Studies, September 2012, http://www.epri.com/abstracts/Pages/ProductAbstract.aspx?ProductId=00000000000102 6539 [20] Wassel, A.T., et al., “Analysis of Radionuclide Retention in Water Pool,” Nuclear Engineering and Design, Volume 90, Issue 1, November 3, 1985, Pages 87-104 [21] Dehbi, A., et al., “Aerosol Retention in Low-Subcooling Pools Under Realistic Accident Conditions,” Nuclear Engineering and Design, Volume 203, Issues 2-3, January 2, 2001, Pages 229-241 [22] NEA/CSNI/R(2009)5, “State-of-the-Art Report on Nuclear Aerosols,” Nuclear Energy Agency, Committee on the Safety of Nuclear Installations, December 17, 2009, http://www.oecd-nea.org/nsd/docs/2009/csni-r2009-5.pdf [23] NUREG-1150, “Severe Accident Risks: An Assessment for Five U.S. Nuclear Power Plants,” U.S. Nuclear Regulatory Commission, http://www.nrc.gov/readingrm/doc-collections/nuregs/staff/sr1150/ 48 [24] Rust, H., et al., “Pressure Release of Containments During Severe Accidents in Switzerland,” Nuclear Engineering and Design, Volume 157, Issue 3, August 1995, Pages 337-352 [25] Schlueter, R. O., Schmitz, R. P., “Filtered Vented Containments,” Nuclear Engineering and Design, Volume 120, Issue 1, June 1, 1990, Pages 93-103 [26] Brookhaven National Laboratory, Selected Cryogenic Data Notebook, Section 3 Properties of Hydrogen, Revised August 1980, http://www.bnl.gov/magnets/staff/gupta/cryogenic-data-handbook/Section3.pdf [27] Dallman, R. J., Galyean, W. J., Wagner, K. C., “Containment Venting as an Accident Management Strategy for BWRs with Mark I Containments,” Nuclear Engineering and Design, Volume 121, Issue 3, August 1990, Pages 421-429 [28] VR-SECY-12-0157, Commission Voting Record for SECY-12-0157, March 19, 2013, NRC ADAMS Accession Number ML13078A012 49 6. Appendix 6.1 Mass Flow Rate Requirements Spreadsheet – Non-Severe Accidents 50 Mass Flow Rate Requirements Spreadsheet Continued 51 6.2 Required HCVS Pipe Sizing Calculation Spreadsheet-Non-Severe Accidents 52 6.2 continued 53 6.3 Mass Flow Rate Requirements Spreadsheet – Severe Accidents 54 6.4 Required HCVS Pipe Sizing Calculation Spreadsheet – Severe Accidents 55 6.4 cont 56 6.5 Properties of Hydrogen Vapor – Excerpted from [26] 57 6.6 Properties of Hydrogen – Interpolation Table 58 6.7 Specific Volume Chart - Hydrogen 59 6.8 Enthalpy Chart - Hydrogen 60