CONSTRUCTION PROJECT HEALTH & SAFETY FILE Name of premises: Project No: Address: Plinth property ref. no:* Plinth site plan key:* Completion date: Brief description of work carried out (with specific building name) Please e-mail WSCC Property & Asset Management Records Team on propertyrecords@westsussex.gov.uk for this information. Form E555 (08/15) 1 HEALTH & SAFETY FILE WSCC Property Ref WSCC Premises Project Description WSCC Project No 2 NOTES The designers and contractor for projects where there is only one contractor working on the project, or Principal Designer on projects where there is more than one contractor working on the project must complete form E555 Health and Safety File for hand-over to the client at completion of the works. The file must contain information about the current project that is likely to be needed to ensure health and safety during any subsequent work such as maintenance, cleaning, refurbishment or demolition. When preparing the health and safety file, information on the following should be considered for inclusion: a) A brief description of the work carried out; b) Any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (e.g surveys or other information concerning asbestos or contaminated land); c) Key structural principles (e.g bracing, sources of substantial stored energy – including pre-or post-tensioned members) and safe working loads for floors and roofs; d) Hazardous materials used (e.g lead paints and special coatings) e) Information regarding the removal or dismantling of installed plant and equipment (e.g any special arrangements for lifting such equipment); f) Health and safety information about equipment provided for cleaning or maintaining the structure; g) The nature, location and markings of significant services, including underground cables; gas supply equipment; fire-fighting services etc; h) Information and as-built drawings of the building, its plant and equipment (e.g the means of safe access to and from service voids and fire doors) There should be enough detail to allow the likely risks to be identified and addressed by those carrying out the work and be proportionate to those risks. Complete each section page and attach it to the completed cover page. If you do not consider that there is any need to complete a section, please state 'None' in that section. If you consider that certain information not asked for should be included, please do so and provide an explanation. Forward the completed Health & Safety File in accordance with WSCC Building Contract Directive (BCD 55). 3 DETAILS Principal Designer: Name & contact details Other Designers: Names & contact details Other Designers: Names & contact details Other Designers: Names & contact details Principal Contractor Name & contact details Signed: Principal Designer Date handed over: 4 CONTENTS SECTION 1 2 3 4 5 6 7 8 TITLE RESIDUAL HAZARDS Asbestos Silica dust Retained lead Confined Spaces Buried Surfaces Fragile Roofs Voids Remaining Survey Documents DESIGN of STRUCTURE Wall Floor Foundations Roof Other Structural Element Manufacturers Details Foundation Details Further information for future development or demolition of structure MATERIAL HAZARDS Special Coatings Lead Base Paints Materials Containing Small Particles / Fibres Other Hazards PLANT & EQUIPMENT Statutory Examination Preventative Maintenance Shutdown / Isolation Requirements Decommissioning / Dismantling / Disposal Procedures Removal & Replacement Routes & Strategies Lifting Arrangements Access Arrangements Environmental Issues Emergency Procedures Labelling Legends / Keys / Pipework colour coding Manufacturer Details Other Information Enclosed Documents CLEANING & MAINTENANCE EQUIPMENT Architect’s External Building Envelope Cleaning Strategy Internal / External Hazards & Risks Built-in Access / Lifting Arrangements Location of Rodding / Cleaning Points UTILITIES Utilities & Services DRAWING SCHEDULE Schedule APPENDICES 5 Residual Hazards S E C T I O N Should include any hazards that have not been eliminated through the design and construction processes, and how they have been addressed (e.g. surveys or other information concerning asbestos or contaminated land) 1 6 RESIDUAL HAZARDS ASBESTOS – any that has been left in situ after project completion, so that the asbestos register can be updated if applicable Asbestos element Appendix / Location Ref. (from original Details Ref. asbestos register) SILICA DUST – potential for and adverse effect Location Details Appendix / Ref. RETAINED LEAD – potential adverse effect Location Details Appendix / Ref. BURIED SERVICES – inc. electrical cables, gas pipes, communications cables, water supply pipes, drainage & sewer systems Appendix / Service Details Ref. 7 FRAGILE ROOFS / ROOF ELEMENTS – inc. skylights, fragile roofing materials Roof Location Appendix / Ref. Details VOIDS REMAINING – remaining after any demolition work Void Location Appendix / Ref. Details OTHER – please specify Location Appendix / Ref. Details SURVEY DOCUMENTS Enclosed Y N Document Title Contaminated land survey Soil survey Geological survey Hydrological survey Archaeological survey Environmental survey M & E installation hazards Refurbishment and demolition (R&D) asbestos survey. Other (please specify) 8 Appendix / Ref. 9 Design of Structure S E C T I O N Should include key structural principles with cross references to other documents where applicable. Include any references to product literature, specifications etc 2 10 DESIGN OF STRUCTURE Area Max. designed load Point loading Tensioned members PrePost- Wall Floor Foundations Roof Other structural element (please specify) 11 Bracing details Other details Appendix / Ref. Manufacturers Details where relevant Appendix / Ref. Foundation Details Appendix / Ref. 12 Further information, as appropriate, for either the future development or demolition of part or whole of the structure 13 Appendix / Ref. Material Hazards Hazardous materials only. If no known hazardous materials used, this should be stated. Does not include asbestos. Should not repeat Section 1 above. S E C T I O N 3 14 MATERIAL HAZARDS SPECIAL COATINGS – include any material safety data sheets Appendix Y/N Details / Ref. Are there any special coatings which should not be burned off? LEAD-BASED PAINTS – include any material safety data sheets Appendix Y/N Details / Ref. Are there any lead-based paints used? PARTICULATE MATERIALS – include any material safety data sheets Appendix Y/N Details / Ref. Are there any materials that emit small particles or fibres if moved? OTHER HAZARDS (e.g. particularly hazardous adhesives) – any include material safety data sheets Appendix Other Hazards Details / Ref. 15 S E C T Plant & I Equipment O This section should include information regarding the removal or dismantling of installed plant and equipment. e.g. heating, ventilation, hot / cold water service, energy supply, pumps, generators, fixed lifting equipment, fixed access arrangements etc. Should include lists which cross-reference To O&M manuals for full details. N 4 16 PLANT & EQUIPMENT PLANT & EQUIPMENT REQUIRING STATUTORY EXAMINATION - e.g. pressure systems, lifting equipment Appendix / Name of Plant or Equipment Summary of requirements Ref. PLANT & EQUIPMENT PLANNED PREVENTATIVE MAINTENANCE REQUIREMENTS – e.g. manufacturer’s recommendations Appendix / Name of Plant or Equipment Ref. 17 PLANT & EQUIPMENT SHUT DOWN / ISOLATION REQUIREMENTS – e.g. lockoff, capping off, de-pressurising etc. Including location of safety switches, valves etc Appendix / Name of Plant & Equipment Ref. PLANT & EQUIPMENT DECOMMISSIONING / DISMANTLING / DISPOSAL PROCEDURES Appendix / Name of Plant & Equipment Ref. 18 PLANT & EQUIPMENT REMOVAL / REPLACEMENT ROUTES & STRATEGIES Appendix / Name of Plant & Equipment Ref. PLANT & EQUIPMENT BUILT-IN LIFTING ARRANGEMENTS – e.g. lifting beams, eyebolts etc Appendix / Name of Plant & Equipment Ref. 19 PLANT & EQUIPMENT ACCESS ARRANGEMENTS – e.g. anchorage points, fixed ladders, ‘mansafe’ systems etc Appendix / Name of Plant & Equipment Ref. PLANT & EQUIPMENT ENVIRONMENTAL ISSUES – e.g. disposal of equipment or residues etc Appendix / Name of Plant & Equipment Ref. 20 PLANT & EQUIPMENT EMERGENCY PROCEDURES Name of Plant & Equipment Appendix / Ref. PLANT & EQUIPMENT EMERGENCY PROCEDURES LABELLING LEGENDS / KEYS / PIPE WORK COLOUR CODING Labelling Legends / Keys Appendix / Name of Plant & Equipment / Pipe Work Colour Ref. Coding? 21 PLANT & EQUIPMENT MANUFACTURER’S DETAILS Name of Plant & Contact Details Of Details Of Spares Appendix / Equipment Manufacturer Catalogues etc Ref. PLANT & EQUIPMENT OTHER RELEVANT INFORMATION e.g. lifts, lightning protection, burglar alarms Name of Plant & Appendix / Other Information Equipment Ref. 22 ENCLOSED DOCUMENTS e.g. installation certificates, statutory examination certificates Enclosed Document Title Appendix / Ref. Y N 23 S E C Cleaning & T Maintenance I Equipment O N This section should include Health and Safety information about equipment provided for cleaning or maintaining the Structure. May have to repeat information from Section 4 above 24 5 CLEANING & MAINTENANCE EQUIPMENT Designers External Building Envelope Access and Cleaning Strategy Appendix / Ref. Internal / External Hazards & Risks Appendix / Ref. BUILT-IN ACCESS / LIFTING ARRANGEMENTS – e.g. at height & below ground (cradles, fastening eyes, roof systems etc), including external features & atriums. Built-in Energy Equipment Loading Safety Testing Appendix / Isolation Name limitations Devices regime Ref. Points (if fitted) 25 LOCATION OF RODDING / CLEANING POINTS Equipment Name Details 26 Appendix / Ref. Utilities This section should include the nature, location and markings of significant services, including underground cables, gas supply equipment, fire fighting services etc. S E C T I O N 6 27 UTILITIES UTILITIES – e.g. gas, water, electricity, drains (foul / surface / interceptors etc), hydrants, fixed fire-fighting systems, communications cabling, fire detection / alarm systems etc Power Location of Location of Capacity of Colour coding Utility & measurements Location entry points & internal systems of pipe-work & Service (i.e. voltage, isolation distribution (e.g. volume) cable systems pressure etc) Utility & Service Drawing reference 28 Appendix / Ref. Drawing Schedule A reference list only giving details of each drawing and where it can be located. S E C T I O N 7 29 DRAWING SCHEDULE DRAWING SCHEDULE – e.g. as-built, as-installed, structure, fabric, landscape, services, means of access to/from service voids, fire doors, compartmentation etc Title Drawing Ref. 30 S E C T Appendices I O N 8 31