CN126 Surveying Practice s School of the Environment Examinations 2005-2006 CN126 SURVEYING PRACTICE Instructions to Candidates Time allowed: TWO hours Answer ALL questions Monday 23 January 2006 9:00 – 12:00 hours Page 1 of 6 CN126 Surveying Practice Question 1 For the traverse shown in Figure 1, point P has coordinates of 110.000 mE, 165.000 mN. Calculate the coordinates of the unknown stations X, H and A the fractional linear misclosure X 87.933 m 110°50′10″ H 108°30′15″ 66.717 m P 118.245 m 87°36′44″ 157.281 m 53°03′11″ A All angles shown are observed values All distances are horizontal Bearing of line PX = 35°10′ 35″ Coordinates P = 110.000 mE, 165.000 mN Figure 1 (40 marks) Page 2 of 6 CN126 Surveying Practice Question 2 The coordinates of three points are A = 210.000mE, 350.000mN B = 129.687mE, 405.219mN C = 268.774mE, 312.050mN Calculate the whole circle bearings and horizontal distances AB, AC and BC. (10 marks) Question 3 The extract given below is from a level book and shows staff readings taken between two TBMs. ______________________________________________________________ BS IS FS Remarks ______________________________________________________________ 1.525 1.471 1.690 TBM 38.077 m CP A 1.869 B 2.364 2.058 E 2.650 F 2.660 G 2.368 2.110 CP 2.659 2.587 CP 2.851 2.793 CP 3.005 TBM 37.009 m ______________________________________________________________ 1.689 1.745 Calculate adjusted reduced levels for all entries in the book. (20 marks) Page 3 of 6 CN126 Surveying Practice Question 4 15 Multiple choice questions Please choose the MOST CORRECT ANSWER for each question. If you think the answer to Question 4.1 is e write 4.1 = e in your answer book. Repeat for all questions. TWO points each 4.1 The three basic surveying measurements are a b c d e 4.2 In levels, parallax is caused by a b c d e 4.3 The compensator must be checked before every reading The compensator ensures that the viewed line of sight is horizontal The coincidence bubble reader must be set carefully It does not have to be levelled It is not necessary to check any readings When levelling points which will be used later as TBMs a b c d e 4.5 An incorrect setting of the compensator An incorrect setting of the eyepiece and telescope focus Moving the eye whilst looking through the telescope Refraction along the line of sight causing it to bend None of these When using an automatic level a b c d e 4.4 Levelling, taping and total stations Height, distance and angle Angle, coordinates and distance Tapes, EDM and levels None of these The rise and fall method of calculation should be used The HPC method of calculation should be used It is best not to use intermediate sights An automatic level must be used None of these apply When using a digital level a b c d e It is not necessary to level the instrument as this is done electronically Readings are taken automatically without the need to read a staff Great care is needed when writing staff readings on the booking form It must be connected to a computer for data transfer None of these apply Continued Page 4 of 6 CN126 Surveying Practice 4.6 The primary purpose of engineering surveying on a construction site is to a b c d e 4.7 When working on surveying projects, it is best to a b c d e 4.8 Is much lighter and more flexible in use Is much more accurate Must be handled with care to avoid bending or kinking Has graduations every mm Is none of these GPS is an abbreviation for a b c d e 4.11 Is always an arbitrary direction chosen for convenience Is measured anticlockwise from a chosen north direction Lies in the range 0 – 360° Lies in the range 0 to ± 180° Is none of these Compared to a steel tape, a plastic tape a b c d e 4.10 Hurry to complete work to avoid making mistakes Always check work where possible Only measure values once to avoid confusion in bookings Have a partner with you who has done surveying before Avoid all of these The whole circle bearing of a line a b c d e 4.9 Produce maps or plans of the site Measure and cost volumes of material moved around the site Carry out as-built surveys for a project Ensure that the project is built with the correct dimensions and in the correct location Monitor for structural movement Global Positioning System General Positioning System Global Precise Surveying General Purpose Surveying None of these When a total station has been levelled a b c d e The line of sight is horizontal The horizontal reading is 00° 00′ 00″ The vertical axis is vertical The instrument has been centred None of these apply Continued Page 5 of 6 CN126 Surveying Practice 4.12 Coordinates are used extensively in building and surveying for a b c d e 4.13 When using a total station a b c d e 4.14 Levelling is not necessary as this is done automatically All angle and distance readings are referenced to zero Always make sure you have enough batteries with you There is no need to remove parallax None of these apply In surveying, horizontal position is defined as a b c d e 4.15 Measuring bearings and distances Defining horizontal position Measuring distances and angles Defining heights None of these X and Y axes X and Y coordinates A bearing and a distance An easting and northing None of these When measuring horizontal angles a b c d e The horizontal circle is set so that 00° 00′ 00″ is the first reading Two rounds must be taken to check for any mistakes Only one round can be taken Face right readings are not necessary None of these apply (30 marks in total for Question 4) Page 6 of 6